Patents
Literature
Patsnap Eureka AI that helps you search prior art, draft patents, and assess FTO risks, powered by patent and scientific literature data.

768 results about "Pile cap" patented technology

A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. It usually forms part of the foundation of a building, typically a multi-story building, structure or support base for heavy equipment. The cast concrete pile cap distributes the load of the building into the piles. A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.

Construction process of offshore bridge high-rise pile platform

Disclosed in the present invention is a construction process of an offshore bridge high-rise pile platform. A cofferdam of a steel-concrete structure is used for construction. The cofferdam consists of a cofferdam bottom plate prefabricated by means of reinforced concrete and a steel side formwork. The construction process comprises the following stages: a preparation stage, a cofferdam mounting stage, a cofferdam lowering stage, a cofferdam bottom plate blocking and water pumping stage, and a platform concrete pouring stage. The preparation stage comprises the following steps: pile foundation casing sinking, cast-in-place pile construction, pile foundation casing pile head trimming, cofferdam bottom plate and skirt plate prefabrication, and steel side formwork manufacturing. The cofferdam mounting stage comprises: first, mounting the cofferdam bottom plate, and then mounting the steel side formwork, wherein the cofferdam bottom plate is mounted by means of suspension hangers, and each suspension hanger comprises a pile cap, an inverted hanging beam, and two first finish-rolled twisted steel bars. The cofferdam lowering stage comprises mounting a jack lowering system on the cofferdam bottom plate, wherein the cofferdam lowering system comprises I-shaped hangers, carrying pole beams, center hole jacks, and steel strands. The construction process of the present invention can greatly reduce the construction difficulty and can improve the construction efficiency.
Owner:CCCC THIRD HARBOR ENGINEERING CO LTD +1

Building structure automatic design and automatic drawing

A method for automatic design and automatic drawing of building structures is implemented by operating a graphical display interface and a control operation via FSDT and AUD programs. With FSDT program, the user can obtain structural items from architectural drawings, draw and modify columns, walls, beams, slabs, and drop panels, add point loads, line loads, and slab load automatically, set up Ready-to-Run Etabs model and Safe model automatically, design and check concrete column one by one automatically. The user can transfer the Etabs and Safe results into FSDT and AUD programs automatically. With AUD program, the user can get structural drawing information from FSDT program and architectural drawings automatically, make Typical Pile Cap Details and add pile caps on plan automatically, draw and modify shear wall plans, plan rebars, column schedule, Typical Pile Cap Details, CAD Beam, column above-below symbols, column number symbols, section symbols, different elevation symbols automatically.
Owner:PAN SHISHENG

Reverse self-balancing pile foundation bearing capacity detection method based on prefabricated steel pipe pile

The invention provides a reverse self-balancing pile foundation bearing capacity detection method based on prefabricated steel pipe piles, and relates to the technical field of pile foundation detection, and the method comprises the steps that the assembled prefabricated steel pipe piles are constructed at preset elevation positions of a target test field; obtaining first record data and second record data; on the basis of the first recorded data and the second recorded data, the total compressive bearing capacity and the total uplift bearing capacity of the prefabricated steel pipe pile are obtained through calculation according to a reverse self-balancing method; wherein a pile body load box in the loading pile body section is used for loading, the upper pile body and the lower pile body are driven to deform oppositely, and at least the stress of the pile body load box and the opposite displacement of the pile body are recorded as first record data; and a pile top load box in the pile cap loading section is loaded, the upper pile body and the lower pile body are driven to deform oppositely, and at least the stress of the pile top load box and the opposite displacement of the pile body are recorded as second record data. The method for detecting the bearing capacity of the pile foundation is simpler, more efficient and quicker.
Owner:HUBEI UNIV OF TECH +1

Reverse hanging bottom die structure for wharf cast-in-place pile cap construction and installation method of reverse hanging bottom die structure

The invention provides a reverse hanging bottom die structure for wharf cast-in-place pile cap construction and a mounting method of the reverse hanging bottom die structure, and belongs to the technical field of wharf construction. The reverse hanging bottom die structure comprises a steel pipe pile, a stand column support arranged on the steel pipe pile, a transverse steel carrying pole arranged on the stand column, a hanging rod system, a limiting system, a supporting main beam structure and a die frame used for pile cap pouring. The supporting performance of the steel pipe cast-in-place pile is fully utilized, the structural steel structure is used for building the reverse hanging bottom die supporting structure for the cast-in-place pile cap, the defects of a welding construction technology of a traditional bracket supporting system are overcome, the supporting structure facilitating cast-in-place construction of the pile cap is provided, and the construction efficiency of a wharf cast-in-place project is effectively improved.
Owner:CCCC THIRD HARBOR ENGINEERING CO LTD

