Waterproof and drainage construction method for tunnel and leakage monitoring device

Through three-dimensional simulation optimization of construction and the use of leakage strain equipment, the problem of poor tunnel waterproofing and drainage effects was solved, efficient leakage monitoring and protection was achieved, and the safety and efficiency of tunnel waterproofing and drainage construction were improved.

CN118774897APending Publication Date: 2024-10-15ERCHU CO LTD OF CHINA RAILWAY TUNNEL GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410826176.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

The existing tunnel waterproofing and drainage construction methods and monitoring devices are ineffective, making it difficult to effectively prevent groundwater leakage and rainwater intrusion, and there is a lack of mature leakage monitoring devices.

Method used

Three-dimensional simulation software is used to optimize the construction. Reinforced concrete lining is used. The ramp waterproofing is constructed first, and then the main line is fully waterproofed and circumferential blind pipes are laid. It is also equipped with leakage strain equipment and humidity sensing modules. Through sensing positioning and analysis devices Pinpoint the leak location and activate the alarm device.

Benefits of technology

It improves the tunnel's waterproof and drainage effect, enhances leakage monitoring accuracy and construction safety, ensures the normal use of lining structures and equipment, and reduces risks during construction and use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774897A_ABST
    Figure CN118774897A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel construction and waterproofing, in particular to a tunnel waterproof and drainage construction method and a leakage monitoring device.The tunnel waterproof and drainage construction method comprises the following steps that S1, the soil texture of a tunnel excavation soil body is analyzed, and meanwhile three-dimensional simulation software is adopted to simulate and optimize construction in advance; s2, the excavated soil layer is treated, and lining construction is conducted on the tunnel soil layer through reinforced concrete; and S3, waterproof construction: firstly constructing left and right line ramps for waterproofing, and constructing a main line after the ramp lining construction is completed and the main line temporary support is dismantled. Fully wrapping waterproof annular blind pipes, and directly laying geotechnical cloth and waterproof plates; s4, waterproof treatment is conducted on joints such as a construction joint and a deformation joint, waterproof performance of a waterproof layer is enhanced, and normal use of a lining structure and equipment in a hole is ensured; s5, monitoring the seepage condition in the tunnel by adopting seepage strain equipment; the waterproof and drainage construction efficiency of the tunnel can be improved, and the leakage monitoring safety can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction and waterproofing, and in particular to a tunnel waterproofing and drainage construction method and a leakage monitoring device. Background Art

[0002] In tunnel construction, groundwater leakage and rainwater inflow are the main causes of water accumulation inside the tunnel. If there is too much water in the tunnel, it will have a certain impact on the engineering structure; at the same time, since tunnels are often used by vehicles such as cars and trains, if there is water accumulation in the tunnel, it will pose a great threat to driving safety. Therefore, preventing groundwater leakage and rainwater from entering the tunnel and reducing water accumulation inside the tunnel are fundamental measures to prevent floods. Tunnel drainage refers to waterproofing and drainage measures taken to ensure that tunnel construction will not be damaged by water leakage, endanger driving safety, corrode equipment in the tunnel, and reduce the service life of the structure. It is a comprehensive work involving factors such as topography, climate, engineering strata and hydrogeology, structural schemes, construction methods and material properties; the basic requirement should be prevention-oriented. In the construction of shallow buried super-large span tunnels, tunnel drainage construction methods are very important.

[0003] At present, domestic and foreign tunnel drainage construction mostly adopts waterproof lining and the method of adding waterproof layer inside and outside the lining for waterproof design. The layout of drainage pipes is also relatively simple, which has poor effect on tunnel drainage. At the same time, there is no particularly mature monitoring device for leakage monitoring.

[0004] Therefore, it is necessary to further explore more complete and optimized drainage and leakage monitoring solutions based on previous research. Summary of the invention

[0005] The object of the present invention is to provide a tunnel waterproofing and drainage construction method and a leakage monitoring device to solve the problems raised in the above-mentioned background technology.

