Load resource management method and device based on demand side, equipment and medium

By acquiring and analyzing user-side load data, predicting demand and power supply capacity, matching load resources, and generating and executing load management plans, the efficiency and reliability problems of load resource management in smart grids are solved, and the utilization rate of power resources and the power grid are improved. Operational stability.

CN118747587APending Publication Date: 2024-10-08GUIZHOU POWER GRID CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410926368.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

In smart grids, the level of information interaction between the demand side and the power grid continues to improve. The output characteristics and load characteristics of demand side resources are complementary in time and space, causing load resource management to become an urgent problem that needs to be solved and affecting the operation of the power grid. efficiency and reliability.

Method used

By obtaining real-time and historical load data from users, identify power consumption patterns and trends, predict future user needs and power supply capabilities, calculate load gaps, and match controllable load resources from the preset load resource pool to generate load management plans. Execute the plan and record abnormal information, and generate alarm notifications to optimize power resource utilization.

Benefits of technology

It improves the utilization rate of power resources, ensures the balance between supply and demand of the power grid, improves the operating efficiency and reliability of the power grid, and responds to changes and abnormalities in the power grid in a timely manner.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118747587A_ABST
    Figure CN118747587A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of power system management, and discloses a load resource management method based on a demand side, which comprises the following steps: querying various data of a user side through a user number, and monitoring to obtain real-time monitoring data; acquiring historical load data of the user side through the user number, and identifying a power consumption mode and trend to obtain power consumption behavior trend data of the user; acquiring a power utilization plan of a power supplier, and predicting future user demands and power supply capability based on the user power utilization behavior trend data and the real-time monitoring data to obtain a load gap; according to the load gap and the power utilization plan, controllable load resources are matched from a preset load resource pool, and a load management scheme is generated; and executing the load management scheme, recording abnormal information, generating a corresponding alarm notification based on the abnormal information, and contacting a worker to query. The invention further provides a load resource management device and equipment based on the demand side and a storage medium. The utilization rate of electric power resources can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power system regulation and management, and in particular to a method, device, equipment and medium for load resource management based on the demand side. Background Art

[0002] Since the beginning of the 21st century, global resources have become increasingly scarce, and the global demand for resources has continued to increase. As the world's calls for clean, environmentally friendly and efficient use of energy are getting louder and louder, electricity as a terminal energy source has been increasingly widely used for its clean, environmentally friendly and convenient use. In today's power grid construction tasks, the main content is smart electricity use, and its intelligent planning is reflected in the automatic and real-time interaction of electricity prices and load information between customers and power grids, as well as the scientific, economical and rational use of electricity, so that new energy and renewable energy can be developed and social energy conservation can be achieved.

[0003] With the continuous advancement of smart grid construction, the level of information exchange between the demand side and the power grid is also constantly improving. The impact of flexible interactive loads on the demand side on the operation of the power grid has gradually received attention. The output characteristics and load characteristics of demand-side resources are different, and there are complementary characteristics in time and space. Therefore, studying the complementary characteristics and interactive influences between various demand-side resources and managing load resources have become issues that need to be urgently addressed. Summary of the invention

[0004] The present invention provides a method, device, equipment and medium for load resource management based on the demand side, the main purpose of which is to improve the utilization rate of power resources.

[0005] To achieve the above object, the present invention provides a load resource management method based on the demand side, comprising:

[0006] Obtaining a user number based on a preset load control instruction, querying various data of the user end through the user number, and monitoring to obtain real-time monitoring data;

[0007] Obtaining historical load data of the user terminal through the user ID, identifying power consumption patterns and trends, and obtaining user power consumption behavior trend data;

[0008] Obtain the power supplier's power consumption plan, and predict future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap;

[0009] According to the load gap and the power consumption plan, controllable load resources are matched from a preset load resource pool to generate a load management plan;

[0010] Execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

[0011] Optionally, querying various data of the user terminal by the user number and monitoring to obtain real-time monitoring data includes:

[0012] Using the user number, calling a database interface of a power grid management system, and extracting the power consumption data of the user terminal from the database;

[0013] Retrieve the integrity of said electricity consumption data and integrate data from different sources and types into a unified data warehouse;

[0014] The real-time monitoring data is obtained by setting a monitoring system for the data warehouse and setting monitoring parameters and thresholds.

