A BIM modeling method, system, and medium for pile-column tunnel portals.

By determining the portal modeling base point and local coordinate system in the 3D modeling of the pile-column tunnel portal, creating models of piles, pile cap stones, end walls and wing walls, and establishing the dependencies between components, the problem of low modeling efficiency and positioning accuracy in the existing technology is solved, and efficient model updating and accurate component positioning are achieved.

CN123116397APending Publication Date: 2026-11-17CHENGDU CONSTR ENG GROUP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611259437.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-19
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies lack a modeling method that can combine the spatial location of the tunnel, the tunnel structure, and the spatial relationships between various components in the 3D modeling process of pile-column tunnel portals. This results in low modeling efficiency and positioning accuracy, and cumbersome model updates after parameter changes.

Method used

By acquiring route data, a route model is created, the portal modeling base point is determined, and a local coordinate system is established. The models of piles, pile cap stones, end walls, and wing walls are created in sequence, and the other side model is generated through mirror transformation. The dependency relationship between the component modeling base points is established to achieve automatic model updates.

Benefits of technology

It improves the modeling efficiency and positioning accuracy of pile-column tunnel portals, reduces manual measurement errors, reduces repetitive modeling operations, improves the efficiency of model updates after parameter adjustments, and reduces the possibility of missing or incorrect modifications to related components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123116397A_ABST
    Figure CN123116397A_ABST
Patent Text Reader

Abstract

This invention discloses a BIM modeling method, system, and medium for pile-and-column tunnel portals, relating to the field of 3D modeling technology. It includes: creating a route model and a tunnel body model based on route data; establishing a local coordinate system based on the portal modeling reference points, sequentially determining the pile top center point, the intermediate end wall cap stone design reference point, the one-sided end wall cap stone design reference point, and the one-sided wing wall design reference point, and creating corresponding pile, pile cap stone, end wall, end wall cap stone, and wing wall models; performing Boolean difference operations on the intermediate end wall model based on the outer contour of the tunnel body model; generating the other side model through mirror transformation; establishing the dependency relationships between the design reference points of each component, and identifying and updating the affected components when the design reference points or component parameters change. This invention can improve the modeling and related update efficiency of pile-and-column tunnel portals.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of three-dimensional modeling technology, specifically to a BIM modeling method, system, and medium for a pile-column tunnel portal. Background Technology

[0002] Building Information Modeling (BIM) technology can digitally represent the geometric and attribute information of engineering structures and is currently widely used in the design, construction, and operation and maintenance of tunnel engineering. Compared with traditional two-dimensional design methods, three-dimensional modeling can more intuitively reflect the spatial relationship between tunnel structures and components, and is conducive to improving the efficiency of engineering design, model reuse, and subsequent information management.

[0003] Pile-and-column tunnel portals typically consist of multiple components, including piles, pile caps, intermediate end walls, intermediate end wall caps, side end walls, side end wall caps, and wing walls. These components have complex spatial positioning and dimensional relationships. Current modeling processes usually require determining the dimensions and spatial positions of each component based on 2D design drawings, followed by manual creation, positioning, and adjustment of the components sequentially. When changes occur in the horizontal and vertical alignment of the tunnel, the portal location, or component dimensions, the relevant components often need to be repositioned or adjusted, easily leading to problems such as inaccurate connections between components and omissions in modifications.

[0004] While existing parametric modeling methods can improve the efficiency of model creation and modification by setting component size parameters, for structures like pile-and-column tunnel portals, which consist of multiple interconnected components, there is still a lack of a modeling method that can accurately locate, continuously create, and update each component by combining the spatial location of the tunnel, the tunnel structure, and the spatial relationships between the portal components. Therefore, improving the modeling efficiency, positioning accuracy, and model update efficiency after parameter changes in 3D models of pile-and-column tunnel portals is a problem that needs to be solved. Summary of the Invention

[0005] The technical problem this invention aims to solve is: Existing engineering construction modeling methods for pile-and-column tunnel portals, which consist of multiple interconnected components, lack the ability to integrate the spatial location of the tunnel, the tunnel structure, and the spatial relationships between the portal components. This invention provides a BIM modeling method, system, and medium for pile-and-column tunnel portals to address the issues of requiring separate positioning and adjustment of each component during existing 3D modeling processes, difficulty in maintaining spatial relationships between components, resulting in low modeling efficiency and positioning accuracy, and cumbersome updates to related components after parameter changes.

[0006] This invention is achieved through the following technical solution:

[0007] A BIM modeling method for pile-and-column tunnel portals includes:

[0008] Acquire route data, create a route model based on the route data, and create a tunnel body model based on the route model;

[0009] The portal modeling base point is determined based on the start and end mileage of the tunnel body model. A local coordinate system is established based on the portal modeling base point and the line direction of the line model at the portal modeling base point. The center point of the pile top of one side pile is determined based on the pile positioning parameters and the portal modeling base point. The pile top center point and pile cap stone model of one side pile are created based on the pile top center point.

[0010] The base point for the design of the intermediate end cap stone is determined based on the center point of the pile top. The intermediate end cap stone model and the intermediate end wall model are created based on the base point of the design of the intermediate end cap stone. Boolean difference operation is performed on the intermediate end wall model based on the outer contour of the tunnel body model to obtain the intermediate end wall model with the tunnel body passage.

[0011] Based on the central end cap stone design base point, determine the side end cap stone design base point, create a side end cap stone model and a side end wall model based on the side end cap stone design base point, and determine the side wing wall design base point based on the cross-section points of the side end wall model, and create a side wing wall model based on the side wing wall design base point.

