Method for analyzing influence of typhoon disaster on operation of power system and related device

Through technical means such as the Jesse Typhoon model and N-i criterion, the impact of typhoon disasters on the power system was analyzed, and the problem that existing methods could not accurately reflect the impact of typhoon disasters was solved, and the impact on the power system was quantified and risk assessment was achieved.

CN119089700APending Publication Date: 2024-12-06CHINA SOUTHERN POWER GRID COMPANY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411384354.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing analysis methods for the impact of typhoon disasters on the power system operation cannot accurately quantify and compare the impact of typhoon disasters on the power system, and the accuracy of the Batts typhoon model is poor and cannot accurately reflect the actual situation.

Method used

The Jesse Typhoon model combined with meteorological typhoon speed data is used to construct a wind field model, calculate the wind speed at any point in the power system, calculate the failure rate of the transmission line section and the pole tower, determine the failure probability, and calculate the expected cut through the N-i criterion and state enumeration method. Load volume, analyze the impact of typhoon disasters on the power system.

Benefits of technology

It realizes accurate quantification of the impact of typhoon disasters on the operation of the power system, and provides reference data for network reconstruction and scheduling in subsequent responses to typhoon disasters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119089700A_ABST
    Figure CN119089700A_ABST
Patent Text Reader

Abstract

The invention discloses a method for analyzing the influence of typhoon disasters on operation of an electric power system and a related device, key information data of the typhoon disasters are obtained through a meteorological station, a wind field model of the typhoon disasters is established according to a Jersey typhoon model, and therefore the typhoon encountering wind speed of any point of the electric power system is obtained; according to a power transmission branch vulnerability model, a power transmission branch of the power system is composed of a plurality of power transmission line sections and a plurality of power transmission towers, faults of the whole power transmission branch can be caused by faults of any power transmission line section or tower due to typhoon disasters, and the fault probability of each power transmission branch of the power system is calculated; a fault line set of the power system is screened out according to an N-i criterion, and then the expected load shedding amount of the power system is calculated through a state enumeration method and serves as a risk index. The result obtained by the method can quantify and compare the influence of the typhoon disaster on the operation of the power system, and can provide reference for the operation of network reconstruction, scheduling and the like for the power system to subsequently cope with the typhoon disaster.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of power system planning, and in particular to a method for analyzing the impact of typhoon disasters on power system operation and related devices. Background Art

[0002] With the development of social economy and the continuous growth of electricity demand, the scale of transmission network is constantly expanding. Long-distance transmission branches including overhead transmission line sections and transmission towers have become the key link of power transmission in the entire power grid. Due to long-term exposure to the atmospheric environment, the equipment in the transmission network is very vulnerable to typhoon disasters and failures. Once a failure occurs, it may lead to the interruption of power transmission of the entire transmission branch, and even cause large-scale power outages, posing a serious threat to the safe and stable operation of the transmission network.

[0003] At present, some scholars have carried out research on the failure of transmission networks under typhoon disasters. However, most of them believe that the typhoon wind speeds in the area where the transmission network is located are the same, or simply divide the transmission network according to weather conditions, which cannot accurately reflect the impact of typhoon disasters on the transmission network. In addition, many people use the Batts typhoon model to characterize the wind speed and attenuation process of each point in the wind field after the typhoon lands. It has the advantages of simple calculation and fast operation speed, but the typhoon wind field obtained by the Batts typhoon model is less accurate, and it is believed that the typhoon moves in a straight line after landing, which deviates from the actual situation.

[0004] Therefore, it is urgent to design an analysis method for the impact of typhoon disasters on the operation of power systems to accurately quantify and compare the impact of typhoon disasters on the operation of power systems, and at the same time provide a reference for subsequent network reconstruction, dispatching and other operations of the power system in response to typhoon disasters. Summary of the invention

[0005] The present application provides an analysis method and related devices for the impact of typhoon disasters on the operation of a power system, which are used to accurately quantify and compare the impact of typhoon disasters on the operation of a power system.

