Power control systems and power control equipment

The power control system addresses the challenge of self-consigning electricity by using a demand calculator and output control unit to manage energy flow and comply with electric power utility directives, achieving efficient and balanced energy transmission.

JP7660488B2Active Publication Date: 2025-04-11KYOCERA CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2021201279
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-12-10
Publication Date
2025-04-11
Estimated Expiration
2041-12-10

AI Technical Summary

Technical Problem

Existing power control systems struggle to self-consign electricity generated while satisfying the power directives of electric power utilities, particularly in managing output control during periods of high electricity generation or low demand.

Method used

A power control system comprising a demand calculator, a simultaneous amount calculation unit, and an output control unit that calculates electricity demand, determines the amount of energy flowing backward into the power system, and controls power output to reduce the difference between planned and actual energy flow, ensuring compliance with electric power company commands.

Benefits of technology

The system effectively self-consigns power generated while adhering to electric power utility directives, optimizing energy flow and reducing imbalances between planned and actual energy transmission.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007660488000001
    Figure 0007660488000001
  • Figure 0007660488000002
    Figure 0007660488000002
  • Figure 0007660488000003
    Figure 0007660488000003
Patent Text Reader

Abstract

To provide a power control system and a power control device that realize self-consignment of generated power while satisfying the power directives of electric utilities.SOLUTION: A power control system 1A includes a demand calculation unit 50A that calculates the power demand of a first base, a simultaneous same amount calculation unit 60A that calculates the amount of power that reversely flows from the first base to a power system in a predetermined time segment on the basis of the power demand and the amount of power generated by a power generation unit of the first base, and an output control unit 70A that controls the power output by the power generation unit so as to meet the power directives of electric utilities and reduce the difference between the planned and actual amount of reverse power flow from the first base to the power system on the basis of the power demand.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a power control system and a power control device. [Background technology]

[0002] Conventionally, self-consignment is known as a mechanism for transmitting power output from a power generation facility to a demand facility via a power grid managed by a third-party entity. In a system that performs self-consignment, a technology has been proposed for appropriately grasping the amount of self-consignment power (for example, see Patent Document 1).

[0003] When photovoltaic power generation is performed, for example, when the amount of power generation is high or when the demand for power is low, it is necessary to suppress the power generation output (output control) so that the power supplied to the power grid does not exceed the amount that the electric power company can connect. In addition, when the demand for power is high, the addition of photovoltaic power generation may require output control to prevent the power lines from overheating. When a command regarding power (power command) is issued by the electric power company, the power generation equipment is required to control the power output so as to satisfy the power command. In output control, a technology has been proposed in which the value of the power command is calculated based on the command value for output control and the result of abnormality detection, and the value is transmitted to the power conditioner (see, for example, Patent Document 2). [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Patent Publication No. 2021-52557 [Patent Document 2] JP2017-229213 Public Relations Summary of the Invention [Problem to be solved by the invention]

[0005] In the above-mentioned system, it is desirable to suitably realize self-transportation of generated electricity while satisfying power commands from electric power companies.

[0006] An object of the present disclosure is to provide a power control system and a power control device that can realize self-transmission of generated power while satisfying power instructions from electric power companies. [Means for solving the problem]

[0007] A power control system according to an embodiment includes: a demand calculation unit that calculates the power demand of the first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls the power output by the power generation unit so as to satisfy a power command from an electric power utility and reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base to the power grid based on the power demand; Equipped with.

[0008] Moreover, the power control system according to one embodiment includes: a demand calculation unit that calculates the power demand of the first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls at least one of charging and discharging of the storage battery at the first base so as to satisfy a power command from an electric utility company and reduce a difference between a planned amount of power flowing back from the first base to the power grid and an actual amount of power flowing back based on the power demand; Equipped with.

[0009] Moreover, the power control device according to one embodiment includes: a demand calculation unit that calculates the power demand of the first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls the power output by the power generation unit so as to satisfy a power command from an electric power utility and reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base to the power grid based on the power demand; Equipped with.

[0010] Moreover, the power control device according to one embodiment includes: a demand calculation unit that calculates the power demand of the first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls at least one of charging and discharging of the storage battery at the first base so as to satisfy a power command from an electric utility company and reduce a difference between a planned amount of power flowing back from the first base to the power grid and an actual amount of power flowing back based on the power demand; Equipped with. Effect of the Invention

[0011] According to one embodiment, it is possible to provide a power control system and a power control device that can realize self-transmission of generated power while satisfying power commands from electric power companies. [Brief description of the drawings]

[0012] [Figure 1] 1 is a diagram illustrating an example of the configuration of a power control system according to an embodiment; [Diagram 2] 4 is a flowchart illustrating the operation of a power control system according to an embodiment. [Diagram 3] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 4] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Diagram 5]FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 6] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 7] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 8] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 9] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 10] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. [Figure 11] FIG. 2 is a diagram illustrating the operation of a power control system according to an embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] In the present disclosure, a power control system and / or a power control device may be a system and / or a device that operates by power. Also, a power control system and / or a power control device may include a function of controlling power. The function of the power control system and / or the power control device is not limited to the function of controlling power, and may have other functions.

[0014] In addition, in this disclosure, "self-dispatch" may be, for example, as defined in the "Guidelines for Self-Dispatch" (enforced on April 1, 2014) established by the Agency for Natural Resources and Energy, an external bureau of the Ministry of Economy, Trade and Industry. In other words, self-dispatch may be defined as a power transmission service provided by a general electric utility when a person who installs a private power generation facility transmits power generated using the private power generation facility to a factory or the like located in another location of the person who installs the private power generation facility via a power transmission and distribution network maintained and operated by the general electric utility.

[0015] Hereinafter, a power control system according to an embodiment will be described with reference to the drawings.

[0016] Fig. 1 is a diagram showing an example of the configuration of a power control system according to an embodiment. As shown in Fig. 1, in an embodiment, power control system 1A may be a system installed at a first location, and power control system 1B may be a system installed at a second location. Hereinafter, when there is no particular distinction between power control system 1A and power control system 1B, they will be collectively referred to simply as "power control system 1."

[0017] In FIG. 1, the first base is a base that is shown in the region above the dashed line shown in the upper part of FIG. 1, and the second base is a base that is shown in the region below the dashed line shown in the lower part of FIG. 1. The first base and / or the second base may be any location where power generation and / or consumption is expected, such as a place where so-called ground-mounted solar power generation is performed, a business office or sales office of each business operator, a factory, and an apartment building. In addition, in FIG. 1, the area between the first base and the second base may be, for example, a base other than the first base or the second base, may be a part of the first base and / or the second base, or may be any base.

[0018] 1, paths for transmitting and / or receiving power, i.e., paths for electric power, are primarily shown by solid lines, whereas paths for transmitting and / or receiving information, i.e., paths for electric signals, are primarily shown by dashed lines.

[0019] Furthermore, the functional units shown in Fig. 1 may be connected to each other by at least one of wired and wireless connections as appropriate. In Fig. 1, communication interfaces and various repeaters (repeaters) that connect the functional units to each other by at least one of wired and wireless connections are omitted from the illustration. Furthermore, each functional unit may be provided with a storage unit such as a semiconductor memory that stores various information and / or programs as appropriate. In Fig. 1, storage units such as semiconductor memories are omitted from the illustration.

[0020] 1, the power control system 1A at the first base may include a power generation unit 10A, a power adjustment unit 20A, a load 30A, a smart meter 40A, a demand calculation unit 50A, a simultaneous balancing calculation unit 60A, and an output control unit 70A. The power control system 1A may not include some of the functional units described above, or may include functional units other than the functional units described above.

[0021] 1, the power control system 1B at the second base may include a power generation unit 10B, a power adjustment unit 20B, a load 30B, a smart meter 40B, a demand calculation unit 50B, a simultaneous balancing calculation unit 60B, and an output control unit 70B. The power control system 1B may not include some of the functional units described above, or may include functional units other than the functional units described above.

