System for creating a schedule for converting a generator into a synchronous condenser, and method for creating a schedule for converting a generator into a synchronous condenser
The process chart creation system optimizes the conversion of decommissioned nuclear power plant generators into synchronous phase modifiers by considering decommissioning stages and future power system plans, addressing cost and operational efficiency challenges.
Patent Information
- Application Number
- JP2021042914
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-03-16
- Publication Date
- 2024-12-09
- Estimated Expiration
- 2041-03-16
AI Technical Summary
The challenge lies in converting decommissioned nuclear power plant generators into synchronous phase modifiers while minimizing initial costs, operating costs, and maintenance costs, while also addressing the unique requirements and changes in equipment configuration due to the decommissioning process and the need to operate in controlled or uncontrolled areas.
A process chart creation system and method that considers the necessity of equipment for decommissioning work, scheduled usage period, and customer requests to create an optimal modification and operation process for converting generators into synchronous phase modifiers, taking into account the decommissioning stage and future power system plans.
Enables the creation of a tailored process chart that minimizes initial costs, optimizes operating and maintenance costs, and ensures efficient operation of synchronous phase modifiers throughout the decommissioning process, considering the changing equipment needs and environmental conditions.
Smart Images

Figure 0007596188000001 
Figure 0007596188000002 
Figure 0007596188000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a generator synchronous phase modifier conversion schedule creation system and a generator synchronous phase modifier conversion schedule creation method that create a schedule for converting a generator of a nuclear power plant into a synchronous phase modifier and operating it. [Background technology]
[0002] Synchronous phase modifiers are used as phase modifiers to control the voltage and reactive power of power systems. Synchronous phase modifiers stabilize power systems by supplying reactive power to the power system at the required timing. Compared to static var compensators (SVCs) and self-excited static var compensators (STATCOMs), synchronous phase modifiers can perform voltage control continuously and, being a rotating machine, can also provide inertia to the system. However, synchronous phase modifiers are rotating machines and require high-cost generators, so construction costs tend to be high when newly installed.
[0003] Thermal and nuclear power plants generally use synchronous generators (rotating machines). These synchronous generators can provide reactive power as well as active power. They also provide inertial power to the power system by rotating large turbines and generators.
[0004] In recent years, the number of nuclear power plants and old thermal power plants (particularly coal-fired plants) being decommissioned has been increasing, and a shortage of inertial force and reactive power that can be supplied to the power grid has become an issue. To solve this issue, Patent Document 1 describes a method of modifying a generator of an idle thermal power plant into a synchronous modifier to supply inertial force and reactive power to the power grid. Non-Patent Document 1 also describes an example of modifying a generator of a decommissioned nuclear power plant (to be decommissioned) and using it as a synchronous modifier.
[0005] By reusing generators from existing thermal power plants or nuclear power plants as synchronous phase modifiers, the costs of the generators and the equipment required to operate them, which account for a large proportion of the cost when installing a new synchronous phase modifier, are eliminated, making it possible to provide a synchronous phase modifier at low cost. [Prior art documents] [Patent documents]
[0006] [Patent Document 1] Japanese Patent Application Publication No. 3-82339 Summary of the Invention [Problem to be solved by the invention]
[0007] When trying to use the generators of decommissioned nuclear power plants as synchronous modifiers, there are other directly and indirectly necessary facilities in addition to the generator itself. Directly necessary facilities include, for example, cooling water facilities to cool the generator, and indirectly necessary facilities include, for example, ventilation and air conditioning facilities related to the environment in the generator area. In addition, there may also be service facilities such as a water supply system, a compressed air supply system, and a wastewater system.
[0008] The same is true for electrical equipment. In addition to the main circuits such as switchyards, main transformers, and isolated phase buses, there are other directly and indirectly necessary facilities. Directly necessary facilities include, for example, circuit breakers and disconnectors installed on the main circuits, and indirect facilities include, for example, cooling facilities for isolated phase buses. In addition, there may be electrical facilities for lighting and other services.
[0009] Both mechanical and electrical equipment that is directly necessary can be said to be unconditionally necessary equipment. On the other hand, indirectly necessary equipment and service equipment can be either necessary or unnecessary depending on the conditions. For example, ventilation and air conditioning equipment may no longer be necessary because the thermal load is reduced compared to when the plant was a power plant.
[0010] When generators at thermal or nuclear power plants are converted into synchronous phase modifiers, initial costs can be significantly reduced if the power supply system and auxiliary equipment (lubrication and cooling devices) are also used as is. In addition, since large power plants are connected to large-capacity power systems, synchronous phase modifiers can also use these large-capacity power systems as is. On the other hand, since the power supply system and auxiliary equipment (lubrication and cooling devices) are designed assuming the power plant is operating at its output, if these devices are used as is, they are over-specified for a synchronous phase modifier, resulting in high operating and maintenance costs. For example, operating and maintenance costs can be reduced by replacing equipment that reduces thermal load with smaller equipment, or by replacing water-cooled equipment with air-cooled equipment.
[0011] In this way, when a modified synchronous phase condenser is to be used for only a short period of time, it is reasonable to minimize the total cost by minimizing the modifications and keeping the initial costs down. On the other hand, when a synchronous phase condenser is to be used for a long period of time, it is reasonable to minimize the total cost by streamlining the operation and maintenance costs, for example by replacing equipment with high operation and maintenance costs with equipment with specifications that require a synchronous phase condenser. These costs also include reduced operation costs due to improvements in the working environment for operators and improved controllability of the plant, as well as costs for permits and licenses.
[0012] In Patent Document 1, when converting a generator of a thermal power plant into a synchronous phase modifier, the internal hydrogen gas pressure of the hydrogen-cooled generator is lowered in advance to reduce windage loss and minimize the capacity of the drive motor. However, Patent Document 1 does not address the power supply system or auxiliary equipment (lubrication system and cooling system), and there is little improvement in terms of operation costs and maintenance costs.
[0013] In nuclear power plants, safety during operation is paramount, so the configuration of power supply systems and auxiliary equipment is multiplexed and designed with a margin of equipment capacity. Therefore, when using a nuclear power plant as a synchronous modifier, the power supply systems and auxiliary equipment are often over-specified. Therefore, in order to reduce operating costs, it is necessary to rationalize the power supply systems and auxiliary equipment by appropriately downsizing them.
[0014] Compared to thermal power plants, there are some issues specific to nuclear power plants when converting nuclear power plants into synchronous condensers. When decommissioning a thermal power plant and converting it into a synchronous condenser, the boilers and combustors that are being decommissioned do not require safety measures after shutdown. Therefore, in thermal power plants, the appropriate equipment configuration for a synchronous condenser can be taken from the beginning of the conversion.
[0015] On the other hand, in a nuclear power plant, there is spent fuel in the pressure vessel of the reactor immediately after decommissioning. The spent fuel emits decay heat, so it needs to be constantly cooled. For example, in a boiling water reactor, it is cooled by the reactor shutdown cooling mode of the residual heat removal system. This operation requires multiple power sources, securing emergency generators, and maintaining the cooling system. Therefore, the power supply system and auxiliary equipment required for cooling the spent fuel in the pressure vessel of the reactor during decommissioning cannot be rationalized, even if they are power supply systems and auxiliary equipment that are not necessary for operation as a synchronous phase converter. After that, as the cooling of the fuel progresses and all the fuel is transferred to the spent fuel pool, the spent fuel is cooled by the spent fuel pool cooling system (called FPC). Then, since there is no fuel in the pressure vessel, there is no possibility of the need to inject water into the pressure vessel. Therefore, the power supply system and auxiliary equipment related to the FPC cannot be rationalized, but the equipment that injects water into the pressure vessel, such as the reactor shutdown cooling mode of the residual heat removal system, and the related power supply system and auxiliary equipment become unnecessary. Furthermore, as the decommissioning work progresses and fuel is removed from the spent fuel pool, all fuel cooling systems and the associated power systems and auxiliary machinery will no longer be needed.
[0016] Thus, in a nuclear power plant, the power supply system and auxiliary system of a synchronous phase condenser are not determined solely by its operation as a synchronous phase condenser, but the available equipment configuration changes depending on where the spent fuel, which is part of the decommissioning process, is located. As for the control device for the synchronous phase condenser, if a central control room is still in place in the early stages of decommissioning, it is possible to install a control panel for the synchronous phase condenser in the central control room and control it. In this case, the schedule creator creates a schedule that includes a process for installing the control panel for the synchronous phase condenser in the central control room and monitoring and / or controlling the synchronous phase condenser from the central control room. However, when it is expected that the synchronous condenser will be used until the decommissioning of the nuclear power plant progresses and the central control room is removed, it is more reasonable to install a separate control device for the synchronous condenser and a separate control room.