[0012] The models of the pile and pile cap stone on one side, the cap stone of the end wall on one side, the end wall on one side, and the wing wall on one side are mirrored to obtain the corresponding models on the other side.

[0013] Establish the dependency relationship between the modeling base points of each component. When any modeling base point or component parameter changes, determine the affected component according to the dependency relationship, and recalculate the modeling base point and cross-section point of the affected component according to the dependency relationship. Update the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

[0014] Furthermore, the process involves acquiring route data, creating a route model based on the route data, and creating a tunnel body model based on the route model, including:

[0015] Read the planar data, longitudinal profile data, and chain break data of the line from the line database, convert the planar data and longitudinal profile data into corresponding line geometric elements, and generate the line geometry based on the line geometric elements;

[0016] Based on the conversion relationship between mileage and route length, the broken chain data is associated with the route geometry to obtain the route model;

[0017] Obtain the starting and ending mileages of the tunnel body, and lay out the preset tunnel body cross-section template along the line model within the range defined by the starting and ending mileages to obtain the tunnel body model.

[0018] Furthermore, a local coordinate system is established based on the portal modeling base point and the route direction of the route model at the portal modeling base point, including:

[0019] Taking the tunnel portal modeling base point as the origin, the horizontal tangential direction of the line along the mileage increase direction at the tunnel portal modeling base point is the first direction, and the vertical upward direction is the third direction. The direction perpendicular to the line is determined as the second direction based on the first direction and the third direction.

[0020] The center point of the pile top is determined based on the horizontal distance of the pile top center point relative to the portal modeling base point in the second direction and the vertical distance in the third direction.

[0021] The pile top section is determined based on the length of the pile section along the first direction and the width along the second direction. The pile bottom section is obtained by offsetting the pile top section downward along the third direction by the pile length. The pile top section and the pile bottom section are then laid out to generate the pile on one side.

[0022] Furthermore, a pile cap stone model is created based on the center point of the pile top, including:

[0023] Based on the pile top section, the bottom section point set, middle section point set, and top section point set of the pile cap stone are determined according to the outer overhang width of the pile cap stone, the pile cap height, the height of the top tapering section of the pile cap, and the top width of the pile cap stone.

[0024] Based on the bottom section point set, middle section point set, and top section point set, corresponding sections are generated respectively, and each section is laid out to obtain the pile cap stone model.

[0025] Furthermore, based on the center point of the pile top, the base point for the intermediate end cap stone design is determined, and based on the base point, a model of the intermediate end cap stone and a model of the intermediate end wall are created, including:

[0026] The base point for the intermediate end cap stone is determined based on the vertical distance, the distance along the line, and the distance perpendicular to the line from the base point of the intermediate end cap stone relative to the center point of the pile top.

[0027] The first side section point set is determined based on the design base point of the middle end cap stone and the cross-sectional parameters of the middle end cap stone. The first side section point set is offset along the length direction of the cap stone to obtain the second side section point set. The middle end cap stone model is generated based on the first side section point set and the second side section point set.

[0028] The design base point of the middle end wall is determined based on the design base point of the middle end wall cap stone, and the middle end wall model without openings is generated based on the design base point of the middle end wall and the cross-sectional parameters of the middle end wall.

[0029] Extract the outer contour of the tunnel body model, generate a closed contour surface based on the outer contour, and stretch the closed contour surface along the line direction to form a cutting body. Use the cutting body to perform Boolean difference operation on the unopened intermediate end wall model.

[0030] Furthermore, based on the design base points of the end cap stone on one side, a model of the end cap stone on one side and a model of the end wall on one side are created. The design base points of the wing wall on one side are determined based on the cross-sectional points of the end wall model on one side. A model of the wing wall on one side is then created based on these design base points, including:

[0031] Based on the design base point of the end cap stone on one side and the cross-sectional parameters of the end cap stone on one side, determine the cross-sections of the two end cap stones, and then lay out the two cross-sections of the end cap stones to generate the model of the end cap stone on one side.

[0032] The design base point of one end wall is determined based on the design base point of the cap stone of one end wall. The cross-sections of two end walls are determined based on the design base point of one end wall, the thickness of the end wall, the height of the outer side of the end wall, the height of the inner side of the end wall, and the length of the lower side of the end wall. The two cross-sections of the end walls are then laid out to generate the model of the one end wall.

[0033] The model base points of the wing wall on one side are determined from the cross-sectional point set of the end wall on one side. The front section and rear section of the wing wall are determined according to the wing wall length, wing wall width, front height of the wing wall, rear height of the wing wall and wing wall slope, respectively. The front section and rear section of the wing wall are then laid out to generate the model of the wing wall on one side.

[0034] Furthermore, the models of the pile and pile cap stone on one side, the cap stone of the end wall on one side, the end wall on one side, and the wing wall on one side are mirrored, including:

[0035] Determine a vertical plane that passes through the portal modeling base point and is jointly defined by the line direction and vertical direction of the line model at the portal modeling base point, and use the vertical plane as a mirror plane;

[0036] Using the mirrored plane as the plane of symmetry, the models of the pile and pile cap stone on one side, the cap stone on one side, the end wall on one side, and the wing wall on one side are mirrored and copied to obtain the corresponding models on the other side.

[0037] Furthermore, the dependency relationships between the modeling base points of each component are established. When any modeling base point or component parameter changes, the affected component is determined according to the dependency relationships, and the modeling base points and cross-sectional points of the affected component are recalculated according to the dependency relationships, including:

[0038] A directed acyclic dependency relationship is established based on the coordinates between the base points of each component's shape.

