Intelligent construction management system and method for overhead line system, electronic equipment and storage medium

Through the intelligent construction management system of the contact network, the automatic management of the entire process of contact network construction is achieved, the problems of low construction efficiency and insufficient mechanization rate are solved, and the level and efficiency of construction intelligence are improved.

CN119919071APending Publication Date: 2025-05-02CHINA RAILWAY CONSTR CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411768906.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-04
Publication Date
2025-05-02

AI Technical Summary

Technical Problem

During the construction of high-speed railway contact network, the construction efficiency is low and the mechanization rate and automation rate are insufficient, resulting in the construction quality dependent on the ability of technical workers and managers, making it difficult to improve the connection between processes and project progress.

Method used

It provides an intelligent construction management system for contact networks, including task creation module, data management module, provisioning management module, transportation management module and on-site management module. Through these modules, the full process management and automation of task creation, material preparation, provisioning and assembly, transportation and on-site installation are realized.

Benefits of technology

Through the digital data management platform, information drive and command sending and receiving of each subsystem are realized, information flow of the entire process is improved, the intelligent level of contact network construction is improved, and the construction efficiency of high-speed railway contact network is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119919071A_ABST
    Figure CN119919071A_ABST
Patent Text Reader

Abstract

The invention relates to an intelligent construction management system and method for a contact network, electronic equipment and a storage medium, and the system comprises a task creation module which is used for responding to a task creation instruction, creating a test task, and obtaining measurement data and design data required by the test task; the data management module is used for judging whether materials required by the test task are prepared or not based on the measurement data and the design data, and sending a material delivery instruction after determining that the materials are prepared; the pre-assembly management module is used for performing pre-assembly calculation based on the measurement data and the design data to obtain a pre-assembly calculation result, and performing pre-assembly assembly on parts in the materials to obtain construction components of the overhead line system; the transportation management module is used for responding to the transportation instruction, sequentially loading the construction components of the contact network into a finished product turnover box, loading the finished product turnover box, and then transporting the finished product turnover box to an installation site; and the on-site management module is used for responding to the on-site installation instruction and installing the construction component of the overhead line system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electrified railway overhead contact network engineering, and in particular to an overhead contact network intelligent construction management system, method, electronic equipment and storage medium. Background Art

[0002] The contact network of high-speed railway is an important part of the traction power supply system of high-speed railway. It is not only the only functional equipment of high-speed railway, but also the mechanical slideway of pantograph. Its safe operation is the key to ensure the safe, reliable and efficient operation of high-speed railway. The quality of contact network construction directly affects the safe operation of railway and social and economic benefits. The on-site installation operation of contact network construction includes: excavation of foundation pit, pouring foundation, assembling pillars, installing arm pre-equipment, erecting conductors, installing hanging strings, installing additional conductors and equipment, fine-tuning various equipment, prefabrication of materials, transportation and other processes.

[0003] In the relevant technologies, the construction process of the contact network mainly adopts an operation mode in which manual labor is the main method and machinery is the auxiliary method. The automation rate of the workshop pre-configuration process is low, and the mechanization rate of the overall construction process is low. The construction quality depends on the ability and level of technical workers and management personnel. This method is difficult to further improve the connection between the various processes, and the progress of the project is limited by the external material preparation period.

[0004] Therefore, how to improve the construction efficiency of high-speed railway contact network is a technical problem that needs to be solved urgently. Summary of the invention

[0005] In order to solve the above technical problems or at least partially solve the above technical problems, the present disclosure provides a contact network intelligent construction management system, method, electronic device and storage medium.

[0006] According to a first aspect of the present disclosure, there is provided a contact network intelligent construction management system, the system comprising:

[0007] A task creation module, used to create a test task in response to a task creation instruction, and obtain measurement data and design data required for the test task;

[0008] A data management module, used to determine whether the materials required for the test task are ready based on the measurement data and the design data, and send a material delivery instruction after determining that the materials required for the test task are ready;

[0009] A pre-configuration management module, used to perform pre-configuration calculation according to the measurement data and the design data, obtain pre-configuration calculation results, and pre-assemble the parts in the material based on the pre-configuration calculation results to obtain the construction components of the contact network;

[0010] A transport management module, for responding to a transport instruction, sequentially loading the construction components of the contact network into finished product turnover boxes, and loading the finished product turnover boxes onto trucks and transporting them to the installation site;

[0011] The on-site management module is used to respond to on-site installation instructions, install the construction components of the contact network at the installation site, and complete the installation of the contact network.

