Distribution network construction equipment cost analysis control method and system
By collecting and analyzing various cost data of power distribution network projects, setting early warning mechanisms and real-time feedback, the problem of lack of management systems in distribution network construction is solved, and effective control of equipment costs and improvement of construction efficiency is achieved.
Patent Information
- Application Number
- CN202410852928.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-28
- Publication Date
- 2024-11-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the construction of power distribution network projects, the lack of complete engineering management systems and standards has led to unsuccessful cost management work, affecting overall quality and cost control.
By collecting and analyzing employment costs, material costs, equipment costs and operation and maintenance management costs, calculating the total investment costs and total revenue, setting different levels of early warning mechanisms, and real-time feedback and reminding clients through wireless transmission technology and graphic display tools Equipment cost control status of distribution network construction.
It has achieved effective control of the cost of distribution network construction equipment, timely adjustment of investment costs, ensure profitability, and improve construction efficiency and overall quality.
Smart Images

Figure CN118886733A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of distribution network construction, and in particular to a distribution network construction equipment cost analysis control method and system. Background Art
[0002] Abstract Electric energy is an indispensable basic energy in our daily life and has a very important and special status; with the continuous implementation of distribution network engineering projects, the rationalization control of engineering costs must be the focus of work, and engineering cost control is one of the most critical contents in the construction of power distribution network engineering projects; using new technologies and advanced equipment, constantly exploring new construction methods, using more advanced and scientific technologies at home and abroad to enhance the management of the construction process, save costs, enhance the overall economic value and social value, so that the rationalization control of engineering costs can be implemented more effectively, thereby accelerating the future development of power distribution network engineering projects.
[0003] As our quality of life improves, the demand for electricity is also gradually increasing, and at the same time, there are higher requirements for the reliability of electricity; a more comprehensive and sound management system can greatly improve the overall quality of power distribution network projects, and can also ensure the overall construction efficiency of distribution network projects; however, in the current stage of power distribution network project construction, relevant units have not formulated more complete engineering management systems and standards, which makes the subsequent work not smooth enough, and also has a great obstacle to the orderly progress of cost management work, which has a great impact on the overall quality of subsequent work.
[0004] Therefore, the existing needs are not met, and we propose a distribution network construction equipment cost analysis control method and system. Summary of the invention
[0005] The purpose of the present invention is to provide a distribution network construction equipment cost analysis and control method and system, by obtaining various cost data and various revenue data, the total investment cost and the total revenue are statistically obtained; the distribution network construction revenue status is obtained by comparing and calculating, and then the distribution network construction equipment cost control effect is obtained, so that when the control effect is not good, the projects with high or unreasonable investment costs can be adjusted in time; by setting different levels of early warning mechanisms, signal lights of different colors flash for different levels of loss status, thereby reminding the client of the current equipment cost control effect of the distribution network construction; and by drawing bar charts to intuitively display various cost data, so that the client can quickly view the current projects with high or unreasonable investment costs, ensure the effective control of the distribution network construction equipment cost, and solve the problems raised in the above background technology.
[0006] To achieve the above object, the present invention provides the following technical solutions:
[0007] A distribution network construction equipment cost analysis and control method comprises the following steps:
[0008] S1. Collect the labor costs, material costs, equipment costs and operation and maintenance management costs in the construction of the distribution network. After obtaining the cost data of each item, calculate the total investment cost in the construction of the distribution network;
[0009] S2. Collect various revenue data of the distribution network during the construction of the distribution network, and after obtaining various revenue data, calculate the total revenue of the distribution network construction;
[0010] S3. Enable the cost accounting function to calculate and analyze the total investment cost and total income in the distribution network construction to obtain the profit and loss status of the distribution network construction;
[0011] S4. Based on wireless transmission technology, the total input cost, total income and profit and loss status are fed back to the client in real time, and a bar chart is used to display the input cost data and the income data, and a pie chart is used to display the total input cost, total income and profit and loss ratio of the period;
[0012] S5. Set up different levels of early warning mechanisms under loss conditions, set different levels of early warning intervals for the loss conditions of distribution network construction, and configure different color signal lights on the client to ensure that the client receives prompt signals of the loss conditions of distribution network construction in a timely manner;
[0013] S6. When the distribution network construction is in a loss, the client determines the loss level through signal lights of different colors, and then checks the input cost data during the loss period based on the bar chart, and adjusts the costs of projects with high or unreasonable input costs at the moment, to ensure effective control of the distribution network construction equipment costs.
[0014] Furthermore, obtaining the profit and loss status of the distribution network construction in S3 specifically includes the following steps:
[0015] The total cost and total income of each item in the distribution network construction are recorded through Excel tables, and the total cost and total income are obtained through statistical functions in Excel tables;
[0016] The total input cost and total income are compared and analyzed. When the total income is greater than the total input cost, it means that the distribution network construction is currently in a profitable state, and it also means that the current equipment cost of the distribution network construction is under effective control; when the total income is equal to the total input cost, it means that the distribution network construction is currently in a slightly profitable state, and it also means that the current equipment cost of the distribution network construction is under good control; when the total income is less than the total input cost, it means that the distribution network construction is currently in a loss-making state, and it also means that the current equipment cost of the distribution network construction is in a state of control failure. Based on this, the profit and loss status of the distribution network construction is obtained.
