Up-down overlapped tunnel connection channel and mining method construction reinforcing structure
By setting up inclined shafts in the upper and lower overlap tunnel contact channels and grouting and reinforcement, construction complexity and safety issues are solved, and safe and reliable soil reinforcement and construction risks are achieved.
Patent Information
- Application Number
- CN202420676130.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-27
AI Technical Summary
In urban subway construction, the construction of vertical liaison channels is complex and costly, making it difficult to ensure safety and stability. In addition, conventional open excavation methods affect the surrounding environment and deformation of existing tunnels.
By setting up an inclined shaft in the upper and lower overlap tunnel connection channel, the upper and lower overlap tunnel connection channel is connected into an integral unit, and the grouting reinforcement structure in the inclined shaft is constructed by the mine method, and steel support and grouting pipe are installed for reinforcement. .
The safety and stability of the upper and lower overlap tunnel connection channels have been achieved, soil reinforcement has been strengthened, construction risks and impact on the surrounding environment have been reduced.
Smart Images

Figure CN222102041U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of civil engineering, and specifically relates to an upper and lower overlapping tunnel communication channel and a mining method construction reinforcement structure. Background Art
[0002] In urban subway construction, subject to the layout of urban underground space, underground pipelines, existing buildings and structures, it is inevitable that more overlapping tunnels with large height differences will appear in subway construction. For the evacuation of personnel under interval accident conditions, overlapping lines are often connected through vertical communication channels. Since the structure and shape of vertical communication channels are more complex than those of general channels, the construction and technical difficulties are higher. At present, there is no very safe and easy-to-construct communication channel reinforcement construction plan for vertical communication channels. Therefore, a communication channel for upper and lower overlapping tunnels and a mining method construction reinforcement structure are needed.
[0003] However, due to the complex structure of the overlapping shield tunnels, if the conventional open-cut excavation method is adopted, firstly, the ground space is not sufficient, secondly, the cost of structural reinforcement and maintenance is high, and thirdly, the construction period is relatively long. It is difficult to ensure the strength of the reinforcement of the connecting channel and the stability of the construction, which also affects the deformation of the ground and the existing tunnel.
[0004] Therefore, a connecting channel for overlapping tunnels and a mining method construction reinforcement structure are needed to solve the above problems. This reinforcement method can ensure the safety of connecting channel construction and the stability of shield tunnels, while reducing the impact of construction on the surrounding environment. Utility Model Content
[0005] The purpose of the utility model is to provide a communication channel for upper and lower overlapping tunnels and a reinforcement structure for mining method construction based on the above-mentioned deficiencies in the prior art. The reinforcement method is to set an inclined shaft in the middle of the communication channel for the upper and lower overlapping shield tunnels, and connect the communication channels for the upper and lower overlapping tunnels into an integral unit through the inclined shaft. The upward line transverse communication channel, the downward line transverse communication channel and the inclined shaft grouting reinforcement area overlap with each other, which can not only meet the needs of the construction of the communication channel for the upper and lower overlapping tunnels, but also reduce the risk of mining method dark excavation construction.
[0006] The technical scheme adopted by the utility model comprises an up-line tunnel and a down-line tunnel which are parallel to each other, the up-line tunnel is located above the down-line tunnel, the up-line tunnel has a dark-digging horse-head door connected to an up-line transverse communication channel which is vertically connected thereto and extends to the inclined shaft, the down-line tunnel has a dark-digging horse-head door connected to a down-line transverse communication channel which is vertically connected thereto and extends to the inclined shaft, the up-line transverse communication channel and the down-line transverse communication channel are parallel to the ground, the up-line transverse communication channel and the down-line transverse communication channel both comprise dark-digging horse-head doors, a primary support structure, a first grouting pipe, a second grouting pipe, and a secondary lining, and the secondary lining is arranged on the inner side of the primary support structure.
[0007] Furthermore, the up-line transverse communication channel and the down-line transverse communication channel are connected through an inclined shaft, a steel support structure is arranged inside the inclined shaft, and a first grouting pipe and a second grouting pipe are buried for grouting reinforcement to form a grouting reinforcement body.
[0008] Furthermore, the horizontal connecting passages of the up line are excavated in sections through dark tunnels using the mining method, and the initial support structure, grouting conduit installation and grouting reinforcement are carried out simultaneously; the horizontal connecting passages of the down line are excavated in sections through dark tunnels using the mining method, and the initial support structure, grouting conduit installation and grouting reinforcement are carried out simultaneously to form a grouting reinforced body.
