Monitoring device, monitoring method, and program
The monitoring device adjusts monitoring intervals based on server failure rates influenced by hardware, time, and environment, optimizing detection efficiency and reducing network load.
Patent Information
- Application Number
- JP2020199275
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-12-01
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2040-12-01
AI Technical Summary
Existing server monitoring technologies do not adequately consider the impact of operating environments such as temperature and humidity on failure rates, leading to inefficient monitoring and potential delays in failure detection.
A monitoring device that acquires individual failure rates based on hardware, operating time, and environmental conditions to determine tailored monitoring intervals for each server, adjusting intervals based on the calculated failure rates to optimize detection efficiency.
Enhances monitoring efficiency by reducing network load and detecting failures promptly, thereby maintaining system stability and service quality.
Smart Images

Figure 0007604858000001 
Figure 0007604858000002 
Figure 0007604858000003
Abstract
Description
[Technical field]
[0001] The present disclosure relates to monitoring of servers. [Background technology]
[0002] Various services provided via the Internet are realized by running servers that have installed programs on computers. However, computers do not always operate stably, and unexpected problems can cause servers to go down or slow down. In order to provide stable services, it is important to constantly monitor servers and take prompt action when a problem occurs.
[0003] In order to detect the occurrence of a fault in an electronic device, the electronic device is monitored through a network. Patent Document 1 discloses that a maintenance management target device such as a personal computer or a server, or a monitoring device, notifies the occurrence of a fault in the maintenance management target device. Patent Document 2 discloses that a management target device such as a printer is monitored at a predetermined monitoring interval according to the usage status.
[0004] As a technology related to the present disclosure, Patent Document 3 discloses an operation and maintenance support system that determines whether or not there is an abnormality in equipment by taking into account information on the cumulative operating status of the equipment and parameters specific to each piece of equipment. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] JP 2016-081374 A [Patent Document 2] JP 2014-053027 A [Patent Document 3] JP 2010-271905 A Summary of the Invention [Problem to be solved by the invention]
[0006] The failure rate of electronic devices varies depending on the operating environment, such as temperature, humidity, etc. However, in Patent Document 2, the monitoring of the electronic devices is not controlled with the operating environment of the devices taken into consideration.
[0007] The present disclosure aims to provide a monitoring device and the like that controls monitoring taking into account the operating environment of a server. [Means for solving the problem]
[0008] The monitoring device according to the present disclosure includes an acquisition means for acquiring an individual failure rate caused by the hardware, operating time, and operating environment of each server, and a determination means for determining a monitoring interval for the server based on the individual failure rate.
[0009] The monitoring method according to the present disclosure obtains an individual failure rate caused by the hardware, operating time, and operating environment of each server, and determines a monitoring interval for the server based on the individual failure rate.
[0010] A program according to the present disclosure causes a computer to execute a process of acquiring an individual failure rate caused by the hardware, operating time, and operating environment of each server, and determining a monitoring interval for the server based on the individual failure rate. Effect of the Invention
[0011] According to the present disclosure, monitoring can be controlled taking into account the operating environment of the server. [Brief description of the drawings]
[0012] [Figure 1] 1 is a schematic diagram showing a configuration of a maintenance management system according to a first embodiment. [Diagram 2] 3 is a hardware schematic diagram of the server 300. FIG. [Diagram 3] FIG. 2 is a sequence diagram showing an example of the operation of the maintenance management system. [Figure 4] 1 is a graph illustrating an example of a relational model. [Diagram 5] 13 is a graph showing another example of a relational model. [Figure 6] FIG. 11 is a block diagram showing the configuration of a monitoring device 100 according to a second embodiment. [Figure 7] 2 is a schematic diagram showing an example of the arrangement of a calculation device 120. FIG. [Figure 8] 13 is a graph showing another example of the relationship between the individual failure rate and the determined monitoring interval. [Figure 9] 10 is a flowchart showing an example of the operation of the monitoring device 100 according to the second embodiment. [Figure 10] FIG. 5 is a block diagram showing an example of the hardware configuration of a computer 500. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0013] In this disclosure, a monitoring device that monitors a plurality of electronic devices constituting a large-scale system for maintenance management will be described. As an example of the electronic device to be monitored, a monitoring device that monitors a server will be described in the following embodiment with reference to the drawings. However, the monitored device may include electronic devices other than servers.
