Automatic cement pole defect detection system and method based on machine vision

Through machine vision technology and environmental data compensation, the problem of inaccurate prediction of cement pole defects is solved, real-time monitoring and prediction of cement pole status is realized, and prediction accuracy and resource utilization efficiency are improved.

CN118887192AInactive Publication Date: 2024-11-01ZIYUN QIANGUAN POWER EQUIP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411000680.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the prior art, the defect amount of cement poles is affected by environmental factors and is difficult to quantify, resulting in inaccurate prediction of replacement time.

Method used

The cement pole defect automatic detection system based on machine vision is adopted to collect the external surface images of the pole through the drone, extract feature information, and make compensation predictions based on the historical data of the environmental protection station, and dynamically update the remaining replacement time.

Benefits of technology

Real-time monitoring and prediction of cement pole status is achieved, the accuracy and credibility of prediction are improved, and the maintenance plan is arranged reasonably, power outages and maintenance costs are avoided, and resource utilization efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118887192A_ABST
    Figure CN118887192A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of defect detection, in particular to a cement pole defect automatic detection system and method based on machine vision, and the method specifically comprises the steps: collecting daily outer surface images of a cement pole through unmanned aerial vehicle equipment; performing feature information extraction on cement color features, pole body crack features and electric pole geometric features of the preprocessed outer surface image; calculating the sinking speed of the concrete pole; synchronously extracting historical environment data of the to-be-detected concrete pole in the past one year, and compensating and predicting the actual sinking speed of the concrete pole; predicting the remaining replacement duration of the concrete pole, and dynamically updating the remaining replacement duration of the concrete pole to an electric power system maintenance department every day; the problems that in the prior art, the defect quantity of the concrete pole is difficult to quantify due to the influence of environmental factors, and the residual replacement time is inaccurate to predict are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of defect detection, and is a cement pole defect automatic detection system and method based on machine vision. Background Art

[0002] Cement poles usually refer to the supporting structure of power transmission lines made of cement mixture. It is a mixture of raw materials such as cement, sand, gravel, etc., formed by molds, and then hardened. Cement poles usually have high durability and load-bearing capacity, and are used to support the conductors, insulators and other components of power transmission lines. In fishery areas, cement poles will be affected by the salt and corrosive substances in seawater, causing surface wear, deformation or cracking. In addition, the water environment in fishery areas will increase the reflection and scattering of ultraviolet rays, making cement poles more susceptible to strong sunlight, which may lead to problems such as defects in cement poles that are difficult to quantify and replacement time is difficult to predict.

[0003] Among the existing disclosed invention technologies, the patent with application publication number CN117092115A discloses a cement pole defect detection method, including three-dimensional image acquisition and analysis of the cement pole to be detected, structural information identification and division, steel layer defect detection, concrete layer defect detection and cement pole defect assessment and control to be detected. The invention analyzes the appearance influence index of the cement pole to be detected, and conducts a combined analysis of the cracks, leakage seams and steel plate rings in the cement pole to be detected.

[0004] The above patent only considers the impact of the defects of cement poles on the performance of the poles, and ignores the difficulty in quantifying the impact of environmental factors on the defects of cement poles. Summary of the invention

[0005] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0006] The technical problem to be solved by the present invention is that in the prior art, the defect quantity of cement poles is difficult to quantify due to the influence of environmental factors, and the remaining replacement time prediction is inaccurate. A system and method for automatic detection of cement pole defects based on machine vision are proposed.

[0007] In order to achieve the above object, the technical solution of the method for automatic detection of cement pole defects based on machine vision of the present invention comprises the following steps:

[0008] S1: Use drone equipment to collect daily external surface images of cement poles and perform image preprocessing on the collected external surface images;

[0009] S2: Extract feature information from cement color features, pole crack features, and pole geometry features of the pre-processed outer surface image;

[0010] S3: Import the feature information extracted in S2 into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed;

[0011] S4: Access the database of the environmental protection station and simultaneously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data;

[0012] S5: According to the actual sinking speed of cement poles, the remaining replacement time of cement poles is predicted, and the remaining replacement time of cement poles is dynamically updated to the power system maintenance department every day.