[0015] Optionally, acquiring historical load data of the user terminal through the user ID, identifying power consumption patterns and trends, and obtaining user power consumption behavior trend data includes:

[0016] Based on the user number, locate the relevant database of the user terminal, and extract the historical load data of the user terminal from the database;

[0017] Cleaning the historical load data, removing invalid or erroneous data, and filling in missing values ​​in the historical load data to obtain standard historical load data;

[0018] The power consumption pattern of the standard historical load data is identified by a cluster analysis algorithm, and time series analysis is performed to identify power consumption trends, thereby obtaining the user power consumption behavior trend data.

[0019] Optionally, the obtaining of the power supplier's power consumption plan and predicting future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain a load gap includes:

[0020] Identify the key features that affect electricity demand and obtain electricity demand characteristics;

[0021] Dividing the electricity usage behavior trend data into an electricity usage training model and electricity usage test data;

[0022] Selecting a prediction model suitable for the electricity demand characteristics, and training the prediction model using the electricity training data to obtain an electricity prediction model;

[0023] Testing the electricity consumption prediction model using the electricity consumption test data, and obtaining a standard electricity consumption prediction model when the test passes;

[0024] Inputting the real-time monitoring data into the power consumption prediction model to perform dynamic prediction to obtain user demand;

[0025] The power supply capacity of the user end is queried through the power consumption plan, and the load gap is obtained based on the user demand and the power supply capacity.

[0026] Optionally, matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan to generate a load management plan includes:

[0027] Obtaining detailed information of all load resources in the load resource pool, and determining resource characteristics that need to be analyzed based on the detailed information;

[0028] Selecting a load resource from the load resource pool based on the resource characteristics to obtain a target load resource, and optimizing the target load resource through a preset optimization algorithm and the load gap and the power consumption plan to obtain an optimized load resource;

[0029] According to the optimized load resources, the control time, control amount, and participating users are adjusted to generate a load management plan.

[0030] Optionally, executing the load management plan and recording abnormal information occurring during the execution of the plan includes:

[0031] Deploy the instructions and parameters of the load management scheme to a preset power grid management system and user-end equipment;

[0032] The monitoring in the power grid management system is performed, and the operation data and user power consumption data in the power grid management system are collected in real time to obtain monitoring data;

[0033] Monitor abnormal information in the monitoring data.

[0034] Optionally, after matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan and generating a load management plan, the method further includes:

[0035] When the load management scheme is put into use and contacted, the user end is informed of the operation to be performed through the customer interaction function, and after the operation is performed, control contact instructions are issued in batches for control contact;

[0036] The load resources after successful contact are restored to the load resource pool.

[0037] In order to solve the above problems, the present invention further provides a load resource management device based on the demand side, the device comprising:

[0038] A data monitoring module is used to obtain a user number based on a preset load control instruction, query various data of the user end through the user number, and monitor and obtain real-time monitoring data;

[0039] The gap calculation module is used to obtain the historical load data of the user end through the user number, identify the power consumption mode and trend, and obtain the user's power consumption behavior trend data; obtain the power consumption plan of the power supplier, and predict the future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap;

[0040] A scheme generating module, used for matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan, and generating a load management scheme;

[0041] The alarm notification module is used to execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact the staff for inquiry.

[0042] In order to solve the above problem, the present invention further provides an electronic device, the electronic device comprising:

[0043] at least one processor; and,

[0044] a memory communicatively connected to the at least one processor; wherein,

[0045] The memory stores a computer program that can be executed by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the demand-side-based load resource management method as described above.

[0046] In order to solve the above problems, the present invention also provides a computer-readable storage medium, including a data storage area and a program storage area, the data storage area stores created data, and the program storage area stores a computer program; wherein, when the computer program is executed by a processor, the demand-side-based load resource management method as described above is implemented.

