Method for generating optimal temporary construction project design scheme based on comparison and selection
Through the weight and score comparison method, a temporary construction project design plan is generated, which solves the complex design and difficult decision-making problems of temporary construction project design, and achieves a more scientific and efficient design plan selection, reducing project costs.
Patent Information
- Application Number
- CN202411202504.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-12-17
AI Technical Summary
The design plan of temporary construction projects is complex and lacks visual scientific basis, which leads to a long time and high cost in the construction plan. The selected plan is often not the preferred plan, which increases the time and economic cost of the project.
A weight-based and scoring comparison method is adopted, and results are solicited through preset categories, and global and sub-item quality control is carried out. Combined with the comprehensive scoring model, a temporary construction engineering design plan database is generated, and a design plan with the highest final weight value is selected as the output.
It realizes that according to the specific requirements of the project to be designed, the appropriate preferred temporary construction engineering design plan is output, and comprehensively considers safety, feasibility, economy and legal compliance, improving the scientificity and efficiency of the design plan.
Smart Images

Figure CN119148879A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of engineering design and construction, and in particular to a method for generating an optimal temporary construction engineering design scheme based on comparison and selection. Background Art
[0002] Temporary construction projects refer to non-permanent buildings, structures and other facilities used for office, living and production that serve the construction project and are built or demolished as the construction project progresses. These facilities are built to meet temporary needs during the construction process. The design plan of temporary construction projects has a vital impact on the construction project and is of great significance to the smooth progress of the construction project. Therefore, there are high requirements for the design plan decision-making of temporary construction projects.
[0003] However, the design plan of temporary construction projects is complex and needs to consider the influence of many factors. Moreover, for the construction of the same project, the construction plan of the temporary construction project is not unique. In the current mature fields and construction enterprise groups, the design plan of temporary construction projects is not unified. When construction projects need to make decisions on temporary construction project plans, there are relatively few high-quality plans that can be referred to, which increases the difficulty of making decisions on temporary construction project plans. At present, the design plan for temporary construction projects usually requires relevant engineering personnel to make decisions, relying on the experience and judgment of construction personnel. It often takes a long time to decide on a temporary construction project construction plan and lacks a visual scientific basis. In addition, the selected temporary construction project construction plan is often not the best, which increases the time and economic costs of the overall project. Summary of the invention
[0004] The purpose of the present invention is to output a temporary construction engineering design scheme that meets the optimization standard based on weight and score comparison, output a temporary construction engineering design scheme suitable for the project to be designed, and provide a method for generating an optimal temporary construction engineering design scheme based on comparison.
[0005] The present invention provides a method for generating an optimal temporary construction engineering design scheme based on comparison and selection, comprising the following steps:
[0006] S1: Collect results through preset solicitation categories, randomly select three categories to solicit from mature fields or enterprises, so that the collected results cover the six categories and obtain temporary construction project design results;
[0007] S2: Perform a global quality control check on the temporary construction project design results obtained in S1, perform an overall score on the temporary construction project design results, screen out the excellent overall results, and then perform sub-item quality control on the overall results to screen out the excellent results
[0008] S3: Input the excellent results into the database, rank and score them in combination with the pre-constructed comprehensive scoring model, and generate a temporary construction project design results database;
[0009] S4: According to the project to be designed, the preferred results are selected from the temporary construction project design results database, and the final weight value of the preferred results is obtained by establishing a matrix. Combined with the ranking score in S3, the final weight value is calculated, and the temporary construction project design plan with the highest final weight value is selected as the output, and the optimal construction plan is output.
[0010] The mature fields or related enterprises mentioned refer to the engineering construction fields and engineering construction enterprises.
[0011] The excellent level refers to the quality level of the preferred solution judged by experts in combination with construction standards.
[0012] Preferably, in step S1, the temporary construction project design results are obtained, and the temporary construction project design results include six categories: project manager's residence, concrete mixing station, T-beam prefabrication yard or railway box beam prefabrication yard, steel bar intelligent processing plant, small component prefabrication yard or pipe segment prefabrication yard, and sand and gravel self-mining processing plant.
[0013] Preferably, step S1 obtains temporary construction project design results, and the collection directions of the temporary construction project design results are randomly selected from three of the six categories, and then collectors in mature fields or related enterprises are allowed to choose from them, so that the collected results cover the six categories as the temporary construction project design results obtained in S1.
[0014] Preferably, step S2 performs a global quality control check on the temporary construction project design results obtained in S1, and the review experts perform an overall score on the temporary construction project design results obtained in S1 according to the construction standards, and screen out the overall results of excellent level.
[0015] The construction standards mentioned above refer to the standards promulgated by the state, including JGJT 188-2009 Technical Code for Temporary Buildings at Construction Sites, GB50720-2011 Technical Code for Fire Safety at Construction Sites of Construction Projects, JGJ 146-2013 Environmental and Sanitation Standards for Construction Projects, JGJT 435-2018 Technical Standards for Modular Facilities at Construction Sites, and standard documents for the formulation of temporary construction project plans within the enterprise.
[0016] Preferably, step S2 performs sub-item quality control on the overall results, and the review experts perform sub-item quality control on the overall results according to the construction standards. The review experts perform sub-item quality control on the overall results according to the construction standards. The categories of sub-item quality control include spatial layout, plane layout, functional division, reasonable process flow, reasonable general layout, sufficient and appropriate site selection basis, accurate and appropriate estimated engineering quantity, reasonable estimated unit cost, appropriate and reasonable estimated total price, and no major omissions or errors. According to the results of sub-item quality control, excellent results are screened out.
