Patents
Literature
Patsnap Eureka AI that helps you search prior art, draft patents, and assess FTO risks, powered by patent and scientific literature data.

353results about How to "Construction safety" patented technology

Method for calculating bending resistance of reinforcing steel bar lap joint of underground diaphragm wall based on big data

The invention discloses an underground diaphragm wall steel bar lap joint bending resistance calculation method based on big data, and belongs to the technical field of underground engineering design. In order to solve the problems that the condition change of a construction site is difficult to respond in real time, the construction parameters are difficult to dynamically adjust and the complex construction environment is difficult to adapt, the data set quality and the bending resistance prediction precision are effectively improved through multi-source data acquisition and key feature screening, and a physical prediction model of a steel bar lap joint is established. According to the method, factors such as stress transmission and binding power are comprehensively considered, so that the model has good adaptability under different working conditions, model parameters are dynamically adjusted, the model responds to changes of environments and construction errors in real time, the weight is automatically adjusted when monitoring data fluctuates, accurate prediction of the bending resistance is achieved, potential failure risks are effectively prevented, and the construction quality is improved. And a failure mode pre-judgment and multi-level risk management mechanism helps a construction team to quickly identify a high-risk area and flexibly adjust a construction scheme.
Owner:SHENGZHOU WANGXIN JINSHUI CONSTR INVESTMENT CO LTD

Double-row steel sheet pile soil core combined cofferdam structure and construction method

The invention discloses a double-row steel sheet pile and soil core combined cofferdam structure and a construction method. The double-row steel sheet pile and soil core combined cofferdam structure comprises double-row pile connecting units, steel sheet piles, brackets, steel enclosing purlins, dredger fill and drainage plates. Each double-row pile connecting unit is formed by welding an upper connecting plate between two connecting steel sheet piles; the double-row pile connecting units are inserted into a soil body, and a steel sheet pile is inserted between every two double-row pile connecting units; corbels are welded to the outer sides of the steel sheet piles, steel enclosing purlins are arranged on the corbels, and the steel enclosing purlins, the steel sheet piles and the corbels are connected in a welded mode; dredger fill is filled between the two rows of steel sheet piles and is compacted by a hammer-attached soil squeezer; a drainage plate is inserted into the dredger fill; earth excavation is conducted on the side, close to water, of the double-row pile cofferdam to form a foundation pit; when shallow excavation is conducted on the foundation pit, no sand filling pipe bag is arranged; when the foundation pit is deeply excavated, a slope section is reserved; sand filling pipe bags are arranged on the outer side of the slope section and stacked on the outer side of the slope section in a staggered mode. The hammer-attached soil squeezing device comprises an attached hammer, a pressing plate, water permeable holes, geotechnical cloth and a brush.
Owner:ZHEJIANG UNIV CITY COLLEGE

Lattice column positioning device suitable for subway deep foundation pit in soft soil area

The invention provides a latticed column positioning device suitable for a subway deep foundation pit in a soft soil area, and belongs to the technical field of building construction. Comprising a latticed column body, a steel casing arranged outside the latticed column body, a positioning adjusting platform arranged at the upper end of a subway foundation pit, a guiding positioning assembly arranged at the bottom end of the positioning adjusting platform and a supporting positioning assembly arranged between the steel casing and the latticed column body. The reference line of the position of the axis positioning barrel can be adjusted according to the positioning adjusting platform, then the axis positioning barrel is used for positioning the latticed column body, the perpendicularity of the latticed column body is guaranteed, the more accurate positioning effect is achieved, the interior of the latticed column body is positioned and supported through the axis positioning barrel and the Y-shaped positioning rod, and the positioning accuracy is improved. The position of the latticed column body is indirectly adjusted through the axis positioning barrel, it is guaranteed that the latticed column body, the axis positioning barrel and the subway foundation pit are kept coaxial, then the perpendicularity and axis positioning of the latticed column body are achieved, the perpendicularity deviation of the latticed column body is reduced, and construction safety is guaranteed.
Owner:NINGBO METRO GRP +2

Automatic analysis method and system for tunnel advanced geological forecast by elastic wave method