[0022] Hereinafter, when there is no particular distinction between power generation unit 10A and power generation unit 10B, they will simply be referred to as "power generation unit 10." Similarly, for other functional units, when there is no particular distinction between a functional unit of power control system 1A and a functional unit of power control system 1B, they will simply be referred to by the reference number of the functional unit (i.e., the symbol A or B will be omitted). For example, when there is no particular distinction between power adjustment unit 20A and power adjustment unit 20B, they will simply be referred to as "power adjustment unit 20."

[0023] Each functional unit of power control system 1B corresponding to a functional unit of power control system 1A may have the same or similar configuration as the functional units of power control system 1A, or may have a different configuration. For the sake of simplicity of explanation, each functional unit of power control system 1B corresponding to a functional unit of power control system 1A will be described below as being the same as the functional units of power control system 1A.

[0024] Unless otherwise specified, the following will basically describe the power control system 1A in more detail. However, a description based on the same or similar gist as that of the power control system 1A may also be applicable to the power control system 1B.

[0025] The power generating unit 10 may be a functional unit that generates power such as solar power generation by including, for example, a solar cell. The power generating unit 10 may be capable of outputting the generated power to the outside. The power generating unit 10 may appropriately include a power conditioner (hereinafter, also referred to as PCS (Power Conditioning Subsystem)) that controls the power generated by the power generating unit 10 and output to the outside. Hereinafter, the power generating unit 10 will be described as performing solar power generation. However, in one embodiment, the power generation performed by the power generating unit 10 is not limited to solar power generation. For example, the power generating unit 10 may perform wind power generation, hydroelectric power generation, thermal power generation, power generation by a fuel cell, or power generation by a plug-in hybrid vehicle. In one embodiment, the power generating unit 10 may generate power that can be reverse-flowed to the power grid. The power generating unit 10 may be configured by various known technologies. Therefore, a more detailed description of the power generating unit 10 will be omitted.

[0026] The power generated by the power generation unit 10 may be supplied to the smart meter 40 (through a PCS provided in the power generation unit 10). For this reason, as shown in FIG. 1, the power generation unit 10 may be connected to the smart meter 40 by a power line. The power supplied from the power generation unit 10 to the smart meter 40 may be power that flows back to the power grid. Furthermore, the power that flows back in this way may be used as self-consignment power. Furthermore, the power supplied from the power generation unit 10 to the smart meter 40 may be purchased by the power grid as surplus imbalance power. The power generation unit 10 may control the power to be output based on an output control value (e.g., %) transmitted from the output control unit 70. Furthermore, information on the power generated by the power generation unit 10 (such as the amount of power to be output) may be transmitted to the demand calculation unit 50.

[0027] The power adjustment unit 20A may be a function of adjusting power at the first base. The power adjustment unit 20B may be a function of adjusting power at the second base. The power adjustment unit 20 may have at least one of a function of enabling power to be output to the outside and a function of enabling power to be input from the outside. Specifically, the power adjustment unit 20 may be equipped with, for example, a storage battery. The power adjustment unit 20 may appropriately include a PCS that controls at least one of the power output by the power adjustment unit 20 and the power input to the power adjustment unit 20. That is, in this case, the PCS of the power adjustment unit 20 may control at least one of the power discharged by the storage battery of the power adjustment unit 20 and the power charged to the storage battery. The power control system 1 can obtain an adjustment power for achieving the simultaneous equal amount of a planned value described later by the power that is charged and discharged by the power adjustment unit 20.

[0028] The power adjustment unit 20 may include, for example, a stationary storage battery, or may include, for example, a storage battery (battery) of an electric vehicle such as an EV or a plug-in hybrid vehicle. The power adjustment unit 20 can be configured using various known technologies. Therefore, a detailed description of the power adjustment unit 20 will be omitted.

[0029] The power discharged by the power adjustment unit 20 may be supplied to the smart meter 40 (through a PCS provided in the power adjustment unit 20). Furthermore, the power adjustment unit 20 may be charged with power supplied from the power generation unit 10 (through a PCS provided in the power adjustment unit 20). For this reason, as shown in FIG. 1, the power adjustment unit 20 may be connected to the smart meter 40 by a power line. The power adjustment unit 20 may control the power to be charged and discharged based on an adjustment value (e.g., %) transmitted from the output control unit 70. Furthermore, the power adjustment unit 20 may be controlled so as not to be charged with power supplied from the power grid.

[0030] The power regulating unit 20 may be charged with at least a portion of the power generated by the power generating unit 10.

[0031] The load 30A may be any of various devices that consume power at the first location, and the load 30B may be any of various devices that consume power at the second location. The load 30 may be any electronic device.

[0032] The load 30 may consume at least a portion of the power generated by the power generation unit 10. The load 30 may also consume at least a portion of the power discharged by the power adjustment unit 20. The load 30 may also consume at least a portion of the power purchased from the grid power. As shown in Fig. 1, the load 30 may be connected to the power generation unit 10, the power adjustment unit 20, and the smart meter 40 by power lines.

[0033] The smart meter 40 may be a functional unit having a function of digitally measuring power information and communicating the measured information. Here, the power information may be, for example, the amount of power purchased, the amount of power to be reversely flowed, and / or information related to power such as time. As shown in FIG. 1, the smart meter 40 may be connected to the power generation unit 10, the power adjustment unit 20, and the load 30 by power lines. The smart meter 40 may be configured using various known technologies. Therefore, a detailed description of the smart meter 40 will be omitted.

[0034] As shown in FIG. 1, a smart meter 40A at a first base and a smart meter 40B at a second base may be connected by a power line (power system). In this way, by connecting the smart meters 40 to each other by a power line, it is possible to perform self-consignment of power from one base to the other base. In FIG. 1, the power generated by the power generation unit 10A at the first base may be self-consignment to the load 30B at the second base. Also, in FIG. 1, the power generated by the power generation unit 10B at the second base may be self-consignment to the load 30A at the first base. When realizing bidirectional self-consignment in this way, a functional unit (hereinafter, referred to as a "determination unit") that determines the direction of self-consignment may be provided. Such a determination unit may be provided at the first base as a part of the power control system 1A, at the second base as a part of the power control system 1B, or at a location different from the first base or the second base.

[0035] The smart meter 40A may be communicatively connected to the demand calculation unit 50 and the output control unit 70. The smart meter 40A may transmit information (e.g., the amount of power) of power purchased and / or reverse flow at the first base to the demand calculation unit 50. Furthermore, the smart meter 40 may transmit information (e.g., the amount of power) of power to be reverse flowed out of the power generated by the power generation unit 10 to the output control unit 70. Furthermore, the smart meter 40 may transmit information (e.g., the amount of power) of power to be self-consigned as reverse flow power out of the power generated by the power generation unit 10 to the output control unit 70.

[0036] The demand calculation unit 50, the simultaneous and equal amount calculation unit 60, and the output control unit 70 may each be a controller that controls the operation of the power control system 1. The controller may include at least one processor, such as a CPU (Central Processing Unit) or a DSP (Digital Signal Processor), to provide control and processing capabilities for executing various functions. The controller may be realized with one processor or multiple processors. The controller may be realized as a single integrated circuit. The processor may be realized as multiple integrated circuits and discrete circuits communicatively connected. The controller may be configured as a CPU or DSP, and software such as a program executed by the CPU or DSP. The program executed in the controller and the results of the processing executed in the controller may each be stored in an arbitrary storage unit.

[0037] The demand calculation unit 50, the simultaneous balancing calculation unit 60, and the output control unit 70 may be separate functional units, or may be functional units in which at least a part of them are combined, or may be functional units in which all of them are combined. The demand calculation unit 50, the simultaneous balancing calculation unit 60, and the output control unit 70 may be configured as hardware resources, or may be configured as software, or may be constructed by software and hardware resources working together. The functions of the demand calculation unit 50, the simultaneous balancing calculation unit 60, and the output control unit 70 will be described further below.

