Shield construction method based on oversized-diameter shield tunnel segment floating control
By optimizing parameters such as excavation posture, excavation pressure and grouting management in the construction of super-large diameter shield tunnels, the problem of pipe sheet floating is solved and the quality and stability of tunnel molding are improved.
Patent Information
- Application Number
- CN202411610012.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-12
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2044-11-12
AI Technical Summary
During the construction of an ultra-large diameter shield tunnel, the pipe sheet has serious problems, which can easily lead to leakage of pipe sheets, staggered stages, damage and tunnel ellipticity exceeding the standard, affecting the overall performance and long-term stability of the tunnel.
Effectively control the floating of the pipe sheet by optimizing the shield construction process and parameters, including controlling the excavation posture, setting the excavation pressure, optimizing the grouting management system, synchronous grouting and secondary grouting behind the pipe sheet, advance grouting, radial grouting of the shield machine and bolt retightening.
It realizes effective control of the floating of the pipe sheet of the ultra-large diameter shield tunnel, improves the quality of tunnel forming, reduces construction risks and uncertainties, and ensures the overall stability and waterproof performance of the tunnel.