A rapid repair method for a regulating pool covering system
By placing an airbag below the damaged point of the cover system to create a water-proof space, the problem of needing to shut down the pool and drain the liquid in the existing technology is solved, realizing rapid and efficient repair of the cover system and ensuring the continuous operation and safety of the sewage treatment facility.
Patent Information
- Application Number
- CN202611319516.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-28
- Publication Date
- 2026-11-17
AI Technical Summary
The existing repair methods for equalization tank covering systems require shutting down the tank and draining the liquid, which results in long repair cycles, high costs, and unstable quality, making it difficult to meet the requirements for continuous operation.
By placing an airbag below the damaged point of the covering system to create a dry and water-proof space, the covering membrane can be repaired, achieving rapid repair without stopping the pool or draining liquid.
It enables rapid and efficient repair of the coverage system, ensures the continuous operation of sewage treatment facilities, reduces costs and safety risks, and improves repair quality and ease of operation.
Smart Images

Figure CN123104124A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of membrane repair technology, and more specifically, to a rapid repair method for a regulating pool covering system. Background Technology
[0002] The equalization tank is a core pretreatment structure in a wastewater treatment system, primarily used to regulate the quality and quantity of influent and balance the pollution load. Because the wastewater stored in the equalization tank continuously produces and releases harmful and odorous gases such as hydrogen sulfide, ammonia, and volatile organic compounds (VOCs) under anaerobic conditions, a covering system is typically installed above the liquid level in the equalization tank in engineering practice. This system collects and seals the gases within the tank before transporting them to a deodorization system for treatment, thus preventing external water from entering the equalization tank.
[0003] Currently, the most widely used covering systems are either HDPE (high-density polyethylene) membrane floating or fixed covering systems. Taking a floating covering system as an example, the HDPE membrane is laid directly above the liquid surface in the equalization tank, with the membrane perimeter sealed to the tank wall. Gas collection pipes and flow-guiding weights are installed on the membrane, creating a gas collection space between the membrane surface and the liquid surface. However, during long-term operation, the covering system often experiences damage and leaks due to the following reasons: 1. Material aging: HDPE film is exposed to the outdoor environment for a long time and is affected by factors such as ultraviolet radiation, temperature changes, and ozone. The mechanical properties of the material gradually decline, resulting in aging phenomena such as cracking and embrittlement. 2. Chemical corrosion: Hydrogen sulfide, ammonia, and some organic solvents escaping from the pool chemically corrode the membrane material, accelerating local thinning and perforation; 3. Mechanical damage: Misoperation during routine inspections, equipment maintenance, and other operations can cause scratches or punctures to the membrane surface; 4. Structural stress: Under the action of external forces such as wind load, snow load, and water on the membrane surface, excessive tensile stress is locally applied to the membrane surface, leading to tearing; 5. Weld failure: Due to welding quality defects or long-term stress, the weld seams of the membrane splicing may detach or crack.
[0004] If the covering system is damaged, harmful gases will escape from the pool, causing environmental pollution and posing safety risks. At the same time, a damaged covering system can easily cause liquid to leak from the pool to the surface, producing a foul odor. External rainwater can also enter the pool through the damaged area, increasing the water volume. Therefore, it needs to be repaired in a timely manner.
[0005] Currently, the following methods are commonly used to repair damaged regulating pool covering systems: Method 1: Emptying and Repairing Method All wastewater in the equalization tank is pumped to other storage tanks or emergency tanks. After the tanks are emptied, personnel enter the tanks or go to the membrane surface to clean, repair, and weld the damaged areas. After the repairs are completed, water is refilled to restore operation.
[0006] This method has the following drawbacks: The equalization tank needs to be shut down, which severely affects the continuity of wastewater treatment. It requires emergency water storage facilities or external drainage conditions, and has high infrastructure and operating costs; A large amount of gas escapes during liquid transfer, posing safety and environmental risks. The repair process is lengthy, typically requiring several days or even weeks. Even after the tank is emptied, the gas produced by the residual sludge still poses a safety risk.
[0007] Method 2: Underwater Repair Method The damaged points were directly repaired using underwater curing repair materials.
[0008] This method has the following drawbacks: There are limited types of underwater curing repair materials, and their adhesion to HDPE membranes is not as good as that of repair materials under normal temperature and pressure conditions. Repair quality is difficult to guarantee, and the underwater environment limits operational precision; The material cost is relatively high; It is impossible to fully inspect and treat the damaged area.
[0009] Method 3: Local cofferdam repair method A temporary dike was set up around the damaged area, and the liquid inside the dike was pumped out before repairs were carried out.