Pipe pile grouting expanded head pile forming process special for prestressed concrete water jet cutter and pipe

The invention relates to a pipe pile grouting expanded head pile forming process special for a prestressed concrete water jet cutter and a pipe, and belongs to the field of pipe pile construction. The large-head concrete block is integrally connected with the lower end of the tubular pile body and is in an irregular shape, the tubular pile body sequentially comprises a pile cap, a plurality of pipe joints and an inverted-cone-shaped pile head from top to bottom, the tubular pile body is provided with at least one high-pressure water or cement paste channel in the axial direction of the tubular pile body, and the pile head is provided with a material water hole communicated with the high-pressure water or cement paste channel. During construction, even if a special stratum is encountered, the hard stratum is impacted through the high-pressure water jet cutter, and static pressure or hammering is matched, so that the problem that an existing pipe pile is difficult to descend is solved. When the designed elevation is reached, guniting is carried out through high-pressure water or a cement paste channel in the pipe pile body, and a sphere-like expanded head is formed at the bottom of the pipe pile; the bearing capacity of a single pile can be improved, settlement of the pile body is limited, local displacement of the pile body is eliminated, and the anti-floating effect of the pile body is achieved.
Owner:BEIJING ZHENCHONG INTERNATIONAL TRADE CO LTD

Complex geology pile releasing construction method and system based on BIM (Building Information Modeling) technology

The invention relates to the technical field of complex geology pile releasing construction methods based on the BIM technology, and discloses a construction method named as a complex geology pile releasing construction method based on the BIM technology. The method aims at solving the problems of design and construction disjunction, insufficient risk pre-control, low resource utilization rate and the like caused by geological information dimension reduction processing and construction process static management in the prior art. The method is characterized by comprising the following steps: constructing a multi-source heterogeneous geological information full-parameterization three-dimensional attribute body model, and carrying out integrated simulation optimization design on a single-group pile cap based on the model; and sensing construction parameters in real time to dynamically correct the geologic model, so as to generate a self-adaptive construction control instruction and high-precision lofting data. By the adoption of the technical scheme, the safety, economical efficiency and environment friendliness of pile foundation engineering can be remarkably improved.
Owner:HANGZHOU HUANGWEI MUNICIPAL ENG CO LTD

High-rise pile cap equipment under horizontal load and centrifuge test method for foundation bearing characteristics thereof

Disclosed in the present invention are high-rise pile cap equipment under a horizontal load and a centrifuge test method for foundation bearing characteristics thereof. The equipment comprises a model box, a sand layer, a model pile cap, at least eight model piles, a horizontal loading device, at least two laser displacement sensors, an axial force sensor, and a plurality of strain gauges. The method comprises: S1, performing one-way horizontal loading on high-rise pile cap equipment under a horizontal load to obtain an ultimate foundation bearing capacity situation, a model pile body axial force distribution situation, a pile foundation axial force comparison situation, a model pile body bending moment distribution situation, and a model pile body bending moment comparison situation of the equipment; and S2, performing one-way variable amplitude cyclic loading on the high-rise pile cap equipment under the horizontal load to obtain a foundation displacement situation, an effect of the number of cycles on foundation stiffness, an effect of a cyclic load amplitude on the foundation stiffness, and a foundation inclination situation. In this way, the foundation design of the high-rise pile cap can be optimized, and a basis and a reference for evaluating safety of foundation long-term service are provided.
Owner:TIANJIN RES INST FOR WATER TRANSPORT ENG M O T

Integrally modularized and prefabricated assembly type high-pile wharf structure and assembling method

The invention relates to an overall modular prefabricated assembly type high-pile wharf structure and an assembling method. The structure comprises an upper structure main module part, an upper structure secondary module part, a pile cap module part, a node connecting part, a pile foundation part and an ancillary facility part. The upper structure main module part and the upper structure secondary module part are arranged in a staggered mode in the longitudinal direction of a wharf, the pile cap module part is located on the lower portion of the upper structure main module part, the pile foundation part is located on the lower portions of the upper structure main module part and the pile cap module part, and the node connecting part is connected with all modules. And the subsidiary facility part is mounted on the upper structure main module part and the upper structure secondary module part. The upper structure is composed of multiple sets of standardized integrally prefabricated modules, the number of connecting joints of components and the field workload can be greatly reduced, the assembly rate of the high-pile wharf is increased, large-scale crane ship machine equipment is fully utilized, the labor cost is saved, the dependence of engineering construction on the construction window period is reduced, the construction risk is reduced, and the construction efficiency is improved. Construction is rapid, and economic cost is low.
Owner:SHANGHAI DONGHUA CONSTR MANAGEMENT