[0012] In an optional implementation, the task creation module is specifically used to create multiple sub-test tasks, select test circuits and test intervals corresponding to each of the multiple sub-test tasks, and measurement data and design data corresponding to each of the multiple sub-test tasks.

[0013] In an optional implementation, the system further includes: a material management module,

[0014] Used to receive the material outbound instruction sent by the data management module, and perform intelligent material outbound based on the measurement data and design data corresponding to each of the multiple sub-test tasks.

[0015] In an optional embodiment, the system further includes:

[0016] The intelligent assembly module is used to receive the materials transported by the material management module and to intelligently assemble the materials based on intelligent assembly equipment.

[0017] In an optional embodiment, the system further includes:

[0018] The parameter detection module is used to detect whether the installation data on site is consistent with the design data in response to the parameter detection instruction.

[0019] In an optional implementation, the design data includes: support column design data, arm design data, suspension string design data, arm component material basic data, and suspension string component material basic data.

[0020] In an optional implementation, the measurement data includes arm calculation measurement data and suspension string calculation measurement data.

[0021] According to a second aspect of the present disclosure, a method for intelligent construction management of a contact network is provided, the method comprising:

[0022] In response to the task creation instruction, create a test task and obtain measurement data and design data required for the test task;

[0023] Based on the measurement data and the design data, determine whether the materials required for the test task are ready, and after determining that the materials required for the test task are ready, send a material delivery instruction;

[0024] Performing pre-configuration calculation according to the measurement data and the design data to obtain pre-configuration calculation results, and pre-assembling the parts in the material based on the pre-configuration calculation results to obtain construction components of the contact network;

[0025] In response to the transport instruction, the construction components of the contact network are sequentially loaded into finished product turnover boxes, and the finished product turnover boxes are loaded onto trucks and then transported to the installation site;

[0026] In response to the on-site installation instruction, the construction components of the overhead contact network are installed at the installation site to complete the overhead contact network installation.

[0027] In an optional implementation, the creating a test task in response to a task creation instruction and acquiring measurement data and design data required for the test task includes:

[0028] A plurality of sub-test tasks are created, and test circuits and test intervals corresponding to the plurality of sub-test tasks and measurement data and design data corresponding to the plurality of sub-test tasks are selected.

[0029] In an optional implementation manner, after determining that the materials required for the test task are ready and sending the material delivery instruction, the method further includes:

[0030] Receive the material outbound instruction sent by the data management module, and perform intelligent material outbound based on the measurement data and design data corresponding to each of the multiple sub-test tasks.

[0031] In an optional implementation manner, before performing the pre-configuration calculation according to the measurement data and the design data and obtaining the pre-configuration calculation result, the method further includes:

[0032] Receive the materials transported by the material management module, and intelligently assemble the materials based on intelligent assembly equipment.

[0033] In an optional embodiment, in response to the on-site installation instruction, after installing the construction components of the contact network at the installation site and completing the contact network installation, the process further includes:

[0034] In response to the parameter detection instruction, it is detected whether the installation data at the site is consistent with the design data.

[0035] In an optional implementation, the design data includes: support column design data, arm design data, suspension string design data, arm component material basic data, and suspension string component material basic data.

[0036] In an optional implementation, the measurement data includes arm calculation measurement data and suspension string calculation measurement data.

[0037] According to a third aspect of the present disclosure, there is provided an electronic device, including:

[0038] Processor; and

[0039] A memory, configured to store executable instructions of the processor;

[0040] The processor is configured to execute the method described in the second aspect by executing the executable instructions.

[0041] According to a fourth aspect of the present disclosure, a storage medium is provided, on which a computer program is stored, and when the computer program is executed by a processor, the method described in the second aspect is implemented.

[0042] Compared with the prior art, the technical solution provided by the embodiments of the present disclosure has the following advantages:

[0043] The contact network intelligent construction management system of the disclosed embodiment covers all links of the whole process of contact network construction, that is, in response to the task creation instruction, a test task is created, the measurement data and design data required for the test task are obtained, and in the material management module, the material required for the test task is queried based on the measurement data and design data to see whether the material is ready. After determining that the material required for the test task is ready, a material outbound instruction is sent, and then a pre-configuration calculation is performed according to the measurement data and design data of the test task, and the pre-configuration calculation result is obtained. The parts in the material are pre-assembled and assembled based on the pre-configuration calculation result, the construction components of the contact network are obtained, and in response to the transportation instruction, the construction components of the contact network are sequentially loaded into the finished product turnover box, and the finished product turnover box is loaded and transported to the installation site, and in response to the on-site installation instruction, the construction components of the contact network are installed at the installation site to complete the contact network installation. In this way, the digital data management platform drives information and sends and receives instructions to each subsystem, realizes the information flow of the whole process, improves the intelligent level of contact network construction, and thus improves the construction efficiency of the high-speed railway contact network. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present disclosure and, together with the description, serve to explain the principles of the present disclosure.

