Coordination control method based on AGC prediction signal

Through the coordination control method based on AGC prediction signal, the fuel, water supply and air supply volume of the coal-fired unit are dynamically adjusted, the problem of lagging adjustment response of the coal-fired unit is solved, the load response capability is improved and economical is taken into account, and the unit parameters and Matching of grid requirements.

CN118998738APending Publication Date: 2024-11-22内蒙古电力(集团)有限责任公司电力调度控制分公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411081386.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing coal-fired unit regulation and control methods have failed to effectively solve the problem of hysteresis of regulation response caused by boiler inertia and delay, and cannot respond to changes in the grid load in a timely manner.

Method used

Using a coordinated control method based on AGC prediction signal, the confidence level of AGC commands is calculated, and the fuel, water and air supply volume are dynamically adjusted. The segmented function is used to convert the main steam pressure and intermediate temperature demand, and the boiler control system is adjusted. Set the value to match the grid requirements.

Benefits of technology

The load response capacity of coal-fired units is improved, avoids prematurely greatly improving energy storage, takes into account the economic and responsiveness of unit operation, and ensures the synchronous matching of unit parameters and grid scheduling instructions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118998738A_ABST
    Figure CN118998738A_ABST
Patent Text Reader

Abstract

The invention discloses a coordination control method based on an AGC prediction signal. The coordination control method comprises the steps that S1, a power grid dispatching mechanism receives an electric power spot clearing result and frequency; s2, calculating the confidence coefficient of the AGC instruction in each time period according to the frequency of the electric power spot clearing result; s3, calculating to obtain the energy storage increment demand quantity of the unit; s4, converting the energy storage demand quantity into a main steam pressure increment demand quantity and an intermediate point temperature increment demand quantity by utilizing a piecewise function through a boiler main steam pressure and intermediate point temperature conversion function; and S5, the amount of fuel entering the boiler, the water supply amount and the air supply amount are adjusted by changing the set value. The invention aims to solve the problem that an existing coal-fired unit regulation control method does not introduce an AGC prediction signal and cannot solve the problem of regulation response lag caused by boiler inertia and delay.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of electric coal-fired unit regulation, and in particular relates to a coordinated control method based on AGC prediction signals. Background Art

[0002] With the rapid construction of new power systems, the proportion of wind power, photovoltaic and other new energy installed capacity has gradually increased. Due to the randomness and volatility of new energy power generation, in order to smooth out the fluctuations of new energy and ensure the safe operation of the power grid, higher requirements are placed on the regulation performance of coal-fired units. Coal-fired units are mainly composed of boilers, steam turbines and generators. Due to the large inertia and delay of boiler combustion and heat transfer, coal-fired units are difficult to respond to the power grid load regulation needs in a timely manner.

[0003] In the Chinese Public Invention with application number CN202311474105.6, a control method adapted to the wide step change of the AGC load command of a thermal power unit is disclosed, including correcting the unit's variable load rate and variable load feedforward coefficient; correcting the unit's water-coal ratio parameters; adding a variable load command feedforward dynamic feedforward loop in the fuel main control loop; adding a load command change signal in the feedforward of the unit's primary air pressure control loop; when the unit is put into AGC mode, adopting an operation mode of first constant pressure, then sliding pressure, and then constant pressure; optimizing the steam turbine valve response load command logic. This method corrects the control parameters such as the variable load rate, feedforward coefficient, and water-coal ratio according to the AGC command step, thereby reducing the parameter fluctuations in the load regulation process and improving the AGC regulation rate.

[0004] The defect of the prior art is that the above patent corrects the parameters of the coordinated control system according to the real-time AGC instruction step of the coal-fired unit to avoid overshoot or undershoot of fuel, feed water and other parameters caused by mismatch between parameters and step, and reduce the fluctuation of main steam pressure and main steam temperature during the regulation response process. However, the control system does not introduce AGC prediction signals, and cannot solve the regulation response lag problem caused by boiler inertia and delay. Summary of the invention

[0005] In view of the fact that the existing regulation and control method for coal-fired units does not introduce an AGC prediction signal and cannot solve the problem of delayed regulation response caused by boiler inertia and delay, the present invention provides a coordinated control method based on an AGC prediction signal.

