A method for real-time BIM comparison and hierarchical early warning of cumulative deformation throughout the construction process of steel space frame

By deploying sensors on the BIM model of the steel space frame to monitor and verify deformation data in real time, the problems of real-time deformation monitoring and hierarchical early warning in the construction of the steel space frame are solved, achieving efficient deformation management in the construction process and reducing construction risks and costs.

CN123116385APending Publication Date: 2026-11-17CHINA MCC17 GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611051536.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-15
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The existing steel space frame construction process lacks continuous deformation monitoring, making it impossible to know the deformation trend in real time. The monitoring data is disconnected from the BIM model, making it impossible to achieve graded early warning. As a result, it is difficult to correct the excessive deformation after construction and the cost is high.

Method used

Key control points are selected on the BIM design model of the steel space frame, coordinate measurement targets, temperature sensors and strain sensors are set up, data is monitored in real time and uploaded to the cloud platform, temperature deformation is stripped through consistency verification, the real deformation value is calculated, dynamic early warning thresholds are set and deformation distribution is updated in real time in the BIM model to trigger graded early warning signals.

Benefits of technology

It enables real-time deformation monitoring and linkage with the BIM model during the construction of steel space frame, improving the accuracy and reliability of monitoring data, reducing the risk of rework due to excessive cumulative deformation, and enhancing decision-making efficiency and deformation situation awareness on the construction site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123116385A_ABST
    Figure CN123116385A_ABST
Patent Text Reader

Abstract

This invention discloses a method for real-time comparison and graded early warning of cumulative deformation in steel space frame construction using BIM. This invention relates to the field of building construction monitoring and intelligent construction technology, and solves the technical problems of post-construction correction, inability to know deformation trends in real time, and disconnect between monitoring data and the BIM model in steel space frame construction deformation monitoring. This invention imports the steel space frame BIM design model into a deformation monitoring cloud platform. Throughout the construction process, a total station is used to measure the actual three-dimensional coordinates of key control points of the steel space frame in batches, and the coordinate data is uploaded to the cloud platform in real time. The cloud platform automatically compares the measured coordinates with the theoretical coordinates in the BIM design model, calculates the deformation deviation value, and triggers a three-level early warning mechanism based on the magnitude of the deformation deviation value. This solves the problem of hindsight regarding cumulative deformation in steel space frame construction, advancing the detection of deformation from post-construction acceptance to the construction process, and reducing the risk of rework due to excessive cumulative deformation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction monitoring and intelligent construction technology, specifically a method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction in the entire process using BIM. Background Technology

[0002] During the construction of steel space frame structures, cumulative deformation (deflection) will occur due to factors such as the self-weight of the members, the removal of temporary supports, and temperature deformation. If the cumulative deformation is too large, it will affect the final geometric accuracy and load-bearing performance of the structure, and in severe cases, it may even lead to structural safety accidents.

[0003] Current deformation monitoring methods mainly involve: after construction, using a total station to measure the elevation of several control points and comparing it with the design values; the monitoring data is recorded manually and then entered into a computer for analysis. The above methods have the following prominent problems: Deformation monitoring is conducted only after construction is completed. If the deformation exceeds the limit at this time, rectification will be difficult and costly.

[0004] The lack of continuous deformation monitoring data during construction makes it impossible to determine whether the deformation exceeds the warning value.

[0005] Existing monitoring methods can only provide discrete deformation data and cannot intuitively display the location and amount of deformation in the BIM model, making it difficult for construction personnel to quickly understand the deformation situation.

[0006] Existing technologies include a technical solution that compares total station measurement data with BIM models, but it is usually only used for final acceptance after construction is completed, failing to cover the entire construction process and unable to achieve graded early warning. Summary of the Invention

[0007] To address the shortcomings of existing technologies, this invention provides a method for real-time comparison and hierarchical early warning of cumulative deformation in steel space frame construction using BIM, which solves the problems of post-construction correction, inability to know deformation trends in real time, and disconnect between monitoring data and BIM model in steel space frame construction deformation monitoring.