[0039] In response to changes in the modeling base point or component parameters, the affected components associated with the changes are determined based on the directed acyclic dependency relationship.

[0040] According to the order determined by the directed acyclic dependency relationship, the modeling base points and cross-section points of the affected components are recalculated in sequence, and the corresponding three-dimensional models are reconstructed based on the recalculated modeling base points and cross-section points.

[0041] When the affected component includes the middle end wall, the Boolean difference operation is re-performed on the middle end wall according to the outer contour of the current tunnel body model; when the affected component includes a mirror-generated component, the mirror-generated component is updated according to the corresponding side component.

[0042] This invention also provides a BIM modeling system for pile-and-column tunnel portals, used to implement the aforementioned BIM modeling method for pile-and-column tunnel portals, comprising:

[0043] The basic model creation module is used to acquire line data, create a line model based on the line data, and create a tunnel body model based on the line model.

[0044] The pile and pile cap stone creation module is used to determine the portal modeling base point according to the start and end mileage of the tunnel body model, establish a local coordinate system according to the portal modeling base point and the line direction of the line model at the portal modeling base point, determine the center point of the pile top of one side pile according to the pile positioning parameters and the portal modeling base point, and create the pile and pile cap stone model of one side pile according to the center point of the pile top.

[0045] The end wall creation module is used to determine the base point of the middle end wall cap stone shape based on the center point of the pile top, create the middle end wall cap stone model and the middle end wall model based on the base point of the middle end wall cap stone shape, perform Boolean difference operation on the middle end wall model based on the outer contour of the tunnel body model, and create a side end wall cap stone model and a side end wall model based on the base point of the middle end wall cap stone shape.

[0046] The wing wall creation module is used to determine the wing wall modeling base point based on the cross-section points of the wing wall model and to create the wing wall model based on the wing wall modeling base point.

[0047] The mirroring module is used to mirror the pile and pile cap stone model, the end wall cap stone model, the end wall model, and the wing wall model on one side to obtain the corresponding model on the other side.

[0048] The associated update module is used to establish the dependency relationship between the modeling base points of each component, and when any modeling base point or component parameter changes, it determines the affected component according to the dependency relationship, recalculates the modeling base point and cross-section point of the affected component according to the dependency relationship, and updates the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

[0049] The present invention also provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the program to implement the BIM modeling method for the pile-type tunnel portal as described above.

[0050] The present invention also provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the BIM modeling method for pile-type tunnel portals as described above.

[0051] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0052] This invention determines the portal modeling base point based on the line model and tunnel body model, and establishes a local coordinate system based on the portal modeling base point. Through the spatial relationship between the pile top center point, the middle end wall cap stone modeling base point, the side end wall cap stone modeling base point and the side wing wall modeling base point, the positioning and three-dimensional model creation of the pile, pile cap stone, end wall, end wall cap stone and wing wall are completed in sequence. This allows the position of each component to be determined according to a unified spatial benchmark, reduces the error caused by manual measurement and one-by-one positioning, and improves the modeling efficiency and positioning accuracy of the pile-column tunnel portal.

[0053] Simultaneously, Boolean difference operations are performed on the intermediate end wall model based on the outer contour of the tunnel body model to match the resulting tunnel passage with the tunnel body model. A mirror transformation is then used to generate the corresponding component on the other side, further reducing repetitive modeling operations. By establishing dependencies between the modeling base points of each component, affected components are identified when modeling base points or component parameters change. These affected components are then recalculated and the model updated according to the dependencies, thus avoiding repeated modeling of unaffected components, improving the efficiency of model updates after parameter adjustments, and reducing the possibility of missing or incorrect modifications to related components. Attached Figure Description

[0054] To more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly described below. It should be understood that the following drawings only show some embodiments of the present invention and should not be considered as a limitation of the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort. In the drawings:

[0055] Figure 1 This is a flowchart illustrating the BIM modeling method for the pile-column tunnel portal of the present invention.

[0056] Figure 2 This is a schematic diagram of the route model and tunnel body model of the present invention;

[0057] Figure 3 This is a schematic diagram showing the parameter settings for the tunnel cross-section template of the present invention;

[0058] Figure 4a This is a schematic diagram showing the positioning and parameters of the pile of the present invention;

[0059] Figure 4b This is a schematic diagram of the parameters of the pile cap stone of the present invention;

[0060] Figure 5a This is a side view of the middle end wall of the present invention;

[0061] Figure 5b This is a front view of the middle end wall of the present invention;

[0062] Figure 5c This is a schematic diagram showing the dimensions of the middle end cap stone of the present invention;

[0063] Figure 5d This is a schematic diagram showing the positional relationship between the intermediate end wall and the intermediate end wall cap stone of the present invention;

[0064] Figure 6a This is a schematic diagram showing the positional relationship between one end wall and the pile of this invention;

[0065] Figure 6b This is a schematic diagram showing the size and positional relationship between the end wall and the end wall cap stone on one side of the present invention;

[0066] Figure 7a This is a frontal schematic diagram of the wing wall of the present invention;

[0067] Figure 7b This is a side view of the wing wall of the present invention;

[0068] Figure 8 This is a schematic diagram of the positional relationship model of the pile, the middle end wall, the left end wall and the wing wall of the present invention;

[0069] Figure 9aThis is a schematic diagram showing the positional relationship between the mirror plane of the present invention and the pile-column tunnel portal model;

[0070] Figure 9b This is a schematic diagram showing the positional relationship between the mirrored surface and the pile-column tunnel portal model of the present invention. Detailed Implementation

[0071] To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the embodiments and accompanying drawings. The illustrative embodiments and descriptions of the present invention are only used to explain the present invention and are not intended to limit the present invention.

