A drainage-adjustable slope protection ecological restoration system and method

By laying the ecological blanket horizontally and using the waste tire body and drainage adjustment parts, the problems of autonomous drainage and unstable fixation in the existing ecological blanket slope protection construction are solved, efficient construction and independent drainage adjustment are achieved, and the anti-scouring ability of the slope protection is enhanced.

CN118639604BActive Publication Date: 2024-10-18WATER RESOURCES RES INST OF SHANDONG PROVINCE
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411103231.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-10-18
Estimated Expiration
2044-08-13

AI Technical Summary

Technical Problem

The existing ecological blanket slope protection construction lacks independent drainage adjustment function, resulting in rainwater loss or accumulation problems, and the construction efficiency of traditional fixed nails is low and unstable.

Method used

The ecological blanket is laid horizontally and the waste tire body interceptor is used to divide the slope surface. Combined with drainage adjustment parts and fixing mechanisms, autonomous drainage adjustment and rapid fixation are achieved.

Benefits of technology

It improves construction safety and efficiency, realizes the independent drainage adjustment of the slope and the stable fixation of the ecological blanket, avoids soil erosion and waterlogging, and enhances the anti-scouring ability of the slope protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118639604B_ABST
    Figure CN118639604B_ABST
Patent Text Reader

Abstract

The present invention proposes a drainage-adjustable slope protection ecological restoration system and method, which relates to the technical field of slope protection restoration; the system includes an interception body arranged along the slope surface, the interception body divides the slope surface into a plurality of laying units, an ecological blanket is laid in the laying unit, and the ecological blanket is fixed by a fixing mechanism; the interception body is composed of closely arranged tire bodies, and overflow holes are formed between adjacent tire bodies; the interior of the tire body has a cavity, and a drainage hole is formed between the cavity and the slope surface; a drainage adjustment member is provided at the drainage hole, and the drainage adjustment member includes a rotating shaft, a baffle, a compression spring, etc., and an inverted "V"-shaped structure is formed between two groups of baffles. The present invention forms an integrated system of quick construction and regional fixation with the tire body as the axis + small area construction + blanket surface area pressure holding and fixing, which can solve the problems of low construction efficiency, easy overhead of the blanket surface, loose fixation, and inability of slope protection to self-drain and adjust the drainage when the traditional ecological blanket is constructed with fixed nails.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of slope protection and restoration, and in particular to a drainage-adjustable slope protection ecological restoration system and method. Background Art

[0002] In the past, slope protection mostly used slope protection bricks, concrete and other structures. With the implementation of ecological concepts, the above slope protection structures cannot meet higher demands and need to seek better options. Ecological blanket is a new type of slope protection material. It is an integrated new ecological slope protection material composed of composite fiber fabrics, anti-filtration non-woven fabrics, diversified grass seeds, fertilizer layers and degradable fabrics. While preventing hydraulic erosion and soil loss on the slope bank, it can achieve the effect of slope ecological restoration and landscape greening. It is an ideal slope protection and repair material. Figure 1 At present, the ecological blanket is used perpendicular to the direction of the river channel. The ecological blanket is laid on the flat slope surface. The blanket surface of the ecological blanket is fixed with fixing nails. The specific construction process is slope leveling → grooving → laying → overlapping and anchoring → maintenance.

[0003] The following areas need to be improved in the current ecological blanket construction process: a. The slope protection grass in the ecological blanket requires appropriate moisture. Drought and flood disasters will affect the growth of the slope protection grass, and then affect the ecological restoration effect of the slope protection. Most of the current ecological blanket slope protection does not have the function of autonomous drainage and regulation, which may lead to the following situation: when it rains lightly, the ecological blanket has not fully absorbed the rainwater, and the rainwater flows down the slope quickly, causing precious water resources to flow away in vain and cause waste; if some rain-blocking structures are set on the slope to slow down the flow rate of water, rainwater resources can be fully utilized to solve the problem of under-utilization in light rain, but when it rains heavily, the rain-blocking structure will have a negative effect, causing the slow water flow to easily accumulate, forming waterlogging, and easily drowning grass seeds or plants, and slow drainage can easily cause excessive soaking of the slope, which can easily lead to collapse and landslide due to stagnant water; therefore, it is very necessary to deepen research on how to achieve autonomous drainage and regulation of slope protection in different situations. b. The ecological blanket is laid perpendicular to the direction of the river, that is, it is laid longitudinally from top to bottom along the slope. After laying, multiple fixing nails need to be installed on the blanket surface and the edge joints of the ecological blanket. From the top to the bottom of the slope, the ecological blanket has a large span. For some steep slopes, it is inconvenient for workers to stand on the slope for construction, which is very dangerous. They need to be tied with safety ropes for construction, which will lead to slow construction speed and low efficiency. In addition, the use of fixing nails is easy to have poor fixing effect, especially in windy weather, it is easy to lift the ecological blanket. In addition, due to the different construction levels of workers, it is also easy to have the problem of ecological blanket overhead, and the construction quality cannot be guaranteed.