[0010] This method has the following drawbacks: Sealing the cofferdam is difficult, and continuous liquid seepage affects the quality of the repair. The installation and dismantling of cofferdams are complex operations; It is only suitable for working conditions where the liquid surface is relatively calm, thus limiting its practicality.
[0011] In summary, existing repair methods generally suffer from problems such as the need to shut down the pool for drainage, long repair cycles, high costs, and unstable repair quality, making it difficult to meet the rapid repair needs of the coverage system under continuous operation conditions of the equalization pool. Summary of the Invention
[0012] The purpose of this invention is to provide a rapid repair method for a regulating pool covering system. This method involves placing an airbag below the damaged point of the covering system to lift the covering membrane off the liquid surface, forming a dry, watertight space. This allows the repair work to be carried out in a dry environment while the liquid is still present, thereby achieving rapid and efficient repair of the covering system without stopping the pool or draining the liquid.
[0013] The technical solution adopted in this invention is as follows: This application provides a rapid repair method for a regulating pool coverage system, including the following steps: S1: Cut an operating opening along the point of damage to the covering film; S2: Insert the uninflated airbag under the covering membrane through the operation opening; S3: Pass the inflation tube of the inflation device through the operating opening and connect it to the air nozzle of the airbag. Inflate the airbag with the inflation device to make the airbag expand. The expanded airbag will push the operating opening area of the covering membrane upward, so that the operating opening area is separated from the liquid surface below. S4: Repair all damaged areas and areas other than where the inflation tube passes through the operating opening; S5: Pull the inflation tube out of the air valve of the airbag and out of the operating opening. Repair the gap where the inflation tube passes through the operating opening during the deflation of the airbag.
[0014] Furthermore, in this invention, the airbag is annular, and after the airbag is inflated, the rupture point is located in the middle of the airbag.
[0015] Furthermore, in this invention, the operating opening is a cross-shaped cut centered on the point of breakage.
[0016] Furthermore, in this invention, step S4, during repair, includes the following steps: S41: Surface cleaning: Use cleaning tools to remove moisture, dirt and deposits from the membrane surface around the damaged points and operating openings, so that the membrane surface is clean and dry; S42: Grinding treatment: Use grinding tools to roughen the membrane surface around the damaged points and operation openings to increase the adhesion between the repair material and the membrane surface; S43: Repair solution coating: Apply membrane repair solution to the damaged points and operation openings to seal them, and wait for the membrane repair solution to cure.
[0017] S44: Reinforcement treatment: After the membrane repair solution has cured, a membrane patch is superimposed, and the membrane patch is bonded and fixed to the mother membrane using membrane repair solution or hot melt method.
[0018] Furthermore, in this invention, in step S4, after repair, the repaired area is inspected. If the inspection fails, the repair continues; if the inspection passes, step S5 is performed.
[0019] Furthermore, in this invention, step S5, during repair, includes the following steps: S51: Use sandpaper to roughen the membrane surface on both sides of the cut; S52: The coating repair liquid will align and bond the cut seams; S53: Cover the cut with a membrane patch and use a membrane repair solution or hot-melt method to bond and fix the membrane patch to the mother membrane.
[0020] Compared with the prior art, the present invention has at least the following advantages or beneficial effects: This application provides a rapid repair method for a regulating pool covering system. By placing an airbag below the damaged point of the covering system, the covering membrane is lifted off the liquid surface to form a dry, watertight space. This allows the repair work to be carried out in a dry environment while the liquid is still present, thereby achieving rapid and efficient repair of the covering system without stopping the pool or draining the liquid. Attached Figure Description
[0021] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0022] Figure 1 A top view of the covering film provided in an embodiment of the present invention; Figure 2 This is a front view of the location of the regulating pool provided in an embodiment of the present invention; Figure 3 This is a top view of the airbag provided in an embodiment of the present invention.
[0023] Icons: 1-Covering film; 2-Damage point; 3-Operating opening; 4-Airbag; 41-Air nozzle; 5-Inflation tube. Detailed Implementation
[0024] The embodiments of this application will now be described in detail with reference to the accompanying drawings. Example
[0025] Please refer to Figures 1-3 This embodiment provides a rapid repair method for a regulating tank covering system. Before repair, the damaged points can be located and assessed, and a comprehensive inspection of the regulating tank covering system can be conducted to determine the location, number, and size of the damaged points. Inspection methods can include visual inspection, gas detection (detecting areas with abnormal concentrations of harmful gases above the membrane surface), and soap solution leak detection. The size and condition of each damaged point are measured and assessed to determine whether this method is suitable for repair. The repair process includes the following steps: S1: At the identified damage point 2, use a cutting tool to cut an operating opening 3 in the covering film 1 along the damage point 2. Preferably, as follows: Figure 1As shown, the operating opening 3 is a cross-shaped incision centered on the damage point 2. The size of the operating opening 3 is determined based on the damaged area and the size of the airbag 4. Generally, the length of the operating opening 3 is 2-3 times the maximum size of the damage point, and the width should be sufficient to insert the airbag 4, usually 10-20cm. When making the incision, care should be taken to keep the incision neat to facilitate the alignment of the membrane material during subsequent repair.
