Construction method of a combined support system for continuous beam construction of combined road and rail bridges
By adopting a combined support system of steel pipe scaffolding and full-span scaffolding in the construction of the combined road-rail bridge, and by implementing graded load loading, the problems of insufficient or excessive preloading were solved, ensuring the stability and safety of the construction process and reducing construction costs and time.
Patent Information
- Application Number
- CN202510119347.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-24
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2045-01-24
AI Technical Summary
In the construction of bridges combining road and rail, conventional construction techniques often result in insufficient or excessive preloading, leading to excessive deformation or damage of the supports, which affects construction safety and load-bearing capacity.
A combined support system using steel pipe scaffolding and full-span scaffolding was adopted, and the stability and safety of the support system during construction were ensured by simulating graded load loading.
It effectively simulates the actual construction load of the beam, avoids excessive deformation or damage to the support, reduces construction difficulty and cost, and improves construction efficiency and safety.
Smart Images

Figure CN119711357B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of bridges, and in particular to a construction method for a combined support system for constructing continuous beams for combined road and rail bridges. Background Technology
[0002] In modern transportation construction, the joint construction of highways and railways has become an important trend. Generally, the bridges built by combining highways and railways are mostly double-deck bridges. Conventional construction techniques often use independent steel pipes with few or full supports. After the upper beam is completed, some supports are removed and the lower support is completed before the lower beam can be constructed.
[0003] When constructing bridges using conventional methods, there are instances of insufficient or excessive preloading. Insufficient preloading cannot simulate the full load during the actual construction of the bridge beam, potentially leading to excessive deformation of the support structure during subsequent construction. Conversely, excessive preloading may damage the support structure and affect its load-bearing capacity. Summary of the Invention
[0004] To address the shortcomings of the existing technologies, the technical problem to be solved by this invention is to provide a construction method for a combined support system for the construction of continuous beams for combined road and rail construction. This method can adopt a combined support system that combines steel pipe support with less support and full-span support. By simulating load grading, the stability and safety of the support system during construction are ensured, and the construction difficulty is reduced.
[0005] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is as follows: The present invention provides a construction method for a combined support system for the construction of a continuous beam for combined road and rail construction, comprising the following steps: S1. Foundation and scaffolding construction: Complete the construction of the foundation and the upper and lower piers, and install the lower railway steel pipe scaffolding and the upper highway scaffolding. S2. Construction of the upper highway beam: Erect formwork, tie the steel bars of the upper highway beam, pour concrete, tension the prestressing, and dismantle the upper support in sequence to complete the structural system conversion and the construction of the bridge deck system and traffic safety facilities. S3. Construction of the lower railway beam: After the upper highway beam is inspected and accepted, the bottom formwork of the lower railway beam is installed and prestressed repeatedly. The supports are installed on the pier, the formwork is erected and the lower railway steel bars are tied, concrete is poured, prestressing is tensioned, and the lower railway beam supports are dismantled in sequence to complete the construction of the railway bridge deck system and ancillary works.
[0006] In the preferred embodiment, the specific steps of step S1 are as follows: S11. Foundation and Pier Construction: Obtain geological survey results and carry out foundation construction based on the geological survey results; The bearing capacity of the foundation ranges from 150 to 300 kPa, and the verticality deviation of the pier body ranges from [missing information]. Column height, cross-sectional dimension error range is ±20mm, concrete strength grade is 100%; S12. Support installation: Obtain the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway, and determine the support installation data based on the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway.
[0007] In the preferred embodiment, the specific steps in step S12 are as follows: S121. Installation of steel pipe piles with fewer supports for the lower-level railway: The position of the steel pipe piles is determined using measuring equipment, and the deviation range of the plane position of the steel pipe piles is ±50mm; Using piling equipment, steel pipe piles are driven vertically into the foundation, with a verticality deviation range of 1%. The depth of the steel pipe piles into the soil is determined based on the geological survey report and the design bearing capacity, and the depth of the pile tip into the bearing layer ranges from 3m to 7m. The verticality and penetration depth of the piles are monitored in real time, and a measurement is performed every 2m of penetration. Once the piling is confirmed to be complete, the measurement error range of the top elevation of the steel pipe pile is controlled to be ±30mm. A steel column is installed on the top of the steel pipe pile, with the bottom of the steel column connected to the top of the steel pipe pile. The weld height between the steel column and the steel pipe pile is between 8mm and 16mm. The position and elevation of the steel columns were measured and adjusted using measuring equipment. A measurement check was performed after each steel column was installed, and diagonal bracing and horizontal bracing were installed on the steel columns respectively. The horizontal bracing is installed at different heights on the steel column. The horizontal bracing has a level deviation range of ±10mm. The horizontal bracing is installed first, followed by the diagonal bracing. The position and angle of the diagonal bracing and the horizontal bracing are monitored in real time. An unloading block is installed at the top of the steel column near the railway beam, and the installation position deviation of the unloading block is ±10mm; After the installation of the lower-level railway steel pipe supports is completed, a comprehensive inspection of the support system is carried out.
[0008] S122. Installation of the upper-level highway full-span scaffolding: Multiple uprights are installed on the full-span scaffolding. The lateral spacing between each adjacent upright is 0.9m to 1.5m perpendicular to the longitudinal direction of the bridge, and the longitudinal spacing between each adjacent upright is 0.6m to 1.2m along the longitudinal direction of the bridge. The step distance between each two adjacent horizontal bars is 1.2m to 1.8m. Sweeping bars are installed at the bottom of each upright and close to the ground to form a closed bottom frame structure. The uprights, horizontal bars, and diagonal bars are connected to each other to form a triangular structure. The uprights are equipped with sealing rods that connect the uprights at the edges to prevent the uprights at the ends of the support from opening outwards or deforming.
[0009] In the preferred embodiment, in step S121, the verticality deviation range of the steel column is: The column height, the spacing deviation between adjacent steel columns is ±20mm, the installation angle formed between the diagonal brace and the steel column is 45° to 60°, the angle error between the diagonal brace and the steel column is ±2°, and the tightening torque range of the connection between the steel column and the steel pipe pile is 400N・m to 600N・m. In step S122, the tightening torque of the connecting fasteners of the horizontal bar ranges from 40 N·m to 70 N·m, and the spacing between each adjacent diagonal bar ranges from 0.1 m to 1 m.
[0010] In the preferred embodiment, the specific steps of step S2 are as follows: S21. Reinforcing bar binding: Reinforcing bars are fixed using positioning bars and binding wires. The spacing of the positioning bars is 10cm to 50cm, and the thickness of the concrete cover is determined to be 30mm to 50mm. S22. Concrete pouring: Layered pouring method shall be adopted, with each layer ranging from 30cm to 50cm in thickness. An immersion vibrator shall be used for quick insertion and slow withdrawal for vibration, and the spacing between vibration points shall be 1 to 1.5 times the radius of action of the vibrator. The concrete pouring speed is determined based on the concrete supply capacity, formwork bearing capacity, and vibration effect, with the hourly pouring volume being 70% to 80% of the formwork design bearing capacity.