[0047] The embodiment of the present invention first queries various data of the user end through the user number, and monitors to obtain real-time monitoring data; then obtains the historical load data of the user end through the user number, and identifies the power consumption mode and trend, obtains the user's power consumption behavior trend data, and realizes the acquisition of the power consumption behavior trend; then obtains the power supplier's power consumption plan, and predicts future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap; finally, according to the load gap and the power consumption plan, matches the controllable load resources from the preset load resource pool, generates a load management plan, and achieves the purpose of constructing the load management plan; executes the load management plan, records abnormal information, and generates corresponding alarm notifications based on the abnormal information, and contacts the staff for inquiry. Therefore, the load resource management method, device, electronic device and computer-readable storage medium based on the demand side proposed by the present invention predict the power supply capacity and user demand through the monitoring data of the user end and the power consumption behavior trend data in the historical data, calculates the load gap, generates a load management plan based on the load gap and the power consumption plan combined with the load resource pool, manages the load resources through the load management plan, and improves the utilization rate of power resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] Figure 1 A flow chart of a method for load resource management based on the demand side provided by an embodiment of the present invention;

[0049] Figure 2 A module diagram of a load resource management device based on the demand side provided by an embodiment of the present invention;

[0050] Figure 3 A schematic diagram of the internal structure of an electronic device for implementing a method for load resource management based on the demand side provided in one embodiment of the present invention.

[0051] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0052] It should be understood that the specific embodiments described herein are only used to explain the present invention, and are not used to limit the present invention.

[0053] The embodiment of the present application provides a method for load resource management based on the demand side. The execution subject of the method for load resource management based on the demand side includes but is not limited to at least one of the electronic devices such as the server and the terminal that can be configured to execute the method provided by the embodiment of the present application. Among them, the server can be an independent server, or it can be a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, content delivery networks (Content Delivery Network, CDN), and big data and artificial intelligence platforms. In other words, the method for load resource management based on the demand side can be executed by software or hardware installed on a remote device or a server device, and the software can be a blockchain platform. The server includes but is not limited to: a single server, a server cluster, a cloud server or a cloud server cluster, etc.

[0054] Reference Figure 1 FIG. 1 is a flow chart of a method for managing load resources based on the demand side according to an embodiment of the present invention. In this embodiment, the method for managing load resources based on the demand side includes the following steps S1-S5:

[0055] S1. Obtain a user number based on a preset load control instruction, query various data of the user end through the user number, and monitor and obtain real-time monitoring data.

[0056] In the embodiment of the present invention, the load control instruction plays a vital role in the power system, not only providing clear knowledge for system monitoring, ensuring that specific user numbers and their power parameters (such as power consumption, voltage, current, etc.) are effectively monitored, but also enabling the system to automatically retrieve and analyze the real-time data of these user terminals. The load control instruction is the basis for the formulation and execution of load management plans, and contains key information for achieving control objectives and strategies, thereby guiding the system on how to dynamically adjust the power load of the user terminal according to real-time monitoring data and power consumption plans, and optimize the supply and demand balance of the power grid.

[0057] In the embodiment of the present invention, the user number is a reference code used to identify each user in the power system, allowing the power grid operator and the load management system to accurately locate, monitor and analyze the power consumption behavior of a specific user, and realize rapid data retrieval and personalized load regulation. Through the user number, the system can effectively track power consumption patterns, formulate and implement customized load management strategies, and ensure the stability and efficiency of power grid operation.

[0058] Furthermore, the user ID is used to query various data of the user terminal, and monitor to obtain real-time monitoring data, including:

[0059] Using the user number, calling a database interface of a power grid management system, and extracting the power consumption data of the user terminal from the database;

[0060] Retrieve the integrity of said electricity consumption data and integrate data from different sources and types into a unified data warehouse;

[0061] The real-time monitoring data is obtained by setting a monitoring system for the data warehouse and setting monitoring parameters and thresholds.

[0062] In the embodiment of the present invention, the monitoring system refers to a technical and operational framework for real-time tracking and evaluation of user electricity consumption, and has functions such as data integration, real-time, and visualization, and is used to ensure continuous monitoring of the operating status of the power grid, and can effectively improve the response speed and processing capabilities to power grid anomalies.

[0063] Furthermore, after querying various data of the user terminal through the user number and monitoring and obtaining real-time monitoring data, the method further includes:

[0064] The real-time monitoring data is visualized in the form of charts, dashboards, etc.

[0065] Among them, visualizing real-time monitoring data can help monitoring personnel quickly understand the current monitoring status.

[0066] In the embodiment of the present invention, by querying and real-time monitoring the data on the user side, not only can comprehensive and immediate data support be provided for load management to ensure in-depth analysis of the user's electricity consumption behavior, but also a solid foundation is laid for subsequent load forecasting, resource matching, program formulation and execution monitoring, so that the entire power system can respond more flexibly and efficiently to various demands and changes in the operation of the power grid.