[0013] Specifically, in S1, the image preprocessing includes: using an edge detection algorithm to identify the boundary of the cement pole, and separating the cement pole from the environmental background by using an image segmentation technology;

[0014] The feature information extraction of cement color features and shaft crack features in S2 includes the following specific steps:

[0015] S21: graying the preprocessed outer surface image of the cement pole, and grouping and compressing the gray levels in the outer surface image of the cement pole into gray intervals of different magnitudes, including N gray intervals in total;

[0016] S22: Calculate the co-occurrence matrix in the horizontal and vertical directions according to the grouped grayscale intervals. The calculation strategy of the co-occurrence matrix in the direction of θ is:

[0017] Among them, A[] is a quantity screening symbol, which indicates the number of pixel pairs under the constraint condition in the grayscale interval;

[0018] When θ=0, Represents the co-occurrence matrix in the horizontal direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, forming a pixel pair in the grayscale interval, and the constraint conditions of the pixel points are: When θ=90, Represents the co-occurrence matrix in the vertical direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, and the constraint conditions of the pixels are:

[0019] S23: Calculate the clarity XD and pixel mutation value TB of each co-occurrence matrix;

[0020] Among them, the clarity XD is used to express the cement color characteristics of the outer surface of the cement pole, and the pixel mutation value TB is used to express the crack characteristics of the cement pole body. The specific calculation steps are as follows:

[0021]

[0022]

[0023] in, is a subscript, indicating the mean of the data at 0 degree and 90 degree directions;

[0024] Represents the mean probability of occurrence of pixel pairs at 0 degrees and 90 degrees; Represents the mean of the horizontal and vertical coordinates of the pixel pairs at 0 degree and 90 degree directions respectively.

[0025] Specifically, the feature information extraction of the pole geometric features in S2 also includes: the acute angle φ formed by the cement pole base and the horizontal plane jz , the acute angle between the top of the cement pole and the cable plane φ dw And the height data H of the cement pole exposed on the foundation LU .

[0026] Specifically, in S3, the concrete pole sinking speed calculation strategy is as follows:

[0027] W=α1×YS+α2×LF+α3×JH;

[0028] Among them, W represents the sinking speed of cement poles, YS represents the sinking speed of cement color, XD n is the clarity of the nth grayscale interval of the cement pole; XD qs The starting clarity of cement used for cement poles; is the mean value of the clarity of N grayscale intervals of the cement pole;

[0029] LF is the speed from the shaft crack to the sinking. K n is the ratio of the length and width of the crack in the nth grayscale interval of the cement pole; TB n is the pixel mutation value of the nth grayscale interval of the cement pole; K cs TB is the ratio of the length to the width of the maximum crack that a cement pole can withstand without exposed steel bars; cs It is the pixel mutation value of the maximum crack that the cement pole can withstand when there is no exposed steel bar; is the mean value of pixel mutation values ​​in N grayscale intervals of cement poles;

[0030] JH is the pole geometry sinking speed,

[0031]

[0032] e and e-1 are both superscripts, representing the e-th and e-1-th cement pole defect detection days, respectively;

[0033] are the acute angles between the cement pole base and the horizontal plane on the e-th and e-1-th cement pole defect detection days respectively;

[0034] are the acute angles between the top of the cement pole and the cable plane on the e-th and e-1-th cement pole defect detection days, respectively;

[0035] The height data of cement poles exposed above the foundation on the e-th and e-1-th cement pole defect detection days respectively.

[0036] Specifically, in S4, the access to the database of the environmental protection station and the synchronous extraction of the historical environmental data of the cement pole to be detected in the past year include: in the past year, the temperature data {q1, q2, ..., q m}, the water area within the detection range of the cement pole environment {S1, S2, ..., S m}, the environmental humidity data of the cement pole environment {R1, R2, ..., R m ] and the wind speed data of the cement pole environment {f1, f2, ..., f m}, where m is a subscript, indicating the mth cement pole defect detection day in the past year.

