Construction process of underground drainage system under high fill

Through detailed construction steps and precautions, the problem of lack of specific content in the existing high-fill bottom drainage system construction method is solved, and a low-cost, low-carbon and environmentally friendly high-fill bottom underground drainage system construction technology is provided, including the main The construction of blind grooves, sub-blind grooves and branch blind grooves has improved the standardization and efficiency of construction.

CN118932979APending Publication Date: 2024-11-12CHINA RAILWAY BEIJING ENG GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411036941.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing construction methods of high-fill bottom drainage system do not specify the specific construction steps and precautions, which makes it difficult for technicians to understand the detailed construction process.

Method used

Provides a construction process for underground drainage system under high fill, including detailed construction steps of main blind trenches, secondary blind trenches and branch blind trenches, including excavation of trenches, laying geotextiles, filling gravel, pouring concrete, and setting up sedimentation trenches. , laying drain pipes and gabions, and using paving devices to pave gravel cushions.

Benefits of technology

It realizes the detailed and standardized construction, reduces the difficulty and cost of construction, has the advantages of low carbon and environmental protection, and has more advantages than traditional reinforced concrete structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932979A_ABST
    Figure CN118932979A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of drainage system construction, and discloses a construction process of an underground drainage system under a high fill, which comprises the construction of a main blind ditch, a secondary blind ditch and a branch blind ditch, and the same construction procedures of the main blind ditch, the secondary blind ditch and the branch blind ditch comprise ditch excavation, ditch bottom leveling, ditch drainage, drainage and drainage. After the bearing capacity of the dug ditch is detected to be qualified, geotextile is laid, and gravel is filled; the construction procedure of the secondary blind ditches and the branch blind ditches further comprises the step of laying plastic blind ditches after the geotechnical cloth is laid, the construction of the secondary blind ditches further comprises the step of paving broken stone hardcore layers before the plastic blind ditches are laid and paving inverted filter layers and water-permeable geotechnical cloth after the broken stones are filled, and precipitation tanks are arranged at the intersections of the branch blind ditches and the main blind ditches; the construction process of the main blind ditch further comprises the steps that before the geotechnical cloth is laid, a concrete cushion layer and a reinforced concrete bottom plate are sequentially poured in the ditch, a masonry ditch wall is constructed, after the geotechnical cloth is laid, a broken stone cushion layer is laid, an HMMP drainage pipe is laid, and finally a coarse-grained stone drainage body is constructed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of drainage system construction, in particular to a construction process of an underground drainage system under high fill. Background Art

[0002] Chinese patent CN114293534 A discloses a high fill bottom drainage system and construction method, including setting main blind ditches, secondary blind ditches and branch blind ditches according to surface catchment area and flow rate, setting main blind ditches along main gullies in gullies and low-lying ditches with large catchment area and flow rate, setting secondary blind ditches in small gullies or low-lying ditches, and setting branch blind ditches for springs and seepage at exposed places in combination with site topography; also including spring eye drainage structure and horizontal drainage layer structure, the spring eye drainage structure sets spring eye blind ditches to connect the main blind ditch according to spring eye grouping, the horizontal drainage layer structure is set in the gravel pile or strong compaction replacement treatment area, the horizontal drainage layer is connected to the blind ditch drainage network on the original foundation surface; a number of groundwater level monitoring pumping wells are set at the connection between the main blind ditch and the secondary blind ditch and at the downstream of the main blind ditch; the high fill bottom drainage system of the present invention can effectively meet the drainage demand when the groundwater recharge source is abundant in the high fill site, and the drainage monitoring can also achieve the expected effect.

[0003] The above patent discloses a construction method for a high fill bottom drainage system, but simply discloses eight steps of the construction method, making it impossible for those skilled in the art to understand the specific content and precautions of each construction step. Summary of the invention

[0004] To achieve the above-mentioned purpose, the present invention discloses a construction process of underground drainage system under high fill, including the construction of main blind ditch, secondary blind ditch and branch blind ditch. The same construction process of the main blind ditch, secondary blind ditch and branch blind ditch includes digging ditch, leveling ditch bottom, carrying out bearing capacity test on the excavated ditch and passing it, laying geotextile and filling with gravel;

[0005] Among them, the construction process of the secondary blind ditch and the branch blind ditch also includes the laying of the plastic blind ditch after the laying of the geotextile. The construction of the secondary blind ditch also includes the laying of the crushed stone cushion before the laying of the plastic blind ditch and the laying of the filter layer and the permeable geotextile after filling the crushed stone. A sedimentation tank is set at the intersection of the branch blind ditch and the main blind ditch.

[0006] The construction process of the main blind ditch also includes pouring a 200mm thick C20 concrete cushion layer and an 800mm thick C25 reinforced concrete bottom plate in the ditch before laying the geotextile, constructing the mortar-laid stone ditch wall and spreading the gravel cushion layer after laying the geotextile, laying the HMMP drainage pipe, and then laying the wire mesh gabion and plastic blind ditch, and laying the filter layer and permeable geotextile after filling the gravel, and finally constructing the coarse-grained stone drainage body.

[0007] Preferably, the length of the sedimentation tank is 4.5m, the width is the same as the branch blind ditch, and the depth is 0.5m. When the base of the sedimentation tank is soil, the sedimentation tank is wrapped with a composite geomembrane on all sides, and the overlap length of the composite geomembrane and the blind ditch non-woven geotextile is not less than 300mm. When the base of the sedimentation tank is bedrock, the sedimentation tank is wrapped with a non-woven geotextile on all sides, and the sedimentation tank is filled with 15 to 30cm of gravel.

