A raised beam, tube, slab combined hybrid tower foundation structure

By using a raised, combined beam, tube, and slab hybrid tower foundation structure, the problems of high material costs, low construction efficiency, and poor stability of gravity foundations and beam-slab foundations in the wind power field are solved, achieving an efficient and economical foundation design that adapts to the construction needs of complex terrain and harsh environments.

CN121024108BActive Publication Date: 2026-07-21CHINA POWER CONSRTUCTION GRP GUIYANG SURVEY & DESIGN INST CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA POWER CONSRTUCTION GRP GUIYANG SURVEY & DESIGN INST CO LTD
Filing Date
2025-09-24
Publication Date
2026-07-21

AI Technical Summary

Technical Problem

Existing gravity foundations and beam-slab foundations in the wind power field suffer from high material costs, low construction efficiency, poor stability, easy settlement, and high maintenance costs, making it difficult to meet the foundation requirements of wind power in complex terrain and harsh environments.

Method used

The raised beam-tube-slab hybrid tower foundation structure optimizes the force transmission path, improves the foundation stiffness and stability, and simplifies the construction process by combining precast beams, cylindrical tubes, base plates, connecting pile caps, buttress columns, prestressed steel strand assemblies, and prestressed anchor bolt assemblies.

Benefits of technology

It improves the load-bearing capacity and durability of the foundation, reduces construction and maintenance costs, adapts to complex and ever-changing engineering environments, simplifies construction processes, and enhances construction quality and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN121024108B_ABST
    Figure CN121024108B_ABST
Patent Text Reader

Abstract

The application discloses a raised beam-tube-plate combined mixed-tower foundation structure. The mixed-tower foundation comprises a raised prefabricated beam, a cylindrical tube, a bottom plate, a connecting pile cap, a buttress column, a prestressed steel strand assembly and a prestressed anchor bolt assembly. The cylindrical tube is arranged above a ground surface and abuts against the ground surface. The buttress column is distributed along the circumference of the cylindrical tube and is integrally formed with the cylindrical tube by casting. The upper part of the raised prefabricated beam is arranged on the upper part of the buttress column and corresponds to the buttress column in a one-to-one manner in the circumferential direction. The bottom plate is integrally formed with the cylindrical tube and the bottom part of the raised prefabricated beam by casting and is arranged above the ground surface and abuts against the ground surface. The connecting pile cap is integrally formed with the connecting part of the raised prefabricated beam and the cylindrical tube by casting. The prestressed steel strand assembly is arranged along the connecting pile cap in the circumferential direction and penetrates through the connecting pile cap. The prestressed anchor bolt assembly is arranged along the connecting pile cap in the circumferential direction and penetrates through the connecting pile cap and the cylindrical tube. The scheme adopts the raised prefabricated beam, the beam support is higher, and the foundation rigidity is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of wind power hybrid tower foundation technology, specifically to a raised hybrid tower foundation structure combining beams, tubes, and slabs. Background Technology

[0002] In fields such as wind power generation, the performance of hybrid tower foundations is crucial for the stable operation of the entire power generation system. With the continuous development of wind power technology, wind farm construction is gradually expanding into areas with complex terrain and harsh environments, which places higher demands on the design and construction of hybrid tower foundations. Currently, traditional gravity foundations and beam-slab foundations have revealed many problems that cannot be ignored in practical applications.

[0003] Traditional gravity foundations rely primarily on their own massive weight to withstand the loads of the superstructure and external forces such as wind and earthquakes. However, this type of foundation consumes a large amount of concrete, resulting in a huge foundation volume. On the one hand, material costs increase significantly; on the other hand, on-site concrete pouring is labor-intensive and inefficient. Furthermore, gravity foundations require extremely high soil bearing capacity and are prone to significant settlement on soft soil, causing the tower to tilt, severely affecting the wind turbine's power generation efficiency, and even threatening its safe operation. For example, in wind farms in soft soil areas such as coastal mudflats, gravity foundations frequently experience tower verticality issues due to uneven soil settlement, increasing maintenance costs and safety hazards.

[0004] While beam-slab foundations address some of the drawbacks of gravity foundations, they also have their own inherent limitations. The beams and slabs of beam-slab foundations are typically cast-in-place on-site, involving complex construction processes and significant susceptibility to external factors such as weather. Furthermore, vibrating the concrete during high-altitude pouring presents challenges in ensuring its density and uniformity, potentially leading to honeycombing, pitting, and other quality issues that affect the beam's load-bearing capacity and durability. In addition, the structural form of beam-slab foundations results in relatively low overall stiffness, making them prone to cracking under long-term dynamic loads from wind turbines, thus reducing the foundation's lifespan and increasing subsequent maintenance costs.

