Energy isolation practical training device and training method for maintenance of static equipment in petrochemical industry
By designing the energy isolation training device for static equipment inspection and maintenance in the petrochemical industry, combining simulated petrochemical material media and training and assessment software system, the problem of energy isolation practical training in the existing technology has not been carried out in combination with specific petrochemical industry production devices, and efficient and safe energy isolation training has been achieved.
Patent Information
- Application Number
- CN202311387978.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-25
- Publication Date
- 2025-05-02
AI Technical Summary
The existing technology has not carried out practical training on energy isolation in combination with the process equipment conditions of specific petrochemical industry production equipment, and has not introduced simulated petrochemical material media to cooperate with energy isolation operations. It lacks the support for the simulation construction of practical multi-scenarios and the functions of the energy isolation training and assessment system.
Design a training device for inspection and maintenance of static equipment in the petrochemical industry, including the training device area, process flow chart, attachment management area and training and assessment software system. By simulating the process flow of the cold and low-voltage separator, combined with the sensor signal transmitting device and the process isolation method interactive selection module, the simulation operation training and assessment of the energy isolation scenarios of the inspection and maintenance process are realized.
The professionalism and authenticity of energy isolation training are improved, and the effective combination of practical training devices and training assessment software systems is achieved through linkage control and data interconnection, ensuring the safety of the training process, and multi-scene energy isolation training and assessment can be conducted according to the inspection and maintenance scenarios of different parts.
Smart Images

Figure CN119920135A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of safety management and control of inspection and maintenance in the petrochemical industry, and in particular relates to an energy isolation training device and a training method for inspection and maintenance of static equipment in the petrochemical industry. Background Art
[0002] In industries such as energy and chemical engineering, the loss of control over hazardous energy often leads to serious personal injury and death accidents. Some companies have implemented energy isolation and lockout management, locking hazardous energy through energy isolation and lockout to avoid direct contact between operators and hazardous energy, and using warning signs to warn other personnel. However, since the content of energy isolation management is closely related to the on-site process equipment conditions of the device and involves hazardous energy, in training practice, it only relies on training materials and classroom lectures, lacks effective operating methods, and it is difficult for operators to acquire the ability to perform energy isolation and lockout in actual application scenarios.
[0003] At present, there have been relevant studies on energy isolation training. Chinese invention patent CN111882938A discloses a training assessment and evaluation method for a one-stop lockout tagout training and assessment system, including a theoretical training module and a practical simulation electrical module. After the assessee passes the theoretical training, the practical simulation is performed through the practical simulation electrical module and the hydraulic and pneumatic module, integrating a set of lockout tagout training and implementation methods from the perspectives of training guides, equipment and methods. Chinese invention patent CN111192493A discloses a practical training device and training method for blind plate extraction and plugging operation training, and designs a practical training device for blind plate extraction and plugging operation training. The training of blind plate extraction and plugging operation is realized through a liquid level indicator, pressure gauge, pump and various valves interconnected between a horizontal tank and a vertical tank. Chinese utility model patent CN209785293U discloses a "lockout / tagout" operation operation training model, which is a training teaching aid for electrical isolation, including a power supply, a first-class energy isolation device, multiple second-class energy isolation devices, a splitter, a selection switch and multiple signal display devices.
[0004] However, the existing technology has not carried out practical training on energy isolation in combination with the process equipment conditions of specific petrochemical industry production units, has not introduced simulated petrochemical material media to cooperate with energy isolation operations, and lacks the support of simulation construction of multiple actual production scenarios and energy isolation training and assessment system functions. Summary of the invention
[0005] One purpose of the present invention is to provide an energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry, which effectively solves the problems that the prior art does not carry out energy isolation practical training in combination with the process equipment conditions of specific petrochemical industry production equipment and does not cooperate with energy isolation operations by introducing simulated petrochemical material media.
[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0007] A petrochemical industry static equipment inspection and maintenance energy isolation training device comprises a training device area, a process flow chart corresponding to the training device area, an accessory management area and a training assessment software system.
[0008] The training and assessment software system includes training scenarios and assessment scenarios.
[0009] The training device area includes a cold low-pressure separator. The feed end of the cold low-pressure separator is provided with a feed pipeline A for conveying cold high-fraction oil, a feed pipeline B for conveying sulfur-containing wastewater, a feed pipeline C for conveying low-fraction gas, a feed pipeline D for conveying softened water and a feed pipeline E for conveying hydrogen, a total of five feed pipelines. The other ends of the feed pipeline A and the feed pipeline B are both connected to the cold high-pressure separator, the other end of the feed pipeline C is connected to the hot low-fraction gas air cooler, the other end of the feed pipeline D is connected to the water injection tank, and the other end of the feed pipeline E is connected to the hydrogen tank.
[0010] The feed pipeline A, feed pipeline B and feed pipeline C are all provided with an 8-shaped blind plate, the feed pipeline D is provided with a first stop valve, a shower valve, a liquid level control valve and a second stop valve in sequence from the end close to the water injection tank, and the feed pipeline E is provided with a first stop valve, a check valve, a shower valve, an 8-shaped blind plate and a second stop valve in sequence from the end close to the hydrogen tank.
[0011] The discharge end of the cold low-pressure separator is provided with a discharge pipeline F for conveying low-fraction gas, a discharge pipeline G for conveying cold low-fraction oil, a discharge pipeline H for conveying reaction injection water, and a discharge pipeline I and a discharge pipeline J for conveying sulfur-containing wastewater. The other end of the discharge pipeline H is connected to a hot high-fraction gas air cooler, and the hot high-fraction gas air cooler is connected to the cold high-pressure separator.
[0012] The discharge pipeline F is provided with an 8-shaped blind plate, a shower valve, a flow transmitter, a first stop valve, a shower valve, a pressure control valve and a second stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline G is provided with an 8-shaped blind plate, a flow transmitter, a first stop valve, a shower valve, a flow control valve and a second stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline H is provided with a stop valve; the discharge pipeline I is provided with an 8-shaped blind plate, a first stop valve, a second stop valve, a liquid level control valve and a third stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline J is provided with a stop valve; the discharge pipeline I and the discharge pipeline J are connected to the discharge pipeline K after merging; the discharge pipeline K is provided with a first stop valve, a shower valve, a liquid level control valve and a second stop valve in sequence at the confluence point of the near-discharge pipeline I and the discharge pipeline J.