[0037] Specifically, in S4, the specific steps of compensating and predicting the actual sinking speed of the cement pole according to the historical environmental data are as follows:

[0038] S41: Extract the historical environmental data of the cement pole to be tested in the past year to calculate the sinking factors of different environmental factors. The specific calculation strategy is as follows:

[0039] The calculation strategy of the temperature sink factor u1 caused by solar radiation is:

[0040]

[0041] The calculation strategy of wind force sink factor u2 caused by cement weathering is:

[0042]

[0043] The calculation strategy for the salt sink factor u3 caused by air salt corrosion is:

[0044]

[0045] Among them, q m ,q m-1 They are the temperature data of the mth and m-1th cement pole defect detection days in the past year;

[0046] f m , f m-1 They are the wind speed data of the mth and m-1th cement pole defect detection days in the past year;

[0047] R m , R m-1 They are the humidity data of the mth and m-1th cement pole defect detection days in the past year;

[0048] S m , S m-1 They are the water area data of the mth and m-1th cement pole defect detection days in the past year;

[0049] W m-1 , W m , W m+1 are the cement pole sinking speeds on the m-1th, mth and m+1th cement pole defect detection days in the past year;

[0050] S42: According to S41, the trap factors of different environmental factors are extracted and the environmental trap compensation factor calculation strategy is introduced to calculate the environmental trap compensation factor U as follows: U = β1×u1+β2×u2+β3×u3; β1, β2, β3 are the environmental trap compensation factor influence ratios of solar radiation, cement weathering, and air salt corrosion, respectively;

[0051] S43: extracting environmental data of the next cement pole defect detection day predicted by the meteorological bureau and the environmental protection station, and screening and matching environmental data corresponding to the environmental data of the next cement pole defect detection day in the past year;

[0052] S44: performing difference processing on the environmental data of the two groups of cement pole defect detection days, and calculating the difference mean Δ of the temperature data difference, the water area difference, the environmental humidity data difference and the wind speed data difference;

[0053] S45: The calculation formula for predicting the actual sinking speed W′ of cement poles based on historical environmental data compensation is:

[0054] Specifically, in S5, predicting the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole includes the following specific steps:

[0055] S51: extracting the predicted actual sinking speed W′ and daily cumulative defect amount G of cement poles within the next 15 days;

[0056] S52: Predict the remaining replacement time Li of cement poles,

[0057] Among them, G yz It is the defect threshold for cement pole performance failure.

[0058] In addition, the automatic detection system for cement pole defects based on machine vision of the present invention includes the following modules:

[0059] External surface image acquisition module, visual feature information extraction module, cement pole to sink speed calculation module, environmental compensation module, and remaining replacement time assessment module;

[0060] The outer surface image acquisition module uses drone equipment to collect outer surface images of cement poles every day, and performs image preprocessing on the collected outer surface images;

[0061] The visual feature information extraction module is used to extract visual feature information from the color features, crack features and geometric features of the pre-processed outer surface image;

[0062] The cement pole to trap speed calculation module is used to import the extracted feature information into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed;

[0063] The environmental compensation module is used to access the database of the environmental protection station and synchronously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data;

[0064] The remaining replacement time evaluation module is used to predict the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole, and dynamically update the remaining replacement time of the cement pole to the power system maintenance department every day.

[0065] A storage medium stores instructions, and when a computer reads the instructions, the computer executes the automatic detection method for cement pole defects based on machine vision.

[0066] An electronic device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned automatic detection method of cement pole defects based on machine vision when executing the computer program.

[0067] Compared with the prior art, the technical effects of the present invention are as follows:

[0068] 1. The present invention collects outer surface images and extracts feature information daily through UAV equipment, which can realize real-time monitoring and prediction of the status of cement poles, help to find problems in time and take corresponding maintenance or replacement measures.

[0069] 2. The present invention takes into account that cement poles in fishery areas may be affected by the salt and corrosive substances in seawater, causing surface wear, deformation or cracking. By accessing the database of the environmental protection station and combining historical environmental data to compensate for the sinking speed of the cement poles, the accuracy and credibility of the prediction are improved in combination with the specific environment in which the cement poles are located.