[0011] Among them, the slump of the monitored concrete is maintained within the range of 160mm to 200mm; S23. Prestressing tensioning: When the concrete strength reaches 75% of the design strength, the prestressing tensioning operation shall be performed. S24. Scaffold dismantling: The upper full-span scaffolding shall be dismantled in sequence. The dismantling order is as follows: first, dismantle the sealing rods, then the diagonal rods and horizontal rods, and finally the vertical rods. The dismantled parts shall be hoisted to the designated location for storage using hoisting equipment, and warning signs shall be set up around the dismantling area. S25. Structural system conversion and ancillary facility construction: After the scaffolding is removed, the structural system conversion will be carried out; S26. Bridge Inspection and Operation: After the construction of the bridge deck system and traffic safety facilities is completed, a bridge inspection shall be carried out.
[0012] In a preferred embodiment, in step S23, the tensioning sequence and tensioning control force F are obtained, and sensors are installed on the tensioning equipment; The sensors include displacement sensors and pressure sensors; A pressure sensor with a full-scale range of ±1% and a displacement sensor with an accuracy of ±1mm are used to monitor the tension force and the elongation ΔL of the prestressing tendon in real time. Based on the elastic modulus E, cross-sectional area A, and length L of the prestressed tendon, Hooke's law is applied. Calculate the theoretical elongation of the prestressing tendon, compare the theoretical elongation with the measured elongation, and the deviation range between the theoretical elongation and the measured elongation of the prestressing tendon is ±6%. If the deviation exceeds the set range, tensioning is stopped.
[0013] In the preferred embodiment, in step S25, the structural system includes casting guardrails, installing drainage pipes, expansion joints, and constructing bridge deck paving. During the pouring of the guardrail, the deviation of the guardrail's planar position is controlled within ±20mm, and the elevation deviation is controlled within ±10mm. During the installation of drainage pipes, the slope of the drainage pipes should be controlled within the range of 1% to 3%. The installation temperature range for expansion joints should be controlled between 10℃ and 25℃. During the bridge deck paving stage, the surface of the beam is first cleaned and roughened to ensure a tight bond between the beam and the paving layer. The thickness error of the bridge deck pavement is ±5mm, the flatness error range is ±3mm, and the cross slope error range is ±0.5%. Vibrating beams and plate vibrators are used to perform vibration and compaction.
[0014] In the preferred embodiment, step S3 consists of the following steps: S31. Bottom formwork installation: During the bottom formwork installation stage, measuring equipment is used to measure and control the bottom formwork elevation error to ±5mm and the flatness error to ±3mm. The bottom mold uses a template with a thickness of 18mm, and the joints are sealed to prevent grout leakage. A release agent is applied to the surface of the bottom mold. S32. Scaffold preloading: Scaffold preloading is performed. The design load value P is calculated based on the beam's self-weight and construction load. Sandbags or water tanks are selected as the preloading material. The load is applied in stages of 0.6, 0.8, 1.0, and 1.2 times the design load. The holding time after each loading stage is 3 to 4 hours. During each loading stage, sensors are used to monitor the scaffold settlement and stress in real time. Data is recorded and a load-settlement curve Ps curve is plotted. When the scaffold settlement remains within ±2mm for 3 consecutive hours, the next loading stage is performed. After preloading is completed, the elevation of the support is adjusted according to the settlement observation data, and the elastic deformation of the support is controlled within the range of 5mm to 10mm. S33. Support installation: When installing supports on the pier, the deviation range of the plane position of the support shall be ±10mm and the deviation range of the elevation shall be ±5mm. The supports are connected to the pier and beam by bolts. The tightening torque of the bolts ranges from 300 N·m to 500 N·m, and anti-loosening treatment is performed.
[0015] In the preferred embodiment, the construction process from steps S1 to S3 further includes step S4, which uses an AI model for data processing and construction control, specifically including the following steps: S41. Data Acquisition and Preprocessing Steps: Collect construction data for the support pre-stressing stage, concrete pouring process, and tensioning prestressing process, and perform preprocessing on the collected construction data. The preprocessed construction data was divided into three sets: 70% for training, 20% for validation, and 10% for testing. S42. Model selection and training steps: Select a suitable AI model based on the preprocessed construction data, including neural network models or support vector machine models; A neural network model is used to determine the number of input layer nodes based on the dimension of the input data, including the number of variables such as load, time, and temperature. Set the hidden layer structure to 2 to 3 layers, with 10 to 20 nodes in each layer, and determine the optimal hidden layer parameters through experimentation and optimization; The number of output layer nodes is determined based on the type of prediction results, including settlement prediction values and stress prediction values; The selected model is trained using the training set data. The backpropagation algorithm is used to dynamically adjust the model's weights and biases. A reasonable learning rate range is set to 0.001 to 0.01, the number of training epochs is set to 100 to 500, and the batch size is set to 32 to 64. During training, the performance of the model is continuously evaluated using the validation set. The mean squared error (MSE) and mean absolute error (MAE) are used to measure the deviation between the predicted and the true values. Training is stopped when the validation set error no longer decreases to prevent overfitting. S43. Model Evaluation and Application Steps: Perform a comprehensive evaluation of the trained model using the test set data, calculate the mean square error (MSE) and mean absolute error (MAE) of each evaluation index, and apply the model in actual construction if the model performance meets the predetermined requirements. During the preloading stage of the support, load data is collected in real time and input into the model to quickly predict settlement values. The results are then compared and analyzed with measured settlement values, and the loading strategy is adjusted in a timely manner based on the deviation. During the concrete pouring process, models are used to predict changes in concrete temperature stress, based on the concrete temperature stress calculation formula: ; in, The elastic modulus of concrete. This is the coefficient of linear expansion of concrete. The temperature difference between the inside and outside of the concrete; Based on the forecast results, take effective temperature control measures, including adjusting the curing temperature and optimizing the pouring time interval; During the prestressing stage, prestress loss is predicted using a model. This prestress loss includes losses caused by anchor deformation and prestressing tendon shrinkage. Losses caused by friction between prestressed tendons and the duct wall Losses caused by the temperature difference between the prestressed tendons under tension and the equipment bearing the tension during concrete heating and curing. Losses caused by stress relaxation of prestressed tendons Losses caused by concrete shrinkage and creep ; The calculation formulas for losses caused by anchor deformation and prestressed tendon shrinkage are as follows: ; in, This represents the deformation of the anchorage and the inward shrinkage of the prestressing tendons. This refers to the effective length of the prestressing tendon; The formula for calculating the loss caused by friction between the prestressing tendon and the duct wall is as follows: ; in, To control the tension stress, To account for the friction coefficient of local deviation per meter of duct length, The length of the duct from the tensioning end to the calculated cross-section. The coefficient of friction between the prestressing tendon and the duct wall is denoted as . It is the sum of the angles from the tensioning end to the tangents of the duct section of the calculated cross-section curve; Based on the predicted results, corresponding measures are taken during the tensioning process, including increasing the tensioning control force and optimizing the anchoring process.