[0004] To this end, further optimization is needed in terms of efficient and convenient construction of ecological blanket slope protection, reliable fixation, and autonomous adjustment of slope protection. Summary of the invention

[0005] The present invention aims to solve one of the technical problems in the related art at least to a certain extent. To this end, the present invention proposes a drainage adjustable slope protection ecological restoration system and method.

[0006] The technical solution of the present invention to solve the technical problem is:

[0007] This technical solution proposes a drainage-adjustable slope protection ecological restoration system, in which:

[0008] It comprises several rows of interception bodies arranged along the slope surface, the interception bodies are arranged transversely, and adjacent interception bodies are arranged at intervals, the interception bodies divide the slope surface into several laying units, and ecological blankets are laid in the laying units;

[0009] The interception body is composed of a number of closely arranged tire bodies, which are used as the fulcrum during construction; the bottom of the tire body is buried in the slope surface, and overflow holes are formed between adjacent tire bodies; the interior of the tire body has a cavity, and a drainage hole is formed between the cavity and the slope surface; the drainage capacity of the drainage hole is greater than that of the overflow hole;

[0010] A drainage adjustment member is provided at the drainage hole, and the drainage adjustment member includes a rotating shaft, the rotating shaft is connected to the slope surface, two groups of baffles are rotatably connected to the rotating shaft, a compression spring is connected between the baffles, and an inverted "V"-shaped structure is formed between the two groups of baffles; the top of the baffle is not lower than the top of the overflow hole; the drainage adjustment member divides the drainage hole into two parts, namely the first drainage channel and the second drainage channel;

[0011] In the initial state, under the elastic force of the compression spring, the surface of the baffle rests against the sidewall of the tire body, blocking the second drainage channel, and the small flow of slope runoff water is only discharged through the overflow hole; the large flow of slope runoff water can flush open the drainage regulating part, so that the two groups of baffles squeeze the compression spring, the two groups of baffles approach each other, the baffles no longer contact the sidewall of the tire, the second drainage channel is opened, and accelerated drainage is achieved.

[0012] Preferably, the ecological blanket is fixed by multiple sets of fixing mechanisms, which include a jack, which is arranged in some of the drainage holes, with the top of the jack supported on the inner top of the tire body, and the bottom of the jack pressed on a support frame, which is pressed on the edge of the ecological blanket; a plurality of threaded rods are threadedly connected to the support frame; and the support frame also includes a frame pressed on the surface of the ecological blanket, and the bottom end of the threaded rod acts on the top surface of the frame to press the frame tightly on the ecological blanket to form a pressed and fixed area.

[0013] Preferably, the support frame includes a support body, the support body is an inverted U-shaped structure, and ear plates are fixedly connected to both sides of the support body, and the bottom end of the jack is pressed on the ear plates.

[0014] Preferably, the threaded rod is a stainless steel bolt.

[0015] Preferably, it also includes a plurality of groups of guide rails arranged at intervals, wherein the guide rails are arranged longitudinally along the slope and fixed to the top of the tire body; a maintenance watering area is formed between adjacent guide rails, and sprinklers for watering and maintenance are installed between adjacent guide rails, and the sprinklers can slide up and down along the guide rails.

[0016] This technical solution also proposes a drainage adjustable slope protection ecological restoration method, using the drainage adjustable slope protection ecological restoration system, the specific steps are as follows:

[0017] S1, Construction:

[0018] S11, slope repair, installing multiple groups of horizontally laid interceptors along the slope;

[0019] The interception body is composed of a number of closely arranged tire bodies, the bottom of which is buried in the slope surface, and overflow holes are formed between adjacent tire bodies; the interior of the tire body has a cavity, and a drainage hole is formed between the cavity and the slope surface;

[0020] S12, installing a drainage adjustment member: installing a drainage adjustment member in the drainage hole of the tire body, the drainage adjustment member dividing the drainage hole into two parts, namely, a first drainage channel and a second drainage channel; in an initial state, under the elastic force of the compression spring, the surfaces of the two groups of baffles in the drainage adjustment member abut against the sidewall of the tire body, and the bottom ends of the baffles are close to the slope surface, thereby blocking the second drainage channel;

[0021] S13, laying ecological blankets: adjacent intercepting bodies are arranged at intervals to divide the slope into a number of laying units, and ecological blankets are laid in the laying units;

[0022] S14, fix the ecological blanket: install the support frame and the frame, and fix the two ends of the support frame to the edge of the ecological blanket through the counter-supporting force between the jack and the tire body; screw the threaded rod on the support frame, and the threaded rod presses the frame downward to achieve the frame pressing the ecological blanket surface;