[0008] Preferably, the geotextile is manually laid into the ditch, and the geotextile is placed upright on the ditch walls on both sides of the masonry. After the geotextile is laid, it is leveled and fixed with stones. The ditch surface position close to the ditch is reserved with a geotextile curling edge and wrapped with crushed stone filler. The overlap length of the geotextile along the longitudinal direction of the ditch is not less than 80cm, and the overlap length when wrapping the crushed stone is not less than 30cm. Two layers of crushed stone are laid on the laid geotextile. The first layer uses 3-7cm crushed stone backfilled with 40cm, and the second layer uses 2-5cm crushed stone backfilled with 50cm.

[0009] Preferably, a handheld electric drill is used to drill a water-permeable pipe in the HMPP drainage pipe, with a hole diameter of 20 mm, a longitudinal spacing of 80 mm, and a lateral spacing of 120° between two water-permeable holes. The water-permeable holes are arranged between the double ribs of the HMPP drainage pipe and should not be arranged on the ribs of the drainage pipe. After the water-permeable holes are arranged, the HMPP drainage pipe is wrapped with a geotextile, and the seams of the geotextile are overlapped by 100 mm. Then, the centerline position of the pipeline is determined, and the HMPP drainage pipe is installed.

[0010] Preferably, the wire gabions are assembled on site, and a single 2.0 mm galvanized wire is wound into two strands, and the two main frame wires are tied from the top corner end, and then tied every 100-150 mm downward until the bottom corner end. A total of three wire gabions are set in the middle and on both sides of the blind ditch, and the assembled wire gabions are manually transported to the construction work surface. The wire gabions are put in place in sequence according to the position lines of each row of wire gabions. The frames of adjacent wire gabions are wound into two strands with a single 2 mm galvanized wire and connected in sequence every 150 mm starting from the corner end. The surface net is connected every 150 mm in the vertical and horizontal directions. 15-30 cm blocks of stone are filled in the wire gabions, and 5 plastic blind ditches are laid above each of the two HMPP drainage pipes, and they are fixed to the bottom with iron nails every 5 m. The plastic blind ditches are connected with iron wire.

[0011] Preferably, crushed stone with a particle size of 2 to 5 cm is first filled in manually with an excavator, and then crushed stone with a particle size of 3 to 7 cm is used to backfill 90 cm. A 5m wide geogrid is laid every 20 cm on the bottom of the crushed stone, with a width of 5 m and a total of three layers. The top of the main blind ditch is backfilled with 20 cm of 2 to 5 cm crushed stone as a filter layer. The overlap length of the permeable geotextile along the longitudinal direction of the ditch is not less than 80 cm, and the overlap length when wrapping the crushed stone is not less than 30 cm.

[0012] Preferably, the coarse-grained stone drainage body consists of an upper filter layer, a lower filter layer and a coarse-grained stone filling body in the middle. The upper filter layer and the lower filter layer are both composed of a layer of 400g / ㎡ non-woven geotextile and three layers of 30cm thick filler filter layers. The particle sizes of the three 30cm thick filler filter layers are 0.3mm~2.0mm, 2.0mm~10.0mm and 20mm~40mm respectively. The filler of the coarse-grained stone filling body adopts continuously graded medium-weathered carbonate with a maximum particle size of 300mm, the content of particles less than 5mm does not exceed 20%, the content of particles less than 0.075mm does not exceed 5%, and the porosity is 16~20%.

[0013] Preferably, the gravel cushion layer is paved by a paving device, and the paving device comprises:

[0014] Walking seat;

[0015] The paving roller group is located at the front end of the traveling direction of the traveling seat. The paving roller group includes a posture adjustment frame and a center roller group, a left roller group and a right roller group installed on the posture adjustment frame. The left roller group and the right roller group are symmetrically located on both sides of the center roller group, and the low ends of the left roller group and the right roller group are both arranged close to the center roller group. The middle roller group is half-distributed with spiral winches with opposite rotation directions, and the left roller group and the right roller group are also distributed with spiral winches with opposite rotation directions.

[0016] Preferably, the posture adjustment frame includes: a fixed frame installed at the front end of the walking direction of the walking seat, a bow-shaped rotating frame rotatably installed on the fixed frame, an electric telescopic rod installed on the bottom of the bow-shaped rotating frame, an intermediate roller group rotatably installed on the bow-shaped rotating frame, an inner support frame installed on two side ends of the bow-shaped rotating frame, a middle part of the balancing frame installed on the inner support frame through a mounting shaft, a left roller group installed on one end of an L-shaped connecting frame one, and the other end of the L-shaped connecting frame one is set on one of the side ends of the bow-shaped rotating frame through a slider, a right roller group installed on one end of an L-shaped connecting frame two, and the other end of the L-shaped connecting frame two is set on the other side end of the bow-shaped rotating frame through a slider two, two ends of the balancing frame are respectively clamped on the L-shaped connecting frame one and the L-shaped connecting frame two, and the telescopic end of the electric telescopic rod is connected to the slider two through a supporting cross bar.