[0014] [First embodiment] (composition) 1 is a schematic diagram showing the configuration of a maintenance management system according to a first embodiment. The maintenance management system includes a monitoring device 100 and one or more server racks 200 (200_1, ..., 200_y) to be monitored. Each server rack 200 includes one or more servers 300 (300_1, 300_2, ..., 300_x) and a temperature sensor 400. The monitoring device 100 is communicatively connected to each server 300 and temperature sensor 400 via a network 010. The number of servers 300 in each server rack 200 can be changed arbitrarily.
[0015] The monitoring device 100 monitors whether or not a failure has occurred in the server 300. In the first embodiment, the monitoring device 100 includes an acquisition unit 101, a calculation unit 102, and a determination unit 103.
[0016] The acquiring unit 101 acquires hardware monitoring information, operation information, and information on the operating environment for each server 300. The hardware monitoring information indicates hardware monitoring data for determining abnormal trends of each component inside the server 300. The operation information indicates the operating status of the server 300, such as the operating time from initial placement or the number of years of use. The information on the operating environment is information indicating, for example, the temperature or humidity inside the server rack 200, or the temperature of the server 300. Furthermore, the acquiring unit 101 acquires the individual failure rate based on the hardware, operation information, and operating environment of each server 300 calculated by the calculating unit 102.
[0017] The calculation unit 102 calculates an individual failure rate P for each server 300 based on the hardware monitoring information, the operation information, and the information on the operating environment acquired by the acquisition unit 101. The calculation of the individual failure rate P will be described later.
[0018] The determining unit 103 determines the monitoring interval for each server 300 based on a relational model between the individual failure rate of each server 300 and the monitoring interval. The monitoring interval is a time interval from when the monitoring device 100 executes a fault monitoring process for the server 300 until it executes the monitoring process again. As the monitoring process, the monitoring device 100 may, for example, send an input / output request to the server 300 and check whether the response time to the input / output request is within a normal range. Alternatively, as the monitoring process, the monitoring device 100 may check whether the monitoring data of each component of the server 300 is within a normal range.
[0019] The relational model between the individual failure rate and the monitoring interval may show a decreasing trend of the monitoring interval corresponding to an increase in the individual failure rate. The relational model may be represented by a relational equation between the individual failure rate and the monitoring interval, or may be represented by a table. The relational model may be obtained by machine learning using the network load as the objective variable and, for example, the failure rate, the monitoring interval, the number of servers, and the network bandwidth as the explanatory variables.
[0020] In the first embodiment, the temperature sensor 400 measures the temperature inside the server rack 200. The temperature sensor 400 transmits the measured temperature to the monitoring device 100 as information on the operating environment of the servers 300_1, . . . , 300_x in the server rack 200.
[0021] When the temperature of each server 300 is used as the information regarding the operating environment, one temperature sensor 400 may be installed for each server 300. The temperature sensor 400 transmits the measured temperature of each server to the monitoring device 100.
[0022] Other sensors may be installed in the server rack 200 depending on the type of information about the operating environment acquired by the acquisition unit 101. When humidity is used as the information about the operating environment, the description of the temperature sensor 400 in the following description may be replaced with a humidity sensor.
[0023] 2 is a schematic diagram of the hardware of the server 300. The server 300 includes a central processing unit (CPU) 301, a memory 302, a hard disk drive (HDD) 303, an ethernet port 304, and a baseboard management controller (BMC) 309. The BMC 309 acquires monitoring data from the hardware of the server 300 (each component and element configured inside the server 300) and transmits it to the monitoring device 100 as hardware monitoring information.
[0024] (operation) Fig. 3 is a sequence diagram showing an example of the operation of the maintenance management system. For the sake of simplicity, only one server 300 is shown in Fig. 3, but each server 300 operates in the same manner.
[0025] <<Calculating the failure rate due to hardware>> The acquisition unit 101 of the monitoring device 100 acquires hardware monitoring information from the server 300 via the network 010 and the BMC 309. The calculation unit 102 calculates a failure rate P his calculated (step S101).
[0026] Hardware-related failure rate P h is the probability of failure of an individual device. h is calculated, for example, between 0 and 1 (or 0% and 100%).