The invention belongs to the field of geological engineering construction, discloses an automatic analysis method and system for tunnel advanced geological forecast by an elastic wave method, and solves the problems of few training samples, poor universality of intelligent model engineering and low automation level in the research of applying artificial intelligence to tunnel advanced geological forecast analysis in the prior art. The method comprises the following steps: identifying an elastic wave method parameter image to obtain elastic wave method parameter data, and establishing an elastic wave method parameter database; a mapping relation of elastic wave method key geophysical prospecting parameters-geological indexes-geological quality is established by combining a rock mass mechanics theory, a geological disaster formation mechanism and the like so as to establish a classifier classification principle; and finally, adopting a machine learning method to construct a classifier model according to a classifier classification principle, and obtaining training and testing samples based on an elastic wave method parameter database to train and verify the model. By utilizing the model, real-time whole-process automatic analysis can be realized, so that the analysis accuracy and efficiency are improved.
Owner:CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE

Impact hydraulic control valve group of rock drill and rock drill

The utility model provides a rock drill impact hydraulic control valve group and a rock drill, the valve group comprises a hydraulic control reversing valve, a first throttling hole, an electric proportional overflow valve, an overflow valve, a second throttling hole, a valve body and an electromagnetic reversing valve, the valve body is provided with a pressure oil port P, an oil return port T, an oil drainage port L, an LS oil port and a working oil port A; the pressure oil port P is communicated with an oil inlet of the overflow valve and an oil inlet of the second throttling hole through a hole channel in the valve body. An oil outlet of the second throttling hole is communicated with an oil inlet of the electromagnetic reversing valve; a working oil port of the electromagnetic reversing valve is communicated with a control oil port of the hydraulic control reversing valve; the oil return port T is communicated with an oil outlet of the overflow valve; and the oil drainage port L is communicated with an oil drainage port of the electromagnetic reversing valve, and is communicated with an oil drainage port of the hydraulic control reversing valve, an oil outlet of the electric proportional overflow valve and a control oil port at the same time. Damage of pressure building to a system and elements is eliminated, and residual impact pressure existing after oil cut-off is eliminated.
Owner:CHINA RAILWAY CONSTR HEAVY IND

Polyurethane material for leaking stoppage of coal mine spraying as well as preparation method and application of polyurethane material

The invention relates to a polyurethane material for coal mine spraying air leakage stoppage and a preparation method and application thereof, and relates to the technical field of polyurethane materials.The polyurethane material for coal mine spraying air leakage stoppage comprises a component A and a component B, and the volume ratio of the component A to the component B is 1: (0.85-1.15); the component A comprises the following components: polyester polyol, a first flame retardant, a catalyst and a functional aid; and the component B comprises the following components: polymerized MDI and a second flame retardant. The polyurethane material for leaking stoppage of coal mine spraying provided by the invention at least has the following characteristics: the foaming speed is high, and the reaction time can be regulated and controlled; the spraying layer is good in sealing performance and can block leaked air and harmful gas; the adhesive force to coal rock walls and various wall surfaces is strong; and the fabric is flame-retardant and antistatic. The spraying agent can be used for spraying wall surfaces such as various fractured sealing walls, air leakage wind-shield walls and gas leakage sealing walls, and coal oxidation spontaneous combustion and harmful gas leakage are prevented.
Owner:SHANDONG HEQING ENVIRONMENTAL PROTECTION TECH CO LTD

Construction method for double-track tunnel to pass through basalt with tuff in water-rich section

PendingCN119122566AImprove self-stabilityReduce self-stabilization abilityUnderground chambersTunnel liningSupporting systemSteel frame
The invention relates to the technical field of tunnel construction, in particular to a construction method for a double-track tunnel to pass through basalt with tuff in a water-rich section. Comprising the following steps: S1, tuff identification; s2, advanced geological forecast; s3, closing the tunnel face; s4, a forepoling system is established; S5, a tunnel body is excavated, wherein a three-step method is adopted as an excavation construction method; s6, reinforcing a steel frame lock leg support; s7, support parameters are determined; s8, arranging drainage holes; and S9, monitoring and measuring. A plurality of supporting systems are formed, the supporting effect is good, combination with the soil body is stable, the water plugging consolidation effect is obvious, and construction is safe and reliable; the supporting method and the grouting means are organically combined, the procedure connection continuity is good, safety is high, the application range is wide, the construction speed is high, and safety performance is high. The construction method is mainly applied to the construction aspect of the double-track tunnel crossing the basalt and tuff in the water-rich section.
Owner:CHINA RAILWAY 12TH BUREAU GRP CO LTD +1

