Conveying System and Scheduling Method
By introducing a circular first track, a movable second track, and a third track structure into the conveyor system, the transportation congestion problem caused by the single track design is solved, realizing continuous and efficient material transportation and flexible system adaptability, and ensuring the stability and smoothness of production.
Patent Information
- Application Number
- CN202611397971.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-09
- Publication Date
- 2026-11-17
AI Technical Summary
The existing conveyor system, due to its single-track design, will occupy the main circuit resources when a certain circular vehicle needs to be repaired or maintained due to a malfunction, hindering the operation of other vehicles and affecting the continuity of production and the smooth flow of products.
The system employs a structure consisting of a circular first track, a movable second track, and a spaced third track. The second track enables flexible docking and separation of the first and third tracks, providing a continuous transport path. Steering components and drive units ensure smooth transfer of the transport vehicle.
It improved the continuity of material transportation and the flexibility of the system, reduced equipment idle rate, ensured the smooth flow of the main transportation channel, enhanced the overall throughput and operational stability of the system, and avoided system blockage caused by faulty vehicles.
Smart Images

Figure CN123105183A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of material transportation technology, and more specifically, to a conveying system and scheduling method. Background Technology
[0002] In the production and manufacturing process of glass fiber, the transfer of raw materials is a key link connecting the upstream raw material preparation and the downstream fiber drawing process. Typically, the raw materials need to be loaded onto empty fiber carts, which are then transported to the second station 520 via a conveyor system. After the raw materials are loaded, the carts carrying full fiber carts are then transported to the next station.
[0003] However, existing conveyor systems typically employ a single-track design. Since all the loopers operate on the same track, when a looper needs repair or maintenance due to a malfunction, it occupies the main loop resources. This directly hinders the operation of other normally functioning vehicles, causing obstruction of the entire conveyor system's flow and severely impacting the smoothness of continuous production and product turnover in the workshop. Summary of the Invention
[0004] The main objective of this invention is to provide a conveying system and scheduling method to solve the problem of easy congestion in the existing conveying system.
[0005] To achieve the above objectives, according to one aspect of the present invention, a conveying system is provided, comprising: a first track having a ring structure; a transport carrier for transporting target material; a second track and a third track, the third track being spaced apart from the first track, the second track being movably disposed, both ends of the second track being respectively connected to the first track and the third track, such that the second track is in a connected position, and the transport carrier moves from the second track to the third track; the second track is separated from the first track and the third track, the second track being in a clearance position, and the transport carrier moves on the first track or the third track.
[0006] Furthermore, there are multiple third tracks, each of which is spaced apart from the first track. Each third track has a second track at both ends, so that each third track can be connected to or separated from the first track through the second track.
[0007] Furthermore, the second orbit has an arc-shaped structure; or, the second orbit has a straight-line structure.
[0008] Furthermore, the transport vehicle is equipped with a steering assembly, which includes a steering component located at the bottom of the transport vehicle; the second track includes a guide track section, which, when the second track is in the docking position, has its two ends docked with the first track and the third track respectively, and the steering component abuts against the side wall of the guide track section to guide the transport vehicle.
[0009] Furthermore, there are at least two steering components, which are spaced apart on the transport vehicle along the direction of movement of the transport vehicle.
[0010] Furthermore, the steering component includes a steering wheel, which is rotatably disposed at the bottom of the transport vehicle, and the steering wheel abuts against the side wall of the guide rail section.
[0011] Furthermore, the second track also includes a support track section disposed on the guide track section; the steering assembly also includes a first drive member and a drive wheel, the drive wheel being rotatably disposed, the drive wheel being in contact with the upper surface of the support track section, the first drive member being drivenly connected to the drive wheel, and the first drive member driving the drive wheel to rotate, thereby moving the transport vehicle.
[0012] Furthermore, a second driving component is provided on the second track, and the second driving component is driven to move the second track so that the two ends of the second track are respectively connected to the first track and the third track.
[0013] Furthermore, the second driving member has an output shaft, which is telescopically configured and connected to the second track to drive the second track to rise and fall; or, the second driving member further includes: a first connector and a second connector arranged in a cross configuration, the ends of the first connector and the second connector being slidably connected to the second track respectively, the output shaft being located at the intersection of the first connector and the second connector, the output shaft being sequentially passed through the first connector and the second connector respectively, the output shaft being threadedly connected to the first connector and the second connector respectively, and the output shaft being rotatably configured to allow the first connector and the second connector to retract or open, thereby pushing the second track to rise and fall.
[0014] According to another aspect of the present invention, a scheduling method is provided, applicable to the above-described conveying system, wherein there are at least two transport carriers, both of which are movably mounted on a first track to transport target materials; the conveying system further includes a control unit, which is signal-connected to each of the transport carriers; the scheduling method includes: acquiring position information of at least two transport carriers; determining, based on the position information, whether one of the at least two transport carriers is located on the movement path of the other transport carrier; when one transport carrier is located on the movement path of the other transport carrier, controlling the movement of a second track to connect the first track and a third track via the second track, and then controlling one transport carrier to move to the third track.
[0015] By applying the technical solution of this invention, the first track has a ring structure, which provides a continuous travel path for the transport vehicle. The ring design of the first track enables the transport vehicle to run in a cycle, improving the continuity of material transportation and providing a stable and efficient basic operating environment for the entire conveying system.