[0016] In the preferred embodiment, during the prestress loss calculation process in step S53, the total prestress loss is calculated by summing the above-mentioned losses, and the formula is expressed as follows: Based on the calculation results of the total prestress loss, the prestress loss is effectively compensated by increasing the tension control force and optimizing the anchoring system.
[0017] This invention provides a construction method for a combined support system for continuous beam construction in combined road and rail projects. Through the cooperation between the above-mentioned structures, it has the following beneficial effects: First, a combined scaffolding system that combines steel pipe scaffolding with full-span scaffolding can be adopted. After the upper beam is constructed, the disc-buckle scaffolding can be removed to construct the lower beam. The design of the combined scaffolding system meets the needs of different construction stages, eliminating the need for frequent replacement or adjustment of scaffolding, saving construction time and costs, greatly improving construction efficiency, and reducing construction difficulty. Secondly, during the installation of the support structure, the actual construction load of the beam was effectively simulated by applying loads at 0.6, 0.8, 1.0, and 1.2 times the design load in stages. This avoided the problem of excessive deformation of the support structure during subsequent construction due to insufficient preloading, ensuring the stability and safety of the support structure during construction and guaranteeing the construction quality of the beam. At the same time, it also prevented the support structure from being damaged by excessive preloading, thus extending its service life and reducing construction costs. Attached Figure Description
[0018] The present invention will be further described below with reference to the accompanying drawings and embodiments: Figure 1 This is a main view structural diagram of the process of this invention; Figure 2 This is an elevation view of the upper layer of the combined support system of the present invention; Figure 3 This is a lower elevation view of the combined support system of the present invention.
[0019] In the diagram: 1. Railway beam; 2. Highway beam; 3. Steel pipe pile; 4. Steel column; 5. Diagonal brace; 6. Horizontal brace; 7. Unloading block; 8. Ground sweeping bar; 9. Vertical pole; 10. Horizontal bar; 11. Diagonal bar; 12. Sealing bar. Detailed Implementation
[0020] To better understand the purpose, structure, and function of this invention, the embodiments and features described herein can be combined with each other without conflict. The invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0021] Example 1 like Figures 1-3 As shown in the figure, this embodiment illustrates a construction method for a combined support system for constructing a continuous beam in a combined road-railway project, including the following steps: S1. Foundation and scaffolding construction: Complete the construction of the foundation and upper and lower piers, and install the lower-level railway steel pipe scaffolding and the upper-level highway scaffolding. The specific steps are as follows: S11. Foundation and Pier Construction: Obtain geological survey results and carry out foundation construction based on the geological survey results; The bearing capacity of the foundation ranges from 150 to 300 kPa, and the verticality deviation of the pier body ranges from [missing information]. Column height and cross-sectional dimensions have an error range of ±20mm; concrete strength grade range is 100%. S12. Support installation: Obtain the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway, and determine the support installation data based on the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway.
[0022] S121. Installation of steel pipe supports for lower-level railway: Using total station and other surveying equipment, the position of steel pipe pile 3 is accurately determined, with a planar position deviation range of ±50mm.
[0023] Using appropriate piling equipment, specifically a hydraulic piling machine, the steel pipe piles 3 are driven vertically into the foundation, with the verticality deviation controlled within 1%.
[0024] The depth of steel pipe pile 3 into the soil is determined based on the geological survey report and the design bearing requirements, ensuring that the depth of the pile tip of steel pipe pile 3 into the bearing layer is 3m-7m to guarantee the bearing capacity of the foundation.
[0025] During the pile driving process, the verticality and penetration depth of the piles are monitored in real time, and measurements are taken every 2 meters. Any deviations are adjusted promptly.
[0026] After the pile driving is completed, the elevation of the top of the steel pipe pile is measured, with an error range of ±30mm. A steel column 4 is installed on the top of the completed steel pipe pile 3, and the bottom of the steel column 4 is connected to the top of the steel pipe pile 3 by welding or high-strength bolts.
[0027] Before connection, ensure that the contact surfaces of the top of the steel pipe pile 3 and the bottom of the steel column 4 are flat and clean. During welding, the weld height range is 8mm to 16mm, and the welding quality must meet the secondary weld standard. When using high-strength bolts, the tightening torque range is 400 N·m to 600 N·m to ensure a firm and reliable connection.
[0028] During the installation of steel column 4, the verticality deviation range is: The column height and the spacing deviation between adjacent steel columns 4 are ±20mm to ensure the accurate installation of subsequent diagonal bracing and horizontal bracing.
[0029] The position and elevation of the steel column 4 were measured and adjusted using a total station and a level. After each steel column 4 was installed, a measurement was performed to verify its position. Diagonal bracing 5 and horizontal bracing 6 were installed to enhance the stability of the support structure.
[0030] The diagonal brace 5 and the horizontal brace 6 are connected to the steel column 4 by welding or bolting.
[0031] During welding, the weld quality must meet the Class II weld standard; When bolting, the installation angle of the diagonal brace 5 is determined according to the design, and the angle between it and the steel column 4 is 45° to 60°. The angle error between the diagonal brace 5 and the steel column 4 is ±2°.
[0032] The horizontal bracing 6 is installed at different heights on the steel column 4, and the horizontal deviation range of the horizontal bracing 6 is ±10mm. The horizontal bracing 6 is installed first, followed by the diagonal bracing 5. During the installation process, measuring tools are used to monitor the position and angle of the diagonal bracing 5 and the horizontal bracing 6 in real time to ensure installation accuracy.
[0033] After installation, check the firmness of each connection point, and conduct visual inspection and non-destructive testing on the welds, including ultrasonic testing, to ensure there are no welding defects. Specifically, the bridge consists of railway beam 1 and highway beam 2. The main function of steel pipe piles 3 is to transfer various loads from the superstructure to the deep foundation. In the construction of the combined railway and highway bridge, it bears the weight of the supports from railway beam 1 and highway beam 2, resists vertical loads and horizontal loads, and prevents horizontal displacement of the supports and beams. The steel column 4 plays a crucial role in the support structure, transferring the loads from the railway beam 1, highway beam 2, and the support structure to the steel pipe piles 3 below. The steel column 4, together with the diagonal braces 5 and horizontal bracing 6, forms a stable spatial structure. As the main vertical component, it, together with the horizontal bars 10, constitutes the frame system, enabling the support structure to withstand loads from all directions. Under load, the steel column 4 transfers vertical forces to the foundation and, through its connection with other components, distributes horizontal forces throughout the entire support structure, ensuring the overall stability of the support. When the support is subjected to horizontal loads, such as wind loads, the horizontal braking force of vehicles and trains, the diagonal bracing can convert the horizontal force into axial pressure or tension, effectively resisting the lateral deformation of the support and preventing the support from tilting or becoming unstable. During the construction of the beam, when one side is subjected to a large load, such as uneven concrete pouring, the diagonal bracing can transfer this load to other parts, avoiding damage to local components due to excessive stress. The horizontal bracing 6 is mainly used to connect adjacent steel columns or other vertical components, enabling them to work together in the horizontal direction. During bridge construction, the horizontal bracing 6 can evenly distribute horizontal forces across the various vertical components, preventing individual components from deforming or being damaged due to excessive horizontal forces. Perform torque checks on the bolt connections to ensure that the bolt tightening torque meets the requirements. Install unloading block 7 at the top of the steel column 4 near the railway beam 1. The installation position of unloading block 7 needs to be accurately measured and positioned, and the installation position deviation of unloading block 7 is ±10mm.