[0070] 3. The present invention can reasonably arrange maintenance plans by predicting the remaining replacement time of cement poles and timely updating the information to the power system maintenance department, thus avoiding unnecessary power outages and maintenance costs caused by pole damage and improving resource utilization efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0071] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative labor.

[0072] in:

[0073] Figure 1 It is a flow chart of the automatic detection method of cement pole defects based on machine vision of the present invention;

[0074] Figure 2 It is a structural schematic diagram of the automatic cement pole defect detection system based on machine vision of the present invention. DETAILED DESCRIPTION

[0075] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0076] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0077] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0078] Embodiment 1:

[0079] like Figure 1 As shown, the automatic detection of cement pole defects based on machine vision in an embodiment of the present invention is as follows: Figure 1 As shown, the specific steps are as follows:

[0080] S1: Use drone equipment to collect daily external surface images of cement poles and perform image preprocessing on the collected external surface images;

[0081] In S1, the image preprocessing includes: using an edge detection algorithm to identify the boundary of the cement pole, and separating the cement pole from the environmental background by using an image segmentation technology;

[0082] The feature information extraction of cement color features and shaft crack features in S2 includes the following specific steps:

[0083] S21: graying the preprocessed outer surface image of the cement pole, and grouping and compressing the gray levels in the outer surface image of the cement pole into gray intervals of different magnitudes, including N gray intervals in total;

[0084] Exemplarily, in this embodiment, there are 20 grayscale intervals in total.

[0085] S22: Calculate the co-occurrence matrix in the horizontal and vertical directions according to the grouped grayscale intervals. The calculation strategy of the co-occurrence matrix in the direction of θ is:

[0086] Among them, A[] is a quantity screening symbol, which indicates the number of pixel pairs under the constraint condition in the grayscale interval;

[0087] When θ=0, Represents the co-occurrence matrix in the horizontal direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, forming a pixel pair in the grayscale interval, and the constraint conditions of the pixel points are: When θ=90, Represents the co-occurrence matrix in the vertical direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, and the constraint conditions of the pixels are:

[0088] S23: Calculate the clarity XD and pixel mutation value TB of each co-occurrence matrix;

[0089] Among them, the clarity XD is used to express the cement color characteristics of the outer surface of the cement pole, and the pixel mutation value TB is used to express the crack characteristics of the cement pole body. The specific calculation steps are as follows:

[0090]

[0091] in, is a subscript, indicating the mean of the data at 0 degree and 90 degree directions;

[0092] Represents the mean probability of occurrence of pixel pairs at 0 degrees and 90 degrees;

[0093] Represents the mean of the horizontal and vertical coordinates of the pixel pairs at 0 degree and 90 degree directions respectively.

[0094] S2: Extract feature information from cement color features, pole crack features, and pole geometry features of the pre-processed outer surface image;

[0095] The feature information extraction of the pole geometric features in S2 also includes: the acute angle φ formed by the cement pole base and the horizontal plane jz , the acute angle between the top of the cement pole and the cable plane φ dw And the height data H of the cement pole exposed on the foundation LU .

[0096] S3: Import the feature information extracted in S2 into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed;

[0097] In S3, the concrete pole sinking speed calculation strategy is as follows:

[0098] W=α1×YS+α2×LF+α3×JH;

[0099] Among them, W represents the sinking speed of cement poles, YS represents the sinking speed of cement color, XD n is the clarity of the nth grayscale interval of the cement pole; XD qs The starting clarity of cement used for cement poles; is the mean value of the clarity of N grayscale intervals of the cement pole;

[0100] LF is the speed from the shaft crack to the sinking. K n is the ratio of the length and width of the crack in the nth grayscale interval of the cement pole; TB n is the pixel mutation value of the nth grayscale interval of the cement pole; K cs TB is the ratio of the length to the width of the maximum crack that a cement pole can withstand without exposed steel bars; cs It is the pixel mutation value of the maximum crack that the cement pole can withstand when there is no exposed steel bar; is the mean value of pixel mutation values ​​in N grayscale intervals of cement poles;

[0101] JH is the pole geometry sinking speed,

[0102]

[0103] e and e-1 are both superscripts, representing the e-th and e-1-th cement pole defect detection days, respectively;

[0104] are the acute angles between the cement pole base and the horizontal plane on the e-th and e-1-th cement pole defect detection days respectively;

[0105] are the acute angles between the top of the cement pole and the cable plane on the e-th and e-1-th cement pole defect detection days, respectively;

[0106] The height data of cement poles exposed above the foundation on the e-th and e-1-th cement pole defect detection days respectively.