[0045] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0046] Figure 1It is a structural diagram of the overhead line intelligent construction management system in the embodiment of the present disclosure;

[0047] Figure 2 A flow chart of the contact network intelligent construction management method in the embodiment of the present disclosure;

[0048] Figure 3 A schematic diagram of the structure of an electronic device in an embodiment of the present disclosure. DETAILED DESCRIPTION

[0049] In order to more clearly understand the above-mentioned objectives, features and advantages of the present disclosure, the scheme of the present disclosure will be further described below. It should be noted that the embodiments of the present disclosure and the features in the embodiments can be combined with each other without conflict.

[0050] In the following description, many specific details are set forth to facilitate a full understanding of the present disclosure, but the present disclosure may also be implemented in other ways different from those described herein; it is obvious that the embodiments in the specification are only part of the embodiments of the present disclosure, rather than all of the embodiments.

[0051] Terminology explanation:

[0052] High-speed railway contact network: It is a transmission line erected above the railway line to supply power to electric locomotives. The current that high-speed trains rely on is transmitted through the contact network on the top of the locomotive. Once the contact network is powered off, or the train pantograph has poor contact with the contact network, the power supply of the train will be affected. The contact network consists of contact suspension, support device, positioning device, pillars and foundation. The contact suspension includes contact wires, suspension strings, load-bearing cables and connecting parts. It is erected on the pillars through the support device. Its function is to transmit the electric energy obtained from the traction substation to the electric locomotive.

[0053] Train pantograph: also known as pantograph, is a key device for electrified railway trains to obtain electrical energy from the contact network.

[0054] Intelligent construction: It is a concept covering the three stages of design, production and construction of construction projects. It realizes data integration of the entire industry chain through the use of advanced information technologies such as the Internet, big data, BIM, etc., and provides support for full life cycle management. The purpose of intelligent construction is to improve the intelligence level of the construction process, reduce dependence on people, and achieve the purpose of safe construction. The intelligent construction data management platform realizes data integration and command control management of each subsystem of the contact network intelligent construction, and supports traceability query. Data information management and command control of the entire process from material procurement, inventory management, pre-configuration management, transportation management, and on-site equipment management. As an important configuration and data analysis object, the data itself can not only support the management needs at the business level, but also meet the data display functions required for analysis. The system adopts the mode of "centralized storage, unified sending and receiving". The management platform automatically synchronizes the data of the entire process of warehousing, pre-configuration, transportation, and on-site installation through the interface, collects feedback systems, and issues planning instructions.

[0055] The following is a detailed introduction to the overhead line intelligent construction management system of the embodiment of the present disclosure. The overhead line intelligent construction management system is mainly implemented by means of a software interface.

[0056] See also Figure 1 , Figure 1 A schematic diagram of a structure of an overhead line intelligent construction management system in an embodiment of the present disclosure may include:

[0057] The task creation module 110 is used to create a test task in response to a task creation instruction, and obtain measurement data and design data required for the test task.

[0058] In the disclosed embodiment, in response to the task creation instruction, a general task is created, and the general task plan can be created in sequence according to the sequence number. For example, general task 1 is a test data joint debugging task, and general task 2 is a full-process debugging of the general task, etc. Among them, the design data includes but is not limited to: support column design data and suspension string design data. The measurement data is to detect the bridge roadbed, measure the side limits, models, elevations, mileage positions of the reserved pillar foundations, and detect the reserved contact network foundation bolt spacing, bolt status, exposed length, etc. It should be noted that the reserved contact network foundation bolt spacing, bolt status, exposed length and other data are detected on site and compared with the design data to determine whether they meet the preset standards.

[0059] In an optional implementation, the design data includes: support column design data, arm design data, suspension string design data, arm component material basic data, and suspension string component material basic data.

[0060] In the disclosed embodiment, the design data of the hanging pillar includes but is not limited to the test section, up and down lines, pillar number, whether it is a hanging pillar, mileage, anchor section number, anchor section length, design span, guy wire pre-embedded direction, guy wire pre-embedded distance, exposed length of bolt, foundation bolt model, foundation bolt spacing, pillar model, slide chute length, slide chute model, side limit design length, and tunnel name.