[0017] In this way, the rational design differs depending on the progress of the decommissioning measures. Thus, nuclear power plants to be decommissioned have equipment that is unique to the decommissioning plant, unrelated to synchronous condensers. Furthermore, the necessary equipment and existing equipment in a decommissioning plant changes over time as the decommissioning work process progresses. When considering equipment degeneration (suspension or removal of unnecessary equipment) in order to retrofit a nuclear power plant to a synchronous condenser, a condition is that there is no impact on the decommissioning work. Therefore, one of the challenges is to identify the scope of degeneration and modification taking these points into consideration.
[0018] In the modification example in Non-Patent Document 1, the scope of modification is merely minimized, and appropriate changes to the scope of modification of the synchronous phase modifier in accordance with the decommissioning measures to be implemented during the period in which it is operated as a synchronous phase modifier and the resulting optimization of costs, etc. are not implemented. In addition, in order to identify the period in which it will be used as a synchronous phase modifier, it is also necessary to determine how long it can be used in the future based on the future development status of the power system, plans for introducing power sources such as renewable energy, and the status of the generator to be modified.
[0019] Furthermore, compared to pressurized water reactors, boiling water reactors have the challenge that the turbines are contaminated by radioactive materials and the turbine buildings are controlled areas. Synchronous condensers are used by modifying generators installed in turbine buildings, so unless they can be decontaminated or confirmed to be free of radioactive materials, they must be operated in a controlled area. Operating them in a controlled area increases the operational effort, but changing the controlled area to a non-controlled area and operating them there requires initial costs and construction time. Therefore, these issues must be considered while also taking into account the operation period of the synchronous condenser. In addition, it is highly likely that some of the turbines will need to be removed to use a synchronous condenser, but because the turbines in boiling water reactors are contaminated, the modification must be carried out using a construction method that suppresses the dispersion of radioactive materials.
[0020] Therefore, an object of the present invention is to create a process schedule that includes a modification process and an operation process of a synchronous phase condenser that are suitable for a customer when modifying a generator of a nuclear power plant that is to be decommissioned into a synchronous phase condenser. [Means for solving the problem]
[0021] In order to solve the above-mentioned problems, the generator synchronous phase modifier conversion schedule creation system of the present invention is characterized by having a memory unit that stores information on whether each piece of equipment that constitutes a generator of a decommissioning plant of a nuclear plant is necessary for decommissioning work and information on the planned period for using the generator as a synchronous phase modifier, an input unit into which customer requests regarding the conversion of the generator into a synchronous phase modifier are input, and a schedule creation unit that uses the information stored in the memory unit to create a schedule that includes a process for converting the generator into a synchronous phase modifier in accordance with the customer requests input into the input unit.
[0022] The method for creating a schedule for converting a generator into a synchronous phase modifier of the present invention is characterized in that it executes the steps of: a memory unit storing information on whether each piece of equipment that constitutes a generator of a decommissioning plant of a nuclear power plant is necessary for decommissioning work, and information on the planned period for using the generator as a synchronous phase modifier; an input unit accepting input of customer requests regarding the conversion of the generator into a synchronous phase modifier; and a schedule creation unit using the information stored in the memory unit to create a schedule that includes a process for converting the generator into a synchronous phase modifier in accordance with the customer requests inputted to the input unit. Other means will be described in the description of the embodiment of the invention. Effect of the Invention
[0023] According to the present invention, when converting a generator of a nuclear power plant to be decommissioned into a synchronous phase condenser, it is possible to create a process schedule including a conversion process and an operation process of the synchronous phase condenser that are suitable for the customer. [Brief description of the drawings]
[0024] [Figure 1] FIG. 2 is a block diagram showing a schedule proposal server according to the embodiment; [Diagram 2] FIG. 2 is a hardware configuration diagram of a schedule proposal server. [Diagram 3] 13 is a flowchart of a process for proposing a synchronous modifier conversion schedule for a generator of a decommissioned plant. [Figure 4] FIG. 1 is a diagram showing an example of a decommissioning schedule for a nuclear power plant. [Diagram 5] FIG. 2 is a diagram showing the relationship between the decommissioning schedule and the equipment configuration of a nuclear power plant. [Figure 6] FIG. 2 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous modifier according to the first embodiment. [Figure 7] FIG. 11 is a diagram showing an arrangement of equipment inside a turbine building for synchronous modifier according to a second embodiment. [Figure 8] FIG. 11 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous modifier according to the third embodiment. [Figure 9] FIG. 13 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous phase modifier according to the fourth embodiment. [Figure 10] FIG. 13 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous modifier according to the fifth embodiment. [Figure 11] FIG. 13 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous phase modifier according to the sixth embodiment. [Figure 12] FIG. 13 is a diagram showing an arrangement of equipment inside a turbine building related to the synchronous phase modifier according to the seventh embodiment. [Figure 13] 23 is a flowchart of a process proposal process according to the eighth embodiment. [Figure 14] 13 is a flowchart of a process proposal process according to the ninth embodiment. [Figure 15] 23 is a flowchart of a process proposal process according to a tenth embodiment. [Figure 16] 23 is a flowchart of a generator number proposal process for a generator to be converted into a synchronous phase modifier according to the eleventh embodiment. [Figure 17] 23 is a flowchart of a process proposal process according to a twelfth embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0025] Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. When modifying a generator at a decommissioning plant into a synchronous phase condenser, the period during which the generator will be operated as a synchronous phase condenser is considered, and a modification schedule for each piece of equipment in the synchronous phase condenser is created in accordance with customer requests (cost reduction, improved synchronous phase condenser performance, etc.) using information on whether each piece of equipment used by the synchronous phase condenser is necessary for the decommissioning work during that period, and information on the planned period for which it will be used as a synchronous phase condenser.
[0026] A first embodiment of a synchronous modifier for a generator in a decommissioned plant, which is one of the preferred embodiments for achieving this object, will be described with reference to Figures 1 to 6. In this embodiment, a synchronous modifier for a generator in a boiling water reactor will be described as an example, but the present invention can also be applied to a pressurized water reactor, except for the problem of contaminated turbines and turning controlled areas into uncontrolled areas.
[0027] FIG. 1 is a block diagram showing a schedule proposal server 30 according to the present embodiment. This schedule proposal server 30 is a computer, and includes an input unit 31, a schedule creation unit 32, a generator selection unit 33, and a storage unit 34. The schedule proposal server 30 constitutes a synchronous phase modifier conversion schedule creation system that creates a schedule (schedule) including modification processes and operation processes for each device when converting a generator into a synchronous phase modifier in accordance with customer requests. This allows the customer to appropriately operate a synchronous phase modifier that has been appropriately converted.
[0028] The input unit 31 is, for example, a keyboard or a mouse, and receives customer requests indicating high-priority items to be achieved by converting the generator into a synchronous phase modifier. The customer requests include any one of the following: reduction in initial costs, reduction in operating costs, improvement in the performance of the synchronous phase modifier, improvement in convenience, ease of explanation to surrounding residents, and minimization of future waste.
[0029] The schedule creation unit 32 is a functional unit having a function of creating a schedule, and is realized, for example, by a CPU (Central Processing Unit) executing a schedule creation program (not shown). The schedule creation unit 32 creates a schedule including a process for modifying the generator to a synchronous phase modifier based on one or more of the future development status of the power system, the power source introduction plan, the utilization status of the generator proposed to be modified to a synchronous phase modifier as a power plant, and the condition of the generator assumed from the maintenance data or the status data.
[0030] The generator selection unit 33 is a part that selects a generator to be retrofitted to a synchronous phase modifier, and is embodied, for example, by a CPU executing a generator selection program. The generator selection unit 33 is a selection unit that determines the number of generators in the decommissioning plant that need to be retrofitted to a synchronous phase modifier through system analysis, and selects a generator that is appropriate for retrofitting as a synchronous phase modifier, taking into consideration the control width and speed of reactive power and operational needs.
[0031] The storage unit 34 is a large-capacity storage device such as an HDD (Hard Disk Drive), and stores generator configuration information 341 and planned utilization period information 342. The generator configuration information 341 is information on whether each device constituting the generator of the decommissioning plant of the nuclear plant is necessary for the decommissioning work. The planned utilization period information 342 is information on the planned period for using the generator as a synchronous modifier.
[0032] FIG. 2 is a diagram showing the hardware configuration of the schedule proposal server 30. As shown in FIG. A computer 900 such as the schedule proposal server 30 has a CPU 901 , a RAM (Random Access Memory) 902 , a ROM (Read Only Memory) 903 , a HDD 904 , a communication interface 905 , an input / output interface 906 , and a media interface 907 .
[0033] The communication interface 905 is connected to an external communication device 915. The input / output interface 906 is connected to an input / output device 916. The media interface 907 reads and writes data from a recording medium 917. Furthermore, the CPU 901 controls each processing unit by executing a program loaded into the RAM 902. This program can also be distributed via a communication line, or recorded on a recording medium 917 such as a CD-ROM and distributed.