[0006] The purpose of the present invention can be achieved through the following technical solutions:

[0007] A tunnel waterproofing and drainage construction method comprises the following steps:

[0008] S1: Analyze the soil quality of the tunnel excavation and use 3D simulation software to simulate and optimize the construction in advance;

[0009] S2: Treat the excavated soil layer and use reinforced concrete to line the tunnel soil layer;

[0010] S3: Waterproofing construction: First waterproof the left and right ramps, and then construct the main line after the ramp lining construction is completed and the temporary support of the main line is removed; full waterproofing without annular blind pipes, directly lay geotextiles and waterproof boards;

[0011] S4: Carry out waterproof treatment on construction joints, deformation joints and other joints, strengthen the waterproofing of the waterproof layer, and ensure the normal use of the lining structure and equipment in the tunnel;

[0012] S5: Use leakage strain equipment to monitor the seepage conditions in the tunnel, accurately locate the leakage and trigger the alarm device, process the data based on the feedback of the leakage and take emergency measures.

[0013] Furthermore, in the step S3, during the construction of the waterproof layer, a total station is used to perform cross-section detection on the section to be lined before the waterproof layer is laid;

[0014] The section inspection interval is 2-3m. One section is inspected and written and oral instructions are given to the construction team.

[0015] When under-excavation occurs, the excavation team will organize construction personnel and use the lining waterproof board work platform to deal with the under-excavation. If there is no under-excavation, the next construction process will be carried out and reported to the professional supervision engineer for acceptance.

[0016] Furthermore, in the step S3, when constructing the drainage pipe, the material is half-wrapped waterproof section wall back to evenly lay a circular water guide blind ditch Ø50mm spring soft permeable pipe, the construction spacing is 4m per level V, 6m per level VI; 2 pipes are set in each protruding and gushing section;

[0017] A Ф125 HDPE double-wall perforated corrugated pipe is installed behind the left and right side walls of the main line tunnel, and a Ф100 HDPE double-wall perforated corrugated pipe is installed behind the left and right side walls of the ramp tunnel. The longitudinal slope is consistent with the longitudinal slope of the road surface.

[0018] The two longitudinal blind pipe joints and the annular blind pipe and the longitudinal blind pipe joint are connected with a tee, and the joints are wrapped with non-woven fabrics and tied with wire.

[0019] Furthermore, during the construction of the annular blind pipe and the longitudinal blind pipe, the annular blind pipe construction method is:

[0020] The tunnel arch wall is equipped with an annular blind pipe, which is set according to the design requirements, and a drainage hole is left outside the ditch, and the blind pipe is connected to the longitudinal blind pipe with a tee;

[0021] The construction method of the longitudinal blind pipe is as follows: the longitudinal blind pipe is arranged longitudinally at the left and right arch feet. The main tunnel longitudinal blind pipe adopts a diameter of 125 HDPE double-wall perforated corrugated pipe, and the ramp longitudinal blind pipe adopts a diameter of 100 HDPE double-wall perforated corrugated pipe; the slope of the drainage pipe is consistent with the slope of the line;

[0022] The drainage pipe is positioned by drilling holes with a spacing of 50 cm; it is connected to the annular permeable pipe and the blind pipe through a tee;

[0023] The main line and ramps both use Ф50 HDPE double-wall perforated corrugated pipes as transverse water pipes for the roadbed, and the side ditches on both sides are connected through the transverse water pipes.

[0024] Furthermore, when geotextile is constructed in step S3, the full waterproof layer uses 500g / m2 non-woven fabric, and the half waterproof layer uses 400g / m2 non-woven fabric;

[0025] The geotextile is laid in a whole piece on a hanging trolley, and laid continuously in the circumferential direction. No longitudinal joints are set in the arch wall. The geotextile is cut according to the circumferential length of the initial support surface, and a surplus amount is left. It is rolled and placed on the trolley;

[0026] When the geotextile is laid longitudinally and continuously, a laser locator is used to project the fixed points, and the geotextile is fixed on the base surface with nails and hot-melt washers. It is arranged in a plum blossom shape, fixed left and right, up and down, and additional fixed points are added in uneven places, with a spacing of 3-4 points / m on the arch. 2 , 2-3 points / m on the side wall 2 , the vault is 0.7m, and the side walls are 1.0m;

[0027] Add fixing points where the base is more uneven to make the non-woven fabric fit closely to the base surface.