[0017] Preferably, the posture adjustment frame further comprises:

[0018] A central gear, which is mounted on the fixed frame through a central shaft and away from the end of the bow-shaped rotating frame, and the bow-shaped rotating frame is mounted on the central rotating shaft;

[0019] A sector gear, which is mounted on the fixed frame away from the end of the bow-shaped rotating frame and meshes with the central gear;

[0020] A driving bevel groove is provided on the fixed frame, a strip groove is provided on the sector gear, a straight line where the strip groove is located points to the rotating end of the sector gear, a limit slide rod is slidably connected in the driving bevel groove and the strip groove, the limit slide rod is connected to the connecting rod through a universal joint, and the connecting rod is connected to the horizontal section of the L-shaped connecting frame through a spherical mounting head. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 It is a work flow chart of the present invention;

[0023] Figure 2 It is a schematic diagram of the structure of the paving device of the present invention;

[0024] Figure 3 It is a schematic diagram of the installation of the inner support frame and the balance frame of the present invention;

[0025] Figure 4 It is a schematic diagram of installing the center roller group of the present invention on the bow-shaped rotating frame;

[0026] Figure 5 It is a schematic diagram of the connection between the limit sliding rod and the connecting rod of the present invention;

[0027] Figure 6 It is a schematic diagram of the cooperation between the central gear and the sector gear of the present invention.

[0028] In the figure: 10. L-shaped connecting frame 1; 11. posture adjustment frame; 12. center roller group; 13. left roller group; 14. right roller group; 15. fixed frame; 16. bow-shaped rotating frame; 17. electric telescopic rod; 18. inner support frame; 19. balance frame; 21. slider 1; 22. L-shaped connecting frame 2; 23. slider 2; 24. support cross bar; 25. center gear; 26. sector gear; 27. driving inclined slot; 28. strip slot; 29. ​​limit slide bar; 30. universal joint; 31. connecting rod. DETAILED DESCRIPTION

[0029] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] Example

[0031] The present invention will be further described below in conjunction with the accompanying drawings.

[0032] like Figure 1 As shown, the present embodiment provides a construction process of an underground drainage system under high fill, including the construction of a main blind ditch, a secondary blind ditch and a branch blind ditch. The same construction process of the main blind ditch, the secondary blind ditch and the branch blind ditch includes digging the ditch, leveling the bottom of the ditch, and after the bearing capacity of the excavated ditch is tested to be qualified, laying geotextiles and filling gravel;

[0033] Among them, the construction process of the secondary blind ditch and the branch blind ditch also includes the laying of the plastic blind ditch after the laying of the geotextile. The construction of the secondary blind ditch also includes the laying of the crushed stone cushion before the laying of the plastic blind ditch and the laying of the filter layer and the permeable geotextile after filling the crushed stone. A sedimentation tank is set at the intersection of the branch blind ditch and the main blind ditch.

[0034] The construction process of the main blind ditch also includes pouring a 200mm thick C20 concrete cushion layer and an 800mm thick C25 reinforced concrete bottom plate in the ditch before laying the geotextile, constructing the mortar-laid stone ditch wall and spreading the gravel cushion layer after laying the geotextile, laying the HMMP drainage pipe, and then laying the wire mesh gabion and plastic blind ditch, and laying the filter layer and permeable geotextile after filling the gravel, and finally constructing the coarse-grained stone drainage body.

[0035] The working principle and beneficial effects of the above technical solution are:

[0036] The invention provides a construction process for an underground drainage system under high fill, which specifically discloses the construction contents and precautions of a main blind ditch, a secondary blind ditch and a branch blind ditch. Compared with traditional drainage blind ditches which usually adopt reinforced concrete structures, increase the structural cross-sectional dimensions, reduce the spacing between steel bars and other measures to resist the pressure of upper structures, have the defects of great construction difficulty, high cost and disadvantageous to environmental protection, the invention has the advantages of simple construction, low cost and low carbon and environmental protection.

[0037] In addition, the key points of the operation of the 200mm thick C20 concrete cushion and the 800mm thick C25 reinforced concrete base plate include pouring the 200mm thick C20 concrete cushion first, and then pouring the 800mm thick C25 reinforced concrete base plate. Before pouring the plain concrete cushion, the formwork should be supported, the piles should be driven and the wires should be pulled to control the flatness, elevation, thickness, width, longitudinal slope, etc. of the concrete after pouring to meet the design requirements. After the concrete cushion is finally set, the measurement and laying out of the lines and the installation and binding of the steel bars are started. After the steel bars are tied, the formwork is installed. After the formwork is installed and the diameter is qualified after the self-inspection, an application for hidden acceptance is submitted to the supervision agency. After the hidden acceptance is qualified, the concrete is poured. After the base plate is completed, the construction of the mortar-laid stone trench wall begins. The trench wall material is 7.5 mortar-laid block stone, and water-permeable holes are set to ensure smooth drainage. The diameter of the water-permeable holes is 100mm, the spacing is 2.0m, and the plum blossom pattern is arranged.

[0038] The key points of trench excavation include:

[0039] (1) After surveying and laying out, start trenching. The depth of trenching is controlled by surveyors testing the elevation. The construction is mainly carried out by machinery (excavator) and supplemented by manual labor. Waterproofing and drainage measures should be taken at the same time when trenching to prevent the bottom of the trench from being soaked by water. The exposure time of the trench should be shortened. If the next process cannot be carried out immediately after trenching, a depth of 10 to 30 cm should be left unexcavated, and the trench should be repaired to the designed trench bottom elevation before the next process is constructed, and then manually excavated. It is strictly forbidden to disturb the trench bottom. If over-excavation occurs, backfilling should be carried out according to the design requirements. After the trench excavation reaches the designed depth, the trench bottom is compacted by a frog-type rammer in combination with manual labor.