[0034] FIG. 3 is a flowchart of a proposed process for converting generators in decommissioned plants into synchronous modifiers. When the process starts, the input unit 31 receives input of customer requests such as reduction in initial costs, reduction in operating costs, improvement in the performance of the synchronous modifier, and improvement in convenience (step S10). The schedule creation unit 32 determines the period for which the synchronous modifier will be used (step S11). The schedule creation unit 32 determines how long the synchronous modifier can be used in the future based on the future development status of the power system, the power source introduction plan for renewable energy and the like, and the status of the generator to be remodeled. Then, the schedule creation unit 32 estimates the decommissioning process during the utilization period (step S12). For example, consider a case where there is a short-term shortage of reactive power due to the decommissioning of a nuclear power plant, but there is a plan to develop the power system after that, and it is expected that the synchronous phase condenser will no longer be needed. The schedule creation unit 32 determines the period until the synchronous phase condenser becomes unnecessary as the period for which it will be used as a synchronous phase condenser.
[0035] Furthermore, when there is a plan to introduce power sources such as renewable energy, the tendency for reactive power to be insufficient increases. In this case, the schedule creation unit 32 refers to the power system development plan and determines to extend the period for which the device is used as a synchronous modifier in accordance with the plan to introduce power sources such as renewable energy.
[0036] Next, the schedule creation unit 32 compares the convenience, etc., of updating the generator with the convenience of using the original generator (step S13). If updating the generator is more convenient (Yes), the schedule creation unit 32 proceeds to step S14, adds a step of updating the generator, and proceeds to step S15. If updating the generator is less convenient (No), the schedule creation unit 32 proceeds to step S15. The generator used as a synchronous phase modifier has been used as a generator in a nuclear power plant until now, and although it has been regularly maintained, it has deteriorated to some extent with time. Therefore, the schedule creation unit 32 may determine the period for which the generator is used as a synchronous phase modifier depending on the condition of the generator at the stage of conversion to a synchronous phase modifier.
[0037] The limit on the service life due to aging can be extended by overhauling the generator (rewinding the stator winding and rotor winding, etc.), but this is very costly. Therefore, it is necessary to compare the effect of extending the service life with the cost involved and decide to what extent to overhaul the generator. If rewinding is performed, modifications can be made accordingly, such as changing the winding method to one that allows for a wider control range of reactive power.
[0038] Then, in step S15, the process schedule creation unit 32 creates an optimal process schedule including the process of modifying the generator to a synchronous phase modifier and the operation process, and then ends the processing in FIG.
[0039] FIG. 4 is a diagram showing an example of a decommissioning schedule for a nuclear power plant. Here, we estimate the decommissioning cost of the decommissioning plant that will occur while it is operating as a synchronous condenser. The decommissioning cost is divided into four stages, each lasting about 10 years.
[0040] The first phase is the preparation period for the dismantling works, which corresponds to 10 years from the start of decommissioning. The second phase involves the dismantling and removal of the reactor body and surrounding equipment, and corresponds to 10 to 20 years after the start of decommissioning.
[0041] The third stage is the period in which the reactor body and other components will be dismantled and removed, which corresponds to 20 to 30 years after the start of decommissioning measures. The fourth stage is the period in which buildings etc. will be dismantled and removed, which corresponds to 30 to 40 years after the start of decommissioning.
[0042] The fourth phase will be completed approximately 40 years after the plant is decommissioned, and the plant will be returned to a vacant lot. Decommissioning procedures that are particularly relevant to synchronous condensers include the removal of nuclear fuel materials, the dismantling and removal of equipment within the controlled area (other than the reactor itself), the dismantling of buildings, etc., and the dismantling and removal of equipment outside the controlled area.
[0043] The removal of nuclear fuel material refers to the movement of spent fuel. Immediately after the nuclear power plant is shut down for decommissioning, the spent fuel is in the reactor pressure vessel. After that, as the cooling of the spent fuel progresses, the spent fuel is moved to the spent fuel pool. At this stage, the equipment for cooling the spent fuel needs to be maintained, so the power supply system is also required to be highly reliable. Therefore, the extent to which the power supply system can be rationalized is limited. After that, as the cooling of the spent fuel progresses further in the spent fuel pool, the spent fuel is stored in a cask and removed. Once the spent fuel is removed, the equipment related to fuel cooling becomes unnecessary, so the auxiliary equipment and power supply system that support it can be significantly rationalized. These things occur during the period up to the second stage. In particular, this system determines the rationalization of the auxiliary equipment and power supply system depending on how long the auxiliary equipment and power supply system will be used after the fuel is removed.
[0044] From the second stage of decommissioning, the dismantling and removal of the facilities in the controlled area, except for the reactor itself, will begin. Among the facilities to be dismantled and removed, the facility related to the synchronous phase modifier is the central control room. The generators used for the synchronous phase modifiers can essentially be controlled from the central control room. Therefore, it is recommended that the control panels for the electric motors (described below) required for use as synchronous phase modifiers should also be installed and operated in the central control room. If the synchronous phase modifiers are to be operated up to the second stage, the plant operator should build a new control room at this time so as not to affect the removal of the central control room. However, since there is a high possibility that operation as a synchronous phase modifier will be hindered during the period in which the new control room is being constructed, a process of setting up a separate control room in advance at the time of conversion to a synchronous phase modifier will enable rational operation.
[0045] In the fourth stage of decommissioning, the dismantling of all buildings will begin, and at the end of the fourth stage, all equipment as a nuclear power plant will be removed. Since the turbine building containing the synchronous condenser will also be dismantled and removed, for example, if the synchronous condenser is to be operated until the fourth stage, it is advisable to move the generator used as the synchronous condenser to a separately constructed building.
[0046] Furthermore, in order to complete the dismantling and removal of the turbine building at the end of the fourth stage, it is desirable to have a process in which the equipment in the turbine building that is not required as a synchronous phase modifier is sequentially removed while it is being operated as a synchronous phase modifier.
[0047] Dismantling and removal of facilities outside the controlled area will begin with the first phase. Among them, the main transformer required as a synchronous phase modifier will be removed early in the first phase. Therefore, if it is to be used as a synchronous phase modifier, it is desirable to complete the study before the first phase begins.
[0048] 5 is a diagram showing the relationship between the decommissioning schedule and the equipment configuration of a nuclear power plant. This schedule is proposed by, for example, the schedule proposal server 30 in FIG. From the customer's perspective, it is desirable to minimize investment in the first stage. From the customer's perspective, it is desirable to minimize total costs and improve operability in the second and third stages. And it is desirable to return the site to a vacant lot in the fourth stage. The schedule proposal server 30 proposes remodeling and operation processes based on the customer's perspective in each of these stages.
[0049] The schedule proposal server 30 proposes a state confirmation process for the generator in the first stage, and then proposes a stator rewinding process in the second to fourth stages, and it is desirable to increase the reactive power control range and speed. It is desirable that the schedule proposal server 30 proposes a minimum remodeling process for peripheral equipment in the first stage, and then proposes equipment replacement processes in the second to fourth stages.
[0050] It is desirable that the schedule proposal server 30 proposes a minimum remodeling process for the power generation facility in the first stage, a partial air-cooling process in the second stage, and a removal process from the seawater system by full air-cooling in the third and fourth stages. The schedule proposal server 30 proposes a process for using the power source almost as it is in the first stage. Then, in the second stage and after, the schedule proposal server 30 proposes a process for reducing the load on the reactor side due to the transfer of fuel (reduction in the fuel cooling equipment).
[0051] Regarding the control system, the schedule proposal server 30 proposes an operation in which the control system is controlled from a central control room in the first stage. Then, in the second to fourth stages, the schedule proposal server 30 proposes any one of a process of making a part of the turbine building an uncontrolled area, a process of making the whole area an uncontrolled area and using it as a control room, and an operation process of controlling the whole area from a remote location via a network. Regarding the situation inside the turbine building, the schedule proposal server 30 proposes a process for temporarily storing the turbine removed in the first stage. Then, in the second stage, the schedule proposal server 30 proposes a process for making part of the turbine building a non-controlled area. In the third and fourth stages, the schedule proposal server 30 proposes a process for previously removing equipment that is not required for operation as a synchronous modifier.
[0052] 5 is an example, and it is not necessary to strictly follow this. The final modification method and scope will be determined after evaluating the total cost and listening to the customer's requests. Each equipment configuration will be described in detail in each embodiment.
[0053] In this embodiment, an example of the equipment configuration is shown for the case where the period during which the synchronous condenser is operated is the first stage of the above-mentioned decommissioning stages, and the spent fuel is in the reactor pressure vessel or the spent fuel pool. First, the main equipment required for operating a nuclear power plant to be decommissioned as a synchronous condenser is listed below, and the modification process and operation process for each piece of equipment are described.
