Self-wheel operation construction plan management method, device, equipment, medium and product
Through digital self-wheel operation plan management, the problems of low efficiency and complex approval process in the existing technology of self-wheel operation plan management are solved, and paperless approval and efficient operation plan management are realized.
Patent Information
- Application Number
- CN202510105062.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-23
- Publication Date
- 2025-02-28
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing self-wheel operation plan management methods have problems such as repeated reports, missed reports, large workload of planning and organization, unclear responsibilities and low efficiency. The approval process is complex, and it is impossible to check the planning content and approval process in a timely manner, which affects the operation planning and internal management of self-wheel operation equipment.
Through the digital self-wheel operation plan submission and approval process, the self-wheel operation plan is generated based on the operation of the applicant, and the corresponding approval process is obtained; the corresponding operation authority of the operator at each stage is obtained, and multiple approval operators are determined; according to the approval process, the plan is published to the client of each approval operator until the approval is approved.
Paperless approval has been achieved, the efficiency of self-wheel operation plan approval has been improved, the responsibilities of each approval node have been clarified, and the accurate and efficient progress of self-wheel operation construction has been ensured.
Smart Images

Figure CN119539749A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of railway technology, and in particular to a self-propelled wheel operation construction plan management method, device, equipment, medium and product. Background Art
[0002] On local freight railways, self-propelled wheel operation construction plan management is one of the core tasks of daily railway construction and maintenance management.
[0003] At present, the existing self-propelled wheel operation plan management method is that when the self-propelled wheel operation equipment management unit submits the plan, it mainly relies on the equipment management unit personnel to send it to the locomotive section duty officer in the form of documents. There are problems such as repeated submission, omissions, large workload for plan sorting, unclear responsibilities, and low efficiency, which will affect the operation plan arrangement of the self-propelled wheel operation equipment; secondly, the self-propelled wheel operation plan approval process is complicated, and the existing technology does not have a timely query of the plan content and the approval process, and cannot clarify the responsibilities of each process node, which is not conducive to the operation time planning and internal management of the self-propelled wheel operation equipment, and it is difficult to meet the requirements of refined management of railway transportation enterprises. Summary of the invention
[0004] The present invention provides a self-propelled wheel operation construction plan management method, device, equipment, medium and product, which can realize paperless approval, monitor the approval process, improve the efficiency of self-propelled wheel operation plan approval, and ensure that the self-propelled wheel operation construction work is carried out accurately and efficiently.
[0005] According to one aspect of the present invention, a self-propelled wheel operation construction plan management method is provided, comprising:
[0006] Generate a self-turbine operation plan according to the self-turbine operation plan editing operation of the submitter, and obtain the approval process corresponding to the self-turbine operation plan;
[0007] Obtaining the operation authority corresponding to the operator at each stage, and obtaining multiple approval operators corresponding to the self-propulsion operation plan according to the operation authority and the approval process;
[0008] According to the approval process, the self-propelled wheel operation plan is published to the client of each of the approval operators, so that each of the approval operators can approve the self-propelled wheel operation plan until it is approved.
[0009] According to another aspect of the present invention, there is provided a self-propelled wheel operation construction plan management device, comprising:
[0010] A plan generation module, used to generate a self-turbine operation plan according to the self-turbine operation plan editing operation of the submitter, and obtain the approval process corresponding to the self-turbine operation plan;
[0011] An approval operator acquisition module is used to acquire the operation authority corresponding to the operator at each stage, and acquire multiple approval operators corresponding to the self-propulsion operation plan according to the operation authority and the approval process;
[0012] The plan approval module is used to publish the self-propelled wheel operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-propelled wheel operation plan until it is approved.
[0013] According to another aspect of the present invention, there is provided an electronic device, the electronic device comprising:
[0014] at least one processor; and
[0015] a memory communicatively connected to the at least one processor; wherein,
[0016] The memory stores a computer program that can be executed by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the self-propelled operation construction plan management method described in any embodiment of the present invention.
[0017] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and the computer program is used to enable a processor to implement the self-propelled operation construction plan management method described in any embodiment of the present invention when executed.
[0018] According to another aspect of the present invention, a computer program product is provided, comprising a computer program, wherein when the computer program is executed by a processor, the method for managing a self-propelled wheel operation construction plan according to any embodiment of the present invention is implemented.