[0027] The hardware monitoring information includes monitoring data corresponding to a plurality of monitored components such as the CPU 301, memory 302, HDD 303, ethernet port 304, and power supply. The monitoring data related to the CPU 301 is, for example, the CPU usage rate and temperature. The monitoring data related to the memory 302 is, for example, the number of errors in ECC (Error checking and correcting). The monitoring data related to the HDD 303 is, for example, an inspection value by SMART (Self-Monitoring, Analysis and Reporting Technology). The monitoring data related to the power supply indicates, for example, the redundancy status of the power supply.
[0028] The calculation unit 102 determines whether or not there is an abnormal trend based on, for example, the value of the monitoring data acquired for each hardware component that is subject to failure. The calculation unit 102 determines that a component has an abnormal trend when the monitoring data exceeds a predetermined threshold. Alternatively, the calculation unit 102 may determine that a component has an abnormal trend when the failure rate of the component calculated based on the value of the monitoring data of the component is equal to or greater than a predetermined threshold. When the monitoring information includes information on 100 components, the calculation unit 102 calculates, for example, a failure rate P h The failure rate P is increased by +0.01 (or +1%). The increase in the failure rate P is determined based on the importance of the parts included in the monitoring information and the values of the measured data. h may be adjusted on a part-by-part basis.
[0029] <<Calculation of failure rate due to operating environment>> The acquisition unit 101 of the monitoring device 100 acquires the measured temperature of the temperature sensor 400 installed in the server rack 200 as information about the operating environment of the server 300. The calculation unit 102 calculates the failure rate P e is calculated (step S102).
[0030] Failure rate due to operating environment P e is the probability of failure calculated based on the difference between the environment in which the server 300 is installed and the stable operating conditions. e is calculated, for example, between 0 and 1 (0% to 100%).
[0031] For example, the calculation unit 102 calculates 0 (or 0%) if the temperature is the median of the assumed operating temperatures, 1 (or 100%) if it is equal to or higher than the upper temperature limit, and 1 (or 100%) if it is equal to or lower than the lower temperature limit. The calculation unit 102 calculates the failure rate P e may be calculated.
[0032] The acquiring unit 101 may acquire the temperature distribution of the server room in which the servers 300 are arranged from an external device. The acquiring unit 101 may acquire the operating environment temperature of each server 300 based on the temperature distribution of the server room and the arrangement of the servers 300.
[0033] <<Calculating the failure rate due to operating time>> The server 300 records and accumulates the total operation time (total power-on time) from the initial placement. The acquisition unit 101 acquires the operation time of the server 300 from the server 300 as operation information. The calculation unit 102 calculates the failure rate P t is calculated (step S103).
[0034] Failure rate due to operating time P t is the probability of failure calculated based on the bathtub curve of the device, which indicates the lifespan characteristics of the server 300 due to the total operating time. tWhen unused, the upper limit of operation time is set to 0 (0%), and the upper limit of operation time is set to 1 (100%).
[0035] <<Calculation and acquisition of individual failure rate P>> The calculation unit 102 calculates the hardware-related failure rate P h , the failure rate due to the operating environment P e , and the failure rate due to operating time P t Taking all of the above into consideration, the individual failure rate P is calculated (step S104). The acquisition unit 101 acquires the individual failure rate P calculated by the calculation unit 102 (step S105).
[0036] The order of steps S101 to S103 can be changed.
[0037] Calculation example 1 of individual failure rate P: The calculation unit 102 calculates three failure rates P h ,P e ,P t The individual failure rate P can be expressed by the following formula, for example: P=W h ×P h +W e ×P e +W t ×P t (Weighting constant W h ,W e ,W t >0) Calculation example 2 of individual failure rate P: The calculation unit 102 calculates the failure rate P h and P t When increases to a given value, the failure rate P e Weight W e In other words, the hardware-related failure rate P h and the failure rate due to operating time P t Servers with high failure rates due to the operating environment P e Even if the individual failure rate P is low, the individual failure rate P may be calculated to be high. This allows the server to be monitored at short monitoring intervals.