[0006] In view of this, the first aspect of the present application provides a method for analyzing the impact of typhoon disasters on power system operation, the method comprising:

[0007] Acquire key typhoon information in the power system, and construct a typhoon wind field model based on the key typhoon information to obtain the encountered wind speed at any point in the power system;

[0008] The failure rate of the transmission line section and the tower under a certain wind speed is calculated according to the encountered wind speed, thereby calculating the failure probability of the transmission branch within a certain period of time;

[0009] A fault line set is determined according to the fault probability of each transmission branch, and the expected load shedding amount of the power system is calculated according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

[0010] Optionally, obtaining key typhoon information in the power system, and constructing a typhoon wind field model according to the key typhoon information to obtain the encountered wind speed at any point in the power system, includes:

[0011] Acquire key information of typhoon in the power system, and calculate the central symmetric wind field of the typhoon and the migratory wind field of the typhoon center according to the key information of the typhoon;

[0012] The central symmetric wind field and the migratory wind field are superimposed to obtain a wind field model of the Typhoon Jericho model, which is used to obtain the encountered wind speed at any point in the power system.

[0013] Optionally, the calculating of the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, thereby calculating the failure probability of the transmission branch within a certain period of time, includes:

[0014] Calculate, according to the encountered wind speed, a first cumulative failure probability of a certain transmission line section of a certain transmission branch within the typhoon impact time, and a second cumulative failure probability of a certain transmission tower of a certain transmission branch within the typhoon impact time in the power system;

[0015] Based on a calculation method for the failure probability of a series model in reliability assessment theory, the failure probability of the transmission branch within a certain period of time is calculated according to the first cumulative failure probability and the second cumulative failure probability.

[0016] Optionally, determining a fault line set according to the fault probability of each transmission branch, and calculating an expected load shedding amount of the power system according to the fault line set for analyzing the impact of typhoon disasters on the operation of the power system, includes:

[0017] Assuming that the faults between the transmission branches are independent of each other, the combined fault probability of several transmission branches is determined according to the fault probability of each transmission branch, and the combined fault probability that meets the preset threshold is screened out from the combined fault probabilities using the Ni criterion, so that the transmission branch combination corresponding to the screened combined fault probability is taken as the fault line set;

[0018] Based on the state enumeration method, the expected load shedding amount of the power system is calculated according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

[0019] Optionally, the calculation expression of the wind field model is:

[0020] when hour:

[0021] ;

[0022] ;

[0023] when hour:

[0024] ;

[0025] ;

[0026] In the formula, is the maximum wind speed radius, is the typhoon velocity component in the x direction at a distance r from the typhoon center, is the typhoon velocity component in the y direction at a distance r from the typhoon center, , are the two components of the typhoon center migration speed in the x and y directions, , are the two coordinate values ​​of the typhoon center in the x and y directions, respectively; x and y are the two coordinate values ​​of the typhoon center at a distance r from the typhoon center in the x and y directions, respectively. It is the typhoon inflow corner.

[0027] Optionally, the calculation expression of the failure probability is:

[0028] ;

[0029] Where L is the number of transmission line sections included in the m-th transmission branch; K is the number of transmission towers included in the m-th transmission branch. is the second cumulative failure probability, is the first cumulative failure probability.

[0030] Optionally, the calculation expression of the expected load shedding amount is:

[0031] ;

[0032] Where n is the number of elements in the fault line set, P i is the probability of the occurrence of the i-th fault condition, is the maximum value of the load supplied by the power system during normal operation. is the maximum value of the power system load supply that meets the power flow constraints under the i-th fault condition.

[0033] A second aspect of the present application provides a system for analyzing the impact of typhoon disasters on power system operation, the system comprising:

[0034] A first calculation unit is used to obtain typhoon key information in the power system, and to construct a typhoon wind field model according to the typhoon key information to obtain the encountered wind speed at any point in the power system;

[0035] A second calculation unit is used to calculate the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, so as to calculate the failure probability of the transmission branch within a certain time;

[0036] The third calculation unit is used to determine the fault line set according to the fault probability of each transmission branch, and calculate the expected load shedding amount of the power system according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

[0037] In a third aspect, the present application provides a device for analyzing the impact of typhoon disasters on power system operation, the device comprising a processor and a memory:

[0038] The memory is used to store program code and transmit the program code to the processor;

[0039] The processor is used to execute the steps of the method for analyzing the impact of typhoon disasters on power system operation as described in the first aspect according to the instructions in the program code.