[0008] To achieve the above objectives, the present invention provides the following technical solution: a method for real-time comparison and hierarchical early warning of cumulative deformation in the entire construction process of a steel space frame using BIM, the method specifically including the following steps: Step 1: Import the steel space frame BIM design model into the monitoring cloud platform, select several key control points on the model, set up coordinate measurement targets, temperature sensors and strain sensors at each key control point, and record the theoretical coordinate values ​​of each key control point. Step 2: Divide the entire steel space frame construction process into several construction batches. After each batch is completed, measure the actual three-dimensional coordinates of all key control points, collect temperature and strain data at each monitoring point simultaneously, and upload the measurement data to the cloud platform. Step 3: Based on the temperature data, the temperature deformation component is separated from the total measured deformation to obtain the actual deformation value of the structure. At the same time, the theoretical deformation value is calculated based on the strain data. The consistency between the actual deformation value and the theoretical deformation value is checked to determine whether the data is normal. Step 4: Based on the structural stiffness development level corresponding to the current construction batch, dynamically set the early warning threshold for the batch. Based on the comparison between the actual structural deformation value of the current batch and the early warning threshold, trigger the corresponding level of early warning signal and execute the corresponding handling measures.

[0009] As a further aspect of the present invention, the specific method for separating the temperature deformation component from the total measured deformation based on temperature data is as follows: Based on the temperature data of each monitoring point and the coefficient of thermal expansion of steel α, the deformation component caused by temperature ΔT = α × L × ΔTEMP is calculated, where L is the original length of the component and ΔTEMP is the amount of temperature change. By separating the temperature deformation from the total deformation ΔL measured by the total station, the actual structural deformation ΔS = ΔL - ΔT is obtained.

[0010] As a further aspect of the present invention, the specific method for calculating the theoretical deformation value based on strain data is as follows: According to the formula The theoretical deformation value Δ is calculated, where Let be the strain function at each point along the length of the component.

[0011] As a further aspect of the present invention, the step of verifying the consistency between the actual deformation value and the theoretical deformation value of the structure to determine whether the data is normal includes: The difference between the actual deformation value ΔS and the theoretical deformation value Δ is calculated to obtain the deformation deviation η. If 5% < η ≤ 10%, it is judged as data fluctuation, and the data set is automatically marked as pending verification. The system prompts the operator to check the sensor condition. If η > 10%, the data is considered abnormal, and the system will automatically issue a retest command until the retest data passes the verification. Conversely, if the deviation rate η ≤ 5%, the data is considered normal.

[0012] As a further aspect of the present invention, the actual deformation value ΔS of the structure after verification is mapped to the corresponding control point in the BIM model, and the deformation distribution is updated in real time in the form of a heat map. In the heat map, cool colors represent small deformation and warm colors represent large deformation, and the deformation history curve of each control point is dynamically displayed in the model.

[0013] As a further aspect of the present invention, the specific method for dynamically setting the early warning threshold for this batch is as follows: A finite element model was established based on the BIM model to simulate and calculate the theoretical deformation value D for each construction batch. i And i = 1, 2, ..., n represent construction batches. After each batch is completed, the actual deformation ΔS of the structure is measured and obtained. i Then, ΔS i Compared with the theoretical deformation value D of the current batch i Compare and calculate the deviation rate δ i =|ΔS i -D i | / D i ×100%, if δ i If the value exceeds the second preset threshold, it is determined that the finite element model has a deviation, and a penalty is imposed to correct and update the model. For the warning threshold setting of batch i, the green warning interval |ΔS i |≤1.2×D i Yellow alert zone 1.2×D i <|ΔS i |≤1.5×D i Red alert zone | ΔS i |>1.5×D i .

[0014] As a further aspect of the present invention, a deformation rate index is introduced, and the deformation rate V is calculated based on the actual deformation data of the completed batches. k =(ΔS k -ΔS k-1 ) / (t k -t k-1 ), where t k For the completion time of the kth batch, based on the construction process simulation results and the 3σ criterion, a change rate warning threshold is set: Green warning interval |V k |≤μ+σ;Yellow warning zone:μ+σ<|V k |≤μ+2σ;Red warning interval:|V k |>μ+2σ, where μ is the mean of the historical rate of change and σ is the standard deviation.

[0015] As a further aspect of the present invention, step four also includes: The deformation data of the first k batches that have been completed are used as the original sequence. At the same time, the timestamp information of each batch is introduced as a prior constraint to establish a non-equidistant GM(1,1) prediction model. After each batch is completed, the measured values ​​are substituted into the model to recalculate the model parameters, so as to realize the dynamic iterative optimization of the prediction model. Based on the updated model, the deformation values ​​of the k+1th batch and the final batch are predicted.