[0034] The contact surfaces of the unloading block 7 with the steel column 4 and the railway beam 1 must be flat and fit together, and fixed by welding or bolt connection.
[0035] Furthermore, the unloading block 7 can adjust the contact state between the beam and the support. It can compensate for any unevenness that may exist between the bottom surface of the beam and the top of the support, so that the load of the beam is transferred to the support more evenly. At the same time, when dismantling the support, the unloading block 7 can gradually release the pressure of the beam on the support, so as to achieve a safe and stable unloading process and avoid damage to the beam and support caused by sudden unloading. During welding, the weld height and length meet the design requirements, and the welding quality meets the relevant standards; when bolting, the tightening torque of the bolts is between 200 N·m and 300 N·m.
[0036] The material of the unloading block 7 is selected according to the design, possessing sufficient strength and elasticity, including rubber alloy materials. After installation, check the firmness of the unloading block 7 installation and its fit with the contact surface to ensure that the unloading block can effectively buffer and transfer the load; After the lower-level railway steel pipe supports are installed, a comprehensive inspection of the entire support system is conducted. The inspection includes checking the installation position, verticality, horizontality, connection strength, and installation of unloading blocks for each component. Using total stations and levels, the overall dimensions and elevation of the support system are measured and verified against the design drawings; any deviations are adjusted promptly. The welds and bolt connections at each joint are re-inspected to ensure there are no looseness or defects. The installation angle and connection of the diagonal braces 5 and the horizontal bracing 6 are checked to ensure the stability of the support system. During the inspection, any problems found are recorded in detail, and corrective measures are developed and implemented promptly to ensure the support system meets design and construction requirements. S122. Installation of the upper-level highway full-span scaffolding: In the full-span scaffolding, the lateral spacing between each adjacent upright 9 perpendicular to the longitudinal direction of the bridge ranges from 0.9m to 1.5m, and the longitudinal spacing between each adjacent upright 9 along the longitudinal direction of the bridge ranges from 0.6m to 1.2m. The step distance between each pair of adjacent horizontal bars 10 ranges from 1.2m to 1.8m. A ground-level bracing 8 is installed at the bottom of each upright 9, close to the ground, to ensure close contact with the load-bearing platform and uniform force distribution, forming a closed bottom frame structure. The horizontal bars 10 and diagonal bars 11 are firmly connected to the uprights 9 to form a stable triangular structure. The tightening torque of the connecting fasteners for the horizontal bars 10 ranges from 40N·m to 70N·m, and the spacing between each adjacent diagonal bar 11 ranges from 0.1m to 1m. The presence of the diagonal bars 11 can adjust the internal force distribution and force transmission path within the scaffolding structure. When the support is under load, the diagonal brace can change the direction of force transmission, distributing the load concentrated on some components to other components, making the stress on the entire support structure more uniform and reasonable. Specifically, during construction, the sweeping rod 8 prevents displacement of the bottom of the uprights 9, especially when subjected to horizontal forces such as wind or collisions with construction equipment. The sweeping rod 8 restricts the horizontal movement of the uprights 9. Simultaneously, the sweeping rod 8 transmits horizontal forces and distributes them evenly across all the uprights 9. When the support is subjected to a horizontal load, the sweeping rod 8, acting as a horizontal force-transmitting component, transfers the horizontal force from the loaded area to adjacent uprights 9, enabling all uprights 9 to collectively resist the horizontal force. The horizontal bar 10 is mainly used to connect adjacent vertical bars 9, forming a stable support structure in the horizontal direction. This ensures the stability of the vertical bars in the horizontal direction and prevents them from tilting or becoming unstable due to horizontal forces. In the full-span scaffolding of combined road and rail bridges, the horizontal bar 10 connects all the vertical bars 9 into a whole, working together to resist horizontal loads from the beam and the external environment. The horizontal bar 10 plays a role in distributing and transferring loads in the scaffolding structure. When the beam load is transferred to the scaffolding system through the vertical bars 9, the horizontal bar 10 can distribute the vertical load among adjacent vertical bars 9, making the load borne by each vertical bar more even and reasonable. Simultaneously, the horizontal bar 10 can also transfer horizontal loads, including the braking force of vehicles and trains, and wind loads, transferring these loads to the entire scaffolding system for all components to resist together. Among them, the upright 9 is the main vertical load-bearing component of the full-span scaffold, which is used to directly bear the vertical loads from the railway beam 1 and the highway beam 2; Specifically, in a full-span scaffold, the sealing rod 12 connects the edge uprights 9 to prevent the uprights 9 at the end of the scaffold from opening outward or deforming, thereby ensuring the integrity and stability of the scaffold structure. It is mainly used to seal the ends of the scaffold.
[0037] S2. Construction of the upper highway beam: Erect formwork, tie the reinforcing steel of the upper highway beam, pour concrete, tension prestressing, and then dismantle the upper support in sequence to complete the structural system conversion and the construction of the bridge deck system and traffic safety facilities. The specific steps are as follows: S21. Reinforcing bar binding: Based on the design drawings, accurately control the type, specifications, quantity, and position of the reinforcing bars. Use positioning bars and binding wire to firmly fix the reinforcing bars. The spacing of the positioning bars should be between 10cm and 50cm. The tightening method and degree of the binding wire should ensure that the reinforcing bars do not shift during the concrete pouring process.
[0038] To ensure the thickness of the concrete cover for reinforcing bars is between 30mm and 50mm, plastic spacers or concrete cover positioning devices can be used for control. The spacing between the spacers or positioning devices should be between 0.1m and 1m.
[0039] S22. Concrete Pouring: A layered pouring method is adopted, with each layer ranging from 30cm to 50cm in thickness. An immersion vibrator is used for rapid insertion and slow withdrawal, with the spacing between vibration points being 1 to 1.5 times the radius of action of the vibrator. During the pouring process, the concrete pouring speed is controlled and determined based on the concrete supply capacity, formwork bearing capacity, and vibration effect. The hourly pouring volume is 70% to 80% of the formwork's design bearing capacity.