[0013] The 8-shaped blind plate is embedded with a sensor signal transmitting device, and the sensor signal transmitting device is connected to the training and assessment software system.
[0014] The materials in the training device area are replaced by safe media. The isolation points on each feed pipeline and each discharge pipeline in the training device area are equipped with a process isolation mode interactive selection module. The process isolation mode interactive selection module is connected to the training and assessment software system. Each isolation point on the process flow chart is marked with Arabic numerals.
[0015] The accessory management area is equipped with multiple sets of blind plates, locking accessories, multiple sets of safety locks and keys compatible with the safety locks. Signal transmitting devices are embedded in the blind plates, safety locks and locking accessories, and the signal transmitting devices are connected to the process isolation mode interactive selection module.
[0016] Furthermore, the process isolation mode interactive selection module includes an isolation point selection module and an intelligent sensing module, and the signal transmitting device is connected to the intelligent sensing module.
[0017] Furthermore, a first bypass branch is provided on the feed pipeline D, the first bypass branch spans a first stop valve and a second stop valve on the feed pipeline D, and a first bypass valve is provided on the first bypass branch.
[0018] Furthermore, a second bypass branch is provided on the discharge pipeline F, the second bypass branch spans the first stop valve and the second stop valve on the discharge pipeline F, and a second bypass valve is provided on the second bypass branch.
[0019] Furthermore, a third bypass branch is provided on the discharge pipeline G, the third bypass branch spans the first stop valve and the second stop valve on the discharge pipeline G, and a third bypass valve is provided on the third bypass branch.
[0020] Furthermore, a fourth bypass branch is provided on the discharge pipeline I, the fourth bypass branch spans the second stop valve and the third stop valve on the discharge pipeline I, and a fourth bypass valve is provided on the fourth bypass branch.
[0021] Furthermore, a fifth bypass branch is provided on the discharge pipeline K, the fifth bypass branch crosses the first stop valve and the second stop valve on the discharge pipeline K, and a fifth bypass valve is provided on the fifth bypass branch.
[0022] Furthermore, the cold low-pressure separator and each isolation point are provided with an acoustic and optical alarm device, and the acoustic and optical alarm device is connected to the training and assessment software system.
[0023] Furthermore, a smart touch panel is provided at each isolation point, and the smart touch panel integrates the process isolation mode interactive selection module.
[0024] Furthermore, the safety medium includes water and air, different liquid phase media are replaced by water mixed with inks of different colors, and different gas phase media are replaced by air mixed with gases of different colors.
[0025] Furthermore, the softened water is replaced by water, the cold high-fraction oil and the cold low-fraction oil are both replaced by water mixed with red ink, the sulfur-containing wastewater is replaced by water mixed with black ink, the low-fraction gas is replaced by air mixed with red gas, and the hydrogen is replaced by air mixed with blue gas.
[0026] Furthermore, the locking accessories include a plurality of locks and a plurality of warning signs.
[0027] Furthermore, the lock comprises a lock buckle and a chain.
[0028] Another object of the present invention is to provide a training method to effectively solve the problems that the prior art does not carry out energy isolation practical training in combination with the process equipment conditions of specific petrochemical industry production equipment and does not cooperate with energy isolation operations by introducing simulated petrochemical material media.
[0029] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0030] A training method using the petrochemical industry static equipment inspection and maintenance energy isolation training device as described in the above embodiment, comprising: in a specified inspection and maintenance operation scenario, analyzing process equipment conditions and formulating an energy isolation plan; selecting isolation points on a process flow chart, selecting an applicable process isolation method, and performing energy isolation and lockout operations on the selected isolation points; combining a process isolation method interactive selection module and a sensor signal transmitting device provided in the training device to achieve simulated operation training and assessment of energy isolation scenarios in the inspection and maintenance process.
[0031] Furthermore, trainees complete energy isolation operations under given process conditions and inspection and maintenance scenarios, including selecting isolation points, choosing isolation methods, confirming material medium isolation, executing lockout and tagout operations, and unlocking and tagout steps.
[0032] (1) In the isolation point selection step, the sources and types of hazardous materials in the equipment, system or environment in the work area should be identified, and the isolation points of the equipment, facilities and devices that need to be isolated should be defined and confirmed.
[0033] (2) In the isolation method selection step, determine the process isolation method based on the material type and the characteristics of the inspection and maintenance work.
[0034] (3) In the material medium isolation confirmation step, the pipelines and equipment are purged, cleaned, and tested to confirm that the hazardous materials have been cleared or isolated.
[0035] (4) When executing the lockout and tagout operation steps, select appropriate locks for lockout and tagout according to the determined isolation points and isolation methods. In scenarios involving the cooperation of production units and construction units, ensure that each isolation point is locked by the production unit and the construction unit respectively, and ensure that each isolation locking point is hung with an appropriate warning sign.
[0036] (5) In the unlocking and delisting step, unlocking and delisting are performed after confirming that the equipment and system reset meet the conditions for commissioning.
[0037] The beneficial technical effects of the present invention are:
[0038] (1) The present invention designs an energy isolation training device to simulate the process flow of an actual production device of a cold low-pressure separator, thereby improving the professionalism and authenticity of energy isolation training.
[0039] (2) The present invention realizes linkage control and data interconnection between the practical training device and the training and assessment software system by combining the sensor device design of the practical training device and various energy isolation accessories.
[0040] (3) The present invention ensures the safety of the training process by using safe media - water and air, rather than actual flammable and explosive media.
[0041] (4) The present invention can preset different energy isolation processes, focus points and scoring points in the training and assessment software system according to training needs and for inspection and maintenance scenarios of different parts, thereby realizing training and assessment of multi-scenario energy isolation, designing targeted practical training content for different types of trainees, shortening the training cycle of various types of trainees, and improving training effects. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] In order to clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0043] Figure 1 It is a process flow chart of the training device area of the present invention;
[0044] Figure 2 It is a schematic diagram of the connection structure of the training device area of the present invention;
[0045] Figure 3 It is a schematic diagram of the working principle of the training device of the present invention. DETAILED DESCRIPTION
[0046] Example 1
[0047] A petrochemical industry static equipment inspection and maintenance energy isolation training device, with a cold low-pressure separator 100 as the core equipment of the training device, a feed pipeline and a discharge pipeline are set according to process conditions, and an accessory management area and a training assessment software system 200 are set at the same time, such as Figure 3 As shown, the process isolation mode interactive selection module 300 of the isolation point set on the training device interacts with the training assessment software system for data information, thereby realizing the full recording of the training process and the automatic determination of the assessment results.