[0061] In the disclosed embodiment, the arm design data includes but is not limited to the test section, up and down lines, pillar number, whether it is a hanging column, mileage, anchor section number, anchor section length, positioning form, industrial branch pull-out value, non-branch pull-out value, industrial branch contact line height, and non-branch contact line height.

[0062] In the embodiment of the present disclosure, the suspension string design data includes but is not limited to the test section, up and down lines, starting pillar number, number of suspension strings, ending pillar number, guide height, starting pillar mileage, ending pillar mileage, anchor section number, anchor section length, suspension type, front elastic suspension distance, rear elastic suspension distance, elastic sling tension, front first suspension string distance, and rear first suspension string distance.

[0063] In the disclosed embodiment, the basic data of the materials of the arm components include but are not limited to the pillar number, arm positioning direction, component name, component specification model, component quantity, and component unit.

[0064] In the embodiment of the present disclosure, the basic data of the materials of the suspension string components include but are not limited to the pillar number, the number of suspension strings, the component name, the component specification model, the component quantity, and the component unit.

[0065] In an optional implementation, the measurement data includes arm calculation measurement data and drop string calculation measurement data.

[0066] In the disclosed embodiment, the arm calculation and measurement data include but are not limited to the pillar number, side limit, pillar inclination, working branch pull-out value (positive on the left and negative on the right), non-working branch pull-out value (positive on the left and negative on the right), right rail superelevation distance, upper arm base height, lower arm base height, contact line height, and load-bearing cable base type.

[0067] In the disclosed embodiment, the calculation and measurement data of the suspension strings include but are not limited to the pillar name, span, number of suspension strings, track superelevation distance, suspension type, front elastic suspension distance, rear elastic suspension distance, elastic suspension cable tension, front first suspension string distance, and rear first suspension string distance.

[0068] In an optional implementation, the task creation module 110 is specifically used to create multiple sub-test tasks, select test circuits and test intervals corresponding to each of the multiple sub-test tasks, and measurement data and design data corresponding to each of the multiple sub-test tasks.

[0069] Among them, multiple sub-test tasks include: pillar assembly task, arm installation task, arm tray and loading task, wire laying task, hanging string installation task, hanging string tray and loading task, etc.

[0070] In the disclosed embodiment, the system initiates a data collection task instruction, and the system and the on-site installation equipment automatically call an interface to obtain the instruction, and return the measurement data and design data required for each sub-test task of data collection.

[0071] The data management module 120 is used to query in the material management module whether the materials required for the test task are ready based on the measurement data and the design data, and after determining that the materials required for the test task are ready, send a material outbound instruction to the material management module.

[0072] In the disclosed embodiment, a subtask is created by the system, such as a pillar assembly task, a wrist arm installation task, a wrist arm tray and material loading task, a wire laying task, a hanging string installation task, a hanging string tray and material loading task, etc., to determine whether the materials involved in the task are ready. After determining that the materials required for the task are ready, a material outbound instruction is sent. If the materials required for the task are not ready, wait for the material warehouse to prepare the materials.

[0073] In an optional implementation, the system further includes: a material management module, configured to receive a material delivery instruction sent by the data management module, and perform intelligent delivery of materials based on the measurement data and design data corresponding to each of the plurality of sub-test tasks.

[0074] Exemplarily, the system initiates the task of creating a pillar assembly, which includes: selecting the line, section, pillar number, and determining whether the pillars involved are ready. When selecting the pillars to be assembled, only pillars that have passed the interface basic inspection can be selected. For example, the starting number and the ending number of the pillar group can be selected, and then the set of pillars to be assembled this time can be determined through a union operation. Among them, pillar assembly is a key link in the construction of high-speed railway contact network, which involves accurately installing the contact network pillars to the predetermined position.

[0075] Exemplarily, the system initiates the task of creating a column assembly, which includes: selecting the line, section, column number, and determining whether the columns involved are ready. When selecting columns to be assembled, only columns that have passed the interface foundation inspection can be selected. For example, the starting number and the ending number of the column group can be selected, and then the set of columns to be assembled this time can be determined by a union operation. Among them, column assembly is an important link in the construction of electrified railway contact network, which involves accurately installing the columns to the predetermined position.

[0076] In an optional embodiment, the system further includes:

[0077] The intelligent assembly module is used to receive the materials transported by the material management module and to intelligently assemble the materials based on intelligent assembly equipment.

[0078] For example, for the pillar assembly task, after the pillar assembly vehicle receives the pillars transported by the material management module, it completes the pillar assembly and feeds back the information of pillar assembly completion to the system. For the suspender column assembly task, after the suspender column assembly vehicle receives the suspender column transported by the material management module, it completes the suspender column assembly and feeds back the information of suspender column assembly completion to the system.