[0038] The power server 200 may be a server that distributes various information of an electric utility such as a power company. In one embodiment, the power server 200 may transmit a command related to power (power command) to each base such as the first base and / or the second base. Here, the power command may be a command that requests control (e.g., suppression) of the output of power generated when the balance between the demand and supply of power in the power system becomes unbalanced. In addition, such a power command may be acquired from the power server 200 by, for example, any device in the power control system 1. The power server 200 may transmit the power command to, for example, the simultaneous power balancing calculation unit 60 and / or the output control unit 70 of the power control system 1. In addition, the power server 200 may transmit the power command to the simultaneous power balancing calculation unit 60 via the output control unit 70. In addition, the simultaneous power balancing calculation unit 60 and / or the output control unit 70 of the power control system 1 may acquire the power command from the power server 200. For this reason, the power server 200 may be communicatively connected to the simultaneous power balancing calculation unit 60 and / or the output control unit 70 of the power control system 1, etc.

[0039] In one embodiment, the power server 200 may transmit a power command including a value of a power generation suppression amount (for example, a percentage) to the power generation balancing calculation unit 60 and / or the output control unit 70. In one embodiment, the power server 200 may transmit a power command for a given day up to the day before the given day, or on the day of the given day.

[0040] The power server 200 may be, for example, a server (computer) used in a typical client-server system. The computer used as the server can be configured using various known technologies. Therefore, a detailed description of the computer used as the server will be omitted.

[0041] The cross-regional organization server 300 may be an electronic device such as a server (computer) operated and / or used by an organization such as the Organization for Cross-regional Coordination of Transmission Operators, JAPAN (OCCTO). The Organization for Cross-regional Coordination of Transmission Operators is an organization established based on the Electricity Business Act (Act No. 170 of July 11, 1964) for the purpose of promoting cross-regional operation of the electric power business in Japan. All electric power companies in Japan are obligated to become members of the organization. The organization monitors the electricity supply and demand situation of each member company and instructs other members to lend electricity to a member whose supply and demand situation has deteriorated. The cross-regional organization server 300 may be a server (computer) used in a typical client-server system, for example.

[0042] In one embodiment, the power control system of each base, such as the power control system 1A of the first base and / or the power control system 1B of the second base, may formulate (generate) a power generation plan for each base and transmit the power generation plan to the wide-area organization server 300. Here, the "power generation plan" may be, for example, a planned value of the amount of power for each predetermined time segment to be transmitted from a power generation facility (e.g., the first base) to a demand facility (e.g., the second base). For example, in one embodiment, the simultaneous balancing calculation unit 60 of the power control system 1 may be communicatively connected to the wide-area organization server 300. In one embodiment, the simultaneous balancing calculation unit 60 of the power control system 1 may transmit the formulated power generation plan of the power control system 1 to the wide-area organization server 300. For example, in one embodiment, the simultaneous power balance calculation unit 60 of the power control system 1 may transmit the power generation plan for a specific day of the power control system 1 to the wide-area agency server 300 by the day before the specific day (for example, by noon on the day before the specific day).

[0043] The weather server 400 may be a server that distributes various weather information (weather data), etc. The weather server 400 may be a server operated by an administrative agency such as the Japan Meteorological Agency, or may be a server operated by a private information provider, etc. In one embodiment, the weather server 400 may distribute various weather information (weather data) to the power control systems at each base, such as the power control system 1A at the first base and / or the power control system 1B at the second base. In addition, the various weather information (weather data) may be acquired from the weather server 400 by, for example, any device in the power control system 1. The various weather information (weather data) may include, for example, at least any of the weather, temperature, humidity, sunshine hours, solar radiation, cloud cover, precipitation, and / or snowfall at a specified point at a specified time or in a specified time period.

[0044] In one embodiment, the demand calculation unit 50 and the simultaneous balancing calculation unit 60 of the power control system 1 may be communicatively connected to a weather server 400. In one embodiment, the weather server 400 may transmit various weather information to the demand calculation unit 50 and / or the simultaneous balancing calculation unit 60 of the power control system 1. The weather server 400 may be, for example, a server (computer) used in a typical client-server system.

[0045] In one embodiment, the weather server 400 may not only distribute actual weather data, but also, for example, forecasts of various weather data. In addition, in one embodiment, the weather server 400 may distribute various forecasts as forecasts of various weather data, such as forecast data for a predetermined time before, such as a forecast for the previous day or a forecast for several hours before, forecast data for the current day, and forecast data for a predetermined time after, such as a future forecast.

[0046] Next, the demand calculation unit 50, the simultaneous balancing calculation unit 60, and the output control unit 70, which perform characteristic functions in the power control system 1 according to one embodiment, will be described in more detail.

[0047] The demand calculation unit 50 calculates the demand for power in the power control system 1. In one embodiment, the demand calculation unit 50A calculates the demand for power in the power control system 1A, for example, the demand for power to be supplied to the load 30A. In one embodiment, the demand calculation unit 50 may calculate not only the actual power demand in the power control system 1 (actual value of power demand), but also a predicted value of power in the power control system 1.

[0048] In one embodiment, the demand calculation unit 50 may calculate an actual value of the power demand based on information transmitted from the power generation unit 10, information transmitted from the power adjustment unit 20, and information transmitted from the smart meter 40. In this case, the information transmitted from the power generation unit 10 may be data such as the amount of power actually output by power generation by the power generation unit 10. The information transmitted from the power generation unit 10 may be transmitted, for example, from the PCS of the power generation unit 10. Furthermore, the information transmitted from the power adjustment unit 20 may be data such as the amount of power actually charged and discharged by charging and discharging by the power adjustment unit 20. The information transmitted from the power adjustment unit 20 may be transmitted, for example, from the PCS of the power adjustment unit 20. Furthermore, the information transmitted from the smart meter 40 may be data on the power actually flowing backward and / or purchased in the power control system 1 of each base.

[0049] In one embodiment, the demand calculation unit 50 may calculate the actual value of the power demand, for example, based on the following formula (1). (Power demand)=(output power of power generation unit 10)+(charge / discharge power of power adjustment unit 20)−(power sold)+(power purchased) (1) In formula (1), the charging and discharging power of the power adjustment unit 20 is positive for discharging and negative for charging. The actual value of the power demand calculated in this manner may be stored in any storage unit, such as a storage unit included in the demand calculation unit 50.

[0050] In one embodiment, as described above, the demand calculation unit 50 may receive weather data such as temperature and / or humidity from the weather server 400. The demand calculation unit 50 may store the weather data received from the weather server 400 in any storage unit such as a storage unit included in the demand calculation unit 50.

[0051] In one embodiment, the demand calculation unit 50 may calculate the predicted value of the power demand based on, for example, the above-mentioned weather data. In this case, the demand calculation unit 50 may calculate the predicted value of the power demand by, for example, modeling the relationship between the past actual values ​​of the power demand stored in the storage unit and the weather data, and using multiple regression analysis or the like. In addition, in one embodiment, the demand calculation unit 50 may calculate various predictions of the power demand, such as prediction data for a predetermined time before, such as a prediction for the previous day or a prediction for several hours before, and prediction data for the current day, as the predicted value of the power demand. The predicted value of the power demand calculated by the demand calculation unit 50 in this manner may be supplied to the simultaneous power consumption calculation unit 60.

[0052] In this manner, in one embodiment, the demand calculation unit 50A may calculate the power demand of the first location.

[0053] The simultaneous balancing calculation unit 60 generates a power generation plan that satisfies the simultaneous balancing amount. Here, the simultaneous balancing amount may be defined as the power generation plan and the actual power generation being the same amount at the same time, on the premise that the demand (purchased power) of the self-consignment destination power is greater than the reverse flow of the self-consignment source power. In one embodiment, the simultaneous balancing calculation unit 60 may calculate a predicted value of reverse flow power based on a predicted value of power demand supplied from the demand calculation unit 50.

[0054] As described above, the power balancing calculation unit 60 may receive a predicted value of power demand from the demand calculation unit 50. The power balancing calculation unit 60 may receive various types of power demand predictions as the predicted value of power demand, such as prediction data for a predetermined time before, such as a prediction for the previous day or a prediction for several hours before, and prediction data for the current day.