[0006] In order to achieve the above technical objectives, the technical solution adopted by the present invention is as follows:

[0007] A coordinated control method based on an AGC prediction signal comprises the following steps:

[0008] S1. The grid dispatching agency receives the results and frequency of electricity spot clearing;

[0009] S2. Calculate the confidence level of each time period of the AGC command according to the frequency of the electricity spot clearing result;

[0010] S3. Calculate the required increment of the unit energy storage;

[0011] S4. Through the conversion function of the main steam pressure and the intermediate point temperature of the boiler, convert the energy storage demand into the required increment of the main steam pressure and the required increment of the intermediate point temperature by using a piecewise function;

[0012] S5. Adjust the fuel quantity, feed water quantity and air supply quantity entering the boiler by changing the set value.

[0013] Furthermore, the detailed process of calculating the confidence level of each time period of the AGC command in step S2:

[0014] S201. Preset T i+1 and the number of time periods n divided by the time period of T i ;

[0015] S202. Assign initial confidence levels to different time periods in the number of time periods divided at time T i ;

[0016] S203. Correct the initial confidence level assignment of different time periods of the confidence level according to the historical data of the AGC command;

[0017] S204. Synchronously adjust each confidence interval over time until the AGC command is issued or until time T i+1 ;

[0018] Furthermore, the predicted value of the AGC command includes the amplitude information ΔP of the command change (ΔP = P i+1 -P i ), and the actual issuance time of the command depends on the change of the electricity load;

[0019] If the AGC prediction signal is divided into n time periods, the initial confidence level of each time period is Over time, at the i-th minute (i < n), f t=1:i = 0,

[0020] Furthermore, use the AGC historical data to correct the initial confidence level of each time period. Select the same time of the previous day and the same time of the same day of the previous week as the reference data, and increase the confidence level of the corresponding time period according to the parameter data command issuance time period;

[0021] Let the weight correction value of the previous day be a, and the weight correction value of the same day of the previous week be b. Assume that the command is issued in the j-th time period of the previous day and the command is issued in the k-th time period of the same day of the previous week. Then the corrected confidence level is ​ Other time periods

[0022] Furthermore, the calculation formula for the incremental energy storage demand of the unit is:

[0023] ΔE=ΔP×f i ×k, ΔP is the AGC command amplitude change information, f i is the confidence level corresponding to the AGC instruction issuance period, and k is the energy storage calculation coefficient.

[0024] Furthermore, in step S4, the main steam pressure increment demand and the intermediate point temperature increment demand are respectively added to the pressure setting value of the boiler main control system and the temperature setting value of the intermediate point temperature control system, and then the control system output is controlled by correspondingly changing the setting value in step S5, thereby adjusting the amount of fuel, water supply and air supply entering the boiler.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] The present invention utilizes AGC prediction instructions and AGC historical data, dynamically adjusts the confidence level, calculates the incremental energy storage demand of the unit, and then converts it into the incremental demand of the main steam pressure and the incremental demand of the intermediate point temperature through a piecewise function. By changing the setting values ​​of the boiler master control and intermediate point temperature control systems, the unit energy storage level is gradually matched with the network adjustment demand, and the load response capability of the unit is improved. In addition, through the dynamic adjustment of the confidence level, the unit energy storage is avoided from being greatly increased too early, and the energy storage level is gradually increased with the change of the confidence level, taking into account the unit operation economy and response capability. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is an overall flow chart of a coordinated control method based on an AGC prediction signal in an embodiment of the present invention;

[0028] Figure 2 This is a flow chart of parameter adjustment of the unit control system in an embodiment of the present invention. DETAILED DESCRIPTION

[0029] In order to facilitate the understanding of those skilled in the art, the present invention is further described below in conjunction with embodiments and drawings. The contents mentioned in the implementation modes are not intended to limit the present invention.

[0030] like Figure 1 As shown, this embodiment provides a coordinated control method based on an AGC prediction signal, comprising the steps of:

[0031] S1. The grid dispatching agency receives the results and frequency of electricity spot clearing;

[0032] S2. Calculate the confidence of the AGC instruction in each period according to the frequency of the electricity spot clearing results;

[0033] S3. Calculate the incremental energy storage demand of the unit;

[0034] S4, through the boiler main steam pressure and midpoint temperature conversion function, the energy storage demand is converted into the main steam pressure increment demand and the midpoint temperature increment demand using a piecewise function;

[0035] S5. Adjust the amount of fuel, water supply and air supply entering the boiler by changing the set value.

