Tower crane anchoring device for anti-seismic structure

By using the combination of connecting arms, anchor rods and anchors in the tower crane anchoring device, the anchor points inside the building main body are fixed, which solves the problem of damage and installation efficiency of the tower crane attached arm to the building wall and realizes the tower crane Improved stability and seismic resistance.

CN222099422UActive Publication Date: 2024-12-03BUCG THE EIGHTH CONSTR DEV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323389122.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-12
Publication Date
2024-12-03
Estimated Expiration
2033-12-12

AI Technical Summary

Technical Problem

The fixed area of ​​the tower crane arm and the building facade is small, which makes it easy to damage the building wall during use. The installation efficiency of the fixed frame and tower crane arm is low, making it difficult to ensure the stability of the tower crane. and shock resistance.

Method used

A tower crane anchoring device for seismic structure is designed. By combining connecting arms, anchor rods, central converters and anchors, the anchor points inside the building main body are fixed, increasing the stress range, and central conversion. The parts are connected to the tower crane, and the anchor rod is provided with one end of the anchor rod away from the center converter for enhanced stability.

Benefits of technology

It effectively protects the building walls, improves the installation efficiency of the tower crane's arm, enhances the stability and seismic resistance of the tower crane, and increases the stress range through the dispersed anchor rod arrangement, ensuring the stable and fixed tower crane.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222099422U_ABST
    Figure CN222099422U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of building installation, in particular to a tower footing anchoring device for an anti-seismic structure, which comprises a plurality of connecting arms for connecting a tower crane and a wall body, and the plurality of connecting arms are arranged in different directions; the anchoring rods are connected with the connecting arms, each connecting arm is connected with the multiple anchoring rods, and the connecting arms are fixed to the wall through the anchoring rods; the center conversion piece is arranged at the ends of the multiple anchoring rods and used for being connected with the multiple anchoring rods, and the multiple anchoring rods are fixed through the center conversion piece and then are in a radial shape; and the anchoring parts are installed at the ends, away from the center conversion part, of the multiple anchoring rods, and the multiple anchoring rods are fixed to the peripheral wall body and the top or bottom wall body through the anchoring parts. The mounting structure has the effects of protecting a building wall and improving the mounting efficiency of the tower crane auxiliary arm.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building installation, and in particular to a tower crane anchoring device for earthquake-resistant structures. Background Art

[0002] A tower crane is also called a tower crane. It is a rotating crane with a boom mounted on the top of a tall tower. It is usually used to hoist and transport raw materials such as steel bars, wooden slats, concrete, and steel pipes during construction, and is one of the indispensable equipment on construction sites. It has a large working range and is mainly used for vertical transportation of materials and component installation in multi-story and high-rise building construction. When a tower crane reaches a certain height, it is necessary to add a tower crane attachment to increase the stability of the tower crane. A common practice is to use the tower crane arm to bring a fixed frame to the standard section of the tower crane on the facade of the building, and use the tower crane arm to pull the fixed frame to ensure the stability of the tower crane, protect the structural wall, and improve the seismic performance. However, the fixed area between the tower crane arm and the facade of the building is small, which is easy to damage the wall of the building during use, and the installation efficiency of the fixed frame and the tower crane arm is low. Utility Model Content

[0003] In order to protect the building walls and improve the installation efficiency of the tower crane auxiliary arm, the present application provides a tower crane anchoring device for an earthquake-resistant structure.

[0004] The present application provides a tower crane anchoring device for an earthquake-resistant structure, which adopts the following technical solution:

[0005] A tower crane anchoring device for an earthquake-resistant structure, comprising:

[0006] A connecting arm is used to connect the tower crane and the wall, and a plurality of connecting arms are provided, and the plurality of connecting arms are arranged in different directions;

[0007] Anchor rods are connected to the connecting arms, each connecting arm is connected to a plurality of anchor rods, and the connecting arms are fixed to the wall through the anchor rods;

[0008] A central conversion piece is arranged at the ends of the plurality of anchor rods and is used to connect the plurality of anchor rods. The plurality of anchor rods are fixed by the central conversion piece in a radial shape.

[0009] Anchors are installed at one end of multiple anchor rods away from the central conversion piece. The multiple anchor rods are fixed to the surrounding walls and the top or bottom wall through the anchors.