[0017] Preferably, in step S3, the excellent-level achievements are ranked and scored in combination with a comprehensive scoring model, and the influencing factors of the comprehensive scoring model are construction period, quality, cost, and safety. The influencing factors of each excellent-level achievement are scored in an arithmetic descending order according to the ranking, and the score range is 100 to 80 points. Assuming that there are N excellent-level achievements, according to the ranking, the influencing factor of the first achievement is 100 points, and the difference in the scores of the influencing factors of subsequent achievements is (100-80) / (N-1). As the number N of excellent-level achievements increases, the ranking score is automatically adjusted, and the excellent-level achievements and the ranking score are input into the temporary construction project design achievement database.
[0018] Preferably, step S4 specifically includes the following steps:
[0019] Establish a selection decision matrix, with i as the vertical direction of the decision matrix, j as the horizontal direction of the decision matrix, and a as the influencing factor of the project to be designed. The influencing factors of the project to be designed should include construction period, quality, cost, and safety. If the project to be designed has special requirements, the influencing factors of the project to be designed can be increased or adjusted, and the influencing factors of the project to be designed are used as the horizontal index a of the decision matrix. i and longitudinal indicators and a j , a ij and a ji The specific weight value of the influencing factors of the project to be designed on the project to be designed is determined by the project personnel. i and a j If the impact on the project to be designed is the same, a ij =1, when a i Than a j When the impact is important ij >1,a ji The calculation formula is:
[0020]
[0021] According to the above a ij and a ji Establish a decision matrix, sum each column of the decision matrix to obtain the sum value of each column, normalize the decision matrix, and its matrix element is the single item value of each column divided by the corresponding sum value of each column to obtain a normalized decision matrix, sum each row of the normalized decision matrix to obtain the final weight value of the influencing factors of the project to be designed on the project to be designed;
[0022] S43: Take the final weight value as the full score, use the comprehensive scoring model to score the preferred results respectively, multiply the ranking score obtained in step S3 by the final weight value, if the project to be designed has special requirements, and the influencing factors of the project to be designed are added or adjusted, then return to step S3 to again rank and score the excellent results in combination with the comprehensive scoring model, wherein the influencing factors of the comprehensive scoring model are the influencing factors of the project to be designed. After obtaining the ranking score, add the result obtained by multiplying it with the final weight value to obtain the final score, and the preferred result corresponding to the highest score in the final score is the optimal construction plan to be selected.
[0023] Compared with the prior art, the present invention has the following beneficial effects:
[0024] 1. The present invention provides a method for generating an optimal temporary construction engineering design scheme based on comparison, which selects six categories to collect results, randomly selects three categories to collect results from mature fields or enterprises, so that the collected results cover the six categories, and can output an optimal temporary construction engineering design scheme;
[0025] 2. The present invention provides a method for generating an optimal temporary construction engineering design scheme based on comparison and selection, by screening out the results of the excellent level, establishing a database of temporary construction project design results, and being able to compare and select the temporary construction engineering design scheme that meets the optimization standard;
[0026] 3. The present invention provides a method for generating an optimal temporary construction engineering design scheme based on comparison. According to the project to be designed, the temporary construction engineering design scheme with the highest final weight value is selected as the output. Safety, feasibility, economy, environmental impact, applicability and legal compliance are comprehensively considered, and a temporary construction engineering design scheme that meets the optimization standards and is suitable for the project to be designed can be output. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 The present invention is a flow chart of a method for generating an optimal temporary construction engineering design scheme based on comparison.
[0028] Figure 2 This is an example diagram of a decision matrix.
[0029] Figure 3 An example diagram of a decision matrix with the columns summed.
[0030] Figure 4 This is an example diagram of the normalized decision matrix.
[0031] Figure 5 An example of a matrix diagram for obtaining the final weight values. DETAILED DESCRIPTION
[0032] The present invention is further described in detail below in conjunction with test examples and specific implementation methods. However, this should not be understood as the scope of the above subject matter of the present invention being limited to the following embodiments, and all technologies realized based on the content of the present invention belong to the scope of the present invention.
[0033] Example 1
[0034] A method for generating optimal temporary construction engineering design scheme based on comparison and selection, the flow chart is as follows Figure 1 As shown, the following steps are included:
[0035] S1: Select six categories to collect results, randomly select three categories to collect from mature fields or enterprises, so that the collected results cover the six categories, and obtain the design results of temporary construction projects.
[0036] In an optional implementation, step S1 randomly selects three collection categories from six categories, including project manager residence, concrete mixing station, T-beam prefabrication yard or railway box girder prefabrication yard, steel bar intelligent processing plant, small component prefabrication yard or pipe segment prefabrication yard, and sand and gravel self-mining processing plant, and collects temporary construction project design plans in mature fields or enterprises to ensure that the collected samples cover all six categories. In this embodiment, the collected temporary construction project design results include 40 project manager residences, 35 concrete mixing stations, 35 T-beam prefabrication yards or railway box girder prefabrication yards, 40 steel bar intelligent processing plants, 30 small component prefabrication yards or pipe segment prefabrication yards, and 20 sand and gravel self-mining processing plants.
[0037] S2: The review experts conduct a global quality control check on the temporary construction project design results obtained in S1, give an overall score to the temporary construction project design results, screen out the overall results with excellent levels, and then perform sub-item quality control on the overall results to screen out the results with excellent levels. In this embodiment, the review experts score 200 temporary construction project design results with reference to the construction standards, and then perform sub-item quality control on them, and select excellent samples to input into the temporary construction project design results database.
[0038] S3: Input the excellent results into the database, rank and score them in combination with the comprehensive scoring model, and generate a temporary construction project design results database.