[0067] In another embodiment of the present invention, the demand-side data can also be displayed as a whole, including classified display of the overall adjustable load of each region, subsidy rate, mode distribution, user distribution, number of connected households, total number of access devices, user participation status and other information.

[0068] S2. Obtain historical load data of the user terminal through the user ID, identify power consumption patterns and trends, and obtain user power consumption behavior trend data.

[0069] In the embodiment of the present invention, the historical load data can be queried in a historical database by using user number data to obtain the historical load data corresponding to the user end.

[0070] In the embodiment of the present invention, the acquiring of the historical load data of the user terminal through the user ID, and identifying the power consumption pattern and trend to obtain the user power consumption behavior trend data includes:

[0071] Based on the user number, locate the relevant database of the user terminal, and extract the historical load data of the user terminal from the database;

[0072] Cleaning the historical load data, removing invalid or erroneous data, and filling in missing values ​​in the historical load data to obtain standard historical load data;

[0073] The power consumption pattern of the standard historical load data is identified by a cluster analysis algorithm, and time series analysis is performed to identify power consumption trends, thereby obtaining the user power consumption behavior trend data.

[0074] Specifically, the power consumption pattern of the user end, such as peak hours, off-peak hours, etc., and the identified power consumption trend of the user end, such as seasonal changes, long-term growth or decline trends.

[0075] The embodiments of the present invention can provide the power system with an in-depth understanding of user electricity consumption characteristics by performing pattern and trend analysis based on historical load data, thereby formulating more effective load management policies and demand response plans, ensuring that the power grid can make timely and appropriate adjustments when facing supply and demand fluctuations, and improving the overall operating efficiency and reliability of the power grid.

[0076] S3. Obtain the power consumption plan of the power supplier, and predict future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap.

[0077] In an embodiment of the present invention, the power supplier's power consumption plan is a comprehensive strategic arrangement that covers multiple aspects such as power generation scheduling, grid operation, load forecasting, demand-side management, energy storage scheduling, and equipment maintenance, aiming to ensure that the power system can efficiently and stably meet the power needs of the user end, while optimizing resource allocation and improving the overall operating efficiency and reliability of the power grid.

[0078] In an embodiment of the present invention, the load gap refers to the difference between the total power demand at the user end and the available power supply capacity in the power system within a specific period of time. This situation may be caused by various factors, including but not limited to a sudden increase in power demand, a reduction in power generation resources, power grid transmission limitations or power outages caused by emergencies.

[0079] Furthermore, the power supplier's power consumption plan is obtained, and based on the user's power consumption behavior trend data and real-time monitoring data, future user demand and power supply capacity are predicted to obtain the load gap, including:

[0080] Identify the key features that affect electricity demand and obtain electricity demand characteristics;

[0081] Dividing the electricity usage behavior trend data into an electricity usage training model and electricity usage test data;

[0082] Selecting a prediction model suitable for the electricity demand characteristics, and training the prediction model using the electricity training data to obtain an electricity prediction model;

[0083] Testing the electricity consumption prediction model using the electricity consumption test data, and obtaining a standard electricity consumption prediction model when the test passes;

[0084] Inputting the real-time monitoring data into the power consumption prediction model to perform dynamic prediction to obtain user demand;

[0085] The power supply capacity of the user end is queried through the power consumption plan, and the load gap is obtained based on the user demand and the power supply capacity.

[0086] In the embodiment of the present invention, the existence of a load gap may cause instability in power supply, affecting the reliability of the power grid and the user's power consumption experience. Therefore, measures need to be taken to solve the power consumption gap to ensure the stability and reliability of power supply.

[0087] S4. According to the load gap and the power consumption plan, controllable load resources are matched from a preset load resource pool to generate a load management plan.

[0088] In the embodiment of the present invention, the load management scheme is used to implement the management of user load resources, and supports file information management, customer agreement management, load resource pool management, load group management, controllable resource evaluation and user load monitoring functions.

[0089] In an embodiment of the present invention, the load resource pool refers to a collection of various resources that can be used to regulate power loads in power demand side management, including various controllable power load resources, such as interruptible loads, demand response resources, energy storage equipment, distributed energy resources, etc. These resources can be dispatched and utilized when the supply and demand of the power grid are unbalanced to achieve load regulation.