Intelligent construction methods, systems and complete sets of intelligent construction equipment based on BIM models

ActiveCN113935084BIntelligent constructionRealize cycle adjustmentGeometric CADData processing applicationsInformatizationPDCA
The present invention discloses an intelligent construction method, system and complete set of intelligent construction equipment based on BIM model, the method includes constructing a tunnel BIM information model based on a preset construction plan; automatically issuing construction tasks to intelligent construction units based on the tunnel BIM information model, and the intelligent construction units automatically or guide to complete the construction tasks; automatically monitoring the construction quality data and construction process data of the intelligent construction units, and feeding back to the tunnel BIM information model, optimizing the tunnel BIM information model, and forming a PDCA closed loop. The present invention establishes a tunnel BIM information model, carrying construction geological information, design scheme, construction scheme, construction plan and construction process data, etc., drives the intelligent construction of the tunnel based on the BIM information model, realizes the closed-loop management of planning, issuing, executing and monitoring of construction tasks, and uses advanced geological forecasts and real-time feedback construction reports to timely revise the construction plan.
Owner:JIANGSU XCMG CONSTRUCTION MACHINERY RESEARCH INSTITUTE LTD

Line stringing and tightening mechanism for electric power infrastructure project and use method of line stringing and tightening mechanism

The invention discloses a line stringing and tightening mechanism for electric power infrastructure engineering and a using method, and particularly relates to the technical field of electric power infrastructure engineering, the mechanism comprises a small tractor, a take-up stand and a cable reel, the small tractor comprises a winding roller and a traction driver, the take-up stand comprises a side frame and a bottom frame, the cable reel comprises a winding reel, and the winding reel is connected with the winding roller. A power-assisted driving shaft is rotationally arranged on the bottom frame, a resistance driving piece is fixedly installed at the position, corresponding to the end baffle disc, of the end of the power-assisted driving shaft, and the resistance driving piece is attached to the end baffle disc. The power-assisted driving shaft is driven by the auxiliary driving machine to rotate so as to drive the end baffle disc to rotate, auxiliary driving of the cable reel is formed, the cable reel can automatically rotate to wind a cable, manual control is not needed, the rotating torque needed by the resistance driving part is small, needed power is small, field operation is facilitated, and the cable reel is convenient to use. And direct contact operation of personnel is not needed in the process, and construction is safer.
Owner:SOUTHERN XINJIANG ELECTRICITY SUPPLY COMPANY OF STATE GRID XINJIANG ELECTRIC POWER

Advanced grouting repair method for large-deformation soft rock roadway

The invention relates to the technical field of soft rock roadway repair, and discloses an advanced grouting repair method for a large-deformation soft rock roadway, which comprises the following steps: S1, introducing an evaluation parameter P, and classifying roadways in a to-be-repaired area according to an evaluation model; s2, according to the type of the roadway, the drilling angle of a grouting hole and the number of times of grouting are determined; s3, punching, pre-grouting and hole sealing are conducted on the to-be-repaired area according to the step S2; and S4, the inner wall of the roadway is cleaned, and the shrinkage ratio of roadway deformation is repaired to 1. According to the dynamic advanced pre-grouting repair method for the large-deformation soft rock roadway, through roadway deformation evaluation, pre-grouting filling and cementation reinforcement of loose surrounding rock, a high-strength reinforced arch is formed, then cleaning repair is conducted, active / passive reinforcement supporting is matched, and finally the purpose of rapid, safe and efficient repair of the large-deformation soft rock roadway is achieved.
Owner:宁夏红墩子煤业有限公司

Construction method for hoisting photovoltaic glass kiln steel structure beam based on BIM model

PendingCN118992822AAvoid Construction Safety Risksreduce human errorSafety gearMechanical engineeringIndustrial engineering
The invention discloses a construction method for hoisting a photovoltaic glass kiln steel structure beam based on a BIM model, and relates to the technical field of hoisting supporting. The construction method for hoisting the photovoltaic glass kiln steel structure beam based on the BIM model comprises the following specific operation steps: step 1, model establishment: establishing a steel structure beam and glass kiln construction model by using BIM software; 2, simulating a hoisting path, a hoisting point and a mounting position of the beam, and determining a placement position of hoisting equipment; according to the construction method for hoisting the photovoltaic glass kiln steel structure beam based on the BIM model, a steel structure beam and glass kiln construction model is established, collision detection is conducted, the collision problem possibly occurring in the hoisting process is found in time, the construction safety risk is avoided, the hoisting process is monitored in real time through the BIM model, the positions of hoisting equipment and the steel structure beam are adjusted in time, and the construction efficiency is improved. And the hoisting is implemented according to the guidance of the BIM model, so that the reduction of human errors is facilitated, and the construction quality is improved.
Owner:CHINA MCC17 GRP CO LTD