[0040] Simultaneously, monitor the concrete slump, maintaining it within the range of 160mm to 200mm to ensure workability and density. During pouring, take care to avoid the vibrator touching the reinforcing bars and formwork to prevent displacement of the reinforcing bars and deformation of the formwork.
[0041] S23. Prestressing tensioning: When the concrete strength reaches 75% of the design strength, prestressing tensioning is performed. The tensioning is carried out according to the design-specified tensioning sequence and tensioning control force F. Sensors, including displacement sensors and pressure sensors, are installed on the tensioning equipment. A pressure sensor with a full-scale range of ±1% and a displacement sensor with an accuracy of ±1mm are used to monitor the tension force and the elongation ΔL of the prestressing tendon in real time. Based on the elastic modulus E, cross-sectional area A, and length L of the prestressing tendon, Hooke's law is applied. Calculate the theoretical elongation and compare it with the measured elongation, keeping the deviation within ±6%. If the deviation exceeds this range, tensioning should be stopped, the cause analyzed, and appropriate adjustments taken.
[0042] During the tensioning process, a dual-control method (i.e., tension force and elongation control) is adopted to ensure accurate application of prestress.
[0043] S24. Scaffold dismantling: When dismantling the upper full-span scaffold, dismantle each component in sequence according to the principle of first erecting and then dismantling, and last erecting and then dismantling.
[0044] The dismantling sequence is as follows: first, remove the sealing rod 12; then remove the diagonal rod 11 and the horizontal rod 10; and finally, remove the vertical rod 9. During the dismantling process, use a crane or other suitable lifting equipment to transport the dismantled components to a designated location for storage.
[0045] Demolition workers must wear safety belts and operate within designated safe areas; throwing objects is strictly prohibited. Warning signs should also be placed around the demolition area to prevent unauthorized personnel from entering.
[0046] S25. Structural system conversion and ancillary facility construction: After the scaffolding is removed, the structural system conversion shall be carried out.
[0047] The structural system includes the casting of guardrails, the installation of drainage pipes, expansion joints, and the construction of bridge deck paving. When pouring concrete for the guardrail, ensure its position is accurate, with a horizontal deviation of ±20mm and an elevation deviation of ±10mm. The concrete strength of the guardrail should meet the design requirements, and its appearance should be smooth, clean, and free from defects such as cracks, honeycombing, and pitting.
[0048] When installing drain pipes, ensure that the slope of the drain pipes is between 1% and 3%, and that the joints are tight to prevent leakage.
[0049] The installation temperature range for expansion joints is 10℃ to 25℃ to ensure that the expansion joints function normally and that the connection with the beam is firm and reliable.
[0050] When constructing the bridge deck paving, the surface of the beam is first cleaned and roughened to ensure a tight bond between the beam and the paving layer.
[0051] The thickness, flatness, and cross slope of the bridge deck pavement should meet the design requirements. The thickness error of the bridge deck pavement should be ±5mm, the flatness error range should be ±3mm, and the cross slope error range should be ±0.5%.
[0052] Vibrating beams and plate vibrators are used for compaction to ensure the density of the pavement layer.
[0053] S26. Bridge Inspection and Operation: After the completion of the bridge deck system and traffic safety facilities construction, a bridge inspection will be conducted. The inspection will cover aspects such as the concrete strength, appearance quality, structural dimensions, prestressing tension effect, bridge load-bearing capacity, and alignment of the beams. Concrete strength will be tested using methods such as rebound hammer testing and ultrasonic-rebound combined testing; the estimated strength value must meet the design strength grade requirements. Visual inspection will ensure the beams are free of cracks, deformation, and other defects. The bridge alignment will be checked using measuring instruments such as total stations and levels; its elevation and horizontal position deviations should be within the design allowable range. Only after passing the inspection can the bridge be put into operation. During operation, the bridge will be regularly monitored and maintained, including monitoring structural deformation, crack development, and bearing condition, to ensure the safe use of the bridge.
[0054] S3. Construction of the lower railway beam: After the upper highway beam has been inspected and accepted, the bottom formwork of the lower railway beam is installed and prestressed again. The supports are installed on the pier, the formwork is erected and the lower railway reinforcement is tied, concrete is poured, prestressing is applied, and the lower railway beam supports are dismantled in sequence to complete the construction of the railway bridge deck system and ancillary works. The specific steps are as follows: S31. Bottom formwork installation: When installing the bottom formwork, use a total station and a level to make accurate measurements, and control the elevation of the bottom formwork within ±5mm and the flatness error within ±3mm. The bottom formwork uses high-quality templates with a thickness of 18mm, and the joints are sealed with sealing strips or welding to ensure tightness and prevent grout leakage. At the same time, a release agent is applied to the surface of the bottom formwork to ensure the quality of the concrete surface. S32. Scaffold Preloading: Next, scaffold preloading is performed. The design load value P is calculated based on the beam's self-weight and construction load. Sandbags or water tanks are selected as the preloading material. The load is applied in stages of 0.6, 0.8, 1.0, and 1.2 times the design load. The holding time after each stage is 3 to 4 hours. During each stage, sensors are used to monitor the scaffold settlement and stress in real time. Data is recorded and a load-settlement curve (Ps curve) is plotted. If the scaffold settlement remains within ±2mm for 3 consecutive hours, the next stage of loading is performed. After preloading, the scaffold elevation is adjusted based on the settlement observation data to ensure the beam bottom formwork reaches the design elevation requirement, and the elastic deformation of the scaffold is within the range of 5mm to 10mm.
[0055] S33. Support installation: When installing supports on the pier, ensure that the support is in an accurate position. The deviation range of the support plane position is ±10mm and the deviation range of the elevation is ±5mm.
[0056] The connection between the support and the pier and beam is firm and reliable. When high-strength bolts are used, the tightening torque of the bolts is in the range of 300 N·m to 500 N·m, and anti-loosening treatment is carried out.
[0057] S34. Reinforcing bar binding: When binding the lower layer of railway reinforcing bars in the formwork, the reinforcing bars shall be of grade HRB400 or above, in accordance with the railway engineering design standards.
[0058] The reinforcing bars should be securely fixed using positioning bars and binding wires. The spacing between positioning bars should be 40cm to 50cm, and the tightening method and degree of binding wires should ensure that the reinforcing bars do not shift during concrete pouring. Ensure the thickness of the concrete cover is 30mm to 50mm, which can be controlled using concrete spacers or reinforcing bar cover positioning devices. The spacing between spacers or positioning devices should be 0.1m to 1m.
[0059] S35. Concrete Pouring: The concrete strength grade is C50, and appropriate pouring techniques and vibration methods are adopted. Before pouring, the raw materials are inspected to ensure that the cement, aggregates, admixtures, etc., meet the design and specification requirements. A layered pouring method is adopted, with each layer ranging from 30cm to 40cm in thickness. An immersion vibrator is used for rapid insertion and slow withdrawal vibration, and the spacing between vibration points ranges from 1 to 1.5 times the radius of action of the vibrator.