[0016] As a further aspect of the present invention, triggering the corresponding level of warning signal and executing the corresponding handling measures includes: If both the deformation deviation and the predicted deformation value are within the green warning range, a green warning signal is generated, construction continues, and the system records the monitoring data. When the actual or predicted deformation value of the structure is in the yellow warning range, a yellow warning signal is generated, a warning notice is sent and subsequent batches of construction are suspended, the cause is investigated and local corrections are made. When the actual or predicted deformation value of the structure is in the red warning range, a red warning signal is generated, an alarm notification is sent and work is stopped immediately, and a forced correction plan is automatically generated.

[0017] As a further aspect of the present invention, dividing the entire steel space frame construction process into several construction batches includes: Four batches were completed: 30% of the poles installed, 60% of the poles installed, 100% of the poles installed, and 24 hours after the temporary supports were removed.

[0018] This invention provides a method for real-time BIM comparison and hierarchical early warning of cumulative deformation throughout the entire construction process of a steel space frame. Compared with existing technologies, it has the following advantages: This invention establishes a three-dimensional monitoring system of coordinates, temperature, and strain by simultaneously deploying total station measurement targets, temperature sensors, and strain sensors at key control points. Furthermore, through consistency cross-validation, it achieves mutual verification of multi-source data, eliminating misjudgments caused by sensor malfunctions or temperature interference from a single data source, thus improving the accuracy and reliability of monitoring data. Secondly, the verified actual structural deformation value ΔS is mapped in real-time to the corresponding control points in the BIM model, updating the deformation distribution in real-time using a heatmap. The deformation history curve of each control point is dynamically displayed in the model, allowing construction personnel to intuitively see which areas have significant deformation and how the deformation evolves with the construction process, enhancing the construction site's ability to perceive deformation trends and improving decision-making efficiency.

[0019] This invention constructs a three-dimensional linkage early warning mechanism, which avoids missed detection when a single threshold is abnormal in one dimension while other dimensions are normal. It advances the time for detecting deformation from post-acceptance to the construction process, reduces the risk of rework due to excessive cumulative deformation, and improves the comprehensiveness and accuracy of the early warning. Attached Figure Description

[0020] Figure 1 This is an overview diagram of the method flow of the present invention; Figure 2 This is a schematic diagram of the deformation heat map visualization in the BIM model of this invention; Figure 3 This is a schematic diagram of the three-level early warning triggering logic of the present invention; Figure 4 This is a schematic diagram illustrating the batch division and measurement timing of the entire construction process of this invention. Detailed Implementation

[0021] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0022] First Embodiment Please see Figure 1 This application provides a method for real-time comparison and hierarchical early warning of cumulative deformation in steel space frame construction using BIM. The method specifically includes the following steps: Step 1: Import the steel space frame BIM design model into the deformation monitoring cloud platform. At the same time, select several key control points on the model, such as mid-span nodes, support nodes, and 1 / 4 span nodes. At each key control point, deploy a total station measurement target, temperature sensor, and strain sensor to record the theoretical coordinate values ​​of each key control point.

[0023] Step 2: Next, the entire steel space frame construction process is divided into several construction batches, such as: Batch 1 = 30% of the members are installed, Batch 2 = 60% is completed, Batch 3 = 100% is completed, Batch 4 = after the temporary supports are removed. After each batch of construction is completed, the actual three-dimensional coordinates of all key control points are measured using a total station, and the temperature and strain data of each monitoring point are collected simultaneously and uploaded to the cloud platform.

[0024] Step 3: The cloud platform receives multi-source data and, based on the temperature data from each monitoring point and the steel expansion coefficient α, calculates the temperature-induced deformation component ΔT = α × L × ΔTEMP, where L is the original length of the component, and ΔTEMP is the temperature change, i.e., the current measured temperature minus the reference temperature before construction. Simultaneously, the temperature deformation is extracted from the total deformation ΔL measured by the total station to obtain the actual structural deformation ΔS = ΔL - ΔT. Furthermore, the theoretical deformation value is calculated based on strain data, specifically according to the formula... The theoretical deformation value Δ is calculated, where The strain function is given at each point along the length of the component. The system compares the actual deformation value ΔS with the theoretical deformation value Δ, calculates the difference between the actual deformation value ΔS and the theoretical deformation value Δ to obtain the deformation deviation η. If 5% < η ≤ 10%, it is judged as data fluctuation, and the data set is automatically marked as pending verification. The system prompts the operator to check the sensor condition. If η > 10%, it is judged as data abnormal. The system automatically issues a retest command and locks the batch of data to not participate in subsequent early warning calculations until the retest data passes the verification. Conversely, if the deviation rate η ≤ 5%, the data is judged as normal. If η>10% occurs in two consecutive batches, the system will automatically issue a sensor system fault alarm, prompting the repair of all sensors; The actual deformation value ΔS of the structure after verification is mapped to the corresponding control point in the BIM model, and the deformation distribution is updated in real time in the form of a heat map. In the heat map, cool colors = small deformation and warm colors = large deformation. The deformation history curve of each control point is dynamically displayed in the model.