[0072] Example 1

[0073] like Figure 1 As shown, this embodiment provides a BIM modeling method for pile-column tunnel portals, including the following steps:

[0074] S1: Obtain route data, create a route model based on the route data, and create a tunnel body model based on the route model.

[0075] Specifically, the planar data, longitudinal profile data, and chain break data of the route are read from the route database MDB. The planar data and longitudinal profile data are converted into corresponding route geometric elements. The route geometry is generated by calling the interface tool based on the converted route geometric elements. According to the conversion relationship between route mileage and route length, the chain break data is associated with the corresponding route geometry to obtain a route model containing route geometry and chain break information.

[0076] Furthermore, such as Figure 2 and Figure 3 As shown, a preset tunnel cross-section template is imported, which defines the geometric shape and dimensional parameters of the tunnel cross-section. The start and end mileages of the tunnel are obtained, and the tunnel cross-section template is laid out along the route model within the range defined by the start and end mileages to generate a three-dimensional solid model of the tunnel. The engineering attribute information of lining type, surrounding rock grade, and cross-sectional dimensions is associated with the three-dimensional solid model of the tunnel.

[0077] In this embodiment, the points on the route model at the start and end points of the tunnel are denoted as Pstart and Pend, respectively. Pstart and Pend serve as the modeling base points for the portals at both ends of the tunnel. The modeling process is illustrated below using the pile-and-column tunnel portal at Pstart as an example. The pile-and-column tunnel portal at Pend can be modeled using the same method. A corresponding local coordinate system is re-established based on the route direction at Pend, and the portal model is created.

[0078] S2: Determine the portal modeling base point based on the start and end mileage of the tunnel body model. Establish a local coordinate system based on the portal modeling base point and the line direction of the line model at the portal modeling base point. Determine the center point of the pile top of one side pile based on the pile positioning parameters and the portal modeling base point. Create the model of the pile top and pile cap stone of one side pile based on the center point of the pile top.

[0079] Specifically, in this embodiment, the left side is referred to as the side. The portal modeling base point Pstart is taken as the origin of the local coordinate system. The horizontal tangential direction of the line along the mileage increase direction at Pstart is taken as the positive X-axis direction, and the vertical upward direction is taken as the positive Z-axis direction. The direction perpendicular to the line is determined based on the X-axis direction and the Z-axis direction as the Y-axis direction, where the positive Y-axis direction points to the left side of the line.

[0080] Using the aforementioned local coordinate system, geometric parameters along the route, perpendicular to the route, and vertically can be calculated separately. When the route has a horizontal curve, the direction of the X-axis in the horizontal plane is determined based on the tangential direction of the route at Pstart; when the route has a longitudinal slope or a vertical curve, the Z-axis remains vertical, thus extending the pile vertically and allowing the horizontal and vertical positioning parameters of the component to be calculated separately.

[0081] like Figure 4a As shown, the pile positioning parameters include the horizontal distance PLH and vertical distance PLV of the pile top center point Ptopcenter relative to the portal modeling base point Pstart; the pile section parameters include the length PCL of the pile section along the X-axis, the width PCW along the Y-axis, and the pile length Plength.

[0082] The center point of the pile top, Ptopcenter, is represented as:

[0083]

[0084] in, and These represent the unit vectors along the Y-axis and Z-axis of the local coordinate system, respectively.

[0085] With Ptopcenter as the center of the rectangular section at the pile top, the four corner points of the section at the pile top are represented as follows:

[0086]

[0087]

[0088]

[0089]

[0090] Offset each pile top section corner point along the negative Z-axis by the pile length Plength to obtain:

[0091]

[0092] Where i = 0, 1, 2, 3.

[0093] The pile top and bottom sections are generated based on PileTopPoints and PileBottomPoints respectively. The pile top and bottom sections are then used as the starting and ending sections for lofting to generate a three-dimensional solid model of the left pile.

[0094] Furthermore, such as Figure 4b As shown, a pile cap model is created based on the pile. The pile cap parameters include the overhang width zmb, the pile cap height zmh, the height of the top taper segment of the pile cap zmth, and the top width of the pile cap zmtb.

[0095] Using the pile top section as a reference, the corner points of the pile top section are offset outward in the horizontal plane according to the overhang width zmb to determine the bottom section point set of the pile cap. The elevation of the middle section of the pile cap is determined based on the pile cap height zmh and the top tapering height zmth, while maintaining the horizontal dimensions of the middle section corresponding to the bottom section. Based on the middle section, the top tapering height zmth is extended along the positive Z-axis, while simultaneously tapering towards the center along the Y-axis to the top width zmtb of the pile cap, thus determining the top section point set of the pile cap. Corresponding sections are generated based on the bottom, middle, and top section point sets, and each section is sequentially lofted to obtain the three-dimensional solid model of the pile cap.

[0096] S3: Determine the base point for the intermediate end cap stone shape based on the center point of the pile top, create the intermediate end cap stone model and the intermediate end wall model based on the base point for the intermediate end cap stone shape, and perform Boolean difference operation on the intermediate end wall model based on the outer contour of the tunnel body model to obtain the intermediate end wall model with the tunnel body passage.