[0026] S2: Select an airbag 4 of appropriate size, and insert the uninflated airbag 4 into the underside of the covering membrane 1 through the operation opening 3; preferably, such as Figure 3 As shown, the airbag 4 is ring-shaped. After the airbag 4 is inflated, the rupture point 2 is located in the middle of the airbag 4. The ring-shaped airbag 4 has a hollow structure in the middle. After the airbag 4 is inflated, the rupture point 2 is located in the hollow position. Moreover, after the airbag 4 is inflated, it can evenly lift the covering film 1 above the rupture area, so that the airbag 4 will not obstruct the repair of the rupture point 2, facilitating the repair. The air nozzle 41 of the airbag 4 preferably faces the direction of the operating opening 3, which facilitates the connection of the inflation tube 5 of the inflation device. For rupture points with a large area, multiple airbags 4 can be arranged in parallel or connected end to end to increase the lifted area and ensure sufficient waterproof working space.
[0027] S3: Use an inflation device (electric air pump or portable gas cylinder, etc.) to inflate the airbag 4 through the air nozzle 41. When inflating, the inflation tube 5 of the inflation device passes through the operating opening 3 and is connected to the air nozzle 41 of the airbag 4. The position where the inflation tube 5 passes through is preferably located at the end of the operating opening 3. The airbag 4 is inflated by the inflation device to make the airbag 4 expand. The expanded airbag 4 pushes the operating opening 3 area of the covering membrane 1 upward, so that the operating opening 3 area is separated from the liquid surface below.
[0028] The degree of inflation is controlled based on the following factors: The height between the covering membrane and the liquid surface should be sufficient to allow for the repair operation, generally not less than 5-10 cm. The pressure of the air bladder 4 should not be too high to avoid excessive stretching or damage to the covering membrane; the inflation pressure is generally controlled at 0.3-0.8 bar. During inflation, the membrane surface morphology should be observed to ensure uniform lifting and no local over-inflation. After inflation, the air bladder 4 remains inflated, forming a stable air bladder support under the covering membrane. At this point, the covering membrane in the damaged area has been lifted off the liquid surface, forming a dry, watertight space below the membrane.
[0029] S4: Repair the damaged point 2 and the area outside the point where the inflation tube 5 passes through the operating opening 3. The repair includes the following steps: S41: Surface cleaning: Use cleaning tools (lint-free cloth, brush, etc.) to remove moisture, dirt and attachments from the membrane surface around the damaged point 2 and the operating opening 3, so that the membrane surface is clean and dry; S42: Grinding treatment: Use grinding tools (sandpaper, etc.) to roughen the membrane surface around the damaged point 2 and the operation opening 3 to increase the adhesion between the repair material and the membrane surface. The grinding range should extend 3-5cm beyond the edge of the damage. S43: Repair solution application: Use membrane repair solution (such as HDPE membrane special repair adhesive, hot melt adhesive repair solution, etc.) to apply and seal the damaged point 2 and the operation opening 3. When applying, the damaged area and the surrounding sanded area should be evenly and fully covered to ensure no omissions. According to the product instructions of the repair solution, wait for the membrane repair solution to cure. During the curing process, keep the water-proof space dry and avoid moisture contact with the repair surface.
[0030] S44: Reinforcement treatment: For larger damage points, an HDPE membrane patch can be superimposed after the membrane repair liquid has cured. The membrane patch can be bonded and fixed to the mother membrane using membrane repair liquid or hot melt method to enhance the repair strength.
[0031] After repair, inspect the repaired area. If the inspection fails, continue the repair process; if the inspection passes, proceed to step S5. During the inspection, visually check the repair surface for uniformity, completeness, and the presence of defects such as bubbles or warped edges. A soap solution leak detection method can be used by applying soap solution to the repaired area and observing for bubble formation. If necessary, a portable gas detector can be used to check the gas concentration above the repaired area to confirm there is no leak.