[0048] A petrochemical industry static equipment inspection and maintenance energy isolation training device includes a training device area, a process flow chart corresponding to the training device area, an accessory management area and a training assessment software system 200.
[0049] The training and assessment software system 200 includes training scenarios and assessment scenarios, and can set energy isolation operation procedures and training and assessment key points for the inspection and maintenance of different parts of the training device, and record and automatically determine the training and assessment results.
[0050] like Figure 1 and Figure 2 As shown, the training device area includes a cold low-pressure separator 100, and the feed end of the cold low-pressure separator 100 is provided with a feed pipeline A for conveying cold high-fraction oil, a feed pipeline B for conveying sulfur-containing wastewater, a feed pipeline C for conveying low-fraction gas, a feed pipeline D for conveying softened water and a feed pipeline E for conveying hydrogen, a total of five feed pipelines, the other ends of the feed pipeline A and the feed pipeline B are connected to the cold high-pressure separator 101, the other end of the feed pipeline C is connected to the hot low-fraction gas air cooler 102, the other end of the feed pipeline D is connected to the water injection tank 103, and the other end of the feed pipeline E is connected to the hydrogen tank 104.
[0051] The feed pipeline A is provided with an 8-shaped blind plate 3, the feed pipeline B is provided with an 8-shaped blind plate 2, and the feed pipeline C is provided with an 8-shaped blind plate 1. The feed pipeline D is provided with a first stop valve 9, a shower valve 10, a liquid level control valve 11 and a second stop valve 12 in sequence from one end near the water injection tank 103. The feed pipeline E is provided with a first stop valve 14, a check valve 15, a shower valve 16, an 8-shaped blind plate 17 and a second stop valve 18 in sequence from one end near the hydrogen tank 104.
[0052] The feed pipeline D is provided with a first bypass branch, the first bypass branch spans the first stop valve 9 and the second stop valve 12 on the feed pipeline D, and the first bypass branch is provided with a first bypass valve 13.
[0053] The discharge end of the cold low-pressure separator 100 is provided with a discharge pipeline F for conveying low-fraction gas, a discharge pipeline G for conveying cold low-fraction oil, a discharge pipeline H for conveying reaction injection water, and a discharge pipeline I and a discharge pipeline J for conveying sulfur-containing wastewater. The other end of the discharge pipeline H is connected to a hot high-fraction gas air cooler 105, and the hot high-fraction gas air cooler 105 is connected to the cold high-pressure separator 101. The discharge pipeline H conveys water to the cold high-pressure separator 101 for recycling.
[0054] The discharge pipeline F is provided with an 8-shaped blind plate 4, a shower valve 19, a flow transmitter 20, a first stop valve 21, a shower valve 22, a pressure control valve 23 and a second stop valve 24 in sequence from one end of the near-cold low-pressure separator 100.
[0055] The discharge pipeline F is provided with a second bypass branch, the second bypass branch spans the first stop valve 21 and the second stop valve 24 on the discharge pipeline F, and the second bypass branch is provided with a second bypass valve 25 .
[0056] The discharge pipeline G is provided with an 8-shaped blind plate 5, a flow transmitter 26, a first stop valve 27, a drainage valve 28, a flow control valve 29 and a second stop valve 30 in sequence from one end of the near-cold low-pressure separator 100.
[0057] The discharge pipeline G is provided with a third bypass branch, the third bypass branch spans the first stop valve 27 and the second stop valve 30 on the discharge pipeline G, and the third bypass branch is provided with a third bypass valve 31 .
[0058] The discharge pipeline H is provided with a stop valve 7.
[0059] The discharge pipeline I is provided with an 8-shaped blind plate 8, a first stop valve 32, a second stop valve 33, a liquid level control valve 34 and a third stop valve 35 in sequence from one end of the near-cold low-pressure separator 100.
[0060] The discharge pipeline I is provided with a fourth bypass branch, the fourth bypass branch spans the second stop valve 33 and the third stop valve 35 on the discharge pipeline I, and the fourth bypass branch is provided with a fourth bypass valve 36.
[0061] The discharge pipeline J is provided with a stop valve 6. The discharge pipeline I and the discharge pipeline J are connected to the discharge pipeline K after merging. The discharge pipeline K is provided with a first stop valve 37, a shower valve 38, a liquid level control valve 39 and a second stop valve 40 in sequence near the confluence point of the discharge pipeline I and the discharge pipeline J.
[0062] The discharge pipeline K is provided with a fifth bypass branch, the fifth bypass branch spans the first stop valve 37 and the second stop valve 40 on the discharge pipeline K, and the fifth bypass branch is provided with a fifth bypass valve 41 .
[0063] The 8-shaped blind plates are all embedded with a sensor signal transmitting device 201 , and the sensor signal transmitting device 201 is connected to the training and assessment software system 200 .
[0064] All materials in the training device area are replaced with safe media. In some specific embodiments, the safe media include water and air. Different liquid media are replaced with water mixed with inks of different colors, and different gas media are replaced with air mixed with gases of different colors. In some embodiments, the softened water is replaced with water, the cold high-fraction oil and the cold low-fraction oil are replaced with water mixed with red ink, the sulfur-containing wastewater is replaced with water mixed with black ink, the low-fraction gas is replaced with air mixed with red gas, and the hydrogen is replaced with air mixed with blue gas. The above media are all non-toxic and harmless, and do not have combustion and explosion characteristics.
[0065] Each isolation point on each inlet and outlet pipeline in the training device area is provided with a process isolation mode interactive selection module, and the process isolation mode interactive selection module is connected to the training assessment software system 200. Each isolation point on the process flow chart is marked with Arabic numerals to facilitate trainees' selection.
[0066] In some embodiments, a smart touch panel 202 is provided at each isolation point, and the smart touch panel integrates the process isolation mode interactive selection module.
[0067] The specific implementation method of the process isolation mode interactive selection module is to set an isolation point selection module and an intelligent sensing module at each isolation point. The isolation point selection module is used to select whether to determine the point as an isolation point, and the intelligent sensing module is used to collect signals emitted by blind plates, safety locks, locks and warning signs to determine their usage status.