[0107] S4: Access the database of the environmental protection station and simultaneously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data;

[0108] In S4, the access to the database of the environmental protection station and the synchronous extraction of the historical environmental data of the cement pole to be tested in the past year include: the temperature data {q1, q2, ..., q m}, the water area within the detection range of the cement pole environment {S1, S2, ..., S m}, the environmental humidity data of the cement pole environment {R1, R2, ..., R m} and the wind speed data of the cement pole environment {f1, f2, ..., f m}, where m is a subscript, indicating the mth cement pole defect detection day in the past year.

[0109] In S4, the specific steps of compensating and predicting the actual sinking speed of the cement pole according to the historical environmental data are as follows:

[0110] S41: Extract the historical environmental data of the cement pole to be tested in the past year to calculate the sinking factors of different environmental factors. The specific calculation strategy is as follows:

[0111] The calculation strategy of the temperature sink factor u1 caused by solar radiation is:

[0112]

[0113] The calculation strategy of wind force sink factor u2 caused by cement weathering is:

[0114]

[0115] The calculation strategy for the salt sink factor u3 caused by air salt corrosion is:

[0116]

[0117] Among them, q m ,q m-1 They are the temperature data of the mth and m-1th cement pole defect detection days in the past year;

[0118] f m , f m-1 They are the wind speed data of the mth and m-1th cement pole defect detection days in the past year;

[0119] R m , R m-1 They are the humidity data of the mth and m-1th cement pole defect detection days in the past year;

[0120] S m , S m-1 They are the water area data of the mth and m-1th cement pole defect detection days in the past year;

[0121] W m-1 , W m , W m+1 are the cement pole sinking speeds on the m-1th, mth and m+1th cement pole defect detection days in the past year;

[0122] S42: According to S41, the trap factors of different environmental factors are extracted and the environmental trap compensation factor calculation strategy is introduced to calculate the environmental trap compensation factor U as follows: U = β1×u1+β2×u2+β3×u3; β1, β2, β3 are the environmental trap compensation factor influence ratios of solar radiation, cement weathering, and air salt corrosion, respectively;

[0123] S43: extracting environmental data of the next cement pole defect detection day predicted by the meteorological bureau and the environmental protection station, and screening and matching environmental data corresponding to the environmental data of the next cement pole defect detection day in the past year;

[0124] S44: performing difference processing on the environmental data of the two groups of cement pole defect detection days, and calculating the difference mean Δ of the temperature data difference, the water area difference, the environmental humidity data difference and the wind speed data difference;

[0125] S45: The calculation formula for predicting the actual sinking speed W′ of cement poles based on historical environmental data compensation is:

[0126] S5: According to the actual sinking speed of cement poles, the remaining replacement time of cement poles is predicted, and the remaining replacement time of cement poles is dynamically updated to the power system maintenance department every day.

[0127] In S5, predicting the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole includes the following specific steps:

[0128] S51: extracting the predicted actual sinking speed W′ and daily cumulative defect amount G of cement poles within the next 15 days;

[0129] S52: Predict the remaining replacement time Li of cement poles,

[0130] Among them, G yz It is the defect threshold for cement pole performance failure.