[0079] The pre-configuration management module 130 is used to perform pre-configuration calculations according to the measurement data and design data, obtain pre-configuration calculation results, and pre-assemble the parts in the materials based on the pre-configuration calculation results to obtain construction components of the contact network.

[0080] In the disclosed embodiment, when creating a cantilever arm installation task, only the assembled pillars or suspension columns can be selected. When creating a cantilever arm pre-configuration pallet and material loading task, it is necessary to manually select the type and quantity of materials required this time, as well as the pre-configuration platform pallet capacity.

[0081] Exemplarily, the system initiates the creation of a boom installation task, selects the line, section, and pillar number, determines which parts are needed for the planned boom installation, and sends them to the material management module. The material management module receives the data and inquires whether the materials involved have been prepared. If the materials involved have been prepared, the boom is pre-assembled. After the calculation is completed, the pre-assembly calculation results are obtained, and the parts in the materials are pre-assembled and assembled based on the pre-assembly calculation results to obtain the construction components of the contact network. After the system receives the boom pre-assembly completion information, it confirms that the planned boom pre-assembly is completed, and then executes the next step, that is, sending the boom transportation task instruction to the transportation management module.

[0082] Exemplarily, the system initiates the creation of a string installation task, selects the line, section, and pillar number, determines which parts are needed for the planned installation of the string, and sends them to the material management module. The material management module receives the data and inquires whether the materials involved are ready. If the materials involved are ready, the string pre-configuration task is issued. After the pre-configuration calculation is completed, the pre-configuration calculation result is obtained and sent to the string pre-configuration production platform. After receiving the data, the string pre-configuration production platform starts to pre-configure the string. When the string pre-configuration is completed, the completion information is fed back to the contact network intelligent construction management system. After the system receives the string pre-configuration completion information, it confirms that the planned string pre-configuration is completed, and then executes the next step, which is to send the string transportation task instruction to the transportation management module.

[0083] Furthermore, the system initiates the creation of a wire laying task, selects the line, section, starting pillar number, and ending pillar number, and determines whether the wire laying materials involved are ready in the material management module. If all the wire laying materials involved are ready, the wire laying task is issued. After receiving the wire laying completion information, the tension test instruction and the information of the early stage of the string installation are sent to the corresponding equipment to obtain the tension test result information and the test results before the string installation. It should be noted that when selecting the pillars for the planned wire laying, only the pillar section where the arm has been installed can be selected.

[0084] The transportation management module 140 is used to load the construction components of the contact network into finished product turnover boxes in sequence in response to transportation instructions, and load the finished product turnover boxes onto trucks and then transport them to the installation site.

[0085] In the disclosed embodiment, in response to the transport instruction, the construction components of the contact network are sequentially loaded into finished product turnover boxes, and the finished product turnover boxes are loaded onto trucks and then transported to the installation site.

[0086] The site management module 150 is used to install the construction components of the contact network at the installation site in response to the site installation instructions to complete the contact network installation.

[0087] In the disclosed embodiment, in response to the on-site installation instruction, the construction components of the overhead contact network are installed at the installation site to complete the installation of the overhead contact network.

[0088] The contact network intelligent construction management system of the disclosed embodiment covers all links of the whole process of contact network construction, that is, in response to the task creation instruction, a test task is created, the measurement data and design data required for the test task are obtained, and the materials required for the test task are queried based on the measurement data and design data. After determining that the materials required for the test task are ready, a material outbound instruction is sent, and then a pre-configuration calculation is performed according to the measurement data and design data of the test task, and the pre-configuration calculation result is obtained. Based on the pre-configuration calculation result, the parts in the material are pre-configured and assembled, and the construction components of the contact network are obtained. In response to the transportation instruction, the construction components of the contact network are sequentially loaded into the finished product turnover box, and the finished product turnover box is loaded and transported to the installation site. In response to the on-site installation instruction, the construction components of the contact network are installed at the installation site to complete the contact network installation. In this way, the digital data management platform drives information and sends and receives instructions to each subsystem, realizes the information flow of the whole process, improves the intelligent level of the contact network construction, and thus improves the construction efficiency of the high-speed railway contact network.

[0089] In an optional implementation, the contact network intelligent construction management system further includes a parameter detection module for detecting, in response to a parameter detection instruction, whether the on-site installation data is consistent with the design data.