[0019] The technical solution of the embodiment of the present invention generates a self-wheel operation plan according to the self-wheel operation plan editing operation of the submitter, and obtains the approval process corresponding to the self-wheel operation plan; obtains the operation authority corresponding to the operator at each stage, and obtains multiple approval operators corresponding to the self-wheel operation plan according to the operation authority and the approval process; publishes the self-wheel operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-wheel operation plan until it is approved; by digitally submitting and approving the self-wheel operation plan, and clarifying each approval node based on the operation authority, paperless approval can be achieved, the approval process can be monitored, the approval efficiency of the self-wheel operation plan can be improved, and the accurate and efficient self-wheel operation construction work can be guaranteed.
[0020] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0022] Figure 1 This is a flow chart of a self-propelled wheel operation construction plan management method provided according to the first embodiment of the present invention;
[0023] Figure 2 This is a schematic diagram of operator position correspondence provided according to the first embodiment of the present invention;
[0024] Figure 3 This is a schematic diagram of the approval process at the equipment unit approval stage according to the first embodiment of the present invention;
[0025] Figure 4 It is a schematic diagram of the approval process of the maintenance approval stage and the scheduling approval stage provided according to the first embodiment of the present invention;
[0026] Figure 5 It is a structural schematic diagram of a self-propelled operation construction plan management device provided according to the second embodiment of the present invention;
[0027] Figure 6 It is a structural schematic diagram of an electronic device for implementing the self-propelled wheel operation construction plan management method of an embodiment of the present invention. DETAILED DESCRIPTION
[0028] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0029] It should be noted that the terms "first", "second", "target", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0030] Embodiment 1
[0031] Figure 1 A flowchart of a self-propelled wheel operation construction plan management method is provided for the first embodiment of the present invention. This embodiment is applicable to the case of online management of self-propelled wheel operation construction. The method can be executed by a self-propelled wheel operation construction plan management device. The self-propelled wheel operation construction plan management device can be implemented in the form of hardware and / or software. Typically, the self-propelled wheel operation construction plan management device can be configured in an electronic device, such as a computer device or a server. Figure 1 As shown, the method includes:
[0032] S110, generating a self-propeller operation plan according to the self-propeller operation plan editing operation of the submitter, and obtaining the approval process corresponding to the self-propeller operation plan.
[0033] Among them, the submitter may be an operator with the authority to submit the self-propelled operation plan, for example, the manager of the self-propelled operation equipment. In this embodiment, the basic information and operation authority of the operators at each stage can be pre-configured. The basic information may include name, work number, contact information, affiliated unit, position, etc.; the operation authority may include position authority (for example, submission, first-level approval of equipment unit, second-level approval of equipment unit, first-level approval of maintenance, second-level approval of maintenance, scheduling approval, etc.) and the subordinate approval positions corresponding to each position. Typically, the operation authority corresponding to each operator can be determined based on the operator's affiliated unit and position, as well as the preset mapping relationship between the unit, position and authority.
[0034] In this embodiment, the self-propelled turbine operation construction plan management may include four stages: the submitter submits the self-propelled turbine operation construction plan, the equipment unit approves it, the maintenance department approves it, and the dispatcher approves it. Each stage has a corresponding operator. In a specific example, the operator position correspondence relationship can be as follows: Figure 2 shown.
[0035] Specifically, first, the submitter can log in to the client and fill in and edit the self-turbine operation plan on the new page of the self-turbine operation plan. After completing the editing, the submitter can click Save and Submit. Then, the server can obtain the self-turbine operation plan edited by the submitter and perform content analysis on the plan to obtain the content analysis result; then, the server can determine the approval process corresponding to the self-turbine operation plan based on the content analysis result.
[0036] The approval process may include the approval stages and their sequence, the approval levels and sequence of each approval stage, and the path when each approval level rejects. The sequence of each approval stage and each approval level, as well as the path when each approval level rejects can be preset.
[0037] The self-propelled operation plan is the operation plan of the self-propelled equipment, which may include at least one of the following: operation section, construction content, vehicle departure time, construction unit, precautions, person in charge information, window time and whether it is urgent. Self-propelled equipment refers to rail vehicles and special vehicles for railway construction and maintenance running on railway operating lines, such as rail cranes, bridge erecting machines, track laying machines, overhead wire erecting vehicles, wire laying vehicles, maintenance vehicles, large-scale track maintenance machinery, etc.