[0036] like Figure 2 As shown, the working principle of the present invention is that the present invention utilizes the AGC instruction prediction signal, calculates the energy storage demand of the unit in real time through the instruction amplitude change information and the dynamic confidence, and converts the energy storage demand into the main steam pressure and the intermediate point temperature demand by using the piecewise function. By changing the set values ​​of the boiler main control system and the intermediate point temperature control system, the control system output is adjusted in time, and then the fuel amount, water supply amount and air supply amount entering the boiler are adjusted, so as to ensure the advance action of the unit parameter adjustment, the energy storage level and the power grid dispatching instruction are synchronously matched, and the load regulation capability of the unit is improved.

[0037] The detailed process of calculating the confidence of the AGC instruction in each period in step S2 is:

[0038] S201, preset T i+1 With T i The number of time periods divided into by the time period n;

[0039] S202, T i Assign initial confidence values ​​to different time periods in the divided time periods at all times;

[0040] S203, modifying the initial confidence values ​​of different confidence periods according to the AGC instruction historical data;

[0041] S204, synchronously adjust each confidence interval over time until the AGC instruction is issued or T i+1 Until the moment.

[0042] The frequency of electricity spot clearing results is to calculate the AGC instructions of coal-fired units every 5 minutes, with a total of 288 instructions throughout the day;

[0043] In T i At this moment, the AGC instruction is P i At this time, according to the current electricity spot market clearing results, the next moment T is calculated. i+1 AGC command of coal-fired unit, i.e. AGC command prediction value P i+1 , where T i+1 With Ti The time interval is 5 minutes;

[0044] The predicted value of the AGC command only contains the amplitude information ΔP of the command change (ΔP = P i+1 -P i ), and the actual command issuance time depends on the change of the power consumption load;

[0045] Decompose the prediction signal, match the confidence interval for each time period within the 5-minute time scale, and synchronize the adjustment of the unit's energy storage level with the actual command issuance of the power grid;

[0046] If the AGC prediction signal is divided into n time periods, the initial confidence level of each time period is Changing with time, at the i-th minute (i < n), f t=1:i = 0,

[0047] Decompose the prediction signal, match the confidence interval for each time period within the 5-minute time scale, and synchronize the adjustment of the unit's energy storage level with the actual command issuance of the power grid, avoiding premature or delayed adjustment of unit parameters. Divide the AGC prediction signal into 5 time periods t1, t2, t3, t4, t5, corresponding to each minute between T i+1 and T i . The initial confidence levels f1 - f5 of each time period are all 0.2, but the confidence level changes with time. For example, if the AGC command is not actually issued within the first minute, the confidence level f1 of t1 becomes 0, and the confidence levels f2 - f5 of t2 - t5 become 0.25; if the AGC command is still not issued by the second minute, the confidence levels f1 and f2 of t1 and t2 become 0, and the confidence levels f3 - f5 of t3 - t5 become 0.33; if the AGC command is still not issued by the third minute, the confidence levels f1, f2, and f3 of t1, t2, and t3 become 0, and the confidence levels f4 and f5 of t4 and t5 become 0.5; if the AGC command is still not issued by the fourth minute, the confidence levels f1 - f4 of t1 - t4 become 0, and the confidence level f5 of t5 becomes 1.

