Rapid construction method of high-pressure water-rich fault zone of tunnel
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- CHINA RAILWAY 12TH BUREAU GRP
- Publication Date
- 2010-08-11
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention relates to the field of tunnel construction, in particular to a rapid construction method for high-pressure water-rich faults in tunnels. Background technique
[0002] Today, with the development of engineering construction, tunnel construction technology in complex areas has been greatly improved. At present, the construction methods for tunnels in high-pressure water-rich fault zones mainly include energy release and pressure reduction method and curtain grouting reinforcement method. In actual construction, it is found that these two methods have different problems. The specific analysis is as follows: 1. Energy release and reduction Problems in the pressure method: (1) For the case where there are underground rivers and karst development below the fault surface, and there are wide joint fissure waters in the vertical joint fissures, and the surface above the tunnel is houses, roads and paddy fields, the release of energy and pressure ...