Novel reinforced concrete prefabricated pipe gallery construction method

The invention discloses a novel reinforced concrete prefabricated pipe gallery construction method, relates to the technical field of industrial and civil structure reinforced concrete prefabricated pipe galleries, and solves the technical problems of short construction period and low cost. The method comprises the steps that firstly, concrete beams and columns of the reinforced concrete pipe gallery are split according to a construction drawing and then prefabricated in a prefabrication yard; 2, after construction of the cup foundation is completed, the corresponding prefabricated columns and prefabricated beams are transported to the side of the foundation, the prefabricated columns are hoisted and fixed in the cup foundation, temporary inclined struts are installed, then the prefabricated beams are installed and fixed layer by layer through an elevator or a crank arm vehicle, and formwork clamps are installed at the beam column connecting joints; thirdly, after completion, high-strength-grade non-shrinkage concrete is poured, and therefore the transverse frame without weakening of the integrity is formed; the construction method is simple and easy to operate, and the requirement for the construction technology is not high.
Owner:EAST CHINA ENGINEERING SCIENCE AND TECHNOLOGY CO LTD

Offshore wind turbine tower connecting structure, wind generating set and construction method

The invention relates to the technical field of wind power generation, and discloses an offshore wind turbine tower connecting structure, a wind generating set and a construction method. An offshore wind turbine tower connecting structure is used for connecting a concrete tower and a pipe pile structure and comprises a connecting mechanism, a plurality of prestressed cables and a plurality of anchor bolts. The connecting mechanism is used for connecting the concrete tower and the tubular pile structure, one end of the connecting mechanism is connected with the concrete tower, and the other end is connected with the tubular pile structure; one ends of the prestressed cables are connected with the top end of the concrete tower, the other ends of the prestressed cables are anchored to the connecting mechanism, and the prestressed cables are arranged in the circumferential direction of the concrete tower at intervals. One end of each anchor bolt is pre-buried in the concrete tower, the other end of each anchor bolt is anchored to the connecting mechanism, and a plurality of anchor bolts are arranged between adjacent prestressed cables. The structural strength of the concrete tower and the connecting strength of the concrete tower and the connecting mechanism can be improved through the prestressed cables, the connecting strength of the concrete tower can be improved through the anchor bolts when the prestressed cables are constructed, and the construction difficulty is lowered.
Owner:ZHEJIANG HUADONG XINNENG TECH CO LTD

Reinforced concrete stair lifting point arrangement and construction method under limited space condition

PendingCN118916961Asure reasonableGuarantee construction quality requirementsGeometric CADDesign optimisation/simulationReinforced concreteData set
The invention discloses a reinforced concrete stair lifting point arrangement and construction method under a limited space condition, which comprises the following steps of: interpolating samples in a national building standard design atlas through a thin-plate spline interpolation method to obtain more stair specification data sets for SVR (Support Vector Regression) model training; and after training optimization, a reinforced concrete stair lifting point arrangement model is obtained. And inputting specification parameters of the staircase, and then operating the reinforced concrete staircase lifting point arrangement model to output the number of lifting points and the positions of the lifting points. When the method is applied to subway station deep shaft construction, the subway station shaft PC stair hoisting difficulty can be effectively reduced.
Owner:CHONGQING UNIV +1

Double-hydraulic-drive drilling multifunctional tool capable of achieving continuous leaking stoppage and method