[0016] The transport carrier is movably set on the first track. The transport carrier is used to carry and transport the target material. The transport carrier moves in a cycle on the first track, realizing the automatic flow of materials within the system. This ensures that materials can be delivered to the designated location as needed, reducing the cost and time of manual handling, improving logistics efficiency, and at the same time, the cycle transport mode makes full use of system resources and reduces equipment idle rate.
[0017] The second track is movably set up, with its two ends docking with the first and third tracks respectively. The second track serves as a temporary channel connecting the first and third tracks. Its mobility allows it to flexibly adjust its position. When docked, the second track fills the gap between the first and third tracks. The flexible docking mechanism of the second track enables the system to transport the carrier in the direction of movement according to actual needs, increasing the diversity of paths and improving the system's adaptability and flexibility.
[0018] The third track is spaced apart from the first track. The third track is used to receive transport vehicles transferred from the first track. The spacing of the third track allows the first and third tracks to operate independently or in parallel. The third track provides additional storage or processing area for the transport vehicles. The existence of the third track alleviates the transport pressure on the first track. When the first track is congested, the transport vehicles can enter the third track to wait, thereby ensuring the smooth flow of the main transport channel and improving the overall throughput and operational stability of the system.
[0019] The second track guides the transport vehicle, forming a continuous guiding structure at the docking point. The guiding function of the second track ensures that the transport vehicle smoothly transitions from the first track to the third track. The guiding design of the second track eliminates the risk of misalignment at the track docking point, preventing the transport vehicle from derailing or getting stuck during the transfer process. The precise guidance of the second track improves the safety and reliability of the transfer process, reduces downtime, and ensures the continuity and accuracy of material transportation.
[0020] When the second track is in the docking position, it connects the first and third tracks, enabling the smooth transfer of transport vehicles from the first to the third track. The docking action of the second track establishes a new path, allowing the transport vehicles to move along the second track to the third track. This transfer mechanism allows the system to divert some transport vehicles to the third track without interrupting the main transport flow on the first track. The movable docking design of the second track enables dynamic switching between the main channel and the branch channel, ensuring the priority of the main transport task while providing flexible branch processing capabilities. This effectively balances the system load, improves the overall operating efficiency and robustness of the transport system, and solves the problem of easy congestion in existing transport systems. Attached Figure Description
[0021] The accompanying drawings, which form part of this application, are used to provide a further understanding of the invention. The illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute an undue limitation of the invention. In the drawings:
[0022] Figure 1 A schematic diagram showing a transport vehicle moving on a first track according to an embodiment of the transport system of the present invention is shown;
[0023] Figure 2 A schematic diagram showing a transport vehicle moving on a second track according to an embodiment of the transport system of the present invention is shown;
[0024] Figure 3 A schematic diagram of a transport vehicle according to an embodiment of the transport system of the present invention is shown;
[0025] Figure 4 A schematic diagram of the first direction of the second track according to an embodiment of the conveying system of the present invention is shown;
[0026] Figure 5 A schematic diagram of the second direction of the second track according to an embodiment of the conveying system of the present invention is shown;
[0027] Figure 6 A schematic diagram showing the state of the second station carrying an empty wire car according to an embodiment of the conveying system of the present invention is shown;
[0028] Figure 7 A schematic diagram of the second station carrying a full-bottle yarn cart according to an embodiment of the conveying system of the present invention is shown;
[0029] Figure 8 A schematic diagram of a first embodiment of the scheduling method according to the present invention is shown;
[0030] Figure 9 A schematic diagram of a second embodiment of the scheduling method according to the present invention is shown;
[0031] Figure 10 A schematic diagram of a third embodiment of the scheduling method according to the present invention is shown;
[0032] Figure 11 A schematic diagram of a fourth embodiment of the scheduling method according to the present invention is shown;
[0033] Figure 12 A schematic diagram of a fifth embodiment of the scheduling method according to the present invention is shown;
[0034] Figure 13 A schematic diagram of a sixth embodiment of the scheduling method according to the present invention is shown;
[0035] Figure 14 A schematic diagram of a seventh embodiment of the scheduling method according to the present invention is shown;
[0036] Figure 15 A schematic diagram of an eighth embodiment of the scheduling method according to the present invention is shown;
[0037] Figure 16 A schematic diagram of a ninth embodiment of the scheduling method according to the present invention is shown;
[0038] Figure 17 A first flowchart illustrating an embodiment of the scheduling method according to the present invention is shown;
[0039] Figure 18 A second flowchart illustrating an embodiment of the scheduling method according to the present invention is shown.
[0040] The above figures include the following reference numerals:
[0041] 100. First track;
[0042] 200. Transport vehicle; 201. Steering assembly; 210. Steering component; 211. Steering wheel; 220. Drive wheel; 230. Third chain transplanter; 240. Signal indicator light;
[0043] 300, Second track; 310, Guide track section; 320, Support track section; 330, Second drive component; 331, First connector; 332, Second connector; 340, Support platform;
[0044] 400. Third track; 410. Maintenance area;
[0045] 510, First station; 511, First chain transplanter; 520, Second station; 521, Rotary table; 522, Fourth chain transplanter; 530, Third station; 531, Second chain transplanter. Detailed Implementation
[0046] It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other. The present invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0047] As mentioned in the background section, existing conveyor systems typically employ a single-track design. Since all the loopers operate on the same track, when a looper needs repair or maintenance due to a malfunction, it occupies the main loop resources. This directly hinders the operation of other normally functioning vehicles, causing obstruction of the entire conveyor system's flow and severely impacting the smoothness of continuous production and product turnover in the workshop. Therefore, to address the aforementioned technical problems, the conveying system proposed in this application includes: a first track 100, a transport carrier 200, a second track 300, and a third track 400. The first track 100 has a ring structure; the transport carrier 200 is used to transport target materials; by setting the second track 300 and the third track 400, the third track 400 is spaced apart from the first track 100, and the second track 300 is movably set, with both ends of the second track 300 respectively docking with the first track 100 and the third track 400, so that the second track 300 is in a docking position, and the transport carrier 200 moves onto the third track 400 via the second track 300; the second track 300 is separated from the first track 100 and the third track 400, and the second track 300 is in a clearance position, and the transport carrier 200 moves on the first track 100 or the third track 400, thus solving the problem of easy congestion in the conveying system of the prior art.