[0038] <<Determining the monitoring interval>> The determining unit 103 determines the monitoring interval for the server 300 based on the relational model between the individual failure rate of the server 300 and the monitoring interval (step S106). Fig. 4 is a graph showing an example of the relational model. In Fig. 4, the relational model between the individual failure rate P and the monitoring interval I is represented by a straight line, but it may also be a curved line. Also, in Fig. 4, the monitoring interval I is set to continuous values as the individual failure rate increases, but the monitoring interval I may also be discontinuous (discrete). The monitoring interval I may be represented by different relational expressions depending on the range of the individual failure rate P.
[0039] The closer the individual failure rate P is to 100, the shorter the monitoring interval I may be set to than the normal monitoring interval of a general monitoring device. Also, the closer the individual failure rate P is to 0, the longer the monitoring interval I may be set to than the normal monitoring interval of a general monitoring device.
[0040] The monitoring device 100 monitors the servers 300 at monitoring intervals determined for each server 300 .
[0041] (effect) According to the first embodiment, monitoring can be controlled in consideration of the operating environment of the server 300. This is because the acquisition unit 101 of the monitoring device 100 acquires the individual failure rate caused by the hardware, operating time, and operating environment of each server, and the determination unit 103 determines the monitoring interval for the server 300 based on the individual failure rate.
[0042] In system maintenance management, many electronic devices are monitored using one monitoring device. The larger the system, the more electronic devices are monitored. In addition, each additional monitoring item increases the number of accesses by the number of electronic devices, which increases the network load and the load on the monitoring device. For this reason, in large systems, the monitoring interval is uniformly lengthened to reduce the network load and the load on the monitoring device.
[0043] However, if the monitoring interval is long, it takes a long time for a monitoring device to detect a failure after it occurs. If a failure cannot be detected immediately, the availability rate of the entire system decreases, leading to a deterioration in the quality of service.
[0044] According to the first embodiment, the determination unit 103 determines the monitoring interval of the server 300 whose individual failure rate P is lower than the predetermined failure rate standard to be longer than the predetermined monitoring interval standard, thereby reducing the load on the network 010 when monitoring many servers and reducing the monitoring load.
[0045] Furthermore, according to the first embodiment, the determination unit 103 sets the monitoring interval of the server 300 whose individual failure rate P is higher than the predetermined failure rate standard to be shorter than the predetermined monitoring interval standard, thereby shortening the time from the actual occurrence of a failure to the monitoring device 100 detecting the failure, and preventing delays in detecting the failure.
[0046] (Modification) 5 is a graph showing another example of the relational model. In FIG. 5, the relational model is expressed by different relational expressions depending on whether the individual failure rate P is smaller than the reference failure rate P0 or equal to or greater than the reference failure rate P0.
[0047] When P≦P0, I=I A 0 <P<P0のとき、I=I B In the example of FIG. 5, for example, the monitoring interval I A is 2 to 3 minutes, monitoring interval I B may be determined as 1 hour. The determining unit 103 may set the reference failure rate P0 to, for example, an average value or a median value of the individual failure rates of the servers 300_1, 300_2, ..., 300_x in each server rack 200 in a predetermined period. The determining unit 103 may set the reference failure rate P0 using the above-mentioned machine learning.
[0048] [Second embodiment] In the first embodiment, a case has been described in which the monitoring device 100 includes a calculation unit that calculates the individual failure rate P. In the second embodiment, a case will be described in which another device has the function of the calculation unit 102 according to the first embodiment, and the monitoring device 100 acquires the individual failure rate P calculated by the calculation unit. Descriptions similar to those of the first embodiment will be omitted in the description of the second embodiment.
[0049] (composition) 6 is a block diagram showing the configuration of a monitoring device 100 according to the second embodiment. The monitoring device 100 according to the second embodiment includes an acquisition unit 121 and a determination unit 122. The monitoring device 100 according to the second embodiment can be replaced with the monitoring device 100 in FIG.
[0050] Fig. 7 is a schematic diagram of a maintenance management system according to a second embodiment, showing an example of the arrangement of the calculation devices 120. As shown in Fig. 7, one probability calculation device 120 may be communicatively connected to the monitoring device 100, each server 300 in each server rack 200, and a temperature sensor 400. The calculation device 120 acquires hardware monitoring information and operation information from each server 300, and acquires information related to the operating environment from the temperature sensor 400.
[0051] The acquisition unit 121 of the monitoring device 100 acquires, from the external calculation device 120, the individual failure rate of each server 300 based on the hardware, operation information, and operating environment.