[0040] (2) During the trenching process, the stability of the trench side should be checked. If deformation or cracks are found, the construction must be stopped immediately and handled. After the trench is dug, the trench cross-sectional dimensions and the longitudinal slope of the trench bottom should be tested.

[0041] In one embodiment, the length of the sedimentation tank is 4.5m, the width is the same as the branch blind ditch, and the depth is 0.5m. When the base of the sedimentation tank is soil, the sedimentation tank is wrapped with a composite geomembrane on all sides, and the overlap length of the composite geomembrane and the blind ditch non-woven geotextile is not less than 300mm. When the base of the sedimentation tank is bedrock, the sedimentation tank is wrapped with a non-woven geotextile on all sides, and the sedimentation tank is filled with 15 to 30cm of gravel.

[0042] The working principle and beneficial effects of the above technical solution are:

[0043] At the intersection of the branch blind ditch and the main blind ditch, a sedimentation trough with a length of 4.5m, a width of the same as the branch blind ditch, and a depth of 0.5m is set. When the sedimentation trough base is soil, the sediment sedimentation trough is wrapped with composite geomembrane on all sides, and the overlap length between the composite geomembrane and the blind ditch non-woven geotextile is not less than 300mm. When the base is bedrock, the sediment sedimentation trough is wrapped with non-woven geotextile on all sides. Fill the sedimentation trough with 15-30cm gravel and compact it.

[0044] In one embodiment, the geotextile is manually laid into the ditch, and the geotextile is placed upright on the masonry-formed ditch walls on both sides. After the geotextile is laid, it is leveled and fixed with stones. The ditch surface near the ditch is reserved with a geotextile curling edge and wrapped with crushed stone filler. The overlap length of the geotextile along the longitudinal direction of the ditch is not less than 80cm, and the overlap length when wrapping the crushed stone is not less than 30cm. Two layers of crushed stone are laid on the laid geotextile. The first layer uses 3-7cm crushed stone backfilled with 40cm, and the second layer uses 2-5cm crushed stone backfilled with 50cm.

[0045] The working principle and beneficial effects of the above technical solution are:

[0046] The geotextile is manually laid into the ditch, and the geotextile is placed upright on the ditch walls on both sides of the masonry. After the geotextile is laid, it should be properly flattened and maintained at a certain degree of looseness, and fixed with stones. When laying the geotextile, a certain amount of geotextile curling should be left on the ditch surface to wrap the gravel filler. The overlap length of the geotextile along the longitudinal direction of the ditch should not be less than 80cm, and the overlap length when wrapping the gravel should not be less than 30cm to ensure the filtering effect. When laying the geotextile, take appropriate fixing measures to prevent the geotextile from moving when the gravel is filled. After the construction of the geotextile is completed, the protection of the finished product should be strengthened. When preparing the geotextile, it should be cut according to the size required by the design, and the narrow width should be sewn according to the design requirements. When laying the geotextile, it should be smooth, close to the concrete bottom plate, and the tightness should be appropriate; it should be sewn at the place where displacement may occur; the overlap width should be appropriately increased when laying on soft soil and underwater; laying on the slope is carried out from bottom to top, and the overlap should be done close to the ground.

[0047] Two layers of crushed stone are laid on the laid geotextile. The first layer uses 3-7 cm crushed stone to backfill 40 cm, and the second layer uses 2-5 cm crushed stone to backfill 50 cm. During construction, the crushed stone is laid manually at the bottom of the ditch and flattened, and compacted with a small roller.

[0048] In one embodiment, a handheld electric drill is used to drill a water pipe in the HMPP drainage pipe, with a hole diameter of 20 mm, a longitudinal spacing of 80 mm, and a lateral spacing of 120° between two water-permeable holes. The water-permeable holes are arranged between the double ribs of the HMPP drainage pipe, and the ribs of the drainage pipe should not be arranged. After the water-permeable holes are arranged, the HMPP drainage pipe is wrapped with a geotextile, and the seams of the geotextile are overlapped by 100 mm. Then, the centerline position of the pipe is determined, and the HMPP drainage pipe is installed.

[0049] The working principle and beneficial effects of the above technical solution are:

[0050] The laying of HMPP drainage pipes specifically includes the following key points:

[0051] (1) Arrangement of water holes in HMPP drainage pipes: Use a handheld electric drill to drill water holes in the HMPP drainage pipes. The hole diameter is 20 mm, the longitudinal spacing is 80 mm, and the lateral spacing between two water holes is 120°. The water holes are set between the two ribs of the HMPP drainage pipes. They should not be set on the ribs of the drainage pipes to damage their mechanical properties. After the water holes are set, the HMPP drainage pipes are wrapped with geotextiles, and the seams of the geotextiles are overlapped by 100 mm.

[0052] (2) First measure and lay out the lines to locate the centerline of the pipeline.

[0053] (3) Carrying, laying and installing pipes. When carrying, lift and place gently. Do not drag on the ground. Manually cooperate with lifting machinery to lay pipes. During the installation of pipes, it is necessary to ensure that the drainage of the trench is unobstructed to prevent the pipes from floating. When the pipeline is installed but not backfilled, once it is soaked in water, the center line and top elevation of the pipe should be re-measured and the appearance should be inspected. If displacement, floating, etc. occur, rework should be carried out.