[0039] For reference, the following are construction standards that can be used as references for preferred scoring. The corresponding regulations and standards mentioned therein are specified by the project to be designed, or are well-known regulations and standards.
[0040] 1. The construction standards for project manager's residence that can be used as reference for selection and scoring are as follows:
[0041] 1. Main door: automatic retractable door, door width: 6m~8m; three columns are recommended: 0.8mx0.8m; separate passages for pedestrians and vehicles, vermilion facing bricks.
[0042] 2. Site hardening: C20 concrete, 10cm thick. Hardening planning should be combined with the layout of roads and parking spaces, with a hardening thickness of 20cm for driveways and parking spaces; permeable bricks can be used for parking spaces, and the rest should be greened. The ring beam of the house is 30cm*30cm, and 5cm is hardened inside the house.
[0043] 3. Fence: Brick or iron fence or color steel plate enclosure; Brick fence: 12cm thick, 1.8m high, 50cmx50cm wall columns every 4m, 50cmx50cm brick foundation; Iron fence: 1.8m high iron fence; Color steel plate enclosure: according to municipal construction standards. If the local government or construction unit has requirements, they should be followed.
[0044] 4. Flagpole: Brick-built, dimensions: 4.5m (length) 0.6m (top) ~ 0.9m (bottom) width, 0.5m high; 3 stainless steel pipe flagpoles with diameters of 80 to 170mm and thickness, with a spacing of 1.5m, and heights of 8.5m, 9m, and 8.5m respectively.
[0045] 5. Office space for project manager and party committee secretary: S≤20m 2 / person, office room standard: color steel plate, floor height ≤3m, floor hardened with C20 concrete, thickness 5cm, can be paved with economical and practical tiles; gypsum board ceiling. The foundation of the board room is cast with C20 concrete, the cross section is 30cm (width) x 20cm (height), and the area of each board room is about 24m 2 .
[0046] 6. Office space for deputy project leaders: S≤10m 2 / person, other standards are the same as the office space in the project.
[0047] 7. Office space for management personnel: S≤20m 2 / room; 5-8 persons S≤40m 2 / room; 9 persons or more S≤60m 2 / room. S≤6m 2 / person, applicable to comprehensive office area, other standards are the same as project office rooms.
[0048] 8. Dormitory for project manager, secretary and deputy: S≤20m 2 / person, other standards are the same as the office space in the project.
[0049] 9. Dormitory for management staff: S≤10m 2 / person, other standards are the same as the office space in the project.
[0050] 10. Meeting room: S≤140m 2, 1 room, based on 80 participants; applicable to the company's management department (command center, including deputy bureau command); S≤100m 2 , 1 room, based on 40 participants, applicable to project divisions, authorized project management departments, and subsidiary self-managed project departments; S≤60m 2 , 1 room, assuming 20 participants, suitable for project operation teams; S≤20m 2 , 1 small meeting room, which can be set up by project departments at all levels; economical and practical tiles can be laid; gypsum board ceiling.
[0051] 11. Resident guesthouse: S≤20m 2 / room, depending on the project needs, 2 to 3 rooms can be set up, the floor is consistent with the office room, and it is equipped with necessary living facilities. Other standards are the same as the project office room.
[0052] 12. Kitchen and restaurant: Floor height: 3.5-4.0m; kitchen and staff restaurant per capita area S≤2m 2 , total area S≤100m 2 The stove is built with solid bricks, and the walls are white tiles; economical and practical non-slip floor tiles can be laid; the ceiling is made of fire-resistant board.
[0053] 13. Reception restaurant: The reception restaurant area of the company's management department (command center, including the bureau headquarters) is ≤ 40m 2 ; The reception restaurant area of the project branch, authorized project management department, and subsidiary self-managed project department is ≤ 20m 2 ; Other standards are the same as the office space in the project.
[0054] 14. Toilet and bathroom, laundry room and clothes drying shed: set up according to the site conditions, the ground is hardened and paved with non-slip tiles, the bathroom should use integrated board ceiling, and the clothes drying shed should use transparent roof. Other standards are the same as the office room of the project.
[0055] 15. Cultural and sports facilities and employee (civilian) service station: according to the scale of the project department, build a basketball court, table tennis room (gym), activity room according to the principle of adapting measures to local conditions; set up a 20≤S≤40m 2 Activity room; other standards are the same as the office rooms of the project.
[0056] 16. Supervisor’s or owner’s room: set up according to specific contract requirements.
[0057] 17. Drainage ditch: Reasonably arrange brick drainage ditch, the water flow surface around the site is 50cm (width) x 50cm (height), the water flow surface inside the site is 30cm (width) x 30cm (height), and the cover plate is customized. (The structural dimensions are determined by calculation according to the specifications).
[0058] 18. Septic tank and grease trap: Brick septic tank (6m*2m*2m) and grease trap (2m*1m*1m) shall be reasonably arranged according to the number of residents. (The structural dimensions shall be determined by calculation according to the specifications).
[0059] 19. Other facilities: set S≤10m 2 Guard room: information systems such as video surveillance and fire prevention systems can be set up according to actual conditions.
[0060] 2. The construction standards for concrete mixing plants that can be used as reference for optimal scoring are as follows:
[0061] 1. Scale of mixing station: Based on comprehensive consideration of the project volume and construction period, the reference floor area is the floor area of the mixing station * number of units + standard silo area + channel area + spare material yard area.
[0062] 2. Office area: 60m2 prefabricated house 2 .
[0063] 3. Site leveling: The bottom layer is filled with gravel with a thickness not exceeding 20cm.
[0064] 4. Mixing plant foundation: C30 concrete, the size is determined according to the bearing capacity of the foundation.