[0017] Furthermore, the S5 sets different levels of early warning mechanisms, which specifically include the following steps:
[0018] After obtaining the loss status of distribution network construction through S3, the first-level warning interval, second-level warning interval and third-level warning interval are set according to the ratio of total input cost to total income. The first-level warning interval is when the total input cost is 5%-10% higher than the total income, the second-level warning interval is when the total input cost is 3%-5% higher than the total income, and the third-level warning interval is when the total input cost is 1%-3% higher than the total income;
[0019] Different color signal lights are set for the first-level warning interval, the second-level warning interval and the third-level warning interval, that is: the first-level warning interval is red, the second-level warning interval is yellow, and the third-level warning interval is blue. The profit status is set to green, and the micro-profit status is set to purple. Based on this, the cost control status of the current distribution network construction is distinguished.
[0020] Furthermore, after obtaining the profit and loss status of the distribution network construction through S3, when the distribution network construction is in a profitable state, the signal light is green; when the distribution network construction is in a slightly profitable state, the signal light is purple; when the distribution network construction is in the third-level warning interval, the signal light is blue; when the distribution network construction is in the second-level warning interval, the signal light is yellow; when the distribution network construction is in the first-level warning interval, the signal light is red.
[0021] A distribution network construction equipment cost analysis control system, comprising
[0022] Data collection unit for
[0023] Collect various input cost data and various income data of distribution network construction to determine whether the equipment cost investment of distribution network construction is in a normal state;
[0024] Statistics unit for
[0025] According to Excel spreadsheets, the collected input cost data and distribution network revenue data are sorted and counted to obtain the total input cost and total revenue in distribution network construction;
[0026] Data accounting unit, used for
[0027] Compare and calculate the total investment cost and total income after statistics to determine whether the current profit or loss status of the distribution network construction is proportional to the equipment investment cost;
[0028] Warning establishment unit, used for
[0029] An early warning mechanism is set up for the loss status of distribution network construction. Different levels of warning intervals and corresponding color signal lights are used to remind the client of the current loss status of distribution network construction, and the loss status is remedied in time;
[0030] Client, for
[0031] The total input cost, total income and profit and loss status are received based on wireless transmission technology, and warning lights of different colors are emitted for loss status.
[0032] Furthermore, the data statistics unit includes
[0033] The data cleaning module is used to delete duplicate and erroneous data in various input cost data and distribution network revenue data, and use the median value method to supplement the missing data to ensure the validity of various data;
[0034] The graphics production module is used to draw bar charts of various input cost data and various distribution network revenue data, and is also used to draw pie charts of total input cost, total revenue and profit and loss status ratio.
[0035] Furthermore, the data cleaning module includes:
[0036] A duplicate data extraction module, used to extract duplicate data from the various input cost data and various distribution network revenue data;
[0037] The first data coefficient acquisition module is used to extract the data amount corresponding to the erroneous data appearing in the repeated data, and obtain the first data coefficient of the erroneous data corresponding to the repeated data; wherein the first data coefficient is obtained by the following formula:
[0038]
[0039] Among them, Q 01 represents the first data coefficient of the erroneous data corresponding to the repeated data; n represents the number of data items with erroneous data in the repeated data; ω i Represents the weight coefficient corresponding to the i-th error data; ω z Represents the comprehensive value of the weight coefficients contained in the repeated data; R c Indicates the total amount of erroneous data in the duplicate data; R z Indicates the total amount of data corresponding to the repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the duplicate data;
[0040] An error data extraction module is used to extract the data volume corresponding to the error data in the non-duplicate data;
[0041] The second data coefficient acquisition module is used to acquire the second data coefficient by using the data amount corresponding to the error data in the non-repetitive data; wherein the second data coefficient is acquired by the following formula:
[0042]
[0043] Among them, Q 02 represents the second data coefficient; m represents the number of erroneous data in the non-repeated data; ω j Represents the weight coefficient corresponding to the jth erroneous data in the non-repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data;
[0044] A first early warning module, configured to issue a data quality abnormality alarm when the second data coefficient exceeds the first data coefficient;
[0045] A comprehensive data coefficient acquisition module is used to obtain a comprehensive data coefficient using the first data coefficient and the second data coefficient when the second data coefficient does not exceed the first data coefficient, wherein the comprehensive data coefficient is obtained by the following formula:
[0046]
[0047] Among them, Q represents the comprehensive data coefficient; Q 01 The first data coefficient representing the erroneous data corresponding to the repeated data; Q 02 represents the second data coefficient; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data;
[0048] The second early warning module is used to issue a data quality abnormality alarm when the comprehensive data coefficient exceeds a preset comprehensive coefficient threshold.