[0048] Please refer to Figures 1 to 5 This application provides a conveying system, including: a first track 100, which has a ring structure; a transport carrier 200 for transporting target materials; a second track 300 and a third track 400, wherein the third track 400 is spaced apart from the first track 100, the second track 300 is movably arranged, and both ends of the second track 300 are respectively connected to the first track 100 and the third track 400 so that the second track 300 is in a connected position, and the transport carrier 200 moves to the third track 400 via the second track 300; the second track 300 is separated from the first track 100 and the third track 400, and the second track 300 is in a clearance position, and the transport carrier 200 moves on the first track 100 or the third track 400.
[0049] The first track 100 has a ring structure and provides a continuous travel path for the transport vehicle 200. The ring design of the first track 100 enables the transport vehicle 200 to run in a cycle, improving the continuity of material transportation and providing a stable and efficient basic operating environment for the entire conveying system.
[0050] The transport carrier 200 is movably set on the first track 100. The transport carrier 200 is used to carry and transport the target material. The transport carrier 200 moves cyclically on the first track 100, realizing the automatic flow of materials within the system. This ensures that materials can be delivered to the designated location as needed, reducing the cost and time of manual handling, improving logistics efficiency, and at the same time, the cyclical transport mode makes full use of system resources and reduces equipment idle rate.
[0051] The second track 300 is movably configured, with its two ends docking with the first track 100 and the third track 400, respectively. The second track 300 serves as a temporary channel connecting the first track 100 and the third track 400. Its mobility allows it to flexibly adjust its position. When docked, the second track 300 fills the gap between the first track 100 and the third track 400. The flexible docking mechanism of the second track 300 enables the system to move the transport carrier 200 according to actual needs, increasing the diversity of paths and improving the system's adaptability and flexibility.
[0052] The third track 400 is spaced apart from the first track 100. The third track 400 is used to receive the transport vehicle 200 transferred from the first track 100. The spaced arrangement of the third track 400 allows the first track 100 and the third track 400 to operate independently or in parallel. The third track 400 provides additional storage or processing area for the transport vehicle 200. The presence of the third track 400 alleviates the transport pressure on the first track 100. When the first track 100 is congested, the transport vehicle 200 can enter the third track 400 to wait, thereby ensuring the smooth flow of the main transport channel and improving the overall throughput and operational stability of the system.
[0053] The second track 300 guides the transport carrier 200. The second track 300 forms a continuous guiding structure at the docking position. The guiding function of the second track 300 ensures that the transport carrier 200 smoothly transitions from the first track 100 to the third track 400. The guiding design of the second track 300 eliminates the risk of misalignment at the track docking point, preventing the transport carrier 200 from derailing or getting stuck during the transfer process. The precise guidance of the second track 300 improves the safety and reliability of the transfer process, reduces downtime, and ensures the continuity and accuracy of material transportation.
[0054] When the second track 300 is in the docking position, it connects the first track 100 and the third track 400. This process enables the smooth transfer of the transport vehicle 200 from the first track 100 to the third track 400. The docking action of the second track 300 establishes a new path, and the transport vehicle 200 moves along the second track 300 to the third track 400. This transfer mechanism allows the system to divert some of the transport vehicles 200 to the third track 400 without interrupting the main transport flow on the first track 100. The movable docking design of the second track 300 enables dynamic switching between the main channel and the branch channel, ensuring the priority of the main transport task while providing flexible branch processing capabilities. This effectively balances the system load, improves the overall operating efficiency and robustness of the transport system, and solves the problem of easy congestion in existing transport systems.
[0055] Specifically, the transport carrier 200 includes a transport vehicle. The target material includes fiberglass.
[0056] In the specific implementation process, such as Figure 1 As shown, there are multiple third tracks 400, each of which is spaced apart from the first track 100. Each third track 400 has a second track 300 at both ends, and each second track 300 guides the transport carrier 200 so that each third track 400 can be connected to or separated from the first track 100 through the second track 300.
[0057] The first track 100 has a ring structure, on which the transport carrier 200 is movably mounted to transport target materials. Simultaneously, several third tracks 400 are spaced apart from the first track 100. Each third track 400 has a second track 300 at both ends, which are movably mounted and respectively connect to the first track 100 and the corresponding third track 400, positioning the second track 300 in the docking position. This guides the transport carrier 200, directing it bidirectionally between the third track 400 and the first track 100. By introducing multiple third tracks 400 and corresponding second tracks 300, the limitation of a single channel is broken, allowing the transport carrier 200 to flexibly enter and exit between the ring main track and multiple branch tracks using different second tracks 300. This not only provides multiple independent transfer paths but also achieves efficient bidirectional guidance of the transport carrier between the first track 100 and each third track 400, effectively improving the throughput capacity and path selection flexibility of the conveying system.