[0023] S2, use:

[0024] During daily maintenance or when it rains, slope runoff water will form on the surface of the ecological blanket. If the slope runoff water is a small flow, the small flow of slope runoff water cannot overcome the pressure of the compression spring, and the baffle cannot rotate, so that the small flow of slope runoff water can only be discharged slowly through the overflow hole but cannot be discharged through the drainage hole, which is beneficial to the plants in the ecological blanket to fully absorb water resources; if the slope runoff water is a large flow, the large flow of slope runoff water impacts the baffle, which can overcome the pressure of the compression spring, causing the baffle to rotate, the baffle squeezes the compression spring, the two sets of baffles approach each other, the baffle no longer contacts the sidewall of the tire, and the second drainage channel opens to accelerate drainage and prevent waterlogging.

[0025] The above technical solution has the following advantages or beneficial effects:

[0026] 1. The present invention adjusts the traditional longitudinal laying of ecological blankets to horizontal laying, and uses interceptors based on waste tire bodies to divide the slope surface to form a number of horizontally arranged laying units. The ecological blankets are laid in the laying units. The tire bodies can play four roles. First, the construction area is divided into small-area laying units. The height difference of each laying unit is relatively small. When workers are working, they use the tire bodies as footholds or gripping points, which can improve safety and construction efficiency, and achieve the purpose of zoning construction, zoning management, and efficient coordination. Second, the interceptors are set on the slope. The layer-by-layer layout on the surface can reduce soil erosion, and can also block falling rocks and rolling stones on the top of the slope, thereby improving safety; thirdly, the elasticity of the waste tire body can be used to adaptively resist the swelling and shrinkage or frost heave and thaw deformation of the slope; fourthly, the tire body can be used in conjunction with the drainage adjustment part to form overflow holes and drainage holes of different sizes, and the drainage adjustment part can be automatically opened and closed according to the size of the slope runoff, thereby realizing the switching of the runoff discharge speed between fast and slow. The simple structure is used to achieve autonomous adjustment of slope drainage, and the design is reasonable, ingenious and practical.

[0027] 2. The drainage adjustment member designed in the present invention has a simple structure and low cost. It adopts two sets of baffles and uses compression springs to achieve the coordination between the baffles and the sidewalls of the tire body, thereby achieving the purpose of water blocking or drainage.

[0028] 3. The present invention adopts a fixing mechanism to fix the ecological blanket, abandoning the traditional fixing nail method. The fixing mechanism and the laying area complement each other. The ecological blanket is laid horizontally, and multiple fixing mechanisms can be used to fix the edge and surface of the blanket, forming an integrated system of fast construction and regional fixation with the tire body as the axis + small area construction + blanket surface area pressure holding and fixation, which solves the problems of low construction efficiency, easy overhead of the blanket surface, and loose fixation in traditional fixing nail construction, and provides a new construction system and method for the engineering application of ecological blankets. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.

[0030] Figure 1 It is a structural cross-sectional diagram of an ecological blanket after laying in the prior art.

[0031] Figure 2 It is a three-dimensional diagram of the structure of the present invention (after the grass seeds have germinated).

[0032] Figure 3 yes Figure 2 Schematic diagram of the enlarged structure of area A in the middle.

[0033] Figure 4 It is a three-dimensional diagram of the structure of the present invention (before the grass seeds sprout).

[0034] Figure 5 It is a structural stereogram of the drainage adjustment component.

[0035] Figure 6 It is the front view of the coordination between the tire body, the support and the drainage adjustment parts.

[0036] Figure 7 It is a schematic diagram of the structure of the overflow holes and drainage holes formed between the tire bodies.

[0037] Figure 8 It is a cross-sectional view of the matching relationship between the tire body and the drainage adjustment part in the top view (when the drainage adjustment part is in a small flow slope runoff state).

[0038] Fig. 9 It is a cross-sectional view of the matching relationship between the tire body and the drainage adjustment part in the top view (when the drainage adjustment part is in a large flow slope runoff state).

[0039] Fig.10 It is a structural stereogram of the frame in the present invention.

[0040] Fig.11 It is a structural schematic diagram of the connection relationship between the support frame and the threaded rod in the present invention.

[0041] Description of reference numerals:

[0042] 1. Slope; 2. Slope top; 3. Slope surface; 4. Slope bottom; 5. Gabion stone cage; 6. Ecological blanket; 601. Fixing nail; 7. Interceptor; 71. Tire body; 701. Overflow hole; 702. Drainage hole; 8. Guide rail; 801. Guide groove; 802. Upper connecting piece; 9. Sprayer; 10. Moving wheel; 11. Traction rope; 12. Drainage adjustment piece; 121. Rotating shaft; 122. Baffle; 123. Compression spring; 13. Jack; 14. Lower connecting piece; 15. Support frame; 16. Frame; 17. Threaded rod; 18. Fastening bolts. DETAILED DESCRIPTION

[0043] In order to make the objects, features and advantages of the present invention more obvious and easy to understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the embodiments described below are only part of the embodiments of the present invention, rather than all the embodiments.