[0060] During the pouring process, the pouring speed of concrete is controlled and determined based on the concrete supply capacity, the formwork bearing capacity, and the vibration effect. The hourly pouring volume ranges from 60% to 70% of the formwork design bearing capacity.
[0061] Simultaneously, monitor the concrete slump, maintaining it within the range of 140mm to 180mm to ensure workability and density. During pouring, take care to avoid the vibrator touching the reinforcing bars and formwork to prevent displacement of the reinforcing bars and deformation of the formwork.
[0062] S36. Prestressing Tensioning: When the concrete strength reaches 80% of the design strength, prestressing is performed. The tensioning sequence must be strictly followed according to the railway engineering design, and even more stringent standards must be applied to control the tensioning force and elongation. Pressure sensors with an accuracy of ±1% of full scale and displacement sensors with an accuracy of ±1mm are installed on the tensioning equipment to monitor the tensioning force and prestressing tendon elongation in real time. Based on the elastic modulus of the prestressing tendons Cross-sectional area and length Using Hooke's Law Calculate the theoretical elongation and compare it with the measured elongation, with a deviation range of ±5%.
[0063] If the deviation exceeds the range, tensioning should be stopped, the cause analyzed, and corresponding measures taken for adjustment. During tensioning, a dual-control method (i.e., tension force and elongation control) is used to ensure accurate application of prestress.
[0064] S37. Scaffold dismantling: Dismantle the lower-level railway beam scaffolds according to the principle of dismantling the last scaffolds first and dismantling the last scaffolds first.
[0065] The dismantling sequence is as follows: first, remove the adjustable top support, then remove the diagonal brace (11) and horizontal bar (10), and finally remove the vertical bar (9).
[0066] During the dismantling process, cranes or other suitable lifting equipment will be used to transport the dismantled components to a designated storage location. Dismantling personnel must wear safety belts and operate within a safe area; throwing components is strictly prohibited. Warning signs will be placed around the dismantling area to prevent unauthorized personnel from entering.
[0067] S38. Construction of railway bridge deck system and ancillary works: When constructing railway bridge deck system and ancillary works, ensure that the track laying accuracy meets the requirements of railway specifications, with a track gauge error range of ±6mm, a track elevation deviation range of ±10mm, and a track flatness error range of ±3mm.
[0068] The installation of ancillary facilities such as cable troughs and sound barriers should be firm, reliable, and accurately positioned to meet the functional and safety requirements of railway operation. During construction, quality control and safety management should be strengthened to ensure both construction quality and safety.
[0069] The construction process from steps S1 to S3 above also includes step S4, which uses an AI model for data processing and construction control. This specifically includes the following steps: S41. Data Acquisition and Preprocessing Steps: Throughout the construction process, comprehensive data were collected on load, settlement, and time during the prestressing stage of the support frame; temperature, stress, and strain during concrete pouring; and tension force, elongation, and time during the prestressing process. The collected data underwent rigorous screening to remove obvious outliers and erroneous data. Data processing techniques such as moving average or Savitzky-Golay filtering were used to eliminate noise interference. The processed data was scientifically divided into a 70% training set, a 20% validation set, and a 10% test set to prepare for subsequent model training and validation.
[0070] S42. Model Selection and Training Steps: Based on the characteristics of the construction data and the prediction objectives, select an appropriate AI model, such as a neural network model or a support vector machine model.
[0071] For neural network models, the number of input layer nodes is determined based on the dimension of the input data, such as the number of variables like load, time, and temperature. Set the hidden layer structure to 2 to 3 layers, with 10 to 20 nodes in each layer, and determine the optimal hidden layer parameters through experimentation and optimization; The number of output layer nodes is determined based on the type of prediction results, including settlement prediction values and stress prediction values; The selected model is trained using the training set data. The backpropagation algorithm is used to dynamically adjust the model's weights and biases. A reasonable learning rate range is set to 0.001 to 0.01, the number of training epochs is set to 100 to 500, and the batch size is set to 32. Between 64; During training, the performance of the model is continuously evaluated using the validation set. The mean squared error (MSE) and mean absolute error (MAE) are used to measure the deviation between the predicted and the true values. Training is stopped when the validation set error no longer decreases to prevent overfitting. S43. Model Evaluation and Application Steps: Use the test set data to comprehensively evaluate the trained model, calculate the mean square error (MSE) and mean absolute error (MAE) of each evaluation index, and apply the model in actual construction if the model performance meets the predetermined requirements.
[0072] During the preloading stage of the support, the load data collected in real time is input into the model to quickly predict the settlement value and compare it with the measured settlement value. The subsequent loading strategy is adjusted in a timely manner according to the deviation. During the concrete pouring process, models are used to predict changes in concrete temperature stress, based on the concrete temperature stress calculation formula: ; in, The elastic modulus of concrete. This is the coefficient of linear expansion of concrete. The internal and external temperature difference of the concrete needs to be determined in actual calculations based on factors such as the concrete mix proportions, pouring time, and ambient temperature. and The value can be reduced by controlling the concrete pouring temperature and adopting heat preservation and curing measures. This reduces temperature stress and prevents concrete cracks from forming.
[0073] Based on the forecast results, take effective temperature control measures, including adjusting the curing temperature and optimizing the pouring time interval; During the prestressing stage, prestress loss is predicted using a model. This prestress loss includes losses caused by anchor deformation and prestressing tendon shrinkage. Losses caused by friction between prestressed tendons and the duct wall Losses caused by the temperature difference between the prestressed tendons under tension and the equipment bearing the tension during concrete heating and curing. Losses caused by stress relaxation of prestressed tendons Losses caused by concrete shrinkage and creep ; The calculation formulas for losses caused by anchor deformation and prestressed tendon shrinkage are as follows: ; in, This represents the deformation of the anchorage and the inward shrinkage of the prestressing tendons. This refers to the effective length of the prestressing tendon; The formula for calculating the loss caused by friction between the prestressing tendon and the duct wall is as follows: ; in, To control the tension stress, To account for the friction coefficient of local deviation per meter of duct length, The length of the duct from the tensioning end to the calculated cross-section. The coefficient of friction between the prestressing tendon and the duct wall is denoted as . It is the sum of the angles from the tensioning end to the tangents of the duct section of the calculated cross-section curve; Based on the predicted results, corresponding measures are taken during the tensioning process, including increasing the tensioning control force and optimizing the anchoring process, to ensure that the prestress of the beam meets the design requirements, effectively improve the crack resistance and load-bearing capacity of the beam, and ensure construction quality and safety.