The tool comprises an outer pipe, a throttling sleeve, a touch rod, a driving sleeve and a drill bit, a plurality of cutter blocks are arranged in the side wall of the lower portion of the outer pipe, the throttling sleeve is arranged in the outer pipe and can move up and down, the touch rod is connected to the bottom of the throttling sleeve, and the driving sleeve is arranged in the outer pipe. A plurality of pushing blocks are arranged on the outer wall of the driving sleeve in the circumferential direction at intervals. The throttling sleeve can move downwards by a preset distance when the displacement of liquid injected into the throttling sleeve reaches a preset value, and drives the touch rod to move downwards to be inserted into the driving sleeve to generate throttling, so that the liquid pushes the driving sleeve to move downwards to a preset position, the push block pushes the corresponding cutter block outwards, and the cutter block is opened outwards. According to the tool and the method, an existing polished drill rod can be replaced for cement injection for leaking stoppage, a roller bit can also be replaced for cement plug drilling, continuous multiple cement leaking stoppage operation without pulling out of a hole is achieved, meanwhile, after plug drilling is completed, the normal drilling capacity is achieved, the number of times of pulling out of the hole is reduced, and the leaking stoppage operation period is greatly shortened.
Owner:CHINA NAT PETROLEUM CORP +1

Surrounding rock steel arch support construction method

The invention relates to the technical field of railway tunnels, in particular to a surrounding rock steel arch support construction method, after a tunnel is excavated, a steel arch is annularly spliced and installed along the section of the tunnel, primary support is carried out, the steel arch is formed by splicing and connecting steel arch sections, and each steel arch section is composed of a profile steel arch section and a flexible expansion pipe; the section steel arch frame sections are circular-arc-shaped section steel arch frame sections with openings in the upper portions, the flexible expansion pipes are embedded in the circular-arc-shaped steel arch frame sections, the flexible expansion pipes are filled with filling materials, and the flexible expansion pipes are extruded through the filling materials till the flexible expansion pipes are tightly attached to the inner walls of the circular-arc-shaped section steel arch frame sections. A first buffer layer is further arranged between the flexible expansion pipe and the arc-shaped steel arch frame section, and the first buffer layer is an elastic rubber plate arranged on the inner side of the arc-shaped steel arch frame section. According to the method, the primary support is more stable and firmer, the supporting force is higher, certain toughness and buffering force are achieved, and on the basis that the supporting strength is guaranteed, the support is not prone to breakage.
Owner:CHINA RAILWAY SEVENTH GRP CO LTD +1

Method for treating cracking of power transmission tower foundation by reducing upward pulling force

The invention discloses a method for treating cracking of a power transmission tower foundation by reducing uplift force. The method comprises the following steps: building an uplift-resistant foundation; processing a connecting plate; a protective cap of the cracked foundation is dismantled; welding the connecting plate and the tower foot plate; installing a temporary stay wire for controlling the safety of the iron tower; the cracked concrete is removed; pouring and curing concrete at the cracking part; dismantling the temporary stay wire; and pouring a concrete protective cap. According to the method for treating power transmission tower foundation cracking by reducing the upward pulling force, the upward pulling force acting on the foundation is reduced, and cracked concrete is removed, so that the problem of foundation cracking is fundamentally solved.
Owner:STATE GRID CORPORATION OF CHINA +1

Lifting mechanism capable of automatically adjusting counter weight

The utility model discloses a lifting mechanism capable of automatically adjusting a counter weight, and belongs to the field of construction equipment. According to the lifting mechanism, a suspension arm is hinged to a rotary supporting platform, and vertical swing of the suspension arm is achieved through an amplitude modulation oil cylinder; the balance arm is formed by hinging one end of a first arm section and one end of a second arm section, the other end of the first arm section is hinged to the rotary supporting platform, and a weight used as a balance weight is fixed to the other end of the second arm section. The two ends of the push-pull oil cylinder are hinged to the first arm section and the rotary supporting platform respectively, and the pitch angle of the first arm section is changed through stretching and retracting of the push-pull oil cylinder. The two ends of the balance arm jacking oil cylinder are hinged to the first arm section and the second arm section respectively, and the opening angle between the first arm section and the second arm section is changed through stretching and retracting of the balance arm jacking oil cylinder. According to the lifting mechanism, the balance moment can be dynamically adjusted through matching of different oil cylinders, so that the balance bending moment of the lifting mechanism is dynamically adjusted, and the lifting weight of the lifting mechanism is increased.
Owner:ZHONGTIAN CONSTR GRP ZHEJIANG STEEL STRUCTURE +1