[0052] The determination unit 122 determines the monitoring interval for each server 300 based on the individual failure rate of the server.
[0053] When the individual failure rate is higher than a predetermined reference failure rate, the determination unit 122 may determine the monitoring interval of the server 300 to be a first monitoring interval, and when the individual failure rate is lower than the reference failure rate, the determination unit 122 may determine the monitoring interval of the server 300 to be a second monitoring interval longer than the first monitoring interval. When the individual failure rate is equal to the reference failure rate, the determination unit 122 determines the monitoring interval to be an arbitrary time equal to or greater than the first monitoring interval and equal to or less than the second monitoring interval.
[0054] The relationship between the individual failure rate and the monitoring interval determined by the determining unit 122 may be shown by the graph of Fig. 4 or Fig. 5. Fig. 8 is a graph showing another example of the relationship between the individual failure rate and the determined monitoring interval. In Fig. 8, monitoring intervals I1 to I5 are determined corresponding to reference failure rates P1 to P4. Each of the reference failure rates P1 to P4 is an embodiment of the predetermined reference failure rate. Each of the monitoring intervals I1 to I5 is an embodiment of the first or second monitoring interval.
[0055] The monitoring device 100 monitors the server 300 at the determined monitoring interval. Alternatively, the monitoring device 100 transmits the determined monitoring interval to another monitoring process execution device (not shown) and causes the monitoring process execution device to monitor the server 300.
[0056] 7, one calculation device 120 is arranged, but one calculation device 120 may be arranged for each server rack 200. In this case, the calculation device 120 calculates the individual failure rate of each server 300 in the server rack 200. Alternatively, the function of the calculation device 120 may be provided in each server 300. In this case, each server 300 acquires information about the operating environment from the temperature sensor 400 and calculates the individual failure rate of the own device. The monitoring device 100 acquires the individual failure rate of each server 300 from each of the multiple calculation devices 120.
[0057] (operation) 9 is a flowchart showing an example of the operation of the monitoring device 100 according to the second embodiment. The acquisition unit 121 acquires the individual failure rate caused by the hardware, the operating time, and the operating environment of each server 300 (step S121). The determination unit 122 determines the monitoring interval for each server 300 based on the individual failure rate of each server 300 (step S122).
[0058] (effect) According to the second embodiment, monitoring can be controlled in consideration of the operating environment of the server 300. This is because the acquisition unit 121 of the monitoring device 100 acquires the individual failure rate caused by the hardware, operating time, and operating environment of each server, and the determination unit 122 determines the monitoring interval for the server 300 based on the individual failure rate.
[0059] (Modification) The determining unit 122 may determine the monitoring interval for the server based on the ratio of the number of the servers 300 for each monitoring interval or the upper limit number in addition to the individual failure rate. That is, the determining unit 122 determines the reference failure rate so that, for example, when the number of the servers 300 monitored at the first monitoring interval reaches a predetermined upper limit number, the remaining servers 300 are monitored at a longer second monitoring interval.
[0060] According to this modified example, it is possible to meet both the demand for reducing the network load when monitoring many servers, thereby reducing the monitoring load, and the demand for shortening the time from when an actual failure occurs until the monitoring device 100 detects the failure, thereby preventing delays in detecting the failure.
[0061] [Hardware configuration] In each of the above-described embodiments, each component of the monitoring device 100 is represented by a functional block. A part or all of each component of each device may be realized by any combination of the computer 500 and a program.
[0062] Fig. 10 is a block diagram showing an example of a hardware configuration of a computer 500. Referring to Fig. 10, the computer 500 includes, for example, a CPU (Central Processing Unit) 501, a ROM (Read Only Memory) 502, a RAM (Random Access Memory) 503, a program 504, a storage device 505, a drive device 507, a communication interface 508, an input device 509, an input / output interface 511, and a bus 512.
[0063] The program 504 includes instructions for implementing each function of each device. The program 504 is stored in advance in the ROM 502, the RAM 503, or the storage device 505. The CPU 501 implements each function of each device by executing instructions included in the program 504. For example, the CPU 501 of the monitoring device 100 implements the functions of the monitoring device 100 by executing instructions included in the program 504. The RAM 503 may also store data to be processed in each function of each device. For example, the RAM 503 of the computer 500 may store hardware monitoring information and an operating environment temperature used by the calculation unit 102 of the monitoring device 100.
