Disclosed in the present invention is a harbor basin dredging construction method. The method comprises: construction preparation, wherein an antifouling curtain is arranged on the periphery of a construction
water area, and a
total station is used to survey the construction area; harbor basin dredging, wherein a grab dredger is used for layered excavation, and a hopper
barge is used to convey mud to a mud unloading site for discharging; foundation trench and ocean-side inter-
pile soil excavation, wherein a
pipe head of a suction dredger extends to the ocean-side part of an inter-
pile area, and pumps mud and sand to form an ocean-side dredging section; inter-
pile soil excavation, wherein a long reach
excavator barge is used for inter-pile soil excavation and dredging;
shore-side inter-pile soil excavation, wherein a long reach
excavator is used for excavation to form a
shore-side dredging section; and harbor basin spot dredging, wherein an all-
terrain survey is carried out to determine shallow spots and a spot dredging
route, and spot dredging is carried out in the harbor basin according to the shallow spots and the spot dredging
route so as to ensure dredging depth. The construction method provided in the present invention solves the problem of loss or reduction of dredging results that can be caused by the continuous movement and
sedimentation of
silt in excavation trenches as well as consequent
siltation, thus ensuring dredging effectiveness and saving dredging construction time.