[0054] Generator ·Stator cooling water system · Motor for driving the gas-powered synchronous condenser generator and inverter for the motor · Generator seal oil system Turbine lubricating oil system ·Synchronous condenser drive motor (driver) and drive motor inverter ·Excitation device Main transformers and other electrical equipment Turbine auxiliary cooling water system and seawater system ·Compressed air system for instrumentation Turbine building ventilation and air conditioning system ·Pure water supplementary water system -Drainage system inside the turbine building, drainage treatment system
[0055] Dynamo As for the generator, the most basic case is to use the generator that was operated as a nuclear power plant as it is. The real power and reactive power that the generator can output are determined by the output capability curve, and the output capability curve of the generator is determined by the winding shape of the generator. A generator used for power generation is usually wound in a way that allows it to output more real power than reactive power. Therefore, when rewinding or replacing the winding of the generator, it is acceptable to change the winding shape to one that allows it to output more reactive power. However, since rewinding or replacing is expensive, if the period of use as a synchronous phase modifier is limited to the first stage, it is reasonable to use the generator as it is in order to reduce the initial cost and total cost.
[0056] 《Stator cooling water system》 As for the stator cooling water system, when it is operated as a synchronous phase modifier, the heat loss from the stator is 50% or less. In general nuclear power plants, two stator cooling pumps (one is a spare) are often operated, accounting for 10% of the total, so in such a plant, for example, if only the first stage is used, only one of the pumps can be operated and the other can be decommissioned. Also, if the cost of decommissioning the stator cooling pumps is high, they can be kept in operation.
[0057] 《Gas Generator》 The generator gas system is composed of a motor for driving the synchronous phase modifier and an inverter for the motor. The heat loss of the rotor remains the same even when it is operated as a synchronous phase modifier, so it is used as is. In nuclear power plants, the rotor and stator core of the generator are cooled by hydrogen, and the generator gas system is responsible for supplying and sealing the hydrogen.
[0058] <Generator seal oil system> It is reasonable to continue using the generator seal oil system as is, regardless of the stage of decommissioning that it will be used at.
[0059] Turbine lubricating oil system The oil pump for the turbine lubricating oil system is generally a turbine-driven pump. Since the synchronous phase modifier of this embodiment is operated with the turbine separated (described later), it is necessary to newly install an electric pump for this oil pump.
[0060] <<Synchronous phase modifier drive motor (driver) and drive motor inverter>> The motor (driver) for driving the synchronous phase modifier and the inverter for the drive are necessary to compensate for the loss when used as a synchronous phase modifier, and at start-up, the motor is accelerated to synchronous speed and merged. When using a generator as a synchronous phase modifier, a new motor (driver) for driving the synchronous phase modifier and an inverter for the drive are required. The inverter for the drive is also required to drive this drive. The power supply to this inverter for the drive is supplied by connecting it to the metacla in the turbine electrical equipment room. If there is a margin in the capacity of the metacla, there is no need to install a new power supply panel, but if there is a shortage, a new power supply panel is required. It is necessary to proceed with the connection to the power supply panel that will remain until the end of the utilization phase, and proceed with the selection of the power supply panel that will remain until the end and the power supply to the drive from there (design of the electrical circuit, cost, etc.). This is the same for all decommissioning stages. It is also important to design appropriately to match the existing electrical circuits.
[0061] In addition, cooling water and lubricating oil are also required for the drive unit and inverter, but since the amount of cooling water and lubricating oil required by the generator itself is significantly less than that required by the generator itself, it is reasonable to supply them by branching them off from the cooling water supply system and lubricating oil supply system for the main unit. The inverter may be air-cooled.
[0062] 《Excitation device》 Regarding the exciter, it is possible to improve the reactive power control width and control speed by modifying it. In other words, the schedule creation unit 32 creates a schedule including a process for changing the control method of the exciter. However, when only the first stage is used as a synchronous phase modifier, it is reasonable to use the excitation device as it is.
[0063] Main transformers and other electrical equipment Regarding the main transformer and other electrical equipment, it may be possible to change the cooling method, but if use is limited to the first stage, it is reasonable to continue using them as they are.
[0064] <Turbine auxiliary cooling water system and seawater system> Regarding the turbine auxiliary cooling water system and seawater system, the thermal load will decrease (to about half) if the system is converted to a synchronous condenser, so these can be rationalized. However, if only the first stage is used, no major modifications will be required, and since the turbine auxiliary cooling water system and seawater system are often composed of multiple systems, it is desirable to operate them by using only a portion of these systems.
[0065] Compressed air system for instrumentation In a typical design, the instrumentation compressed air system receives cooling water from the reactor's auxiliary cooling water system (reactor auxiliary cooling water system). Since the reactor's auxiliary cooling water system is necessary for the operation of the equipment for cooling the spent fuel, if only the first stage is used, the reactor's auxiliary cooling water system will remain in operation. Therefore, it is reasonable to use the instrumentation compressed air system as is. Conversely, if the instrumentation compressed air system is to be reused as existing equipment, the reactor auxiliary cooling water system will be excluded from the equipment that can be degenerated.
[0066] In other words, the schedule creation unit 32 in FIG. 1 creates a schedule including a process for reusing the power supply system, lubrication device, and cooling device of the generator as the power supply system, lubrication device, and cooling device of the synchronous phase modifier, with regard to the auxiliary equipment and power supply system required for the synchronous phase modifier.
[0067] <Turbine building ventilation and air conditioning system> The ventilation and air conditioning system for the turbine building needs to have the function of ventilating the controlled area and maintaining negative pressure when the turbine building is used as a controlled area. Since making the turbine building a non-controlled area requires cost and construction time, it is reasonable to use it as it is when using it as a synchronous condenser only in the first stage.
[0068] 《Pure water supply system》 A pure water make-up water system is necessary for filling the system with water. It is possible to change to a filter method for pure water production, but the decision is made after comparing the cost of modifications. This is the same regardless of the stage at which the system is operated.
[0069] <Drainage system and drain treatment system inside the turbine building> The drainage system and drain treatment system inside the turbine building are necessary for drainage during equipment inspections, and it is desirable to use them as they are.
[0070] First Embodiment Based on the above, the device layout and modification method according to the first embodiment of the present invention will be described. The work to convert the reactor to a synchronous condenser is carried out inside the turbine building 1. If the conversion target is a boiling water reactor, this turbine building 1 is a controlled area where there is a risk of radiation exposure. Lifting the controlled area requires time and cost for decontamination and radiation level checks, so if only the first stage of use is involved, it is reasonable to use the building as a controlled area. It is reasonable to set up a command console in the vacant space in the central control room to carry out monitoring and control.
[0071] FIG. 6 is a diagram showing the arrangement of equipment in the turbine building 1 regarding the synchronous phase modifier according to the first embodiment. In a typical large nuclear power plant, the turbines are composed of one high-pressure turbine 14, three low-pressure turbines A-train 13, a low-pressure turbine B-train 12, and a low-pressure turbine C-train 16. All of these turbines are connected to the same generator drive shaft 7 and rotate the generator 5 together. Here, the plant operator removes the low-pressure turbine C-train 16 that is closest to the generator 5. This separates the turbine from the generator 5. Thereafter, the plant operator levels the site 6 of the low-pressure turbine C system that was created by removing the low-pressure turbine C system 16, and installs the drive machine 8 and the drive machine inverter 9 at that location.
[0072] In other words, the schedule creation unit 32 in Figure 1 creates a schedule that includes a process of removing the low-pressure turbine C system 16 in the system adjacent to the generator 5 and installing the driving machine necessary for operation as a synchronous modifier in the removed site.
[0073] The driver 8 is connected to the remaining generator drive shaft 7, and compensates for the loss that occurs when the generator 5 operates as a synchronous phase modifier. This allows the generator 5 to operate in synchronization with the power grid. The output of the generator 5 is controlled by the exciter 4. The driver inverter 9 is connected to a power supply panel 11 in the turbine building electrical equipment room 2 by driver wiring 10, and supplies power from the power supply panel 11. Since the central control room 22 is already capable of monitoring and controlling the generator 5 and the driver 8, the driver 8 is also controlled by running a control line 17 for driver control to the central control room 22 and providing a control panel in the central control room 22. Digitalization may be promoted by installing an on-site I / O panel for connection with existing equipment.
[0074] Regarding the control method, it is not realistic to transmit all information about grid faults to the control console of the synchronous modifier. Therefore, the most realistic configuration is to receive operation commands from the central load dispatching center via the control centers of each power source. In this case, for cyber security reasons, it is necessary to use a dedicated line for the operation commands from the central load dispatching center or to install a firewall. This is the same for the following embodiments.
[0075] The removed low-pressure turbine C system 16a is contaminated by radioactive materials in a boiling water reactor, so it is moved to and stored in a part of the turbine building 1. A space is provided in the turbine building 1 for temporarily storing turbines that are removed during periodic inspections, so it is desirable to temporarily store it in that space. This makes it unnecessary to reconsider the temporary storage location and floor load of the low-pressure turbine C system 16a.