[0054] In one embodiment, wire gabions are assembled on site, and a single 2.0 mm galvanized wire is wound into two strands, and two main frame wires are tied from the top corner end, and then tied every 100 to 150 mm downward until the bottom corner end. A total of three wire gabions are set in the middle and on both sides of the blind ditch, and the assembled wire gabions are manually transported to the construction work surface. The wire gabions are put in place in sequence according to the position lines of each row of wire gabions. The frames of adjacent wire gabions are wound into two strands with a single 2 mm galvanized wire, and connected in sequence every 150 mm starting from the corner end. The surface net is connected every 150 mm in the vertical and horizontal directions. 15 to 30 cm blocks of stone are filled in the wire gabions, and 5 plastic blind ditches are laid above each of the two HMPP drainage pipes, and they are fixed to the bottom with iron nails every 5 m. The plastic blind ditches are connected with iron wires.

[0055] The working principle and beneficial effects of the above technical solution are:

[0056] The laying of wire mesh gabions and plastic blind ditches includes the following key points:

[0057] (1) Assembly of wire gabions. Wire gabions are box-shaped structures composed of hexagonal double-interlocking wire meshes woven by low-carbon steel wires with special anti-corrosion treatment. Wire gabions are composed of gabion components such as end plates, front plates, back plates, bottom plates, top covers and partitions. Specifications: length × width × height = 1.5m × 1m × 1m. Wire gabion materials are assembled on site. A single 2.0mm galvanized wire is wound into two strands. The two main frame wires are tied from the top corners, and then tied every 100 to 150mm downwards until the bottom corners.

[0058] (2) Positioning, assembling and connecting wire gabions: A total of three wire gabions are set in the middle and on both sides of the blind ditch. The assembled wire gabions are transported to the construction site manually and put in place in sequence according to the position lines of each row of wire gabions. The frames of adjacent wire gabions are wound into double strands with a single 2mm galvanized wire and connected in sequence every 150mm starting from the corner end. The surface nets are connected every 150mm in the vertical and horizontal directions, and the connection method is the same.

[0059] (3) Manual loading of rocks: 15-30cm rocks are filled into wire gabions and transported to the construction site by loaders. The rocks are loaded manually with the help of excavators. The filling stones must not be filled all at once to ensure the integrity of the wire gabion. Each wire gabion must be evenly loaded at the same time to ensure that the appearance is not deformed. The wire gabion is loaded twice and evenly each time. Rusty stones, weathered stones, and garbage stones are strictly prohibited. The loading of rocks should be carried out by a team of two, one responsible for transporting materials and the other for paving. When paving, start from the four corners of the bottom of the cage and evenly place large and small stones and then pave upwards in sequence.

[0060] (4) Lay 5 plastic blind ditches on top of each of the two HMPP plastic steel pipes. After arranging them neatly according to the designed position, use iron nails to fix them at the bottom every 5 meters to prevent displacement. The plastic blind ditches are connected with iron wires.

[0061] In one embodiment, crushed stone with a particle size of 2 to 5 cm is first filled in manually with an excavator, and then crushed stone with a particle size of 3 to 7 cm is used to backfill 90 cm. A 5m wide geogrid is laid every 20 cm on the bottom of the crushed stone, with a width of 5 m and a total of three layers. The top of the main blind ditch is backfilled with 20 cm of 2 to 5 cm crushed stone as a filter layer. The overlap length of the permeable geotextile along the longitudinal direction of the ditch is not less than 80 cm, and the overlap length when wrapping the crushed stone is not less than 30 cm.

[0062] In one embodiment, the coarse-grained stone drainage body is composed of an upper filter layer, a lower filter layer and a coarse-grained stone filling body in the middle. The upper filter layer and the lower filter layer are both composed of a layer of 400g / ㎡ non-woven geotextile and three layers of 30cm thick filler filter layers. The particle sizes of the three 30cm thick filler filter layers are 0.3mm~2.0mm, 2.0mm~10.0mm and 20mm~40mm respectively. The filler of the coarse-grained stone filling body adopts continuously graded medium-weathered carbonate with a maximum particle size of 300mm, the content of particles smaller than 5mm does not exceed 20%, the content of particles smaller than 0.075mm does not exceed 5%, and the porosity is 16~20%.

[0063] The working principle and beneficial effects of the above technical solution are:

[0064] The coarse-grained stone drainage system includes the following operating points:

[0065] (1) The coarse-grained stone drainage body consists of an upper filter layer, a lower filter layer and an intermediate coarse-grained stone filling body, which has the function of collecting groundwater to the drainage ditch and filtering groundwater. The upper and lower filter layers are composed of 1 layer of 400g / ㎡ non-woven geotextile + 3 layers of 30cm thick filler filter layers. The particle size of filter layer 1 is 0.3mm~2.0mm, the particle size of filter layer 2 is 2.0mm~10.0mm, and the particle size of filter layer 3 is 20mm~40mm; the filler of the intermediate coarse-grained stone filling body adopts continuously graded medium-weathered carbonate, with a maximum particle size of 300mm, the content of particles less than 5mm does not exceed 20%, the content of particles less than 0.075mm does not exceed 5%, and the porosity is 16~20%.

[0066] (2) Before the construction of the filter layer under the coarse-grained stone drainage body, the original foundation shall be backfilled and leveled with weakly permeable materials. After leveling, the ground slope shall not be less than 0.5%, and the slope direction shall be the main blind ditch, secondary blind ditch, and branch blind ditch.

[0067] (3) Lay the geotextile with an overlap length of no less than 50 cm in the vertical and horizontal directions. After the geotextile is laid, fix it with stone blocks to prevent the filter layer from moving during filling.

