A truss integral lifting bridge high pier climbing formwork device and construction method

Through the truss integral lifting bridge high pier formwork climbing device, the embedded climbing rails and hydraulic hoisting mechanisms are used to solve the safety hazards and low efficiency problems of the existing high pier construction methods, and achieve efficient, safe and economical high pier construction results.

CN111749140BActive Publication Date: 2025-03-21SHAANXI PUHUI STEEL STRUCTURE CO LTD
1 Cites 0 Cited by

Patent Information

Application Number
CN202010714107.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-07-23
Publication Date
2025-03-21
Estimated Expiration
2040-07-23

AI Technical Summary

Technical Problem

The existing high-pier construction methods have safety hazards, low construction efficiency and low economic benefits, which are difficult to meet the needs of mountain highway construction.

Method used

The truss integral lifting bridge high pier formwork climbing device is adopted. This device achieves safe, reliable and efficient construction of high pier through technical means such as embedded climbing rails, hydraulic hoisting mechanisms and penetrating jacks.

Benefits of technology

It improves the safety and efficiency of high piers construction, reduces construction costs, improves economic benefits, and takes into account the construction progress, quality and safety.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

A truss integral lifting type bridge high pier climbing formwork device and construction method, four embedded climbing rail fixing parts on the rectangular corners of the bridge pier are all provided with climbing rails, the upper end of the climbing rail is provided with a top truss operating platform, the lower end is provided with a climbing rail anchor bolt, an outer formwork is provided between two circumferentially adjacent climbing rails, an inner formwork is provided on the inner side of the outer formwork, an outer formwork truss operating platform is provided on the outer side of the climbing rail, a hydraulic jacking mechanism is provided between the outer formwork truss operating platform and the climbing rail, the outer formwork truss operating platform is connected to the top truss operating platform through a first hydraulic lifting mechanism, an inner formwork truss operating platform is provided on the inner side of the inner formwork, and the inner formwork truss operating platform is connected to the top truss operating platform through a second hydraulic lifting mechanism; the construction method comprises installing the climbing rails and the top truss operating platform; lifting the outer formwork and the outer formwork truss operating platform and pouring the pier body solid transition section concrete; climbing rail jacking; installing the inner formwork and the inner formwork truss operating platform; constructing the standard section of the bridge pier body; and dismantling the entire structure.
Need to check novelty before this filing date? Find Prior Art