[0131] Embodiment 2:

[0132] like Figure 2 As shown, the automatic detection system for cement pole defects based on machine vision in the embodiment of the present invention is as follows: Figure 2 As shown, it includes the following modules:

[0133] External surface image acquisition module, visual feature information extraction module, cement pole to sink speed calculation module, environmental compensation module, and remaining replacement time assessment module;

[0134] The outer surface image acquisition module uses drone equipment to collect outer surface images of cement poles every day, and performs image preprocessing on the collected outer surface images;

[0135] The visual feature information extraction module is used to extract visual feature information from the color features, crack features and geometric features of the pre-processed outer surface image;

[0136] The cement pole to trap speed calculation module is used to import the extracted feature information into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed;

[0137] The environmental compensation module is used to access the database of the environmental protection station and synchronously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data;

[0138] The remaining replacement time evaluation module is used to predict the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole, and dynamically update the remaining replacement time of the cement pole to the power system maintenance department every day.

[0139] Embodiment three:

[0140] This embodiment provides an electronic device, including: a processor and a memory, wherein the memory stores a computer program that can be called by the processor;

[0141] The processor executes the above-mentioned automatic cement pole defect detection method based on machine vision by calling the computer program stored in the memory.

[0142] The electronic device may have relatively large differences due to different configurations or performances, and may include one or more processors (Central Processing Units, CPU) and one or more memories, wherein the memory stores at least one computer program, and the computer program is loaded and executed by the processor to implement the automatic detection method of cement pole defects based on machine vision provided by the above method embodiment. The electronic device may also include other components for realizing the functions of the device. For example, the electronic device may also have components such as a wired or wireless network interface and an input and output interface to input and output data. This embodiment will not be described in detail here.

[0143] Embodiment 4:

[0144] This embodiment provides a computer-readable storage medium having a rewritable computer program stored thereon;

[0145] When the computer program runs on a computer device, the computer device executes the above-mentioned automatic cement pole defect detection method based on machine vision.

[0146] For example, the computer readable storage medium can be a read-only memory (ROM), a random access memory (RAM), a compact disc (CD-ROM), a magnetic tape, a floppy disk, and an optical data storage device, etc.

[0147] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0148] It should be understood that determining B based on A does not mean determining B only based on A. B can also be determined based on A and / or other information.

[0149] The above embodiments can be implemented in whole or in part by software, hardware, firmware or any other combination. When implemented by software, the above embodiments can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions or computer programs. When a computer instruction or computer program is loaded or executed on a computer, a process or function according to an embodiment of the present invention is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. Computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, computer instructions can be transmitted from one website site, computer, server or data center to another website site, computer, server or data center through a wired network or / and a wireless network. The computer-readable storage medium can be any available medium that a computer can access or a data storage device such as a server or data center that contains one or more available media sets. The available medium can be a magnetic medium (for example, a floppy disk, a hard disk, a tape), an optical medium (for example, a DVD), or a semiconductor medium. The semiconductor medium can be a solid-state hard disk.

[0150] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed in the present invention can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0151] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0152] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic, for example, the division of units is only one, and there may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0153] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0154] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0155] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0156] In summary, compared with the prior art, the technical effects of the present invention are as follows:

[0157] 1. The present invention collects outer surface images and extracts feature information daily through UAV equipment, which can realize real-time monitoring and prediction of the status of cement poles, help to find problems in time and take corresponding maintenance or replacement measures.

[0158] 2. The present invention takes into account that cement poles in fishery areas may be affected by the salt and corrosive substances in seawater, causing surface wear, deformation or cracking. By accessing the database of the environmental protection station and combining historical environmental data to compensate for the sinking speed of the cement poles, the accuracy and credibility of the prediction are improved in combination with the specific environment in which the cement poles are located.

[0159] 3. The present invention can reasonably arrange maintenance plans by predicting the remaining replacement time of cement poles and timely updating the information to the power system maintenance department, thus avoiding unnecessary power outages and maintenance costs caused by pole damage and improving resource utilization efficiency.

[0160] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. The automatic detection method of cement pole defects based on machine vision is characterized by: The method comprises the following specific steps: S1: Use drone equipment to collect daily external surface images of cement poles and perform image preprocessing on the collected external surface images; S2: Extract feature information from cement color features, pole crack features, and pole geometry features of the pre-processed outer surface image; S3: Import the feature information extracted in S2 into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed; S4: Access the database of the environmental protection station and simultaneously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data; S5: According to the actual sinking speed of cement poles, the remaining replacement time of cement poles is predicted, and the remaining replacement time of cement poles is dynamically updated to the power system maintenance department every day.