[0049] Furthermore, the data accounting unit includes
[0050] The status transmission module is used to provide real-time feedback of the total investment cost, total income and profit and loss status to the client based on wireless transmission technology.
[0051] Furthermore, the warning establishment unit includes:
[0052] The interval establishment module is used to establish different levels of warning intervals according to the loss status, namely: first-level warning interval, second-level warning interval and third-level warning interval;
[0053] The light color establishment module is used to establish signal lights of different colors according to different levels of warning intervals, namely: the first-level warning interval is red, the second-level warning interval is yellow, and the third-level warning interval is blue. The profit status is set to green, and the micro-profit status is set to purple.
[0054] Furthermore, the warning establishment unit also includes
[0055] The light color association module is used to associate and bind different levels of warning intervals with different color signal lights to ensure the effectiveness of the signal light output;
[0056] The central controller is used to turn on the signal light of the corresponding color number to flash according to the received loss status.
[0057] Compared with the prior art, the present invention has the following beneficial effects:
[0058] 1. The present invention obtains various cost data and various revenue data in the distribution network construction, and statistically obtains the total input cost and the total revenue; the total input cost and the total revenue are compared and calculated to obtain the current revenue status of the distribution network construction, and then the current equipment cost control effect of the distribution network construction is obtained, so that when the equipment cost control effect is not good, the cost of projects with high input costs or unreasonable input costs can be adjusted in time to ensure effective control of the equipment cost of the distribution network construction.
[0059] 2. The present invention sets different levels of early warning mechanisms and flashes signal lights of different colors for different levels of loss status, thereby reminding the client of the current equipment cost control effect of the distribution network construction; and intuitively displays various cost data by drawing bar charts, so that the client can quickly check the projects with high or unreasonable investment costs at present, further ensuring the effective control of the equipment cost of the distribution network construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] Figure 1 It is a logic diagram of the cost analysis and control method of the distribution network construction equipment of the present invention;
[0061] Figure 2 This is a composition diagram of the distribution network construction equipment cost analysis control system of the present invention. DETAILED DESCRIPTION
[0062] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0063] In order to solve the technical problems in the existing power distribution network construction, the relevant units have not formulated a relatively complete engineering management system and standards, which makes the subsequent work not smooth, and also has a great obstacle to the orderly progress of cost management work, which has a great impact on the overall quality of subsequent work. Figure 1-Figure 2 , this embodiment provides the following technical solutions:
[0064] A distribution network construction equipment cost analysis and control method comprises the following steps:
[0065] S1. Collect the labor costs, material costs, equipment costs and operation and maintenance management costs in the construction of the distribution network. After obtaining the cost data of each item, calculate the total investment cost in the construction of the distribution network;
[0066] In this embodiment, for example, by selecting a certain distribution plant as the target distribution plant of this embodiment, the current labor cost data, material cost data, equipment cost data and operation and maintenance management cost data of the distribution plant are obtained. The labor cost expenses mainly include the wages and welfare expenses of basic construction personnel, technical personnel and supervisors; the material costs mainly include cables, wires, switches, sockets, distribution boxes, terminal blocks, etc., and the equipment costs include various lifting equipment, transportation equipment, and construction equipment; in the construction of distribution projects, commonly used equipment includes hoists, cranes, mixers, pile drivers, etc.; the operation and maintenance management costs include water and electricity charges, communication fees, travel expenses, accommodation fees, etc. related to the construction site.
[0067] S2. Collect various revenue data of the distribution network during the construction of the distribution network, and after obtaining various revenue data, calculate the total revenue of the distribution network construction;
[0068] Continuing with the above embodiment, for example, after obtaining the current cost data of the distribution plant, the revenue data of the distribution network are also required. The revenue mainly includes: revenue from electricity purchase and sale, revenue from the "grid access fee" of the distribution network, capacity costs of the distribution network, comprehensive energy revenue and revenue from value-added services.
[0069] S3. Enable the cost accounting function to calculate and analyze the total input cost and total income in the distribution network construction to obtain the profit and loss status of the distribution network construction; specifically include the following steps: record the total input costs and total income in the distribution network construction through Excel tables, and obtain the total input costs and total income through statistical functions in Excel tables; compare and analyze the total input costs and total income. When the total income is greater than the total input costs, it indicates that the distribution network construction is currently in a profitable state, and also indicates that the current equipment cost of the distribution network construction is under effective control; when the total income is equal to the total input cost, it indicates that the distribution network construction is currently in a slightly profitable state, and also indicates that the current equipment cost of the distribution network construction is under good control; when the total income is less than the total input cost, it indicates that the distribution network construction is currently in a loss state, and also indicates that the current equipment cost of the distribution network construction is in a state of control failure. Based on this, the profit and loss status of the distribution network construction is obtained;
[0070] Continuing with the above embodiment, for example: the client draws an Excel table through a computer device, imports the above-collected data into the Excel table, and obtains the total investment cost and the total income through the Excel table summary function; for example: the current total investment cost in the Excel table is 100 million yuan, and the total income is 150 million yuan. After comparison and calculation, it is concluded that the current total investment cost of 100 million yuan is less than the total income of 150 million yuan, which indicates that the current distribution network construction operation status is in a profitable state, and then indicates that the current distribution network construction equipment cost is effectively controlled; otherwise, the opposite is true.