[0058] Specifically, such as Figure 1 As shown, the second track 300 has an arc-shaped structure; or, the second track 300 has a straight structure.
[0059] By limiting the second track 300 to either an arc-shaped or straight structure, the conveying system offers a choice of physical form to adapt to different site environments. When the second track 300 adopts an arc-shaped structure, its curved extension conforms to the circular layout of the first track 100, providing a smooth curved guiding path for the transport carrier 200 and reducing the impact and energy consumption of the carrier during turning. When the second track 300 adopts a straight structure, its straight extension is suitable for scenarios with narrow spaces or large straight-line conveying requirements, simplifying the difficulty of track processing and installation. This diverse limitation of geometric configuration allows the second track 300, as a guiding component connecting the first track 100 and the third track 400, to be flexibly adjusted according to the specific needs of the actual spatial layout or conveying process, improving the spatial adaptability of the track and enhancing the installation flexibility and operational adaptability of the conveying system under different working conditions.
[0060] In this application, such as Figure 3 As shown, a steering assembly 201 is provided on the transport carrier 200. The steering assembly 201 includes a steering component 210, which is located below the transport carrier 200. The second track 300 includes a guide track section 310. When the second track 300 is in the docking position, the two ends of the guide track section 310 are docked with the first track 100 and the third track 400, respectively. The steering component 210 abuts against the side wall of the guide track section 310 to guide the transport carrier 200.
[0061] By directly contacting the side wall of the guide rail section 310 with the steering component 210, the mechanical contact generated by the physical contact guides the trajectory of the transport vehicle 200 as it transfers from the first track 100 to the third track 400 via the second track 300. This side-wall contact guidance method effectively prevents the transport vehicle 200 from lateral deviation or derailment in the track docking transition zone, ensuring that the transport vehicle 200 enters the third track 400 stably and accurately along the predetermined path. This improves the operational safety and path control accuracy of the conveying system during track changing.
[0062] In the specific implementation process, such as Figure 3 As shown, there are at least two steering assemblies 201, and at least two steering assemblies 201 are spaced apart on the transport vehicle 200 along the direction of movement of the transport vehicle 200.
[0063] When at least two steering components 201 are installed on the transport carrier 200 and spaced apart along its direction of movement, during the transfer of the transport carrier 200 from the first track 100 to the third track 400, multiple steering components 210 can sequentially engage with the sidewall of the guide track section 310 of the second track 300. This multi-point spaced guiding structure can constrain the movement posture of the transport carrier 200 over a longer travel range, effectively limiting its lateral sway or deflection freedom during the transition, thereby ensuring that the steering components 210 slide smoothly and accurately along the guide track section 310. This design improves the guiding stability and steering accuracy of the transport carrier 200 during docking transition, avoids jamming or trajectory deviation caused by insufficient guiding support, and makes the material conveying process more reliable and precise.
[0064] Specifically, such as Figure 3 As shown, the steering component 210 includes a steering wheel 211, which is rotatably disposed at the bottom of the transport carrier 200, and the steering wheel 211 abuts against the side wall of the guide rail section 310.
[0065] During the transfer of the transport vehicle 200 from the first track 100 to the third track 400, the steering wheel 211 rolls along with the transport vehicle 200 and transmits guiding force through contact with the side wall of the guide track section 310. This structural design, which transforms sliding contact into rolling contact, effectively reduces frictional resistance during the guiding process and avoids problems such as instability in guidance or excessive wear of components caused by direct contact friction. This ensures that the transport vehicle 200 moves smoothly and steadily along the guide track section 310, improving the smoothness and stability of the docking and transfer of the conveying system.
[0066] In this application, such as Figure 4 and Figure 3 As shown, the second track 300 further includes a support track section 320, which is disposed on the guide track section 310; the steering assembly 201 further includes a first driving member and a driving wheel 220, the driving wheel 220 is rotatably disposed, the driving wheel 220 is in contact with the upper surface of the support track section 320, the first driving member is drivingly connected to the driving wheel 220, and the first driving member drives the driving wheel 220 to rotate, so as to move the transport carrier 200.
[0067] The support track section 320 provides a stable top support surface for the drive wheel 220, ensuring stable contact between the drive wheel 220 and the track. This effectively solves the problem of unstable movement of the transport vehicle 200 when passing through the second track 300 due to the lack of active driving force and top support. During operation, the drive wheel 220 is rotatably mounted and closely fits the upper surface of the support track section 320. When the first driving component is activated and drives the drive wheel 220 to rotate, the drive wheel 220 rolls on the support track section 320 through friction, thereby generating driving force along the track extension direction and directly driving the transport vehicle 200 to move. At the same time, the steering component 210 abuts against the side wall of the guide track section 310, providing forward power from the drive wheel 220 while laterally limiting the transport vehicle 200 to prevent it from deviating from the predetermined path. This cooperative effect of the drive wheel 220 and the steering component 210 allows the transport vehicle 200 to obtain moving power on the second track 300 while maintaining a stable travel trajectory, realizing precise and efficient movement of the conveying system under different operational requirements.
[0068] Specifically, the first driving component includes a motor.
[0069] In this application, such as Figure 4 As shown, a second driving member 330 is provided on the second track 300. The second driving member 330 is driven to connect with the second track 300 to drive the second track 300 to move, so that the two ends of the second track 300 are respectively connected to the first track 100 and the third track 400.