[0055] The simultaneous and synchronous amount calculation unit 60 may also receive weather data including, for example, solar radiation amount, from the weather server 400. In particular, the simultaneous and synchronous amount calculation unit 60 may receive predictions of various weather data from the weather server 400. As described above, the simultaneous and synchronous amount calculation unit 60 may receive various predictions from the weather server 400, such as prediction data for a predetermined time before, such as a prediction for the previous day or a prediction for several hours before, prediction data for the current day, and prediction data for a predetermined time after, such as a future prediction.

[0056] In one embodiment, the power generation balancing calculation unit 60 may calculate a prediction of the amount of power generated by the power generation unit 10 based on weather data received from the weather server 400. In this case, the power generation balancing calculation unit 60 may calculate a prediction of the amount of power generated by the power generation unit 10 based on, for example, the following formula (2). (Power generation amount of the power generation unit 10) = (solar radiation amount) × (coefficient) (2) Here, the Japanese Industrial Standards (JIS) "Method for Estimating the Amount of Power Generated by a Photovoltaic Power Generation System" (JIS C8907:2005) prescribes an equation for estimating the amount of power generated by a photovoltaic power generation system from various parameters. In one embodiment, the equation may be used. Since these are prescribed in JIS C8907:2005, a detailed description will be omitted.

[0057] Furthermore, in one embodiment, the simultaneous power balancing calculation unit 60 may calculate the reverse flow power at the base where the power control system 1 is installed, for example, based on the following formula (3). Here, reverse flow power occurs when the generated power is greater than the power demand. For this reason, the reverse flow power may be calculated based on formula (3) for example, when the generated power is greater than the power demand. (Reverse flow power)=(power generation by power generation unit 10)-(power demand) (3) The power generation balancing calculation unit 60 may generate a power generation plan for the base based on this calculation result. For example, the calculation result may be generated as is as the power generation plan, or a value obtained by multiplying the calculation result by a certain coefficient may be generated as the power generation plan. In one embodiment, the power generation balancing calculation unit 60 may transmit the power generation plan for the reverse flow power generated in this manner to, for example, the output control unit 70 and / or the wide-area organization server 300. In one embodiment, the power generation balancing calculation unit 60 may transmit, for example, power generation a predetermined time ago, such as a power generation plan for the previous day or a power generation plan for several hours ago, and a power generation plan for the current day, to the output control unit 70 as the generated power generation plan for the reverse flow power.

[0058] Furthermore, in one embodiment, the simultaneous power balancing calculation unit 60 may receive a power command transmitted from the power server 200. In one embodiment, the simultaneous power balancing calculation unit 60 may receive a power command including a value of a power generation suppression amount (for example, %) from the power server 200. Also, in one embodiment, the simultaneous power balancing calculation unit 60 may receive a power command transmitted by the day before the specified day as a power command transmitted from the power server 200, or may receive a power command transmitted on the specified day. In this case, the simultaneous power balancing calculation unit 60 may transmit to the output control unit 70 a power generation plan for reverse flow power generated by taking into account the power command transmitted from the power server 200.

[0059] In this manner, the power generation balancing calculation unit 60 may generate a power generation plan for the base based on inputs such as power demand and solar radiation at the base. The power generation plan generated in this manner may be stored in any storage unit such as a storage unit provided in the power generation balancing calculation unit 60. The power generation balancing calculation unit 60 may also submit (transmit) the power generation plan generated in this manner to the wide-area organization server 300. The power generation balancing calculation unit 60 may also transmit the power generation plan generated as described above to the output control unit 70.

[0060] As described above, the power balancing calculation unit 60 may calculate the predicted value of reverse flow power based on the predicted value of power demand supplied from the demand calculation unit 50. In this case, the power balancing calculation unit 60 may register a power generation plan that rationally predicts power generation in advance in the cross-regional operation server 300 and / or the output control unit 70. The power balancing calculation unit 60 may then match the power generation plan with the actual power generation on the day in 30-minute increments (30-minute time intervals) (power balancing). Here, the power generation plan may be the amount of power to be reverse flowed to the power grid.

[0061] In one embodiment, the power generation amount calculation unit 60 may calculate the amount of power in the power generation plan based on, for example, the following formula (4). (Power consumption of power generation plan)=(output power of power generation unit 10)−(power consumption of load 30) (4) That is, the amount of power in the power generation plan can be calculated as (the amount of power generated by the power generation unit 10 (the amount of power output from the PCS))-(the amount of power self-consumed at that base). Here, the amount of power consumed at the base can be calculated from the amount of power generated by the power generation unit 10 (the amount of power generated from the PCS) and the power demand at the base. The amount of power generated by the power generation unit 10 (the amount of power generated from the PCS) can be calculated from data such as the amount of solar radiation.

[0062] Thus, in one embodiment, for example, the simultaneous power balancing calculation unit 60A may calculate the amount of power to be reverse-flowed from the first base to the power grid in a specified time interval based on the power demand of the first base and the amount of power generated by the power generation unit 10A at the first base.

[0063] The output control unit 70 controls the output of power generated by the power generation unit 10. In this case, the output control unit 70 may control the output of power output from the power generation unit 10, for example, by controlling a PCS included in the power generation unit 10. The output control unit 70 may also control the power input to the power adjustment unit 20 and / or the power output from the power adjustment unit 20. In this case as well, the output control unit 70 may control the power discharged by the power adjustment unit 20 and / or the power charged to the power adjustment unit 20, for example, by controlling a PCS included in the power adjustment unit 20.

[0064] In one embodiment, the output control unit 70 may control the output of power generated by the power generation unit 10, based on the power generation plan received from the power balancing calculation unit 60 and / or the power command received from the power server 200. The output control unit 70 may also control the power input to the power adjustment unit 20 and / or the power output from the power adjustment unit 20, based on the power generation plan received from the power balancing calculation unit 60 and / or the power command received from the power server 200.

[0065] In this case, the output control unit 70 may receive a power generation plan for reverse flow power transmitted from the simultaneous power balancing calculation unit 60. Here, the power generation plan that the output control unit 70 receives from the simultaneous power balancing calculation unit 60 may be power generation a predetermined time ago, such as a power generation plan for the previous day or a power generation plan for several hours ago, and a power generation plan for the current day.

[0066] Furthermore, the output control unit 70 may receive a power command transmitted from the power server 200. In one embodiment, the output control unit 70 may receive a power command including a value of a power generation suppression amount (e.g., %) from the power server 200. Furthermore, in one embodiment, the output control unit 70 may receive a power command transmitted by the day before a specific day as a power command transmitted from the power server 200, or may receive a power command transmitted on the specific day.

[0067] Furthermore, in one embodiment, the output control unit 70 may receive information on power transmitted from the smart meter 40. Here, the information on power transmitted from the smart meter 40 may be information on power (e.g., the amount of power) that flows backward among the power generated by the power generation unit 10. Also, the information on power transmitted from the smart meter 40 may be information on power (e.g., the amount of power) that flows backward among the power generated by the power generation unit 10 and that is self-consignment.

[0068] The output control unit 70 may control the output of power output from the power generation unit 10 based on the input of the information received as described above. For example, the output control unit 70 may satisfy a power command from an electric utility when controlling the power output from the power generation unit 10. Furthermore, for example, when controlling the power output from the power generation unit 10, the output control unit 70 may reduce the difference between the planned and actual amounts of power to be reversely flowed from the base where the power control system 1 is installed to the power grid, based on the power demand at the base.

[0069] In this way, for example, the output control unit 70A may control the power output by the power generation unit 10 so as to satisfy the power command from the electric utility company and reduce the difference between the planned and actual amount of power flowing back from the first base to the power grid based on the power demand.