[0044] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be understood as a limitation on the present invention.

[0045] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.

[0046] Reference Figure 1 At present, the ecological blanket 6 is used perpendicular to the direction of the river channel. The ecological blanket 6 is laid on the flat slope. The blanket surface of the ecological blanket 6 is fixed with fixing nails 601. The specific construction process is slope leveling → grooving → laying → overlapping and anchoring → maintenance.

[0047] Embodiment 1:

[0048] Aiming at the technical problems existing in the existing ecological blanket 6 slope protection system and construction technology, such as Figure 2 - Fig. 9 As shown, this embodiment proposes a drainage adjustable slope protection ecological restoration system, which is used for repairing a slope body 1, wherein the slope body 1 includes a slope top 2 and a slope bottom 4, and a slope surface 3 is between the slope top 2 and the slope bottom 4, wherein:

[0049] The invention comprises several rows of interception bodies 7 arranged along the slope 3, wherein the interception bodies 7 are arranged horizontally and spaced apart from each other. The interception bodies 7 divide the slope 3 into several laying units, and ecological blankets 6 are laid in the laying units. Considering that there are no supporting points on the slope 3, if a large area is constructed, workers can only use the method of hanging safety ropes for construction, and they will also trample on the laid ecological blankets 6. In this way, the probability of the ecological blankets 6 being damaged by workers during the construction process is high. Once damaged, they need to be repaired in time. If the damage is serious, new ecological blankets 6 need to be replaced. However, after being fixed by fixing nails 601, each ecological blanket 6 is chained into one piece, which is very troublesome for replacing new ecological blankets 6. For this reason, the idea of ​​zoning management and zoning construction is adopted in this embodiment, and the large area of ​​the slope 3 is divided to form several independent small-area construction areas, which can reduce the construction difficulty and improve the construction efficiency.

[0050] Considering that the interception body 7 not only has to play a role of segmentation, but also serves as a support point during construction, and waste tires are very good resources, if waste tires can be introduced into the ecological blanket 6 slope protection body 1 system, it can not only improve the anti-scouring ability of the slope 1, but also provide a fulcrum for workers to facilitate construction operations. To this end, the interception body 7 is composed of a number of closely arranged tire bodies 71, which are used as fulcrums during construction; the bottom of the tire body 71 is buried in the slope surface 3, which is equivalent to forming a number of bosses on the surface of the slope 1, so that workers can step on the tire body 71 to move or perform other operations during construction. In this embodiment, an overflow hole 701 is formed between adjacent tire bodies 71. The overflow hole 701 is formed by two adjacent tire bodies 71 being closely connected. The overflow hole 701 is used to realize a small-diameter drainage channel and slow down the water flow rate so that the water body can fully nourish the ecological blanket 6. The tire body 71 has a cavity inside, which is provided by the tire body 71. A drainage hole 702 is formed between the cavity and the slope 3. The drainage capacity of the drainage hole 702 is greater than that of the overflow hole 701. In this way, the structure formed by the tire body 71 has two drainage channels with different flow rates, namely the overflow hole 701 and the drainage hole 702.

[0051] In order to facilitate the realization of the self-drainage adjustment of the slope body 1, a drainage adjustment member 12 is provided at the drainage hole 702. The drainage adjustment member 12 includes a rotating shaft 121, which is connected to the slope surface 3 and can be directly set on the slope surface 3. Two groups of baffles 122 are rotatably connected to the rotating shaft 121, and each baffle 122 can rotate relative to the rotating shaft 121; a compression spring 123 is connected between the baffles 122, and an inverted "V"-shaped structure is formed between the two groups of baffles 122; the top of the baffle 122 is not lower than the top of the overflow hole 701, and the purpose of such a setting is to ensure that when the flow rate is small, the water body can only overflow through the overflow hole 701; the drainage adjustment member 12 divides the drainage hole 702 into two parts, namely, the first drainage channel and the second drainage channel; since the aperture of the drainage hole 702 is relatively large, it is not necessary to block all the drainage holes 702. For this purpose, it is only necessary to block the drainage area below the drainage hole 702, that is, to block the second drainage channel. When the second drainage channel is opened, water can flow downward through the second drainage channel. When encountering heavy rain, rainwater may flood the drainage adjustment member 12. At this time, the rainwater may overflow the top diameter of the drainage adjustment member 12 and flow out of the first drainage channel. Therefore, the design of the first drainage channel is mainly to cope with emergencies, such as short-term heavy rain and other severe situations, to increase the diameter of the drainage hole 702 for rapid drainage. In general, only the second drainage hole 702 and the overflow hole 701 are needed to achieve self-regulation.