[0025] Step 4: For the deformation deviation calculated under normal data conditions, make dynamic adjustments based on the structural stiffness development level corresponding to the current construction batch. The specific adjustment method is as follows: Before construction begins, a finite element model is established based on the BIM model to simulate and calculate the theoretical deformation value D for each construction batch. i And i = 1, 2, ..., n represent construction batches. After each batch is completed, the actual deformation ΔS of the structure is measured and obtained. i Then, ΔS i Compared with the theoretical deformation value D of the current batch i Compare and calculate the deviation rate δ i =|ΔS i -D i | / D i ×100%, if δ i If the value exceeds the second preset threshold (where the second preset threshold is 10%), it is determined that there is a deviation in the boundary conditions or load assumptions of the finite element model. The system automatically triggers a model correction procedure, specifically using measured deformation data as the objective function and employing an optimization algorithm to inversely calculate the equivalent boundary stiffness, nodal connection stiffness, and actual load distribution of the model, generating correction coefficients and updating the finite element model parameters. For batch i, the warning threshold setting is a green warning interval |ΔS i |≤1.2×D i Yellow alert zone 1.2×D i <|ΔS i |≤1.5×D i Red alert zone | ΔS i |>1.5×D i ; Simultaneously, a deformation change rate index is introduced, and the deformation change rate V is calculated based on the actual deformation data of the completed batches. k =(ΔS k -ΔS k-1 ) / (t k -t k-1 ), where t k For the completion time of the kth batch, based on the construction process simulation results and the 3σ criterion, a change rate warning threshold is set: Green warning interval |V k |≤μ+σ;Yellow warning zone:μ+σ<|V k |≤μ+2σ;Red warning interval:|V k |>μ+2σ, where μ is the mean of the historical rate of change and σ is the standard deviation; Since the time intervals between construction batches are not equal, a non-equidistant grey prediction model is required. The deformation data of the first k completed batches are used as the original sequence, and the timestamp information of each batch is introduced as a priori constraint to establish a non-equidistant GM(1,1) prediction model. After each batch is completed, the measured values ​​are substituted into the model to recalculate the model parameters, so as to realize the dynamic iterative optimization of the prediction model. Based on the updated model, the deformation values ​​of the (k+1)th batch and the final batch are predicted.

[0026] Step 5: Next, the deformation deviation and predicted deformation value are combined for graded early warning processing. If both the deformation deviation and the predicted deformation value are in the green early warning range, a green early warning signal is generated. This signal indicates that the situation is normal and construction can continue. The system records the monitoring data. If the deformation deviation is in the yellow warning zone, or the predicted deformation value is in the yellow warning interval, a yellow warning signal will be generated. This signal will be automatically sent to warn and notify the relevant person in charge, suspend subsequent batches of construction, investigate the cause, and carry out local correction if necessary. If the deformation deviation is within the red warning zone, or if the predicted deformation value will enter the red warning zone, a red warning signal will be generated. This signal will automatically send an alarm notification to the project manager and supervising engineer, and at the same time automatically generate a mandatory correction plan, including: the specific lifting amount and lifting point of the suggested local lifting adjustment; the suggested suspended construction procedures and resumption conditions; and a visual correction simulation based on the BIM model.

[0027] Step Six: After the entire construction process is completed, the cloud platform will automatically generate a cumulative deformation monitoring report, which includes: the original deformation value of each batch, the actual deformation value after temperature stripping, the comparison between the predicted value and the measured value, the early warning trigger record, the corrective measures and their implementation effect, and the conclusion on whether the final deformation value meets the design requirements.