[0010] By adopting the above technical solution, the main body of the building is fully utilized, the anchoring structure is fixed inside the main body of the building, and suitable anchoring points are selected to achieve the purpose of stabilizing the anchoring tower crane. The central conversion component is connected to the tower crane through a connecting arm, and the central conversion component is also connected to at least a plurality of anchor rods. An anchor is provided at one end of the anchor rod away from the central conversion component. When in use, at least one anchor is anchored to the horizontal ground inside the main body of the building, and the remaining anchors are anchored to different side walls inside the main body of the building. The anchor rods are arranged as dispersedly as possible to increase the force range.

[0011] Preferably, the connecting arm includes a tower crane square frame and a connecting rod head, the tower crane square frame is provided with a connecting rod head near a fixed point, the connecting rod head is provided with two or more sections, both ends of each section of the connecting rod head are movably provided, the tower crane square frame is provided with a square frame stabilizing mechanism, and a clamping mechanism is provided at one end of the connecting rod head away from the tower crane square frame.

[0012] Preferably, the square frame stabilizing mechanism includes a connecting plate arranged at one end of the tower crane square frame, and a fixing member for fixing two adjacent tower crane square frames.

[0013] Preferably, the tower crane square frame includes a variable diameter wall attachment rod, a main limb angle steel connected to the variable diameter wall attachment rod, and a web angle steel arranged on the variable diameter wall attachment rod and the main limb angle steel; the web angle steel is arranged at an angle, and both ends of the web angle steel are fixedly connected to the variable diameter wall attachment rod or the main limb angle steel.

[0014] Preferably, the variable diameter wall attaching rods are arranged at both ends of the tower crane square frame, and there are multiple main limb angle steels and fixing parts, and the connecting rod heads are connected to the variable diameter wall attaching rods.

[0015] Preferably, the diameter of the connecting rod head is 65-70 mm, and the size of the junction between the variable diameter wall attaching rod and the connecting rod head is at least twice the diameter of the connecting rod head.

[0016] Preferably, threaded sleeves are provided on the heads of the multiple sections of the connecting rods, and the vertical distance between each two adjacent threaded sleeves is 2.5-3 cm.

[0017] Preferably, when the anchor seat is installed, a reserved hole is reserved at the anchor seat position, and 6-8 steel pipes are used as a mold for the reserved holes on each side, with the same length as the wall width, a horizontal spacing of 20 cm, and a vertical spacing of 40 cm. The steel pipes are connected with = threaded steel bars.

[0018] Preferably, an attachment device is also required to be installed, and the attachment rod is used for adjustment during installation. The allowable deviation of verticality below the highest anchor point is 0.2%. When the attachment frame and attachment support are laid out, the upward and downward inclination angle of the attachment rod along the tower body shall not exceed 10°.

[0019] In summary, the present application includes at least one of the following beneficial technical effects:

[0020] 1. Make full use of the main body of the building, fix the anchoring structure inside the main body of the building, select appropriate anchoring points to achieve the purpose of stabilizing the anchoring tower crane. The central conversion component is connected to the tower crane through a connecting arm, and the central conversion component is also connected to at least multiple anchor rods. An anchor is provided at one end of the anchor rod away from the central conversion component. When in use, at least one anchor is anchored on the horizontal ground inside the main body of the building, and the remaining anchors are anchored on different side walls inside the main body of the building. The anchor rods are arranged as dispersedly as possible to increase the force range. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a simplified connection diagram in the embodiment of the present application;

[0022] Figure 2 It is a schematic diagram of the fixed structure of the connecting rod;

[0023] Figure 3 It is a schematic diagram of the connection structure of the tower crane frame.

[0024] Explanation of the reference numerals in the accompanying drawings: 1. connecting arm; 11. tower crane square frame; 111. square frame stabilizing mechanism; 1111. connecting plate; 1112. fixing piece; 112. variable diameter wall rod; 113. limb angle steel; 114. web rod angle steel; 12. connecting rod head; 121. threaded sleeve; 2. anchor rod; 3. center conversion piece; 4. anchor piece. DETAILED DESCRIPTION

[0025] The following is combined with Figure 1-3 This application is described in further detail.