[0070] The second drive component 330 directly drives the second track 300 upward, enabling active and precise control of its movement trajectory and position, ensuring reliable docking of both ends of the second track 300 with the first track 100 and the third track 400 respectively. This direct driving force provided by the second drive component 330 ensures the continuity and stability of the second track 300 as a transition path, thereby guaranteeing that the transport carrier 200 can be smoothly and steadily guided from the first track 100 to the third track 400, effectively improving the reliability and safety of the conveying system.
[0071] Specifically, such as Figure 4As shown, the second driving member 330 has an output shaft, which is telescopically configured and connected to the second track 300 to drive the second track 300 to rise and fall; or, the second driving member 330 further includes: a first connector 331 and a second connector 332 arranged in a cross configuration, the ends of the first connector 331 and the second connector 332 being slidably connected to the second track 300 respectively, the output shaft being located at the intersection of the first connector 331 and the second connector 332, the output shaft being sequentially threaded through the first connector 331 and the second connector 332 respectively, and the output shaft being rotatably configured to allow the first connector 331 and the second connector 332 to retract or open, thereby pushing the second track 300 to rise and fall.
[0072] When the second drive member 330 adopts a structure with a retractable output shaft, the output shaft moves telescopically, driving the second track 300 to rise or fall via linear displacement of the output shaft, thereby completing the docking with the first track 100 and the third track 400. Specifically, the second drive member 330 is a hydraulic cylinder or a pneumatic cylinder; or, the second drive member 330 is a motor. When the second drive member 330 adopts a structure including a first connector 331 and a second connector 332, the output shaft is located at the intersection of the first connector 331 and the second connector 332, and the output shaft passes through the first connector 331 and... The second connector 332 drives the relative movement of the two components through a threaded connection. Since the ends of the first connector 331 and the second connector 332 are slidably connected to the second track 300, the rotational motion of the output shaft is converted into the opening and closing or retracting action of the first connector 331 and the second connector 332, thereby pushing the second track 300 to rise or fall. This design converts rotational motion into lifting motion, realizing the precise lifting and docking of the second track 300 relative to the first track 100 and the third track 400, ensuring the connectivity of the transmission path, and improving the operational stability and docking accuracy of the conveying system.
[0073] like Figures 6 to 18As shown, this application also provides a scheduling method applicable to the conveying system of the above embodiments. There are at least two transport carriers 200, each movably mounted on a first track 100 to transport target materials. The conveying system also includes a control unit, which is signal-connected to each transport carrier 200. The scheduling method includes: acquiring position information of at least two transport carriers 200; determining, based on the position information, whether one of the transport carriers 200 is located on the movement path of the other transport carrier 200; when one transport carrier 200 is located on the movement path of the other transport carrier 200, controlling the second track 300 to move, so that the first track 100 and the third track 400 are connected via the second track 300; and then controlling one transport carrier 200 to move to the third track 400.
[0074] By acquiring the location information of at least two transport vehicles 200, the dynamics of each vehicle are monitored in real time, thereby determining whether one transport vehicle 200 is located on the movement path of another transport vehicle 200 to identify potential driving conflicts. When a risk of path overlap is detected, the two ends of the second track 300 are connected to the first track 100 and the third track 400 respectively, establishing a temporary connecting path from the main loop track to the branch track. Subsequently, the transport vehicle 200 in the conflict position is guided to move through the second track 300 to the third track 400. The third track 400 is used as a clearance space to temporarily remove the vehicle to be clearanced from the main operating loop. This achieves dynamic isolation and passing between vehicles while the first track 100 continues to operate continuously, effectively avoiding energy waste caused by vehicles queuing or chasing each other, and improving the traffic efficiency and scheduling flexibility of the transport system when multiple vehicles are operating in parallel.
[0075] The conveying system of this application is described below with reference to a specific embodiment:
[0076] This application relates to the field of logistics scheduling, and in particular to a parallel closed track and scheduling method.
[0077] In the fiberglass production process, raw materials need to be loaded into empty drum yarn carts and transported to the raw material processing area by a conveyor line. The conveyor line consists of a closed loop, loop carts, and an automated storage and retrieval system. However, the existing closed loop is basically a single loop with multiple loop carts running on it. When there is little work on site, there will be situations where non-idle loop carts drive idle loop carts around, resulting in a waste of energy and equipment and a significant reduction in the efficiency of the conveyor line.
[0078] Compared with the prior art, this application has the following beneficial effects: when an idle loop car is driven away by a non-idle loop car, it can travel to the third track 400 to wait for the next job assignment, which reduces the waste of equipment and energy, responds quickly to job assignments, increases the effective working time of equipment, and improves the efficiency of the conveyor line; and the faulty vehicle does not need to be taken off the line for repair, which does not hinder the normal operation of other vehicles, and ensures the smooth flow of continuous production and product circulation in the workshop.
[0079] This application provides a conveying system including a first track 100 and at least one transport vehicle 200. Along the circumferential direction of the first track 100, a first station 510, a second station 520, and a third station 530 are spaced apart on the side of the first track 100. At least one transport vehicle 200 travels along the first track 100 to transport empty yarn carts on the first station 510 to the second station 520, and to transport full yarn carts on the second station 520 to the third station 530.
[0080] In this embodiment, two transport vehicles 200 travel on the first track 100. One transport vehicle 200 is located at the first work station 510 and is designated as the No. 1 loop-through vehicle. The other transport vehicle 200 is located at the third work station 530 and is designated as the No. 2 loop-through vehicle. The two loop-through vehicles travel in the direction indicated by the arrow in the second work station 520. Multiple rotary tables 521 are provided on the second work station 520. Multiple first chain transplanters 511 are provided on the first work station 510. Multiple second chain transplanters 531 are provided on the third work station 530.