[0065] 5. Hardening of main roads: The sidewalk is combined with the station road, with a width of not less than 1.5m, and facilities for separating people and vehicles are set up.
[0066] 6. Silo and material yard floor: C20 concrete, thickness not more than 15cm, and set a 2% drainage slope.
[0067] 7. Site floor: C20 concrete, thickness not more than 10cm, surface layer with drainage slope not less than 1.5%.
[0068] 8. Drainage ditch: Brickwork, 30cm (width) x 50 cm (depth), M10 mortar finishing; customized cover.
[0069] 9. Color steel shed for mixing plant and silo: Height: 7m, blue roof and white walls.
[0070] 10. Silo wall: C20 reinforced concrete, Φ8 steel bars, spacing 300x300mm. Thickness not more than 30cm, height not more than 3m.
[0071] 11. Reservoir: Brick 10m (length) x 5m (width) x 2 m (depth).
[0072] 12. Sewage sedimentation tank: brickwork, requirements: five-level sedimentation, reference size: 20m (length) x 3m (width) x 2 m (depth), M10 mortar finishing.
[0073] 13. Car wash trough and sedimentation tank: A wheel washing machine (automatic) is installed on the main road inside the gate, and a three-stage sedimentation tank of 8m (length) x 3m (width) x 2 m (depth) is set up, brick-built, mortar-plastered, covered with steel mesh and railings.
[0074] 14. Weighing scale: Weighing scale shall be set up as needed. The material receiving room shall be a mobile house and the weighing scale foundation shall be set up according to the standard weighing scale drawing requirements.
[0075] 3. The construction standards for railway box girder prefabrication yards that can be used as reference for optimal scoring are as follows:
[0076] 1. Scale: Individually designed according to the design, construction period and scale.
[0077] 2. Office and living area: implemented in accordance with the corresponding standards of the project to be designed.
[0078] 3. Production auxiliary area:
[0079] 3.1. Production area housing:
[0080] 3.1.1. Laboratory: Standard laboratory area.
[0081] 3.1.2. Material room and warehouse: brick-built or prefabricated houses, set up according to actual conditions on site.
[0082] 3.1.3. Tool room: Brick or mobile house, with a special tool room set up for 8 work shifts.
[0083] 3.1.4. Weighing scale room, machining room and steaming room: brick-built or prefabricated house.
[0084] 3.1.5. Production house foundation: C30 concrete, foundation: height not more than 30cm, thickness not more than 30cm.
[0085] 3.1.6. Production room ditch: brickwork, reference size: 30cm (width) x 30 cm (depth), M10 mortar finishing, customized cover: 50cmx50cmx50mm.
[0086] 3.2. Distribution room, transformer and generator room: brick-built.
[0087] 3.3. Sand and gravel yard:
[0088] 3.3.1. Sand and gravel yard scaffolding: single reference size: 20mx25m.
[0089] 3.3.2. Sand and gravel yard enclosure: three sides, height should be 9m.
[0090] 3.3.3. Hardening of gravel yard: C20 concrete, thickness not more than 20cm.
[0091] 3.3.4. Sand and gravel yard partition wall: C20 reinforced concrete, thickness not more than 30cm, average height 2m.
[0092] 3.3.5. Sand and gravel yard ditch: brickwork, reference size: 30cm (width) x 30 cm (depth), M10 mortar finishing, customized cover: 50cmx50cmx20mm.
[0093] 3.4. Mixing station:
[0094] 3.4.1. Mixing plant foundation: C30 concrete, calculated based on the bearing capacity of the foundation.
[0095] 3.4.2. Mixing station foundation cushion layer: crushed stone, sand and gravel, with a thickness not exceeding 30cm.
[0096] 3.4.3. Mixing station shelter: light color steel shelter, single reference size: 25mx4.2m.
[0097] 3.4.4. Water reducing agent shed: brick or mobile board house, for storing water reducing agent barrels 8mx10m.
[0098] 3.4.5. Hardening of mixing station area: full hardening, C20 concrete, thickness not more than 10cm.
[0099] 3.4.6. Mixing station channel: C20 concrete, thickness not more than 20cm. Ballast, rubble or crushed stone filling, thickness not more than 30cm.
[0100] 3.4.7. Mixing station pool: brickwork, reference size: 7m (length) x 3.5m (width) x 3 m (depth), M10 mortar plastering, customized cover.
[0101] 3.4.8. Stone washing area: C20 concrete hardening, brick-built sedimentation tank.
[0102] 3.5. Steel bar storage and processing area:
[0103] 3.5.1.Cushion layer: crushed stone, sand and gravel, thickness not more than 30cm.
[0104] 3.5.2. Hardening of steel bar processing area: C20 concrete, thickness not more than 20cm.
[0105] 3.5.3. Steel bar processing shed: steel structure room and foundation.
[0106] 3.6. Roads within the production auxiliary area:
[0107] 3.6.1. Hardening of the roads within the site: The sidewalks shall be combined with the roads within the site, with a width of not less than 1.5m, and facilities for separating people and vehicles shall be set up.
[0108] 3.6.2. On-site road cushion: ballast, stone or crushed stone filling, thickness not more than 30cm.
[0109] 3.7. Car wash trough: An automatic car wash trough shall be set up at the entrance or exit of the venue.
[0110] 3.8. Sedimentation tank: brick or concrete structure, reference size: 2m (side) x 2m (depth) in front of mixing station, main sedimentation tank 15m (length) x 5m (width) x 3m (depth).
[0111] 3.9. Scale foundation: determined by calculation based on the bearing capacity of the foundation.
[0112] 3.10. Main ditch: brickwork, reference size: 0.8mx1m, M10 mortar finishing, customized cover: 100cmx50cmx50mm.