[0097] Specifically, such as Figure 5a and Figure 5b As shown, the positioning parameters of the middle end cap stone include L1, L2, L3 and L4. Among them, L1 represents the vertical distance from the pile top center point Ptopcenter to the shape base point Pms of the middle end cap stone, L2 represents the distance from Ptopcenter to Pms along the line direction, L3 represents the distance from Ptopcenter to Pms in the vertical line direction, and L4 represents the length of the middle end cap stone along the Y-axis.

[0098] The base point Pms of the middle end cap stone design is represented as:

[0099]

[0100] like Figure 5c As shown, using Pms as the reference, the key points of each contour of the cap stone's cross-section are calculated based on the cross-sectional parameters of the middle end cap stone, resulting in the first side section point set. The first side section point set is then offset by L4 along the length of the cap stone to obtain the second side section point set. Corresponding cross-sections are generated based on the first and second side section point sets, and the two cross-sections are lofted to generate a three-dimensional solid model of the middle end cap stone.

[0101] Furthermore, such as Figure 5d As shown, the design base point Pdq of the intermediate end wall is determined based on the design base point Pms of the intermediate end wall cap stone and the connection relationship between the intermediate end wall and the intermediate end wall cap stone. The cross-sectional parameters of the intermediate end wall include the cross-sectional thickness qb along the X-axis and the cross-sectional height qh along the Z-axis. Using Pdq as the reference, the cross-sectional points of the first side cross-section of the intermediate end wall are calculated according to the aforementioned cross-sectional parameters. The cross-sectional points of the first side cross-section are offset by L4 along the positive Y-axis to obtain the corresponding cross-sectional points of the second side cross-section. Two cross-sections are generated and lofted to obtain a three-dimensional solid model of the intermediate end wall without openings.

[0102] Since the intermediate end wall is located at the end of the tunnel body, a tunnel passage corresponding to the tunnel body needs to be formed in the intermediate end wall. Specifically, the outer contour line of the tunnel body model generated in S1 is extracted, a closed contour surface is constructed based on the outer contour line, and the closed contour surface is stretched along the line direction at a distance not less than the thickness qb of the intermediate end wall section to form a temporary cut body; the temporary cut body and the 3D solid model of the intermediate end wall without openings are used to perform a Boolean difference operation, and the part corresponding to the tunnel body is cut out from the intermediate end wall. After completing the Boolean difference operation, the temporary cut body is deleted to obtain an intermediate end wall model that matches the current outer contour of the tunnel body.

[0103] S4: Determine the design base point of the side wall cap stone based on the design base point of the middle wall cap stone, and create a side wall cap stone model and a side wall model based on the design base point of the side wall cap stone.

[0104] Specifically, such as Figure 6a As shown, based on the design reference point Pms of the middle end cap stone and the design offset relationship between the side end cap stone and the middle end cap stone, the design reference point Pbms of the side end cap stone is determined. The length of the side end cap stone is L5, and its cross-sectional dimensions correspond to those of the middle end cap stone.

[0105] Using Pbms as a reference, the cross-sectional point set of the first end cap stone is calculated based on the cross-sectional parameters of the end cap stone on one side. The cross-sectional point set of the first end cap stone is offset by L5 along the negative Y-axis to obtain the cross-sectional point set of the second end cap stone. Corresponding cross-sections are generated based on the cross-sectional point sets of the two end cap stones respectively, and the layout is performed to obtain the three-dimensional solid model of the end cap stone on one side.

[0106] It should be noted that the specific vertical offset relationship between Pbms and Pms can be determined based on the actual design elevation relationship between the end cap stone on one side and the middle end cap stone.

[0107] like Figure 6b As shown, the design base point Pzdq of one end wall is determined based on the design base point Pbms of the cap stone on one side and the structural relationship between one end wall and the corresponding cap stone. The cross-sectional parameters of one end wall include the end wall thickness dqt, the outer height dqh1, the inner height dqh2, and the lower length dqb.

[0108] Using Pzdq as the reference, the cross-sectional points of the first cross-section of one end wall are determined according to dqh1, dqh2, and dqb. Then, the cross-sectional points of the second cross-section are obtained by offsetting the end wall thickness dqt along the X-axis from the cross-sectional points of the first cross-section. The cross-sections of the end wall are generated based on the cross-sectional points of the two cross-sections, and then lofted to obtain the three-dimensional solid model of one end wall.

[0109] S5: Determine the base point of the wing wall shape based on the cross-section point of the wing wall model, and create the wing wall model based on the base point of the wing wall shape.

[0110] Specifically, such as Figure 7a and Figure 7b As shown, the parameters of one wing wall include the wing wall width yqw, the wing wall length along the Y-axis yql, the wing wall front height yqh1, the wing wall rear height yqh2, and the wing wall slope rate.

[0111] The cross-sectional point corresponding to the connection position of the wing wall is selected from the set of cross-sectional points of the first cross-section of the end wall on one side as the shape base point Pyq of the wing wall on one side. In one specific implementation, Pyq is the third point in the set of cross-sectional points of the first cross-section of the end wall on one side, that is, the lower outer corner point of the cross-section of the end wall.

[0112] Using Pyq as a reference, the contour points of the front section of the wing wall are determined based on the front height yqh1, forming a point set for the front section of the wing wall. Pyq is offset along the negative Y-axis by the wing wall width yqw to determine the reference position of the rear section of the wing wall. The contour points of the rear section of the wing wall are then determined based on the rear height yqh2 and the wing wall slope rate. The elevation change of the wing wall top surface between the front and rear sections is determined based on the wing wall slope rate and the wing wall width yqw.