[0068] The trainee first confirms whether to select the isolation point as the energy isolation point through the process isolation mode interactive selection module of the isolation point. The signal data is connected with the training and assessment software system 200. By presetting all process isolation mode options in the training and assessment software system 200 in advance and marking the correct options, after the trainee selects the corresponding option, the data is transmitted back to the system, and the system determines the selection result to determine whether the process isolation of this isolation point is effective.
[0069] The system's preset process isolation methods can be customized according to the material characteristics, process characteristics, and operation attributes of the equipment and pipelines. Specifically, they may include single-valve isolation method, double-valve isolation plus drain method, single-valve plus blind plate isolation method, pipeline disassembly isolation method, double partition and blind plate insertion method, etc.
[0070] After receiving the correct process isolation mode selection signal, the training and assessment software system 200 controls the opening and closing of the water source and gas source of the corresponding pipeline to ensure that after correct isolation, the water source and gas source automatically stop conveying the material medium.
[0071] The accessory management area is equipped with multiple sets of blind plates, locking accessories, multiple sets of safety locks and keys compatible with the safety locks. Signal transmitting devices are embedded in the blind plates, safety locks and locking accessories. The signal transmitting devices are connected to the intelligent sensor module of the process isolation mode interactive selection module.
[0072] In some embodiments, the accessory management area: (1) places 10 sets of blind plates (including gaskets), which are numbered B001, B002...B010, and the size of the blind plates meets the requirements of various flanges of the training device. A signal transmitter is embedded inside the blind plate, and the signal marks the number information of the blind plate. (2) Place 20 sets of safety locks and keys, the safety locks are numbered L001, L002...L020, and the keys are numbered K001, K002...K020, and the digital numbers of the safety locks and keys correspond one to one. A signal transmitter is embedded inside the safety lock, and the signal marks the number information of the safety locks and keys. (3) Place locking accessories such as locks and warning signs, and the locks include several lock buckles and several chains, and the warning signs include several pieces. The lock buckles, chains and warning signs are all embedded with signal transmitters, and the signals mark the type and number information of the locks.
[0073] In some specific embodiments, the cold low-pressure separator 100 and each isolation point are provided with an acoustic and optical alarm device 203, and the acoustic and optical alarm device 203 is connected to the training and assessment software system 200. If the energy isolation point is selected incorrectly or the process isolation method is selected incorrectly, the leakage of hazardous materials is simulated and the acoustic and optical alarm device 203 is triggered. If the blind plate, safety lock, lock and warning sign are not installed or hung as required, the leakage of hazardous materials is simulated and the acoustic and optical alarm device 203 is triggered. The correct or incorrect operation results of each isolation point are sent to the training and assessment software system 200, and the training and assessment software system 200 records the actual operation results.
[0074] Example 2
[0075] A training method using the petrochemical industry static equipment inspection and maintenance energy isolation training device described in Example 1, comprising:
[0076] S1. In the specified inspection and maintenance operation scenario, analyze the process equipment conditions, specifically the cold low-pressure separator 100 separates the three-phase medium of gas, oil and water, and outputs low-pressure gas, cold low-pressure oil and water respectively. Analyze the transmission pipelines of different characteristic media respectively and prepare energy isolation schemes.
[0077] S2. Select the isolation point on the process flow chart and choose the appropriate process isolation method to ensure that during the inspection and maintenance of the cold low-pressure separator 100 equipment body, the material media of each feed and discharge pipeline are effectively isolated to ensure the safety of the operators.
[0078] S3. Energy isolation and lockout and tagout operations are performed on the selected isolation points. The process isolation mode options are preset through the training and assessment software system 200. The correct options for the process isolation modes applicable to each isolation point are marked. The process isolation mode of the isolation point is selected on the process isolation mode interactive selection module set at the isolation point of the training device, and the lockout and tagout operation is performed. If the isolation point selection is wrong, the process isolation mode selection is wrong, or the lockout and tagout operation is wrong, the sound and light device alarm 203 may be triggered, and the signal is transmitted back to the training and assessment software system 200 to record the actual operation data and determine the assessment results, so as to realize the simulated operation training and assessment of the energy isolation scene of the inspection and maintenance process.
[0079] The training method specifically includes:
[0080] Under given process conditions and maintenance scenarios, in this embodiment, that is, the maintenance scenario of the cold low-pressure separator 100, the trainees complete the energy isolation operation, including selecting the isolation point, selecting the isolation method, confirming the isolation of the material medium, executing the lock-out and tag-out operations, and unlocking and de-tag-ing.
[0081] (1) In the isolation point selection step, the sources and types of hazardous materials in the equipment, system or environment in the work area should be identified, and the isolation points of the equipment, facilities and devices that need to be isolated should be defined and confirmed.
[0082] A selection confirmation operation is performed on the intelligent touch panel 202 of the selected isolation point, and the selected isolation point data is transmitted back to the training and assessment software system 200, and the system records the isolation point selection information.
[0083] (2) In the isolation method selection step, determine the process isolation method based on the material type and the characteristics of the inspection and maintenance work.
[0084] The process isolation method selection confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the process isolation method selection data is transmitted back to the training and assessment software system 200, and the system records the process isolation method selection information.
[0085] (3) In the blind plate plugging operation step, select a blind plate of appropriate size in the accessory area to perform the blind plate plugging operation, or adjust the blind pass state of the figure 8 blind plate.
[0086] After completion, the signal transmitting device embedded in the blind plate transmits a signal to the process isolation mode interactive selection module of the isolation point, and the data is transmitted back to the training and assessment software system 200, which records the blind plate plugging operation step information.
[0087] (4) In the material medium isolation confirmation step, the pipelines and equipment are purged, cleaned, and tested to confirm that the hazardous materials have been cleared or isolated.
[0088] After the simulation operation of this step is completed, a confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records the information of this step.
[0089] (5) When executing the lockout and tagout operation steps, select appropriate locks for lockout and tagout according to the determined isolation points and isolation methods. In scenarios involving the cooperation of production units and construction units, ensure that each isolation point is locked separately by the production unit and the construction unit, and ensure that each isolation locking point is hung with an appropriate warning sign.
[0090] If the simulated inspection and maintenance scenario involves the cooperation of the production unit and the construction unit, this mode needs to be selected in the training and assessment software system to ensure that each isolation point is locked separately by the production unit and the construction unit. The safety lock, lock and warning sign are connected to the process isolation mode interactive selection module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200, which records the error information such as wrong lock selection, no warning sign, and failure of the production unit and the construction unit to lock separately.