[0028] Furthermore, when laying the waterproof board in step S3, the waterproof board is constructed 10 to 20 meters ahead of the secondary lining. When laying, the waterproof board is hot-melted on the liner with a manual special welder, and the bonding peel strength shall not be less than the tensile strength of the waterproof board;

[0029] The welder welds by double-seam hot-melt welding process, the overlap width of the two layers of boards shall not be less than 12cm, the width of a single weld shall not be less than 25mm, and a vacuum inspection gap shall be left between the two welds for inflating and checking the tightness of the welds; the bond peel strength of the weld shall not be less than 80% of the tensile strength of the parent body;

[0030] The overlapping and fusion areas between waterproof boards are tested by vacuum pressure.

[0031] Furthermore, when waterproofing the construction joint in step S4, the embedded steel-edge rubber waterstop is drilled with Φ12 holes at a spacing of 1m on the head formwork along the design axis of the second lining, and the Φ10 steel bars are passed through the side of the concrete to be poured, with half of the waterstop clamped on the inner side, and the other half of the waterstop is flat on the head formwork;

[0032] After the secondary lining concrete is poured and solidified, remove the head formwork, straighten the water stop near the joint, then bend the other end of the Φ10 steel bar to fix the water stop, and then mold the next ring of secondary lining;

[0033] Before installing the waterstop, clean the dirt on the surface of the waterstop. During installation, make sure the center line of the waterstop's air holes coincide with the center line of the expansion joint. The caulking plate should be vertical and supported firmly without any mold slippage. The concrete at the construction joint should be vibrated and cured in time.

[0034] Another object of the present invention is to provide a tunnel drainage construction leakage monitoring device, comprising a humidity sensing module, a sensing positioning and analysis device, a leakage prevention alarm device and a computer output terminal; the humidity sensing module senses the tunnel leakage, and the sensing module transmits the leakage information to the sensing positioning and analysis device to accurately locate the leakage position and analyze the seepage amount; the positioning and analysis results are displayed through the computer output terminal;

[0035] When the seepage exceeds the preset critical value, the anti-leakage alarm device is activated to remind construction workers to protect against seepage.

[0036] Beneficial effects of the present invention:

[0037] 1. When laying the waterproof board, the waterproof board is constructed 10 to 20 meters ahead of the secondary lining. When laying, the waterproof board is hot-melted on the liner with a manual special welder, and the bonding peel strength is not less than the tensile strength of the waterproof board; when joining, a manual special welder is used to weld according to the double-seam hot fusion process, and a vacuum inspection gap is left between the two fusion seams for inflating to check the tightness of the fusion seams. The bonding peel strength of the fusion seams shall not be less than 80% of the tensile strength of the parent body. This laying method can not only meet the requirements of waterproof and drainage construction, but also meet the requirements of material performance, and can improve the utilization efficiency of waterproof and drainage materials, thereby improving the waterproof and drainage effect.

[0038] 2. The present invention provides a device for monitoring tunnel leakage. The humidity sensor module senses the tunnel leakage, and the sensor module transmits the leakage information to the sensor positioning and analysis device to accurately locate the leakage position and analyze the seepage volume. The positioning and analysis results are displayed through the computer output terminal. When the seepage exceeds the critical value, the anti-leakage alarm device will be activated to remind the construction personnel to protect against the seepage, thereby improving the safety of construction and later use. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, for those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0040] Figure 1 It is an overall flow chart of the construction method of the present invention;

[0041] Figure 2It is a schematic diagram of drainage in an embodiment of the present invention;

[0042] Figure 3 It is a large-scale drawing of the waterproof layer arrangement in the embodiment of the present invention;

[0043] Figure 4 It is a large-scale drawing of the connection of the longitudinal and transverse water pipes in the embodiment of the present invention;

[0044] Figure 5 It is a waterproof structure diagram of a construction joint in an embodiment of the present invention;

[0045] Figure 6 It is a layout diagram of the detection device in an embodiment of the present invention.