2. The method for automatic detection of cement pole defects based on machine vision according to claim 1 is characterized in that: In S1, the image preprocessing includes: using an edge detection algorithm to identify the boundary of the cement pole, and separating the cement pole from the environmental background by using an image segmentation technology; The feature information extraction of cement color features and shaft crack features in S2 includes the following specific steps: S21: graying the preprocessed outer surface image of the cement pole, and grouping and compressing the gray levels in the outer surface image of the cement pole into gray intervals of different magnitudes, including N gray intervals in total; S22: Calculate the co-occurrence matrix in the horizontal and vertical directions according to the grouped grayscale intervals. The calculation strategy of the co-occurrence matrix in the direction of θ is: Among them, A[] is a quantity screening symbol, which indicates the number of pixel pairs under the constraint condition in the grayscale interval; When θ=0, Represents the co-occurrence matrix in the horizontal direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, forming a pixel pair in the grayscale interval, and the constraint conditions of the pixel points are: When θ=90, Represents the co-occurrence matrix in the vertical direction, (x1, y1), (x2, y2) are two pixels with a distance of L in the grayscale interval, and the constraint conditions of the pixels are: S23: Calculate the clarity XD and pixel mutation value TB of each co-occurrence matrix; Among them, the clarity XD is used to express the cement color characteristics of the outer surface of the cement pole, and the pixel mutation value TB is used to express the crack characteristics of the cement pole body. The specific calculation steps are as follows: in, is a subscript, indicating the mean of the data at 0 degree and 90 degree directions; Represents the mean probability of occurrence of pixel pairs at 0 degrees and 90 degrees; Represents the mean of the horizontal and vertical coordinates of the pixel pairs at 0 degree and 90 degree directions respectively.

3. The method for automatic detection of cement pole defects based on machine vision according to claim 2 is characterized in that: The feature information extraction of the pole geometric features in S2 also includes: the acute angle φ formed by the cement pole base and the horizontal plane jz , the acute angle between the top of the cement pole and the cable plane φ dw And the height data H of the cement pole exposed on the foundation LU .

4. The method for automatic detection of cement pole defects based on machine vision according to claim 3 is characterized in that: In S3, the concrete pole sinking speed calculation strategy is as follows: W=α1×YS+α2×LF+α3×JH; Among them, W represents the sinking speed of cement poles, YS represents the sinking speed of cement color, XD n is the clarity of the nth grayscale interval of the cement pole; XD qs The starting clarity of cement used for cement poles; is the mean value of the clarity of N grayscale intervals of the cement pole; L is the speed from the crack to the sinking of the shaft. K n is the ratio of the length and width of the crack in the nth grayscale interval of the cement pole; TB n is the pixel mutation value of the nth grayscale interval of the cement pole; K cs TB is the ratio of the length to the width of the maximum crack that a cement pole can withstand without exposed steel bars; cs It is the pixel mutation value of the maximum crack that the cement pole can withstand when there is no exposed steel bar; is the mean value of pixel mutation values ​​in N grayscale intervals of cement poles; JH is the pole geometry sinking speed, e and e-1 are both superscripts, representing the e-th and e-1-th cement pole defect detection days, respectively; are the acute angles between the cement pole base and the horizontal plane on the e-th and e-1-th cement pole defect detection days respectively; are the acute angles between the top of the cement pole and the cable plane on the e-th and e-1-th cement pole defect detection days, respectively; The height data of cement poles exposed above the foundation on the e-th and e-1-th cement pole defect detection days respectively.

5. The method for automatic detection of cement pole defects based on machine vision according to claim 4 is characterized in that: In S4, the access to the database of the environmental protection station and the synchronous extraction of the historical environmental data of the cement pole to be tested in the past year include: the temperature data {q1, q2, ..., q m }, the water area within the detection range of the cement pole environment {S1, S2, ..., S m }, the environmental humidity data of the cement pole environment {R1, R2, ..., R m } and the wind speed data of the cement pole environment {f1, f2, ..., f n }, where m is a subscript, indicating the mth cement pole defect detection day in the past year.