Lattice type foundation for wind power tower and construction method of lattice type foundation

The invention relates to the technical field of wind power, and discloses a lattice type foundation for a wind power tower and a construction method thereof.The foundation comprises a plurality of bearing platforms, and a cross beam is fixedly connected between every two adjacent bearing platforms; a lattice type wind power tower column can be erected on the upper side of the bearing platform; an embedded pipe is reserved in the center of any bearing platform and used for penetration of a prestressed steel strand, and the prestressed steel strand can be fixed to the top face of the tensioning cavity; a tensioning cavity is formed in the bottom surface of any bearing platform and can be used as a prestressed steel strand tensioning or anchoring operation space; any bearing platform is provided with a pre-stressed anchor bolt assembly, and the pre-stressed anchor bolt assembly is suitable for being fixed to a lattice type wind power tower column. The multiple bearing platforms are adopted for providing support for fixing of the lattice type wind power tower, compared with a fan foundation of a traditional cylinder type tower, the land acquisition area can be remarkably saved, the material cost is reduced, and the wind power tower foundation is suitable for various terrain environments.
Owner:ZHEJIANG HUADONG XINNENG TECH CO LTD

Composite pile foundation structure for road surface rigidity optimization of road transition section and design and use method of composite pile foundation structure

The invention provides a composite pile foundation structure for road surface rigidity optimization of a road transition section and a design and use method of the composite pile foundation structure, and relates to the technical field of composite pile foundations. The composite pile foundation structure can be applied to an embankment foundation and a bridge abutment pile foundation and comprises a bearing platform, a pile cap, a gasket, an elastic composite plate, replaceable filler, a pile and a pile end self-adaptive deformer. The design and use method of the bridge abutment pile foundation is guided by the load settlement characteristic of the butted roadbed, and the design and use method of the embankment composite pile foundation is guided by the settlement control standard. Design variables comprise the pile length, the pile diameter, the pile number, the compression thickness of the elastic composite plate, the arrangement depth of the replaceable filler, the limit pile side friction resistance of the replaceable filler and the compression modulus of the replaceable material, the structure can optimize the overall rigidity of the road surface on one side of the abutment, the phenomenon of bump of the abutment is effectively avoided, zero-differential settlement is achieved theoretically, and the construction efficiency is improved. And the settlement index can be controlled in the application of an embankment foundation.
Owner:SOUTHWEST JIAOTONG UNIV

Fabricated low pile cap structure and construction method thereof

The invention relates to an assembled low pile cap structure and a construction method thereof, and relates to the field of port wharf engineering. The structure comprises a pile foundation, an upper hollow structure, a top panel and a leveling cushion layer. The pile foundation is embedded into a soft soil foundation on the outer side of a wharf, the upper permeable structure is arranged above the pile foundation, and holes are reserved in the bottom according to the pile foundation; a leveling cushion layer is arranged between the pile foundation and the upper transparent structure; and the top panel is arranged above the pile foundation. The construction method comprises the steps that the upper permeable structure is of an integrated assembly type structure and is machined and manufactured in a prefabrication factory; a pile foundation is inserted, a leveling cushion layer is arranged, corresponding reserved holes of the upper permeable structure are connected with the pile foundation, and grouting anchoring is carried out; and a top panel is arranged above the upper permeable structure, and the low pile cap structure is assembled. The foundation piles serve as stress foundations, the upper portion is of an assembly type permeable structure, durability is good, environment friendliness is achieved, construction is easy and rapid, and the foundation pile can be widely applied to the inland river excavation type harbor basin wharf.
Owner:CCCC THIRD HARBOR CONSULTANTS

Hoop and bottom die integrated quick mounting system

The invention relates to the construction technology of a hoop bottom die, and discloses a hoop bottom die integrated quick-mounting system which comprises a bottom die plate arranged on the outer side of the end of a vertical pile, and the bottom die plate is used for side die erecting and pouring forming positioning of a vertical pile cap; the main beam and the secondary beam are fixed to the bottom of the bottom formwork, first transverse rib plates and second transverse rib plates are fixed to the main beam and the secondary beam respectively, and a fastening and locking buckle assembly is arranged between the first transverse rib plates with the ends in butt joint; the hoop body is arranged at the end of the vertical pile in a sleeving mode through a bolt, hoop pressure-bearing ribs used for bearing and supporting the bottom formwork and the main beam are arranged on the side of the hoop body, and a hoop guide chain which is integrally detached in a hoisting mode is further arranged between the outer side of the hoop body and the secondary beam. According to the hoop and bottom die integrated quick assembly system, bottom die integrated quick assembly and disassembly construction of double-pile and single-pile cap construction operation can be achieved, secondary bottom disassembly during disassembly is not needed, and the die erecting and pouring efficiency of pile cap construction is improved.
Owner:CCCC FIRST HARBOR ENGINEERING CO LTD +1