[0026] The present application embodiment discloses a tower crane anchoring device for an earthquake-resistant structure. Figure 1 and Figure 2 The tower crane anchoring device for earthquake-resistant structure includes a connecting arm 1, an anchor rod 2, a central conversion piece 3, and an anchor 4; wherein the connecting arm 1 is used to connect the tower crane and the wall, and a plurality of connecting arms 1 are provided, and the plurality of connecting arms 1 are arranged in different directions; the anchor rod 2 is connected to the connecting arm 1, and each connecting arm 1 is connected to a plurality of anchor rods 2, and the connecting arm 1 is fixed to the wall through the anchor rod 2; the central conversion piece 3 is provided at the end of the plurality of anchor rods 2, and is used to connect the plurality of anchor rods 2, and the plurality of anchor rods 2 are radially fixed through the central conversion piece 3; the anchor 4 is installed at one end of the plurality of anchor rods 2 away from the central conversion piece 3, and the plurality of anchor rods 2 are fixed to the surrounding walls and the top or bottom wall through the anchor 4.

[0027] In an optional embodiment, the connecting arm 1 includes a tower crane square frame 11 and a connecting rod head 12. The connecting rod head 12 is arranged near the fixed point of the tower crane square frame 11. The connecting rod head 12 is arranged with two or more sections. Both ends of each section of the connecting rod head 12 are movably arranged. A square frame stabilizing mechanism 111 is arranged on the tower crane square frame 11. A clamping mechanism is arranged at one end of the connecting rod head 12 away from the tower crane square frame 11. The square frame stabilizing mechanism 111 includes a connecting plate 1111 arranged at one end of the tower crane square frame 11, and a fixing member 1112 for fixing two adjacent tower crane square frames 11.

[0028] In an optional embodiment, the tower crane square frame 11 includes a variable diameter wall attachment rod 112, a main limb angle steel 113 connected to the variable diameter wall attachment rod 112, and a web angle steel 114 arranged on the variable diameter wall attachment rod 112 and the main limb angle steel 113; the web angle steel 114 is arranged obliquely, and both ends of the web angle steel 114 are fixedly connected to the variable diameter wall attachment rod 112 or the main limb angle steel 113. The variable diameter wall attachment rod 112 is arranged at both ends of the tower crane square frame 11, and there are multiple main limb angle steels 113 and fixing parts 1112, and the connecting rod head 12 is connected to the variable diameter wall attachment rod 112. The diameter of the connecting rod head 12 is 65-70mm, and the size of the junction between the variable diameter wall attachment rod 112 and the connecting rod head 12 is at least twice the diameter of the connecting rod head 12. The multi-section connecting rod head 12 is provided with a threaded sleeve 121 , and the vertical distance between each two adjacent threaded sleeves 121 is 2.5-3 cm.

[0029] In an optional embodiment, when the anchor seat is installed, a reserved hole is set at the anchor seat position. The reserved holes on each side use 6-8 steel pipes as molds, with the same length as the wall width, 20 cm horizontal spacing, 40 cm vertical spacing, and threaded steel bars between the steel pipes. An attachment device is also required to be installed. During installation, an attachment rod is used for adjustment. The allowable deviation of verticality below the highest anchor point is 0.2%. When the attachment frame and attachment support are laid out, the attachment rod shall not be tilted up and down by more than 10° along the tower body.

[0030] In an optional embodiment, when there are three tower cranes that need to be attached, the ring beam structure type is basically the same, where the cross-section of the attachment ring beam of two tower cranes is 1.6×1.6m, and that of the other tower crane is 2.0×2.0m. The connection between the tower crane attachment rod and the attachment ring beam is made by using the attachment ring beam as a standard part, and the connection with the attachment rod is connected by a Ф60 pin. During construction, according to the construction drawings and the on-site conditions, the tower crane wall attachment parts are connected to the building and the cast-in-place wall of the structure is selected as the attachment point. The tower crane wall support adopts a double-ear plate wall mount, which is easy and quick to install. The wall mount is made of 16-20mm thick steel plate with grade Q235B welded, and the connecting bolts are 8.8-grade M36 high-strength bolts. The corresponding connection method is adopted according to the different structural conditions of the structural wall corresponding to each tower crane attachment point.