[0046] Figure 7 It is a schematic diagram of the composition of the monitoring device in the embodiment of the present invention.

[0047] In the figure: 1. Pavement ditch; 2. Longitudinal drainage pipe; 3. Horizontal drainage pipe; 4. Drain pipe; 5. Horizontal duct of roadbed; 6. Lateral drainage pipe; 7. Non-woven fabric; 8. Concrete waterproof board; 9. 1.5mm pre-laid polymer waterproof membrane; 10. PVC pipe; 11. Plastic tee; 12. Polymer waterproof layer; 13. P type waterproof reinforcement layer; 14. Water-swelling waterstop; 15. Steel plate waterstop; 16. Cement-based penetrating crystalline waterproof material; 17. Humidity sensor module; 18. Sensor positioning and analysis device; 19. Anti-leakage alarm device; 20. Computer output terminal; A. Waterproof layer sample. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] Embodiment 1:

[0050] See also Figures 1 to 5 In an embodiment of the present invention, a tunnel drainage construction method includes the following steps:

[0051] S1: Analyze the soil quality of the tunnel excavation and use 3D simulation software to simulate and optimize the construction in advance;

[0052] S2: Treat the excavated soil layer and use reinforced concrete to line the tunnel soil layer;

[0053] S3: Waterproofing construction: First waterproof the left and right ramps, and then construct the main line after the ramp lining construction is completed and the temporary support of the main line is removed; full waterproofing without annular blind pipes, directly lay geotextiles and waterproof boards;

[0054] S4: Carry out waterproof treatment on construction joints, deformation joints and other joints, strengthen the waterproofing of the waterproof layer, and ensure the normal use of the lining structure and equipment in the tunnel;

[0055] S5: Use leakage strain equipment to monitor the seepage conditions in the tunnel, accurately locate the leakage and trigger the alarm device, process the data based on the feedback of the leakage and take emergency measures.

[0056] The location distribution of the waterproof facilities, drainage facilities and other construction facilities mentioned in step S3 is as follows: Figure 2 As shown, the specific laying of each waterproof layer and the installation arrangement of the drainage pipe are as follows:

[0057] First, the waterproofing membrane is laid and installed. The location distribution of each waterproofing membrane is as follows: Figure 3 As shown, before laying the waterproof layer, the survey team uses a total station to conduct cross-section detection on the section to be lined, with a cross-section detection interval of 2-3m. After the monitoring is qualified, the non-woven fabric 7 and the concrete waterproof board 8 are installed and laid, and finally the 1.5mm pre-laid polymer waterproof membrane 9 is laid to complete the waterproof construction.

[0058] Then the drainage pipes are laid and installed. Horizontal drainage pipes 3 are evenly laid on the back of the wall of the half-wrapped waterproof section, and a waterproof board hanging trolley is used for hanging. The longitudinal spacing is one every 8 meters; the joints of the two longitudinal drainage pipes 2 and the horizontal drainage pipe 3 are connected with plastic tees 11, and the joints are all wrapped with non-woven fabrics 7 and tied with wire to prevent cement slurry from entering and clogging the drainage pipes when plastering. The number of drainage pipes can be appropriately increased in the initial support of water seepage.

[0059] During the road drainage construction, firstly, road side ditches 1 are set on both sides of the road surface, and lateral drainage pipes 6 are set on both sides of the underground road surface. A certain road surface inclination angle is designed, and the roadbed transverse conduit 5 is installed at the same time. Finally, the drainage pipe 4 is installed to complete the drainage pipe installation.

[0060] Finally, the polymer waterproof layer 12 and the P-type waterproof reinforcement layer 13 are laid, and the waterproof material is spread symmetrically along the tunnel contour from the left and right sides of the trolley top, and the polymer waterproof layer 12 and the P-type waterproof reinforcement layer 13 are stretched out along the tunnel contour with short wooden sticks.