[0040] A fourth aspect of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium is used to store program code, and the program code is used to execute the analysis method of the impact of typhoon disasters on power system operation described in the first aspect above.

[0041] It can be seen from the above technical solutions that this application has the following advantages:

[0042] The present application provides an analysis method for the impact of typhoon disasters on the operation of power systems. The key information data of typhoon disasters are obtained through the meteorological station. The wind field model of typhoon disasters is established according to the Typhoon Jessler model, so as to obtain the typhoon encounter wind speed at any point in the power system; according to the transmission branch vulnerability model, the transmission branch of the power system is composed of multiple transmission line segments and multiple transmission towers. Any failure of a transmission line segment or tower due to a typhoon disaster will cause the failure of the entire transmission branch, and the failure probability of each transmission branch of the power system is calculated; the fault line set of the power system is screened out according to the Ni criterion, and then the expected load shedding of the power system is calculated by the state enumeration method as a risk indicator. The results obtained by this method can quantitatively compare the impact of typhoon disasters on the operation of the power system, and can provide a reference for the subsequent network reconstruction, scheduling and other operations of the power system in response to typhoon disasters. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1A schematic flow chart of a method for analyzing the impact of typhoon disasters on power system operation provided in an embodiment of the present application;

[0044] Figure 2 A schematic diagram of an IEEE14 standard node system provided in an embodiment of the present application;

[0045] Figure 3 A typhoon wind field diagram with r<R0 obtained by simulation provided in an embodiment of the present application;

[0046] Figure 4 A typhoon wind field diagram with r>R0 obtained by simulation provided in an embodiment of the present application;

[0047] Figure 5 The failure probability of each branch of the IEEE14-node system provided in the embodiment of the present application;

[0048] Figure 6 After the bus9-bus10 and bus10-bus11 provided in the embodiment of the present application fail, an electrical island appears in the IEEE14-node system;

[0049] Figure 7 A system for analyzing the impact of typhoon disasters on power system operation is provided in an embodiment of the present application. DETAILED DESCRIPTION

[0050] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0051] See also Figure 1 , a method for analyzing the impact of typhoon disasters on power system operation provided in an embodiment of the present application includes:

[0052] Step 101: Acquire key information of typhoons in the power system, and construct a typhoon wind field model based on the key information of typhoons to obtain the encountered wind speed at any point in the power system.

[0053] It should be noted that key information such as the longitude and latitude of the typhoon center, maximum wind speed, typhoon center air pressure, typhoon moving speed, and moving direction of the typhoon disaster is obtained through the meteorological station and used to model the wind field of the typhoon disaster; thereby obtaining the typhoon encounter wind speed at any point in the power system.

[0054] Step 102: Calculate the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, thereby calculating the failure probability of the transmission branch within a certain period of time.

[0055] It should be noted that each transmission branch of the power system is composed of multiple transmission line sections and multiple transmission towers. Any failure of a transmission line section or transmission tower will cause a failure of the transmission branch. The failure rate of the transmission line section and tower at a certain wind speed is calculated based on the encountered wind speed, and then the failure probability of the transmission branch within a certain period of time is calculated.

[0056] Step 103: determine the fault line set according to the fault probability of each transmission branch, and calculate the expected load shedding amount of the power system according to the fault line set, so as to analyze the impact of the typhoon disaster on the operation of the power system.

[0057] It should be noted that, according to the fault line set of the power system obtained in step 102, one element in the fault line set corresponds to a fault scenario; then, the risk indicators such as the expected load shedding of the power system are calculated, so that the impact of typhoon disasters on the operation of the power system can be quantitatively compared, and at the same time, a reference can be provided for the subsequent network reconstruction, dispatching and other operations of the power system in response to typhoon disasters.

[0058] In one embodiment, step 101 includes:

[0059] Obtain key typhoon information in the power system, and calculate the central symmetric wind field of the typhoon and the migratory wind field of the typhoon center based on the key typhoon information;

[0060] The central symmetric wind field and the migrating wind field are superimposed to obtain the wind field model of the Typhoon Jericho model, which is used to obtain the encountered wind speed at any point in the power system.