[0076] Although the removed low-pressure turbine C system 16a is contaminated, the radiation dose around it is not so high that it does not need to be sealed in principle. However, in order to minimize the radiation dose to which the operators and workers who enter the turbine building 1 are exposed, it is desirable to shield the removed low-pressure turbine C system 16a with concrete blocks or the like.
[0077] In a pressurized water reactor, the turbine and condenser are not contaminated, so they may be carried out of the turbine building 1 through the large item entrance 3 without being temporarily stored inside the turbine building 1. In addition, at a site where multiple reactors share a controlled area such as a rad, the removed low-pressure turbine C system 16a of the reactor that will be converted into a synchronous phase modifier may be carried out to the turbine building 1 of the reactor that will not be converted into a synchronous phase modifier. In that case, the low-pressure turbine C system 16a can be decontaminated, dismantled and removed at the destination in conjunction with the decommissioning of the reactor that will not be converted into a synchronous phase modifier.
[0078] Furthermore, in boiling water reactors, turbines are contaminated, and contaminants are dispersed when the turbines are removed. It is necessary to minimize the increase in new contaminants. Therefore, the opening left after the removal of the low-pressure turbine C series 16 must be closed with a concrete plug, or a combination of H-shaped steel and steel plates. Also, measures such as caulking are required to prevent the spread of contamination from the condenser side. A combination of H-shaped steel and steel plates is sufficient if only supporting the weight of the drive unit 8, but if anchors are used to secure the drive unit 8, it is preferable to close it with a concrete plug (fabricated outside in advance and brought in through the large item entrance 3).
[0079] That is, when creating the turbine removal process or the turbine blade removal process, the process schedule creation unit 32 in FIG. 1 assumes that a construction method that prevents scattering of radioactive materials is used.
[0080] Second Embodiment The following describes the equipment layout and modification method of the second embodiment of the present invention. As in the first embodiment, this embodiment also shows an example of the equipment configuration when only the first stage of the decommissioning stage is planned to be operated and the spent fuel is in the reactor pressure vessel or the spent fuel pool. FIG. 7 is a diagram showing the arrangement of equipment in the turbine building 1 regarding the synchronous phase modifier according to the second embodiment.
[0081] In the first embodiment, the low pressure turbine C system 16 was removed, but in the second embodiment, the plant operator does not remove the low pressure turbine C system 16, but installs the driver 8 and the driver inverter 9 on the opposite end of the turbine to the side connected to the generator 5. Then, the plant operator connects the driver 8 to the generator drive shaft 7 through the connection shaft 15. The driver 8 compensates for the loss, and the generator 5 is operated as a synchronous phase modifier, but since the loss due to the windage loss of the turbine is too large in this state, all the blades of each turbine are removed and only the generator drive shaft 7 is rotated. In this case, since the mass of the generator drive shaft 7 is large, the inertia that can be provided to the power system can be made larger than that of the first embodiment, compared to the first embodiment. In addition, since the generator drive shaft 7 is maintained, the turbine lubricating oil system, which required modification to an electric pump in the first embodiment, does not need to be modified to an electric pump because the generator drive shaft 7 that drives it is maintained. In some cases, modification of the bearing box containing the main oil pump is required.
[0082] In other words, the schedule creation unit 32 in FIG. 1 creates a schedule that includes a process of removing the turbine blades of the generator 5 and installing a driving machine 8 required for operation as a synchronous phase modifier on the end of the turbine shaft that is not connected to the generator 5, or on the end of the generator 5 shaft that is not connected to the turbine.
[0083] Third Embodiment The equipment layout and modification method of the third embodiment of the present invention will be described. As in the first embodiment, this embodiment also shows an example of the equipment configuration when only the first stage of the decommissioning stage is planned to be operated and the spent fuel is in the reactor pressure vessel or the spent fuel pool. Here, only the differences from the first embodiment will be described.
[0084] FIG. 8 is a diagram showing the arrangement of equipment in the turbine building 1 regarding the synchronous phase modifier according to the third embodiment.
[0085] In the first embodiment, the low-pressure turbine C system 16 is removed, but in this embodiment, the plant operator does not remove the low-pressure turbine C system 16. The plant operator removes the exciter 4 on the opposite end to the side where the generator 5 and the generator drive shaft 7 are connected, installs a driver 8 and a driver inverter 9 instead, and connects the driver 8 to the generator 5 through a connection shaft 15. The driver 8 compensates for the loss, and the generator 5 is operated as a synchronous phase modifier, but if this continues, the loss due to the windage loss of the turbine will be too large. Therefore, as in the second embodiment, all the blades of each turbine are removed, and only the generator drive shaft 7 is rotated. In other words, the schedule creation unit 32 in Figure 1 creates a schedule that includes a process of installing a drive machine 8 and a drive machine inverter 9 at the end opposite to the end where the generator 5 and the generator drive shaft 7 are connected, and connecting the drive machine 8 to the generator 5 through a connecting shaft 15.
[0086] In this case, since the mass of the generator drive shaft 7 is large, the inertia that can be provided to the power system can be made larger than that of the first embodiment. In addition, since the generator drive shaft 7 is maintained, the turbine lubricating oil system, which required modification to an electric pump in the first embodiment, does not need to be modified to an electric pump because the generator drive shaft 7 that drives it is maintained. In order to achieve this configuration, it is a condition that the exciter 4 is not on the shaft of the generator 5.
[0087] Fourth Embodiment The equipment layout and modification method of the fourth embodiment will be described. In this embodiment, an example of the equipment configuration is shown in which the synchronous condenser is planned to be operated until the second stage of decommissioning, and the spent fuel is in the reactor pressure vessel or the spent fuel pool.
[0088] FIG. 9 is a diagram showing the arrangement of equipment in the turbine building 1 regarding the synchronous phase modifier according to the fourth embodiment. When operating in the second stage, it is necessary to deal with the abolition of the central control room 22, which may be implemented in the second stage. In order to deal with the abolition of the central control room 22, a synchronous phase condenser control room 19 is provided as a separate building outside the turbine building 1, a synchronous phase condenser control panel 20 is installed therein, and a drive machine control control line 17 and a generator control control line 18 are connected to the control panel, so that the synchronous phase condenser can be monitored and / or controlled. Since the synchronous phase condenser control room 19 is provided outside the turbine building 1, the inside of the turbine building 1 can be operated as a controlled area, and the modification costs can be minimized. Furthermore, if the modification costs are small, this form may also be adopted in the first stage of decommissioning. In other words, the schedule creation unit 32 in FIG. 1 creates a schedule including a process of setting up a synchronous condenser control room 19 as a separate building outside the turbine building 1 and installing a synchronous condenser control panel 20 inside it, and a process of connecting the control line 17 for driving machine control and the control line 18 for generator control to the control panel.
[0089] This configuration may be proposed from the start of operations, or modifications may be proposed when moving from the first to the second stage. Cloud-based monitoring and control (eliminating the need for a control room), which is currently being considered for thermal power plants, may also be considered for proposal, taking into account regulations and costs. Since the spent fuel is in the reactor pressure vessel or the spent fuel pool, the other equipment configurations are the same as in the first embodiment.
[0090] Regarding the arrangement of the driving machine 8, a configuration like the second embodiment or the third embodiment may be proposed. The active power and reactive power that the generator 5 can output are determined by the output capability curve. The output capability curve is determined by the winding shape of the generator 5. A generator used for power generation is usually wound in a way that allows it to output more active power than reactive power. Therefore, when proposing a rewinding or rewinding process, a process of changing the winding shape to one that allows it to output more reactive power may be proposed. Although rewinding or rewinding is costly, if the generator 5 is operated as a synchronous phase modifier in the second stage as well and the total cost can be recovered, a rewinding or rewinding process of the generator 5 may be proposed. In addition, a process of modifying the exciter 4 may be proposed to improve the control width and speed of reactive power.
[0091] At this stage, it is also possible to remove and streamline unnecessary metal cladding and the like from within the turbine building electrical equipment room 2. For this reason, it is desirable to propose a process for connecting the drive wiring 10 to the metal cladding of the power supply panel 11, which is assumed to remain in place. Regarding the ventilation and air conditioning system of the turbine building 1, when the turbine building 1 is used as a controlled area, ventilation and negative pressure maintenance functions for the controlled area are required. In this embodiment, since the turbine building 1 remains a controlled area, these maintenance functions are required.
[0092] Fifth Embodiment The equipment layout and modification method of the fifth embodiment will be described. In this embodiment, an example of the equipment configuration is shown in which the synchronous condenser is scheduled to be operated until the second stage of decommissioning, and the spent fuel is in the reactor pressure vessel or the spent fuel pool.