[0061] Use a manual special welder to melt the polymer waterproof layer 12 and preheat the adhesive to make the two hot-melt and bond, which plays the role of fixing the polymer waterproof layer 12. Perform quality inspection to check whether there is leakage welding at the joint, whether there is cold welding and welding penetration at the welding point, and use a manual special welder or welding gun to perform repair welding. When the quality inspection is qualified, the trolley moves to the next working surface.

[0062] After completing the above-mentioned waterproofing and drainage construction, the construction joints and deformation joints are treated. When constructing the embedded steel-edge rubber waterstop, drill Φ12 holes at a spacing of 1m on the head formwork along the designed axis of the second lining, and pass the processed Φ10 steel bars through the side of the concrete to be poured. Clamp half of the steel plate waterstop 15 on the inside, and the other half of the steel plate waterstop 15 is flat on the head formwork.

[0063] After the secondary lining concrete is poured and solidified, the head formwork is removed, the steel plate waterstop 15 near the joint is straightened, and then the other end of the Φ10 steel bar is bent to fix the steel plate waterstop 15, and the next ring of secondary lining is molded.

[0064] Before installing the steel plate water stop 15, the dirt on the surface of the water stop should be cleaned. During installation, the center line of the water stop pores should be aligned with the center line of the deformation joint. The caulking plate must be vertical and firmly supported without mold slipping. The concrete at the construction joint should be vibrated and cured in time. After the construction of the steel plate water stop 15 is completed, the cement-based penetrating crystalline waterproof material 16 should be laid at the construction joint, and the water-expanding water stop glue 14 should be added therein to complete the waterproof construction of the construction joint and the deformation gap.

[0065] After the waterproofing and drainage facilities are completed, the leakage monitoring device will be installed.

[0066] Embodiment 2:

[0067] See also Figure 6-7 On the basis of Example 1, the monitoring device includes a plurality of humidity sensor modules 17, a sensor positioning and analysis device 18, an anti-leakage alarm device 19 and a computer output terminal 20.

[0068] First, the humidity sensor module 17 is installed on the waterproof layer, and then the sensor positioning and analysis device 18 and the anti-leakage alarm device 19 are installed on the top of the tunnel, and finally connected to the computer output terminal 20.

[0069] After the installation is completed, the humidity sensor module senses the tunnel leakage, and the sensor module transmits the leakage information to the sensor positioning and analysis device to accurately locate the leakage position and analyze the seepage volume. The positioning and analysis results are displayed through the computer output terminal.

[0070] When the seepage exceeds a certain limit, the anti-leakage alarm device will be activated, reminding construction workers to protect against seepage.

[0071] Embodiment 3:

[0072] Based on Example 2, several situations simulated using the leakage monitoring device are listed:

[0073] Simulation 1: This simulation is mainly aimed at monitoring the leakage of the tunnel lining waterproof layer under rainfall conditions.

[0074] First, several humidity sensor modules 17 are installed on the pre-prepared tunnel model, and the humidity sensor modules 17 are connected to the sensor positioning and analysis device 18 and the anti-leakage alarm device 19, and the connection status between the computer output terminal 20 and the sensor positioning and analysis device 18 is debugged.

[0075] Then, a water gun is used to spray water to simulate tunnel precipitation, and the amount of rainfall is simulated by adjusting the spray rate of the water gun. When the lining waterproof layer inside the tunnel leaks, the leakage position of the lining waterproof layer is accurately located through the computer output terminal 20, and the leakage data is recorded at the same time, and the limit leakage amount when the anti-leakage alarm device 19 alarms is observed.

[0076] Simulation 2: This simulation is mainly aimed at monitoring the leakage of drainage pipes in tunnels.

[0077] First, several humidity sensor modules 17 are installed on the pre-prepared drainage pipes with leakage. At the same time, the humidity sensor modules 17 are connected to the sensor positioning and analysis device 18 and the anti-leakage alarm device 19, and the connection status between the computer output terminal 20 and the sensor positioning and analysis device 18 is debugged.