[0061] It should be noted that typhoon disasters have a bad impact on the safe and stable operation of the power system. Major power outages caused by typhoons have occurred all over the world, causing serious economic losses. Typhoon wind speeds usually expand rapidly from the center to the outside, and then decrease sharply with the increase of radial distance. The maximum wind speed radius generally ranges from tens of kilometers. In order to accurately describe the typhoon's wind speed value, direction, wind vector distribution and other information, as well as the impact of typhoon disasters on the power system, it is necessary to use a typhoon wind field model to model typhoon disasters. This application uses the Typhoon Jessler model to simulate typhoon disasters and obtain the magnitude of wind speeds at various locations within the range of influence of the typhoon disaster.

[0062] The simulation of the typhoon wind field by the Typhoon Jessen model is divided into two steps: first, the central symmetric wind field of the typhoon is calculated according to a certain relationship, and then the migratory wind field of the typhoon center is superimposed to obtain the actual wind speed of each point within the affected range.

[0063] The Typhoon Model assumes that the distribution of the symmetrical wind field in the center of the typhoon has a certain regularity. The tangential wind speed of the typhoon circulation is calculated using the known maximum wind speed and maximum wind speed radius of the typhoon. The formula is as follows:

[0064] (1)

[0065] In the formula, is the tangential wind speed of the typhoon circulation at a distance r from the typhoon center, is the maximum wind speed, is the maximum wind speed radius.

[0066] The transition wind field of the Typhoon Jericho model is calculated using the following formula:

[0067] (2)

[0068] In the formula, is the typhoon moving speed at a distance r from the typhoon center, is the moving speed of the typhoon center.

[0069] The determination of the maximum wind speed radius is relatively complex. In actual calculations, it is usually taken as a constant. For typhoons with level 7 wind circle data, the radius of the level 7 wind circle can be selected. As the value of the maximum wind speed radius. For typhoons with missing seventh-level wind circle data, the maximum wind speed radius is calculated using the empirical relationship:

[0070] (3)

[0071] In the formula, is an empirical constant, usually between 30 and 60. Represents the central air pressure of a typhoon.

[0072] The tangential wind speed of the typhoon circulation and migration speed By superposition, we can get the wind field velocity calculation formula of the Typhoon Jericho model, as follows:

[0073] when hour:

[0074] (4)

[0075] (5)

[0076] when hour:

[0077] (6)

[0078] (7)

[0079] In the formula, is the typhoon velocity component in the x direction at a distance r from the typhoon center, is the typhoon velocity component in the y direction at a distance r from the typhoon center, , are the two components of the typhoon center's migration speed in the x and y directions, , are the two coordinate values ​​of the typhoon center in the x and y directions, respectively; x and y are the two coordinate values ​​of the typhoon center at a distance r from the typhoon center in the x and y directions, It is the typhoon inflow corner.

[0080] In one embodiment, step 102 includes:

[0081] According to the encountered wind speed, the first cumulative failure probability of a certain transmission line section of a certain transmission branch in the power system during the typhoon impact time and the second cumulative failure probability of a certain transmission tower of a certain transmission branch during the typhoon impact time are calculated;

[0082] Based on the calculation method of the failure probability of the series model in the reliability assessment theory, the failure probability of the transmission branch within a certain period of time is calculated according to the first cumulative failure probability and the second cumulative failure probability.

[0083] It should be noted that the transmission branch of the power system consists of multiple transmission line segments and multiple towers. Typhoon disasters may cause mechanical or electrical failures in the transmission line segments and towers, causing the transmission branch to stop operating, and may even cause regional or large-scale power outages. For the convenience of calculation, this application assumes that the wind speed of the transmission line segment connected between every two transmission towers is the same, and the total typhoon duration T w Divided into T time intervals, the interval length , the wind speed remains constant in each time interval. The failure rate of the transmission line segment of the power system in the tth time interval can be calculated by the following formula:

[0084] (8)

[0085] In the formula, v m,l (t) represents the typhoon wind speed borne by the lth transmission line section of the mth transmission branch in the tth time interval; v d,line Indicates the design wind speed of the transmission line section, which is 30m / s in this application; Indicates the length of the transmission line section in km.