[0031] In an optional embodiment, according to the length and angle of each tower crane attachment rod, 4×L75×5 angle steels are used to form a grid member with a cross section of 350×350, and L40×4 tie bars are used with a spacing of 400mm to weld the angle steel on all sides. The weld height is 6mm in the form of fillet welds, and the welding rods are E43 welding rods, which can meet the force requirements of the wall attachment rods. Before each attachment, the project department is responsible for reserving holes in the structural wall in advance. According to the construction progress, the construction personnel of the project department reserve two holes at the designated location. The diameter of the reserved holes is ф48. During construction, reserved holes must be reserved in advance at the anchor seat position. 6 to 8 ф48mm steel pipes are used as molds for the reserved holes on each side. The length is the same as the width of the wall, the horizontal spacing is 200mm, and the vertical spacing is 400mm. The steel pipes are connected with ф12mm threaded steel.

[0032] In an optional embodiment, in order to facilitate the embedding of the reserved hole mold, the mold must be fixed before tying the transverse reinforcement or stirrups, and then the upper reinforcement is tied. After embedding, the tube needs to be filled with foam before closing the mold, and the two ends are sealed with tape to prevent mortar from pouring into the tube during the concrete pouring process. In an optional embodiment, the maximum tensile pressure of the seat in the parallel direction to the wall is about 380KN, and the maximum tensile pressure in the vertical direction to the wall is about 480KN. In an optional embodiment, the plane position of the tower crane attachment needs to be set, and the cast-in-place wall of the structure is selected as the attachment point according to the structural form of each construction building number. According to the requirements of the manual of each tower crane and the actual situation on site, the attached tower cranes all use the four-rod attachment form calibrated in the manual.

[0033] When anchoring the tower crane, first, the concrete strength grade at the building attachment point must be no less than C30, and it can only be anchored and attached if it reaches more than 90% of the standard value. Before attachment, the project department is responsible for setting up the tower crane and the attachment point attachment construction platform at the attachment position, and setting up the working platform 1200mm below the corresponding building attachment point of the tower crane to facilitate the installation and positioning of the attachment frame and attachment seat. The attachment frame installation platform needs to be set up around the tower body. The drop width is not less than 0.8 meters, the guardrail height is 1 meter, and a safety net is hung.

[0034] In an optional embodiment, when installing the attachment frame and the wall attachment, the standard ladder on the tower section is removed before installing the anchor frame. The two side beams and are first connected to the front beam on the ground. The pins are inserted to facilitate the adjustment of the spacing between the side beams and. The assembly frame is lifted to the exact position of the tower body, so that the front beam side of the anchor frame faces the building. For easy installation, two ropes are used as guides. Lift the front beam and place it on the horizontal support located in the middle of the tower body, and fold back the side beams and connect them with pins. Lift the rear beam and connect it to the side beams with pins after it is in place. Continue to lift the support and connect it to the beam with pins. Install the diagonal brace and check the horizontal position of the anchor frame and make appropriate adjustments if necessary. Install the diagonal wedge and drive it in. Make the anchor frame close to the main pole of the tower body. After installing the wedge, check whether there is any gap between the wedge and the tower body. Install the ladder supplied with the anchor frame and then install the two guardrail components on this ladder. Install the wall mount on the wall and fasten it with 6 to 8 M36 bolts. Pay attention to the direction of the pin of the wall mount.

[0035] In an optional embodiment, after the attachment ring beam and the wall attachment are installed, the actual size of each attachment rod is measured when the tower crane is in a vertical state. During the measurement, the theodolite is supported on the ground, the tower crane rotates the boom to the jacking direction, lifts two standard sections and starts the trolley to adjust the position until the tower crane is completely in a vertical state and then locks the various mechanisms of the tower crane. Then the verticality of the tower crane is measured from another direction to obtain the actual deviation data. At this time, the actual size from the ring beam hole to the wall attachment hole is measured to obtain the actual size of each attachment rod. According to the actual deviation data and the actual size of the attachment rod, the final size of the attachment rod is obtained after addition and subtraction.

[0036] Adjust the exact length of each attachment rod according to the final size, and tighten the adjustment rod nut to fix it after completion to prevent errors caused by the rotation of the adjustment rod during installation. Install each attachment rod to the exact position according to the size of the attachment rod. The four attached struts should be on the same horizontal plane as much as possible, and tighten the pin shaft to align the cotter pin. In an optional embodiment, when installing the attachment device, the verticality of the tower body should be checked with a theodolite, and the attachment rod should be used for adjustment. The allowable deviation of the verticality below the highest anchor point is 0.2%. When the attachment frame and attachment support are laid out, the up and down inclination angle of the attachment rod along the tower body shall not exceed 10°.