Self-balancing modular fully-prefabricated elevated station transition structure construction method and structure

The present invention relates to the technical field of prefabricated elevated stations. Disclosed are a self-balancing modular fully-prefabricated elevated station transition structure construction method and a structure. The construction method comprises the following steps: constructing precast pipe piles and a precast pile cap; executing concrete backfilling; installing a pier column and connecting same to the pile cap; installing a Y-pier cap for executing a connection; installing a precast middle cap beam and precast side cap beams; installing precast steel tubular columns; installing top overhanging precast reinforced concrete cap beams and a precast reinforced concrete middle cross beam; hoisting and installing precast platform slabs and precast arched platform headwalls; installing precast straddle monorail track beams; and installing a precast steel structure canopy. By using the dual columns to achieve an overhead layer and an upper structure, the present invention reduces the absolute overhanging length, improves the performance of the structure under stress, and reduces the sectional dimensions of components, thus saving the floor area of the pier column to the utmost extent, enhancing the applicability of station structures in a wider range of various urban environments, and improving the universality of the structure.
Owner:CRRC P & D INSTITUTE CO LTD

Floating suspension type jacket high-pile wharf structure suitable for ultra-large water depth and construction method of floating suspension type jacket high-pile wharf structure

The invention discloses a floating suspension type jacket high-pile wharf structure suitable for ultra-large water depth and a construction method, and belongs to the technical field of high-pile wharfs. The structure comprises a jacket, a pile foundation and an upper structure; the lower part of the upper structure is connected with a pile foundation; the jacket is installed on the lower end face of the upper structure and connected to the pile foundation. The upper structure comprises a sleeve box type pile cap, a cross beam, a longitudinal beam and a laminated panel; the sleeve box type pile cap is installed on the upper end face of the pile foundation. The longitudinal beam system is installed on the upper end face of the sleeve box type pile cap. The cross beams are mounted between the adjacent longitudinal beam systems; and the laminated panel is flatly laid on the surface layer of the upper structure. The structure adapts to a large-water-depth and large-flow-velocity environment by exerting the structural advantages of the structure, and the structure is small in underwater construction work amount, high in assembly degree, small in environmental influence, short in construction period and low in engineering investment.
Owner:CCCC THIRD HARBOR CONSULTANTS

Screw-in type environment-friendly steel pipe pile with tip blades and construction method

PendingCN119981021ABulkheads/pilesPile capPipe
The invention discloses a screw-in type environment-friendly steel pipe pile with tip blades and a construction method. The screw-in type environment-friendly steel pipe pile comprises a steel pipe pile body, a pile cap fixed to the steel pipe pile body and a spinning driving device driving the steel pipe pile body to rotate downwards, and the pile cap is installed at the pile back position of the steel pipe pile body and driven by the spinning driving device; a tip blade is mounted at the pile tip position of the steel pipe pile, covers the pile tip position of the steel pipe pile, and comprises two semi-doughnut-shaped steel plates; the two semi-doughnut-shaped steel plates are arranged on the periphery of the steel pipe pile in a V shape; the steel plates with the semi-doughnut-shaped tip blades are arranged on the periphery of the steel pipe pile and welded in a V-shaped intersection mode, so that a wider stress surface can be formed when the pile tip enters a soil layer, the pressure of a soil body is dispersed, the soil body is effectively broken through through the gradual rotary cutting effect, the penetrating power of the pile is improved, and the construction efficiency is improved. And the situation that the construction speed is reduced or the pile body deflects due to the fact that large resistance occurs when the pile tip of the steel pipe pile makes contact with a hard soil layer is avoided.
Owner:AIKE (SHANGHAI) ENVIRONMENTAL TECH ENG CO LTD +1