[0086] Since the typhoon wind speed remains constant within the length range of each transmission line segment and the selected typhoon impact time interval, the failure rate of a single transmission line segment remains constant. At this time, the lth transmission line segment of the mth transmission branch has a typhoon impact time T w The cumulative failure probability within can be calculated by the following formula:

[0087] (9)

[0088] Similarly, the kth transmission tower of the mth transmission branch has the same w The failure rate in the tth time interval can be calculated as follows:

[0089] (10)

[0090] In the formula, v m,k (t) represents the typhoon wind speed borne by the kth transmission tower of the mth transmission branch in the tth time interval; is the model coefficient, the value range is 0~0.4, and this application takes 0.2; v d,tower It represents the design wind speed of the transmission tower, which can be determined based on destructive tests. In this application, 35m / s is taken.

[0091] Correspondingly, the kth transmission tower of the mth transmission branch is w The cumulative failure probability within is expressed as:

[0092] (11)

[0093] Since the distance between nodes of the transmission network is generally long, the transmission branch usually crosses multiple areas with different typhoon intensities. From a mathematical point of view, the transmission branch can be regarded as a series model consisting of multiple transmission line segments and multiple transmission towers. According to the calculation method of the failure probability of the series model in the reliability assessment theory, it is assumed that the failures between each transmission line segment and tower are independent of each other. The failure of any transmission line segment or tower will lead to the interruption of power transmission of the entire transmission branch. Therefore, the failure probability of the mth transmission branch can be calculated by the following formula:

[0094] (12)

[0095] Wherein, L represents the number of transmission line sections included in the m-th transmission branch; K represents the number of transmission towers included in the m-th transmission branch.

[0096] In one embodiment, step 103 includes:

[0097] Assuming that the faults between the transmission branches are independent of each other, the combined fault probability of several transmission branches is determined according to the fault probability of each transmission branch, and the combined fault probability that meets the preset threshold is screened out from each combined fault probability using the Ni criterion, so that the transmission branch combination corresponding to the screened combined fault probability is taken as the fault line set;

[0098] Based on the state enumeration method, the expected load shedding of the power system is calculated according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

[0099] It should be noted that the Ni criterion, also known as the single fault safety test rule, is a technical requirement proposed from the perspective of safe operation of the power grid. If any component (such as lines, generators, transformers, DC single poles, etc.) in the power system under normal operation is fault-free or disconnected due to a fault, the power system should be able to maintain stable operation and normal power supply, other components are not overloaded, and the voltage and frequency are within the allowable range.

[0100] It should be noted that based on the Typhoon Jericho model and the transmission branch vulnerability model, the failure probability of each transmission branch can be obtained. In this application, it is assumed that the failures between the transmission branches are independent of each other, so that the probability of branch combination failure (multiple branches failing at the same time) can be obtained, as follows:

[0101] (13)

[0102] In the formula, express The probability that these j branches fail at the same time and the remaining branches are not faulty; P j represents the probability of failure of branch j; represents the probability that the j+1th branch operates normally; N is the total number of transmission branches.

[0103] Since the power system planning is carried out through N-1 test, a single branch failure will not affect the power supply of the power system load. The criterion selects the fault line set of the power system, as shown in the following formula:

[0104] (14)

[0105] In the formula, is a preset threshold, and N is the total number of transmission branches in the power system.

[0106] When the branch combination failure probability satisfies formula (14), it is considered that The combination of these j branches is an element in the fault line set of the power system. Each element in the fault line set corresponds to a situation where a power system failure occurs. Finally, the expected load shedding amount and other risk indicators of the power system can be obtained through the state enumeration method, as shown below:

[0107] (15)

[0108] Where n is the number of elements in the fault line set; P i is the probability of the i-th fault condition occurring; It is the maximum value of the load supplied by the power system during normal operation; It is the maximum value of the power system load supply that meets the power flow constraints under the i-th fault condition.

[0109] It can be calculated by the following model:

[0110] Objective function:

[0111] (16)

[0112] Where n b is the number of nodes in the power system, It represents the load supply value of node k in the case of the i-th fault.

[0113] Constraints:

[0114] 1) Generator output constraints

[0115] (17)

[0116] In the formula, is the output value of generator m under the i-th fault condition; is the output upper limit of generator m; S G is the set of generator nodes.