[0081] The first track 100, the second track 300, and the third track 400 are all T-shaped tracks. The horizontal surface of the T supports the drive wheel 220 of the transport vehicle 200 to move, and the vertical surface of the T is in contact with the steering wheel 211 of the transport vehicle 200 to control the direction of the circumferential vehicle.
[0082] The first track 100 is installed on the ground. The straight section of the third track 400 includes a maintenance area 410, which is also installed on the ground, so that maintenance vehicles can enter the track without affecting the normal operation of the first track 100.
[0083] The second track 300 is installed on the support platform 340, which is set on the second drive component 330. The second drive component 330 and the support platform 340 are connected by a drive, which drives the second track 300 and the support platform 340 to rise or fall. When the second track 300 falls, the second track 300 and the third track 400 separate. At this time, the circumferential vehicle can only move on the first track 100.
[0084] The second track 300 rises until its two ends connect with the first track 100 and the third track 400 respectively. At this point, the circumferential vehicle can only move on the second track 300 and the third track 400. The second track 300 is in a descending state by default.
[0085] A third chain transplanter 230 is installed on the transport carrier 200, and multiple second chain transplanters 531 are installed on the third workstation 530. The circumferential vehicle passes through the third chain transplanter 230 and the second chain transplanters 531 to realize the flow of the vehicle and the workstation.
[0086] The transport vehicle 200 is equipped with a drive wheel 220 and a steering wheel 211. The drive wheel 220 travels on the horizontal plane of the T-shaped track, and the steering wheel 211 is in contact with the vertical plane of the T-shaped track, which drives the transport vehicle 200 to turn. The steering wheel 211 is installed on the inner side of the transport vehicle 200.
[0087] The transport vehicle 200 is equipped with a signal indicator light 240. A flashing red light indicates that the transport vehicle 200 is heading to the second track 300. A solid red light indicates that the transport vehicle 200 is under alarm. A flashing green light indicates that the transport vehicle 200 is performing operations. A solid green light indicates that the circumferential vehicle is not operating.
[0088] like Figure 6 , Figure 7 and Figure 8 As shown, a fourth chain transplanter 522 is installed on the second station 520. The fourth chain transplanter 522 is used to transport empty or full barrels of yarn.
[0089] like Figure 6 As shown, the second station 520 in the state of carrying an empty wire trolley is marked with a single diagonal line on the fourth chain transplanter 522. It should be noted that the first station 510 in the state of carrying an empty wire trolley is marked with a single diagonal line on the first chain transplanter 511; similarly, the transport carrier 200 in the state of carrying an empty wire trolley is marked with a single diagonal line on the third chain transplanter 230.
[0090] like Figure 7 As shown, the second station 520, when carrying a full bucket of yarn, is marked with a cross line on the fourth chain transplanter 522. It should be noted that the second station 520, when carrying a full bucket of yarn, is also marked with a cross line on the fourth chain transplanter 522; the third station 530, when carrying a full bucket of yarn, is also marked with a cross line on the second chain transplanter 531; and the transport carrier 200, when carrying a full bucket of yarn, is marked with a single diagonal line on the third chain transplanter 230.
[0091] This application provides a method for transporting goods using a parallel closed track, the method comprising the following steps;
[0092] Determine whether there are non-idle ring vehicles driving through the first direction of the idle ring vehicle's operation;
[0093] Determine whether the idle loop vehicle has left the second workstation 520;
[0094] The idle loop car travels to the second track 300 and the third track 400;
[0095] Determine if workstation 520 has a call for an empty drum wire car;
[0096] Determine if there is an empty wire drum machine at the first workstation 510;
[0097] The idle loop car travels to the first workstation 510 and delivers the empty wire drum car to the call workstation.
[0098] Determine whether there is a workstation with a full-bore wire machine in the second direction of the ring-shaped car's operation, since the first direction is the opposite of the second direction;
[0099] The ring-type machine transports the full drum of yarn to the third workstation, 530.
[0100] Specifically, the control unit detects that among the multiple second workstations 520, two workstations call in empty yarn carts and one workstation calls out full yarn carts. Based on the workstation call waiting time, along the direction of travel of the circular train, the workstation closer to the first workstation 510 has a call waiting time of 12 seconds, and the workstation farther from the first workstation along the direction of travel of the circular train has a call waiting time of 10 seconds. The workstation closer to the first workstation 510 along the direction of travel of the circular train is determined to be the priority workstation.