Convenient and efficient micro-grid line erection rapid support

The invention belongs to the technical field of micro-grid construction, and particularly relates to a convenient and efficient micro-grid line erection rapid support which comprises a wire rod, a movable base is arranged at the bottom of the wire rod, a fixed part and a movable part are arranged on the movable base, a mounting frame is slidably connected to the wire rod, a vertical rod is arranged on the mounting frame, and the vertical rod is arranged on the wire rod. Cross arms are symmetrically arranged on the two sides of the vertical rod and do not interfere with the wire rod, insulators are arranged at the top end of the vertical rod and the tops of the two ends of the cross arms, wire clamping grooves are formed in the top ends of the insulators, and a lifting assembly capable of driving the mounting frame to move up and down along the wire rod is arranged on the wire rod. The side, away from the wire rod, of the mounting frame is connected with an auxiliary supporting piece. The device is simple in structure, convenient to operate, capable of completing high-altitude erection of lines without high-altitude operation, high in working efficiency and safe and reliable in construction.
Owner:BOAI COUNTY POWER SUPPLY CO OF STATE GRID HENAN ELECTRIC POWER CO

Induction pay-off device

The utility model provides an induction pay-off device which comprises a pay-off mechanism which comprises a stocker for storing materials and drawing lines during pay-off; the frame is connected with the stocker, and the frame is provided with at least one wheel; the sensing mechanism comprises a receiver and an emitter, the receiver is connected with the frame, the emitter is arranged on a preset moving route, and the receiver collects and prompts the moving deviation state by sensing signals emitted by the emitter; the wheels can be provided with bulges to enhance the road holding force; the pay-off mechanism is provided with a baffle and a baffle base to adjust the pay-off amount. The pay-off device has the advantages that inaccurate pay-off or re-pay-off caused by deviation from a preset route is avoided, body injury of personnel is reduced, uneven spreading of ash is avoided, the pay-off device can adapt to complex terrain operation, the structure is simple, construction is safe, cost is reduced, and construction efficiency and pay-off quality are improved.
Owner:MCC TIANGONG GROUP TIANJIN CO LTD

TBM surrounding rock quality real-time sensing method based on physical guidance online transfer learning

The invention discloses a TBM surrounding rock quality real-time sensing method based on physical guidance online transfer learning. The TBM surrounding rock quality real-time sensing method comprises the steps that 1, source domain and target domain tunnel engineering objects are divided; step 2, feature parameter extraction based on a source domain field monitoring data sharing parameter space; 3, constructing a thrust prediction model based on LSTM (Long Short Term Memory); 4, constructing a surrounding rock state prediction model based on a similarity index; and step 5, target domain surrounding rock quality online prediction. According to the method, characteristic values of working section data streams are extracted based on shared space parameters in different tunnel engineering field monitoring data in a source domain, and a surrounding rock quality online prediction module based on shared characteristics is constructed for real-time identification of a cross-engineering surrounding rock state. The migration application feasibility of a related intelligent model is broadened, the online prediction module can achieve rapid diagnosis of the surrounding rock state by means of real-time monitoring data flow in the construction process of the newly-built tunnel TBM, and an important basis is provided for guaranteeing efficient and safe construction of the TBM.
Owner:HOHAI UNIV

Steel support stress conversion device

The utility model relates to a steel support stress conversion device. A traditional construction method is tedious in construction procedure, poor in waterproof effect of a post-pouring part, high in construction risk and long in construction period. The device comprises a stress conversion mechanism, the stress conversion mechanism is arranged on a station structure top plate and a station structure middle plate, an air flue steel support is connected to the stress conversion mechanism, and the other end of the air flue steel support is connected with an auxiliary fender post; the stress conversion mechanism comprises a first supporting base and a second supporting base, the first supporting base is arranged on a top plate of a station structure, the second supporting base is arranged on a middle plate of the station structure, the air duct steel support comprises a first steel pipe support and a second steel pipe support, the first steel pipe support is connected to the first supporting base, and the second steel pipe support is connected to the second supporting base. The second steel pipe support is connected to the second supporting base. Only one-time pouring is needed, the construction procedure is simple, construction is safe, and the construction period is short.
Owner:CHINA RAILWAY FIRST SURVEY & DESIGN INST GRP