[0078] Then, water is passed through the drain pipe, and the water leakage condition is simulated by changing the drainage rate. As the water is passed through, the leakage position of the drain pipe is accurately located at the computer output terminal 20, and the flow rate of the drain pipe is recorded at the same time, and the limit leakage amount when the anti-leakage alarm device 19 alarms is observed.

[0079] Simulation 3: This simulation is mainly aimed at monitoring the situation of water pouring from outside the tunnel into the tunnel.

[0080] First, several humidity sensor modules 17 are installed on the pre-prepared tunnel model, and at the same time, the humidity sensor modules 17 are connected to the sensor positioning and analysis device 18 and the anti-leakage alarm device 19, and the connection status between the computer output terminal 20 and the sensor positioning and analysis device 18 is debugged.

[0081] Then, water is poured into the tunnel through a water pipe, and the water filling situation in the tunnel is simulated by changing the water filling rate. As the water filling progresses, the water level change in the tunnel during the water filling is recorded at the computer output terminal 20, and the limit leakage amount when the anti-leakage alarm device 19 alarms is observed.

[0082] Therefore, the tunnel drainage construction method and leakage monitoring device provided by the present invention can improve the efficiency of drainage construction and the effect of leakage monitoring, and can strengthen the drainage function, thereby reducing the risks during construction and use; through a series of innovative construction methods, it not only has obvious effects on the leakage monitoring of the drainage construction of the Qianmai super-large span tunnel, but also has good effects and guiding significance for the drainage construction and leakage monitoring under other engineering geological conditions.

[0083] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.

Claims

1. A tunnel waterproofing and drainage construction method, characterized in that: The following steps are involved: S1: Analyze the soil quality of the tunnel excavation and use 3D simulation software to simulate and optimize the construction in advance; S2: Treat the excavated soil layer and use reinforced concrete to line the tunnel soil layer; S3: Waterproofing construction: First waterproof the left and right ramps, and then construct the main line after the ramp lining construction is completed and the temporary support of the main line is removed; full waterproofing without annular blind pipes, directly lay geotextiles and waterproof boards; S4: Carry out waterproof treatment on construction joints, deformation joints and other joints, strengthen the waterproofing of the waterproof layer, and ensure the normal use of the lining structure and equipment in the tunnel; S5: Use leakage strain equipment to monitor the seepage conditions in the tunnel, accurately locate the leakage and trigger the alarm device, process the data based on the feedback of the leakage and take emergency measures.

2. A tunnel waterproofing and drainage construction method according to claim 1, characterized in that: In the step S3, during the construction of the waterproof layer, a total station is used to perform cross-section detection on the section to be lined before the waterproof layer is laid; The section inspection interval is 2-3m. One section is inspected and written and oral instructions are given to the construction team. When under-excavation occurs, the excavation team will organize construction personnel and use the lining waterproof board work platform to deal with the under-excavation. If there is no under-excavation, the next construction process will be carried out and reported to the professional supervision engineer for acceptance.

3. The tunnel waterproofing and drainage construction method according to claim 1, characterized in that: In the step S3, when constructing the drainage pipe, the material is half-wrapped waterproof section wall back evenly laid with 50mm spring soft permeable pipes around the water guide blind ditch, the construction spacing is 4m for level V and 6m for level VI; 2 pipes are set for each protruding and gushing section; A Ф125 HDPE double-wall perforated corrugated pipe is installed behind the left and right side walls of the main line tunnel, and a Ф100 HDPE double-wall perforated corrugated pipe is installed behind the left and right side walls of the ramp tunnel. The longitudinal slope is consistent with the longitudinal slope of the road surface. The two longitudinal blind pipe joints and the annular blind pipe and the longitudinal blind pipe joint are connected with a tee, and the joints are wrapped with non-woven fabrics and tied with wire.