6. The method for automatic detection of cement pole defects based on machine vision according to claim 5 is characterized in that: In S4, the specific steps of compensating and predicting the actual sinking speed of the cement pole according to the historical environmental data are as follows: S41: Extract the historical environmental data of the cement pole to be tested in the past year to calculate the sinking factors of different environmental factors. The specific calculation strategy is as follows: The calculation strategy of the temperature sink factor u1 caused by solar radiation is: The calculation strategy of wind force sink factor u2 caused by cement weathering is: The calculation strategy for the salt sink factor u3 caused by air salt corrosion is: Among them, q m ,q m -1 refers to the temperature data of the mth and m-1th cement pole defect detection days in the past year; f m , f m-1 They are the wind speed data of the mth and m-1th cement pole defect detection days in the past year; R m , R m-1 They are the humidity data of the mth and m-1th cement pole defect detection days in the past year; S m , S m-1 They are the water area data of the mth and m-1th cement pole defect detection days in the past year; W m-1 , W m , W m+1 are the cement pole sinking speeds on the m-1th, mth and m+1th cement pole defect detection days in the past year; S42: According to S41, the trap factors of different environmental factors are extracted and the environmental trap compensation factor calculation strategy is introduced to calculate the environmental trap compensation factor U as follows: U = β1×u1+β2×u2+β3×u3; β1, β2, β3 are the environmental trap compensation factor influence ratios of solar radiation, cement weathering, and air salt corrosion, respectively; S43: extracting environmental data of the next cement pole defect detection day predicted by the meteorological bureau and the environmental protection station, and screening and matching environmental data corresponding to the environmental data of the next cement pole defect detection day in the past year; S44: performing difference processing on the environmental data of the two groups of cement pole defect detection days, and calculating the difference mean Δ of the temperature data difference, the water area difference, the environmental humidity data difference and the wind speed data difference; S45: The calculation formula for predicting the actual sinking speed W′ of cement poles based on historical environmental data compensation is:

7. The method for automatic detection of cement pole defects based on machine vision according to claim 6 is characterized in that: In S5, predicting the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole includes the following specific steps: S51: extracting the predicted actual sinking speed W′ and daily cumulative defect amount G of cement poles within the next 15 days; S52: Predict the remaining replacement time Li of cement poles, Among them, G yz It is the defect threshold for cement pole performance failure.

8. A cement pole defect automatic detection system based on machine vision, which is used to implement the cement pole defect automatic detection method based on machine vision as described in any one of claims 1 to 7, characterized in that: The system includes the following modules: External surface image acquisition module, visual feature information extraction module, cement pole to sink speed calculation module, environmental compensation module, and remaining replacement time assessment module; The outer surface image acquisition module uses drone equipment to collect outer surface images of cement poles every day, and performs image preprocessing on the collected outer surface images; The visual feature information extraction module is used to extract visual feature information from the color features, crack features and geometric features of the pre-processed outer surface image; The cement pole to trap speed calculation module is used to import the extracted feature information into the cement pole to trap speed calculation strategy to calculate the cement pole to trap speed; The environmental compensation module is used to access the database of the environmental protection station and synchronously extract the historical environmental data of the cement pole to be tested in the past year, and compensate and predict the actual sinking speed of the cement pole based on the historical environmental data; The remaining replacement time evaluation module is used to predict the remaining replacement time of the cement pole according to the actual sinking speed of the cement pole, and dynamically update the remaining replacement time of the cement pole to the power system maintenance department every day.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method for automatically detecting cement pole defects based on machine vision as described in any one of claims 1 to 7 is implemented.

10. An electronic device, characterized in that: include: A memory for storing instructions; A processor is used to execute the instructions so that the device performs operations to implement the method for automatic detection of cement pole defects based on machine vision as described in any one of claims 1-7.

Citation Information

Cited By

  • A machine vision-based system and method for detecting surface defects in cement poles