[0113] 4. Beam making area:
[0114] 4.1. Beam making pedestal:
[0115] 4.1.1. Beam pedestal cap: C30 concrete, the size is determined according to the bearing capacity of the foundation and the beam type.
[0116] 4.1.2. U-shaped cushion beam of beam pedestal: C30 concrete, the size is determined according to the bearing capacity of the foundation and the beam type.
[0117] 4.1.3. Side form support rod foundation: C20 concrete.
[0118] 4.2. Inner formwork assembly frame: C20 concrete.
[0119] 4.3.95t gantry crane: C30 concrete, foundation reference size: 1.2mx2.5m.
[0120] 4.4. Site hardening: C20 concrete, thickness not more than 10cm.
[0121] 4.5. Ditch in beam making area: brickwork, reference size: 40cmx60cm, M10 mortar finishing; customized steel cover: 60cmx50cmx50mm.
[0122] 5. Beam storage area and beam transportation channel:
[0123] 5.1. Beam storage pedestal:
[0124] 5.1.1. Concrete for the pedestal and pad stone of the existing beam pedestal: C30 / C40 concrete, reference size: pedestal 3mx3mx1m, pad stone 0.8mx0.6mx0.6m.
[0125] 5.1.2. Replacement pedestal foundation and pad stone concrete C30 / C40: C30 / C40 concrete, reference size: foundation 3mx3mx1m, pad stone 0.8mx0.6mx1.6m.
[0126] 5.2. Beam transport channel, including beam fabrication channel:
[0127] 5.2.1. Horizontal beam transport channel: C30 concrete, thickness not more than 20cm, width determined by the requirements of the transporter and safety distance.
[0128] 5.2.2. Longitudinal beam transport channel: C30 concrete, thickness not more than 20cm, width determined by the requirements of the transporter and safety distance.
[0129] 5.2.3. Beam transport channel cushion: ballast, stone or crushed stone, with a thickness not exceeding 30cm.
[0130] 6. Beam lifting station, selected according to the on-site bridge access method, generally 200m long:
[0131] 6.1. Foundation cushion layer of the running line of the lifting beam station: ballast, stone or crushed stone filling, with a thickness not exceeding 30cm.
[0132] 6.2. U-shaped foundation of the running line of the lifting beam station: C30 concrete, reference size: width 3m, thickness 35cm, slag retaining walls on both sides 40cm.
[0133] 6.3. Hardening of the lifting beam station area: C20 concrete, thickness not more than 10cm.
[0134] 6.4. Hardening of small parts prefabrication area: C20 concrete, thickness not more than 20cm, hardening of vehicle passage and loading areas.
[0135] 7. Others:
[0136] 7.1. Water supply, maintenance and other pipelines: The main pipes of water supply and maintenance pipelines are 100mm PPR pipes, and the branch pipes are 75mm PPR pipes.
[0137] 7.2. Production area fence: implemented in accordance with relevant fence construction standards.
[0138] 4. T-beam prefabrication site, the construction standards that can be used as reference for optimal scoring are as follows:
[0139] 1. Scale: Individually designed according to the design, construction period and scale.
[0140] 2. Access road: two lanes, implemented in accordance with relevant standards.
[0141] 3. Office and living area: implement according to relevant standards.
[0142] 4. Production auxiliary area:
[0143] 4.1. Production area housing:
[0144] 4.1.1. Laboratory: Standard laboratory area.
[0145] 4.1.2. Material room and warehouse: brick or mobile cabin.
[0146] 4.1.3. Tool room: Brick or mobile house, with a special tool room for 6-8 work shifts.
[0147] 4.1.4. Weighing scale room, machining room and steaming room: brick-built or prefabricated house.
[0148] 4.1.5. Production house foundation: C30 concrete, foundation: height not more than 30cm, thickness not more than 30cm.
[0149] 4.1.6. Production house ditch: brickwork, reference size: 30cm (width) x 30 cm (depth), M10 mortar plastering, customized cover: 50cmx50cmx50mm.
[0150] 4.2. Distribution room, transformer and generator room: brick-built.
[0151] 4.3. Sand and gravel yard:
[0152] 4.3.1. Sand and gravel yard shed: single reference size: 15mx20m.
[0153] 4.3.2. Sand and gravel yard enclosure: three sides, height should be 9m.
[0154] 4.3.3. Treatment of the base layer of the gravel yard: filling with ballast, slabs or crushed stones, with a thickness not exceeding 30cm.
[0155] 4.3.4. Sand and gravel yard partition wall: C20 reinforced concrete, thickness not more than 30cm, average height 2m.
[0156] 4.3.5. Sand and gravel yard ditch: brickwork, reference size: 30cm (width) x 30 cm (depth), M10 mortar finishing, customized cover: 50cmx50cmx20 mm.
[0157] 4.4. Mixing station:
[0158] 4.4.1. Mixing station foundation: C30 concrete, the size is determined according to the bearing capacity of the foundation.
[0159] 4.4.2. Mixing station shelter: light color steel shelter, single reference size: 25mx4.2m.
[0160] 4.4.3. Water reducing agent shed: brick or mobile board house, for storing water reducing agent barrels 8mx10m.
[0161] 4.4.4. Hardening of mixing station area: full hardening, C20 concrete, thickness not more than 20cm.
[0162] 4.4.5. Mixing station channel: C20 concrete, thickness not more than 20cm. Ballast, rubble or crushed stone filling, thickness not more than 30cm.
[0163] 4.4.6. Mixing station pool: brickwork, reference size: 7m (length) x 3.5m (width) x 3 m (depth), M10 mortar plastering, customized cover.