[0090] Furthermore, matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan to generate a load management plan includes:

[0091] Obtaining detailed information of all load resources in the load resource pool, and determining resource characteristics that need to be analyzed based on the detailed information;

[0092] Selecting a load resource from the load resource pool based on the resource characteristics to obtain a target load resource, and optimizing the target load resource through a preset optimization algorithm and the load gap and the power consumption plan to obtain an optimized load resource;

[0093] According to the optimized load resources, the control time, control amount, and participating users are adjusted to generate a load management plan.

[0094] The resource characteristics include response time, adjustment capacity, cost, user preference, etc. The optimization algorithm may be a linear programming algorithm, an integer programming algorithm, a heuristic algorithm, etc.

[0095] In the embodiment of the present invention, after matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan and generating a load management plan, the method further includes:

[0096] When the load management scheme is put into use and contacted, the user is informed of the operation to be performed through the customer interaction function, and after the operation is performed, control contact instructions are issued in batches for control contact;

[0097] The load resources after successful contact are restored to the load resource pool.

[0098] In another embodiment of the present invention, a user profile can be constructed for each user to perform user profile information management. Specifically, a unified load management user basic profile is constructed through multi-party data aggregation, cleaning, conversion, and fusion to provide support for the unified management of load resources.

[0099] S5. Execute the load management plan, record abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

[0100] In the embodiment of the present invention, the abnormal information refers to the data or time monitored during the execution of the load management scheme that is inconsistent with the expected or normal operating state, including but not limited to a sudden increase or decrease in power consumption that exceeds the normal fluctuation range; abnormal equipment operating parameters, such as voltage or frequency exceeding the normal operating range; power grid components or systems fail, such as circuit breaker tripping, transformer overload, etc. The alarm notification refers to a notification automatically or manually generated based on the abnormal information, which is used to alert staff to pay attention to and deal with potential problems. The alarm notification usually includes the type and severity level of the alarm; the time, location and affected system or equipment of the alarm; a brief description of the abnormality and possible causes.

[0101] Furthermore, the executing the load management scheme and recording abnormal information occurring during the execution of the scheme include:

[0102] Deploy the instructions and parameters of the load management scheme to a preset power grid management system and user-end equipment;

[0103] The monitoring in the power grid management system is performed, and the operation data and user power consumption data in the power grid management system are collected in real time to obtain monitoring data;

[0104] Monitor abnormal information in the monitoring data.

[0105] In the embodiment of the present invention, alarm notification can ensure that the power grid operator can quickly receive timely notification of abnormal power grid conditions, accurately identify problems and take recommended response measures to reduce risks, optimize resource allocation, and improve power grid stability and reliability. At the same time, it provides data support for accident investigations, system improvements and preventive measures, and enhances the transparency and compliance of power grid operations.

[0106] The embodiment of the present invention first queries various data of the user end through the user number, and monitors to obtain real-time monitoring data; then obtains the historical load data of the user end through the user number, and identifies the power consumption mode and trend, obtains the user's power consumption behavior trend data, and realizes the acquisition of the power consumption behavior trend; then obtains the power supplier's power consumption plan, and predicts future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap; finally, according to the load gap and the power consumption plan, matches the controllable load resources from the preset load resource pool, generates a load management plan, and achieves the purpose of constructing the load management plan; executes the load management plan, records abnormal information, and generates corresponding alarm notifications based on the abnormal information, and contacts the staff for inquiry. Therefore, the load resource management method, device, electronic device and computer-readable storage medium based on the demand side proposed by the present invention predict the power supply capacity and user demand through the monitoring data of the user end and the power consumption behavior trend data in the historical data, calculates the load gap, generates a load management plan based on the load gap and the power consumption plan combined with the load resource pool, manages the load resources through the load management plan, and improves the utilization rate of power resources.

[0107] like Figure 2 The figure shows a module diagram of a load resource management device based on the demand side of the present invention.

[0108] The load resource management device 100 based on the demand side of the present invention can be installed in an electronic device. According to the functions to be implemented, the load resource management device based on the demand side can include a data monitoring module 101, a gap calculation module 102, a solution generation module 103 and an alarm notification module 104. The module of the present invention can also be referred to as a unit, which refers to a series of computer program segments that can be executed by an electronic device processor and can complete fixed functions, which are stored in the memory of the electronic device.