[0071] S4. Based on wireless transmission technology, the total input cost, total income and profit and loss status are fed back to the client in real time, and a bar chart is used to display the input cost data and the income data, and a pie chart is used to display the total input cost, total income and profit and loss ratio of the period;
[0072] Continuing with the above embodiment, for example: the client draws bar charts and pie charts through computer equipment, displays various input cost data and various revenue data through bar charts, and displays the total investment cost, total revenue and the proportion of profit and loss status through pie charts, thereby facilitating the client to more intuitively understand the current investment cost and revenue ratio of distribution network construction.
[0073] S5. Set up different levels of early warning mechanisms under loss status, set different levels of early warning intervals for the loss status of distribution network construction, and configure different color signal lights on the client to ensure that the client receives prompt signals of the loss status of distribution network construction in a timely manner; specifically, the following steps are included:
[0074] After obtaining the loss status of distribution network construction through S3, the first-level warning interval, second-level warning interval and third-level warning interval are set according to the ratio of total input cost to total income. The first-level warning interval is when the total input cost is 5%-10% higher than the total income, the second-level warning interval is when the total input cost is 3%-5% higher than the total income, and the third-level warning interval is when the total input cost is 1%-3% higher than the total income;
[0075] Set different color signal lights for the first-level warning interval, the second-level warning interval and the third-level warning interval, that is: the first-level warning interval is red, the second-level warning interval is yellow, and the third-level warning interval is blue, and the profit state is set to green, and the micro-profit state is set to purple; based on this, distinguish the cost control state of the current distribution network construction; when the distribution network construction is in a profitable state, the signal light is green; when the distribution network construction is in a micro-profit state, the signal light is purple; when the distribution network construction is in the third-level warning interval, the signal light is blue; when the distribution network construction is in the second-level warning interval, the signal light is yellow; when the distribution network construction is in the first-level warning interval, the signal light is red;
[0076] Continuing with the above embodiment, for example, through statistics, it is concluded that the current total investment cost is 100 million yuan, and the total income is 150 million yuan. After calculation, it is determined that the current total investment cost is 100 million yuan, which is less than the total income of 150 million yuan, indicating that the current distribution network construction operation status is in a profitable state, and then it indicates that the current distribution construction equipment cost is effectively controlled, and the signal light is green at this time; if the current total investment cost is 100 million yuan, and the total income is 110 million yuan, after calculation, it is determined that the total investment cost and the total income are basically kept equal, then it indicates that the current distribution network construction operation status is in a slightly profitable state, and then it indicates that the current distribution construction equipment cost is well controlled, and the signal light is purple at this time; if the current total investment cost is 100 million yuan, and the total income is 90 million yuan, after calculation, it is determined that the total investment cost is higher than 1%-3% of the total income, then it indicates that the current is a loss level 3 warning interval, indicating that the current distribution construction equipment cost is not well controlled, and the signal light is blue at this time; and so on, the revenue status of the current distribution network construction is explained through signal lights of different colors, so that the client can obtain effective information in a timely manner.
[0077] S6. When the distribution network construction is at different levels of loss, the client will judge the loss level through different color signal lights, and then check the input cost data of each item in the loss period according to the bar chart, and adjust the cost of projects with high or unreasonable input costs at the moment, to ensure effective control of the distribution network construction equipment cost;
[0078] Continuing with the above embodiment, for example: if the current total investment cost is 100 million yuan and the total income is 90 million yuan, and after calculation it is determined that the total investment cost is higher than 1%-3% of the total income, it means that the current period is in the third-level warning interval for losses, indicating that the current distribution network construction equipment costs are not well controlled; at this time, the client can view the bar chart of the various investment cost data for this period to check whether there are unreasonable factors in the various investment costs, and make rational adjustments based on the unreasonable factors obtained, thereby realizing the analysis and control of the distribution network construction equipment costs.