[0093] FIG. 10 is a diagram showing the arrangement of equipment in a turbine building 1 regarding the synchronous phase modifier according to the fifth embodiment. When operating in the second phase, it is necessary to deal with the possibility of abolishing the central control room, which may be implemented in the second phase. In order to deal with the abolishment of the central control room, the plant operator decontaminates a part of the turbine building 1 or confirms that the radiation dose is lower than the limit value, and establishes a synchronous phase condenser control room 19 inside the turbine building 1. The plant operator installs a synchronous phase condenser control panel 20 inside the synchronous phase condenser control room 19, connects the drive machine control control line 17 and the generator control control line 18 to the control panel, and makes it possible to monitor and / or control the synchronous phase condenser. Since the synchronous phase condenser control room 19 is established inside the turbine building 1, it is possible to operate it as a synchronous phase condenser even if sufficient installation space cannot be secured outside the turbine building 1.
[0094] At this time, the schedule creation unit 32 in FIG. 1 creates a schedule including a process of installing a control panel for the synchronous phase modifier in the turbine building and monitoring and / or controlling the synchronous phase modifier with the control panel.
[0095] This embodiment may be proposed to have this configuration from the beginning of operation, or a process of modification may be proposed at the timing of moving from the first stage to the second stage. As in the fourth embodiment, a process of rewinding or replacing the stator or improving the exciter 4 may be proposed.
[0096] Since the spent fuel is in the reactor pressure vessel or the spent fuel pool, the other equipment configurations are the same as in the first embodiment. Regarding the arrangement of the driving machine 8, a configuration like that of the second or third embodiment may be proposed. Also, a rewinding or rewinding process of the generator 5 may be proposed.
[0097] Regarding the ventilation and air conditioning system for the turbine building 1, if the turbine building 1 is used as a controlled area, ventilation and negative pressure maintenance functions for the controlled area will be required. Since a controlled area remains within the turbine building 1, it is reasonable to use it as is.
[0098] Sixth Embodiment The equipment layout and modification method of the sixth embodiment will be described. In this embodiment, an example of the equipment configuration is shown in which the synchronous condenser is scheduled to be operated until the second stage of decommissioning, and the spent fuel is in the reactor pressure vessel or the spent fuel pool.
[0099] FIG. 11 is a diagram showing the arrangement of equipment in a turbine building 1 regarding the synchronous phase modifier according to the sixth embodiment. When operating in the second stage, it is necessary to deal with the abolition of the central control room, which may be implemented in the second stage. To deal with the abolition of the central control room, the plant operator decontaminates the entire turbine building 1 or confirms that the radiation dose is lower than the limit value. As a result, the plant operator installs a synchronous phase modifier control panel 20 inside the turbine building 1 and connects the drive control line 17 and the generator control line 18 to the control panel, so that the synchronous phase modifier can be monitored and / or controlled. Since the synchronous phase modifier control room 19 is provided inside the turbine building 1, it is possible to operate it as a synchronous phase modifier even if sufficient installation space cannot be secured outside the turbine building 1, as in the fifth embodiment. In addition, since the entire area inside the turbine building 1 becomes a non-controlled area, there is no restriction on the placement of operators. In addition, the removed low-pressure turbine C system 16a may be kept inside the turbine building 1 after being tightly sealed, but in the case of adopting this embodiment, it is more reasonable to decontaminate it and carry it outside or transfer it to another unit that is not in use.
[0100] 1 creates a schedule that includes a process for decontaminating the turbine building 1, which is entirely a controlled area. The schedule creation unit 32 then creates a schedule that includes a process for measuring radiation doses in areas that are to be used as non-controlled areas, and changing part or all of the turbine building 1 into a non-controlled area.
[0101] The interior of the turbine building 1 may be proposed to have this configuration from the start of operation, or a process of remodeling may be proposed at the timing of moving from the first stage to the second stage. Since the spent fuel is in the reactor pressure vessel or the spent fuel pool, the other equipment configurations are the same as in the first embodiment. Also, similar to the fourth embodiment, a process of rewinding or replacing the stator or improving the exciter 4 may be proposed. Regarding the arrangement of the driving machine 8, a configuration like that of the second or third embodiment may be proposed. Also, a rewinding or rewinding process of the generator 5 may be proposed.
[0102] As the turbine building 1 will be an uncontrolled area, there will be no need for a ventilation and air conditioning system for it, except for the capacity required for temperature control of the turbine building 1. If it is not expected that the turbine building 1 will become hot, this ventilation and air conditioning system will not be necessary.
[0103] Seventh Embodiment The equipment layout and modification method of the seventh embodiment will be described. In this embodiment, an example of the equipment configuration is shown in which the synchronous condenser is planned to be operated until the second stage of decommissioning, and the spent fuel is in the reactor pressure vessel or the spent fuel pool.
[0104] FIG. 12 is a diagram showing the arrangement of equipment in the turbine building 1 regarding the synchronous phase modifier according to the seventh embodiment. When operating in the second stage, it is necessary to deal with the abolition of the central control room, which may be implemented in the second stage. In order to deal with the abolition of the central control room, the plant operator installs a partition wall 21 between the generator 5 and the turbine building electrical equipment room 2, which are unlikely to be attached with radioactive materials, in the turbine building 1, and the area where the turbine, which is certainly attached with radioactive materials, is located. Then, the plant operator sets up a synchronous phase modifier control panel 20 inside the side where the generator 5 and the turbine building electrical equipment room 2 are located, as a non-controlled area. Furthermore, the plant operator connects the driving machine control line 17 and the generator control line 18 to the control panel, so that the synchronous phase modifier can be monitored and / or controlled. Since the synchronous phase modifier control room 19 is provided inside the turbine building 1, it is possible to operate it as a synchronous phase modifier even if sufficient installation space cannot be secured outside the turbine building 1, as in the fifth embodiment. In addition, since the entire area inside the turbine building 1 is a non-controlled area, there is no restriction on the placement of operators. In addition, the area of the non-controlled area can be made smaller than that of the fifth embodiment. The removed low-pressure turbine C system 16a may remain in the turbine building 1 since it is placed in a controlled area.
[0105] In other words, the schedule creation unit 32 in Figure 1 creates a schedule that includes a process for decontaminating the turbine building 1, the entire building being a controlled area, or a process for constructing a partition wall 21 to separate the area expected to be contaminated from the rest.
[0106] The interior of the turbine building 1 may be proposed to have this configuration from the start of operation, or a process of remodeling may be proposed at the timing of moving from the first stage to the second stage. Since the spent fuel is in the reactor pressure vessel or the spent fuel pool, the other equipment configurations are the same as in the first embodiment.
[0107] Regarding the arrangement of the driving machine 8, a configuration like that of the second or third embodiment may be proposed. Also, rewinding or replacement of the generator 5 may be proposed. As in the fourth embodiment, rewinding or replacement of the stator of the generator 5 or improvement of the exciter 4 may be proposed.
[0108] Regarding the ventilation and air conditioning system for the turbine building 1, if the turbine building 1 is used as a controlled area, ventilation and negative pressure maintenance functions for the controlled area will be required. Since a controlled area remains within the turbine building 1, it is reasonable to use it as is.
[0109] Eighth Embodiment A modification method of the eighth embodiment will be described. In this embodiment, a proposed example of a process is shown in which the synchronous condenser is planned to be operated until the second stage of the decommissioning stage, and the synchronous condenser is used until the stage where the spent fuel is stored in a cask and transported outside the reactor building.
[0110] FIG. 13 is a flowchart of a process proposal process according to the eighth embodiment. First, the schedule creation unit 32 in Fig. 1 proposes a process for storing the spent fuel in a cask and transporting it outside the reactor building (step S30). When the spent fuel is stored in a cask and transported outside the reactor building, the equipment (auxiliary equipment) related to cooling the spent fuel and the power supply system required to operate that equipment become unnecessary. Since there is no longer a possibility of being involved in cooling the spent fuel, it is no problem if the reliability of the power supply system is reduced to a certain extent. Therefore, the schedule creation unit 32 proposes a process for reducing the number of power supply systems after the process for transporting the spent fuel (step S31).
[0111] Then, the schedule creation unit 32 proposes a process for modifying the cooling system to a simpler one (step S32). This is because cooling of the spent fuel is no longer necessary. Therefore, the process proposed by the schedule creation unit 32 can further streamline the power supply system. Furthermore, since cooling of the spent fuel is no longer necessary, the number of devices that require seawater cooling, including the reactor auxiliary cooling water system, is reduced. Accordingly, the schedule creation unit 32 may propose a process for changing the power supply system devices to air cooling in step S32. By reducing the dependency on seawater cooling, the plant operator can reduce the operating costs of the synchronous condenser and smoothly carry out the subsequent decommissioning measures.