[0109] In this embodiment, the functions of each module / unit are as follows:

[0110] The data monitoring module 101 is used to obtain a user number based on a preset load control instruction, query various data of the user end through the user number, and monitor and obtain real-time monitoring data;

[0111] The gap calculation module 102 is used to obtain the historical load data of the user end through the user number, identify the power consumption pattern and trend, and obtain the user's power consumption behavior trend data; obtain the power consumption plan of the power supplier, and predict the future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap;

[0112] A solution generation module 103 is used to match controllable load resources from a preset load resource pool according to the load gap and the power consumption plan to generate a load management solution;

[0113] The alarm notification module 104 is used to execute the load management plan, record abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

[0114] In detail, each module described in the demand-side based load resource management device 100 in the embodiment of the present invention is used in the same manner as described above. Figure 1 The above-mentioned technical means are the same as the demand-side load resource management method and can produce the same technical effects, so they will not be repeated here.

[0115] like Figure 3 FIG. 1 is a schematic diagram of the structure of an electronic device for implementing a method for load resource management based on the demand side according to the present invention.

[0116] The electronic device may include a processor 10, a memory 11, a communication bus 12, and a communication interface 13, and may also include a computer program stored in the memory 11 and executable on the processor 10, such as a demand-side-based load resource management program.

[0117] In some embodiments, the processor 10 may be composed of an integrated circuit, for example, a single packaged integrated circuit, or a plurality of integrated circuits with the same or different functions, including one or more central processing units (CPUs), microprocessors, digital processing chips, graphics processors, and combinations of various control chips. The processor 10 is the control core (ControlUnit) of the electronic device, and uses various interfaces and lines to connect various components of the entire electronic device, and executes or executes programs or modules stored in the memory 11 (for example, executing a demand-side load resource management program, etc.), and calls data stored in the memory 11 to execute various functions of the electronic device and process data.

[0118] The memory 11 includes at least one type of readable storage medium, and the readable storage medium includes a flash memory, a mobile hard disk, a multimedia card, a card-type memory (for example, SD or DX memory, etc.), a magnetic memory, a disk, an optical disk, etc. In some embodiments, the memory 11 may be an internal storage unit of an electronic device, such as a mobile hard disk of the electronic device. In other embodiments, the memory 11 may also be an external storage device of an electronic device, such as a plug-in mobile hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the electronic device. Further, the memory 11 may also include both an internal storage unit of the electronic device and an external storage device. The memory 11 can not only be used to store application software and various types of data installed in the electronic device, such as the code of the load resource management program based on the demand side, but also can be used to temporarily store data that has been output or is to be output.

[0119] The communication bus 12 may be a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. The bus is configured to realize connection and communication between the memory 11 and at least one processor 10, etc.

[0120] The communication interface 13 is used for communication between the above-mentioned electronic device and other devices, including a network interface and a user interface. Optionally, the network interface may include a wired interface and / or a wireless interface (such as a WI-FI interface, a Bluetooth interface, etc.), which is generally used to establish a communication connection between the electronic device and other electronic devices. The user interface may be a display (Display), an input unit (such as a keyboard (Keyboard)), and optionally, the user interface may also be a standard wired interface, a wireless interface. Optionally, in some embodiments, the display may be an LED display, a liquid crystal display, a touch-sensitive liquid crystal display, and an OLED (Organic Light-Emitting Diode, organic light-emitting diode) touch device, etc. Among them, the display may also be appropriately referred to as a display screen or a display unit, which is used to display information processed in the electronic device and to display a visual user interface.

[0121] Figure 3 Only an electronic device with components is shown, and those skilled in the art will understand that Figure 3 The structure shown does not constitute a limitation on the electronic device, and may include fewer or more components than shown in the figure, or combine certain components, or arrange the components differently.

[0122] For example, although not shown, the electronic device may also include a power source (such as a battery) for supplying power to each component. Preferably, the power source may be logically connected to the at least one processor 10 through a power management device, so that the power management device can realize functions such as charging management, discharging management, and power consumption management. The power source may also include one or more DC or AC power sources, recharging devices, power failure detection circuits, power converters or inverters, power status indicators, and other arbitrary components. The electronic device may also include a variety of sensors, Bluetooth modules, Wi-Fi modules, etc., which will not be repeated here.