[0009] Furthermore, an upper emergency safety door is arranged between the upper end of the inclined shaft and the right end of the upward line horizontal communication channel, and a lower emergency safety door is arranged between the lower end of the inclined shaft and the right end of the downward line horizontal communication channel.
[0010] Furthermore, deformation joints are provided at the connection between the inclined shaft and the up-line transverse communication channel and the down-line transverse communication channel respectively.
[0011] Furthermore, the inclined shaft adopts the mining method of construction, constructing the initial support structure while excavating. At the same time, a steel support structure is set up in the inclined shaft according to the construction steps, and the first grouting pipe is drilled. The first grouting pipe adopts two hole forming angles, nearly horizontal and downward, to carry out grouting and form a grouting reinforcement body.
[0012] Furthermore, the up-line lateral communication channel and the down-line lateral communication channel adopt the mining method construction method, excavate in blocks and set up the second grouting pipe, and construct the primary support structure while excavating. The second grouting pipe adopts a horizontal hole angle to perform grouting and form a grouting reinforcement body.
[0013] Compared with the prior art, the superior effects of the utility model are: 1) This reinforcement method connects the upper and lower overlapping tunnel communication channels into an integral unit through an inclined shaft, and the upward line transverse communication channel, the downward line transverse communication channel and the inclined shaft grouting reinforcement area overlap each other, which can not only meet the needs of the construction of the upper and lower overlapping tunnel communication channels, but also reduce the risk of underground excavation construction. 2) The first grouting pipe in the inclined shaft of the frozen reinforcement structure adopts two hole-forming angles, nearly horizontal and downward, and the second grouting pipe in the upward line transverse communication channel and the downward line transverse communication channel adopts a horizontal hole-forming angle. The first grouting pipe and the second grouting pipe form a reinforcement body with the outer soil of the upward line transverse communication channel and the downward line transverse communication channel, making the reinforced soil safer and more reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a structural schematic diagram of the reinforcement construction method of the utility model;
[0015] Figure 2It is a structural schematic diagram of the connection relationship between the grouting reinforcement structure and the reinforcement body of the utility model;
[0016] Figure 3 for Figure 1 A is a cross-sectional view;
[0017] Figure 4 for Figure 1 The cross-sectional view of B;
[0018] Figure numerals: 1-up line tunnel, 2-down line tunnel, 3-up line horizontal communication channel, 4-down line horizontal communication channel, 5-primary support structure, 6-blind excavation horse head gate, 7-first grouting pipe, 8-inclined shaft, 9-second grouting pipe, 10-steel support structure, 11-secondary lining, 12-extension joint, 13-upper emergency safety door, 14-lower emergency safety door, 15-grouting reinforcement body. DETAILED DESCRIPTION
[0019] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0020] like Figure 1 As shown, this embodiment provides an upper and lower overlapping tunnel communication channel and a mining method construction reinforcement structure, including an up-line tunnel 1 and a down-line tunnel 2 parallel to each other, the up-line tunnel 1 is located above the down-line tunnel 1, the up-line tunnel 1 is secretly excavated with an up-line transverse communication channel 3 vertically connected thereto and extending to the inclined shaft 8, the down-line tunnel 2 is secretly excavated with a down-line transverse communication channel 4 vertically connected thereto and extending to the inclined shaft 8, the up-line transverse communication channel 3 and the down-line transverse communication channel 4 are parallel to the ground, the up-line transverse communication channel 3 and the down-line transverse communication channel 4 both include a secretly excavated horse head gate 6, a primary support structure 5, a first grouting pipe 7, a second grouting pipe 9, and a secondary lining 11, and the secondary lining is arranged on the inner side of the primary support structure 5.
[0021] The up-line transverse communication channel 3 and the down-line transverse communication channel 4 are connected through an inclined shaft 8. A steel support structure 10 is arranged inside the inclined shaft 8. The wall of the inclined shaft 8 is provided with a first grouting pipe 7 at two angles, nearly horizontal and downward.
[0022] An upper emergency safety door 13 is provided between the upper end of the inclined shaft 8 and the right end of the up-line transverse communication channel 3 , and a lower emergency safety door 14 is provided between the lower end of the inclined shaft 8 and the right end of the down-line transverse communication channel 4 .
[0023] Deformation joints 12 are provided at the connection points between the inclined shaft 8 and the up-line transverse communication channel 3 and the down-line transverse communication channel 4 respectively.
[0024] like Figure 2As shown, the first grouting pipe 7 is set as a long grouting pipe, and the second grouting pipe 9 is set as an advanced small pipe. The grouting pipes make the outer soil of the upward line transverse connecting channel 3, the downward line transverse connecting channel 4 and the inclined shaft 8 form a grouting reinforcement body 15.