[0090] In the disclosed embodiment, in response to the parameter detection instruction, it is detected whether the installation data at the site is consistent with the design data. If the installation data at the site is consistent with the design data, it is determined that the installation meets the expected standard.

[0091] In an optional implementation, the material management module includes: a material inventory information query unit, a material inventory information management unit, a material supplier information management unit, and a planned task management unit;

[0092] The material inventory information query unit is used to query material entry records, material exit records and material classification in response to inventory query instructions;

[0093] The material inventory information management unit is used to respond to inventory management instructions, apply for material procurement plans, manage material warehousing plans, and manage material outbound plans;

[0094] The material supplier information management unit is used to respond to the supplier information query instruction, query the material supplier information and manage the material supplier warehousing application;

[0095] The planned task management unit is used to receive the test task created by the task creation module and divide the test task into nodes.

[0096] In the disclosed embodiment, the material management module effectively and dynamically controls production materials from procurement, assembly and transportation in the system based on the Internet of Things technology. The material management module is equipped with a material traceability function to realize the unique identification and information recording of materials, and quickly locate the production batch, the source of the problem, and the direction of the same batch of materials. The material management module also has functions such as real-time monitoring, intelligent scheduling, and fault warning to improve the safety of material storage and transportation efficiency.

[0097] In an optional embodiment, the provisioning management module is also used to manage provisioning plans, manage materials, and manage finished product turnover boxes in response to provisioning management instructions; wherein, the management of provisioning plans includes querying provisioning plans, adding new provisioning plans, and querying provisioning progress; the management of materials includes the associated material outbound data and the management of material usage; the management of finished product turnover boxes includes querying the finished product turnover box list and querying historical records.

[0098] In the disclosed embodiment, the material outbound data is associated, and the system determines in advance which parts are needed for the contact network. The system determines the parts needed for the contact network based on the created tasks as well as the design data and measurement data. The purpose is to trace back to the parts supplier, parts production date and other information after the contact network is finally built.

[0099] In an optional embodiment, the transportation management module is also used to respond to transportation record query instructions, query transportation records, issue transportation instructions to intelligent transportation equipment, and associate finished product turnover boxes; wherein the transportation record query includes: transportation record query and waybill query.

[0100] In the embodiment of the present disclosure, the method of associating the turnover box is to associate the finished product code with the turnover box code when the finished product is loaded into the turnover box, and to associate by scanning the box body QR code. The purpose is to be able to trace the transportation information. The on-site pillar QR code can trace the information of the entire process of material storage, pre-distribution, transportation, and installation.

[0101] In an optional embodiment, the site management module is also used to respond to installation record query instructions, query installation records, issue installation instructions and associated transportation information to intelligent construction equipment; wherein, querying installation records includes: querying on-site installation progress and querying historical installation progress.

[0102] In an optional embodiment, the data management module is also used to store and process material procurement data, warehousing data, arm construction data, chord construction data, pillar on-site installation data, and suspender on-site installation data.

[0103] The contact network intelligent construction management system of the disclosed embodiment covers all links of the whole process of contact network construction, that is, in response to the task creation instruction, a test task is created, the measurement data and design data required for the test task are obtained, and in the material management module, the material required for the test task is queried based on the measurement data and design data to see whether the material is ready. After determining that the material required for the test task is ready, a material outbound instruction is sent, and then a pre-configuration calculation is performed according to the measurement data and design data of the test task, and the pre-configuration calculation result is obtained. The parts in the material are pre-assembled and assembled based on the pre-configuration calculation result, the construction components of the contact network are obtained, and in response to the transportation instruction, the construction components of the contact network are sequentially loaded into the finished product turnover box, and the finished product turnover box is loaded and transported to the installation site, and in response to the on-site installation instruction, the construction components of the contact network are installed at the installation site to complete the contact network installation. In this way, the digital data management platform drives information and sends and receives instructions to each subsystem, realizes the information flow of the whole process, improves the intelligent level of contact network construction, and thus improves the construction efficiency of the high-speed railway contact network.

[0104] Corresponding to the above system embodiment, the present disclosure also provides a method for intelligent construction management of overhead line, see Figure 2 , Figure 2 This is a flow chart of the contact network intelligent construction management method in the embodiment of the present disclosure, which may include the following steps:

[0105] Step S210, in response to a task creation instruction, creating a test task, and acquiring measurement data and design data required for the test task.

[0106] Step S220: Based on the measurement data and the design data, determine whether the materials required for the test task are ready. After determining that the materials required for the test task are ready, send a material delivery instruction.