[0070] Furthermore, the output control unit 70 may control the power input to the power adjustment unit 20 and / or the power output from the power adjustment unit 20 based on the input of the information received as described above. For example, the output control unit 70 may satisfy a power command from an electric utility when controlling the power input to the power adjustment unit 20 and / or the power output from the power adjustment unit 20. Furthermore, for example, the output control unit 70 may reduce a difference between a planned amount of power to be reversely flowed from the base where the power control system 1 is installed and an actual amount of power to be reversely flowed from the base to the power grid based on a power demand at the base. Furthermore, for example, the output control unit 70 may reduce a difference between a planned amount of power to be reversely flowed from the base to the power grid based on a power demand at the base where the power control system 1 is installed when controlling the power output from the power adjustment unit 20.

[0071] In this way, for example, the output control unit 70A may control at least one of the charging and discharging of the storage battery at the first location so as to satisfy the power command from the electric utility company and reduce the difference between the planned and actual amount of power flowing back from the first location to the power grid based on the power demand.

[0072] The output control unit 70 may transmit an output control value (e.g., %) for controlling the power output by the power generation unit 10 to the power generation unit 10. In this manner, the output control unit 70 may set the output control value to the power generation unit 10. Furthermore, the power adjustment unit 20 may transmit an adjustment value (e.g., %) for adjusting the power input to the power adjustment unit 20 and / or the power output from the power adjustment unit 20 to the power adjustment unit 20. In this manner, the output control unit 70 may set the adjustment value to the power adjustment unit 20.

[0073] When the output control unit 70 controls the power generation unit 10 and / or the power adjustment unit 20, it is ideal to make the difference between the planned amount of power to be reversely flowed to the power grid and the actual amount to be zero. In other words, when the output control unit 70 performs control, it is ideal to make the planned amount of power to be reversely flowed to the power grid and the actual amount to be the same at the same time (same amount at the same time). In other words, it is desirable that the plan of the power to be reversely flowed as self-consignment is equal to the power to be actually reversely flowed as self-consignment. However, for example, a situation in which the actual power generation (actual amount) is not the same as the power generation plan (planned) is also assumed. Therefore, in one embodiment, when the output control unit 70 performs control, it may be possible to reduce the difference between the planned amount of power to be reversely flowed to the power grid and the actual amount to be reversely flowed to the power grid as little as possible. If the planned amount of power to be reversely flowed to the power grid and the actual amount do not completely match, the difference may be settled as an imbalance fee.

[0074] Next, self-wheeling using the power control system 1A and the power control system 1B shown in FIG. 1 will be further described.

[0075] Hereinafter, as an example, the power control system 1A at the first base and the power control system 1B at the second base will be described as facilities owned and / or managed by a certain company X (hereinafter, appropriately referred to as Company X). Here, Company X may be another company other than the company itself, for example, a joint venture established by a company that has a close relationship with the company itself. In particular, the power control system 1A at the first base includes a solar power generation facility owned and / or managed by Company X, as an example. Also, the power control system 1B at the second base includes a production plant facility owned and / or managed by Company X, as an example. Then, a situation (self-consignment) will be described in which the power generated in the power control system 1A at the first base (for example, the power generation unit 10A) is reversely flowed to the power grid and transmitted to the second base, and consumed in the power control system 1B (for example, the load 30B). In this case, the first base having the power generation unit 10A and the second base having the load 30B are different power receiving locations. In one embodiment, when realizing self-wheeling, an attempt is made to calculate the planned value of power generation while taking into account output suppression.

[0076] In self-dispatch, as a condition for simultaneous matching of planned values ​​of power generation, it is required that the plan (scheduled) amount of power to be reverse-flowed to the power grid and the actual amount of power to be reverse-flowed (actual) match (as much as possible). That is, in Fig. 1, it is required that the plan (scheduled) information (e.g., amount of power) of the power to be reverse-flowed out of the power generated by the power generation unit 10, which is information transmitted from the smart meter 40 to the output control unit 70, match (as much as possible) with the actual amount of power to be reverse-flowed (actual).

[0077] For example, when the amount of power actually generated (performance) is less than the amount of power (planned) in the generated power generation plan, the difference between the two amounts of power that is insufficient is called a shortage imbalance. In this case, the condition that the plan (plan) of the amount of power to be reversely flowed to the power grid and the amount of power actually reversely flowed (performance) match is not met (power generation imbalance). On the other hand, for example, when the amount of power actually generated (performance) is greater than the amount of power (planned) in the generated power generation plan, the difference between the two amounts of power that is left over is called a surplus imbalance. In this case, too, the condition that the plan (plan) of the amount of power to be reversely flowed to the power grid and the amount of power actually reversely flowed (performance) match is not met (power generation imbalance). Therefore, the power control system 1 according to one embodiment controls power so as to reduce such a power generation imbalance.

[0078] Fig. 2 is a flowchart for explaining the operation of the power control system 1A at the first base. Hereinafter, with reference to Fig. 2, the operation of performing simultaneous balancing of planned power generation values ​​while taking into account output suppression when realizing self-consignment by the power control system 1A and the power control system 1B will be further explained.

[0079] The operation shown in Fig. 2 may be performed for each time period divided into 30-minute intervals over 24 hours in a day, for example. In other words, the operation shown in Fig. 2 may be performed a maximum of 48 times in a 24-hour day.

[0080] First, as an example, an operation performed by the power control system 1A at 12:00 on the day before the day (today) on which the power control is performed will be described. In this case, the operation shown in Fig. 2 may be performed for a total of 48 frames divided into 30-minute time periods on the day.

[0081] 2 starts, the demand calculation unit 50A of the power control system 1A at the first base calculates an initial power demand at the first base (step S11). Here, the initial power demand at the first base may be, for example, an initial power demand by the load 30A. In step S11, the demand calculation unit 50A may calculate the initial power demand at the first base based on the power information received from the smart meter 40 and the initial weather data received from the weather server 200. The information on the initial power demand at the first base calculated by the demand calculation unit 50A in step S11 may be transmitted to the simultaneous power balance calculation unit 60A.

[0082] Next, the simultaneous power balancing calculation unit 60A generates an initial power generation plan for the first base (step S13). In step S13, the simultaneous power balancing calculation unit 60A may generate the initial power generation plan for the first base based on the initial power demand information for the first base received from the demand calculation unit 50A and the initial weather data received from the weather server 200. The initial power generation plan generated in step S13 may be transmitted to the wide-area organization server 300 and the output control unit 70A.

[0083] Next, the output control unit 70A may store, for example, a process for controlling the output of power generated by the power generation unit 10 in an arbitrary storage unit, for example, internally (step S15). In step S15, the output control unit 70A may control the output of power generated by the power generation unit 10 based on the initial power generation plan received from the simultaneous power generation balance calculation unit 60A. In step S15, the output control unit 70A may transmit an initial output control value to the power generation unit 10. This allows the power generation unit 10 to control the output based on the initial output control value.

[0084] Next, as an example, an operation performed by the power control system 1A on the day before and up to the day on which the power control is performed (today) will be described. In this case, the operation shown in FIG. 2 may be performed for a total of 48 frames divided into 30-minute time periods on the day.

[0085] 2 starts, the demand calculation unit 50A of the power control system 1A at the first base calculates an updated power demand at the first base (step S11). Here, the updated power demand at the first base may be, for example, an updated power demand due to the load 30A. In step S11, the demand calculation unit 50A may calculate the updated power demand at the first base based on the power information received from the smart meter 40 and the updated weather data received from the weather server 200. The information on the updated power demand at the first base calculated by the demand calculation unit 50A in step S11 may be transmitted to the simultaneous power balance calculation unit 60A.

[0086] Next, the power balancing calculation unit 60A calculates the power balancing amount at the first base and generates an updated power generation plan (step S13). In step S13, the power balancing calculation unit 60A may calculate the power balancing amount at the first base and generate an updated power generation plan based on the updated power demand information at the first base received from the demand calculation unit 50A and the updated weather data received from the weather server 200. The updated power generation plan generated in step S13 may be transmitted to the wide-area organization server 300 and the output control unit 70A.