[0032] S5: Remove the inflation tube 5 from the nozzle 41 of the airbag 4 and from the operating opening 3. Repair the gap where the inflation tube 5 passes through the operating opening 3 during the deflation of the airbag 4. Even after the airbag 4 has deflated completely, it will float on the top of the liquid surface, keeping the operating opening 3 a certain distance away from the liquid surface. The repair includes the following steps: S51: Use sandpaper to roughen the membrane surface on both sides of the cut; S52: The coating repair liquid will align and bond the cut seams; S53: Cover the cut gap with a membrane patch, and use membrane repair fluid or hot melt to bond and fix the membrane patch to the mother membrane to ensure a reliable seal at the opening. After curing, check the seal again.
[0033] Once all repairs and sealing work is completed and confirmed to be satisfactory, the covering system can be restored to normal operation. The entire process does not require draining the liquid from the equalization tank or stopping its normal operation.
[0034] The rapid repair method for the equalization tank cover system provided in this application can achieve continuous operation without shutting down the tank or draining liquid: it enables repair of the cover system while liquid is present, without the need to pump out or transfer the liquid in the equalization tank or stop the operation of the equalization tank. This is of great significance for facilities such as wastewater treatment plants that require continuous operation, avoiding production interruptions and water quality fluctuations caused by repairing the cover system.
[0035] Short repair cycle and high efficiency: Traditional drain repair methods require multiple steps such as draining, cleaning, repair, and refilling, taking several days to weeks. This method, from locating the damage point to completing the repair, typically only takes 1-3 hours to repair a single damage point, significantly shortening the repair cycle and quickly restoring the sealing function of the covering system.
[0036] Low cost: The main materials used in this method are airbags (such as bicycle inner tubes) and commercially available HDPE membrane repair fluid, both of which are low-cost and readily available. There is no need for emergency water storage tanks or large-scale pumping equipment, significantly reducing repair costs.
[0037] Reliable repair quality: The water-tight space created by the inflated airbag provides a dry environment for the repair work, allowing the HDPE membrane repair solution to cure and bond under optimal conditions, resulting in repair quality superior to underwater repair methods. Post-repair inspection and verification can be performed to ensure a reliable seal.
[0038] Low safety risk: No drainage operation is required, avoiding the risk of large-scale escape of harmful gases during liquid transfer. Repair work is carried out above the covering membrane, and personnel do not need to enter the pool, resulting in high operational safety.
[0039] Simple to operate and easy to promote: The operation steps of this method are clear and the technical threshold is low. No special equipment or professional skills are required. Ordinary maintenance personnel can operate it after simple training. The repair tool components are simple and portable, and easy to equip and promote.
[0040] High applicability: This method is applicable to HDPE membrane covering systems with different specifications of equalization tanks. It is highly adaptable to the location and size of the damage point and can handle both single and multiple damage points.
[0041] Several typical embodiments of this application are as follows: Repairing a single point of damage: A wastewater treatment plant's equalization tank measures 120m x 20m with an effective water depth of 4m. The covering system uses a 2.0mm thick HDPE membrane floating cover. During routine inspections, a tear approximately 5cm long was found in the membrane, allowing hydrogen sulfide gas to escape from the tear.
[0042] The repair steps are as follows: 1. Location: Confirm the location of the damage point using a gas detector and mark the damaged area; 2. Cutting: Make an operation opening of about 15cm along the membrane surface at the point of damage, so that the point of damage is completely exposed within the opening area; 3. Insert the air bag (a bicycle inner tube is used here. Remove the inner core of the inner tube valve so that it can be deflated directly after the inflation tube is removed): Select a 26-inch bicycle inner tube (wall thickness 1.0mm). Insert it under the covering film through the operation opening when it is not inflated. Lay it directly below the damage point, with the valve of the bicycle inner tube facing the operation opening. 4. Inflation: Use an electric pump to inflate the inner tube. The inflation tube of the electric pump passes through the operation opening 3 and is connected to the valve 41 of the inner tube to inflate. Observe the film surface gradually bulging upward. After measuring and measuring the space between the film surface and the liquid surface that is about 10cm high, stop inflating. At this time, the film surface in the damaged area has been separated from the liquid surface, and a dry and water-proof space is formed below. 5. Repair: Wipe the moisture off the membrane surface around the damaged area with a lint-free cloth. Use 120-grit sandpaper to roughen the film surface within a 5cm radius around the damaged area; Apply HDPE membrane repair solution evenly to the damaged area and surrounding sanded area; Wait 30 minutes for the repair solution to initially harden; Cover with a 10cm x 10cm HDPE film patch and use repair solution to bond the edges of the patch; 6. Inspection: After the repair solution has completely cured (about 2 hours), apply soap solution to the repaired area. If no bubbles are found, the repair is confirmed to be qualified. 7. Deflating the inner tube: Remove the inflation hose. During the deflation process, grind, apply repair fluid, and seal the gap where the inflation hose passed through before the operation opening. 8. Resumption of Operation: After the seal has cured, the coverage system will resume normal operation.