Fabricated tower crane foundation suitable for various types of tower cranes

The utility model discloses an assembly type tower crane foundation suitable for various types of tower cranes, which comprises distribution beams, four steel pipe piles are vertically arranged in a rectangular shape, two groups of distribution beams are fixed together in a crossed manner, and two ends of each group of distribution beams are mounted in two diagonal steel pipe piles through connecting pieces. The side faces of the distribution beams on the two adjacent sides are fixed through a flat connecting beam. The base plates are installed on the distribution beams through finish rolling threaded bolts, and the welding supporting feet are fixed among the four base plates. A conventional cross-shaped distributive girder foundation is adopted, the flat connecting beams are added on the distributive girder foundation, so that the overall strength is improved, meanwhile, the pile caps are arranged at the joints of the distributive girders and the steel pipe piles, and therefore the vertical height of the distributive girders can be finely adjusted through welding of the pile caps. And meanwhile, the base can be welded after being positioned and fixed through the finish-rolled threaded bolts, so that the levelness of the welding supporting legs and the distribution beam can be conveniently adjusted. The utility model also has the advantages of easy splicing, high rigidity, and good overall stability and overturning resistance.
Owner:THE 5TH ENG MBEC +2

Critical height calculation method for pile cap beam supporting type embankment

The embodiment of the invention provides a critical height calculation method for a pile cap beam supporting type embankment. The vertical stress of the pile cap beam supporting type embankment at the given depth is calculated by utilizing a vertical stress calculation formula by obtaining soil filling parameters, pile distribution design parameters and roadbed top surface design load of the pile cap beam supporting type embankment. The method comprises the following steps: obtaining soil filling parameters, pile distribution design parameters, roadbed top surface design load and actual soil filling height of a pile cap beam supporting type embankment, calculating by utilizing a critical height calculation formula to obtain a theoretical critical height of an equal sinking surface, and correcting the theoretical critical height of the equal sinking surface in combination with the actual soil filling height of the pile cap beam supporting type embankment. And obtaining the actual critical height of the equal sinking surface. According to the method, the equivalent sinking face boundary height is related to the filling parameters and pile arrangement design parameters of the embankment and is also positively related to the actual filling height of the embankment and the design load of the top face of the roadbed, so that the calculation of the equivalent sinking face boundary height is more accurate.
Owner:广东省路桥建设发展有限公司 +1

Device and method for measuring pile body stress of rotary excavating implanted pile

The invention discloses a device and a method for measuring the pile body stress of a rotary excavating implanted pile. The device comprises a composite pile inner core, a composite pile outer core, an inner core monitoring unit, an outer core monitoring unit and a bearing platform, the inner core monitoring unit is a first optical fiber string which is formed by connecting a plurality of first high-precision strain sensors in series in a segmented encryption manner, and the first optical fiber string is arranged in a channel formed in the inner core pile body of the composite pile; the outer core detection unit is a second optical fiber string formed by connecting a plurality of second high-precision strain sensors in series in a segmented encryption manner and is mounted in the composite pile outer core, and after mounting is completed, the first optical fiber string and the second optical fiber string are in one-to-one correspondence; the inner core monitoring unit and the outer core monitoring unit are both connected with the fiber bragg grating acquisition instrument and transmit acquired sensor data to a control center for pile body stress measurement; the bearing platform is simultaneously connected with the top of the inner core and the top of the outer core to eliminate stress lag of the outer core of the composite pile; a hole is formed in the center of the bearing platform and used for allowing a pile end settlement testing pipe to penetrate through and providing a pile end monitoring channel.
Owner:QINGDAO UNIV OF TECH

Inclined column formwork supporting frame for cast-in-place of concrete beam

The utility model discloses an inclined column template support frame for cast-in-place of a concrete beam, which is characterized in that a vertical steel pipe upright post and an inclined steel pipe upright post are fixedly arranged on a bearing platform by utilizing bearing platform anchor bolts, and the vertical steel pipe upright post and the inclined steel pipe upright post are pulled into a whole by a horizontal pull rod along the direction of a bridge; the inclined steel pipe stand columns at the corresponding positions in the single span are connected into a whole through corner connectors and horizontal cross rods. The unloading blocks are arranged on the top faces of the vertical steel pipe stand columns and the top faces of the corner connectors respectively. A bearing beam is placed on the top face of the unloading block in the transverse bridge direction, a bailey beam is arranged on the top face of the bearing beam in the bridge direction, a distribution beam is placed on the top face of the bailey beam in the transverse bridge direction, and the batter post formwork supporting frame for concrete beam cast-in-place is formed. The bearing platform is fully used as a supporting point, the inclined steel pipe stand columns are arranged to share the upper load, a strip-shaped foundation does not need to be additionally arranged, construction cost is saved, the spanning capacity of the support is greatly improved, and the support is a preferable scheme for spanning rivers, roads and bridge sites in a large-span mode when the geological environment is poor.
Owner:CHINA RAILWAY 24TH BUREAU GRP ANHUI ENG CO LTD +1