[0074] In the prestress loss calculation process of step S53, in addition to calculating the losses caused by anchor deformation and prestressing tendon shrinkage according to the above formula, Losses caused by friction between prestressed tendons and the duct wall In addition, there are losses caused by the temperature difference between the prestressed tendons under tension and the equipment bearing the tension during concrete heating and curing. Losses caused by stress relaxation of prestressed tendons Losses caused by concrete shrinkage and creep The total prestress loss should also be calculated accurately according to the methods specified in relevant industry standards and design specifications. In actual engineering, the total prestress loss is calculated by summing up the above losses, as shown in the following formula: During the tensioning process, based on the calculation results of the total prestress loss, the prestress loss is effectively compensated by precisely increasing the tensioning control force and optimizing the anchoring system. This ensures that the prestress of the beam meets the design requirements throughout its entire service life, significantly improves the structural stability, crack resistance, and load-bearing capacity of the beam, and guarantees the safe operation of the bridge.
[0075] To enable those skilled in the art to better understand the present invention, the above embodiments are merely preferred technical solutions and should not be considered as limitations on the present invention. The scope of protection of the present invention should be defined by the technical solutions described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the scope of protection of the present invention.
[0076] It should also be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this invention are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate for the embodiments of the invention described herein.
Claims
1. A construction method for a combined support system for constructing a continuous beam in a combined road-railway project, characterized in that, Includes the following steps: S1. Foundation and scaffolding construction: Complete the construction of the foundation and the upper and lower piers, and install the lower railway steel pipe scaffolding and the upper highway scaffolding. A load-bearing block (7) is provided at the top of the steel column (4) near the railway beam (1), and the installation position deviation of the load-bearing block (7) is ±10mm; S2. Construction of the upper highway beam: Erect formwork, tie the steel bars of the upper highway beam, pour concrete, tension the prestressing, and dismantle the upper support in sequence to complete the structural system conversion and the construction of the bridge deck system and traffic safety facilities. Preloading of the support structure was carried out. The design load value P was calculated based on the beam's self-weight and construction load. Sandbags or water tanks were selected as the preloading material. The load was applied in stages at 0.6, 0.8, 1.0, and 1.2 times the design load. The holding time after each loading stage was 3 to 4 hours. During each loading stage, sensors were used to monitor the settlement and stress of the support structure in real time. Data was recorded and a load-settlement curve Ps was plotted. When the settlement of the support structure remained within ±2mm for 3 consecutive hours, the next loading stage was carried out. The elastic deformation of the support structure was controlled to be within the range of 5mm to 10mm. S3. Construction of the lower railway beam: After the upper highway beam is accepted, the bottom formwork of the lower railway beam is installed and prestressed repeatedly. The supports are installed on the pier. The formwork is erected and the lower railway steel bars are tied. Concrete is poured, prestressing is tensioned, and the lower railway beam supports are removed in sequence to complete the construction of the railway bridge deck system and ancillary works. During the prestressing stage, prestress loss is predicted using a model. This prestress loss includes losses caused by anchor deformation and prestressing tendon shrinkage. Losses caused by friction between prestressed tendons and the duct wall Losses caused by the temperature difference between the prestressed tendons under tension and the equipment bearing the tension during concrete heating and curing. Losses caused by stress relaxation of prestressed tendons Losses caused by concrete shrinkage and creep The total prestress loss is obtained by summing up the above losses. Based on the calculation results of the total prestress loss, the prestress loss is effectively compensated by increasing the tension control force and optimizing the anchoring system.
2. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 1, characterized in that, The specific steps of step S1 are as follows: S11. Foundation and Pier Construction: Obtain geological survey results and carry out foundation construction based on the geological survey results; The bearing capacity of the foundation ranges from 150 to 300 kPa, and the verticality deviation of the pier body ranges from [missing information]. The column height and cross-sectional dimensions have an error range of ±20mm. S12. Support installation: Obtain the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway, and determine the support installation data based on the minimum support for the lower-level railway steel pipes and the full support for the upper-level highway.
3. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 2, characterized in that, The specific steps in step S12 are as follows: S121, Installation of steel pipe supports for lower-level railway: The position of the steel pipe pile (3) is determined by measuring equipment, and the deviation range of the plane position of the steel pipe pile (3) is ±50mm; Using piling equipment, steel pipe piles (3) are driven vertically into the foundation, and the verticality deviation of the steel pipe piles (3) is within 1%; The depth of the steel pipe pile (3) into the soil is determined according to the geological survey report and the design bearing capacity, and the depth of the pile tip of the steel pipe pile (3) into the bearing layer is 3m-7m. The verticality and penetration depth of the piles are monitored in real time, and a measurement is performed every 2m of penetration. Once the piling is completed, the measurement error range of the top elevation of the steel pipe pile (3) is controlled to be ±30mm. A steel column (4) is set on the top of the steel pipe pile (3). The bottom of the steel column (4) is connected to the top of the steel pipe pile (3). The weld height range between the steel column (4) and the steel pipe pile (3) is 8mm to 16mm. The position and elevation of the steel column (4) are measured and adjusted using measuring equipment. A measurement check is performed once for each steel column (4) installed, and diagonal bracing (5) and horizontal bracing (6) are installed on the steel column (4). The horizontal bracing (6) is installed at different heights on the steel column (4). The horizontal deviation of the horizontal bracing (6) is ±10mm. The horizontal bracing (6) is installed first, and then the diagonal bracing (5) is installed. The position and angle of the diagonal bracing (5) and the horizontal bracing (6) are monitored in real time. After the installation of the lower-level railway steel pipe supports is completed, a comprehensive inspection of the support system is carried out. S122, Installation of the upper-level highway full-span scaffold: Multiple uprights (9) are provided on the full-span scaffold. The lateral spacing between each adjacent upright (9) perpendicular to the longitudinal direction of the bridge is 0.9m to 1.5m. The longitudinal spacing between each adjacent upright (9) along the longitudinal direction of the bridge is 0.6m to 1.2m. The step distance between each two adjacent horizontal bars (10) is 1.2m to 1.8m. Sweeping bars (8) are set at the bottom of each upright (9) and close to the ground to form a closed bottom frame structure. The uprights (9) are connected to the horizontal bars (10) and diagonal bars (11) to form a triangular structure. A sealing rod (12) is provided on the upright (9). The sealing rod (12) connects the upright (9) at the edge to prevent the upright (9) at the end of the support from opening outward or deforming.
4. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 3, characterized in that, In step S121, the verticality deviation range of the steel column (4) is: The column height, the spacing deviation between adjacent steel columns (4) is ±20mm, the installation angle formed between the diagonal brace (5) and the steel column (4) is 45° to 60°, the angle error between the diagonal brace (5) and the steel column (4) is ±2°, and the tightening torque range of the connection between the steel column (4) and the steel pipe pile (3) is 400N. m to 600N m; In step S122, the tightening torque of the connecting fastener of the horizontal bar (10) is 40N. m to 70N m, the spacing between each adjacent diagonal bar (11) ranges from 0.1m to 1m.
5. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 3, characterized in that, The specific steps of step S2 are as follows: S21. Reinforcing bar binding: Reinforcing bars are fixed using positioning bars and binding wires. The spacing of the positioning bars is 10cm to 50cm, and the thickness of the concrete cover is determined to be 30mm to 50mm. S22. Concrete pouring: Layered pouring method shall be adopted, with each layer ranging from 30cm to 50cm in thickness. An immersion vibrator shall be used for quick insertion and slow withdrawal for vibration, and the spacing between vibration points shall be 1 to 1.5 times the radius of action of the vibrator. The concrete pouring speed is determined based on the concrete supply capacity, formwork bearing capacity, and vibration effect, with the hourly pouring volume being 70% to 80% of the formwork's design bearing capacity. Among them, the slump of the monitored concrete is maintained within the range of 160mm to 200mm; S23. Prestressing tensioning: When the concrete strength reaches 75% of the design strength, the prestressing tensioning operation shall be performed. S24. Dismantling of the support: The upper full-span support is dismantled in sequence. The dismantling order is as follows: first, dismantle the sealing rod (12), then the diagonal rod (11) and the horizontal rod (10), and finally the vertical rod (9). The dismantled parts are hoisted to the designated location for storage using hoisting equipment. Warning signs are set up around the dismantling area. S25. Structural system conversion and ancillary facility construction: After the scaffolding is removed, the structural system conversion will be carried out; S26. Bridge Inspection and Operation: After the construction of the bridge deck system and traffic safety facilities is completed, a bridge inspection shall be carried out.
6. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 5, characterized in that, In step S23, the tensioning sequence and tensioning control force F are obtained, and sensors are installed on the tensioning equipment; The sensors include displacement sensors and pressure sensors; A pressure sensor with a full-scale range of ±1% and a displacement sensor with an accuracy of ±1mm are used to monitor the tension force and the elongation ΔL of the prestressing tendon in real time. Based on the elastic modulus E, cross-sectional area A, and length L of the prestressed tendon, Hooke's law is applied. Calculate the theoretical elongation of the prestressing tendon, compare the theoretical elongation with the measured elongation, and the deviation range between the theoretical elongation and the measured elongation of the prestressing tendon is ±6%. If the deviation exceeds the set range, tensioning is stopped.
7. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 6, characterized in that, In step S25, the structural system includes casting guardrails, installing drainage pipes, expansion joints, and constructing bridge deck paving; During the pouring of the guardrail, the deviation of the guardrail's planar position is controlled within ±20mm, and the elevation deviation is controlled within ±10mm. During the installation of drainage pipes, the slope of the drainage pipes should be controlled within the range of 1% to 3%. The installation temperature range for expansion joints should be controlled between 10℃ and 25℃. During the bridge deck paving stage, the surface of the beam is first cleaned and roughened to ensure a tight bond between the beam and the paving layer. The thickness error of the bridge deck pavement is ±5mm, the flatness error range is ±3mm, and the cross slope error range is ±0.5%. Vibrating beams and plate vibrators are used to perform vibration and compaction.
8. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 7, characterized in that, The specific steps of step S3 are as follows: S31. Bottom formwork installation: During the bottom formwork installation stage, measuring equipment is used to measure and control the bottom formwork elevation error to ±5mm and the flatness error to ±3mm. The bottom mold uses a template with a thickness of 18mm, and the joints are sealed to prevent grout leakage. A release agent is applied to the surface of the bottom mold. S32. Preloading of the support: After preloading is completed, the elevation of the support is adjusted according to the settlement observation data; S33. Support installation: When installing supports on the pier, the deviation range of the plane position of the support shall be ±10mm and the deviation range of the elevation shall be ±5mm. The supports are bolted to the pier and beam, and the tightening torque of the bolts is within 300 N. m to 500N m, and perform anti-loosening treatment.
9. The construction method of the combined support system for the construction of a combined railway and highway continuous beam according to claim 8, characterized in that, The construction process from steps S1 to S3 also includes step S4, which uses an AI model for data processing and construction control, specifically including the following steps: S41. Data Acquisition and Preprocessing Steps: Collect construction data for the support pre-stressing stage, concrete pouring process, and tensioning prestressing process, and perform preprocessing on the collected construction data. The preprocessed construction data was divided into three sets: 70% for training, 20% for validation, and 10% for testing. S42. Model Selection and Training Steps: Select a suitable AI model based on the preprocessed construction data, including neural network models or support vector machine models. A neural network model is used to determine the number of input layer nodes based on the dimension of the input data, including the number of variables such as load, time, and temperature. Set the hidden layer structure to 2 to 3 layers, with 10 to 20 nodes in each layer, and determine the optimal hidden layer parameters through experimentation and optimization; The number of output layer nodes is determined based on the type of prediction results, including settlement prediction values and stress prediction values; The selected model is trained using the training set data. The backpropagation algorithm is used to dynamically adjust the model's weights and biases. A reasonable learning rate range is set to 0.001 to 0.01, the number of training epochs is set to 100 to 500, and the batch size is set to 32 to 64. During training, the performance of the model is continuously evaluated using the validation set. The mean squared error (MSE) and mean absolute error (MAE) are used to measure the deviation between the predicted and the true values. Training is stopped when the validation set error no longer decreases to prevent overfitting. S43. Model Evaluation and Application Steps: Perform a comprehensive evaluation of the trained model using the test set data, calculate the mean square error (MSE) and mean absolute error (MAE) of each evaluation index, and apply the model in actual construction if the model performance meets the predetermined requirements. During the preloading stage of the support, load data is collected in real time and input into the model to quickly predict the settlement value. The value is then compared and analyzed with the measured settlement value, and the loading strategy is adjusted in a timely manner according to the deviation. During the concrete pouring process, models are used to predict changes in concrete temperature stress, based on the concrete temperature stress calculation formula: ; in, The elastic modulus of concrete. This is the coefficient of linear expansion of concrete. The temperature difference between the inside and outside of the concrete; Based on the forecast results, take effective temperature control measures, including adjusting the curing temperature and optimizing the pouring time interval; The calculation formulas for losses caused by anchor deformation and prestressed tendon shrinkage are as follows: ; in, This represents the deformation of the anchorage and the inward shrinkage of the prestressing tendons. This refers to the effective length of the prestressing tendon; The formula for calculating the loss caused by friction between the prestressing tendon and the duct wall is as follows: ; in, To control the tension stress, To account for the friction coefficient of local deviation per meter of duct length, The length of the duct from the tensioning end to the calculated cross-section. The coefficient of friction between the prestressing tendon and the duct wall is denoted as . It is the sum of the angles from the tensioning end to the tangents of the duct section of the calculated cross-section curve; Based on the predicted results, corresponding measures are taken during the tensioning process, including increasing the tensioning control force and optimizing the anchoring process.