[0091] (6) In the unlocking and delisting step, unlocking and delisting are performed after confirming that the equipment and system reset meet the conditions for commissioning.
[0092] The safety locks, locks and warning signs are connected to the process isolation mode interactive selection module of the isolation point through the signal transmitting device, and the data is transmitted back to the training and assessment software system 200. The system records the error message of unlocking and removing the sign without confirming the commissioning conditions.
[0093] At the isolation point where the error information is recorded, the sound and light alarm device 203 can be triggered to start, and under the premise of safety, a small amount of colored water medium leakage and air medium spraying can be used to warn the trainees of their wrong operations.
[0094] The training and assessment software system 200 is logically divided into a training mode and an assessment mode. In the training mode, each time a step is completed, the training and assessment software system 200 can verify whether the step is correct. If all are correct, the next step operation is started; in the assessment mode, all steps must be completed and submitted. The system determines whether the operation of each step is correct. If there is an error, the corresponding isolation point triggers the alarm mechanism, and the system records detailed error information and assessment results. Specific embodiment 1:
[0096] Training scenario: During inspection and maintenance of the cold low-pressure separator 100, energy isolation operation needs to be performed on the cold low-pressure separator 100.
[0097] Step 1: Determine the energy isolation point.
[0098] Trainees should analyze the process equipment conditions, identify all feed lines, discharge lines and instruments of the cold low-pressure separator 100, analyze them one by one and determine the energy isolation points.
[0099] After analysis and confirmation, the 8-shaped blind plate 3 on the feed pipeline A, the 8-shaped blind plate 2 on the feed pipeline B, the 8-shaped blind plate 1 on the feed pipeline C, the 8-shaped blind plate 17 on the feed pipeline E, the feed end flange of the second stop valve 12 on the feed pipeline D, the 8-shaped blind plate 4 on the discharge pipeline F, the 8-shaped blind plate 5 on the discharge pipeline G, the feed end flange of the stop valve 6 on the discharge pipeline J, the feed end flange of the stop valve 7 on the discharge pipeline H and the 8-shaped blind plate 8 on the discharge pipeline I were selected as isolation points.
[0100] At the selected isolation point, the isolation point selection is confirmed through the intelligent touch panel 202. The selected isolation point data is transmitted back to the training and assessment software system 200, and the system records the isolation point selection information.
[0101] Step 2: Select the isolation method.
[0102] Trainees should determine the method of process isolation based on the material type and the characteristics of the inspection and maintenance operations.
[0103] In this specific embodiment, since flammable and explosive materials are involved, it is recommended to use double partitions and blind plate insertion isolation methods at each isolation point.
[0104] The process isolation method selection confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the process isolation method selection data is transmitted back to the training and assessment software system 200, and the system records the process isolation method selection information.
[0105] Step 3: Blind plate blocking operation.
[0106] Trainees select blind plates of appropriate sizes in the accessory management area to plug blind plates or adjust the blind-through state of the 8-shaped blind plates. In this specific embodiment, the states of the 8-shaped blind plate 17 on the feed pipeline E, the 8-shaped blind plate 1 on the feed pipeline C, the 8-shaped blind plate 2 on the feed pipeline B, the 8-shaped blind plate 3 on the feed pipeline A, the 8-shaped blind plate 4 on the discharge pipeline F, the 8-shaped blind plate 5 on the discharge pipeline G, and the 8-shaped blind plate 8 on the discharge pipeline I should be changed from open to blind-dead, and blind plates of appropriate sizes should be installed on the feed end flange of the second stop valve 12 on the feed pipeline D, the feed end flange of the stop valve 6 on the discharge pipeline J, and the feed end flange of the stop valve 7 on the discharge pipeline H.
[0107] After completion, the signal transmitter embedded in the blind plate transmits a signal to the intelligent sensor module at the isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records the blind plate blocking operation step information.
[0108] Step 4: Confirmation of material medium isolation.
[0109] Trainees conduct tests after purging and cleaning the pipelines and equipment to confirm that the hazardous materials have been cleared or isolated.
[0110] In this specific embodiment, the trainees purged and cleaned the cold high-fraction oil, low-fraction gas, hydrogen, softened water, cold low-fraction oil and sulfur-containing wastewater in the pipelines and equipment respectively.
[0111] After the simulation operation of this step is completed, a confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records the information of this step.
[0112] Step 5: Perform the lockout and tagout operation.
[0113] Trainees select appropriate locks and lock and tag out according to the determined isolation points and methods, ensuring that each isolation lock point is hung with a suitable warning sign.
[0114] In this specific embodiment, the production unit and the construction unit are involved in the coordinated operation, so it is necessary to select the production unit and the construction unit coordinated operation mode in the training and assessment software system 200 to ensure that each isolation point is locked by the production unit and the construction unit respectively.
[0115] The safety locks, locks and warning signs are connected to the intelligent sensor module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records error information such as incorrect lock selection, no warning signs, and failure of the production unit and the construction unit to lock separately.
[0116] Step 6: Unlock and delist.
[0117] Trainees will unlock and remove the card after confirming that the equipment and system reset meet the conditions for commissioning.
[0118] The safety locks, locks and warning signs are connected to the intelligent sensor module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records the error message of unlocking and removing the sign without confirming the commissioning conditions.
[0119] In the training scenario, the system records the isolation point of the error information, selectively triggers the sound and light alarm device 203 to start, and under the premise of safety, a small amount of colored water medium leakage and air medium spraying are used to warn the trainees of wrong operations.
[0120] In addition to the cold low-pressure separator 100 inspection and maintenance operation scenario, energy isolation training programs can be designed for the inspection and maintenance of other parts of the training device, such as energy isolation practical training and assessment for the inspection and maintenance scenario of a single valve in a pipeline. The specific implementation method is similar to the principle of this specific embodiment. Specific embodiment 2
[0122] Training scenario: To replace the liquid level control valve 39 on the discharge pipeline K, the liquid level control valve 39 on the discharge pipeline K needs to be energy isolated.
[0123] Step 1: Determine the energy isolation point.
[0124] Trainees should analyze the process equipment conditions, identify the feed pipeline, discharge pipeline and instrumentation of the liquid level control valve 39 on the discharge pipeline K, and analyze and determine the energy isolation points one by one.