[0101] The control unit dispatches the No. 1 loop-through car to receive the empty yarn cart from the first workstation 510 and move it to the priority workstation to complete the transfer of the empty yarn cart. After the No. 1 loop-through car leaves the first workstation 510, the control unit dispatches the No. 2 loop-through car to receive the empty yarn cart from the first workstation 510. At the same time, the control unit detects that a workstation has called out a full yarn cart in the second direction of the No. 1 loop-through car's operation. The control unit dispatches the No. 1 loop-through car to move to that workstation to receive the full yarn cart and then moves along the first track 100 to the third workstation 530. After the No. 2 loop-through car completes the pick-up and drop-off of the empty yarn cart, the unit dispatcher detects that there is no calling workstation in the second direction of the No. 2 loop-through car's operation. The control unit dispatches the No. 2 loop-through car to stay in place. At the same time, the unit dispatcher detects that a workstation has called in an empty yarn cart in the first direction of the No. 2 loop-through car's operation. The control unit dispatches the No. 1 loop-through car to receive the empty yarn cart from the first workstation 510 and move it to the calling workstation to complete the transfer of the empty yarn cart. At the same time, the unit dispatcher detects that there is a second workstation 5 in the first direction of the No. 1 loop-through car and the second direction of the No. 2 loop-through car. Calling a full-bottle wire car, the control unit dispatches the No. 1 ring threading car to this station to receive the full-bottle wire car and then transport it to the third station 530. When the No. 1 ring threading car is discharging a full-bottle wire car, it encounters the No. 2 ring threading car traveling in the second direction. Since the No. 2 ring threading car is not in operation, the control unit dispatches the second track 300 to rise and dispatches the No. 2 ring threading car to travel to the third track 400. Because the No. 1 ring threading car is discharging a full-bottle wire car, the control unit dispatches the second track 300 to descend after the No. 2 ring threading car passes the maintenance area 410. The control unit dispatches another second track 300 to rise, and after the No. 2 ring threading car passes the other second track 300, the control unit dispatches another second track 300 to descend. After the second station 520 discharging a full-bottle wire car, it calls an empty-bottle wire car. The control unit then dispatches the No. 2 ring threading car to the first station 510 to receive the empty-bottle wire car and then to the empty-bottle wire car calling station to complete the flow of the empty-bottle wire car. The first direction and the second direction are opposite.
[0102] When a vehicle is awaiting repair in maintenance area 410, the second track 300 is deactivated, and other vehicles are prohibited from entering the second track 300. When the second track 300 is activated, if there are idle vehicles on the third track 400 and the third workstation 530 at the same time, the idle vehicle at the third workstation 530 will be dispatched first. When picking up and dropping off empty drum wire carts, the control unit can only dispatch the circumferential carts located at the first workstation 510, the third workstation 530, and the third track 400.
[0103] In this embodiment, when an idle loop vehicle is driven by a following vehicle, it directly enters the second track 300 and the third track 400 to wait for the next operation. This reduces the waste of equipment and energy, enables rapid response to job allocation, increases the effective operating time of equipment, and improves the efficiency of the conveyor line. At the same time, vehicles requiring maintenance are dispatched to the maintenance area of the third track 400 without affecting the normal operation of the main circuit, ensuring the smooth flow of products.
[0104] As can be seen from the above description, the embodiments of the present invention achieve the following technical effects:
[0105] The first track 100 has a ring structure, which provides a continuous travel path for the transport vehicle 200. The ring design of the first track 100 enables the transport vehicle 200 to run in a cycle, improving the continuity of material transportation and providing a stable and efficient basic operating environment for the entire conveying system.
[0106] The transport carrier 200 is movably set on the first track 100. The transport carrier 200 is used to carry and transport the target material. The transport carrier 200 moves cyclically on the first track 100, realizing the automatic flow of materials within the system. This ensures that materials can be delivered to the designated location as needed, reducing the cost and time of manual handling, improving logistics efficiency, and at the same time, the cyclical transport mode makes full use of system resources and reduces equipment idle rate.
[0107] The second track 300 is movably configured, with its two ends docking with the first track 100 and the third track 400, respectively. The second track 300 serves as a temporary channel connecting the first track 100 and the third track 400. Its mobility allows it to flexibly adjust its position. When docked, the second track 300 fills the gap between the first track 100 and the third track 400. The flexible docking mechanism of the second track 300 enables the system to move the transport carrier 200 according to actual needs, increasing the diversity of paths and improving the system's adaptability and flexibility.
[0108] The third track 400 is spaced apart from the first track 100. The third track 400 is used to receive the transport vehicle 200 transferred from the first track 100. The spaced arrangement of the third track 400 allows the first track 100 and the third track 400 to operate independently or in parallel. The third track 400 provides additional storage or processing area for the transport vehicle 200. The presence of the third track 400 alleviates the transport pressure on the first track 100. When the first track 100 is congested, the transport vehicle 200 can enter the third track 400 to wait, thereby ensuring the smooth flow of the main transport channel and improving the overall throughput and operational stability of the system.
[0109] The second track 300 guides the transport carrier 200. The second track 300 forms a continuous guiding structure at the docking position. The guiding function of the second track 300 ensures that the transport carrier 200 smoothly transitions from the first track 100 to the third track 400. The guiding design of the second track 300 eliminates the risk of misalignment at the track docking point, preventing the transport carrier 200 from derailing or getting stuck during the transfer process. The precise guidance of the second track 300 improves the safety and reliability of the transfer process, reduces downtime, and ensures the continuity and accuracy of material transportation.
[0110] When the second track 300 is in the docking position, it connects the first track 100 and the third track 400. This process enables the smooth transfer of the transport vehicle 200 from the first track 100 to the third track 400. The docking action of the second track 300 establishes a new path, and the transport vehicle 200 moves along the second track 300 to the third track 400. This transfer mechanism allows the system to divert some of the transport vehicles 200 to the third track 400 without interrupting the main transport flow on the first track 100. The movable docking design of the second track 300 enables dynamic switching between the main channel and the branch channel, ensuring the priority of the main transport task while providing flexible branch processing capabilities. This effectively balances the system load, improves the overall operating efficiency and robustness of the transport system, and solves the problem of easy congestion in existing transport systems.
[0111] It should be noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the exemplary embodiments according to this application. As used herein, the singular form is intended to include the plural form as well, unless the context clearly indicates otherwise. Furthermore, it should be understood that when the terms "comprising" and / or "including" are used in this specification, they indicate the presence of features, steps, operations, devices, components, and / or combinations thereof.