[0068] (4) Filling of filter layer and coarse-grained stone filler: According to the design particle size requirements, fill 1 to 3 layers of filter layer in layers, and then fill the coarse-grained stone filling body in layers. Filling adopts the backfill method and the retreat method to spread the materials, and the bulldozer is used to flatten. The thickness of each layer of filter layer is 30cm, and the thickness of each layer of coarse-grained stone is 50cm. Use a 20T vibratory roller for rolling. The upper filling body can only be constructed after the lower filling body passes the inspection. Before filling the coarse-grained stone filling body, the filter layer is backwrapped with geotextile, and the filter layer is completely wrapped with geotextile. The construction method of the upper filter layer is the same as that of the lower filter layer.

[0069] (5) Before rolling, divide the rolling range and strips, and mark them with lime lines to control the vibration rolling range and ensure the rolling quality. Use a 20T roller for vibration rolling, with an exciting force of 500KN, a travel speed of less than 2km / h, 12 to 14 rolling passes, and the overlap width between the rolling strips should not be less than 20cm, and no missing rolling is allowed. Before vibration rolling, perform two static rolling passes. Use the forward and backward full vibration method for rolling, requiring the roller to travel straight and stably, and not to make sudden turns, stop vibration, or stop the machine on the working surface.

[0070] like Figures 2 to 6 As shown, in one embodiment, the crushed stone cushion layer is paved by a paving device, and the paving device includes:

[0071] Walking seat;

[0072] The paving roller group is located at the front end of the traveling direction of the traveling seat, and the paving roller group includes a posture adjustment frame 11 and a center roller group 12, a left roller group 13 and a right roller group 14 installed on the posture adjustment frame 11. The left roller group 13 and the right roller group 14 are symmetrically located on both sides of the center roller group 12, and the low ends of the left roller group 13 and the right roller group 14 are both arranged close to the center roller group 12. The middle roller group 12 is half-distributed with spiral winches with opposite rotation directions, and the left roller group 13 and the right roller group 14 are also distributed with spiral winches with opposite rotation directions.

[0073] The working principle and beneficial effects of the above technical solution are:

[0074] The walking seat moves on the gravel cushion layer, thereby driving the paving roller group installed at the front end of the walking direction of the walking seat to move, and the middle roller group 12, the left roller group 13 and the right roller group 14 rotate, thereby completing the paving of the gravel on the upper surface of the gravel cushion layer, so as to evenly spread the gravel on the surface of the gravel cushion layer.

[0075] Specifically, the middle roller group 12 rotates to transport the raised crushed stones to the two ends thereof respectively to the left roller group 13 and the right roller group 14 , and the left roller group 13 and the right roller group 14 further spread the crushed stones.

[0076] In one embodiment, the posture adjustment frame 11 includes: a fixed frame 15 installed at the front end of the walking direction of the walking seat, a bow-shaped rotating frame 16 rotatably installed on the fixed frame 15, an electric telescopic rod 17 installed at the bottom of the bow-shaped rotating frame 16, an intermediate roller group 12 rotatably installed on the bow-shaped rotating frame 15, an inner support frame 18 installed on the two side ends of the bow-shaped rotating frame 15, a middle part of a balancing frame 19 installed on the inner support frame 18 through a mounting shaft, a left roller group 13 installed on one end of an L-shaped connecting frame 10, and the other end of the L-shaped connecting frame 10 is sleeved on one of the side ends of the bow-shaped rotating frame 15 through a slider 1 21, a right roller group 14 installed on one end of an L-shaped connecting frame 22, and the other end of the L-shaped connecting frame 22 is sleeved on the other side end of the bow-shaped rotating frame 15 through a slider 2 23, two ends of the balancing frame 19 are respectively clamped on the L-shaped connecting frame 10 and the L-shaped connecting frame 22, and the telescopic end of the electric telescopic rod 17 is connected to the slider 2 23 through a supporting cross bar 24.

[0077] The working principle and beneficial effects of the above technical solution are:

[0078] The middle roller group 12 rotates to transport the raised crushed stones to the left roller group 13 and the right roller group 14 at its two ends respectively. When too much crushed stones are transported to the left roller group 13 or the right roller group 14, the left roller group 13 or the right roller group 14 moves in the traveling direction of the walking seat, thereby increasing the paving area.

[0079] For example, when the middle roller group 12 transports most of the protruding gravel to the left roller group 13, the electric telescopic rod 17 contracts, thereby driving the supporting cross bar 24 installed at the output end of the electric telescopic rod 17 and the slider 23 connected to the supporting cross bar 24 to move in the contraction direction of the electric telescopic rod 17. The slider 23 drives the L-shaped connecting frame 22 connected thereto and the right roller group 14 installed on the L-shaped connecting frame 22 to move in the contraction direction of the electric telescopic rod 17. When the balancing frame 19 clamped with the vertical section of the L-shaped connecting frame 22 moves in the contraction direction of the electric telescopic rod 17, the balancing frame 19 rotates on the inner support frame 18 with the installation axis as the center. At this time, the balancing frame 19 moves near the end of the L-shaped connecting frame 10 toward the walking direction close to the walking seat, thereby driving the left roller group 13 connected to the L-shaped connecting frame 10 to move in the walking direction of the walking seat, thereby increasing the paving area of ​​the left roller group 13.