[0064] The drive device 507 reads and writes data from the recording medium 506. The communication interface 508 provides an interface with a communication network. The input device 509 is, for example, a mouse or a keyboard, and accepts information input from an administrator of the maintenance management system. The output device 510 is, for example, a display, and outputs (displays) information to the administrator. The input / output interface 511 provides an interface with peripheral devices. The bus 512 connects these hardware components. The program 504 may be supplied to the CPU 501 via a communication network, or may be stored in advance in the recording medium 506, read by the drive device 507, and supplied to the CPU 501.
[0065] It should be noted that the hardware configuration shown in FIG. 10 is merely an example, and other components may be added, or some components may not be included.
[0066] There are various variations in the method of realizing each device. For example, each device may be realized by any combination of a different computer and program for each component. Furthermore, multiple components of each device may be realized by any combination of a single computer and program.
[0067] In addition, some or all of the components of each device may be realized by general-purpose or dedicated circuits including a processor, etc., or a combination of these. These circuits may be configured by a single chip, or may be configured by multiple chips connected via a bus. Some or all of the components of each device may be realized by a combination of the above-mentioned circuits, etc., and a program.
[0068] Furthermore, when some or all of the components of each device are realized by a plurality of computers, circuits, etc., the plurality of computers, circuits, etc. may be arranged in a centralized manner or in a distributed manner.
[0069] At least a part of the monitoring device 100 may be provided in a Software as a Service (SaaS) format. That is, at least a part of the functions for realizing the monitoring device 100 may be executed by software executed via a network.
[0070] Although the present disclosure has been described above with reference to the embodiments, the present disclosure is not limited to the above embodiments. Various modifications that can be understood by a person skilled in the art can be made to the configuration and details of the present disclosure within the scope of the present disclosure. Furthermore, the configurations in each embodiment can be combined with each other without departing from the scope of the present disclosure. [Explanation of symbols]
[0071] 100 Monitoring equipment 101, 121 Acquisition Department 102 Calculation section 103, 122 Decision Section 120 Calculation Device 200 Server Racks 300 Servers 400 Temperature Sensor 500 Computers
Claims
1. An acquisition means for acquiring an individual failure rate caused by hardware, operating time, and operating environment of each server; a determination means for determining a monitoring interval for each of the servers based on a relational model showing a decreasing trend of the monitoring interval corresponding to an increase in the individual failure rate; A monitoring device comprising:
2. the acquiring means acquires the individual failure rate based on hardware monitoring information, operating time, and operating environment temperature of the server in the server rack for each of the servers; The monitoring device according to claim 1.
3. a calculation unit for calculating the individual failure rate based on the hardware monitoring information for each server, an operating time, and an operating environment temperature of the server; 3. A monitoring device according to claim 1 or 2.
4. The determining means is If the individual failure rate is higher than a predetermined reference failure rate, a monitoring interval of the server is determined to be a first monitoring interval; If the individual failure rate is lower than the reference failure rate, determining a monitoring interval of the server to be a second monitoring interval that is longer than the first monitoring interval. A monitoring device according to any one of claims 1 to 3.
5. The determining means further determines the monitoring interval based on an upper limit number of the servers to be monitored during the monitoring interval. A monitoring device according to any one of claims 1 to 4.
6. A monitoring device comprising: Obtain the individual failure rate due to the hardware, operating time, and operating environment of each server, determining a monitoring interval for each of the servers based on a relational model showing a decreasing trend of the monitoring interval corresponding to an increase in the individual failure rate; Monitoring method.
7. Obtain the individual failure rate due to the hardware, operating time, and operating environment of each server, determining a monitoring interval for each of the servers based on a relational model showing a decreasing trend of the monitoring interval corresponding to an increase in the individual failure rate; A program that causes a computer to carry out processing.
Citation Information
Patent Citations
Reliability and property value calculating device
JP1991070069A
Operation management / maintenance support system of it equipment, and method for the same
JP2010271905A
Monitoring control method, remote management system and remote management device
JP2014053027A
Failure tendency determination device, failure tendency determination method, and program
JP2016081374A
Information processing device, program, and information providing method
JP2016192016A