Concrete-filled steel tube truss type hybrid wind power tower

The invention relates to the technical field of wind power towers, and discloses a concrete-filled steel tube truss type hybrid wind power tower which comprises a tower drum, a plurality of steel tube beams and a plurality of steel tube beams. The truss unit is suitable for supporting the tower drum; the transition unit is arranged between the tower drum and the truss unit so as to connect the tower drum with the truss unit; the bearing platform unit is arranged at the end, away from the tower drum, of the truss unit and suitable for bearing the truss unit; the truss unit comprises at least one pipe body, and concrete is poured in the pipe body. And the constraint stranded wires are tensioned in the axial direction of the pipe body and anchored to the transition unit and the bearing platform unit correspondingly, and the constraint stranded wires are at least arranged outside the pipe body. According to the concrete-filled steel tube truss type hybrid wind power tower, the constraint stranded wires are arranged outside the tube body, the situation that the cable penetrating process is complex and cannot be observed is avoided, the situation that the constraint stranded wires are mutually wound in the cable penetrating process is avoided, constructors can conveniently and directly observe the tensioning state outside, and it is ensured that prestress is accurately applied.
Owner:ZHEJIANG HUADONG XINNENG TECH CO LTD

Construction method of trestle support pile platform with high bare rock inclination

The invention relates to a construction method of a trestle support pile platform with large bare rock inclination, and belongs to the technical field of trestle construction, four anchors are prefabricated on a slab barge, a floating crane is utilized to throw a designated position on the sea after prefabrication is completed, then a guide frame is machined in a steel structure workshop, and the guide frame is lighted to the designated position through the slab to be positioned; in the flat tide period, a flat plate barge carrying a guide frame is positioned at a designed position through an anchor rope reserved by an anchorage, then the guide frame is temporarily restrained, a winch is installed in advance through the flat plate barge, guide frame positioning pull cables are arranged on the periphery of the guide frame to be fixed through traction of the winch, and an anchor pile is constructed; the guide frame is placed at the designed position through the lifting system, finally, redundant steel pipe piles are cut, steel pipe pile caps are constructed, distribution beams and a bridge deck structure are installed, and the problem that in the prior art, a traditional trestle supporting pile construction method limits application of trestle construction in areas with torrent high waves and large bare rock inclination is solved.
Owner:CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP CO LTD

Traction device for endoscopic electro-static discharge (ESD) operation

The invention discloses a traction device for endoscopic ESD (Electro-Static Discharge) surgery, which comprises a shell, a supporting mechanism and a control box are arranged on the shell, the supporting mechanism is used for lifting the control box, a concave wheel is arranged on the control box, and the concave wheel is used for winding a traction wire; the supporting mechanism comprises a cover plate and a supporting plate, the supporting mechanism adjusts the position of the control box by controlling the relative position and the relative angle of the cover plate and the supporting plate, the control box pulls the pull wire through a concave wheel, an adjusting assembly and a clamping assembly are arranged in the control box, and the adjusting assembly winds and unwinds the pull wire by adjusting rotation of the concave wheel. The clamping assembly is used for locking the concave wheel after rotation adjustment, a fixing pile is arranged at the top end of one side of the concave wheel and comprises a pile cap and a pile body, and the pile cap and the pile body are used for clamping the pull wire. The external traction device is adopted to replace a human hand to hold the traction line, and the traction degree, force and direction can be conveniently controlled, so that flexible adjustment can be performed according to operation requirements in an operation, and the traction operation in the operation is more convenient.
Owner:HAINAN SHULAN BOAO HOSPITAL CO LTD

Composite pile foundation structure for road surface rigidity optimization of road transition section and design and use method of composite pile foundation structure

The invention provides a composite pile foundation structure for road surface rigidity optimization of a road transition section and a design and use method of the composite pile foundation structure, and relates to the technical field of composite pile foundations. The composite pile foundation structure can be applied to an embankment foundation and a bridge abutment pile foundation and comprises a bearing platform, a pile cap, a gasket, an elastic composite plate, replaceable filler, a pile and a pile end self-adaptive deformer. The design and use method of the bridge abutment pile foundation is guided by the load settlement characteristic of the butted roadbed, and the design and use method of the embankment composite pile foundation is guided by the settlement control standard. Design variables comprise the pile length, the pile diameter, the pile number, the compression thickness of the elastic composite plate, the arrangement depth of the replaceable filler, the limit pile side friction resistance of the replaceable filler and the compression modulus of the replaceable material, the structure can optimize the overall rigidity of the road surface on one side of the abutment, the phenomenon of bump of the abutment is effectively avoided, zero-differential settlement is achieved theoretically, and the construction efficiency is improved. And the settlement index can be controlled in the application of an embankment foundation.
Owner:SOUTHWEST JIAOTONG UNIV