[0005] In summary, existing gravity foundations and beam-slab foundations are no longer sufficient to meet the growing development needs of the wind power industry. There is an urgent need to develop a new type of wind power foundation structure to improve the foundation's load-bearing capacity, stability, and durability, while reducing construction and maintenance costs and adapting to complex and ever-changing engineering environments. Summary of the Invention

[0006] To address the above problems, this invention provides a raised hybrid tower foundation that combines beams, tubes, and slabs.

[0007] A raised beam-tube-slab hybrid tower foundation structure, characterized by raised precast beams, cylindrical tubes, a base slab, connecting pile caps, buttress columns, prestressed steel strand assemblies, and prestressed anchor bolt assemblies.

[0008] The raised precast beam has a rectangular cross-section with an inclination angle of 45-55 degrees. The length, height, and width of the beam are designed according to the requirements of the superstructure load and structural layout.

[0009] Furthermore, the raised precast beams are cast using molds laid flat to ensure the quality of vibration and to guarantee the homogeneity and strength of the beam body.

[0010] The cylindrical body is made of reinforced concrete, and the inner diameter, outer diameter and height of the body are determined based on the overall design of the tower and geological conditions.

[0011] Furthermore, doorways can be installed inside the cylinder.

[0012] Furthermore, the cylindrical body is placed above and abuts the ground plane, serving as the main vertical load-bearing structure of the foundation, bearing and transmitting the load of the upper structure downwards.

[0013] The base slab is constructed using cast-in-place concrete, with a thickness of 500-1000mm.

[0014] Furthermore, a crisscrossing steel mesh is installed inside the base plate according to design requirements.

[0015] Furthermore, the specifications, spacing, and other parameters of the reinforcing mesh are determined by calculation based on the load-bearing capacity and crack resistance requirements of the base slab.

[0016] Furthermore, the base plate is cast in place as a whole with the cylindrical body and the bottom of the raised precast beam, and is placed above the ground plane and abuts against the ground plane, which plays the role of distributing the load and stabilizing the foundation.

[0017] The connecting pier is cast in place at the connection between the cylindrical body and the raised precast beam.

[0018] Furthermore, the connecting pier has through-holes of prestressed steel strands and prestressed anchor bolts, which are distributed circumferentially.

[0019] The buttress columns are distributed circumferentially along the cylindrical body and are cast together with the cylindrical body to form a whole.

[0020] Furthermore, the cross-sectional shape of the buttress column can be selected according to the actual stress conditions, such as rectangular or L-shaped, and it is made of reinforced concrete.

[0021] Furthermore, longitudinal reinforcement bars are installed inside the column to ensure its strength and stability.

[0022] Furthermore, the upper part of the raised precast beam rests on the upper part of the buttress column, corresponding one-to-one with the buttress column in the circumferential direction. The buttress column plays the role of supporting the precast beam and assisting in the transfer of load.

[0023] The prestressed steel strand assembly is arranged circumferentially along the connecting bearing and passes through the connecting bearing.

[0024] Furthermore, the prestressed steel strand assembly is arranged in a circumferentially uniform manner within the connecting pier, with the lower tensioning point positioned above ±0.

[0025] The prestressed anchor bolt assembly is arranged circumferentially along the connecting bearing platform, penetrating the connecting bearing platform and the cylindrical body.

[0026] Furthermore, the prestressed anchor bolt assembly is pre-embedded in the bottom of the cylindrical body, and an anchor plate is configured when fixing it to the top of the connecting pier.

[0027] Compared with the prior art, the present invention has the following beneficial effects:

[0028] (1) This invention prefabricates beams that are difficult to cast, and then casts them using a flat mold with equal width beams. This ensures thorough vibration, resulting in beam quality superior to traditional cast-in-place construction and better overall construction quality. The use of raised prefabricated beams provides higher beam support, increasing foundation rigidity. The foundation with a cylindrical core optimizes force transmission, reducing the cost of the superstructure and balancing stability and economy.

[0029] (2) The present invention adopts raised precast beams with higher beam support, which improves the rigidity of the foundation. The foundation with tube body optimizes force transmission, which can reduce the cost of the superstructure and balance stability and economy.

[0030] (3) The present invention can open a doorway in the cylindrical tube between the raised precast beams, so that the upper tube does not need to be opened, which simplifies the design, avoids the doorway weakening the structure, and improves reliability and aesthetics.

[0031] (4) The steel strand of the mixed tower cylinder of the present invention can be tensioned above the natural backfill, avoiding the trouble of basement water leakage, making construction and later maintenance more convenient and safe, reducing costs and increasing efficiency.