[0052] Working principle of drainage adjustment member 12:

[0053] In the initial state, under the elastic force of the compression spring 123, the surface of the baffle 122 is against the sidewall of the tire body 71 to block the second drainage channel. Due to the small flow rate and low flow rate of slope runoff water, the small flow rate of slope runoff water is only discharged through the overflow hole 701, and it cannot flush the baffle 122; for large flow rate of slope runoff water, due to its large flow rate, the overflow hole 701 cannot meet its drainage capacity, and the large flow rate of slope runoff water can flush the drainage adjustment member 12, so that the two groups of baffles 122 squeeze the compression spring 123, the two groups of baffles 122 are close to each other, the baffles 122 no longer contact the sidewall of the tire, the second drainage channel is opened, and accelerated drainage is achieved, which can avoid the formation of waterlogging and drowning of grass seeds or plants, and also solve the technical problem that slow drainage easily causes excessive soaking of the slope 1, which easily leads to disintegration and landslide caused by accumulated water.

[0054] In order to improve the anti-scouring ability at the bottom 4 of the slope, gabion stone cages 5 are arranged at the bottom 4 of the slope to reinforce the foundation.

[0055] This embodiment also proposes a drainage adjustable slope protection ecological restoration method. Based on the above drainage adjustable slope protection ecological restoration system, the specific steps are as follows:

[0056] S1, Construction:

[0057] S11, slope 3 repair, install multiple groups of horizontally laid interception bodies 7 along the slope 3; 1) Slope leveling: Before construction, the slope 3 needs to be repaired to make it sufficiently flat, and secondary leveling can be carried out manually if necessary. When leveling the slope, it is important to pay attention to the fact that the prepared slope or foundation must meet the slope ratio of the drawing. There must be no gravel with a particle size of more than 50 mm on the slope 3, and there must be no tree stumps, tree roots, or other garbage; there must be no concave or convex parts, and it needs to be compacted and all accumulated water within the paving construction range must be removed. If there is no natural topsoil on the slope 3, or the topsoil is thinner than the thickness required in the construction drawings, it is necessary to add topsoil to meet the design standards; 2) Grooving is made on the slope 3, and the waste tire body 71 is buried to form several layers of interception bodies 7.

[0058] It should be noted that the intercepting body 7 is composed of a number of closely arranged tire bodies 71, the bottom of the tire body 71 is buried in the slope 3, and overflow holes 701 are formed between adjacent tire bodies 71. The shape of the overflow holes 701 is similar to a triangle; the tire body 71 has a cavity inside, and a drainage hole 702 is formed between the cavity and the slope 3; in this step, two drainage channels of different sizes are constructed.

[0059] S12, install the drainage adjusting component 12: install the drainage adjusting component 12 in the drainage hole 702 of the tire body 71. It is recorded above that the drainage adjusting component 12 divides the drainage hole 702 into two parts, namely the first drainage channel and the second drainage channel; in the initial state, the two groups of baffles 122 in the drainage adjusting component 12 are under the elastic force of the compression spring 123, and the surface of the baffle 122 is against the sidewall of the tire body 71, and the bottom end of the baffle 122 is close to the slope 3, so the second drainage channel is blocked.

[0060] S13, laying ecological blankets 6: adjacent intercepting bodies 7 are arranged at intervals to divide the slope 3 into a number of laying units, and ecological blankets 6 are laid in the laying units and fixed.

[0061] S2, use:

[0062] During daily maintenance or when it rains, slope runoff water will form on the surface of the ecological blanket 6. If the slope runoff water is a small flow, the small flow of slope runoff water cannot overcome the pressure of the compression spring 123, and the baffle 122 cannot rotate, so that the small flow of slope runoff water can only be discharged slowly through the overflow hole 701 but cannot be discharged through the drainage hole 702, which is beneficial to the plants in the ecological blanket 6 to fully absorb water resources; if the slope runoff water is a large flow, refer to the attached Fig. 9 , attached Fig. 9The arrow in the figure represents the flow direction of slope runoff water. The slope runoff water with a large flow rate hits the baffle 122, which can overcome the pressure of the compression spring 123, causing the baffle 122 to rotate. The baffle 122 squeezes the compression spring 123, and the two groups of baffles 122 approach each other. The baffle 122 no longer contacts the sidewall of the tire, and the second drainage channel is opened to accelerate drainage and prevent waterlogging.