[0080] On the contrary, when the middle roller group 12 transports most of the protruding gravel to the right roller group 14, the electric telescopic rod 17 extends, thereby driving the supporting cross bar 24 installed on the output end of the electric telescopic rod 17 and the slider 23 connected to the supporting cross bar 24 to move in the extension direction of the electric telescopic rod 17, and the slider 23 drives the L-shaped connecting frame 22 connected thereto and the right roller group 14 installed on the L-shaped connecting frame 22 to move in the extension direction of the electric telescopic rod 17, and the right roller group 14 moves in the walking direction of the walking seat, thereby increasing the paving area of ​​the right roller group 14.

[0081] In one embodiment, the posture adjustment frame 11 further includes:

[0082] A central gear 25, the central gear 25 is mounted on the end of the fixed frame 15 away from the arcuate rotating frame 16 through a central shaft, and the arcuate rotating frame 16 is mounted on the central rotating shaft;

[0083] The sector gear 26 is mounted on the end of the fixed frame 15 away from the arc-shaped rotating frame 16 and meshes with the central gear 25;

[0084] The driving inclined groove 27 is provided on the fixed frame 15, the strip groove 28 is provided on the sector gear 26, the straight line where the strip groove 28 is located points to the rotating end of the sector gear 26, the limiting slide bar 29 is slidably connected in the driving inclined groove 27 and the strip groove 28, the limiting slide bar 29 is connected to the connecting rod 31 through a universal joint 30, and the connecting rod 31 is connected to the horizontal section of the L-shaped connecting frame 10 through a spherical mounting head.

[0085] The working principle and beneficial effects of the above technical solution are:

[0086] When paving a gravel cushion on a slope with a certain slope, part of the gravel on the slope rolls down and gathers at the low end of the slope due to gravity, so that the thickness of the gravel cushion near the low end of the slope is slightly greater than the thickness of the gravel cushion near the high end of the slope. At this time, the left roller group 13 is moved close to the low end of the slope, the electric telescopic rod 17 is contracted, and the left roller group 13 moves in the walking direction of the walking seat, thereby increasing the paving area of ​​the left roller group 13. Synchronously, the connecting rod 31 connected to the horizontal section of the L-shaped connecting frame 10 is connected through a universal joint. The head 30 pulls the limit slide bar 29, so that the limit slide bar 29 slides in the driving inclined groove 27. The limit slide bar 29 cooperates with the strip groove 28 to drive the sector gear 26 to rotate in the walking direction close to the walking seat, thereby driving the central gear 25 meshing with the sector gear 26 to rotate clockwise. The central gear 25 drives the bow-shaped rotating frame 16 coaxially connected with it to rotate clockwise on the fixed frame 15 through the central axis, thereby driving the left roller group 13 to make a small downward movement, thereby slightly reducing the thickness of the gravel cushion near the left roller group 13. The middle roller group 12 is replaced, and the left roller group 13 rotates in the opposite direction. The left roller group 13 conveys the gravel to the middle roller group 12, and the middle roller group 12 takes over and conveys the gravel to the right roller group 14, so that the gravel cushion on the slope can be evenly paved.

[0087] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.

Claims

1. A construction process for underground drainage system under high fill, including the construction of main blind ditch, secondary blind ditch and branch blind ditch, characterized in that: The same construction process of the main blind ditch, secondary blind ditch and branch blind ditch includes digging the ditch, leveling the ditch bottom, and laying geotextiles and filling gravel after the excavated ditch is tested for bearing capacity. Among them, the construction process of the secondary blind ditch and the branch blind ditch also includes the laying of the plastic blind ditch after the laying of the geotextile. The construction of the secondary blind ditch also includes the laying of the crushed stone cushion before the laying of the plastic blind ditch and the laying of the filter layer and the permeable geotextile after filling the crushed stone. A sedimentation tank is set at the intersection of the branch blind ditch and the main blind ditch. The construction process of the main blind ditch also includes pouring a 200mm thick C20 concrete cushion layer and an 800mm thick C25 reinforced concrete bottom plate in the ditch before laying the geotextile, constructing the mortar-laid stone ditch wall and spreading the gravel cushion layer after laying the geotextile, laying the HMMP drainage pipe, and then laying the wire mesh gabion and plastic blind ditch, and laying the filter layer and permeable geotextile after filling the gravel, and finally constructing the coarse-grained stone drainage body.

2. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: The length of the sedimentation trough is 4.5m, the width is the same as the branch blind ditch, and the depth is 0.5m. When the base of the sedimentation trough is soil, the sedimentation trough is wrapped with a composite geomembrane on all sides, and the overlap length of the composite geomembrane and the blind ditch non-woven geotextile is not less than 300mm. When the base of the sedimentation trough is bedrock, the sedimentation trough is wrapped with a non-woven geotextile on all sides, and the sedimentation trough is filled with 15 to 30cm of gravel.

3. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: The geotextile is manually laid into the ditch and placed upright on the masonry-formed ditch walls on both sides. After laying, the geotextile is leveled and fixed with stones. A geotextile curling edge is reserved on the ditch surface close to the ditch and wrapped with crushed stone filler. The overlap length of the geotextile along the longitudinal direction of the ditch is not less than 80cm, and the overlap length when wrapping crushed stone is not less than 30cm. Two layers of crushed stone are laid on the laid geotextile. The first layer uses 3-7cm crushed stone backfilled with 40cm, and the second layer uses 2-5cm crushed stone backfilled with 50cm.

4. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: Use a handheld electric drill to drill water-permeable pipes in the HMPP drainage pipe, with a hole diameter of 20mm, a longitudinal spacing of 80mm, and a lateral spacing of 120° between two water-permeable holes. The water-permeable holes are set between the double ribs of the HMPP drainage pipe and should not be set on the ribs of the drainage pipe. After the water-permeable holes are set, wrap the HMPP drainage pipe with geotextile, overlap the seams of the geotextile by 100mm, then determine the centerline position of the pipeline, and install the HMPP drainage pipe.

5. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: Assemble the wire mesh gabions on site. Use a single 2.0mm galvanized wire to wind it into two strands. Tighten the two main frame wires from the top corner, and then tie them every 100-150mm downwards until the bottom corner. Set a total of three wire mesh gabions in the middle and on both sides of the blind ditch. Manually transport the assembled wire mesh gabions to the construction site. Put the wire mesh gabions in place in sequence according to the position lines of each row of wire mesh gabions. The frames of adjacent wire mesh gabions are wound into two strands with a single 2mm galvanized wire and connected in sequence every 150mm starting from the corner. The surface net is connected every 150mm in the vertical and horizontal directions. Fill the wire mesh gabions with 15-30cm stones. Lay 5 plastic blind ditches on top of each HMPP drainage pipe and fix them at the bottom with iron nails every 5m. The plastic blind ditches are connected with iron wires.

6. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: The method of manual labor and excavation is used to first fill the gravel with a particle size of 2 to 5 cm, and then the gravel with a particle size of 3 to 7 cm is used to backfill 90 cm. A 5m wide geogrid is laid every 20 cm on the bottom of the gravel, with a width of 5m, and a total of three layers are laid. The top of the main blind ditch is backfilled with 20 cm of 2 to 5 cm gravel as a filter layer. The overlap length of the permeable geotextile along the longitudinal direction of the ditch is not less than 80 cm, and the overlap length when wrapping the gravel is not less than 30 cm.

7. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: The coarse-grained stone drainage body consists of an upper filter layer, a lower filter layer and a coarse-grained stone filling body in the middle. The upper filter layer and the lower filter layer are composed of a layer of 400g / ㎡ non-woven geotextile and three layers of 30cm thick filler filter layers. The particle sizes of the three 30cm thick filler filter layers are 0.3mm~2.0mm, 2.0mm~10.0mm and 20mm~40mm respectively. The filler of the coarse-grained stone filling body adopts continuously graded medium-weathered carbonate with a maximum particle size of 300mm. The content of particles less than 5mm does not exceed 20%, the content of particles less than 0.075mm does not exceed 5%, and the porosity is 16~20%.

8. The construction process of underground drainage system under high fill according to claim 1 is characterized in that: The gravel cushion layer is paved by a paving device, the paving device comprising: a traveling seat, a paving roller group located at the front end of the traveling direction of the traveling seat, the paving roller group comprising a posture adjustment frame (11) and a central roller group (12), a left roller group (13) and a right roller group (14) installed on the posture adjustment frame (11), the left roller group (13) and the right roller group (14) are symmetrically located on both sides of the central roller group (12), the lower ends of the left roller group (13) and the right roller group (14) are both arranged close to the central roller group (12), the middle roller group (12) is half-distributed with spiral winches with opposite rotation directions, and the left roller group (13) and the right roller group (14) are also distributed with spiral winches with opposite rotation directions.

9. The construction process of underground drainage system under high fill according to claim 8, characterized in that: The posture adjustment frame (11) comprises: a fixed frame (15) installed at the front end of the walking seat in the walking direction, a bow-shaped rotating frame (16) rotatably installed on the fixed frame (15), an electric telescopic rod (17) installed at the bottom of the bow-shaped rotating frame (16), an intermediate roller group (12) rotatably installed on the bow-shaped rotating frame (15), an inner support frame (18) installed at two side ends of the bow-shaped rotating frame (15), a middle part of a balancing frame (19) installed on the inner support frame (18) through a mounting shaft, and a left roller group (13) installed at one end of an L-shaped connecting frame (10). The other end of the L-shaped connecting frame 1 (10) is sleeved on one side end of the bow-shaped rotating frame (15) through a slider 1 (21), the right roller group (14) is installed on one end of the L-shaped connecting frame 2 (22), the other end of the L-shaped connecting frame 2 (22) is sleeved on the other side end of the bow-shaped rotating frame (15) through a slider 2 (23), the two ends of the balance frame (19) are respectively clamped on the L-shaped connecting frame 1 (10) and the L-shaped connecting frame 2 (22), and the telescopic end of the electric telescopic rod (17) is connected to the slider 2 (23) through a supporting cross bar (24).

10. The construction process of underground drainage system under high fill according to claim 9, characterized in that: The attitude adjustment frame (11) also includes: a central gear (25) installed on the end of the fixed frame (15) away from the bow-shaped rotating frame (16) through a central axis, the bow-shaped rotating frame (16) is installed on the central rotating axis, a fan gear (26) is installed on the end of the fixed frame (15) away from the bow-shaped rotating frame (16) and meshes with the central gear (25), a driving inclined groove (27) is opened on the fixed frame (15), a strip groove (28) is opened on the fan gear (26), and the straight line where the strip groove (28) is located points to the rotating end of the fan gear (26), a limit slide rod (29) is slidably connected to the driving inclined groove (27) and the strip groove (28), the limit slide rod (29) is connected to the connecting rod (31) through a universal joint (30), and the connecting rod (31) is connected to the horizontal section of the L-shaped connecting frame (10) through a spherical mounting head.