[0048] Use the AGC historical data to correct the initial confidence level of each time period, select the same time of the previous day and the same time of the same day of the previous week as the reference data, and increase the confidence level of the corresponding time period according to the parameter data command issuance time period;

[0049] Let the weight correction value of the previous day be a, and the weight correction value of the same day of the previous week be b. The initial confidence level of each time period is Assume that the command is issued in the j-th time period of the previous day and the command is issued in the k-th time period of the same day of the previous week. Then the corrected confidence level is Other time periods

[0050] The initial confidence of each time period is corrected using AGC historical data. The same time of the previous day and the same time of the previous week are selected as reference data. The confidence of the corresponding time period is increased according to the time period when the parameter data instruction is issued, where the weight of the previous day is 0.2 and the weight of the previous week is 0.1. For example, if the AGC instruction is issued at the time t3 of the previous day, the confidence f3 of the t3 period is corrected from 0.2 to 0.4, and the corresponding confidences of t1, t2, t4, and t5 are corrected from 0.2 to 0.15. If the AGC instruction is issued at the time t4 of the same day of the previous week, the confidence f4 of the t4 period is corrected from 0.15 to 0.25, and the corresponding confidences of t1, t2, and t5 are corrected from 0.15 to 0.125, and the confidence of t3 is corrected from 0.4 to 0.375.

[0051] The calculation formula for the incremental energy storage demand of the unit is:

[0052] ΔE=ΔP×f i ×k, ΔP is the AGC command amplitude change information, f i is the confidence level corresponding to the AGC instruction issuance period, and k is the energy storage calculation coefficient. The energy storage level of the coal-fired unit is mainly reflected in the main steam pressure and the intermediate point temperature of the boiler. Therefore, the energy storage demand is converted into the main steam pressure increment demand and the intermediate point temperature increment demand using a piecewise function. The piecewise function is shown in Table 1:

[0053] Table 1 Main steam pressure and intermediate point temperature conversion function table

[0054]

[0055] In step S4, the main steam pressure increment demand and the intermediate point temperature increment demand are respectively added to the pressure setting value of the boiler main control system and the temperature setting value of the intermediate point temperature control system, and then the control system output is controlled by corresponding changes in the setting values ​​in step S5, thereby adjusting the amount of fuel, water supply and air supply entering the boiler.

[0056] Assuming that the AGC instruction at 10:05 on January 12 is 200MW, the grid dispatching agency calculates the AGC forecast signal at 10:10 to be 220MW based on the clearing results of the power spot market, then the instruction amplitude changes ΔP = 20MW. 10:05 to 10:10 is divided into 5 time periods, and the initial confidence is 0.2. At 10:08 on January 11, the AGC instruction was issued to the coal-fired units, then f3 was revised from 0.2 to 0.4, and the corresponding other confidences were revised from 0.2 to 0.15. At 10:09 on January 5, the AGC instruction was issued, then the confidence f4 of the t4 period was revised from 0.15 to 0.25, and the corresponding confidences of t1, t2, and t5 were revised from 0.15 to 0.125, and the confidence of t3 was revised from 0.4 to 0.375. Assuming that the energy storage calculation coefficient is 1, the energy storage increment demand ΔE at 10:05 on January 12 is 20×0.125×1=2.5MW. The main steam pressure increment demand ΔH=0.05MPa and the intermediate point temperature increment demand ΔT=1℃ are calculated by referring to the piecewise function table. If the AGC instruction 220MW is not actually issued to the unit at 10:06, the confidence level is dynamically adjusted synchronously, f1 changes from 0.125 to 0, f2 changes from 0.125 to 0.156, f3 changes from 0.375 to 0.406, f4 changes from 0.25 to 0.281, and f5 changes from 0.125 to 0.156. At this time, the energy storage increment demand ΔE=20×0.156×1=3.12MW. According to the calculation of the segmented function table, the main steam pressure increment demand ΔH increases from 0.05MPa to 0.0624MPa, and the intermediate point temperature increment demand ΔT increases from 1℃ to 1.248℃. The main steam pressure increment demand and the intermediate point temperature increment demand are further increased, the set values ​​of the boiler main control system and the intermediate point temperature control system are increased synchronously, and the fuel quantity, feed water quantity and air supply quantity are increased. As the probability of the network dispatching instructions increases, the unit energy storage level gradually increases, thereby avoiding the premature increase of the unit energy storage and the decrease of the operating economy. If the AGC instruction 220MW is not actually issued to the unit at 10:07, the confidence is dynamically adjusted synchronously, f1, f2 become 0, f3 changes from 0.406 to 0.458, f4 changes from 0.281 to 0.0.333, and f5 changes from 0.156 to 0.208. At this time, the energy storage increment demand ΔE=20×0.458×1=9.16MW. According to the calculation of the segmented function table, the main steam pressure increment demand ΔH increased from 0.0624MPa to 0.2664MPa, and the intermediate point temperature increment demand ΔT increased from 1.248℃ to 2.832℃. Since the probability of the unit issuing instructions at 10:08 is high, the unit greatly increases the energy storage level at 10:07 to improve the load response capability. At 10:08, the AGC instruction was issued. Since the unit has a high energy storage level, it can respond well to the load demand.