[0063] Application results:

[0064] The present invention adjusts the traditional longitudinal laying of the ecological blanket 6 to a transverse laying, and adopts an interception body 7 based on a waste tire body 71 to divide the slope 3 to form a plurality of transversely arranged laying units. The ecological blanket 6 is laid in the laying unit, and the tire body 71 can play four roles. First, the construction area is divided into small-area laying units, and the height difference of each laying unit is relatively small. When the workers are working, they use the tire body 71 as a foothold or a gripping point, which can improve safety and construction efficiency, and achieve the purpose of zoning construction, zoning management, and efficient coordination; second, the interception body 7 is arranged layer by layer on the slope 3. The utility model discloses a waste tire body 71, which can reduce water and soil erosion, and can also block falling rocks and rolling stones on the top of the slope 2, thereby improving safety; thirdly, the elasticity of the waste tire body 71 can also be used to adaptively resist the swelling and shrinkage or frost heave and thaw deformation of the slope; fourthly, the tire body 71 is used in conjunction with the drainage adjustment member 12 to form overflow holes 701 and drainage holes 702 of different sizes, and the drainage adjustment member 12 is automatically opened and closed according to the size of the runoff on the slope 3, thereby realizing the switching of the fast and slow discharge speed of the runoff, and adopts a simple structure to realize the autonomous adjustment of the drainage of the slope 1, and the design is reasonable, ingenious and practical.

[0065] The drainage adjustment member 12 designed in this embodiment has a simple structure and low cost. It adopts two sets of baffles 122 and uses compression springs 123 to achieve the cooperation between the baffles 122 and the sidewalls of the tire body 71 to achieve the purpose of water blocking or drainage.

[0066] Embodiment 2:

[0067] Continue to refer to the attached Figure 2 - Fig. 9 The first embodiment mainly solves the problem of slope protection self-regulating drainage. Based on the first embodiment, this embodiment is further optimized to solve the drawbacks of the existing ecological blanket 6 fixed with fixing nails 601, which is described in detail below:

[0068] In this embodiment, the traditional fixing method of fixing nails 601 is abandoned, and the ecological blanket 6 is fixed by a fixing mechanism and a tire body 71. The ecological blanket 6 is mainly fixed by multiple sets of fixing mechanisms. The fixing mechanism uses the tire body 71 as an installation carrier, which includes a jack 13. The jack 13 is arranged in a part of the drainage hole 702. The tire body 71 corresponding to the appropriate position is selected, and the jack 13 is installed in the drainage hole 702. The top of the jack 13 is supported at the top of the tire body 71, and the bottom of the jack 13 is pressed on the support frame 15. The support frame 15 is pressed on the edge of the ecological blanket 6. After the jack 13 is supported, the counter-support force can be used to press the support frame 15, thereby realizing the pressing and fixing of the edge of the ecological blanket 6; a plurality of threaded rods 17 are threadedly connected to the support frame 15; it also includes a frame 16 pressed on the surface of the ecological blanket 6, and the bottom end of the threaded rod 17 acts on the top surface of the frame 16 to tightly press the frame 16 on the ecological blanket 6 to form a pressing and fixing area.

[0069] Regarding the structure of the support frame 15, the following structure can be adopted: the support frame 15 includes a support body, the support body is an inverted U-shaped structure, and ear plates are fixedly connected to both sides of the support body, and the bottom end of the jack 13 is pressed on the ear plates.

[0070] It should be noted that the bottom end of the jack 13 can act on the rotating shaft 121, a pad is installed on the top of the rotating shaft 121 to form a bearing base surface, and then the support frame 15 is installed between the pad and the bottom end of the jack 13. The pressing and holding surface at the bottom end of the jack 13 may not be the rotating shaft 121, and the slope 3 buried in the tire body 71 may be directly used as the bearing base surface. It can be installed according to actual conditions, and both options are acceptable.

[0071] In this embodiment, the threaded rod 17 is made of stainless steel bolts to prevent rust and corrosion, thereby extending the overall service life. In this embodiment, the jack 13 can be selected from common structures such as a scissor jack 13 and a screw jack 13.

[0072] Construction method:

[0073] On the basis of the steps in Example 1, in this embodiment, S1 also includes: S14, fixing the ecological blanket 6: installing the support frame 15 and the frame 16, and the two ends of the support frame 15 are pressed and fixed to the edge of the ecological blanket 6 by the counter-supporting force between the jack 13 and the tire body 71; screwing the threaded rod 17 on the support frame 15, the threaded rod 17 presses down the frame 16, so as to realize the pressure of the frame 16 on the surface of the ecological blanket 6.

[0074] Application results:

[0075] The ecological blanket 6 is fixed by a fixing mechanism, and the traditional fixing nail 601 method is abandoned. The fixing mechanism and the laying area complement each other. The ecological blanket 6 is laid horizontally, and multiple fixing mechanisms can be used to fix the edge and the blanket surface, forming an integrated system of fast construction and regional fixation with the tire body 71 as the axis + small area construction + blanket surface area pressure holding and fixation, which solves the problems of low construction efficiency, easy overhead of the blanket surface, and loose fixation in the traditional construction of fixing nails 601, and provides a new construction system and method for the engineering application of the ecological blanket 6.