[0025] like Figure 3 As shown, a first grouting pipe 7 is drilled in the inclined well. The first grouting pipe 7 adopts two hole-forming angles, nearly horizontal and downward, and is distributed around the inclined well.
[0026] like Figure 1 and Figure 4 As shown, a second grouting pipe 9 is drilled in the downline transverse communication channel 4, and the second grouting pipe 9 is distributed around the downline transverse communication channel 4. The second grouting pipe 9 adopts a horizontal hole angle. Similarly, a second grouting pipe 9 is also drilled in the upline transverse communication channel 3, and the second grouting pipe 9 is also distributed around the upline transverse communication channel 3.
[0027] The following is a brief introduction to the operation steps of the reinforcement construction method:
[0028] Step 1: The up-line tunnel 1 removes the dark excavation gate 6 to excavate the up-line transverse communication channel 3, and sets up the second grouting pipe 9;
[0029] Step 2: In step 1, the inclined shaft 8 is excavated, a steel support structure 10 is set, a first grouting pipe 7 is set, and grouting is performed;
[0030] Step 3: The downline tunnel 2 removes the dark excavation gate 6 to excavate the downline transverse communication channel 4, and sets up the second grouting pipe 9;
[0031] Step 4, connect the downline transverse communication channel 4 and the inclined shaft 8, and construct the secondary lining structure 11;
[0032] It should be noted that the number of grouting pipes drilled in the inclined shaft 8, the upward line transverse communication channel 3 and the downward line transverse communication channel 4 needs to be set according to actual conditions.
[0033] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0034] The present invention is not limited by the above embodiments. The above embodiments and the description are only for explaining the principle of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which are within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims.
Claims
1. A connecting passage of upper and lower overlapping tunnels and a mining method construction reinforcement structure, characterized in that: The invention comprises an up-line tunnel (1) and a down-line tunnel (2) which are parallel to each other. The up-line tunnel (1) is located directly above the down-line tunnel (2). The up-line tunnel has a dark excavated horse head door (6) connected to an up-line transverse communication channel (3) which is vertically connected to the up-line tunnel and extends to an inclined shaft (8). The down-line tunnel has a dark excavated horse head door (6) connected to a down-line transverse communication channel (4) which is vertically connected to the down-line tunnel and extends to the inclined shaft (8). The up-line transverse communication channel (3) and the down-line transverse communication channel (4) are parallel to the ground. The up-line transverse communication channel (3) and the down-line transverse communication channel (4) both comprise a dark excavated horse head door (6), a primary support structure (5), a first grouting pipe (7), a second grouting pipe (9), and a secondary lining (11). The secondary lining is arranged on the inner side of the primary support structure.
2. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1, characterized in that: The up-line transverse communication channel (3) and the down-line transverse communication channel (4) are connected through an inclined shaft (8), a steel support structure (10) is arranged inside the inclined shaft, and a first grouting pipe (7) is buried for grouting reinforcement to form a grouting reinforcement body (15).
3. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1 is characterized by: The up-line transverse communication channel (3) is excavated in sections by using a mining method through a dark excavation gate (6), and the primary support structure (5) and the second grouting pipe (9) are simultaneously buried and reinforced by grouting; The downline transverse communication channel (4) is excavated in sections by a dark-digger (6) using a mining method, and the primary support structure (5) and the second grouting pipe (9) are simultaneously buried and grouting is performed to form a grouting reinforcement body (15).
4. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1, characterized in that: An upper emergency safety door (13) is provided between the upper end of the inclined shaft (8) and the right end of the upward line transverse communication channel (3), and a lower emergency safety door (14) is provided between the lower end of the inclined shaft (8) and the right end of the downward line transverse communication channel (4).
5. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1, characterized in that: Deformation joints (12) are provided at the connection points between the inclined shaft (8) and the up-line transverse communication channel and the down-line transverse communication channel.
6. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1, characterized in that: The inclined shaft (8) is excavated using a mining method, with the primary support structure (5) being constructed while the excavation is being carried out. A steel support structure (10) is set up in the inclined shaft along the construction steps, and a first grouting pipe (7) is set up. The first grouting pipe adopts two hole-forming angles: nearly horizontal and downward.
7. The upper and lower overlapping tunnel communication passage and mining method construction reinforcement structure according to claim 1, characterized in that: The upward line transverse communication channel (3) and the downward line transverse communication channel (4) are excavated in blocks and the second grouting pipe (9) is set by using the mining method. The second grouting pipe (9) adopts a horizontal hole forming angle.