[0079] A distribution network construction equipment cost analysis and control system, comprising:
[0080] Data collection unit for
[0081] Collect various input cost data and distribution network revenue data in distribution network construction to determine whether the equipment cost input of distribution network construction is in a normal state; specifically, the input cost data includes: labor cost, material cost, equipment cost and operation and maintenance management cost. Human cost refers to the cost used to pay the wages of engineering personnel during the construction of distribution projects; these personnel include construction personnel, technical personnel, supervision personnel, etc.; construction personnel are mainly responsible for specific construction work, and their human cost mainly includes wages, welfare expenses, etc.; technical personnel are mainly responsible for engineering design, technical guidance and other work, so this part of human cost is usually relatively high; supervision personnel are mainly responsible for the supervision and acceptance of the project, so this part of human cost is also relatively high; in the construction of distribution projects, human cost usually accounts for a considerable proportion; material cost refers to the cost of purchasing electrical equipment, cables, distribution boxes and other materials during the construction of distribution projects; in the construction of distribution projects, commonly used materials include cables, wires, switches, sockets, distribution boxes, terminal blocks, etc.; these materials are an indispensable part of distribution projects, and their quality and quantity directly affect the quality and progress of the project. degree; therefore, in the construction of power distribution projects, material costs usually account for a large proportion; equipment cost refers to the cost of purchasing various mechanical equipment required for construction during the construction of power distribution projects; in the construction of power distribution projects, commonly used equipment includes various lifting equipment, transportation equipment, and construction equipment. The selection and use of equipment directly affects the efficiency and quality of construction; the cost of equipment is high, so it also has a great impact on the cost of the project; operation and maintenance management cost refers to the main responsibility for the organization and coordination of the project, which plays a vital role in the progress and quality of the project, including water and electricity fees, communication fees, travel expenses, accommodation fees, etc.; water and electricity fees are the costs of daily life and construction water and electricity at the construction site, communication fees are the costs incurred by the communication between construction personnel and management personnel, travel expenses are the costs incurred by management personnel traveling to other places due to work needs, and accommodation fees are the accommodation costs of non-local staff; in general, these costs play a vital role in the construction of power distribution projects and directly affect the quality, progress and cost of the project; therefore, when carrying out the construction of power distribution projects, it is necessary to seriously consider these costs and arrange the budget reasonably to ensure that the project can proceed smoothly and achieve the expected results;
[0082] Secondly, the various revenue data of the distribution network include: revenue from electricity purchase and sale, and incremental distribution operators, as regional guaranteed power supply service agencies, have a good social image and inherent advantages in operating power sales business; revenue from distribution network "grid access fee", and operators of investment incremental distribution networks can charge "distribution network" grid access fees according to the distribution price after obtaining the electricity business license (power supply type); distribution network capacity fees, and the basic electricity fee paid by the distribution network to the power grid is based on the capacity of the substation, and the basic electricity fee charged by the distribution and sales company to users is calculated based on the capacity or demand of a single household. When the load reaches a certain level, the two will generate additional revenue; comprehensive energy revenue, and investment in the park's comprehensive energy network will generate corresponding revenue; value-added service revenue, in order to open up the user-side and grid-side power energy services and make up for the lack of refined services on the user side of the traditional power grid, the following services can be carried out and generate revenue.
[0083] Statistics unit for
[0084] According to the Excel table, the collected input cost data and distribution network revenue data are sorted and counted to obtain the total input cost and total revenue in the distribution network construction; specifically, the above data are recorded by creating an Excel table, and the cost data and revenue data are summarized and counted respectively according to the Excel table summary function, thereby obtaining the total input cost and total revenue of the current distribution network construction.
[0085] Statistics unit, including:
[0086] The data cleaning module is used to delete duplicate data and erroneous data in various input cost data and distribution network revenue data, and to supplement the missing data using the intermediate value method to ensure the validity of various data. Specifically, due to the large and complex amount of data, in the process of collection and transmission, the final statistical data is often affected by external factors, such as: partial data transmission failure or partial data repeated transmission. Therefore, when recording it, it is necessary to delete duplicate data and erroneous data, and then supplement the missing data, thereby ensuring the validity of various data and the authenticity of equipment cost control analysis.
[0087] The graphics production module is used to draw bar charts of various input cost data and various distribution network revenue data, and is also used to draw pie charts of total input cost, total revenue and profit and loss status ratio; specifically, due to the complex attributes of input cost data, it is difficult to intuitively display the amount of various data through a single Excel table. In the bar chart, by observing the height of the bars, the input amount of various costs can be intuitively understood, so that the cost of unreasonable projects can be quickly adjusted in the later stage, thereby improving the control effect of distribution network construction equipment costs.
[0088] Data accounting unit, used for
[0089] Compare and calculate the total investment cost and total income after statistics to determine whether the current profit and loss status of the distribution network construction is proportional to the equipment investment cost; specifically, summarize the total investment cost and total income through Excel spreadsheet, and compare the two. If the total investment cost is lower than the total income, it means that the current distribution network construction is proportional and profitable; otherwise, the opposite is true.
[0090] Data accounting unit, including
[0091] The status transmission module is used to provide real-time feedback of the total investment cost, total income and profit and loss status to the client based on wireless transmission technology.