[0164] 4.4.7. Stone washing area: C20 concrete hardening, brick-built sedimentation tank.
[0165] 4.5. Steel bar storage and processing area
[0166] 4.5.1.Cushion layer: crushed stone, sand and gravel, thickness not more than 30cm.
[0167] 4.5.2. Hardening of steel bar processing area: C20 concrete, thickness not more than 20cm.
[0168] 4.5.3. Steel bar processing shed: steel structure room.
[0169] 4.6. Roads within the production auxiliary area:
[0170] 4.6.1. The roads within the site shall be hardened according to the relevant standards. The sidewalks shall be combined with the roads within the site with a width of not less than 1.5m, and facilities for separating people and vehicles shall be set up.
[0171] 4.6.2. On-site road cushion: ballast, stone or crushed stone filling, thickness not more than 30cm.
[0172] 4.7. Car wash trough: An automatic car wash trough shall be set up at the inlet or outlet of the site, and a three-level sedimentation tank shall be set up.
[0173] 4.8. Sedimentation tank: brick or concrete structure, reference size: 2m (side) x 2m (depth) in front of mixing station, main sedimentation tank 15m (length) x 5m (width) x 3m (depth).
[0174] 4.9. Scale foundation: C30 concrete, the size is determined by the bearing capacity of the foundation.
[0175] 4.10. Main ditch: brickwork, reference size: 0.8mx1m, M10 mortar finishing, customized cover: 100cmx50cmx50mm.
[0176] 5. Beam making area:
[0177] 5.1. Beam making pedestal:
[0178] 5.1.1. Beam pedestal: C30 concrete, the size is determined according to the bearing capacity of the foundation and the beam type.
[0179] 5.1.2.16t gantry crane foundation: C30 concrete, foundation reference size: 0.5mx1m.
[0180] 5.2. Site hardening: C20 concrete, thickness not more than 10cm.
[0181] 5.3. Ditch in beam making area: brickwork, reference size: 40cmx60cm, M10 mortar finishing; customized cover plate: 60cmx50cmx50mm.
[0182] 6. Beam storage area and beam transportation channel:
[0183] 6.1. Single-layer beam pedestal: C30 concrete, the size is determined according to the bearing capacity of the foundation.
[0184] 6.2. Beam transport trolley foundation: C30 concrete, the size is determined according to the bearing capacity of the foundation.
[0185] 6.3. Double-layer beam storage pedestal: C30 concrete.
[0186] 6.4.95t gantry crane foundation: C30 concrete, the size is determined by calculation based on the bearing capacity of the foundation.
[0187] 6.5. Site hardening of small parts prefabrication area: C20 concrete, thickness not more than 10cm.
[0188] 6.6. Beam exit channel:
[0189] 6.6.1. Road cushion: ballast, stone or crushed stone filling, thickness not more than 30cm.
[0190] 6.6.2. Road surface: C30 concrete or graded crushed stone, thickness not more than 20cm.
[0191] 6.7. Others:
[0192] 6.7.1. Water supply pipeline: depends on the actual situation.
[0193] 6.7.2. Maintenance water pipes: 100mm PPR pipes for main water supply pipes and 75mm PPR pipes for branch pipes.
[0194] 6.7.3. Steam-cured pipes: The main pipe of the curing pipe is made of 100mm PPR pipe, and the branch pipe is made of 75mm PPR pipe.
[0195] 6.7.4. Production area fence: implemented in accordance with relevant standards.
[0196] 5. The construction standards for intelligent steel bar processing plants that can be used as reference for optimal scoring are as follows:
[0197] 1. Temporary land rental: set up according to the monthly steel bar processing volume and project conditions.
[0198] 2. Site clearing and leveling: consistent with temporary land rental.
[0199] 3. Site hardening: C20 concrete, thickness 10cm.
[0200] 4. On-site transportation road: C20 concrete, thickness 20cm, on-site road width 5m.
[0201] 5. Closed plant: The steel processing plant adopts closed plant management. The main structure of the plant adopts assembled steel structure, the top is an arched rain shelter, the drainage adopts two-way drainage, i=5%, the roof adopts 0.4mm, 840 color steel plate and 1.2mm, 840 FRP sun plate alternately arranged, the side wall adopts 0.4mm, 900 color steel plate, the lower part is equipped with a 30cm waterproof layer, and the upper length direction reserves a 0.4m ventilation hole. The height of the plant should meet the operating space of the processing equipment and lifting equipment, and the height of the side wall is generally not less than 10.5m.
[0202] 6. Non-enclosed processing shed: The ceiling of the non-enclosed processing shed type steel bar processing plant adopts an arched rainproof shed with a prefabricated steel structure. The side walls are not enclosed. The ceiling height should meet the operating space of the processing equipment and lifting equipment. The height of the side wall is generally not less than 10.5m.
[0203] 7. Drainage: The ground drainage ditch in the factory building has the dimensions of width (0.3m) x height (0.4m), and 12 brick walls; the roof drainage uses 2.5mm shaped drainage grooves, and the roof downpipe uses φ150 PVC pipes; the factory building is surrounded by 30cm high retaining brick walls (12 walls) and drainage ditches, and the general dimensions of the drainage ditch are width (0.5m) x height (0.5m).
[0204] 8. Materials: The material support piers shall be made of recyclable materials. It is advisable to use I-beams to process into frames. The steel mesh semi-finished product support piers shall be arranged in a single layer with a height of 20cm. The raw materials and other semi-finished products shall be arranged in a double layer with welding between layers with a height of 36cm.