[0057] Compared with the prior art, the present invention has the following beneficial effects:

[0058] The present invention utilizes AGC prediction instructions and AGC historical data, dynamically adjusts the confidence level, calculates the incremental energy storage demand of the unit, and then converts it into the incremental demand of the main steam pressure and the incremental demand of the intermediate point temperature through a piecewise function. By changing the setting values ​​of the boiler master control and intermediate point temperature control systems, the unit energy storage level is gradually matched with the network adjustment demand, and the load response capability of the unit is improved. In addition, through the dynamic adjustment of the confidence level, the unit energy storage is avoided from being greatly increased too early, and the energy storage level is gradually increased with the change of the confidence level, taking into account the unit operation economy and response capability.

[0059] The above is a detailed introduction to a coordinated control method based on an AGC prediction signal provided by the present application. The description of the specific embodiment is only used to help understand the method and its core idea of ​​the present application. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the present application, several improvements and modifications can be made to the present application, and these improvements and modifications also fall within the scope of protection of the claims of the present application.

Claims

1. A coordinated control method based on AGC prediction signal, characterized in that: Includes steps: S1. The grid dispatching agency receives the results and frequency of electricity spot clearing; S2. Calculate the confidence of the AGC instruction in each period according to the frequency of the electricity spot clearing results; S3. Calculate the incremental energy storage demand of the unit; S4, through the boiler main steam pressure and midpoint temperature conversion function, the energy storage demand is converted into the main steam pressure increment demand and the midpoint temperature increment demand using a piecewise function; S5. Adjust the amount of fuel, water supply and air supply entering the boiler by changing the set value.

2. The coordinated control method based on AGC prediction signal according to claim 1, characterized in that: The detailed process of calculating the confidence of the AGC instruction in each period in step S2 is: S201, preset T i+1 With T i The number of time periods divided into by the time period n; S202, T i Assign initial confidence values ​​to different time periods in the divided time periods at all times; S203, modifying the initial confidence values ​​of different confidence periods according to the AGC instruction historical data; S204, synchronously adjust each confidence interval over time until the AGC instruction is issued or T i+1 Until the moment.

3. The coordinated control method based on AGC prediction signal according to claim 2, characterized in that: The AGC command prediction value contains the amplitude information of the command change ΔP (ΔP = P i+1 -P i ), the actual time when the instruction is issued depends on the change of power load; If the AGC prediction signal is divided into n time periods, the initial confidence level of each time period is Changing with time, at the i-th minute (i < n), f t=1:i = 0, 4. The coordinated control method based on AGC prediction signal according to claim 3, characterized in that: Use AGC historical data to correct the initial confidence of each time period, select the same time of the previous day and the same time of the previous week as reference data, and increase the confidence of the corresponding time period according to the parameter data instruction; Assume that the weight correction value of the previous day is a, and the weight correction value of the same day of the previous week is b. The initial confidence level of each period is Assuming that the j-period order was issued the day before, and the k-period order was issued on the same day of the previous week, the corrected confidence is Other time periods 5. The coordinated control method based on AGC prediction signal according to claim 4, characterized in that: The calculation formula for the incremental energy storage demand of the unit is: ΔE=ΔP×f i ×k, ΔP is the AGC command amplitude change information, f i Corresponding to the time period when AGC instructions are issued Confidence level, k is the energy storage calculation coefficient.

6. The coordinated control method based on AGC prediction signal according to claim 5, characterized in that: In step S4, the main steam pressure increment demand and the intermediate point temperature increment demand are respectively added to the pressure setting value of the boiler main control system and the temperature setting value of the intermediate point temperature control system, and then the control system output is controlled by corresponding changes in the setting values ​​in step S5, thereby adjusting the amount of fuel, water supply and air supply entering the boiler.