4. A tunnel waterproofing and drainage construction method according to claim 3, characterized in that: During the construction of the annular blind pipe and the longitudinal blind pipe, the annular blind pipe construction method is as follows: The tunnel arch wall is equipped with an annular blind pipe, which is set according to the design requirements, and a drainage hole is left outside the ditch, and the blind pipe is connected to the longitudinal blind pipe with a tee; The construction method of the longitudinal blind pipe is as follows: the longitudinal blind pipe is arranged longitudinally at the left and right arch feet. The main tunnel longitudinal blind pipe adopts a diameter of 125 HDPE double-wall perforated corrugated pipe, and the ramp longitudinal blind pipe adopts a diameter of 100 HDPE double-wall perforated corrugated pipe; the slope of the drainage pipe is consistent with the slope of the line; The drainage pipe is positioned by drilling holes with a spacing of 50 cm; it is connected to the annular permeable pipe and the blind pipe through a tee; The main line and ramps both use Ф50 HDPE double-wall perforated corrugated pipes as transverse water pipes for the roadbed, and the side ditches on both sides are connected through the transverse water pipes.

5. The tunnel waterproofing and drainage construction method according to claim 1, characterized in that: When geotextile is constructed in step S3, the full waterproof layer is made of 500g / m2 non-woven fabric, and the half waterproof layer is made of 400g / m2 non-woven fabric; The geotextile is laid in a whole piece on a hanging trolley, and laid continuously in the circumferential direction. No longitudinal joints are set in the arch wall. The geotextile is cut according to the circumferential length of the initial support surface, and a surplus amount is left. It is rolled and placed on the trolley; When the geotextile is laid longitudinally and continuously, a laser locator is used to project the fixed points, and the geotextile is fixed on the base surface with nails and hot-melt washers. It is arranged in a plum blossom shape, fixed left and right, up and down, and additional fixed points are added in uneven places, with a spacing of 3-4 points / m on the arch. 2 , 2-3 points / m on the side wall 2 , the vault is 0.7m, and the side walls are 1.0m; Add fixing points where the base is more uneven to make the non-woven fabric fit closely to the base surface.

6. The tunnel waterproofing and drainage construction method according to claim 1, characterized in that: When laying the waterproof board in step S3, the waterproof board is constructed 10 to 20 meters ahead of the secondary lining. When laying, the waterproof board is hot-melted on the liner with a manual special welder, and the bonding peel strength shall not be less than the tensile strength of the waterproof board; The welder welds by double-seam hot-melt welding process, the overlap width of the two layers of boards shall not be less than 12cm, the width of a single weld shall not be less than 25mm, and a vacuum inspection gap shall be left between the two welds for inflating and checking the tightness of the welds; the bond peel strength of the weld shall not be less than 80% of the tensile strength of the parent body; The overlapping and fusion areas between waterproof boards are tested by vacuum pressure.

7. The tunnel waterproofing and drainage construction method according to claim 1, characterized in that: When waterproofing the construction joint in step S4, the embedded steel-edge rubber waterstop is drilled with Φ12 holes at a spacing of 1m on the head formwork along the design axis of the second lining, and the Φ10 steel bars are passed through the side of the concrete to be poured, with half of the waterstop clamped on the inner side, and the other half of the waterstop is flat on the head formwork; After the secondary lining concrete is poured and solidified, remove the head formwork, straighten the water stop near the joint, then bend the other end of the Φ10 steel bar to fix the water stop, and then mold the next ring of secondary lining; Before installing the waterstop, clean the dirt on the surface of the waterstop. During installation, make sure the center line of the waterstop's air holes coincide with the center line of the expansion joint. The caulking plate should be vertical and supported firmly without any mold slippage. The concrete at the construction joint should be vibrated and cured in time.

8. A tunnel drainage construction leakage monitoring device, characterized in that: It includes a humidity sensing module, a sensing positioning and analysis device, an anti-leakage alarm device and a computer output terminal; the humidity sensing module senses the tunnel leakage, and the sensing module transmits the leakage information to the sensing positioning and analysis device to accurately locate the leakage position and analyze the seepage amount; the positioning and analysis results are displayed through the computer output terminal; When the seepage exceeds the preset critical value, the anti-leakage alarm device is activated to remind construction workers to protect against seepage.