[0087] Next, the output control unit 70A may control, for example, the updated output of power generated by the power generation unit 10 (step S15). In step S15, the output control unit 70A may control the updated output of power generated by the power generation unit 10 based on the updated power generation plan received from the simultaneous power balancing calculation unit 60A and the updated power command value received from the power server 200. In step S15, the output control unit 70A may transmit the updated output control value to the power generation unit 10. This allows the power generation unit 10 to control the output based on the updated output control value.

[0088] Next, as an example, an operation performed one hour before the day (current day) on which the power control system 1A performs power control will be described. In this case, the operation shown in Fig. 2 may be targeted for a 30-minute time limit one hour or more after the current day.

[0089] 2 starts, the demand calculation unit 50A of the power control system 1A at the first base calculates the final power demand at the first base (step S11). Here, the final power demand at the first base may be, for example, the final power demand by the load 30A. In step S11, the demand calculation unit 50A may calculate the final power demand at the first base based on the power information received from the smart meter 40 and the final weather data received from the weather server 200. The information on the final power demand at the first base calculated by the demand calculation unit 50A in step S11 may be transmitted to the simultaneous power balance calculation unit 60A.

[0090] Next, the power balancing calculation unit 60A calculates the power balancing amount at the first base and generates a final power generation plan (step S13). In step S13, the power balancing calculation unit 60A may calculate the power balancing amount at the first base and generate a final power generation plan based on the final power demand information at the first base received from the demand calculation unit 50A and the final weather data received from the weather server 200. The final power generation plan generated in step S13 may be transmitted to the wide-area organization server 300 and the output control unit 70A.

[0091] Next, the output control unit 70A may control, for example, the further updated output of the power generated by the power generation unit 10 (step S15). In step S15, the output control unit 70A may control the further updated output of the power generated by the power generation unit 10 based on the final power generation plan received from the simultaneous power generation calculation unit 60A and the updated power command value received from the power server 200. In step S15, the output control unit 70A may transmit the further updated output control value to the power generation unit 10. This allows the power generation unit 10 to control the output based on the further updated output control value.

[0092] Next, as an example, an operation performed by the power control system 1A before 0 hours on the day (current day) on which the power control is performed will be described. In this case, the operation shown in Fig. 2 may be targeted for a time limit of 30 minutes before 0 hours on the current day.

[0093] When the operation shown in FIG. 2 starts, the demand calculation unit 50A of the power control system 1A at the first base calculates the final power demand at the first base (step S11). Here, the final power demand at the first base may be, for example, the final power demand by the load 30A. In step S11, the demand calculation unit 50A may calculate the final power demand at the first base based on the power information received from the smart meter 40 and the final weather data received from the weather server 200. The information on the final power demand at the first base calculated by the demand calculation unit 50A in step S11 may be transmitted to the simultaneous power balance calculation unit 60A. This operation may be performed in addition to the operation of step S11 in the operation performed one hour before the day (current day) on which the power control system 1A performs power control.

[0094] Next, the power balancing calculation unit 60A calculates the power balancing amount at the first base and generates a final power generation plan (step S13). In step S13, the power balancing calculation unit 60A may calculate the power balancing amount at the first base and generate a final power generation plan based on the information on the final power demand at the first base received from the demand calculation unit 50A and the final weather data received from the weather server 200. The final power generation plan generated in step S13 may be transmitted to the wide-area organization server 300 and the output control unit 70A. This operation may be performed in addition to the operation of step S13 in the operation performed one hour before the day (current day) on which the power control system 1A performs power control described above.

[0095] Next, the output control unit 70A may control, for example, the final output of the power generated by the power generation unit 10 (step S15). In step S15, the output control unit 70A may control the final output of the power generated by the power generation unit 10 based on the final power generation plan received from the simultaneous power generation calculation unit 60A and the final power command value received from the power server 200. In step S15, the output control unit 70A may transmit the final output control value to the power generation unit 10. This allows the power generation unit 10 to control the output based on the final output control value. This operation may be performed in addition to the operation of step S15 in the operation performed one hour before the day (current day) on which the power control system 1A performs power control described above.

[0096] Next, power control by power control system 1A will be further described with specific examples with reference to Figs. 3 to 6.

[0097] In Figs. 3 to 6, the horizontal axis indicates time, and the vertical axis indicates the power generation capacity ratio. In Figs. 3 to 6, the horizontal axis indicates 24 hours of a day divided into 30-minute increments (48 divisions). The horizontal axis in Figs. 3 to 6 may start at midnight and end at 11:59 pm. In Figs. 3 to 6, the power generation capacity ratio on the vertical axis may be expressed in units of, for example, [%]. Here, the power generation capacity ratio [%] may be calculated by assuming that, in the case of power generation unit 10A, the smaller of the capacity of the solar cell included in power generation unit 10A and the capacity of the PCS included in power generation unit 10A is set to 100.

[0098] Fig. 3 shows a case where the scheduled power demand calculated by the demand calculation unit 50A is greater than the scheduled power of the power command received from the power server 200 at the time the power generation plan is generated. In Fig. 3, the scheduled power (scheduled power generation) generated by the power generation unit 10A is shown by a curve. As shown in Fig. 3, the forecast power generation (scheduled power generation) of the power generation unit 10A is almost zero at the start of midnight, peaks at noon in the center of the graph, and is again almost zero at the end of 23:59.

[0099] In the case shown in Fig. 3, the output control unit 70A targets the region where the planned power generated by the power generation unit 10A (planned power generation) exceeds the planned power of the power demand as the output control target (planned output control value). That is, in this case, even if the region exceeds the planned power of the power command, the region that does not exceed the planned power of the power demand is not targeted for output control.

[0100] Fig. 4 shows a case where a power generation plan (schedule) as shown in Fig. 3 is generated, but the actual power demand is less than the schedule. It is assumed that the actual power generation (actual power generation) of the power generation unit 10A shown in Fig. 4 is almost the same as the power generation schedule shown in Fig. 3. It is also assumed that the actual power command power received from the power server 200 shown in Fig. 4 is almost the same as the scheduled power command power shown in Fig. 3. On the other hand, it is assumed that the actual power demand power as shown in Fig. 4 is less than the scheduled power demand power shown in Fig. 3, and is less than the actual power command power shown in Fig. 4.

[0101] In the case shown in Fig. 4, the output control unit 70A subjects the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the actual power command to output control (actual output control value). However, in such a case, the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the actual power demand is not subject to output control. That is, in this case, the region that exceeds the actual power demand but does not exceed the planned power of the actual power command becomes the power that flows backward (actual reverse flow).

[0102] As shown in Fig. 3, at the time when the power generation plan (plan) was generated, no power was being generated to cause a reverse power flow. Therefore, if an actual reverse power flow were to occur as shown in Fig. 4, this would cause an imbalance in power generation, which is undesirable. Therefore, the output control unit 70A controls the power generation unit 10 and / or the power adjustment unit 20 so as to prevent the situation shown in Fig. 4 from occurring.

[0103] Fig. 5 is a diagram for explaining an example of an operation actually executed by the output control unit 70A when the situation shown in Fig. 4 is likely to occur in the power control system 1A. In Fig. 4, if the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the power of the actual power demand is not subject to output control, an imbalance in power generation will occur. Therefore, as shown in Fig. 5, the output control unit 70A subjects the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the power of the actual power demand to output control (actual output control value). By controlling in this way, in the power control system 1A, no reverse flow of power will be generated, just as at the time when the power generation plan (schedule) was generated.

[0104] Fig. 6 is a diagram for explaining another example of the operation actually executed by the output control unit 70A when the situation shown in Fig. 4 is likely to occur in the power control system 1A. In Fig. 4, if the region in which the power actually generated by the power generation unit 10A (actual power generation) exceeds the power of the actual power demand is not subject to output control, power that flows back to the grid power will occur (actual back flow). Therefore, the output control unit 70A may charge the amount of power shown as the actual back flow in Fig. 4 to the storage battery of the power adjustment unit 20A as shown in Fig. 6 (actual adjustment value). Even with this control, no power that flows back will occur in the power control system 1A, just like when the power generation plan (schedule) was generated.