[0032] (5) The present invention adopts a combination of precast beams and cast-in-place construction. The precast beams are produced in the factory and constructed on site in parallel, which is easy to install and significantly shortens the construction period compared with pure cast-in-place beams and slabs. Attached Figure Description

[0033] Figure 1 This is a diagram of the first type of raised, combined beam, tube, and slab tower foundation;

[0034] Figure 2 This is a drawing of a second, different type of raised, beam-tube-slab hybrid tower foundation;

[0035] Figure 3 This is a diagram of a third type of raised, combined beam-tube-slab tower foundation;

[0036] Figure 4 This is a diagram of a fourth type of raised, combined beam-tube-slab tower foundation;

[0037] Figure 5 A 3D model of the raised precast beam;

[0038] Figure 6 A three-dimensional drawing of a cylindrical body;

[0039] Figure 7 This is a 3D view of the base plate;

[0040] In the diagram: 1. Elevated precast beam, 2. Cylindrical tube, 3. Buttress column, 4. Base slab, 5. Connecting bearing platform, 6. Prestressed steel strand duct, 7. Prestressed anchor bolt duct, 9. Doorway, 12. Upper reinforcement of beam, 13. Bottom reinforcement of beam, 21. Top reinforcement of cylindrical tube, 22. Radial reinforcement of bottom of cylindrical tube, 41. Base slab connection. Detailed Implementation

[0041] Example 1

[0042] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments. These embodiments are based on the technical solution of the present invention and provide detailed implementation methods and specific operating procedures. However, the scope of protection of the present invention is not limited to the following embodiments.

[0043] This invention provides a raised composite tower foundation combining beams, tubes, and slabs. An embodiment is given below to describe the invention in detail.

[0044] like Figures 1-4 The four different forms of the raised beam-tube-slab hybrid tower foundation structure shown include the form with buttresses and prestressed anchor bolts, the form with buttresses but without prestressed anchor bolts, the form without buttresses but with prestressed anchor bolts, and the form without buttresses but without prestressed anchor bolts.

[0045] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5The illustrated raised beam-tube-slab composite tower foundation includes a cylindrical tube 2. The inner diameter, outer diameter, and height of the cylindrical tube are determined based on the overall tower design and geological conditions. Custom-made steel or wooden formwork is used for formwork support. Reinforcing bars are tied within the formwork. Top reinforcing bars (as shown in Figure 21) are installed at the top of the cylindrical tube, and bottom radial reinforcing bars (as shown in Figure 22) are installed at the bottom. Other structural reinforcing bars are arranged according to design requirements to form a complete reinforcing steel skeleton. Prestressed anchor bolt assemblies are pre-embedded at the bottom of the cylindrical tube according to the designed positions and spacing, ensuring accurate positioning and reliable connection with the reinforcing steel skeleton to prevent displacement during concrete pouring. After inspection and approval, concrete is poured in layers and cured promptly. Doorways are opened at appropriate locations within the tube as needed to ensure structural stability.

[0046] Based on the superstructure load and structural layout, the dimensions and inclination angle of the precast beams are designed. The raised precast beams are cast in the precast plant using specially designed flat molds. A steel reinforcement cage, including upper and lower reinforcing bars, is arranged within the mold to ensure that the specifications, quantity, and spacing of the reinforcing bars meet design requirements. Because the beams are cast flat, the vibration quality is effectively guaranteed, resulting in uniform and dense concrete, ensuring the homogeneity and strength of the beam. After the concrete is poured, it is cured and demolded after reaching the design strength. Upon arrival at the site, a crane is used to place the raised precast beam 1 onto the buttress column 3, ensuring a secure connection. Limiters may be added at the placement points as needed.

[0047] Construction of the base slab 4 is carried out at the bottom of the already installed cylindrical tube and raised precast beam. The base slab is constructed using cast-in-place concrete, with a thickness controlled between 500-1000mm. Before pouring the concrete, a crisscrossing steel mesh is laid at the bottom of the foundation according to the design requirements. The specifications, spacing, and other parameters of the steel bars are determined by calculation based on the load-bearing and crack resistance requirements of the base slab. The concrete of the base slab is vibrated using equipment such as a plate vibrator to ensure the density and flatness of the concrete. At the connection 41 between the base slab and the bottom of the cylindrical tube and raised precast beam, special treatment should be carried out, such as roughening and setting connecting steel bars, to ensure a firm connection between the base slab and the superstructure, forming a whole, and jointly playing the role of distributing the load and stabilizing the foundation.