Construction method for improved lock catch steel pipe pile cofferdam formed by covering stratum with lean sand large-particle-size pebbles

The invention discloses a construction method of an improved lock catch steel pipe pile cofferdam with a poor sand large-particle-size pebble covering stratum. The construction method comprises the following steps that an upper structure of a drilling platform is dismantled; measuring and setting out a pile position of the lock catch steel pipe pile cofferdam, sinking and positioning the steel pipe pile cofferdam by adopting a crawler crane and a vibratory hammer, and preliminarily entering a pebble bed; driving a pipe pile to a set elevation by utilizing a hydraulic impact hammer; for a steel pipe pile which is difficult in drilling footage or provided with boulders at the bottom, an XR280 rotary drilling guide hole is adopted; the steel pipe piles are smoothly closed; cofferdam water pumping; a small excavator is adopted for internal excavation, slag is discharged in a long arm excavation up-and-down transfer mode, a local rock stratum is firstly crushed and then excavated through a crushing hammer, water is pumped to the position 70 cm below an inner support of the road, and after the inner support is installed, water pumping continues to be conducted; and bottom sealing, pile head breaking and pile cap construction are carried out. By means of the construction method, the problems that the double-wall steel cofferdam is difficult to put down and level, and the site requirement is high can be effectively solved; the defects that a long steel sheet pile cofferdam is low in rigidity, prone to deformation and poor in water stopping effect are overcome. Through the cofferdam construction technology of the hydraulic impact hammer and the guide hole in the pipe of the rotary drilling rig, the hydraulic impact hammer is used for driving the steel pipe pile, the guide hole in the pipe of the rotary drilling rig and the pile-forming construction of a single pipe pile only need 10 minutes, and the construction period is greatly shortened.
Owner:HUBEI ROAD & BRIDGE GRP BRIDGE & TUNNEL ENG CO LTD +1

Wind turbine foundation and construction method thereof

PCT designated stage expiredWO2025155995A1Artificial islandsTowersReinforced concretePile cap
The present invention relates to a cross-shaped hybrid wind turbine foundation and a construction method thereof. The cross-shaped hybrid wind turbine foundation comprises a pile cap (1) is cast of reinforced concrete in the shape of a inverted drum, consisting of an outer cylinder (9), an inner cylinder (10), and radial walls (11) arranged radially on the outer surface of the inner cylinder (10) to connect the inner cylinder (10) with the outer cylinder (9), forming a integrated rigid slab. A slab (12) covers the top surface of the pile cap (1), creating enclosed chambers between the slab (12), the outer cylinder (9), the inner cylinder (10), and the radial walls (11), allowing for vacuum suction when placing the pile cap (1) on the seabed ground; a adapter tower (2) is connected to the top surface of the pile cap (1); an upper pile segment (3) is connected to the bottom surface of the pile cap (1), and a lower pile segment (4) is inserted inside the upper pile segment (3); a upper anchored wire ropes (6) connects the pile cap (1) to the upper end of the adapter tower (2), and a lower anchored wire ropes (5) connects the pile cap (1) to the upper pile segment (3).
Owner:NGUYEN VIET HUNG +1

A fully prefabricated and assembled bridge and its construction method

The present invention provides a fully prefabricated and assembled bridge, characterized in that: from top to bottom, the bridge successively includes main girders, cap beams, bridge piers, pile caps, and pile foundations, all of which are constructed by means of factory prefabrication and on-site assembly. Among them, the main girders and the cap beams are connected by bearings, and the cap beams and the bridge piers are connected by a connecting device composed of cap beam embedded steel plates, cap beam cast steel parts, pier top column surface sliding plates, pier top cast steel parts, pier top embedded steel plates, pier top steel bars, and pier top nuts. The bridge piers and the pile caps are connected by a connecting device composed of pile cap embedded parts, pier bottom embedded parts, pier bottom steel bars, and pier bottom nuts. The pile caps and the pile foundations are connected by bearings. The present invention has clear force transmission and convenient construction, realizes the full prefabrication, assembly, construction, and demolition of the bridge structure, and can be widely applied to the rapid construction and demolition projects of bridges.
Owner:BEIJING NAT ROADWAY HIGHWAY DESIGN INST

Trestle-free rapid assembling and disassembling construction method for offshore high-rise pile cap steel hanging box