[0205] 6. The construction standards for small component prefabrication yards or segment prefabrication yards that can be used as reference for optimal scoring are as follows:
[0206] 1. Scale: The number of small components is less than 20,000, S≤2200m 2. The number of small components is 20,000 to 40,000 pieces, S≤4000m 2 . The number of small components is more than 40,000 pieces, S≤7000m 2 .
[0207] 2. Site filling: 30cm thick.
[0208] 3. Site leveling concrete: C20 concrete, 0.1cm thick.
[0209] 4. On-site roads: The site roads are 7 meters wide and made of C20 concrete with a thickness of 20 cm.
[0210] 5. Car wash tank and sedimentation tank: A car wash tank (8m long, 3m wide, 0.5m deep, 24 brick wall, C20 concrete foundation 0.2m thick, M10 mortar surface) is set up at the entrance of the site, and a three-level sedimentation tank is set up. The three-level sedimentation tank is 8m (length) x3m (width) x2 m (depth), with 24 brick walls, M10 mortar surface, steel mesh covering and railings.
[0211] 6. Drainage ditches: Drainage ditches are set up along the four sides of the wall and horizontally in the field. The wall is made of 24 bricks, the ditch is 50cm (width) x 50 cm (depth), and the surface is plastered with M10 mortar.
[0212] 7. Brick waterproof wall (around the factory building) 12 wall: wall height 2m.
[0213] 8. Brick wall columns: The length and width of the wall columns are 0.5m, the height is consistent with the height of the wall, and the spacing is 5m.
[0214] 9. C20 concrete for wall column foundation: The wall column foundation is 0.3m deep and 0.9m long and wide.
[0215] 10. C20 concrete for wall foundation: The wall foundation is 0.3m deep and 0.32m wide.
[0216] 11. Wall plastering: Both internal and external walls are plastered with 1cm.
[0217] 12. Processing shed: only for prefabrication processing area, arch height ≥ 8m, using light steel structure ceiling.
[0218] 13. Main door: 75mm sandwich panel sliding door (5*5m).
[0219] 7. For self-mining and processing plants of sand and gravel, the construction standards that can be used as reference for the optimal scoring are as follows:
[0220] 1. Scale: According to the planned site of different production, the aggregate storage yard is planned according to the 15-day production: (1) The production is 250-300t / h and the land area does not exceed 21,000m 2(2) Output is 300-450t / h and the land area does not exceed 27,000m 2 (3) Output is 450-500t / h and the land area does not exceed 28,500m 2 .
[0221] 2. Site leveling: After the foundation is compacted, fill with gravel to a thickness of 20cm.
[0222] 3. Weighing scale: A weighing scale can be set up as needed (usually one), and the weighing scale foundation shall be set up according to the standard weighing scale drawing requirements.
[0223] 4. Crushed stone processing equipment foundation: C30 concrete, determined according to the foundation bearing capacity calculation and equipment foundation drawing.
[0224] 5. Hardening of main roads: The pavement of the on-site roads is made of C20 concrete, 20cm thick.
[0225] 6. Aggregate storage silo: The thickness of the C20 concrete for the floor shall not exceed 20cm, and a drainage slope of not less than 2% shall be provided; the thickness of the C30 concrete for the partition shall not exceed 30cm.
[0226] 7. Site floor: C20 concrete, thickness not more than 10cm, surface layer with drainage slope not less than 1.5%.
[0227] 8. Car wash trough and sedimentation tank: A wheel washing machine (automatic) is set up on the main road inside the gate, and a three-stage sedimentation tank of 8mx3mx2m is set up, which is brick-built, mortar-plastered, C20 bottom paved, steel mesh covered and railings.
[0228] 9. Water storage tank: brickwork 10m (length) x 5m (width) x 2 m (depth), C20 base, M10 mortar surface. Two water storage tanks in the gravel area and sand making area, 10t / each.
[0229] 10. Drainage ditch: Drainage ditch is set up around the site, brick-built 50cm (width) x 50cm (depth), ditch bottom (0.1m thick) C20 concrete, M10 mortar surface. Drainage ditch is set up between the aggregate bin and the production area, brick-built 50cm (width) x 50cm (depth), ditch bottom (0.1m thick) C20 concrete, M10 mortar surface, customized cover.
[0230] 11. Sewage sedimentation tank: brickwork, five-stage sedimentation, reference size: 20m (length) x 4m (width) x 2 m (depth), M10 mortar finishing, pool bottom 10cm C20 concrete.
[0231] 12. Distribution room: Brick-built distribution room with an area of 20m 2 .
[0232] 13. Fence: 1.8m simple fence.
[0233] S3: Generate a database of temporary construction project design results.
[0234] S4: According to the project to be designed, the preferred results are selected from the temporary construction project design results database, and the final weight value of the preferred results is obtained by establishing a matrix. Combined with the ranking score in S3, the final score is calculated, and the temporary construction project design plan with the highest score is selected as the output, and the optimal construction plan is output.
[0235] In this example, the project to be designed is based on the requirements for the project manager's residence, concrete mixing plant, T-beam prefabrication yard or railway box beam prefabrication yard, steel bar intelligent processing plant, small component prefabrication yard or pipe segment prefabrication yard, and sand and gravel self-mining processing plant. Two results, Result 1 and Result 2, are selected from the temporary project design result library. Among them, the ranking score of Result 1 is: 90 points for construction period, 80 points for quality, 80 points for cost, and 80 points for safety. The ranking score of Result 2 is: 80 points for construction period, 90 points for quality, 80 points for cost, and 80 points for safety. A selection decision matrix is established, and a comprehensive scoring model is introduced to establish a decision matrix. In this example, the influencing factors of the project to be designed are construction period, quality, cost, and safety. According to the experts' judgment of the impact of construction period, quality, cost, and safety on this project, they are used as weight values and as matrix elements to generate a decision matrix, such as Figure 2 shown.