[0038] In this embodiment, for different types of self-propelled wheel operation plans, the equipment unit approval stage and the maintenance approval stage may have different approval levels. For example, for the first type of self-propelled wheel operation plan, the equipment unit approval stage may only include the second-level approval, while for the second type of self-propelled wheel operation plan, the equipment unit approval stage may include both the first-level approval and the second-level approval. Thus, the server can determine the type of the self-propelled wheel operation plan based on the content analysis result of the self-propelled wheel operation plan, and then determine the approval level of each approval stage based on the type, so as to finally determine the approval process corresponding to the self-propelled wheel operation plan.
[0039] It should be noted that, in this embodiment, the corresponding type of the self-propelled wheel operation plan can be determined according to a single field or a combination of multiple fields of the self-propelled wheel operation plan; for example, the type of the self-propelled wheel operation plan can be determined only according to the field value of the emergency field; for another example, the type of the self-propelled wheel operation plan can be determined according to the field values of the three fields of operation section, construction content and emergency. Among them, the corresponding relationship between the field, the field value and the type of the self-propelled wheel operation plan can be preset.
[0040] S120, obtaining the operation authority corresponding to the operator at each stage, and obtaining multiple approval operators corresponding to the self-propulsion operation plan according to the operation authority and the approval process.
[0041] Among them, the operators at each stage may include the submitter and the approval operator. In this embodiment, after determining the approval process, the operation permissions corresponding to all operators at each stage that are pre-configured can be read, and the operation permissions may include position permissions and corresponding subordinate approval positions. Then, the various approval levels of the equipment unit approval stage and the maintenance approval stage can be determined according to the approval process, and the approval levels can be searched one by one according to the operation permissions (subordinate approval positions) of each operator in each approval level and the basic information (position) of the submitter to determine the approval operators at each approval level. For example, if it is detected that the subordinate approval position of an operator in the current approval level is the position of the approval operator of the previous approval level, the detected operator can be used as the approval operator of the current approval level. Finally, the approval operator of the final scheduling approval stage can be found according to the basic information corresponding to the approval operators of each approval level in the maintenance approval stage and the operation permissions corresponding to each operator in the scheduling approval stage.
[0042] Among them, the approval operator may include the first-level approval operator of the equipment unit, the second-level approval operator of the equipment unit, the first-level approval operator of the maintenance, the second-level approval operator of the maintenance and / or the dispatching approval operator. In a specific example, the approval process includes the first-level approval and the second-level approval in both the equipment unit approval stage and the maintenance approval stage. At this time, the self-propelled wheel operation plan needs to be approved by the first-level approval operator of the equipment unit, the second-level approval operator of the equipment unit, the first-level approval operator of the maintenance, the second-level approval operator of the maintenance and the dispatching approval operator in turn. Only after successfully passing the approval of all the approval operators can the self-propelled wheel operation plan be implemented.
[0043] S130. According to the approval process, the self-turbine operation plan is published to the client of each approval operator, so that each approval operator can approve the self-turbine operation plan until it is approved.
[0044] Specifically, the server can follow the approval process and first publish the self-wheeling operation plan in the form of a system task to the client of the first approving operator. After the approval is passed, the self-wheeling operation plan will continue to be published to the client of the next approving operator for approval until it passes the approval of all approving operators and is determined to be approved.
[0045] Secondly, if the current approval operator chooses to reject the self-wheel operation plan after approving it, the server can first determine the approval level corresponding to the current approval operator, and can find the rejection path corresponding to the approval level in the approval process; then, the server can finally reject the self-wheel operation plan to the client of the submitter according to the rejection path, so that the submitter can modify the self-wheel operation plan. After the submitter completes the modification of the self-wheel operation plan, the above steps can be re-executed until the self-wheel operation plan is approved.
[0046] The technical solution of the embodiment of the present invention generates a self-wheel operation plan according to the self-wheel operation plan editing operation of the submitter, and obtains the approval process corresponding to the self-wheel operation plan; obtains the operation authority corresponding to the operator at each stage, and obtains multiple approval operators corresponding to the self-wheel operation plan according to the operation authority and the approval process; publishes the self-wheel operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-wheel operation plan until it is approved; by digitally submitting and approving the self-wheel operation plan, and clarifying each approval node based on the operation authority, paperless approval can be achieved, the approval process can be monitored, the approval efficiency of the self-wheel operation plan can be improved, and the accurate and efficient self-wheel operation construction work can be guaranteed.