[0076] Embodiment three:

[0077] The above two embodiments mainly introduce the fixation of the ecological blanket 6 and the self-regulation of the drainage of the slope protection. Considering that the ecological blanket 6 also needs to be maintained, a maintenance system needs to be designed. If the conventional method of watering by hand with a water pipe is adopted, the biggest problem of this method is uneven watering, which is not conducive to maintenance management and is laborious, and may eventually affect the germination and growth of plants.

[0078] In view of this problem, under the idea of ​​water-saving maintenance, based on the first and second embodiments, the whole system also includes a plurality of groups of guide rails 8 arranged at intervals, the guide rails 8 are arranged longitudinally along the slope 3, and the guide rails 8 are fixed on the top of the tire body 71; the adjacent guide rails 8 form a maintenance watering area, and the adjacent guide rails 8 are installed with a sprinkler 9 for watering and maintenance, and the sprinkler 9 can slide up and down along the guide rail 8. The bottom of the sprinkler 9 has a plurality of nozzles for spraying and watering. The top of the sprinkler 9 has a water inlet nozzle for convenient connection with the water inlet pipe.

[0079] In this embodiment, the two sides of the sprayer 9 are rotatably connected with moving wheels 10, and the guide rail 8 has a guide groove 801, and the moving wheels 10 can slide along the guide groove 801. A traction rope 11 is also connected to one end of the sprayer 9 for traction of the sprayer 9 up and down so as to irrigate evenly.

[0080] In this embodiment, in order to facilitate the installation of the guide rail 8, a lower connecting plate 14 is also provided in this embodiment. The lower connecting plate 14 is installed in the drainage hole 702 of the tire body 71. The lower connecting plate 14 is placed on the top of the jack 13. The jack 13 is used to realize the fastening connection between the lower connecting plate 14 and the tire body 71. The lower connecting plate 14 is provided with a bolt mounting hole. Correspondingly, the guide rail 8 is also fixedly connected with an upper connecting plate 802. The upper connecting plate 802 is also provided with corresponding bolt mounting holes. Fastening bolts 18 are installed in the corresponding upper and lower bolt mounting holes to realize the fixation of the guide rail 8 and the tire body 71.

[0081] During maintenance, water can be taken on site, such as pumping water from a river, connecting a water pipe to a water inlet, and then pulling the traction rope 11. The sprinkler 9 slides downward under its own weight, and the traction rope 11 is slowly loosened to slowly lower the sprinkler 9, thereby achieving uniform irrigation. The amount of watering can be determined based on actual conditions. The sprinkler 9 moves back and forth up and down to achieve multiple irrigations until the required amount of watering is reached. After the area is irrigated, the sprinkler 9 is towed to the top 2 of the slope, and the traction rope 11 is tied to the top 2 of the slope to achieve the positioning of the sprinkler 9.

[0082] The method can be used to carry out all-round watering and maintenance of the ecological blanket 6, and can effectively solve the problems of uneven watering, time-consuming and labor-intensive maintenance of the ecological blanket 6.

[0083] Although the above describes the specific implementation mode of the invention in conjunction with the drawings, it is not intended to limit the scope of protection of the invention. Based on the technical solution of the present invention, various modifications or variations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.

Claims

1. A drainage-adjustable slope protection ecological restoration system, characterized by: It comprises a plurality of rows of interception bodies (7) arranged along a slope surface (3), wherein the interception bodies (7) are arranged transversely and adjacent interception bodies (7) are arranged at intervals, and the interception bodies (7) divide the slope surface (3) into a plurality of laying units, and ecological blankets (6) are laid in the laying units; The intercepting body (7) is composed of a plurality of closely arranged tire bodies (71), the tire bodies (71) being used as a fulcrum during construction; the bottom of the tire bodies (71) is buried in the slope surface (3), and overflow holes (701) are formed between adjacent tire bodies (71); the tire bodies (71) have a cavity inside, and a drainage hole (702) is formed between the cavity and the slope surface (3); the drainage capacity of the drainage hole (702) is greater than the drainage capacity of the overflow hole (701); A drainage adjustment member (12) is provided at the drainage hole (702), the drainage adjustment member (12) comprising a rotating shaft (121), the rotating shaft (121) being connected to the slope surface (3), two groups of baffles (122) being rotatably connected to the rotating shaft (121), a compression spring (123) being connected between the baffles (122), and an inverted "V"-shaped structure being formed between the two groups of baffles (122); the top of the baffle (122) is not lower than the top of the overflow hole (701); the drainage adjustment member (12) divides the drainage hole (702) into two upper and lower parts, namely a first drainage channel and a second drainage channel; In the initial state, under the elastic force of the compression spring (123), the surface of the baffle (122) abuts against the sidewall of the tire body (71), thereby blocking the second drainage channel. The slope runoff water with a small flow rate is discharged only through the overflow hole (701); the slope runoff water with a large flow rate can flush the drainage adjustment member (12), so that the two groups of baffles (122) squeeze the compression spring (123), the two groups of baffles (122) approach each other, the baffles (122) no longer contact the sidewall of the tire, and the second drainage channel is opened, thereby achieving accelerated drainage.