[0236] Sum each column of the decision matrix to obtain the sum of each column SUM, such as Figure 3 shown.
[0237] The decision matrix is normalized, and each column element is divided by SUM to obtain the normalized value to form the normalized decision matrix, such as Figure 4 shown.
[0238] Add each row of the normalized decision matrix to get the final weight value, such as Figure 5 shown.
[0239] The final weight value is taken as the full score, and combined with the ranking scores of the selected results 1 and 2, the final score of result 1 is:
[0240] (90x0.483766+80x1.667208+80x1.077922+80x0.771104) / 4=81.21
[0241] The final score of Outcome 2 is:
[0242] (80x0.483766+90x1.667208+80x1.077922+80x0.771104) / 4=84.17
[0243] Comparing the final weight values of Outcome 1 and Outcome 2, Outcome 2 has the highest score and should be output as the optimal temporary construction plan for this project.
[0244] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for generating an optimal temporary construction engineering design scheme based on comparison, characterized in that: The following steps are involved: S1: Collect results through preset solicitation categories, randomly select three categories to solicit from mature fields or enterprises, so that the collected results cover the six categories and obtain temporary construction project design results; S2: Perform a global quality control check on the temporary construction project design results obtained in S1, and perform an overall score on the temporary construction project design results according to the global quality control check results, screen out the excellent overall results, and then perform sub-item quality control on the overall results to screen out the excellent results; S3: Input the excellent results into the database, rank and score them in combination with the pre-constructed comprehensive scoring model, and generate a temporary construction project design results database; S4: According to the project to be designed, the preferred results are selected from the temporary construction project design results database, and the final weight value of the preferred results is obtained by establishing a matrix. Combined with the ranking score in S3, the final score is calculated, and the temporary construction project design plan with the highest final score is selected as the output, and the optimal construction plan is output.
2. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: In step S1, the temporary construction project design results are obtained. The collection categories of the temporary construction project design results mainly include six categories: project manager's residence, concrete mixing station, T-beam prefabrication yard or railway box beam prefabrication yard, steel bar intelligent processing plant, small component prefabrication yard or pipe segment prefabrication yard, and sand and gravel self-mining processing plant.
3. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: Step S1 obtains the temporary construction project design results. The collection direction of the temporary construction project design results is randomly selected from three of the six categories, and then the collectors in mature fields or related enterprises are asked to choose from them, so that the collected results cover the six categories as the temporary construction project design results obtained in S1.
4. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: Step S2 performs a global quality control check on the temporary construction project design results obtained in S1, and the review experts give an overall score to the temporary construction project design results obtained in S1 according to the construction standards, and screen out the overall results of excellent level.
5. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: Step S2 is to conduct sub-item quality control on the overall results. The review experts shall conduct sub-item quality control on the overall results according to the construction standards. The categories of sub-item quality control include spatial layout, plane layout, functional division, reasonable process flow, reasonable general layout, sufficient and appropriate site selection basis, accurate and appropriate estimated engineering quantity, reasonable estimated unit cost, appropriate and reasonable estimated total price, and no major omissions or errors.
6. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: In step S3, the excellent results are ranked and scored in combination with a comprehensive scoring model. The influencing factors of the comprehensive scoring model are construction period, quality, cost, and safety. The influencing factors of each excellent result are scored in an arithmetic descending order according to the ranking, and the score range is 100 to 80 points. Assuming that there are N excellent results, according to the ranking, the influencing factor of the first result is 100 points, and the difference in the scores of the influencing factors of subsequent results is (100-80) / (N-1). As the number N of excellent results increases, the ranking score is automatically adjusted, and the excellent results and the ranking score are input into the temporary construction project design results database.
7. The method for generating an optimal temporary construction engineering design scheme based on comparison according to claim 1 is characterized in that: Step S4 specifically includes the following steps: S41: List feasible temporary construction design schemes for the project, first determine the project to be designed, and select the preferred results of the category corresponding to the project to be designed from the temporary construction project design results database; S42: Establish a selection decision matrix, with i as the vertical direction of the decision matrix, j as the horizontal direction of the decision matrix, and a as the influencing factor of the project to be designed. The influencing factors of the project to be designed should include construction period, quality, cost, and safety. If the project to be designed has special requirements, the influencing factors of the project to be designed can be increased or adjusted, and the influencing factors of the project to be designed are used as the horizontal index a of the decision matrix. i and longitudinal indicators and a j , a ij and a ji The specific weight value of the influencing factors of the project to be designed on the project to be designed is determined by the project personnel. i and a j If the impact on the project to be designed is the same, a ij =1, when a i Than a j When the impact is important ij >1,a ji The calculation formula is: According to the above a ij and a ji Establish a decision matrix, sum each column of the decision matrix to obtain the sum value of each column, normalize the decision matrix, and its matrix element is the single item value of each column divided by the corresponding sum value of each column to obtain a normalized decision matrix, sum each row of the normalized decision matrix to obtain the final weight value of the influencing factors of the project to be designed on the project to be designed; S43: Take the final weight value as the full score, use the comprehensive scoring model to score the preferred results respectively, multiply the ranking score obtained in step S3 by the final weight value, if the project to be designed has special requirements, and the influencing factors of the project to be designed are added or adjusted, then return to step S3 to again rank and score the excellent results in combination with the comprehensive scoring model, wherein the influencing factors of the comprehensive scoring model are the influencing factors of the project to be designed. After obtaining the ranking score, add the result obtained by multiplying it with the final weight value to obtain the final score, and the preferred result corresponding to the highest score in the final score is the optimal construction plan to be selected.