[0125] After analysis and confirmation, the discharge end flange of the first stop valve 37, the feed end flange of the shower valve 38 and the feed end flange of the second stop valve 40 on the discharge pipeline K are selected as isolation points, and the fifth bypass valve 41 on the fifth bypass branch of the discharge pipeline K is opened at the same time to ensure the normal discharge of sulfur-containing wastewater.
[0126] At the selected isolation point, the isolation point selection is confirmed through the intelligent touch panel 202. The selected isolation point data is transmitted back to the training and assessment software system 200, and the system records the isolation point selection information.
[0127] Step 2: Select the isolation method.
[0128] Trainees should determine the method of process isolation based on the material type and the characteristics of the inspection and maintenance operations.
[0129] In this specific embodiment, since the material involved is sulfur-containing wastewater, it is recommended to use double partition and blind plate method isolation methods at each isolation point.
[0130] The process isolation method selection confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the process isolation method selection data is transmitted back to the training and assessment software system 200, and the system records the process isolation method selection information.
[0131] Step 3: Blind plate blocking operation.
[0132] Trainees select blind plates of appropriate sizes in the accessory area to plug blind plates or adjust the blind pass state of the 8-shaped blind plates. In this specific embodiment, blind plates of appropriate sizes should be installed on the discharge end flange of the first stop valve 37, the feed end flange of the shower valve 38, and the feed end flange of the second stop valve 40 on the discharge pipeline K.
[0133] After completion, the signal transmitter embedded in the blind plate transmits a signal to the intelligent sensor module at the isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records the blind plate blocking operation step information.
[0134] Step 4: Confirmation of material medium isolation.
[0135] Trainees conduct tests after purging and cleaning the pipelines and equipment to confirm that the hazardous materials have been cleared or isolated.
[0136] In this specific embodiment, the trainees purged and cleaned the sulfur-containing wastewater in the pipeline.
[0137] After the simulation operation of this step is completed, a confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records the information of this step.
[0138] Step 5: Perform the lockout and tagout operation.
[0139] Trainees select appropriate locks and lock and tag out according to the determined isolation points and methods, ensuring that each isolation lock point is hung with a suitable warning sign.
[0140] In this specific embodiment, the safety lock, lockset and warning sign are connected to the intelligent sensor module of the isolation point through a signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records error information such as incorrect lock selection and failure to hang a warning sign.
[0141] Step 6: Unlock and delist.
[0142] Trainees will unlock and remove the card after confirming that the equipment and system reset meet the conditions for commissioning.
[0143] The safety locks, locks and warning signs are connected to the intelligent sensor module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records the error message of unlocking and removing the sign without confirming the commissioning conditions.
[0144] In the training scenario, the system records the isolation point of the error information, selectively triggers the sound and light alarm device 203 to start, and under the premise of safety, a small amount of colored water medium leakage and air medium spraying are used to warn the trainees of wrong operations.
[0145] In addition to the inspection and maintenance operation scenario of the liquid level control valve 39 on the discharge pipeline K, an energy isolation training program can be designed for the inspection and maintenance of other parts of the training device, and the specific implementation method is similar to the principle of this specific embodiment. Specific embodiment 3:
[0147] Assessment scenario: To replace the liquid level control valve 34 on the discharge pipeline I, the liquid level control valve 34 on the discharge pipeline I needs to be energy isolated.
[0148] Step 1: Determine the energy isolation point.
[0149] Trainees should analyze the process equipment conditions, identify the feed pipeline, discharge pipeline and instrumentation of the liquid level control valve 34 on the discharge pipeline I, and analyze and determine the energy isolation point one by one.
[0150] After analysis and confirmation, the discharge end flange of the second stop valve 33 on the discharge pipeline I and the feed end flange of the third stop valve 35 are selected as isolation points, and the fourth bypass valve 36 on the fourth bypass branch of the discharge pipeline I is opened at the same time to ensure the normal discharge of sulfur-containing wastewater.
[0151] At the selected isolation point, the isolation point selection is confirmed through the smart touch panel 202. The selected isolation point data is transmitted back to the training and assessment software system 200, and the training and assessment software system 200 records the isolation point selection information and determines whether the selected isolation point can meet the energy isolation requirement.
[0152] Step 2: Select the isolation method.
[0153] Trainees should determine the method of process isolation based on the material type and the characteristics of the inspection and maintenance operations.
[0154] In this specific embodiment, since the material involved is sulfur-containing wastewater, it is recommended to use double partition and blind plate method isolation methods at each isolation point.
[0155] The smart touch panel 202 at the corresponding isolation point performs a process isolation method selection confirmation operation, and the process isolation method selection data is transmitted back to the training and assessment software system 200. The system records the process isolation method selection information and determines whether the selected isolation method can meet the energy isolation requirements.
[0156] Step 3: Blind plate blocking operation.
[0157] The trainee selects a blind plate of appropriate size in the accessory area to carry out the blind plate blocking operation or adjust the blind pass state of the 8-shaped blind plate. In this specific embodiment, a blind plate of appropriate size should be installed on the discharge end flange of the second stop valve 33 on the discharge pipeline I and the feed end flange of the third stop valve 35.
[0158] After completion, the signal transmitter embedded in the blind plate transmits a signal to the intelligent sensor module at the isolation point, and the data is transmitted back to the training and assessment software system 200. The system records the blind plate plugging operation step information and determines whether the blind plate type and size are selected correctly.
[0159] Step 4: Confirmation of material medium isolation.
[0160] Trainees conduct tests after purging and cleaning the pipelines and equipment to confirm that the hazardous materials have been cleared or isolated.
[0161] In this specific embodiment, the trainees purged and cleaned the sulfur-containing wastewater in the pipeline.
[0162] After the simulation operation of this step is completed, a confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records whether the information of this step is completed.
[0163] Step 5: Perform the lockout and tagout operation.
[0164] Trainees select appropriate locks and lock and tag out according to the determined isolation points and methods, ensuring that each isolation lock point is hung with a suitable warning sign.
[0165] In this specific embodiment, the safety lock, lockset and warning sign are connected to the intelligent sensor module of the isolation point through a signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records error information such as incorrect lock selection and failure to hang a warning sign.
[0166] Step 6: Unlock and delist.
[0167] Trainees will unlock and remove the card after confirming that the equipment and system reset meet the conditions for commissioning.
[0168] The safety locks, locks and warning signs are connected to the intelligent sensor module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records the error message of unlocking and removing the sign without confirming the commissioning conditions.