[0117] 2) Supply load constraints

[0118] (18)

[0119] In the formula, is the maximum value of the load supplied by node k; S N It is a collection of power system nodes.

[0120] 3) Node power balance constraints

[0121] (19)

[0122] In the formula, represents the sum of the lines in the power system that operate normally under the i-th fault condition; kl represents the line directly connected to node k; Indicates the active power flow value flowing through branch kl.

[0123] 4) Branch power flow safety constraints

[0124] (20)

[0125] In the formula, It is the maximum value of active power flow that can flow through branch kl under the i-th fault condition.

[0126] 5) DC power flow constraints

[0127] (twenty one)

[0128] In the formula, x kl is the reactance value of branch kl; , are the phase angle values ​​of nodes k and l in the i-th fault case respectively.

[0129] The present application provides a method for analyzing the impact of typhoon disasters on the operation of power systems. First, the key information data of typhoon disasters is obtained through the meteorological station, and the wind field model of typhoon disasters is established according to the Typhoon Jessler model, so as to obtain the typhoon encounter wind speed at any point of the power system; according to the transmission branch vulnerability model, the transmission branch of the power system is composed of multiple transmission line segments and multiple transmission towers. Any failure of a transmission line segment or tower due to a typhoon disaster will cause the failure of the entire transmission branch, and the failure probability of each transmission branch of the power system is calculated; according to the "Ni" (i≥2) criterion, the fault line set of the power system is screened out, and then the expected load shedding of the power system is calculated by the state enumeration method as a risk indicator. The results obtained by this method can quantify and compare the impact of typhoon disasters on the operation of the power system, and can provide a reference for the subsequent network reconstruction, dispatching and other operations of the power system to deal with typhoon disasters.

[0130] The following is a simulation example provided in the embodiments of the present application:

[0131] In order to verify the effectiveness and feasibility of the analysis method of the impact of typhoon disasters on power system operation provided in this application, a simulation test was carried out on the IEEE14 standard node system:

[0132] The structure of IEEE14-node system is as follows Figure 2 As shown, there are 14 nodes and 20 branches in total. The longitude and latitude coordinates of each node are shown in Table 1. It is assumed that the 20 branches are connected in a straight line, each branch has two transmission towers, the towers are evenly distributed on the transmission branch, and two adjacent towers are connected by a transmission line segment.

[0133] Table 1. Latitude and longitude coordinates of nodes in the IEEE 14-node system

[0134]

[0135] Based on the meteorological information data of Typhoon Hagupit on August 4, 2020, the Typhoon Model was used to simulate a typhoon disaster: the longitude of the typhoon center is 120°E, the latitude is 30°N, and the maximum wind speed is The air pressure at the center of the typhoon is 38m / s. The temperature is 965hPa. The moving speed of Typhoon Hagupit is The wind speed is 20m / s, and the direction is north-northwest. The typhoon inflow angle is obtained according to the latitude. is 18°, the empirical constant The value is 40.

[0136] According to formula (3), the maximum wind speed radius R0=56.25km can be calculated. Figure 3 and Figure 4 The typhoon wind field simulated by the Typhoon Jericho model is plotted, with arrows representing wind speed and direction. Figure 3 This is the typhoon wind field diagram with r<R0. It can be seen that the wind speed in the typhoon wind field increases radially outward from the typhoon center. Figure 4 This is a typhoon wind field map with r>R0. The double circle dots in the figure represent the typhoon center, and the wind field range displayed is 110°E~130°E, 23°N~38°N. It can be seen that the wind speed in the typhoon wind field decreases radially outward from the typhoon center.

[0137] First, the wind speed of each point under the typhoon disaster can be obtained according to the wind field model of Typhoon Jericho. To simplify the calculation, it is assumed that the wind speed of each point on the same transmission line section is equal. Secondly, according to the topological structure of the IEEE14-node system and the longitude and latitude coordinates of each node, the location information of each transmission line section and each tower can be obtained, and only the impact of the typhoon disaster on the transmission line section and tower is considered. According to the Typhoon Jericho model and the transmission branch vulnerability model, the failure probability of each transmission branch within 1 hour under the spatiotemporal influence of the typhoon disaster can be calculated (it is assumed that the impact of the typhoon wind field on the transmission branch remains unchanged within this 1 hour). The results are shown in Tables 2 and Figure 5 shown.