[0107] Step S230, performing pre-configuration calculation according to the measurement data and the design data, obtaining pre-configuration calculation results, and pre-assembling the parts in the material based on the pre-configuration calculation results to obtain construction components of the contact network.

[0108] Step S240, in response to the transport instruction, the construction components of the contact network are sequentially loaded into finished product turnover boxes, and the finished product turnover boxes are loaded on trucks and then transported to the installation site.

[0109] Step S250, in response to the on-site installation instruction, installing the construction components of the contact network at the installation site to complete the installation of the contact network.

[0110] In an optional implementation, the creating a test task in response to a task creation instruction and acquiring measurement data and design data required for the test task includes:

[0111] A plurality of sub-test tasks are created, and test circuits and test intervals corresponding to the plurality of sub-test tasks and measurement data and design data corresponding to the plurality of sub-test tasks are selected.

[0112] In an optional implementation manner, after determining that the materials required for the test task are ready and sending the material delivery instruction, the method further includes:

[0113] Receive the material outbound instruction sent by the data management module, and perform intelligent material outbound based on the measurement data and design data corresponding to each of the multiple sub-test tasks.

[0114] In an optional implementation manner, before performing the pre-configuration calculation according to the measurement data and the design data and obtaining the pre-configuration calculation result, the method further includes:

[0115] Receive the materials transported by the material management module, and intelligently assemble the materials based on intelligent assembly equipment.

[0116] In an optional embodiment, in response to the on-site installation instruction, after installing the construction components of the contact network at the installation site and completing the contact network installation, the process further includes:

[0117] In response to the parameter detection instruction, it is detected whether the installation data at the site is consistent with the design data.

[0118] In an optional implementation, the design data includes: support column design data, arm design data, suspension string design data, arm component material basic data, and suspension string component material basic data.

[0119] In an optional implementation, the measurement data includes arm calculation measurement data and suspension string calculation measurement data.

[0120] The specific details of each step in the above method have been described in detail in the corresponding system, so they will not be repeated here.

[0121] The intelligent construction management of the contact network disclosed in the embodiment of the present disclosure drives information and sends and receives instructions to each subsystem through a digital data management platform, realizes the information flow of the entire process, improves the intelligence level of the contact network construction, and thus improves the construction efficiency of the high-speed railway contact network.

[0122] See also Figure 3 , Figure 3 This is a schematic diagram of the structure of an electronic device in an embodiment of the present disclosure. The specific embodiment of the present disclosure does not limit the specific implementation of the electronic device.

[0123] like Figure 3 As shown, the electronic device may include: a processor 302 , a communication interface 304 , a memory 306 , and a communication bus 308 .

[0124] in:

[0125] The processor 302 , the communication interface 304 , and the memory 306 communicate with each other via the communication bus 308 .

[0126] The communication interface 304 is used to communicate with other electronic devices or servers.

[0127] The processor 302 is used to execute the program 310, and specifically can execute the relevant steps in the above method embodiment.

[0128] Specifically, the program 310 may include program codes, which include computer operation instructions.

[0129] The processor 302 may be a central processing unit (CPU), or an application-specific integrated circuit (ASIC), or one or more integrated circuits configured to implement the embodiments of the present disclosure. The one or more processors included in the smart device may be processors of the same type, such as one or more CPUs; or processors of different types, such as one or more CPUs and one or more ASICs.

[0130] The memory 306 is used to store the program 310. The memory 306 may include a high-speed RAM memory, and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.

[0131] The specific implementation of each step in program 310 can refer to the corresponding description of the corresponding steps and units in the above method embodiment, which will not be repeated here. Those skilled in the art can clearly understand that for the convenience and simplicity of description, the specific working process of the above-described devices and modules can refer to the corresponding process description in the above method embodiment, which will not be repeated here.

[0132] As another aspect, the present disclosure further provides a computer-readable medium, which may be included in the device described in the above embodiment; or may exist independently without being assembled into the device. The above computer-readable medium carries one or more programs, and when the above one or more programs are executed, the above contact network intelligent construction management method is implemented.

[0133] The present disclosure also provides a computer program product, including computer instructions, which instruct a computing device to execute operations corresponding to the above-mentioned contact network intelligent construction management method.

[0134] It should be pointed out that, according to the needs of implementation, the various components / steps described in the embodiments of the present disclosure can be split into more components / steps, or two or more components / steps or partial operations of components / steps can be combined into new components / steps to achieve the purpose of the embodiments of the present disclosure.

