A temporary lifting sling for a space truss ball joint, a system and a lifting method thereof
By using a temporary lifting system for the ball joints of the space frame, combined with hydraulic lifters and electrical synchronous control, the problems of high material consumption, long equipment rental periods, and long construction cycles in existing space frame assembly methods have been solved, achieving efficient and safe space frame lifting.
Patent Information
- Application Number
- CN202610728397.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-05-25
- Publication Date
- 2026-06-26
AI Technical Summary
Existing methods for assembling space frames require the erection of temporary supports and lifting platforms, resulting in high material consumption, long equipment rental periods, high construction costs, and safety risks.
A temporary lifting system using a space frame ball node is adopted, including welded balls, steel sleeves, stiffening plates and base plates. Combined with a hydraulic lifter, steel strands and an electrical synchronous control system, it achieves vertical lifting and synchronous attitude control. Power is provided by a hydraulic pump station, and a lifting platform is erected using permanent columns. A modular hydraulic pump station and computer control system are used for synchronous lifting.
This enabled flexible use and high utilization of the equipment, reduced the impact of temporary supports, improved construction safety and efficiency, reduced construction costs, and avoided permanent structural damage.