[0092] Warning establishment unit, used for
[0093] An early warning mechanism is set up for the loss status of distribution network construction. Different levels of early warning intervals and corresponding color signal lights are used to remind the client of the current loss status of distribution network construction, and the loss status is remedied in time; the early warning establishment unit includes:
[0094] The interval establishment module is used to establish different levels of warning intervals according to the loss status, namely: first-level warning interval, second-level warning interval and third-level warning interval; specifically: the first-level warning interval is 5%-10% of the total input cost higher than the total income, the second-level warning interval is 3%-5% of the total input cost higher than the total income, and the third-level warning interval is 1%-3% of the total input cost higher than the total income;
[0095] The light color establishment module is used to establish different color signal lights according to different levels of warning intervals, that is, the first-level warning interval is red, the second-level warning interval is yellow, and the third-level warning interval is blue. The profit status is set to green, and the micro-profit status is set to purple;
[0096] The light color association module is used to associate and bind different levels of warning intervals with different color signal lights to ensure the effectiveness of the signal light output;
[0097] The central controller is used to turn on the signal light of the corresponding color to flash according to the received loss status; specifically, the central controller uses the current loss status of the distribution network construction received by science fiction and the pre-established early warning mechanism to control the signal light to flash the corresponding color, thereby facilitating the client to intuitively understand the current loss status of the distribution network construction.
[0098] Client, for
[0099] The total input cost, total income and profit and loss status are received based on wireless transmission technology, and warning lights of different colors are emitted for loss status.
[0100] The beneficial effects achieved by the above content are as follows: Through the above method, the current equipment cost control effect can be judged according to the current revenue status of the distribution network construction, so that when the equipment cost control effect is not good, timely cost adjustment can be made to the projects with high investment costs or unreasonable investment costs, so as to ensure the effective control of the equipment cost of the distribution network construction; signal lights of different colors flash for different levels of loss status, which can effectively remind the client of the current equipment cost control effect of the distribution network construction; and various cost data can be intuitively displayed by drawing bar charts, so that the client can quickly view the projects with high investment costs or unreasonable investment costs, so as to further ensure the effective control of the equipment cost of the distribution network construction.
[0101] Working principle: By obtaining various cost data and various revenue data, the total input cost and total revenue are calculated; the revenue status of distribution network construction is obtained by comparison and calculation, and then the cost control effect of distribution network construction equipment is obtained, so that when the control effect is not good, the projects with high or unreasonable input costs can be adjusted in time; by setting different levels of early warning mechanisms, signal lights of different colors flash for different levels of loss status, thereby reminding the client of the current equipment cost control effect of distribution network construction; and by drawing bar charts to intuitively display various cost data, so that the client can quickly view the current projects with high or unreasonable input costs.
[0102] Specifically, the data cleaning module includes:
[0103] A duplicate data extraction module, used to extract duplicate data from the various input cost data and various distribution network revenue data;
[0104] The first data coefficient acquisition module is used to extract the data amount corresponding to the erroneous data appearing in the repeated data, and obtain the first data coefficient of the erroneous data corresponding to the repeated data; wherein the first data coefficient is obtained by the following formula:
[0105]
[0106] Among them, Q 01 represents the first data coefficient of the erroneous data corresponding to the repeated data; n represents the number of data items with erroneous data in the repeated data; ω i Represents the weight coefficient corresponding to the i-th error data; ω z Represents the comprehensive value of the weight coefficients contained in the repeated data; R c Indicates the total amount of erroneous data in the duplicate data; R z Indicates the total amount of data corresponding to the repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmaxIndicates the amount of erroneous data corresponding to the maximum weight value contained in the duplicate data;
[0107] An error data extraction module is used to extract the data volume corresponding to the error data in the non-duplicate data;
[0108] The second data coefficient acquisition module is used to acquire the second data coefficient by using the data amount corresponding to the error data in the non-repetitive data; wherein the second data coefficient is acquired by the following formula:
[0109]
[0110] Among them, Q 02 represents the second data coefficient; m represents the number of erroneous data in the non-repeated data; ω j Represents the weight coefficient corresponding to the jth erroneous data in the non-repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data;
[0111] A first early warning module, configured to issue a data quality abnormality alarm when the second data coefficient exceeds the first data coefficient;
[0112] A comprehensive data coefficient acquisition module is used to obtain a comprehensive data coefficient using the first data coefficient and the second data coefficient when the second data coefficient does not exceed the first data coefficient, wherein the comprehensive data coefficient is obtained by the following formula:
[0113]
[0114] Among them, Q represents the comprehensive data coefficient; Q 01 The first data coefficient representing the erroneous data corresponding to the repeated data; Q 02 represents the second data coefficient; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data;
[0115] The second early warning module is used to issue a data quality abnormality alarm when the comprehensive data coefficient exceeds a preset comprehensive coefficient threshold.