[0123] It should be understood that the embodiment is for illustration only and the scope of the patent application is not limited to this structure.

[0124] The demand-side based load resource management program stored in the memory 11 in the electronic device is a combination of multiple computer programs. When running in the processor 10, it can achieve:

[0125] Obtaining a user number based on a preset load control instruction, querying various data of the user end through the user number, and monitoring to obtain real-time monitoring data;

[0126] Obtaining historical load data of the user terminal through the user ID, identifying power consumption patterns and trends, and obtaining user power consumption behavior trend data;

[0127] Obtain the power supplier's power consumption plan, and predict future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap;

[0128] According to the load gap and the power consumption plan, controllable load resources are matched from a preset load resource pool to generate a load management plan;

[0129] Execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

[0130] Specifically, the specific implementation method of the processor 10 for the above computer program can refer to Figure 1 The description of the relevant steps in the corresponding embodiments will not be repeated here.

[0131] Furthermore, if the module / unit integrated in the electronic device is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a non-volatile computer-readable storage medium. The computer-readable storage medium can be volatile or non-volatile. For example, the computer-readable medium can include: any entity or device capable of carrying the computer program code, a recording medium, a USB flash drive, a mobile hard disk, a magnetic disk, an optical disk, a computer memory, and a read-only memory (ROM).

[0132] The present invention further provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor of an electronic device, the computer program can implement:

[0133] Obtaining a user number based on a preset load control instruction, querying various data of the user end through the user number, and monitoring to obtain real-time monitoring data;

[0134] Obtaining historical load data of the user terminal through the user ID, identifying power consumption patterns and trends, and obtaining user power consumption behavior trend data;

[0135] Obtain the power supplier's power consumption plan, and predict future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap;

[0136] According to the load gap and the power consumption plan, controllable load resources are matched from a preset load resource pool to generate a load management plan;

[0137] Execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

[0138] In the several embodiments provided by the present invention, it should be understood that the disclosed devices, apparatuses and methods can be implemented in other ways. For example, the device embodiments described above are only schematic, for example, the division of the modules is only a logical function division, and there may be other division methods in actual implementation.

[0139] The modules described as separate components may or may not be physically separated, and the components shown as modules may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0140] In addition, each functional module in each embodiment of the present invention may be integrated into one processing unit, each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of hardware plus software functional modules.

[0141] It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and that the present invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the present invention.

[0142] Therefore, no matter from which point of view, the embodiments should be regarded as illustrative and non-restrictive, and the scope of the present invention is limited by the appended claims rather than the above description, so it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any attached figure mark in the claims should not be regarded as limiting the claims involved.

[0143] The blockchain referred to in this invention is a new application mode of computer technologies such as distributed data storage, peer-to-peer transmission, consensus mechanism, encryption algorithm, etc. Blockchain is essentially a decentralized database, a string of data blocks generated by cryptographic methods. Each data block contains a batch of network transaction information, which is used to verify the validity of its information (anti-counterfeiting) and generate the next block. Blockchain can include the underlying blockchain platform, platform product service layer, and application service layer.

[0144] The embodiments of the present application can acquire and process relevant data based on artificial intelligence technology. Among them, artificial intelligence (AI) is the theory, method, technology and application system that uses digital computers or machines controlled by digital computers to simulate, extend and expand human intelligence, perceive the environment, acquire knowledge and use knowledge to obtain the best results.

[0145] In addition, it is clear that the word "comprising" does not exclude other units or steps, and the singular does not exclude the plural. Multiple units or devices stated in the system claim can also be implemented by one unit or device through software or hardware. The second and other words are used to indicate names, but not to indicate any particular order.

[0146] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present invention.

Claims

1. A method for load resource management based on the demand side, characterized in that: The method comprises: Obtaining a user number based on a preset load control instruction, querying various data of the user end through the user number, and monitoring to obtain real-time monitoring data; Obtaining historical load data of the user terminal through the user ID, identifying power consumption patterns and trends, and obtaining user power consumption behavior trend data; Obtain the power supplier's power consumption plan, and predict future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap; According to the load gap and the power consumption plan, controllable load resources are matched from a preset load resource pool to generate a load management plan; Execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact staff for inquiries.