2. The drainage-adjustable slope protection ecological restoration system according to claim 1 is characterized by: The ecological blanket (6) is fixed by a plurality of fixing mechanisms, the fixing mechanisms comprising a jack (13), the jack (13) being arranged in a portion of the drainage holes (702), the top of the jack (13) being supported on the inner top of the tire body (71), the bottom of the jack (13) being pressed on a support frame (15), the support frame (15) being pressed on the edge of the ecological blanket (6); a plurality of threaded rods (17) being threadedly connected to the support frame (15); and a frame (16) being pressed on the surface of the ecological blanket (6), the bottom ends of the threaded rods (17) acting on the top surface of the frame (16) to tightly press the frame (16) on the ecological blanket (6) to form a pressing and fixing area.

3. The drainage adjustable slope protection ecological restoration system according to claim 2 is characterized by: The support frame (15) comprises a support body, the support body is an inverted U-shaped structure, and ear plates are fixedly connected to both sides of the support body, and the bottom end of the jack (13) is pressed on the ear plates.

4. The drainage-adjustable slope protection ecological restoration system according to claim 2 is characterized by: The threaded rod (17) is made of stainless steel bolts.

5. The drainage-adjustable slope protection ecological restoration system according to claim 3 is characterized by: It also includes a plurality of groups of guide rails (8) arranged at intervals, wherein the guide rails (8) are arranged longitudinally along the slope (3), and the guide rails (8) are fixed to the top of the tire body (71); a maintenance watering area is formed between adjacent guide rails (8), and sprinklers (9) for watering and maintenance are installed between adjacent guide rails (8), and the sprinklers (9) can slide up and down along the guide rails (8).

6. A drainage-adjustable slope protection ecological restoration method, characterized in that: The drainage-adjustable slope protection ecological restoration system according to any one of claims 1 to 5 is adopted, and the specific steps are as follows: S1, Construction: S11, repairing the slope surface (3), installing a plurality of groups of intercepting bodies (7) laid transversely along the slope surface (3); The interception body (7) is composed of a plurality of closely arranged tire bodies (71), the bottom of the tire body (71) is buried in the slope surface (3), and overflow holes (701) are formed between adjacent tire bodies (71); the interior of the tire body (71) has a cavity, and a drainage hole (702) is formed between the cavity and the slope surface (3); S12, installing the drainage adjustment member (12): installing the drainage adjustment member (12) in the drainage hole (702) of the tire body (71), the drainage adjustment member (12) dividing the drainage hole (702) into two parts, an upper part and an lower part, which are respectively a first drainage channel and a second drainage channel; in an initial state, under the elastic force of the compression spring (123), the two groups of baffles (122) in the drainage adjustment member (12) are pressed against the sidewall of the tire body (71), and the bottom end of the baffle (122) is pressed against the slope (3), thereby blocking the second drainage channel; S13, laying ecological blankets (6): adjacent intercepting bodies (7) are arranged at intervals to divide the slope surface (3) into a plurality of laying units, and ecological blankets (6) are laid in the laying units; S14, fixing the ecological blanket (6): installing a support frame (15) and a frame (16), wherein both ends of the support frame (15) are fixed to the edge of the ecological blanket (6) by means of a counter-supporting force between a jack (13) and a tire body (71); screwing a threaded rod (17) on the support frame (15), wherein the threaded rod (17) presses down the frame (16), thereby achieving the frame (16) pressing the surface of the ecological blanket (6); S2, use: During routine maintenance or when it rains, slope runoff water will form on the surface of the ecological blanket (6). If the slope runoff water has a small flow rate, the slope runoff water with a small flow rate cannot overcome the pressure of the compression spring (123), and the baffle (122) cannot rotate, so that the slope runoff water with a small flow rate can only be discharged slowly through the overflow hole (701) but cannot be discharged through the drainage hole (702), which is beneficial for the plants in the ecological blanket (6) to fully absorb water resources. If the slope runoff water has a large flow rate, the slope runoff water with a large flow rate impacts the baffle (122), which can overcome the pressure of the compression spring (123), causing the baffle (122) to rotate, the baffle (122) to press the compression spring (123), and the two groups of baffles (122) approach each other. The baffle (122) no longer contacts the sidewall of the tire, and the second drainage channel is opened, so that drainage is accelerated to prevent waterlogging.

Citation Information

Patent Citations

  • Rail formed by junked tires

    CN104164997A

  • Slope ecological protection device

    CN110984074A