[0112] The schedule creation unit 32 evaluates the cost of rationalization and proposes a process for rationalizing the power system based on the cost during the operation period. One method of rationalization is to reduce the number of systems that have been maintained to cool the spent fuel. It is necessary to optimize the on-site power sources (metal cladding, power center, motor control center) taking into account the results of the necessary auxiliary equipment sorting and identification of the degeneration range (described later) and the decommissioning schedule, and to consider the replacement of the on-site power sources accordingly (drafting a replacement plan that takes into account the decommissioning schedule, the load required for the decommissioning, and the load required for the synchronous condenser).
[0113] The schedule creation unit 32 also proposes a process to reduce the number of power supply panels to be maintained by connecting the power supply panels to which the drive machines are connected to the same power supply panels as the loads that will be maintained until the later stages of decommissioning (step S33).
[0114] Then, the schedule creation unit 32 proposes a process for streamlining the auxiliary equipment (step S34), and ends the process of FIG. 13. Since the auxiliary equipment will no longer require a reactor auxiliary cooling water system, the operation costs can be reduced by streamlining these. However, in many current designs, the cooling of the instrumentation compressed air system is dependent on the reactor auxiliary cooling water system, and in such cases, a design change is required, such as changing the cooling of the instrumentation compressed air system to an air-cooled system, for example. In addition, in line with the fact that the reactor auxiliary cooling water system will no longer be required, it is desirable to further propose a process for degenerating and replacing the turbine auxiliary cooling water system, seawater system, ventilation and air conditioning system, etc., with appropriate ones according to the heat load required as a synchronous condenser.
[0115] Furthermore, in step S32, the schedule creation unit 32 may propose a process for air-cooling the equipment as much as possible to eliminate the need for a seawater system, thereby reducing operational costs and enabling the smooth removal of the seawater system, the removal of which will begin later. This enables the plant operator to smoothly proceed with the subsequent decommissioning measures.
[0116] Regarding the equipment arrangement within the turbine building 1, it is desirable to propose a configuration such as that of the fourth to seventh embodiments, which makes it possible to remove the central control room and enables operation as a synchronous modifier only inside and outside the turbine building 1.
[0117] In other words, the schedule creation unit 32 creates a schedule that includes processes for reducing or modifying the auxiliary equipment and power supply systems required as a synchronous modifier, taking into account the equipment and power supply systems that will become unnecessary as the decommissioning measures on the reactor side progress.
[0118] Ninth Embodiment A modification method according to the ninth embodiment will be described. In this embodiment, a process proposal process will be shown for a case in which a synchronous modifier is scheduled to be operated up to the third stage among the decommissioning stages.
[0119] FIG. 14 is a flowchart of a process proposal process according to the ninth embodiment. In the third stage, the schedule creation unit 32 proposes a process for proceeding with the dismantling and removal of the reactor body (step S40), and proposes a process for removing the seawater cooling system and other systems that were required on the reactor building side (step S41). The schedule creation unit 32 proposes an appropriate reduction and replacement process for auxiliary equipment in accordance with the thermal load required for the synchronous modifier (step S42). At this time, it is particularly desirable to propose a process for replacing the equipment with an air-cooled system rather than cooling using a seawater system. Furthermore, the schedule creation unit 32 also proceeds with streamlining of the power supply system, proposing a process of promoting air-cooling as the cooling required for the power supply system (step S43), and ends the process of FIG.
[0120] It is desirable to propose a configuration such as that of the fourth to seventh embodiments for the equipment layout in the turbine building, which allows the central control room to be removed and allows operation as a synchronous condenser only inside and outside the turbine building. In addition, in the case of operating up to the third stage, in order to hold off on the subsequent decommissioning measures for the turbine building, the schedule creation unit 32 proposes a configuration in which the turbine building is made a non-controlled area as in the sixth embodiment, or most of the turbine building is made a non-controlled area as in the seventh embodiment, and equipment not required for the operation of the synchronous condenser can be carried out and / or removed within the non-controlled area. By implementing this proposal, the plant operator can smoothly proceed with the subsequent decommissioning measures.
[0121] In other words, the schedule creation unit 32 may identify equipment that is not necessary when operating the generator as a synchronous phase modifier, and create a schedule that includes a process for transporting or removing the equipment from the turbine building even during the period when the generator is operated as a synchronous phase modifier.
[0122] Tenth Embodiment A modification method according to the tenth embodiment will be described. In this embodiment, a method for proposing a process in the case where a synchronous condenser is scheduled to be operated up to the fourth stage among the decommissioning stages will be shown.
[0123] FIG. 15 is a flowchart of a process proposal process according to the tenth embodiment. In the fourth stage, it is necessary to complete the decommissioning of all facilities at the end of the stage. Therefore, the schedule creation unit 32 proposes a process for appropriate reduction and / or replacement of the auxiliary equipment in accordance with the thermal load required for the synchronous modifier (step S50). In particular, it is desirable to propose a process for keeping the equipment air-cooled rather than cooling using a seawater system. The schedule creation unit 32 proposes a process for streamlining the power supply system as well (step S51). At this time, it is desirable for the schedule creation unit 32 to propose a process for air-cooling the cooling required for the power supply system together with a process for abolishing or removing the seawater system.
[0124] The schedule creation unit 32 proposes a process for relocating the generator and auxiliary equipment required for operating the generator as a synchronous modifier (step S52), and ends the processing in Fig. 15. This allows the system to be operated independently of the original nuclear power plant, and does not affect the decommissioning measures.
[0125] It is desirable to propose a configuration such as the fourth to seventh embodiments for the equipment layout in the turbine building, which allows the central control room to be removed and allows operation as a synchronous condenser only inside and outside the turbine building. In order to avoid decommissioning of the turbine building during the fourth stage, it is desirable to propose a configuration in which the turbine building is made a non-controlled area as in the sixth embodiment, or in which most of the turbine building is made a non-controlled area as in the seventh embodiment, and equipment not required for operation of the synchronous condenser can be carried out and / or removed within the non-controlled area. This is to allow the plant operator to smoothly proceed with the subsequent decommissioning measures.
[0126] Eleventh Embodiment In nuclear power plants, the capacity and excitation method differ from plant to plant, and often differ from unit to unit even at the same site. In this embodiment, when starting the conversion to a synchronous phase modifier, the number of bases that need to be converted is determined by system analysis taking into account the site conditions and the required reactive power output amount, and the generator to be converted to a synchronous phase modifier is selected taking into account the reactive power control width, speed, and operational needs.
[0127] FIG. 16 is a flowchart of a generator number proposal process for a generator to be converted into a synchronous phase modifier according to the eleventh embodiment. The generator selection unit 33 considers the state of development of the power system, the power source introduction plan, and the like, and obtains the required reactive power output amount and a rough operating location of the synchronous modifier from a system analysis (step S20).
[0128] The generator selection unit 33 selects a plant with a decommissioning plan that matches the selected reactive power output and location (step S21), and determines the number of generators to be retrofitted with synchronous modifiers based on the required reactive power output (step S22).
[0129] Then, the generator selection unit 33 compares the reactive power control width, control speed, ease of operation of the generator, etc. of each unit, and determines the unit to be modified to a synchronous phase modifier (step S23), and then terminates the processing of Figure 16. This unit proposal process allows the plant operator to easily know which unit's generator should be converted to a synchronous modifier. This can also be applied to the first to tenth embodiments.
[0130] Twelfth Embodiment Generally, the maintenance and inspection of generators includes replacing consumable parts such as sealing materials about once every five years, and large-scale construction such as rewinding coils about once during the product's lifespan. In addition, when the generator is in storage, care must be taken to prevent rust, deterioration of resin materials, and malfunction of the rotating body, and care must be taken to use volatile rust inhibitors, store the generator in a dry or water-filled state, and turn the rotating machine periodically. As such, generators to be converted into synchronous phase modifiers have a wide variety of operating and storage histories, so it is necessary to understand the condition of the generator taking such history into consideration before converting it into a synchronous phase modifier.
[0131] FIG. 17 is a flowchart of a process proposal process according to the twelfth embodiment. The schedule creation unit 32 determines whether or not this generator was used until immediately before conversion to a synchronous phase modifier (Step S60). If this generator was used until immediately before conversion to a synchronous phase modifier (Yes), the schedule creation unit 32 proceeds to Step S61, and if this generator was not used for a long period of time, measured in years, until conversion to a synchronous phase modifier (No), the schedule creation unit 32 proceeds to Step S63.
[0132] When using a generator that was in use until just before being converted to a synchronous phase modifier, the operation of the generator was confirmed until just before that. In step S62, the schedule creation unit 32 proposes a maintenance inspection process that is an extension of the previous maintenance inspection plan for this generator, and when it proposes an open inspection process for the generator in conjunction with the work of converting the generator to a synchronous phase modifier (step S62), it ends the processing in Fig. 17. However, if the generator has reached the end of its product life and is to be decommissioned, the schedule creation unit 32 needs to consider whether or not it can be modified to a synchronous phase modifier.