2. The method for load resource management based on the demand side according to claim 1, characterized in that: The user ID is used to query various data of the user terminal, and monitor and obtain real-time monitoring data, including: Using the user number, calling a database interface of a power grid management system, and extracting the power consumption data of the user terminal from the database; Retrieve the integrity of said electricity consumption data and integrate data from different sources and types into a unified data warehouse; The real-time monitoring data is obtained by setting a monitoring system for the data warehouse and setting monitoring parameters and thresholds.

3. The method for load resource management based on the demand side according to claim 1, characterized in that: The acquiring of the historical load data of the user terminal through the user ID, and identifying the power consumption pattern and trend, and obtaining the user power consumption behavior trend data, includes: Based on the user number, locate the relevant database of the user terminal, and extract the historical load data of the user terminal from the database; Cleaning the historical load data, removing invalid or erroneous data, and filling in missing values ​​in the historical load data to obtain standard historical load data; The power consumption pattern of the standard historical load data is identified by a cluster analysis algorithm, and time series analysis is performed to identify power consumption trends, thereby obtaining the user power consumption behavior trend data.

4. The method for load resource management based on the demand side according to claim 1, characterized in that: The obtaining of the power supplier's power consumption plan and predicting future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap include: Identify the key features that affect electricity demand and obtain electricity demand characteristics; Dividing the electricity usage behavior trend data into an electricity usage training model and electricity usage test data; Selecting a prediction model suitable for the electricity demand characteristics, and training the prediction model using the electricity training data to obtain an electricity prediction model; Testing the electricity consumption prediction model using the electricity consumption test data, and obtaining a standard electricity consumption prediction model when the test passes; Inputting the real-time monitoring data into the power consumption prediction model to perform dynamic prediction to obtain user demand; The power supply capacity of the user end is queried through the power consumption plan, and the load gap is obtained based on the user demand and the power supply capacity.

5. The method for load resource management based on the demand side according to claim 4, characterized in that: The matching of controllable load resources from a preset load resource pool according to the load gap and the power consumption plan to generate a load management plan includes: Obtaining detailed information of all load resources in the load resource pool, and determining resource characteristics that need to be analyzed based on the detailed information; Selecting a load resource from the load resource pool based on the resource characteristics to obtain a target load resource, and optimizing the target load resource through a preset optimization algorithm and the load gap and the power consumption plan to obtain an optimized load resource; According to the optimized load resources, the control time, control amount, and participating users are adjusted to generate a load management plan.

6. The method for load resource management based on the demand side according to claim 1, characterized in that: The executing of the load management plan and recording of abnormal information occurring during the execution of the plan include: Deploy the instructions and parameters of the load management scheme to a preset power grid management system and user-end equipment; The monitoring in the power grid management system is performed, and the operation data and user power consumption data in the power grid management system are collected in real time to obtain monitoring data; Monitor abnormal information in the monitoring data.

7. The method for load resource management based on the demand side according to any one of claims 1 to 6, characterized in that: After matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan and generating a load management plan, the method further includes: When the load management scheme is put into use and contacted, the user end is informed of the operation to be performed through the customer interaction function, and after the operation is performed, control contact instructions are issued in batches for control contact; The load resources after successful contact are restored to the load resource pool.

8. A load resource management device based on the demand side, characterized in that: The device comprises: A data monitoring module is used to obtain a user number based on a preset load control instruction, query various data of the user end through the user number, and monitor and obtain real-time monitoring data; The gap calculation module is used to obtain the historical load data of the user end through the user number, identify the power consumption mode and trend, and obtain the user's power consumption behavior trend data; obtain the power consumption plan of the power supplier, and predict the future user demand and power supply capacity based on the user's power consumption behavior trend data and real-time monitoring data to obtain the load gap; A scheme generating module, used for matching controllable load resources from a preset load resource pool according to the load gap and the power consumption plan, and generating a load management scheme; The alarm notification module is used to execute the load management plan, record the abnormal information that occurs during the execution of the plan, generate corresponding alarm notifications based on the abnormal information, and contact the staff for inquiry.

9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and, a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the demand-side based load resource management method as described in any one of claims 1 to 7.

10. A computer-readable storage medium, comprising a data storage area and a program storage area, wherein the data storage area stores created data and the program storage area stores a computer program; wherein: When the computer program is executed by a processor, the demand-side based load resource management method as described in any one of claims 1 to 7 is implemented.