[0047] In an optional implementation of this embodiment, obtaining the approval process corresponding to the self-propelled turbine operation plan may include:
[0048] Analyze the self-propelled wheel operation plan, and determine whether the self-propelled wheel operation plan is urgent according to the analysis result;
[0049] If the self-turbine operation plan is not urgent, determining the approval process corresponding to the self-turbine operation plan is to go through the first-level approval of the equipment unit, the second-level approval of the equipment unit, the first-level approval of the maintenance, the second-level approval of the maintenance and the dispatching approval in sequence;
[0050] If the self-turbine operation plan is urgent, it is determined that the approval process corresponding to the self-turbine operation plan is to go through the second-level approval of the equipment unit, the first-level approval of the maintenance unit, the second-level approval of the maintenance unit and the dispatching approval in sequence.
[0051] In a specific example, the approval process corresponding to the self-turbine operation plan can be determined according to the field value of the emergency field in the self-turbine operation plan. Specifically, when the self-turbine operation plan is not urgent, the equipment unit approval stage and the maintenance approval stage include both the first-level approval and the second-level approval; when the self-turbine operation plan is urgent, the equipment unit approval stage only includes the second-level approval, and the maintenance approval stage still includes the first-level approval and the second-level approval.
[0052] The advantage of the above setting is that when urgent construction is required, the approval process can be simplified, the approval speed can be accelerated, and the approval time can be shortened.
[0053] Optionally, according to the approval process, publishing the self-turbine operation plan to the client of each of the approval operators so that each of the approval operators approves the self-turbine operation plan until the approval is passed, which may include:
[0054] If the self-propelled operation plan is rejected at the equipment unit approval stage, the rejection reason is obtained, and the rejection reason and the self-propelled operation plan are directly rejected to the client of the submitter, so that the submitter can modify the self-propelled operation plan according to the rejection reason;
[0055] According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
[0056] In a specific example, the approval process at the equipment unit approval stage can be as follows: Figure 3 As shown. First, obtain the self-wheel operation plan submitted by the submitter and determine whether the self-wheel operation plan is urgent; if it is a non-urgent plan, the plan will be transferred to the first-level approval operator of the corresponding equipment unit for approval. If the approval is passed, the approval time will be recorded, and the plan will be transferred to the second-level approval operator of the corresponding equipment unit for approval; if the approval is rejected, the rejection reason will be recorded, and the plan will be transferred back to the submitter's node, and the submitter will resubmit it after editing and modification. Secondly, if it is an emergency plan, the plan will be directly transferred to the second-level approval operator of the corresponding equipment unit for approval.
[0057] Afterwards, the second-level approval operator of the equipment unit will review and approve the plan. If approved, the approval time will be recorded, and the plan will be transferred to the first-level approval operator of the maintenance department for approval. If the approval is rejected, the reason for rejection will be recorded, and the plan will be transferred back to the submitter's node to be resubmitted after editing and modification by the submitter.
[0058] Optionally, according to the approval process, publishing the self-turbine operation plan to the client of each of the approval operators so that each of the approval operators approves the self-turbine operation plan until the approval is passed, which may include:
[0059] If the self-turbine operation plan is rejected at the maintenance approval stage or the scheduling approval stage, the rejection reason is obtained, and the rejection reason and the self-turbine operation plan are sent to the client of the secondary approval operator of the equipment unit, so that the rejection reason and the self-turbine operation plan are rejected to the client of the submitter through the secondary approval operator of the equipment unit, so that the submitter can modify the self-turbine operation plan according to the rejection reason;
[0060] According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
[0061] In a specific example, the approval process of the maintenance approval stage and the scheduling approval stage can be as follows: Figure 4 As shown. First, after the equipment unit's second-level approval operator approves it, the system will transfer the plan to the maintenance first-level approval operator for approval. If the approval is passed, the approval time will be recorded, and the plan will be transferred to the maintenance second-level approval operator for approval. If the approval is rejected, the rejection reason will be recorded, and the plan will be transferred back to the equipment unit's second-level approval operator node. After the equipment unit's second-level approval operator rejects the plan to the submitter node, the submitter will edit and modify it and resubmit it.