[0113] Based on the point sets of the front and rear sections of the wing wall, corresponding sections are generated, and the two sections are lofted to obtain a three-dimensional solid model of one side of the wing wall.

[0114] Thus, as Figure 8 As shown, the positioning and 3D model creation of the pile and pile cap stone on one side, the middle end wall and middle end wall cap stone on the middle end wall, the end wall and end wall cap stone on one side, and the wing wall on one side are completed.

[0115] S6: Perform a mirror transformation on the model of the pile and pile cap stone on one side, the model of the cap stone on one side, the model of the end wall on one side, and the model of the wing wall on one side to obtain the corresponding model on the other side.

[0116] Specifically, such as Figure 9a and Figure 9b As shown, a vertical plane passing through the centerline of the track is used as the mirror plane. The mirror plane passes through the centerline of the track, and its normal direction is the Y-axis direction of the local coordinate system.

[0117] Using the mirror plane as the plane of symmetry, the already generated models of one side pile and pile cap stone, one side end wall and end wall cap stone, and one side wing wall are mirrored and copied to generate the other side pile and pile cap stone, the other side end wall and end wall cap stone, and the other side wing wall, thus forming a complete three-dimensional model of the pile-column tunnel portal.

[0118] S7: Establish the dependency relationship between the modeling base points of each component. When any modeling base point or component parameter changes, determine the affected component according to the dependency relationship, and recalculate the modeling base point and cross-section point of the affected component according to the dependency relationship. Update the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

[0119] Specifically, a directed acyclic dependency relationship is established based on the coordinates of the aforementioned modeling base points. Specifically, the portal modeling base point Pstart is the upstream base point; the pile top center point Ptopcenter is determined based on Pstart; and the middle end wall cap stone modeling base point Pms is determined based on Ptopcenter. The middle end wall modeling base point Pdq and the one-sided end wall cap stone modeling base point Pbms are determined based on Pms and the structural relationships between the corresponding components, respectively. The one-sided end wall modeling base point Pzdq is determined based on Pbms, and the one-sided wing wall modeling base point Pyq is determined based on the one-sided end wall section point corresponding to Pzdq.

[0120] Thus, a directed dependency relationship is formed between each model base point, from the upstream base point to the downstream base point, and there is no circular dependency formed by the downstream base point pointing back to its upstream base point.

[0121] When any modeling base point or component parameter changes, the component affected by the change is determined based on its position in the directed acyclic dependency relationship, and the corresponding component is marked as an affected component that needs to be updated. The change propagates downstream along the dependency relationship without affecting upstream components that do not have a dependency relationship with the change.

[0122] For example, when modifying the horizontal distance PLH used to determine the center point Ptopcenter of the pile top, Ptopcenter is redefined, and the pile and pile cap are regenerated. At the same time, the intermediate end wall cap and its downstream components are updated along the dependency relationship. When only the wing wall slope rate is modified, since the wing wall slope is only used to determine the wing wall cross section and does not participate in the calculation of the upstream component modeling base point, the corresponding wing wall is identified as the affected component, and there is no need to recreate the pile, pile cap and end wall models.

[0123] After identifying the affected components, updates are performed in the order determined by the directed acyclic dependency relationship. Specifically, this includes: recalculating the 3D coordinates of all downstream modeling base points starting from the changed modeling base point; re-determining the cross-sectional point set based on the recalculated modeling base points and the corresponding component cross-sectional parameters; and re-performing the lofting based on the re-determined cross-sectional point set to reconstruct the corresponding 3D solid model.

[0124] When the affected component includes the middle end wall, the outer contour of the current tunnel body model is re-extracted and a temporary cutting body is regenerated. Boolean difference operation is performed on the reconstructed middle end wall to ensure that the tunnel passage of the middle end wall matches the current tunnel body model. When the affected component includes the other side component generated by mirroring, the mirror transformation is re-executed based on the updated one side component to ensure that the two side components remain corresponding.

[0125] Furthermore, to reduce errors in 3D model generation caused by abnormal parameter settings, this embodiment can also perform parameter validity verification and geometric rationality detection during model creation and updating.

[0126] Specifically, the input geometric parameters are validated to ensure that the length, width, and height parameters used to generate components meet the geometric generation conditions of the corresponding components. After the calculation of each modeling base point and section point is completed, the coverage relationship between the pile cap stone and the pile top surface, the remaining thickness of the walls surrounding the opening after the opening in the middle end wall, the section matching relationship at the connection position of one wing wall and one end wall, and the section correspondence relationship at the connection position of one end wall cap stone and the middle end wall cap stone are checked. When a geometric conflict is detected, the corresponding conflict location and conflict type are output so that the corresponding component parameters can be adjusted.

[0127] For lines with broken links, the cumulative mileage corresponding to Pstart and Pend can be verified based on the broken link data to determine that the portal modeling base point is within the effective line mileage range. When the line geometry changes significantly in the region where the portal is located, the local coordinate system and component positioning results are reviewed to reduce component positioning deviations caused by changes in line geometry.

[0128] Example 2

[0129] A BIM modeling system for pile-and-column tunnel portals, used to implement the BIM modeling method for pile-and-column tunnel portals in Embodiment 1, includes:

[0130] The basic model creation module is used to acquire line data, create a line model based on the line data, and create a tunnel body model based on the line model.