[0037] The implementation principle of the embodiment of the present application is: make full use of the building body, fix the anchoring structure inside the building body, select suitable anchoring points, and achieve the purpose of stabilizing the anchoring tower crane. The central conversion component is connected to the tower crane through the connecting arm 1, and the central conversion component 3 is also connected to at least multiple anchor rods 2. The end of the anchor rod 2 away from the central conversion component 3 is provided with an anchor 4. When in use, at least one anchor 4 is anchored on the horizontal ground inside the building body, and the remaining anchors 4 are anchored on different side walls inside the building body. The anchor rods 2 are arranged as dispersed as possible to increase the force range.

[0038] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A tower crane anchoring device for earthquake-resistant structures, characterized in that: include: A connecting arm (1) is used to connect the tower crane and the wall, wherein a plurality of connecting arms (1) are provided, and the plurality of connecting arms (1) are arranged in different directions; Anchor rods (2) are connected to the connecting arms (1), each connecting arm (1) is connected to a plurality of anchor rods (2), and the connecting arm (1) is fixed to the wall through the anchor rods (2); A central conversion member (3) is arranged at the ends of the plurality of anchor rods (2) and is used to connect the plurality of anchor rods (2). The plurality of anchor rods (2) are radially arranged after being fixed by the central conversion member (3); An anchor (4) is installed at one end of the plurality of anchor rods (2) away from the central conversion member (3), and the plurality of anchor rods (2) are fixed to surrounding walls and the top or bottom wall through the anchor (4).

2. The tower crane anchoring device for earthquake-resistant structure according to claim 1, characterized in that: The connecting arm (1) comprises a tower crane square frame (11) and a connecting rod head (12); the tower crane square frame (11) is provided with a connecting rod head (12) near a fixed point; the connecting rod head (12) is provided with two or more sections; both ends of each section of the connecting rod head (12) are movably arranged; the tower crane square frame (11) is provided with a square frame stabilizing mechanism (111); and a clamping mechanism is provided at one end of the connecting rod head (12) away from the tower crane square frame (11).

3. The tower crane anchoring device for earthquake-resistant structure according to claim 2, characterized in that: The square frame stabilizing mechanism (111) comprises a connecting plate (1111) arranged at one end of the tower crane square frame (11), and a fixing member (1112) for fixing two adjacent tower crane square frames (11).

4. The tower crane anchoring device for earthquake-resistant structure according to claim 3 is characterized in that: The tower crane square frame (11) comprises a variable diameter wall attachment rod (112), a main limb angle steel (113) connected to the variable diameter wall attachment rod (112), and a web angle steel (114) arranged on the variable diameter wall attachment rod (112) and the main limb angle steel (113); the web angle steel (114) is arranged obliquely, and both ends of the web angle steel (114) are fixedly connected to the variable diameter wall attachment rod (112) or the main limb angle steel (113).

5. The tower crane anchoring device for earthquake-resistant structure according to claim 4, characterized in that: The variable diameter wall attaching rod (112) is arranged at both ends of the tower crane square frame (11), and there are a plurality of main limb angle steels (113) and fixing members (1112). The connecting rod head (12) is connected to the variable diameter wall attaching rod (112).

6. The tower crane anchoring device for earthquake-resistant structure according to claim 5, characterized in that: The diameter of the connecting rod head (12) is 65-70 mm, and the size of the junction between the variable diameter wall attachment rod (112) and the connecting rod head (12) is at least twice the diameter of the connecting rod head (12).

7. The tower crane anchoring device for earthquake-resistant structure according to claim 5, characterized in that: The multiple sections of the connecting rod heads (12) are all provided with threaded sleeves (121), and the vertical distance between any two adjacent threaded sleeves (121) is 2.5-3 cm.

8. The tower crane anchoring device for earthquake-resistant structure according to claim 1, characterized in that: An attachment device also needs to be installed. The attachment device includes an attachment rod, an attachment frame and an attachment support. The attachment rod is used for adjustment during installation. The allowable deviation of verticality below the highest anchor point is 0.2%. When the attachment frame and attachment support are laid out, the upward and downward inclination angle of the attachment rod along the tower body shall not exceed 10°.