[0062] After the plan is transferred to the maintenance second-level approval operator, the maintenance second-level approval operator will approve it. If the approval is passed, the approval time will be recorded, and the plan will be further transferred to the dispatch approval operator for approval. If the approval is rejected, the rejection reason will be recorded, and the plan will be transferred back to the equipment unit second-level approval operator node. After the equipment unit second-level approval operator rejects the plan to the submitter node, the submitter will edit and modify the plan and resubmit it.
[0063] Secondly, after the plan is transferred to the dispatching approval operator, the dispatching approval operator will approve it. If the approval is passed, the approval process ends and the plan is marked as approved for inquiry by stations, locomotive depots, and construction units. If the approval is rejected, the reason for the rejection is recorded and the plan is transferred back to the equipment unit's second-level approval operator node. After the equipment unit's second-level approval operator rejects the plan to the submitter node, the submitter edits and modifies the plan and resubmits it.
[0064] The technical solution of this embodiment can replace the traditional paper or electronic document form of self-propelled wheel operation plan submission and approval process, can reduce omissions and mistransmissions, and can improve work efficiency and accuracy; secondly, it can view the detailed content of each self-propelled wheel operation plan and the detailed record of the approval process, and have a more accurate grasp of the construction window time; and, it can intuitively analyze the submission content, submitter, approver, approval time, approval opinions, etc. of each plan in the three stages of equipment unit, locomotive depot, and dispatching center, can clarify the division of responsibilities for self-propelled wheel operation construction operations that are not carried out according to plan, can ensure the safety of self-propelled wheel operation construction operations, and can improve the management level of self-propelled wheel operation operations.
[0065] Embodiment 2
[0066] Figure 5 This is a schematic diagram of the structure of a self-propelled wheel operation construction plan management device provided in the second embodiment of the present invention. Figure 5 As shown, the device includes: a plan generation module 210, an approval operator acquisition module 220 and a plan approval module 230; wherein,
[0067] The plan generation module 210 is used to generate a self-turbine operation plan according to the self-turbine operation plan editing operation of the submitter, and obtain the approval process corresponding to the self-turbine operation plan;
[0068] The approval operator acquisition module 220 is used to acquire the operation authority corresponding to the operator at each stage, and acquire multiple approval operators corresponding to the self-propeller operation plan according to the operation authority and the approval process;
[0069] The plan approval module 230 is used to publish the self-turbine operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-turbine operation plan until it is approved.
[0070] The technical solution of the embodiment of the present invention generates a self-wheel operation plan according to the self-wheel operation plan editing operation of the submitter, and obtains the approval process corresponding to the self-wheel operation plan; obtains the operation authority corresponding to the operator at each stage, and obtains multiple approval operators corresponding to the self-wheel operation plan according to the operation authority and the approval process; publishes the self-wheel operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-wheel operation plan until it is approved; by digitally submitting and approving the self-wheel operation plan, and clarifying each approval node based on the operation authority, paperless approval can be achieved, the approval process can be monitored, the approval efficiency of the self-wheel operation plan can be improved, and the accurate and efficient self-wheel operation construction work can be guaranteed.
[0071] Optionally, the plan generation module 210 is specifically used to analyze the self-turbine operation plan and determine whether the self-turbine operation plan is urgent according to the analysis result;
[0072] If the self-turbine operation plan is not urgent, determining the approval process corresponding to the self-turbine operation plan is to go through the first-level approval of the equipment unit, the second-level approval of the equipment unit, the first-level approval of the maintenance, the second-level approval of the maintenance and the dispatching approval in sequence;
[0073] If the self-turbine operation plan is urgent, it is determined that the approval process corresponding to the self-turbine operation plan is to go through the second-level approval of the equipment unit, the first-level approval of the maintenance unit, the second-level approval of the maintenance unit and the dispatching approval in sequence.