[0105] In this way, the power control system 1 according to one embodiment can realize self-consignment of generated power while satisfying power commands from electric power companies.

[0106] Next, power control by power control system 1A will be further described with reference to other specific examples with reference to Figs.

[0107] 7 to 11, similarly to FIGS. 3 to 6, the horizontal axis indicates time and the vertical axis indicates the power generation capacity ratio.

[0108] Fig. 7 shows a case where the scheduled power of the power command received from the power server 200 is greater than the scheduled power of the power demand calculated by the demand calculation unit 50A at the time when the power generation plan is generated. In Fig. 7, as in Fig. 3, the scheduled power to be generated by the power generation unit 10A (scheduled power generation) is shown by a curve.

[0109] In the case shown in Fig. 7, the output control unit 70A targets the region where the planned power generated by the power generation unit 10A (power generation plan) exceeds the planned power of the power command as the target of output control (scheduled output control value). That is, in this case, the region where the planned power of the power demand is exceeded but the planned power of the power command is not targeted for output control. In such a case, in the region where the planned power generated by the power generation unit 10A (power generation plan) exceeds the planned power of the power demand but does not exceed the planned power of the power demand, power can be reversed (reverse flow plan).

[0110] Fig. 8 shows a case where a power generation plan (schedule) like that shown in Fig. 7 is generated, but the actual power demand is higher than the schedule. It is assumed that the actual power generation (actual power generation) of the power generation unit 10A shown in Fig. 8 is almost the same as the scheduled power generation shown in Fig. 7. It is also assumed that the actual power command power received from the power server 200 shown in Fig. 8 is also almost the same as the scheduled power command power shown in Fig. 7. On the other hand, it is assumed that the actual power demand power shown in Fig. 8 is higher than the scheduled power demand power shown in Fig. 7, but is lower than the actual power command power shown in Fig. 8.

[0111] In the case shown in FIG. 8, the output control unit 70A targets the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the actual power command as the output control value (actual output control value). In such a case, the region where the power exceeds the actual power demand but does not exceed the planned power of the actual power command becomes the power that flows backward (actual reverse flow). However, in this case, the amount of the power that flows backward (actual reverse flow) shown in FIG. 8 is less than the amount of the power that flows backward (planned reverse flow) shown in FIG. 7. Therefore, if an actual reverse flow occurs as shown in FIG. 8, an imbalance occurs, which is undesirable. For this reason, the output control unit 70A controls the power generation unit 10 and / or the power adjustment unit 20 so as to prevent the situation shown in FIG. 8 from occurring.

[0112] FIG. 9 is a diagram for explaining an example of an operation actually performed by the output control unit 70A when the situation shown in FIG. 8 is likely to occur in the power control system 1A. In FIG. 8, if the reverse flow power (actual reverse flow) is not increased, an imbalance occurs. Therefore, as shown in FIG. 9, the output control unit 70A compensates for the power amount that is insufficient in the reverse flow power (actual reverse flow) with the power discharged by the power adjustment unit 20A (actual adjustment value). That is, the output control unit 70A controls so that the power discharged by the power adjustment unit 20A (actual adjustment value) is added to the reverse flow power (actual reverse flow). By controlling in this way, the power control system 1A can generate the same amount of reverse flow power as at the time when the power generation plan (plan) was generated (FIG. 7) (FIG. 9).

[0113] In this way, the power control system 1 according to one embodiment can realize self-consignment of generated power while satisfying power commands from electric power companies.

[0114] Fig. 10 shows a case where a power generation plan (schedule) like that shown in Fig. 7 is generated, but the actual power demand is less than the schedule. It is assumed that the actual power generation (actual power generation) of the power generation unit 10A shown in Fig. 10 is almost the same as the power generation schedule shown in Fig. 7. It is also assumed that the actual power command power received from the power server 200 shown in Fig. 10 is also almost the same as the scheduled power command power shown in Fig. 7. On the other hand, it is assumed that the actual power demand power is less than the scheduled power demand power shown in Fig. 7, as shown in Fig. 10.

[0115] In the case shown in FIG. 10, the output control unit 70A targets the region where the power actually generated by the power generation unit 10A (actual power generation) exceeds the actual power command as the output control value (actual output control value). In such a case, the region where the power exceeds the actual power demand but does not exceed the planned power of the actual power command becomes the power that flows backward (actual reverse flow). However, in this case, the amount of the power that flows backward (actual reverse flow) shown in FIG. 10 is greater than the amount of the power that flows backward (planned reverse flow) shown in FIG. 7. Therefore, if an actual reverse flow occurs as shown in FIG. 10, an imbalance occurs, which is not desirable. For this reason, the output control unit 70A controls the power generation unit 10 and / or the power adjustment unit 20 so as to prevent the situation shown in FIG. 10 from occurring.

[0116] FIG. 11 is a diagram for explaining an example of an operation actually performed by the output control unit 70A when the situation shown in FIG. 10 is likely to occur in the power control system 1A. In FIG. 10, if the reverse flow power (actual reverse flow) is not reduced, an imbalance occurs. Therefore, the output control unit 70A charges the power adjustment unit 20A with the surplus power amount of the reverse flow power (actual reverse flow) shown in FIG. 10 (actual adjustment value) as shown in FIG. 11. That is, the output control unit 70A controls so that a part of the reverse flow power (actual reverse flow) is charged to the power adjustment unit 20A (actual adjustment value). By controlling in this way, in the power control system 1A, it is possible to generate the same amount of reverse flow power as at the time when the power generation plan (schedule) was generated (FIG. 7) (FIG. 11).

[0117] In this way, the power control system 1 according to one embodiment can realize self-consignment of generated power while satisfying power commands from electric power companies.

[0118] As described above, when the amount of power (planned) in the generated power generation plan does not match the amount of power actually generated (actual), a shortage imbalance or surplus imbalance occurs. In such a case, the condition that the plan (planned) amount of power to be reverse-flowed to the power grid matches the amount of power (actual) that is actually reverse-flowed is not met (power generation imbalance). As a measure against the surplus imbalance, the actual power generation can be reduced by controlling the power generation output. Therefore, the surplus imbalance can be reduced to zero by controlling the power generation output. However, it is difficult to reduce the shortage imbalance to zero by controlling the power generation output. For this reason, it is also possible to reduce the amount of power in the power generation plan in advance in the power generation plan. However, if this is done, the reduced amount of power (the amount of imbalance) will be output-controlled, resulting in waste.

[0119] Therefore, by connecting solar panels exceeding the rated output power of the PCS, so-called overloading, the rated output of the PCS may be used as the power generation performance, making it difficult for a shortage imbalance to occur. In addition, by doing so, it is possible to make it difficult for an output control of a surplus imbalance to occur. Furthermore, by reducing the rated output power of the PCS, it is expected that the cost of the PCS can be reduced. By realizing a state of overloading, the planned value of power generation can be suitably executed at the same time, thereby suppressing the imbalance and increasing profits. In addition, according to the power control system 1 according to one embodiment, the power can be adjusted in the power adjustment unit 20. Therefore, the imbalance can be adjusted by adjusting the power in the power adjustment unit 20.

[0120] As in the above-described embodiment, in the case of self-consignment, the first base and the second base may be different bases. In one embodiment, the simultaneous power balance calculation unit 60 may calculate the amount of power to be reversely flowed from the first base to the power grid in a predetermined time period and supplied to the second base based on the power demand and the amount of power generated by the power generation unit of the first base. In another embodiment, the output control unit 70 may perform control so as to satisfy the power command from the electric utility and reduce the difference between the planned amount of power to be reversely flowed from the first base to the power grid and supplied to the second base based on the power demand and the actual amount of power.

[0121] Although the above-mentioned embodiment has been described as a representative example, it is clear to those skilled in the art that many modifications and substitutions are possible within the spirit and scope of the present disclosure. Therefore, the present disclosure should not be interpreted as being limited by the above-mentioned embodiment, and various modifications and changes are possible without departing from the scope of the claims. For example, it is possible to combine multiple building blocks shown in the configuration diagram of the embodiment into one, or to divide one building block.