[0169] In the assessment scenario, the system automatically records the isolation points of the error information and scores them item by item.
[0170] Each time an operation is completed, the sound and light alarm device 203 is triggered to start, and a small amount of colored water medium leaks and air medium sprays under the premise of safety to warn the trainee of wrong operation. Once the sound and light alarm device 203 is triggered to start, the assessment is over.
[0171] In addition to the inspection and maintenance operation scenario of the liquid level control valve 34 on the discharge pipeline I, an energy isolation assessment plan can be designed for the inspection and maintenance of other parts of this training device, and the specific implementation method is similar to the principle of this specific embodiment. Specific embodiment 4
[0173] Assessment scenario: To replace the third bypass valve 31 provided on the third bypass branch on the discharge pipeline G, energy isolation operation needs to be performed on the flanges at both ends of the third bypass valve 31.
[0174] Step 1: Determine the energy isolation point.
[0175] Trainees should analyze the process equipment conditions, identify the feed pipeline, discharge pipeline and instruments of the third bypass valve 31 provided on the third bypass branch on the discharge pipeline G, and analyze and determine the energy isolation points one by one.
[0176] After analysis and confirmation, the feed end flange and the discharge end flange of the third bypass valve 31 on the third bypass branch on the discharge pipeline G are selected as isolation points. At the same time, ensure that the first stop valve 27, the shower valve 28, the flow control valve 29 and the second stop valve 30 on the discharge pipeline G are in the open state to ensure the normal discharge of the cold low-pressure oil.
[0177] At the selected isolation point, the isolation point selection is confirmed through the smart touch panel 202. The selected isolation point data is transmitted back to the training and assessment software system 200, and the training and assessment software system 200 records the isolation point selection information and determines whether the selected isolation point can meet the energy isolation requirement.
[0178] Step 2: Select the isolation method.
[0179] Trainees should determine the method of process isolation based on the material type and the characteristics of the inspection and maintenance operations.
[0180] In this specific embodiment, since the material involved is cold low-separation oil, it is recommended to use double partition and blind plate insertion process isolation methods at each isolation point.
[0181] The smart touch panel 202 at the corresponding isolation point performs a process isolation method selection confirmation operation, and the process isolation method selection data is transmitted back to the training and assessment software system 200. The system records the process isolation method selection information and determines whether the selected isolation method can meet the energy isolation requirements.
[0182] Step 3: Blind plate blocking operation.
[0183] The trainee selects a blind plate of appropriate size in the accessory area to plug the blind plate or adjust the blind state of the 8-shaped blind plate. In this specific embodiment, a blind plate of appropriate size should be installed on the feed end flange and the discharge end flange of the third bypass valve 31 on the third bypass branch on the discharge pipeline G.
[0184] After completion, the signal transmitter embedded in the blind plate transmits a signal to the intelligent sensor module at the isolation point, and the data is transmitted back to the training and assessment software system 200. The system records the blind plate plugging operation step information and determines whether the blind plate type and size are selected correctly.
[0185] Step 4: Confirmation of material medium isolation.
[0186] Trainees conduct tests after purging and cleaning the pipelines and equipment to confirm that the hazardous materials have been cleared or isolated.
[0187] In this specific embodiment, the trainee purged and cleaned the cold low-fraction oil in the pipeline.
[0188] After the simulation operation of this step is completed, a confirmation operation is performed on the smart touch panel 202 at the corresponding isolation point, and the data is transmitted back to the training and assessment software system 200, and the system records whether the information of this step is completed.
[0189] Step 5: Perform the lockout and tagout operation.
[0190] Trainees select appropriate locks and lock and tag out according to the determined isolation points and methods, ensuring that each isolation lock point is hung with a suitable warning sign.
[0191] In this specific embodiment, the safety lock, lockset and warning sign are connected to the intelligent sensor module of the isolation point through a signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records error information such as incorrect lock selection and failure to hang a warning sign.
[0192] Step 6: Unlock and delist.
[0193] Trainees will unlock and remove the card after confirming that the equipment and system reset meet the conditions for commissioning.
[0194] The safety locks, locks and warning signs are connected to the intelligent sensor module of the isolation point through the signal transmitter, and the data is transmitted back to the training and assessment software system 200. The system records the error message of unlocking and removing the sign without confirming the commissioning conditions.
[0195] In the assessment scenario, the system automatically records the isolation points of the error information and scores them item by item.
[0196] Each time an operation is completed, the sound and light alarm device 203 is triggered to start, and a small amount of colored water medium leaks and air medium sprays under the premise of safety to warn the trainee of wrong operation. Once the sound and light alarm device 203 is triggered to start, the assessment is over.
[0197] In addition to the inspection and maintenance operation scenario of the third bypass valve 31 on the third bypass branch on the discharge pipeline G, an energy isolation assessment plan can be designed for the inspection and maintenance of other parts of this training device, and the specific implementation method is similar to the principle of this specific embodiment.
[0198] It is worth noting that the terms "first" and "second" in the present invention are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. In the description of the present invention, unless otherwise specified, "multiple" and "several" mean two or more.
[0199] In the description of the present invention, unless otherwise clearly specified and limited, the terms "setting", "connection" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium; it can be a wired connection or a wireless connection. If the connection method is not specifically stated, conventional means mature in the prior art are adopted. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0200] In the description of this specification, the description with reference to the terms "some specific implementations" or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0201] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by technicians in this technical field within the essential scope of the present invention should also fall within the protection scope of the present invention.