Expressway optical cable blowing laying construction method

The invention discloses an expressway optical cable blowing laying construction method. The method comprises the steps of S1, construction preparation; s2, the ratio of the outer diameter of the optical cable to the inner diameter of the silicon core pipe ranges from 0.35 to 0.6; the suitable working environment temperature is 6-32 DEG C; s3, slowly opening a compressed air inlet ball valve, and controlling the traction force of an air seal piston on the optical cable by changing the opening size of the valve; s4, when the feeding distance of the optical cable is short, the opening degree of the air inlet of the valve is small, and then the opening degree is gradually increased until the air inlet is completely opened; and S5, after the optical cable reaches a preset point, namely, the air seal piston comes out of the pipe (the air pressure is sharply reduced at the moment), an observer at the pipe end timely prompts an operator of the cable blowing machine to shut down immediately and stop conveying the optical cable into the pipe, so that the air-blowing laying operation of a section of optical cable is completed. And S6, cable reversing operation, namely conveying the optical cable into the'optical cable reversing device ', so as to pour out the remaining optical cable on the original cable tray and find out the other end to prepare for blowing and conveying the optical cable in the reverse direction.
Owner:中邮建技术有限公司

Automatic analysis method and system for advanced geological prediction of tunnels using elastic wave method

The present invention belongs to the field of geological engineering construction, and discloses an automatic analysis method and system for advanced geological prediction of tunnels using elastic wave method, which solves the problems of less training samples, poor universality of intelligent model engineering, and low automation level in the existing research on the application of artificial intelligence to advanced geological prediction analysis of tunnels. The present invention obtains elastic wave method parameter data by identifying elastic wave method parameter images, and establishes an elastic wave method parameter database; combines rock mechanics theory, geological disaster mechanism, etc. to establish a mapping relationship between key geophysical parameters of elastic wave method, geological indicators, and geological quality, to establish a classifier classification principle; finally, a machine learning method is used to construct a classifier model according to the classifier classification principle, and training and test samples are obtained based on the elastic wave method parameter database to train and verify the model. The model can be used to realize real-time automatic analysis of the entire process, thereby improving the accuracy and efficiency of the analysis.
Owner:CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE

Bailey truss integral beam falling device and method

The invention discloses an integral beam falling device and method for a bailey truss, and the main steps are as follows: S00: installing the integral beam falling device, firstly forming a lifting hole, a guide hole and a buffer hole, and then sequentially arranging a lifting beam assembly, a guide limiting assembly and a buffer assembly, S10: dismounting a falling block, and tightly hanging a truss system by a box beam; s20, the truss system falls down; and S30, the truss system is dismantled and transferred, the whole truss system is hoisted through a center hole jack, then under monitoring of an intelligent controller, the whole truss system slowly descends along a guide rod, meanwhile, the truss descending system is decelerated through a buffer assembly, the whole descending process is continuous, frequent operation of workers is not needed, and the working efficiency is improved. The construction period can be shortened and the construction efficiency can be improved while high-altitude operation is avoided to the maximum extent and safety and reliability are guaranteed, so that the whole truss system can quickly fall back to the ground and then is safely and stably disassembled.
Owner:CHINA CONSTR FOURTH ENG DIV CORP LTD

Preparation method and application of high-temperature-resistant graft modified gel suspension stabilizer

The invention relates to the technical field of oil well cement admixtures in the field of oil field well cementation, in particular to a preparation method and application of a high-temperature-resistant graft modified gel suspension stabilizer. The invention aims to solve the problem that the molecular chain structure of the existing common high polymer material suspension stabilizer is easy to break at high temperature and loses the suspension stability. The preparation method of the high-temperature-resistant grafted modified gel suspension stabilizer comprises the following steps: step 1, dissolving a monomer in deionized water, introducing protective gas, regulating the pH value of the solution by using a pH regulator, dissolving an initiator and a cross-linking agent in deionized water, and uniformly stirring to obtain a solution A; and filtering, crushing, purifying and drying the polymer prepared by the reaction to obtain the polymer gel material. And 2, dissolving the grafted component inorganic nanoparticles in deionized water, adding the gel material, introducing protective gas, adding a grafting agent, and carrying out a chemical grafting reaction to obtain the grafted modified gel suspension stabilizer.
Owner:CNPC BOHAI DRILLING ENG +1

A method for improving and grouting slag in shield construction of sandy gravel strata tunnel

The invention discloses a shield construction method for a sand-pebble stratum tunnel, comprising the following steps: reinforcing an end portal and installing a starting bracket; installing a reaction frame support system; installing the shield in slag, extending a portal steel ring and a seal, optimizing shield excavation parameters, measuring and adjusting the shield, etc., thereby ensuring that the shield construction is safe, smooth and fast, and achieving an ideal working condition when the shield is excavating in the sand-pebble stratum.
Owner:CHINA RAILWAY 22ND BUREAU GRP RAIL ENG CO LTD +1