[0131] The pile and pile cap stone creation module is used to determine the portal modeling base point according to the start and end mileage of the tunnel body model, establish a local coordinate system according to the portal modeling base point and the line direction of the line model at the portal modeling base point, determine the center point of the pile top of one side pile according to the pile positioning parameters and the portal modeling base point, and create the pile and pile cap stone model of one side pile according to the center point of the pile top.

[0132] The end wall creation module is used to determine the base point of the middle end wall cap stone shape based on the center point of the pile top, create the middle end wall cap stone model and the middle end wall model based on the base point of the middle end wall cap stone shape, perform Boolean difference operation on the middle end wall model based on the outer contour of the tunnel body model, and create a side end wall cap stone model and a side end wall model based on the base point of the middle end wall cap stone shape.

[0133] The wing wall creation module is used to determine the wing wall modeling base point based on the cross-section points of the wing wall model and to create the wing wall model based on the wing wall modeling base point.

[0134] The mirroring module is used to mirror the pile and pile cap stone model, the end wall cap stone model, the end wall model, and the wing wall model on one side to obtain the corresponding model on the other side.

[0135] The associated update module is used to establish the dependency relationship between the modeling base points of each component, and when any modeling base point or component parameter changes, it determines the affected component according to the dependency relationship, recalculates the modeling base point and cross-section point of the affected component according to the dependency relationship, and updates the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

[0136] Example 3

[0137] An electronic device includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, it implements a BIM modeling method for a pile-type tunnel portal as described in Embodiment 1.

[0138] Example 4

[0139] A computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements a BIM modeling method for a pile-type tunnel portal as described in Example 1.

[0140] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0141] This invention is described with reference to flowchart illustrations and / or block diagrams of methods (systems) and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and / or block diagrams, as well as combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0142] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0143] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1The steps of the function specified in one or more boxes.

[0144] Those skilled in the art will understand that all or part of the steps in the above methods can be executed by computer program instructions to related hardware. The computer program can be stored in a computer-readable storage medium, such as ROM, RAM, disk, or optical disk.

[0145] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of the present invention. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A BIM modeling method of a pile tunnel portal, characterized by, include: Acquire route data, create a route model based on the route data, and create a tunnel body model based on the route model; The portal modeling base point is determined based on the start and end mileage of the tunnel body model. A local coordinate system is established based on the portal modeling base point and the line direction of the line model at the portal modeling base point. The center point of the pile top of one side pile is determined based on the pile positioning parameters and the portal modeling base point. The pile top center point and pile cap stone model of one side pile are created based on the pile top center point. The base point for the design of the intermediate end cap stone is determined based on the center point of the pile top. The intermediate end cap stone model and the intermediate end wall model are created based on the base point of the design of the intermediate end cap stone. Boolean difference operation is performed on the intermediate end wall model based on the outer contour of the tunnel body model to obtain the intermediate end wall model with the tunnel body passage. Based on the central end cap stone design base point, determine the side end cap stone design base point, create a side end cap stone model and a side end wall model based on the side end cap stone design base point, and determine the side wing wall design base point based on the cross-section points of the side end wall model, and create a side wing wall model based on the side wing wall design base point. The models of the pile and pile cap stone on one side, the cap stone of the end wall on one side, the end wall on one side, and the wing wall on one side are mirrored to obtain the corresponding models on the other side. Establish the dependency relationship between the modeling base points of each component. When any modeling base point or component parameter changes, determine the affected component according to the dependency relationship, and recalculate the modeling base point and cross-section point of the affected component according to the dependency relationship. Update the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

2. The BIM modeling method of a pile portal tunnel according to claim 1, characterized in that, Acquire route data, create a route model based on the route data, and create a tunnel body model based on the route model, including: Read the planar data, longitudinal profile data, and chain break data of the line from the line database, convert the planar data and longitudinal profile data into corresponding line geometric elements, and generate the line geometry based on the line geometric elements; Based on the conversion relationship between mileage and route length, the broken chain data is associated with the route geometry to obtain the route model; Obtain the starting and ending mileages of the tunnel body, and lay out the preset tunnel body cross-section template along the line model within the range defined by the starting and ending mileages to obtain the tunnel body model.

3. The BIM modeling method of a pile portal tunnel according to claim 1, wherein, A local coordinate system is established based on the portal modeling base point and the route direction of the route model at the portal modeling base point, including: Taking the tunnel portal modeling base point as the origin, the horizontal tangential direction of the line along the mileage increase direction at the tunnel portal modeling base point is the first direction, and the vertical upward direction is the third direction. The direction perpendicular to the line is determined as the second direction based on the first direction and the third direction. The center point of the pile top is determined based on the horizontal distance of the pile top center point relative to the portal modeling base point in the second direction and the vertical distance in the third direction. The pile top section is determined based on the length of the pile section along the first direction and the width along the second direction. The pile bottom section is obtained by offsetting the pile top section downward along the third direction by the pile length. The pile top section and the pile bottom section are then laid out to generate the pile on one side.

4. The BIM modeling method of a pile portal tunnel according to claim 3, characterized in that, Create a pile cap stone model based on the center point of the pile top, including: Based on the pile top section, the bottom section point set, middle section point set, and top section point set of the pile cap stone are determined according to the outer overhang width of the pile cap stone, the pile cap height, the height of the top tapering section of the pile cap, and the top width of the pile cap stone. Based on the bottom section point set, middle section point set, and top section point set, corresponding sections are generated respectively, and each section is laid out to obtain the pile cap stone model.