[0122] The above-described embodiments are not limited to implementation as a system such as power control system 1A and / or power control system 1 B. For example, the above-described embodiments may be implemented as a device (e.g., a power control device) constituting at least a part of a system such as power control system 1A and / or power control system 1 B.

[0123] The above-mentioned embodiment has been described as an implementation of a system such as the power control system 1A at the first base and the power control system 1B at the second base. However, the system according to one embodiment may include not only the power control system 1A at the first base and the power control system 1B at the second base, but also the power control system 1C at the third base, or may include more than one power control system. In this case, for example, the simultaneous power balance calculation unit 60A may calculate the amount of power that flows back from the first base to the power grid in a predetermined time section and is supplied to multiple bases other than the first base, based on the power demand at the first base and the amount of power generated by the power generation unit at the first base. In addition, the output control unit 70A may perform control so as to satisfy the power command from the electric utility and reduce the difference between the planned amount of power that flows back from the first base to the power grid and the actual amount of power that is supplied to multiple bases other than the first base, based on the power demand.

[0124] The above-mentioned embodiment has been described assuming a case where the power generated by the power generating unit 10A at the first base is self-consigned to the load 30B at the second base. However, as described above, in one embodiment, the power generated by the power generating unit 10B at the second base may be self-consigned to the load 30A at the first base. In this case, the simultaneous power supply calculation unit 60A may calculate the amount of power that flows back from the second base to the power grid in a predetermined time segment and is supplied to the first base based on the power demand of the second base and the amount of power generated by the power generating unit at the second base. In addition, the output control unit 70A may perform control so as to satisfy the power command from the electric utility and reduce the difference between the planned amount of power that flows back from the second base to the power grid and is supplied to the first base based on the power demand of the second base.

[0125] In the above-described embodiment, a system such as the power control system 1 may include a power generation unit 10 that performs solar power generation or the like. In this case, for example, the power control system 1A may include a power generation unit 10A installed at a first base, and the power control system 1B may include a power generation unit 10B installed at a second base. On the other hand, a system such as the power control system 1 may not include the power generation unit 10 as a system for controlling the power generation unit 10 that performs solar power generation or the like.

[0126] The above-described embodiment may be implemented, for example, as a control method for the above-described system or device. The above-described embodiment may be implemented, for example, as a program executed in a computer of the above-described system or device. Furthermore, the above-described embodiment may be implemented, for example, as a recording medium on which a program executed in a computer of the above-described system or device is recorded, i.e., a computer-readable recording medium. [Explanation of symbols]

[0127] 1. Power Control System 10 Power Generation Section 20 Power adjustment section 30 Load 40 Smart Meter 50 Demand Calculation Department 60 Simultaneous and Equal Quantity Calculation Section 70 Output control section 200 Power Server 300 Cross-regional organization server 400 Weather Server

Claims

1. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls power generation of the power generation unit so as to reduce a difference between a planned amount of power flowing back from the first base to the power grid and an actual amount of power flowing back from the first base to the power grid when the power demand becomes smaller than planned, and controls the power generated by the power generation unit so as not to exceed a power command from an electric utility company; A power control system comprising:

2. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls the power output by the power generation unit so as to satisfy a power command from an electric power utility and reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base to the power grid based on the power demand; A power control system comprising: A power control system in which the rated output of the power control system is regarded as the actual power generation result by connecting the power generation unit that exceeds the rated output power of the power control system.

3. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls charging of the storage battery at the first base so as to reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base, so that the power that the power generation unit reverse-flows does not exceed a power command from the electric power utility, when the power demand is less than planned, and controls discharging of the storage battery at the first base so as to reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the power generation unit, so that the power that the power generation unit reverse-flows does not exceed a power command from the electric power utility, when the power demand is more than planned; A power control system comprising:

4. The output control unit:

4. The power control system according to claim 3, wherein, when the power demand is less than planned, charging of the storage battery at the first location is controlled so as to reduce a difference between the planned and actual amount of power to be flowed back from the first location to the power grid, so that the sum of the power generated by the power generation unit and the power charged to the storage battery is within a range that does not exceed a power command by an electric power utility, and when the power demand is more than planned, discharging of the storage battery at the first location is controlled so as to reduce a difference between the planned and actual amount of power to be flowed back from the first location to the power grid, so that the sum of the power generated by the power generation unit and the power discharged from the storage battery is within a range that does not exceed a power command by an electric power utility.

5. The power generation unit is further provided, The power control system according to claim 1 , wherein the power generation unit is installed at the first base.

6. The power control system according to any one of claims 1 to 5, wherein the simultaneous power balance calculation unit calculates the amount of power to be reverse-flowed from the first base to the power grid in a specified time interval and to be supplied to a second base different from the first base, based on the power demand and the amount of power generated by the power generation unit of the first base.

7. The power control system according to any one of claims 1 to 6, wherein the output control unit performs control so as to satisfy a power command from an electric utility company and reduce the difference between the planned amount of power to be reverse-flowed from the first base to the power grid and supplied to a second base different from the first base based on the power demand, and the actual amount of power to be supplied.

8. The power control system according to any one of claims 1 to 5, wherein the simultaneous balancing calculation unit calculates the amount of power to be supplied to the first base from the second base in a specified time interval based on the power demand of a second base different from the first base and the amount of power generated by a power generation unit of the second base.

9. The power control system of any one of claims 1 to 5 or claim 8, wherein the output control unit performs control so as to satisfy a power command from an electric utility company and, based on the power demand of a second base different from the first base, reduce the difference between the planned and actual amount of power to be supplied to the first base and the amount of power to be reverse-flowed from the second base to the power grid.

10. The power control system according to any one of claims 1 to 5, wherein the simultaneous power balance calculation unit calculates the amount of power to be reverse-flowed from the first base to the power grid in a specified time interval and to be supplied to a plurality of bases other than the first base, based on the power demand and the amount of power generated by the power generation unit of the first base.

11. The power control system of any one of claims 1 to 5 or claim 10, wherein the output control unit performs control so as to satisfy a power command from an electric utility company and reduce the difference between the planned and actual amounts of power to be flowed back from the first base to the power grid based on the power demand and to be supplied to a plurality of bases other than the first base.

12. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls power generation of the power generation unit so as to reduce a difference between a planned amount of power flowing back from the first base to the power grid and an actual amount of power flowing back from the first base to the power grid when the power demand becomes smaller than planned, and controls the power generated by the power generation unit so as not to exceed a power command from an electric utility company; A power control device comprising:

13. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls the power output by the power generation unit so as to satisfy a power command from an electric power utility and reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base to the power grid based on the power demand; A power control device comprising: A power control device that, by connecting the power generation unit that exceeds the rated output power of the power device, makes the rated output of the power control device its actual power generation result.

14. A demand calculation unit that calculates an electric power demand of a first base; a power balance calculation unit that calculates an amount of power to be reverse-flowed from the first base to the power grid in a predetermined time segment based on the power demand and an amount of power generated by a power generation unit at the first base; an output control unit that controls charging of the storage battery at the first base so as to reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the first base, so that the power that the power generation unit reverse-flows does not exceed a power command from the electric power utility, when the power demand is less than planned, and controls discharging of the storage battery at the first base so as to reduce a difference between a planned amount of power to be reverse-flowed from the first base to the power grid and an actual amount of power to be reverse-flowed from the power generation unit, so that the power that the power generation unit reverse-flows does not exceed a power command from the electric power utility, when the power demand is more than planned; A power control device comprising:

Citation Information

Patent Citations

  • Power conditioner operation controller, operation control method, and operation control program

    JP2017229213A

  • Energy management system and energy management method

    JP2020190924A

  • Self consignment system and self consignment method

    JP2021052557A

  • Power monitoring control device, power monitoring control method, and control program

    JP2021141769A