[0028] Second Embodiment As a second embodiment of the present invention, this embodiment is implemented based on the first embodiment, and provides a specific implementation method for real-time BIM comparison and hierarchical early warning of cumulative deformation throughout the construction process of steel space frame, as follows: Taking the construction project of the steel space frame for the indoor sports field of a junior high school as an example, the projected area of ​​the steel space frame for the indoor sports field is 3200m². 2 The span is 48m, with 8 support nodes, 1 mid-span node, and 4 1 / 4 span nodes. A total of 13 key control points were selected for monitoring. The method of the first embodiment was used to monitor and warn of cumulative deformation throughout the construction process. Open the BIM design model of the steel space frame of the indoor sports field using Autodesk Revit 2022 software, import the model into the deformation monitoring cloud platform developed based on Autodesk BIM360 platform, select 13 key control points on the BIM model, record the theoretical coordinate values ​​(X / Y / Z) of each control point in the BIM model, and set the warning thresholds: green ≤10mm, yellow 10~20mm, red >20mm. Place 30mm diameter reflective sheets at the corresponding positions on the construction site as measurement targets to ensure that the total station can observe clearly. The entire construction process of the steel space frame for the indoor sports field was divided into four construction batches: Batch 1: Completed 30% of the pole installation, approximately 960 poles, and measured the actual coordinates of all 13 control points; Batch 2: Completed 60% of the pole installation, approximately 1920 poles, and measured the actual coordinates of all 13 control points; Batch 3: Complete 100% installation of 3200 poles, and measure the actual coordinates of all 13 control points; Batch 4: 24 hours after the temporary supports are removed, measure the actual coordinates of all 13 control points.

[0029] After each batch is completed, the actual three-dimensional coordinates of all 13 control points are measured using a total station, and the coordinate data is uploaded to the cloud platform in real time via Bluetooth. After receiving the measured coordinate data, the cloud platform automatically calculates the deformation deviation value, taking the mid-span node as an example: Theoretical coordinates: (12560, 8920, 15600) mm Batch 1 measured coordinates: (12560, 8921, 15598) mm, deviation ΔZ=-2mm, total deviation ΔL=2mm, green alert, continue construction; Batch 2 measured coordinates: (12560, 8923, 15595) mm, deviation ΔZ=-5mm, total deviation ΔL=5mm, green alert, continue construction; Batch 3 measured coordinates: (12560, 8928, 15589) mm, deviation ΔZ=-11mm, total deviation ΔL=11mm, yellow warning, construction suspended and cause investigated; Batch 4 measured coordinates: (12560, 8932, 15586) mm, deviation ΔZ=-14mm, total deviation ΔL=14mm, yellow warning.

[0030] After the measurement of batch 3 was completed, the system automatically triggered a yellow warning, and the cloud platform automatically sent a warning notification to the construction manager. The construction manager organized technical personnel to investigate the cause and concluded that the large deformation was due to the high temperature (35℃) on that day, which caused the space frame to deform excessively due to temperature.

[0031] Remedial measures: Adjust the construction time to avoid installing the poles during the high-temperature period; at the same time, before batch 4, choose to carry out the dismantling work in the early morning when the temperature is lower to reduce the impact of temperature deformation.

[0032] Some of the data in the above formulas are numerical calculations with dimensions removed, and the contents not described in detail in this specification are all prior art known to those skilled in the art.

[0033] The above embodiments are only used to illustrate the technical methods of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical methods of the present invention without departing from the spirit and scope of the technical methods of the present invention.

Claims

1. A method for real-time comparison and hierarchical early warning of cumulative deformation in steel space frame construction throughout the entire process, characterized in that... The method specifically includes the following steps: Step 1: Import the steel space frame BIM design model into the monitoring cloud platform, select several key control points on the model, set up coordinate measurement targets, temperature sensors and strain sensors at each key control point, and record the theoretical coordinate values ​​of each key control point. Step 2: Divide the entire steel space frame construction process into several construction batches. After each batch is completed, measure the actual three-dimensional coordinates of all key control points, collect temperature and strain data at each monitoring point simultaneously, and upload the measurement data to the cloud platform. Step 3: Based on the temperature data, the temperature deformation component is separated from the total measured deformation to obtain the actual deformation value of the structure. At the same time, the theoretical deformation value is calculated based on the strain data. The consistency between the actual deformation value and the theoretical deformation value is checked to determine whether the data is normal. Step 4: Based on the structural stiffness development level corresponding to the current construction batch, dynamically set the early warning threshold for the batch. Based on the comparison between the actual structural deformation value of the current batch and the early warning threshold, trigger the corresponding level of early warning signal and execute the corresponding handling measures.

2. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 1, characterized in that, The specific method for separating the temperature deformation component from the total measured deformation based on temperature data is as follows: Based on the temperature data of each monitoring point and the coefficient of thermal expansion of steel α, the deformation component caused by temperature ΔT = α × L × ΔTEMP is calculated, where L is the original length of the component and ΔTEMP is the amount of temperature change. By separating the temperature deformation from the total deformation ΔL measured by the total station, the actual structural deformation ΔS = ΔL - ΔT is obtained.

3. The method for real-time comparison and graded early warning of cumulative deformation of steel space frame construction process according to claim 1, characterized in that, The specific method for calculating the theoretical deformation value based on strain data is as follows: According to the formula The theoretical deformation value Δ is calculated, where Let be the strain function at each point along the length of the component.

4. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 1, characterized in that, The process of verifying the consistency between the actual deformation value and the theoretical deformation value of the structure to determine whether the data is normal includes: The difference between the actual deformation value ΔS and the theoretical deformation value Δ is calculated to obtain the deformation deviation η. If 5% < η ≤ 10%, it is judged as data fluctuation, and the data set is automatically marked as pending verification. The system prompts the operator to check the sensor condition. If η > 10%, the data is considered abnormal, and the system will automatically issue a retest command until the retest data passes the verification. Conversely, if the deviation rate η ≤ 5%, the data is considered normal.

5. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 4, characterized in that, The actual deformation value ΔS of the structure after verification is mapped to the corresponding control point in the BIM model, and the deformation distribution is updated in real time in the form of a heat map. In the heat map, cool colors represent small deformation and warm colors represent large deformation, and the deformation history curve of each control point is dynamically displayed in the model.

6. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 1, characterized in that, The specific method for dynamically setting the warning threshold for this batch is as follows: A finite element model was established based on the BIM model to simulate and calculate the theoretical deformation value D for each construction batch. i And i = 1, 2, ..., n represent construction batches. After each batch is completed, the actual deformation ΔS of the structure is measured and obtained. i Then, ΔS i Compared with the theoretical deformation value D of the current batch i Compare and calculate the deviation rate δ i =|ΔS i -D i | / D i ×100%, if δ i If the value exceeds the second preset threshold, it is determined that the finite element model has a deviation, and a penalty is imposed to correct and update the model. For the warning threshold setting of batch i, the green warning interval |ΔS i |≤1.2×D i Yellow alert zone 1.2×D i <|ΔS i |≤1.5×D i Red alert zone | ΔS i |>1.5×D i .

7. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 6, characterized in that, Introducing the deformation rate index, the deformation rate V is calculated based on the actual deformation data of completed batches. k =(ΔS k -ΔS k-1 ) / (t k -t k-1 ), where t k For the completion time of the kth batch, based on the construction process simulation results and the 3σ criterion, a change rate warning threshold is set: Green warning interval |V k |≤μ+σ;Yellow warning zone:μ+σ<|V k |≤μ+2σ;Red warning interval:|V k |>μ+2σ, where μ is the mean of the historical rate of change and σ is the standard deviation.

8. The method for real-time comparison and hierarchical early warning of cumulative deformation BIM throughout the construction process of a steel space frame according to claim 1, characterized in that, Step four also includes: The deformation data of the first k batches that have been completed are used as the original sequence. At the same time, the timestamp information of each batch is introduced as a prior constraint to establish a non-equidistant GM(1,1) prediction model. After each batch is completed, the measured values ​​are substituted into the model to recalculate the model parameters, so as to realize the dynamic iterative optimization of the prediction model. Based on the updated model, the deformation values ​​of the k+1th batch and the final batch are predicted.

9. The method for real-time comparison and hierarchical early warning of cumulative deformation of steel space frame construction process according to claim 1, characterized in that, The triggering of the corresponding level of warning signal and the execution of corresponding handling measures include: If both the deformation deviation and the predicted deformation value are within the green warning range, a green warning signal is generated, construction continues, and the system records the monitoring data. When the actual or predicted deformation value of the structure is in the yellow warning range, a yellow warning signal is generated, a warning notice is sent and subsequent batches of construction are suspended, the cause is investigated and local corrections are made. When the actual or predicted deformation value of the structure is in the red warning range, a red warning signal is generated, an alarm notification is sent and work is stopped immediately, and a forced correction plan is automatically generated.

10. The method for real-time comparison and hierarchical early warning of cumulative deformation BIM throughout the construction process of a steel space frame according to claim 1, characterized in that, The division of the entire steel space frame construction process into several construction batches includes: Four batches were completed: 30% of the poles installed, 60% of the poles installed, 100% of the poles installed, and 24 hours after the temporary supports were removed.