[0074] Optionally, the plan approval module 230 is specifically used to obtain the rejection reason if the self-turbine operation plan is rejected at the equipment unit approval stage, and directly reject the rejection reason and the self-turbine operation plan to the client of the submitter, so that the submitter can modify the self-turbine operation plan according to the rejection reason;
[0075] According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
[0076] Optionally, the plan approval module 230 is specifically used to obtain the rejection reason if the self-turbine operation plan is rejected in the maintenance approval stage or the scheduling approval stage, and send the rejection reason and the self-turbine operation plan to the client of the secondary approval operator of the equipment unit, so that the rejection reason and the self-turbine operation plan are rejected to the client of the submitter through the secondary approval operator of the equipment unit, so that the submitter modifies the self-turbine operation plan according to the rejection reason;
[0077] According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
[0078] Optionally, the approval operators include the first-level approval operator of the equipment unit, the second-level approval operator of the equipment unit, the first-level approval operator of the maintenance department, the second-level approval operator of the maintenance department and / or the dispatching approval operator.
[0079] Optionally, the self-propelled wheel operation plan includes at least one of the operating section, construction content, vehicle departure time, construction unit, precautions, person in charge information, skylight time and whether it is urgent.
[0080] The self-propelled wheel operation construction plan management device provided in the embodiment of the present invention can execute the self-propelled wheel operation construction plan management method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.
[0081] In the technical solution of the present disclosure, the collection, storage, use, processing, transmission, provision and disclosure of user personal information involved are in compliance with the provisions of relevant laws and regulations and do not violate public order and good morals.
[0082] Embodiment 3
[0083] Figure 6 A schematic diagram of the structure of an electronic device 30 that can be used to implement an embodiment of the present invention is shown. The electronic device 30 is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device 30 can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0084] like Figure 6 As shown, the electronic device 30 includes at least one processor 31, and a memory connected to the at least one processor 31, such as a read-only memory (ROM) 32, a random access memory (RAM) 33, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 31 can perform various appropriate actions and processes according to the computer program stored in the read-only memory 32 or the computer program loaded from the storage unit 38 to the random access memory 33. In the RAM 33, various programs and data required for the operation of the electronic device 30 can also be stored. The processor 31, the ROM 32 and the RAM 33 are connected to each other through a bus 34. The input / output (I / O) interface 35 is also connected to the bus 34.
[0085] A number of components in the electronic device 30 are connected to the I / O interface 35, including: an input unit 36, such as a keyboard, a mouse, etc.; an output unit 37, such as various types of displays, speakers, etc.; a storage unit 38, such as a disk, an optical disk, etc.; and a communication unit 39, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 39 allows the electronic device 30 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0086] The processor 31 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 31 include, but are not limited to, a central processing unit, a graphics processing unit, various special artificial intelligence computing chips, various processors running machine learning model algorithms, digital signal processors, and any appropriate processors, controllers, microcontrollers, etc. The processor 31 executes the various methods and processes described above, such as the self-propelled wheel operation construction plan management method.
[0087] In some embodiments, the self-propelled wheel operation construction plan management method can be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 38. In some embodiments, part or all of the computer program can be loaded and / or installed on the electronic device 30 via the ROM 32 and / or the communication unit 39. When the computer program is loaded into the RAM 33 and executed by the processor 31, one or more steps of the self-propelled wheel operation construction plan management method described above can be performed. Alternatively, in other embodiments, the processor 31 can be configured to execute the self-propelled wheel operation construction plan management method in any other appropriate manner (for example, by means of firmware).
[0088] Various embodiments of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays, application specific integrated circuits, application specific standard products, systems on a chip, load programmable logic devices, computer hardware, firmware, software, and / or combinations thereof. These various embodiments may include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0089] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0090] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in conjunction with an instruction execution system, device, or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices, or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory, a read-only memory, an erasable programmable read-only memory, an optical fiber, a portable compact disk read-only memory, an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0091] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device 30 having: a display device (e.g., a cathode ray tube or a liquid crystal display) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or a trackball) through which the user can provide input to the electronic device 30. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0092] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: local area networks, wide area networks, blockchain networks, and the Internet.
[0093] A computing system may include clients and servers. Clients and servers are generally remote from each other and typically interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship to each other. The server may be a cloud server.
[0094] This embodiment may also include a computer program product, which includes a computer program. When the computer program is executed by a processor, it implements the self-propelled wheel operation construction plan management method provided by any embodiment of the present invention.