[0116] The technical effect of the above technical solution is: through the duplicate data extraction module and the error data extraction module, the system can accurately identify and extract duplicate data and error data in the data, which is a key step in data cleaning and helps to improve the accuracy and reliability of the data. Through the first data coefficient acquisition module and the second data coefficient acquisition module, the solution provides a quantitative evaluation indicator (i.e., data coefficient) for duplicate data and error data. This makes data quality issues measurable and facilitates managers to monitor and manage data quality.
[0117] The setting of the first warning module and the second warning module enables the system to automatically issue an alarm when the data quality problem reaches a certain level (that is, the data coefficient exceeds a certain threshold). This helps to discover and deal with data quality problems in a timely manner and prevent the further spread and use of problematic data. The comprehensive data coefficient acquisition module can comprehensively consider the impact of duplicate data and erroneous data and give a comprehensive data quality assessment indicator. This helps to grasp the data quality status from a global perspective and provide decision support for data quality management and improvement. The various modules in this solution can work independently or collaboratively, and have high flexibility. At the same time, by adjusting the weight coefficient and comprehensive coefficient threshold in the calculation formula of the data coefficient, it can adapt to the data quality assessment requirements under different scenarios and needs.
[0118] In summary, the above technical solution realizes comprehensive monitoring and early warning of data quality through a series of modular processing processes, which helps to improve the accuracy and reliability of data and provide strong support for the company's data-driven decision-making.
[0119] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0120] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A cost analysis and control method for distribution network construction equipment, It is characterized in that The following steps are involved: S1. Collect the labor costs, material costs, equipment costs and operation and maintenance management costs in the construction of the distribution network. After obtaining the data of various input costs, calculate the total input cost in the construction of the distribution network; S2. Collect various revenue data of the distribution network during the construction of the distribution network, and after obtaining various revenue data, calculate the total revenue of the distribution network construction; S3. Enable the cost accounting function to calculate and analyze the total investment cost and total income in the distribution network construction to obtain the profit and loss status of the distribution network construction; S4. Based on wireless transmission technology, the total input cost, total income and profit and loss status are fed back to the client in real time, and a bar chart is used to display the input cost data and the income data, and a pie chart is used to display the total input cost, total income and profit and loss ratio of the period; S5. Set up different levels of early warning mechanisms under loss conditions, set different levels of early warning intervals for the loss conditions of distribution network construction, and configure different color signal lights on the client to ensure that the client receives prompt signals of the loss conditions of distribution network construction in a timely manner; S6. When the distribution network construction is in a loss, the client determines the loss level through signal lights of different colors, and then checks the input cost data during the loss period based on the bar chart, and adjusts the costs of projects with high or unreasonable input costs at the moment, to ensure effective control of the distribution network construction equipment costs.
2. A distribution network construction equipment cost analysis and control method according to claim 1, Features: The step S3 of obtaining the profit and loss status of the distribution network construction specifically includes the following steps: Record the total cost and total income of each item in the distribution network construction through Excel tables, and obtain the total cost and total income through statistical functions in Excel tables; The total input cost and total income are compared and analyzed. When the total income is greater than the total input cost, it means that the distribution network construction is currently in a profitable state, and it also means that the current equipment cost of the distribution network construction is under effective control; when the total income is equal to the total input cost, it means that the distribution network construction is currently in a slightly profitable state, and it also means that the current equipment cost of the distribution network construction is under good control; when the total income is less than the total input cost, it means that the distribution network construction is currently in a loss-making state, and it also means that the current equipment cost of the distribution network construction is in a state of control failure. Based on this, the profit and loss status of the distribution network construction is obtained.
3. A distribution network construction equipment cost analysis and control method according to claim 2, Features: The S5 sets different levels of early warning mechanisms, which specifically include the following steps: After obtaining the loss status of distribution network construction through S3, the first-level warning interval, second-level warning interval and third-level warning interval are set according to the ratio of total input cost to total income. The first-level warning interval is when the total input cost is 5%-10% higher than the total income, the second-level warning interval is when the total input cost is 3%-5% higher than the total income, and the third-level warning interval is when the total input cost is 1%-3% higher than the total income; Different color signal lights are set for the first-level warning interval, the second-level warning interval and the third-level warning interval, that is: the first-level warning interval is red, the second-level warning interval is yellow, and the third-level warning interval is blue. The profit status is set to green, and the micro-profit status is set to purple. Based on this, the cost control status of the current distribution network construction is distinguished.
4. A distribution network construction equipment cost analysis and control method according to claim 3, Features: After obtaining the profit and loss status of the distribution network construction through S3, when the distribution network construction is in a profitable state, the signal light is green; when the distribution network construction is in a slightly profitable state, the signal light is purple; when the distribution network construction is in the third-level warning interval, the signal light is blue; when the distribution network construction is in the second-level warning interval, the signal light is yellow; when the distribution network construction is in the first-level warning interval, the signal light is red.