Claims
1. A petrochemical industry static equipment inspection and maintenance energy isolation training device, characterized in that: It includes a practical training device area, a process flow chart corresponding to the practical training device area, an accessory management area and a training assessment software system; The training device area includes a cold low-pressure separator, and the feed end of the cold low-pressure separator is provided with a feed pipeline A for conveying cold high-fraction oil, a feed pipeline B for conveying sulfur-containing wastewater, a feed pipeline C for conveying low-fraction gas, a feed pipeline D for conveying softened water, and a feed pipeline E for conveying hydrogen, a total of five feed pipelines, the other ends of the feed pipeline A and the feed pipeline B are connected to the cold high-pressure separator, the other end of the feed pipeline C is connected to the hot low-fraction gas air cooler, the other end of the feed pipeline D is connected to the water injection tank, and the other end of the feed pipeline E is connected to the hydrogen tank; The feed pipeline A, feed pipeline B and feed pipeline C are all provided with an 8-shaped blind plate, the feed pipeline D is provided with a first stop valve, a shower valve, a liquid level control valve and a second stop valve in sequence from the end near the water injection tank, and the feed pipeline E is provided with a first stop valve, a check valve, a shower valve, an 8-shaped blind plate and a second stop valve in sequence from the end near the hydrogen tank; The feed pipeline D is provided with a first bypass branch, the first bypass branch crosses the first stop valve and the second stop valve on the feed pipeline D, and the first bypass branch is provided with a first bypass valve; The discharge end of the cold low-pressure separator is provided with a discharge pipeline F for conveying low-fraction gas, a discharge pipeline G for conveying cold low-fraction oil, a discharge pipeline H for conveying reaction injection water, and a discharge pipeline I and a discharge pipeline J for conveying sulfur-containing wastewater. The other end of the discharge pipeline H is connected to a hot high-fraction gas air cooler, and the hot high-fraction gas air cooler is connected to the cold high-pressure separator; The discharge pipeline F is provided with an 8-shaped blind plate, a shower valve, a flow transmitter, a first stop valve, a shower valve, a pressure control valve and a second stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline G is provided with an 8-shaped blind plate, a flow transmitter, a first stop valve, a shower valve, a flow control valve and a second stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline H is provided with a stop valve; the discharge pipeline I is provided with an 8-shaped blind plate, a first stop valve, a second stop valve, a liquid level control valve and a third stop valve in sequence from one end of the near-cold low-pressure separator; the discharge pipeline J is provided with a stop valve; the discharge pipeline I and the discharge pipeline J are connected to the discharge pipeline K after merging; the discharge pipeline K is provided with a first stop valve, a shower valve, a liquid level control valve and a second stop valve in sequence from the confluence point of the near-discharge pipeline I and the discharge pipeline J; The discharge pipeline F is provided with a second bypass branch, the second bypass branch crosses the first stop valve and the second stop valve on the discharge pipeline F, and the second bypass branch is provided with a second bypass valve; The discharge pipeline G is provided with a third bypass branch, the third bypass branch crosses the first stop valve and the second stop valve on the discharge pipeline G, and the third bypass branch is provided with a third bypass valve; The discharge pipeline I is provided with a fourth bypass branch, the fourth bypass branch crosses the second stop valve and the third stop valve on the discharge pipeline I, and the fourth bypass branch is provided with a fourth bypass valve; The discharge pipeline K is provided with a fifth bypass branch, the fifth bypass branch crosses the first stop valve and the second stop valve on the discharge pipeline K, and the fifth bypass branch is provided with a fifth bypass valve; The 8-shaped blind plate is embedded with a sensor signal transmitting device, and the sensor signal transmitting device is connected to the training and assessment software system; The materials in the training device area are replaced by safe media, and the isolation points on each feed pipeline and each discharge pipeline in the training device area are provided with a process isolation mode interactive selection module, and the process isolation mode interactive selection module is connected to the training assessment software system, and each isolation point on the process flow chart is marked; The accessory management area is equipped with multiple sets of blind plates, locking accessories, multiple sets of safety locks and keys compatible with the safety locks. Signal transmitting devices are embedded in the blind plates, safety locks and locking accessories, and the signal transmitting devices are connected to the process isolation mode interactive selection module.
2. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 1 is characterized in that: The cold low-pressure separator and each isolation point are provided with an acoustic and optical alarm device, and the acoustic and optical alarm device is connected to the training and assessment software system.
3. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 2 is characterized in that: An intelligent touch panel is arranged at each isolation point, and the intelligent touch panel integrates the process isolation mode interactive selection module.
4. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 3 is characterized in that: The process isolation mode interactive selection module includes an isolation point selection module and an intelligent sensing module, and the signal transmitting device is connected to the intelligent sensing module.
5. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 4 is characterized in that: The safety medium includes water and air, different liquid phase media are replaced by water mixed with inks of different colors, and different gas phase media are replaced by air mixed with gases of different colors.
6. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 5 is characterized in that: The softened water is replaced by water, the cold high-fraction oil and the cold low-fraction oil are both replaced by water mixed with red ink, the sulfur-containing wastewater is replaced by water mixed with black ink, the low-fraction gas is replaced by air mixed with red gas, and the hydrogen is replaced by air mixed with blue gas.
7. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 6 is characterized in that: The locking accessories include a plurality of locks and a plurality of warning signs.
8. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 7 is characterized in that: The lock comprises a lock buckle and a chain.
9. The energy isolation training device for inspection and maintenance of static equipment in the petrochemical industry according to claim 8 is characterized in that: The training and assessment software system includes training scenarios and assessment scenarios.
10. A training method using the petrochemical industry static equipment inspection and maintenance energy isolation training device according to any one of claims 1 to 9, characterized in that: include: Analyze process equipment conditions and prepare energy isolation plans in designated inspection and maintenance scenarios; Select the isolation point on the process flow chart, select the process isolation method, and perform energy isolation and lockout operations on the selected isolation point; combine the process isolation method interactive selection module and sensor signal transmitting device set up in the training device to achieve simulated operation training and assessment of the energy isolation scenario of the inspection and maintenance process.
11. The training method according to claim 10, characterized in that: Trainees complete energy isolation operations under given process conditions and maintenance scenarios, including selecting isolation points, selecting isolation methods, confirming material and medium isolation, and performing lockout and tagout operations and unlocking and tagout steps; In the isolation point selection step, the sources and types of hazardous materials in the equipment, system or environment in the work area should be identified, and the isolation points of the equipment, facilities and devices that need to be isolated should be defined and confirmed; In the isolation method selection step, the process isolation method is determined according to the material type and the characteristics of the inspection and maintenance operation; In the material and medium isolation confirmation step, the pipelines and equipment are purged and cleaned before testing to confirm that the hazardous materials have been emptied or isolated; In the lockout and tagout operation steps, select locks for lockout and tagout according to the determined isolation points and isolation methods. In scenarios involving the cooperation of production units and construction units, ensure that each isolation point is locked by the production unit and the construction unit respectively, and ensure that each isolation lock point is hung with a warning sign; In the unlocking and delisting step, unlocking and delisting are performed after confirming that the equipment and system reset meet the conditions for commissioning.
Citation Information
Patent Citations
Practical training device and training method for blind plate unblocking operation training
CN111192493A
Training assessment method for one-stop locking listing training assessment system
CN111882938A
Locking / listing operation training model
CN209785293U