Suspension bridge main cable finished bridge line shape analytical calculation method considering main cable torsional rigidity, electronic equipment and medium

The invention relates to a suspension bridge main cable finished bridge line shape analytical calculation method considering the torsional rigidity of a main cable, electronic equipment and a medium, and the calculation method comprises the following steps: considering the dead weight of the main cable and the load effect of a suspender, simultaneously including the tensile rigidity and the flexural rigidity of the main cable, and constructing a geometric precise equilibrium equation of the main cable under the dead weight and the load of the suspender; the influence of the bending moment in the main cable is ignored, incomplete boundary conditions are considered, and a quadratic approximate solution is solved based on a direct perturbation method; considering the influence of the bending moment of the main cable, combining the complete boundary, solving the influence of the bending moment of the main cable on the static linearity of the suspension bridge based on a direct perturbation method, and obtaining a second-order approximate solution considering the bending moment; through the compatibility condition of the left end point and the right end point, the corrected catenary equation and the second-order approximate solution considering the bending moment are combined. Compared with the prior art, the influence of the bending rigidity of the main cable is considered, the mechanical concept is clear, shape finding under different boundary conditions can be considered, and design and calculation of the main cable can be further guided.
Owner:SOUTHEAST UNIV

Efficient installation method of energy-saving guide wheel

PendingCN119099811AReduce the amount of high-altitude work on siteeasy to operateWaterborne vesselsHull structureStructural engineering
The invention belongs to the technical field of ocean engineering, and particularly relates to an efficient mounting method for an energy-saving guide wheel, which comprises the following steps: S1, a first group of standing sites and a second group of standing sites are separated, and the second group of standing sites are arranged at a tail shaft segmented hull structure; s2, establishing an energy-saving guide wheel and tail shaft casting pre-assembly model, and obtaining interference amount data between a guide vane of the energy-saving guide wheel and the tail shaft casting; the interference amount data comprises a carrying intersecting line generated by connecting interference points of a tail shaft casting and a guide vane on the energy-saving guide wheel and tail shaft casting pre-assembly model, and a boundary line which takes the carrying intersecting line as allowance cutting; s3, zero-allowance cutting is conducted on the guide vane according to the interference amount data; s4, the tail shaft casting is placed on the first set of standing sites, and the tail shaft casting is sealed and fixed; s5, the energy-saving guide wheel cut in the step S3 is pre-assembled to a tail shaft casting, and a first pre-assembled section is obtained; and S6, the first pre-assembly section is assembled on the tail shaft section. According to the method, the aloft work amount is reduced, safety is higher, and the assembly period can be shortened by more than 5 days.
Owner:DALIAN SHIPBUILDING INDUSTRY CO LTD

Underground diaphragm wall reinforcement cage hoisting process

PendingCN119142985Aprevent collapseReduce the risk of hoistingSafety gearArchitectural engineeringRebar
The invention discloses an underground diaphragm wall reinforcement cage hoisting process which comprises the following steps: S01, commanding a main crane and an auxiliary crane to transfer to a hoisting position, and respectively installing shackles of hoisting points by a hoisting worker; according to the method, the position of the hoisting point is determined firstly, and before hoisting, the node reinforcement at the hoisting point, the U-steel diagonal bracing reinforcement of the L-shaped reinforcement cage, the temporary shelving point, the fixed shelving point, the iron carrying pole and the material cable need to be checked, so that the requirements are met, and the hoisting risk is reduced; when a reinforcement cage is hoisted, a main machine and an auxiliary machine should be synchronous and listen to hoisting commands, the reinforcement cage is hoisted into a groove by the main machine after returning to be straight in the air, channel steel needs to be temporarily placed and firmly fixed when a steel wire rope is lengthened or replaced, and construction safety is ensured; the reinforcement cage is aligned with the center of the groove width when entering the groove, and is vertically and accurately inserted into the groove. The lowering process needs to be constant and slow, and the situation that the reinforcement cage swings transversely due to swing of a crane or other influences, and the groove wall collapses is avoided.
Owner:CHINA FIRST HIGHWAY ENGINEERING CO LTD +1