[0112] Unless otherwise specifically stated, the relative arrangement, numerical expressions, and values of the components and steps described in these embodiments do not limit the scope of this application. It should also be understood that, for ease of description, the dimensions of the various parts shown in the drawings are not drawn to actual scale. Techniques, methods, and devices known to those skilled in the art may not be discussed in detail, but where appropriate, such techniques, methods, and devices should be considered part of the specification. In all examples shown and discussed herein, any specific values should be interpreted as merely exemplary and not as limitations. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar reference numerals and letters in the following drawings denote similar items; therefore, once an item is defined in one drawing, it need not be further discussed in subsequent drawings.
[0113] For ease of description, spatial relative terms such as "above," "on top of," "on the upper surface of," "above," etc., are used herein to describe the spatial positional relationship of a device or feature as shown in the figures to other devices or features. It should be understood that spatial relative terms are intended to encompass different orientations in use or operation beyond the orientation of the device as described in the figures. For example, if the device in the figures were inverted, a device described as "above" or "on top of" other devices or structures would subsequently be positioned as "below" or "under" other devices or structures. Thus, the exemplary term "above" can include both "above" and "below." The device may also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatial relative descriptions used herein will be interpreted accordingly.
[0114] It should be noted that the terms "first," "second," etc., used in the specification, claims, and accompanying drawings of this application are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of this application described herein can be implemented in sequences other than those illustrated or described herein.
[0115] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A conveying system, characterized in that, include: The first track (100) has a ring structure; Transport vehicle (200) is used to transport the target material; The second track (300) and the third track (400) are spaced apart from the first track (100). The second track (300) is movably arranged, and its two ends are respectively connected to the first track (100) and the third track (400) so that the second track (300) is in a docking position. The transport vehicle (200) moves to the third track (400) via the second track (300). The second track (300) is separated from the first track (100) and the third track (400) and is in a clearance position. The transport vehicle (200) moves on the first track (100) or the third track (400).
2. The conveying system according to claim 1, characterized in that, There are multiple third tracks (400), each of which is spaced apart from the first track (100). Each of the third tracks (400) has a second track (300) at both ends, so that each of the third tracks (400) can be connected to or separated from the first track (100) through the second track (300).
3. The conveying system according to claim 1, characterized in that, The second track (300) has an arc-shaped structure; or, The second track (300) has a straight structure.
4. The conveying system according to claim 1, characterized in that, The transport vehicle (200) is provided with a steering assembly (201), the steering assembly (201) comprising: Steering component (210), the steering component (210) being located at the bottom of the transport vehicle (200); The second track (300) includes: When the second track (300) is in the docking position, the two ends of the guide track segment (310) are docked with the first track (100) and the third track (400) respectively, and the steering component (210) abuts against the side wall of the guide track segment (310) to guide the transport vehicle (200).
5. The conveying system according to claim 4, characterized in that, There are at least two steering components (201), and at least two steering components (201) are spaced apart on the transport vehicle (200) along the direction of movement of the transport vehicle (200).
6. The conveying system according to claim 4, characterized in that, The steering component (210) includes: A steering wheel (211) is rotatably disposed at the bottom of the transport vehicle (200), and the steering wheel (211) abuts against the side wall of the guide track section (310).
7. The conveying system according to claim 4, characterized in that, The second track (300) also includes: A support track section (320) is disposed on the guide track section (310); The steering assembly (201) also includes: A first driving member and a driving wheel (220) are provided. The driving wheel (220) is rotatably disposed and is in contact with the upper surface of the support track section (320). The first driving member is drivingly connected to the driving wheel (220) and drives the driving wheel (220) to rotate so as to move the transport carrier (200).
8. The conveying system according to claim 1, characterized in that, A second driving member (330) is provided on the second track (300). The second driving member (330) is driven to connect with the second track (300) to drive the second track (300) to move, so that the two ends of the second track (300) are respectively connected to the first track (100) and the third track (400).
9. The conveying system according to claim 8, characterized in that, The second drive unit (330) has an output shaft that is telescopically configured and connected to the second track (300) to drive the second track (300) to rise and fall; or, The second drive unit (330) also includes: A first connector (331) and a second connector (332) are arranged in a cross configuration. The ends of the first connector (331) and the second connector (332) are slidably connected to the second track (300). The output shaft is located at the intersection of the first connector (331) and the second connector (332). The output shaft passes through the first connector (331) and the second connector (332) in sequence. The output shaft is threadedly connected to the first connector (331) and the second connector (332) respectively. The output shaft is rotatably configured so that the first connector (331) and the second connector (332) can be retracted or opened to push the second track (300) up and down.
10. A scheduling method, characterized in that, The scheduling method is applicable to the conveying system according to any one of claims 1 to 9, wherein there are at least two transport carriers (200), and at least two of the transport carriers (200) are movably arranged on the first track (100) to transport target materials; the conveying system further includes a control unit, which is signal-connected to each of the transport carriers (200), and the scheduling method includes: Obtain the location information of at least two of the transport vehicles (200); Based on the location information, determine whether one of the at least two transport vehicles (200) is located on the movement path of the other transport vehicle (200); When one of the transport vehicles (200) is on the movement path of another transport vehicle (200), the second track (300) is controlled to move so that the first track (100) and the third track (400) are connected through the second track (300), and then one of the transport vehicles (200) is controlled to move to the third track (400).