Group bin concrete pouring device and pouring method

By designing the concrete pouring device of the group warehouse, including mixing, adjustment, feeding and pouring devices, the problems of air bubble removal and pouring uniformity in concrete pouring are solved, and high-quality concrete molding and efficient utilization of resources are achieved.

CN119711753APending Publication Date: 2025-03-28CHINA RAILWAY 20TH BUREAU GRP FIFTH ENG CO LTD +2
0 Cites 0 Cited by

Patent Information

Application Number
CN202510004180.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

The prior art is difficult to effectively remove air bubbles in the concrete and ensure uniformity of the pouring position during the concrete pouring process, resulting in poor product quality and waste of resources.

Method used

A group warehousing concrete pouring device is designed, including a mixing device, a regulating device, a material conveying device and a casting device. The bubbles in the concrete are removed by the oscillator, and the adjustment device realizes uniform transport and pouring of concrete. The pouring device can adjust the pouring angle according to the mold to ensure uniform pouring of concrete.

Benefits of technology

It effectively eliminates bubbles in concrete, improves the quality of the product after forming, ensures the uniformity and stability of the pouring process, and reduces waste of manpower and material resources.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a concrete pouring device and a concrete pouring method for a group bin, and relates to the field of concrete pouring devices. The group bin concrete pouring device comprises a material mixing device, an adjusting device, a material conveying device and two pouring devices, the adjusting device is arranged at the bottom end of the material mixing device, the material conveying device is arranged at the bottom end of the adjusting device, the two pouring devices are arranged on the two sides of the material conveying device respectively, the material mixing device comprises a material mixing shell, and the material mixing shell is arranged in the material mixing shell. A first gear is fixedly connected to the position, close to the upper portion, of the front end of the first baffle, a second baffle is rotationally connected to the other side of the bottom end of the mixing shell, and a first telescopic rod is rotationally connected to the side wall of the first baffle. By arranging the mixing device, bubbles in concrete are effectively eliminated in the pouring process, by arranging the adjusting device, the uniformity in the pouring process can be improved, by arranging the pouring device, the concrete is prevented from splashing all around in the pouring process, and by arranging the conveying device, the concrete is effectively conveyed.
Need to check novelty before this filing date? Find Prior Art