[0043] The entire process took approximately 3.5 hours, without draining the liquid or stopping the pool. After a week of operation and observation following the repair, no leakage was observed in the repaired area.
[0044] Simultaneous repair of multiple damaged points: Three damaged points were found on the covering system of the equalization tank of an industrial wastewater treatment plant. The damaged points were located in different locations and had dimensions of 3cm, 4cm and 6cm respectively.
[0045] During the repair, three bicycle inner tubes and three sets of repair materials were prepared. Three teams of operators simultaneously cut open, inserted inner tubes, and inflated the tubes at each damaged point. After creating waterproof spaces at all three damaged points, each team carried out the repair work. After the repairs were completed, a unified inspection was conducted, and the openings were sealed. The simultaneous repair of the three damaged points took approximately four hours, improving the repair efficiency by about 60% compared to repairing each point individually.
[0046] Repairing large areas of damage: A large damaged area, approximately 15cm x 10cm, was found in the covering system of a regulating pool. The area covered by a single inner tube was insufficient to cover the entire damaged area.
[0047] During repair, three 29-inch bicycle inner tubes were connected end-to-end (using inner tube connectors or simple binding), arranged parallel to each other, and inserted into the damaged area under the covering membrane. Each inner tube was then inflated. The inflated inner tubes lifted approximately 20cm x 30cm of the membrane surface, creating sufficient waterproof working space. The large damaged area was then cleaned, sanded, repair fluid applied, and patched sequentially. After repair, each inner tube was deflated and the opening sealed. The repair was successful, and leak testing revealed no leaks in the repaired area.
Claims
1. A method for regulating the rapid repair of a pond covering system, characterized in that, Includes the following steps: S1: Cut an operating opening along the point of damage to the covering film; S2: Insert the uninflated airbag under the covering membrane through the operation opening; S3: Pass the inflation tube of the inflation device through the operating opening and connect it to the air nozzle of the airbag. Inflate the airbag with the inflation device to make the airbag expand. The expanded airbag will push the operating opening area of the covering membrane upward, so that the operating opening area is separated from the liquid surface below. S4: Repair all damaged areas and areas other than where the inflation tube passes through the operating opening; S5: Pull the inflation tube out of the air valve of the airbag and out of the operating opening. Repair the gap where the inflation tube passes through the operating opening during the deflation of the airbag.
2. A method of quickly repairing a regulating pond covering system according to claim 1, characterized in that, The airbag is ring-shaped, and after the airbag is inflated, the rupture point is located in the middle of the airbag.
3. The rapid repair method for a regulating pool covering system according to claim 1, characterized in that, The opening is a cross-shaped cut centered on the point of damage.
4. The rapid repair method for a regulating pool covering system according to claim 1, characterized in that, In step S4, the repair process includes the following steps: S41: Surface cleaning: Use cleaning tools to remove moisture, dirt and deposits from the membrane surface around the damaged points and operating openings, so that the membrane surface is clean and dry; S42: Grinding treatment: Use grinding tools to roughen the membrane surface around the damaged points and operation openings to increase the adhesion between the repair material and the membrane surface; S43: Repair solution coating: Apply membrane repair solution to the damaged points and operation openings to seal them, and wait for the membrane repair solution to cure.
5. A rapid repair method for a regulating pool covering system according to claim 4, characterized in that, The repair process also includes the following steps: S44: Reinforcement treatment: After the membrane repair solution has cured, a membrane patch is superimposed, and the membrane patch is bonded and fixed to the mother membrane using membrane repair solution or hot melt method.
6. The rapid repair method for a regulating pool covering system according to claim 1, characterized in that, In step S4, after repair, the repaired area is inspected. If the inspection fails, the repair continues; if the inspection passes, step S5 is performed.
7. A rapid repair method for a regulating pool covering system according to claim 1, characterized in that, In step S5, the repair process includes the following steps: S51: Use sandpaper to roughen the membrane surface on both sides of the cut; S52: The coating repair liquid will align and bond the cut seams; S53: Cover the cut with a membrane patch and use a membrane repair solution or hot-melt method to bond and fix the membrane patch to the mother membrane.