[0138] Table 2. Failure probability of each transmission branch

[0139]

[0140] Set the threshold for branch combination failure =0.03, thus the fault line set of the power system can be obtained, as shown in Table 3.

[0141] Table 3. IEEE 14-node system fault line set

[0142]

[0143] After analysis and calculation, it can be seen that when the fault line set elements include bus9-bus10 and bus10-bus11, the IEEE14-node system will form an electrical island, such as Figure 6 As shown in the figure, the load shedding capacity at this time is 9MW. For other fault conditions, the load shedding capacity of the power system is 0 after flow calculation.

[0144] In summary, the expected load shedding amount of the IEEE 14-bus system is:

[0145]

[0146] This application proposes a method for analyzing the impact of typhoon disasters on the operation of power systems. The risk indicators such as expected load shedding calculated by the method can quantitatively compare the impact of typhoon disasters on the operation of power systems, and can also provide a reference for subsequent network reconstruction, scheduling and other operations of the power system in response to typhoon disasters.

[0147] The above is a method for analyzing the impact of typhoon disasters on the operation of the power system provided in an embodiment of the present application, and the following is a system for analyzing the impact of typhoon disasters on the operation of the power system provided in an embodiment of the present application.

[0148] See also Figure 7 , a system for analyzing the impact of typhoon disasters on power system operation provided in an embodiment of the present application includes:

[0149] The first calculation unit 201 is used to obtain typhoon key information in the power system, build a typhoon wind field model according to the typhoon key information, and obtain the encountered wind speed at any point in the power system.

[0150] The second calculation unit 202 is used to calculate the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, so as to calculate the failure probability of the transmission branch within a certain time.

[0151] The third calculation unit 203 is used to determine the fault line set according to the fault probability of each transmission branch, and calculate the expected load shedding amount of the power system according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

[0152] Furthermore, an analysis device for the impact of typhoon disasters on power system operation is also provided in an embodiment of the present application, the device comprising a processor and a memory:

[0153] The memory is used to store program code and transmit the program code to the processor;

[0154] The processor is used to execute the steps of the method for analyzing the impact of typhoon disasters on the operation of the power system as described in the above method embodiment according to the instructions in the program code.

[0155] Furthermore, a computer-readable storage medium is provided in an embodiment of the present application, and the computer-readable storage medium is used to store program code, and the program code is used to execute the analysis method of the impact of typhoon disasters on the operation of the power system described in the above method embodiment.

[0156] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0157] The terms "first", "second", "third", "fourth", etc. (if any) in the specification of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchangeable where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein, for example. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0158] It should be understood that in this application, "at least one (item)" means one or more, and "plurality" means two or more. "And / or" is used to describe the association relationship of associated objects, indicating that three relationships may exist. For example, "A and / or B" can mean: only A exists, only B exists, and A and B exist at the same time, where A and B can be singular or plural. The character " / " generally indicates that the objects associated before and after are in an "or" relationship. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b or c can mean: a, b, c, "a and b", "a and c", "b and c", or "a and b and c", where a, b, c can be single or multiple.

[0159] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be an indirect coupling or communication connection through some interfaces, devices or units, which can be electrical, mechanical or other forms.

[0160] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0161] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0162] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application is essentially or the part that contributes to the prior art or all or part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (full name in English: Read-Only Memory, English abbreviation: ROM), random access memory (full name in English: Random Access Memory, English abbreviation: RAM), disk or optical disk and other media that can store program codes.

[0163] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.

Claims

1. A method for analyzing the impact of typhoon disasters on power system operation, characterized in that: include: Acquire key typhoon information in the power system, and construct a typhoon wind field model based on the key typhoon information to obtain the encountered wind speed at any point in the power system; The failure rate of the transmission line section and the tower under a certain wind speed is calculated according to the encountered wind speed, thereby calculating the failure probability of the transmission branch within a certain period of time; A fault line set is determined according to the fault probability of each transmission branch, and the expected load shedding amount of the power system is calculated according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

2. The method for analyzing the impact of typhoon disasters on power system operation according to claim 1, characterized in that: Obtaining key information of typhoons in the power system, and constructing a typhoon wind field model based on the key information of typhoons to obtain the encountered wind speed at any point in the power system, including: Acquire key information of typhoon in the power system, and calculate the central symmetric wind field of the typhoon and the migratory wind field of the typhoon center according to the key information of the typhoon; The central symmetrical wind field and the migratory wind field are superimposed to obtain a wind field model of the Typhoon Jericho model, which is used to obtain the encountered wind speed at any point in the power system.