5. A distribution network construction equipment cost analysis control system, applied to the distribution network construction equipment cost analysis control method according to any one of claims 1 to 4, It is characterized in that include: The data collection unit is used to collect various input cost data and various income data of the distribution network construction, and to determine whether the equipment cost investment of the distribution network construction is in a normal state; The data statistics unit is used to sort out and count the collected input cost data and distribution network income data according to the Excel table to obtain the total input cost and total income in the distribution network construction; The data accounting unit is used to compare and calculate the total investment cost and total income after statistics, and determine whether the current profit and loss status of the distribution network construction is proportional to the equipment investment cost; The early warning establishment unit is used to set up an early warning mechanism for the loss status of the distribution network construction, and use different levels of early warning intervals and corresponding color signal lights to remind the client of the current loss status of the distribution network construction, and promptly remedy the loss status; The client is used to receive the total input cost, total income and profit and loss status based on wireless transmission technology, and emit early warning signal lights of different colors for the loss status.
6. A distribution network construction equipment cost analysis and control system according to claim 5, It is characterized in that The data statistics unit comprises: The data cleaning module is used to delete duplicate and erroneous data in various input cost data and distribution network revenue data, and use the median value method to supplement the missing data to ensure the validity of various data; The graphics production module is used to draw bar charts of various input cost data and various distribution network revenue data, and is also used to draw pie charts of total input cost, total revenue and profit and loss status ratio.
7. A distribution network construction equipment cost analysis and control system according to claim 6, It is characterized in that Data cleaning module, including: A duplicate data extraction module, used to extract duplicate data from the various input cost data and various distribution network revenue data; The first data coefficient acquisition module is used to extract the data amount corresponding to the erroneous data appearing in the repeated data, and obtain the first data coefficient of the erroneous data corresponding to the repeated data; wherein the first data coefficient is obtained by the following formula: Among them, Q 01 represents the first data coefficient of the erroneous data corresponding to the repeated data; n represents the number of data items with erroneous data in the repeated data; ω i Represents the weight coefficient corresponding to the i-th error data; ω z Represents the comprehensive value of the weight coefficients contained in the repeated data; R c Indicates the total amount of erroneous data in the duplicate data; R z Indicates the total amount of data corresponding to the repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the duplicate data; An error data extraction module is used to extract the data volume corresponding to the error data in the non-duplicate data; The second data coefficient acquisition module is used to acquire the second data coefficient by using the data amount corresponding to the error data in the non-repetitive data; wherein the second data coefficient is acquired by the following formula: Among them, Q 02 represents the second data coefficient; m represents the number of erroneous data in the non-repeated data; ω j Represents the weight coefficient corresponding to the jth erroneous data in the non-repeated data; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data; A first early warning module, configured to issue a data quality abnormality alarm when the second data coefficient exceeds the first data coefficient; A comprehensive data coefficient acquisition module is used to obtain a comprehensive data coefficient using the first data coefficient and the second data coefficient when the second data coefficient does not exceed the first data coefficient, wherein the comprehensive data coefficient is obtained by the following formula: Among them, Q represents the comprehensive data coefficient; Q 01 The first data coefficient representing the erroneous data corresponding to the repeated data; Q 02 represents the second data coefficient; ω max Indicates the maximum weight of the erroneous data contained in the repeated data; R cmax Indicates the amount of erroneous data corresponding to the maximum weight value contained in the repeated data; ω fmax Indicates the maximum weight of the erroneous data contained in the non-repeated data; R fmax Indicates the amount of erroneous data corresponding to the maximum weight of erroneous data in non-duplicate data; The second early warning module is used to issue a data quality abnormality alarm when the comprehensive data coefficient exceeds a preset comprehensive coefficient threshold.
8. A distribution network construction equipment cost analysis and control system according to claim 5, It is characterized in that The data accounting unit includes: The status transmission module is used to provide real-time feedback of the total investment cost, total income and profit and loss status to the client based on wireless transmission technology.
9. A distribution network construction equipment cost analysis and control system according to claim 5, It is characterized in that The early warning establishment unit includes: The interval establishment module is used to establish different levels of warning intervals according to the loss status, namely the first-level warning interval, the second-level warning interval and the third-level warning interval; The light color establishment module is used to establish signal lights of different colors according to different levels of warning intervals, namely, red for the first-level warning interval, yellow for the second-level warning interval, and blue for the third-level warning interval. The profit status is set to green, and the micro-profit status is set to purple.
10. A distribution network construction equipment cost analysis and control system according to claim 9, It is characterized in that The early warning establishment unit also includes: The light color association module is used to associate and bind different levels of warning intervals with different color signal lights to ensure the effectiveness of the signal light output; The central controller is used to turn on the signal light of the corresponding color number to flash according to the received loss status.
Citation Information
Patent Citations
Big data quality standard management control method
CN108681814A
Distribution network construction equipment cost analysis control system
CN113947275A
Construction cost management and control method based on BIM and Internet of Things technology
CN114219289A
Power grid operation multi-scene monitoring analysis system and method based on mass data
CN115131169A
Big data platform monitoring method, device and equipment
CN117076968A