[0133] When using a generator that has not been used for a long period of time, such as years, before being converted into a synchronous phase modifier, the state of the generator during shutdown and storage must also be taken into consideration. In step S63, the schedule creation unit 32 determines that the generator has been stored without maintenance in anticipation of decommissioning, and proposes a process for disassembly and inspection, replacement of expendable parts, and operation testing as much as possible (step S63). In this step S63, the schedule creation unit 32 may create a schedule that includes a process for rewinding or replacing the stator and rotor of the generator to convert it into a synchronous phase modifier.
[0134] Then, a process for open inspection of the generator prior to construction work to convert the generator into a synchronous modifier is proposed (step S64), and a process for inspecting the generator's auxiliary systems is also proposed in a similar manner, and then the processing in Fig. 17 is terminated. This enables the plant operator to determine the necessity of large-scale construction work such as coil rewinding based on the inspection results.
[0135] In other words, the schedule creation unit 32 in FIG. 1 creates a schedule including processes including one or more of inspection, maintenance, and operation check of the generator that is to be modified into a synchronous modifier, based on the operational status of the generator before it was decommissioned.
[0136] Since large-scale construction work requires years from planning to completion, the inspection process for the generator must be considered at the early stage of the plan for converting to a synchronous modifier. These considerations can also be applied to the first to eleventh embodiments.
[0137] Effects of the embodiment According to each of the embodiments described above, the schedule proposal server 30 can propose a schedule including a process of modifying or operating a synchronous modifier to an optimum one for the customer, such as optimizing the total cost.
[0138] <<Variation>> The present invention is not limited to the above-described embodiment, and includes various modified examples. For example, the above-described embodiment has been described in detail to clearly explain the present invention, and is not necessarily limited to those having all of the configurations described. It is possible to replace a part of the configuration of one embodiment with the configuration of another embodiment, and it is also possible to add the configuration of another embodiment to the configuration of one embodiment. In addition, it is also possible to add, delete, or replace a part of the configuration of each embodiment with another configuration.
[0139] The above configurations, functions, processing units, processing means, etc. may be realized in part or in whole by hardware such as an integrated circuit. The above configurations, functions, etc. may be realized by software by a processor interpreting and executing a program that realizes each function. Information such as the program, table, file, etc. that realizes each function can be stored in a recording device such as a memory, a hard disk, or an SSD (Solid State Drive), or in a recording medium such as a flash memory card or a DVD (Digital Versatile Disk).
[0140] In each embodiment, the control lines and information lines are those that are considered necessary for the explanation, and not all control lines and information lines in the product are necessarily shown. In reality, it may be considered that almost all components are connected to each other. [Explanation of symbols]
[0141] 1. Turbine Building 2. Turbine building electrical equipment room 3. Large item entrance 4 Exciter 5. Generator 6. Former site of low pressure turbine series C 7 Generator drive shaft 8. Driving Machine 9. Drive inverter 10. Wiring for drive unit 11 Power panel 12 Low pressure turbine B series 13 Low pressure turbine A series 14 High Pressure Turbine 15 Connecting shaft 16 Low pressure turbine C series 16a Low pressure turbine C series (after removal) 17 Control line for drive control 18 Generator control line 19 Synchronous condenser control room 20 Synchronous condenser control panel 21 Bulkhead 22 Central Control Room 30 Process schedule proposal server (System for creating a process schedule for converting generators into synchronous condensers) 31 Input section 32 Process chart creation department 33 Generator Selection Department (Selection Department) 34 Storage section 341 Generator configuration information 342 Information on planned period of use 900 Computers 901 CPU 902 RAM 903 ROM 904 HDD 905 Communication Interface 906 Input / Output Interface 907 Media Interface 915 Communication Equipment 916 Input / Output Device 917 Recording media
Claims
1. A storage unit that stores information on whether each device constituting a generator of a decommissioning plant of a nuclear power plant is necessary for decommissioning work and information on a planned period for using the generator as a synchronous modifier; an input unit for inputting a customer's request for converting the generator into a synchronous modifier; a schedule creation unit that uses the information stored in the storage unit to create a schedule including a process for modifying the generator into a synchronous modifier in accordance with the customer's request inputted into the input unit; A generator synchronous modifier schedule creation system comprising:
2. The customer's requirements include any one of the following: reduction in initial costs, reduction in operating costs, improvement in the performance of the synchronous condenser, improvement in convenience, ease of explanation to surrounding residents, and minimization of future waste.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
3. a selection unit which determines the number of generators in the decommissioning plant that need to be converted into synchronous condensers by system analysis, and selects a generator suitable for conversion into a synchronous condenser in consideration of the reactive power control width, speed, and operational needs; 2. The generator synchronous modifier schedule creation system according to claim 1, further comprising:
4. The schedule creation unit creates a schedule including a process for modifying the generator to a synchronous phase modifier based on at least one of a future development status of a power system, a power source introduction plan, a utilization status of the generator as a power plant for which a modification to a synchronous phase modifier is proposed, and a condition of the generator assumed from maintenance data or status data.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
5. The process schedule creation unit creates a process schedule including at least one process of inspection, maintenance, and operation check of the generator to be modified as a synchronous phase modifier based on the operating status of the generator before it is discontinued.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
6. the schedule creation unit creates a schedule including a step of removing a turbine of a system adjacent to the generator and installing a driving machine necessary for operation as a synchronous modifier at the site where the turbine was removed.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
7. the process schedule creation unit creates a process schedule including a step of removing turbine blades of the generator, and installing a driving machine required for operation as a synchronous phase modifier on an end of the turbine shaft that is not connected to the generator, or on an end of the generator shaft that is not connected to the turbine.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
8. The process schedule creation unit creates a process schedule including a process of reusing the power supply system, lubrication system, and cooling system of the generator as the power supply system, lubrication system, and cooling system of the synchronous phase modifier, with respect to the auxiliary equipment and power supply system required for the synchronous phase modifier.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
9. The process schedule creation unit creates a process schedule including a process of reducing or modifying the auxiliary equipment and power supply system required as the synchronous modifier, taking into consideration the equipment and power supply system that will become unnecessary as the decommissioning measures on the reactor side progress.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
10. The process schedule creation unit creates a process schedule including a process of rewinding or replacing a stator or a rotor of a generator to modify it into a synchronous phase modifier.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
11. The process schedule creation unit creates a process schedule including a process of changing a control method of an exciter.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
12. the schedule creation unit creates a schedule including a step of identifying equipment that is not required when the generator is operated as a synchronous phase modifier, and removing or removing the equipment from a turbine building even during the period when the generator is operated as a synchronous phase modifier.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
13. The process schedule creation unit creates a process schedule including a process of cooling the auxiliary machinery and the power supply system by an air-cooling method and abolishing or removing the seawater system.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
14. the process schedule creation unit creates a process schedule including a step of installing a control panel for the synchronous phase modifier in a central control room and monitoring and / or controlling the synchronous phase modifier from the central control room; 2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
15. the process schedule creation unit creates a process schedule including a process of installing a control panel for the synchronous phase condenser in a separate building installed outside the turbine building and monitoring and / or controlling the synchronous phase condenser from the separate building.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
16. the process schedule creation unit creates a process schedule including a step of installing a control panel for the synchronous phase condenser in a turbine building and monitoring and / or controlling the synchronous phase condenser with the control panel; 2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
17. the process schedule creation unit creates a process schedule including a process of monitoring and / or controlling the synchronous phase modifier from a remote location via a network; 2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
18. the schedule creation unit creates a schedule including a process for decontaminating a turbine building that is an entirely controlled area, or a process for installing a partition wall to separate an area expected to be contaminated from other areas; 2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
19. the schedule creation unit creates a schedule including a step of measuring a radiation dose in an area to be used as a non-controlled area and changing a part or the entirety of a turbine building into a non-controlled area; 2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
20. The process schedule creation unit creates a process for removing a turbine or a process for removing turbine blades on the premise that a construction method that prevents scattering of radioactive materials is used.
2. The system for creating a schedule for converting a generator into a synchronous phase modifier according to claim 1.
21. A step in which a memory unit stores information on whether each device constituting a generator of a decommissioning plant of a nuclear plant is necessary for decommissioning work and information on a planned period for using the generator as a synchronous modifier; An input unit receives an input of a customer's request for converting the generator into a synchronous modifier; a process schedule creation unit creating a process schedule including a process of modifying the generator into a synchronous phase modifier in accordance with the request of the customer inputted into the input unit, using the information stored in the storage unit; A method for creating a schedule for converting a generator into a synchronous phase modifier, comprising the steps of:
Citation Information
Patent Citations
Synchronous phase modifying equipment
JP1991082339A
System for utilizing nuclear power generation steam turbine
JP2015148221A
Compressed-air electricity generation method for nuclear power plant wasted or being halted