[0048] At the connection between the cylindrical tube and the raised precast beam, formwork for the connecting pier 5 is erected. The formwork should have sufficient strength, rigidity, and stability to ensure no deformation during concrete pouring. Reinforcing bars for the connecting pier are tied inside the formwork to form a reinforcing steel skeleton. Through-holes 6 for prestressed steel strands and 7 for prestressed anchor bolts are pre-drilled according to design requirements, ensuring accurate positioning and uniform circumferential distribution of the holes. After inspection and approval, the concrete for the connecting pier is poured. Concrete pouring should be continuous, using equipment such as vibrators to ensure compaction. During concrete pouring, care should be taken to protect the prestressed ducts to prevent damage. After the concrete for the connecting pier reaches its design strength, the prestressed steel strand assemblies are inserted into the prestressed steel strand ducts 6 according to design requirements. The prestressed steel strand assemblies are evenly distributed circumferentially within the connecting pier, with the elevation of the lower tensioning point controlled above the natural fill. Prestress is applied to the steel strands using tensioning equipment, and then anchored using suitable anchors to generate pre-compression stress in the foundation structure, improving the foundation's crack resistance and bearing capacity. The prestressed anchor bolt assembly is connected to the pre-embedded portion at the bottom of the cylindrical body through prestressed anchor bolt channels 7, and an anchor plate is installed on the top of the connecting platform to ensure a firm and reliable connection, allowing the cylindrical body and the connecting platform to work together.

[0049] The raised tower, consisting of beams, tubes, and slabs, is constructed after backfilling. The bottom of the upper tower tube is located at the connection point of the tower body. During construction, high-strength grout is used to fill the connection point, and silicone sealant is applied. Doorway 9 is located between the raised precast beams, above the natural backfill.

[0050] The above embodiments are merely illustrative of the concept and implementation of the present invention and are not intended to limit it. Under the concept of the present invention, technical solutions without substantial changes are still within the scope of protection.

Claims

1. A raised, beam-tube-slab hybrid tower foundation structure, characterized in that: Includes raised precast beams, cylindrical tubes, base plates, connecting bearing platforms, buttress columns, prestressed steel strand assemblies, and prestressed anchor bolt assemblies; The cylindrical body is positioned above and abuts the ground plane. The buttress columns are distributed circumferentially along the cylindrical body and are cast integrally with it. The upper part of the raised precast beam rests on the upper part of the buttress columns and corresponds to each buttress column circumferentially. The base plate is cast integrally with the cylindrical body and the bottom of the raised precast beam, positioned above and abutting the ground plane. The connecting pier is cast in place at the connection between the raised precast beam and the cylindrical body. The prestressed steel strand assembly is arranged circumferentially along the connecting pier and passes through the connecting pier. The prestressed anchor bolt assembly is arranged circumferentially along the connecting pier and passes through the connecting pier and the cylindrical body.

2. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The raised precast beam has a rectangular cross-section with an inclination angle of 45-55 degrees. The length, height, and width of the beam are designed according to the requirements of the upper load and structural layout. The raised precast beam is cast using a mold placed flat.

3. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The base slab is constructed by cast-in-place concrete with a thickness of 500-1000mm. The base slab is equipped with a crisscrossing steel mesh according to the design requirements. The relevant parameters of the steel mesh are determined by calculation based on the load-bearing and crack resistance requirements of the base slab.

4. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The cylindrical body is made of reinforced concrete. The inner diameter, outer diameter and height of the body are determined according to the overall design of the tower and geological conditions. Door openings are set inside the body.

5. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The connecting pier is cast in place at the connection between the cylindrical body and the raised precast beam. The connecting pier has through-holes for prestressed steel strands and prestressed anchor bolts, which are distributed along the circumference.

6. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The prestressed steel strand assembly is arranged in a circumferentially uniform manner within the connecting pier, with the lower tensioning point positioned above the natural fill.

7. The raised beam-tube-slab combined hybrid tower foundation structure according to claim 1, characterized in that, The prestressed anchor bolt assembly is pre-embedded in the bottom of the cylindrical body. When it is fixed at the top of the connecting pier, an anchor plate is configured. The number and spacing of the anchor bolts are determined according to the structural stress calculation.

8. A raised beam-tube-slab combined hybrid tower foundation structure according to any one of claims 1-7, characterized in that, The construction process for the mixed-structure tower foundation is as follows: First, construct the cylindrical shell and pre-embedded prestressed anchor bolt assemblies, then pour the cylindrical shell and buttress columns; precast raised precast beams and cure them; place the raised precast beams in position; tie the reinforcing steel of the connecting pile cap, reserve the ducts and perform preliminary positioning; pour the concrete of the connecting pile cap in place; after the concrete of the connecting pile cap reaches the design requirements, first complete the connection between the upper tower body and the prestressed steel strand assembly, and finally anchor the prestressed anchor bolt assembly to achieve the overall construction of the mixed tower foundation. Subsequent maintenance can be carried out through the openings on the cylindrical shell, ensuring the long-term reliable operation of the structure.