5. The BIM modeling method for pile-column tunnel portals according to claim 1, characterized in that, Based on the center point of the pile top, determine the base point for the intermediate end cap stone design. Based on this base point, create the intermediate end cap stone model and the intermediate end wall model, including: The base point for the intermediate end cap stone is determined based on the vertical distance, the distance along the line, and the distance perpendicular to the line from the base point of the intermediate end cap stone relative to the center point of the pile top. The first side section point set is determined based on the design base point of the middle end cap stone and the cross-sectional parameters of the middle end cap stone. The first side section point set is offset along the length direction of the cap stone to obtain the second side section point set. The middle end cap stone model is generated based on the first side section point set and the second side section point set. The design base point of the middle end wall is determined based on the design base point of the middle end wall cap stone, and the middle end wall model without openings is generated based on the design base point of the middle end wall and the cross-sectional parameters of the middle end wall. Extract the outer contour of the tunnel body model, generate a closed contour surface based on the outer contour, and stretch the closed contour surface along the line direction to form a cutting body. Use the cutting body to perform Boolean difference operation on the unopened intermediate end wall model.

6. The BIM modeling method for pile-column tunnel portals according to claim 1, characterized in that, Based on the design base points of the end cap stone on one side, a model of the end cap stone and a model of the end wall on one side are created. The design base points of the wing wall on one side are determined based on the cross-sectional points of the end wall model. The creation of the wing wall model on one side based on these design base points includes: Based on the design base point of the end cap stone on one side and the cross-sectional parameters of the end cap stone on one side, determine the cross-sections of the two end cap stones, and then lay out the two cross-sections of the end cap stones to generate the model of the end cap stone on one side. The design base point of one end wall is determined based on the design base point of the cap stone of one end wall. The cross-sections of two end walls are determined based on the design base point of one end wall, the thickness of the end wall, the height of the outer side of the end wall, the height of the inner side of the end wall, and the length of the lower side of the end wall. The two cross-sections of the end walls are then laid out to generate the model of the one end wall. The model base points of the wing wall on one side are determined from the cross-sectional point set of the end wall on one side. The front section and rear section of the wing wall are determined according to the wing wall length, wing wall width, front height of the wing wall, rear height of the wing wall and wing wall slope, respectively. The front section and rear section of the wing wall are then laid out to generate the model of the wing wall on one side.

7. The BIM modeling method for pile-column tunnel portals according to claim 1, characterized in that, The mirror transformation of the model of the pile and pile cap stone on one side, the model of the cap stone of the end wall on one side, the model of the end wall on one side, and the model of the wing wall on one side includes: Determine a vertical plane that passes through the portal modeling base point and is jointly defined by the line direction and vertical direction of the line model at the portal modeling base point, and use the vertical plane as a mirror plane; Using the mirrored plane as the plane of symmetry, the models of the pile and pile cap stone on one side, the cap stone on one side, the end wall on one side, and the wing wall on one side are mirrored and copied to obtain the corresponding models on the other side.

8. The BIM modeling method for pile-column tunnel portals according to claim 1, characterized in that, Establish the dependency relationships between the modeling base points of each component. When any modeling base point or component parameter changes, determine the affected component based on the dependency relationships, and recalculate the modeling base points and cross-sectional points of the affected component according to the dependency relationships, including: A directed acyclic dependency relationship is established based on the coordinates between the base points of each component's shape. In response to changes in the modeling base point or component parameters, the affected components associated with the changes are determined based on the directed acyclic dependency relationship. According to the order determined by the directed acyclic dependency relationship, the modeling base points and cross-section points of the affected components are recalculated in sequence, and the corresponding three-dimensional models are reconstructed based on the recalculated modeling base points and cross-section points. When the affected component includes the middle end wall, the Boolean difference operation is re-performed on the middle end wall according to the outer contour of the current tunnel body model; when the affected component includes a mirror-generated component, the mirror-generated component is updated according to the corresponding side component.

9. A BIM modeling system for a pile-column tunnel portal, characterized in that, include: The basic model creation module is used to acquire line data, create a line model based on the line data, and create a tunnel body model based on the line model. The pile and pile cap stone creation module is used to determine the portal modeling base point according to the start and end mileage of the tunnel body model, establish a local coordinate system according to the portal modeling base point and the line direction of the line model at the portal modeling base point, determine the center point of the pile top of one side pile according to the pile positioning parameters and the portal modeling base point, and create the pile and pile cap stone model of one side pile according to the center point of the pile top. The end wall creation module is used to determine the base point of the middle end wall cap stone shape based on the center point of the pile top, create the middle end wall cap stone model and the middle end wall model based on the base point of the middle end wall cap stone shape, perform Boolean difference operation on the middle end wall model based on the outer contour of the tunnel body model, and create a side end wall cap stone model and a side end wall model based on the base point of the middle end wall cap stone shape. The wing wall creation module is used to determine the wing wall modeling base point based on the cross-section points of the wing wall model and to create the wing wall model based on the wing wall modeling base point. The mirroring module is used to mirror the pile and pile cap stone model, the end wall cap stone model, the end wall model, and the wing wall model on one side to obtain the corresponding model on the other side. The associated update module is used to establish the dependency relationship between the modeling base points of each component, and when any modeling base point or component parameter changes, it determines the affected component according to the dependency relationship, recalculates the modeling base point and cross-section point of the affected component according to the dependency relationship, and updates the three-dimensional model of the affected component according to the recalculated modeling base point and cross-section point.

10. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores a computer program, which, when executed by a processor, implements the BIM modeling method for pile-type tunnel portals as described in any one of claims 1-8.