The invention discloses a trestle-free rapid assembling and disassembling construction method for an offshore high-rise pile cap steel hanging box. The trestle-free rapid assembling and disassembling construction method comprises the following steps that S1, the steel hanging box is machined in a factory and pre-assembled; s2, transporting the steel hanging box to an assembling platform at a bridge site, and performing total assembling on the steel hanging box and the prefabricated bottom plate through connecting bolts; s3, hoisting the steel hoisting box to the pier position through a crane ship, and mounting the steel hoisting box at the pier position; s4, after the lower portion of the steel hanging box is in place, a blocking steel plate and a shear bracket are welded, and the shear bracket is located between the blocking steel plate and the steel pipe pile; s5, bottom sealing concrete is poured; s6, a bearing platform is poured; and S7, the hanging box is dismantled. A factory-like and modular process is adopted for the steel hanging box, after the river steel-concrete combined cofferdam is modularly machined in a factory, the steel-concrete combined cofferdam is generally spliced on an offshore splicing platform, then the steel-concrete combined cofferdam is hoisted in place at a time through a large crane ship, the construction efficiency is greatly improved, meanwhile, a temporary trestle is omitted, the overall hoisting technology of the crane ship is utilized, and the construction cost is reduced. The occupation on channels and the dependence on large equipment are reduced, and the construction cost is reduced.
Owner:CRCC HARBOR & CHANNEL ENG BUREAU GRP

Wharf structure reinforced by basalt fiberboards

The invention relates to the technical field of wharf structures, and discloses a wharf structure reinforced by basalt fiberboards, which comprises a pile foundation, a pile cap mounted at the top of the pile foundation, a prefabricated cross beam mounted at the top of the pile cap and a panel mounted at the top of the cross beam, an insertion groove for insertion of the insertion plate is prefabricated in the top of the pile cap, a first prefabricated hole is prefabricated in the insertion plate, second prefabricated holes are prefabricated in the two sides of the insertion groove, a split bolt is arranged in the first prefabricated hole, and the two ends of the split bolt are located in the two second prefabricated holes correspondingly and are in threaded connection with limiting nuts correspondingly; basalt fiber boards are prefabricated at the bottoms of the cross beams and abut against the pile caps. The stability of the wharf structure can be improved.
Owner:CCCC SHANGHAI HARBOR ENG DESIGN & RES INST

Assembly-type pile-top connecting structure and construction method

PCT designated stage expiredWO2025112393A1Artificial islandsUnderwater structuresRubber ringPile cap
Provided in the present invention are an assembly-type pile-top connecting structure and a construction method. The assembly-type pile-top connecting structure comprises pile foundations, wherein a plurality of shear keys are welded to the outer side of the top of each pile foundation, pile-top connecting devices are provided on the pile foundations, the pile-top connecting devices on the plurality of adjacent pile foundations are fixedly connected, and precast beams for assembly are placed on the pile-top connecting devices; a steel sleeve is fixedly arranged at the bottom of a steel plate in each pile-top connecting device, a wedge-shaped support is fixedly arranged in the steel sleeve, the steel sleeve is located on the outer side of the top of a pile foundation, and the wedge-shaped support is supported on the inner side of the top of the pile foundation; and a water-stop rubber ring is provided between the inner side of the bottom of the steel sleeve and the pile foundation, and a grouting material fills the space between the steel sleeve and the pile foundation. Conventional pile caps are eliminated, and the pile foundations are directly connected to transverse and longitudinal precast beams and joints by means of the pile-top connecting devices, such that the green and industrialized construction of marine engineering structures is realized.
Owner:CCCC SECOND HARBOR ENGINEERING CO LTD

Full-prefabricated assembly type double-column high pier device and construction method thereof

The invention discloses a full-prefabricated assembly type double-column high pier device and a construction method thereof.The device comprises a cover beam (13), a bearing platform (6), a pier column upper section (11), a pier column lower section (1) and a pier column middle section (10) with a tie beam, and socket holes (14) are formed in the bottom face of the cover beam (13) and the top face of the bearing platform (6); pier column socket sections (9) embedded in socket holes (14) are arranged on the upper portion of the upper pier column section (11) and the lower portion of the lower pier column section (1) respectively, gaps (3) between the pier column socket sections (9) and the socket holes (14) are filled with high-strength shrinkage-free cement grouting materials (4), and corrugated steel pipes (5) are adopted by the inner walls of the socket holes (14) of the cover beam (13) and the bearing platform (6) to serve as permanent templates. The component is low in transporting and hoisting difficulty, the mechanical property of a connecting joint is reliable, the construction precision requirement is low, and good economic benefits are achieved.
Owner:TONGJI UNIV +1