[0095] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0096] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A self-propelled wheel operation construction plan management method, characterized in that: include: Generate a self-turbine operation plan according to the self-turbine operation plan editing operation of the submitter, and obtain the approval process corresponding to the self-turbine operation plan; Obtaining the operation authority corresponding to the operator at each stage, and obtaining multiple approval operators corresponding to the self-propulsion operation plan according to the operation authority and the approval process; According to the approval process, the self-propelled wheel operation plan is published to the client of each of the approval operators, so that each of the approval operators can approve the self-propelled wheel operation plan until it is approved.
2. The method according to claim 1, characterized in that Obtain the approval process corresponding to the self-propulsion operation plan, including: Analyzing the self-propelled wheel operation plan, and judging whether the self-propelled wheel operation plan is urgent according to the analysis result; If the self-turbine operation plan is not urgent, determining the approval process corresponding to the self-turbine operation plan is to go through the first-level approval of the equipment unit, the second-level approval of the equipment unit, the first-level approval of the maintenance, the second-level approval of the maintenance and the dispatching approval in sequence; If the self-turbine operation plan is urgent, it is determined that the approval process corresponding to the self-turbine operation plan is to go through the second-level approval of the equipment unit, the first-level approval of the maintenance unit, the second-level approval of the maintenance unit and the dispatching approval in sequence.
3. The method according to claim 2, characterized in that According to the approval process, the self-turbine operation plan is published to the client of each approval operator, so that each approval operator approves the self-turbine operation plan until the approval is passed, including: If the self-propelled operation plan is rejected at the equipment unit approval stage, the rejection reason is obtained, and the rejection reason and the self-propelled operation plan are directly rejected to the client of the submitter, so that the submitter can modify the self-propelled operation plan according to the rejection reason; According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
4. The method according to claim 2, characterized in that: According to the approval process, the self-turbine operation plan is published to the client of each approval operator, so that each approval operator approves the self-turbine operation plan until the approval is passed, including: If the self-turbine operation plan is rejected at the maintenance approval stage or the scheduling approval stage, the rejection reason is obtained, and the rejection reason and the self-turbine operation plan are sent to the client of the secondary approval operator of the equipment unit, so that the rejection reason and the self-turbine operation plan are rejected to the client of the submitter through the secondary approval operator of the equipment unit, so that the submitter can modify the self-turbine operation plan according to the rejection reason; According to the modification operation of the submitter on the self-wheel operation plan, the updated self-wheel operation plan is obtained, and according to the approval process, the updated self-wheel operation plan is published to the client of each approval operator, so that each approval operator can approve the updated self-wheel operation plan until it is approved.
5. The method according to claim 1, characterized in that The approval operators include the first-level approval operator of the equipment unit, the second-level approval operator of the equipment unit, the first-level approval operator of the maintenance department, the second-level approval operator of the maintenance department and / or the dispatching approval operator.
6. The method according to any one of claims 1 to 4, characterized in that The self-propelled wheel operation plan includes at least one of the operating section, construction content, vehicle departure time, construction unit, precautions, person in charge information, window time and whether it is urgent.
7. A self-propelled wheel operation construction plan management device, characterized in that: include: A plan generation module, used to generate a self-turbine operation plan according to the self-turbine operation plan editing operation of the submitter, and obtain the approval process corresponding to the self-turbine operation plan; An approval operator acquisition module is used to acquire the operation authority corresponding to the operator at each stage, and acquire multiple approval operators corresponding to the self-propulsion operation plan according to the operation authority and the approval process; The plan approval module is used to publish the self-propelled wheel operation plan to the client of each approval operator according to the approval process, so that each approval operator can approve the self-propelled wheel operation plan until it is approved.
8. An electronic device, characterized in that: The electronic device comprises: at least one processor, and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the self-propelled operation construction plan management method described in any one of claims 1-6.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and the computer program is used to enable a processor to implement the self-propelled wheel operation construction plan management method according to any one of claims 1 to 6 when executed.
10. A computer program product, characterized in that It includes a computer program, which, when executed by a processor, implements the self-propelled wheel operation construction plan management method described in any one of claims 1 to 6.
Citation Information
Patent Citations
Examination and approval management platform, examination and approval method thereof and workflow generation method
CN110443573A
Task approval method and device, server and storage medium
CN110852695A
Examination and approval process processing method and device, equipment and storage medium
CN117151648A
Engine method and device for hierarchically controlling task workflow
CN117875865A
Workflow server device, defect information feedback method, program and recording medium with the program recorded
JP2005018280A