3. The method for analyzing the impact of typhoon disasters on power system operation according to claim 1, characterized in that: The method of calculating the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, thereby calculating the failure probability of the transmission branch within a certain period of time, includes: Calculate, according to the encountered wind speed, a first cumulative failure probability of a certain transmission line section of a certain transmission branch within the typhoon impact time, and a second cumulative failure probability of a certain transmission tower of a certain transmission branch within the typhoon impact time in the power system; Based on a calculation method for the failure probability of a series model in reliability assessment theory, the failure probability of the transmission branch within a certain period of time is calculated according to the first cumulative failure probability and the second cumulative failure probability.

4. The method for analyzing the impact of typhoon disasters on power system operation according to claim 1, characterized in that: Determining a fault line set according to the fault probability of each transmission branch, and calculating the expected load shedding amount of the power system according to the fault line set for analyzing the impact of typhoon disasters on the operation of the power system, includes: Assuming that the faults between the transmission branches are independent of each other, the combined fault probability of several transmission branches is determined according to the fault probability of each transmission branch, and the combined fault probability that meets the preset threshold is screened out from the combined fault probabilities using the Ni criterion, so that the transmission branch combination corresponding to the screened combined fault probability is taken as the fault line set; Based on the state enumeration method, the expected load shedding amount of the power system is calculated according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

5. The method for analyzing the impact of typhoon disasters on power system operation according to claim 2, characterized in that: The calculation expression of the wind field model is: when hour: ; ; when hour: ; ; In the formula, is the maximum wind speed radius, is the typhoon velocity component in the x direction at a distance r from the typhoon center, is the typhoon velocity component in the y direction at a distance r from the typhoon center, , are the two components of the typhoon center migration speed in the x and y directions, , are the two coordinate values ​​of the typhoon center in the x and y directions, respectively; x and y are the two coordinate values ​​of the typhoon center at a distance r from the typhoon center in the x and y directions, respectively. It is the typhoon inflow corner.

6. The method for analyzing the impact of typhoon disasters on power system operation according to claim 3, characterized in that: The calculation expression of the failure probability is: ; Where L is the number of transmission line sections included in the m-th transmission branch; K is the number of transmission towers included in the m-th transmission branch. is the second cumulative failure probability, is the first cumulative failure probability.

7. The method for analyzing the impact of typhoon disasters on power system operation according to claim 4, characterized in that: The calculation expression of the expected load shedding amount is: ; Where n is the number of elements in the fault line set, P i is the probability of the occurrence of the i-th fault condition, is the maximum value of the load supplied by the power system during normal operation. is the maximum value of the power system load supply that meets the power flow constraints under the i-th fault condition.

8. An analysis system for the impact of typhoon disasters on power system operation, characterized in that: include: A first calculation unit is used to obtain typhoon key information in the power system, and to construct a typhoon wind field model according to the typhoon key information to obtain the encountered wind speed at any point in the power system; A second calculation unit is used to calculate the failure rate of the transmission line section and the tower at a certain wind speed according to the encountered wind speed, so as to calculate the failure probability of the transmission branch within a certain time; The third calculation unit is used to determine the fault line set according to the fault probability of each transmission branch, and calculate the expected load shedding amount of the power system according to the fault line set, which is used to analyze the impact of typhoon disasters on the operation of the power system.

9. An analysis device for the impact of typhoon disasters on power system operation, characterized in that: The device comprises a processor and a memory: The memory is used to store program code and transmit the program code to the processor; The processor is used to execute the analysis method of the impact of typhoon disasters on power system operation as described in any one of claims 1-7 according to the instructions in the program code.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium is used to store program codes, and the program codes are used to execute the method for analyzing the impact of typhoon disasters on power system operation as described in any one of claims 1-7.