[0135] The above-mentioned method according to the embodiment of the present disclosure may be implemented in hardware, firmware, or implemented as software or computer code that can be stored in a recording medium (such as a CD ROM, RAM, floppy disk, hard disk or magneto-optical disk), or implemented as computer code originally stored in a remote recording medium or a non-temporary machine-readable medium downloaded through a network and to be stored in a local recording medium, so that the method described herein can be stored in such software processing on a recording medium using a general-purpose computer, a dedicated processor or programmable or dedicated hardware (such as an ASIC or FPGA). It can be understood that a computer, a processor, a microprocessor controller or programmable hardware includes a storage component (e.g., RAM, ROM, flash memory, etc.) that can store or receive software or computer code, and when the software or computer code is accessed and executed by a computer, a processor or hardware, the contact network intelligent construction management method described herein is implemented. In addition, when a general-purpose computer accesses the code for implementing the contact network intelligent construction management method shown herein, the execution of the code converts the general-purpose computer into a dedicated computer for executing the contact network intelligent construction management method shown herein.

[0136] Those of ordinary skill in the art will appreciate that the units and method steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the embodiments of the present disclosure.

[0137] The above implementation methods are only used to illustrate the embodiments of the present disclosure, and are not limitations of the embodiments of the present disclosure. Ordinary technicians in the relevant technical field may make various changes and modifications without departing from the spirit and scope of the embodiments of the present disclosure. Therefore, all equivalent technical solutions also belong to the scope of the embodiments of the present disclosure. The scope of patent protection of the embodiments of the present disclosure should be defined by the claims.

[0138] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0139] The above description is only a specific embodiment of the present disclosure, so that those skilled in the art can understand or implement the present disclosure. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present disclosure. Therefore, the present disclosure will not be limited to the embodiments described herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A contact network intelligent construction management system, characterized in that: The system comprises: A task creation module, used to create a test task in response to a task creation instruction, and obtain measurement data and design data required for the test task; A data management module, used to determine whether the materials required for the test task are ready based on the measurement data and the design data, and send a material delivery instruction after determining that the materials required for the test task are ready; A pre-configuration management module, used to perform pre-configuration calculation according to the measurement data and the design data, obtain pre-configuration calculation results, and pre-assemble the parts in the material based on the pre-configuration calculation results to obtain the construction components of the contact network; A transport management module, for responding to a transport instruction, sequentially loading the construction components of the contact network into finished product turnover boxes, and loading the finished product turnover boxes onto trucks and transporting them to the installation site; The on-site management module is used to respond to on-site installation instructions, install the construction components of the contact network at the installation site, and complete the installation of the contact network.

2. The system according to claim 1, characterized in that The task creation module is specifically used to create multiple sub-test tasks, select test circuits and test intervals corresponding to each of the multiple sub-test tasks, and measurement data and design data corresponding to each of the multiple sub-test tasks.

3. The system according to claim 2, characterized in that The system further comprises: The material management module is used to receive the material delivery instruction sent by the data management module, and perform intelligent delivery of materials based on the measurement data and design data corresponding to each of the multiple sub-test tasks.

4. The system according to claim 3, characterized in that The system further comprises: The intelligent assembly module is used to receive the materials transported by the material management module and to intelligently assemble the materials based on intelligent assembly equipment.

5. The system according to claim 1, characterized in that The system further comprises: The parameter detection module is used to detect whether the installation data on site is consistent with the design data in response to the parameter detection instruction.

6. The system according to claim 1, characterized in that The design data include: support column design data, arm design data, suspension string design data, arm component material basic data, and suspension string component material basic data.

7. The system according to claim 1, characterized in that The measurement data include arm calculation measurement data and suspension string calculation measurement data.

8. A method for intelligent construction management of overhead contact network, characterized in that: The method comprises: In response to the task creation instruction, create a test task and obtain measurement data and design data required for the test task; Based on the measurement data and the design data, query in the material management module whether the materials required for the test task are ready, and after determining that the materials required for the test task are ready, send a material outbound instruction to the material management module; Performing pre-configuration calculation according to the measurement data and design data to obtain pre-configuration calculation results, and pre-assembling the parts in the material based on the pre-configuration calculation results to obtain construction components of the contact network; In response to the transport instruction, the construction components of the contact network are sequentially loaded into finished product turnover boxes, and the finished product turnover boxes are loaded onto trucks and then transported to the installation site; In response to the on-site installation instruction, the construction components of the overhead contact network are installed at the installation site to complete the overhead contact network installation.

9. An electronic device, characterized in that: include: processor; as well as A memory, configured to store executable instructions of the processor; Wherein, the processor is configured to perform the method of claim 8 by executing the executable instructions.

10. A storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the method according to claim 8 is implemented.