Hinged type deformed steel bent railway station building steel roof truss
By adopting articulated connection and temporary support structures in the steel row strata, the problems of lifting, anchoring and temporary stability in the construction of steel row strata are solved, construction safety and efficiency are improved, and installation accuracy is achieved.
Patent Information
- Application Number
- CN202420343020.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-23
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction of steel rack type roof strata, there are problems such as lifting and installation of roof strata structure, anchoring connection between roof strata and support columns, and temporary stability during roof strata installation, resulting in low construction safety and efficiency and low accuracy.
The steel roof framing of the railway station building is adopted by articulated special-shaped steel racks. The steel roof framing is connected to the anchor column through the articulated connection between the steel frame columns and the anchor columns, combined with the bracket trolley and temporary cantilever braces to achieve semi-flexible connection and temporary stability, reducing the risk of brittle damage and lateral displacement deviation. , improve installation reliability and safety.
The risk of brittle damage at the connection is reduced through articulated connections, the construction safety and efficiency of the steel roof squad is improved, and the reliability and accuracy of the installation process is ensured.
Smart Images

Figure CN222120489U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of railway station building steel roof truss construction, in particular to an articulated special-shaped steel frame railway station building steel roof truss. Background Art
[0002] The construction process of steel frame type roof trusses involves the hoisting and installation of the roof truss structure, the anchoring connection between the roof truss and the supporting columns, the installation of the cantilever section of the roof truss, the temporary stabilization of the roof truss during installation, and other issues. It is necessary to further improve the construction method of the steel roof truss in order to improve the safety of the construction and installation of the steel roof truss and improve the construction efficiency and accuracy. Utility Model Content
[0003] The utility model aims to overcome the deficiencies in the prior art and provide an articulated special-shaped steel frame railway station building steel roof truss.
[0004] The hinged special-shaped steel frame railway station steel roof frame includes a steel frame, a cantilever steel frame, a concrete column and an anchor column. One end of the steel frame is provided with a plurality of steel frame columns, the bottom end of the steel frame column is hinged with the top end of the anchor column, and the other end of the steel frame is constructed with a cantilever steel frame, and the concrete column is supported under the steel frame and the cantilever steel frame.
[0005] A support trolley is fixed next to the anchor column to temporarily support the steel frame column; a temporary cantilever support is installed on the concrete column under the cantilever steel frame to temporarily support the cantilever steel frame.
[0006] Preferably, an embedded end is embedded on the anchor column, and the embedded end includes an embedded plate at the top of the anchor column. The lower part of the embedded plate is connected to a steel pipe, a longitudinal steel plate and a transverse steel plate. The longitudinal steel plate and the transverse steel plate are arranged vertically, and the longitudinal steel plate and the transverse steel plate are inserted between the steel pipes.
[0007] Preferably, a hinged end is used to connect the steel frame column and the anchor column, a connecting plate is connected to the bottom of the steel frame column, a hinged end one is connected to the bottom of the connecting plate, matching through holes are provided at the hinged end one and the hinged end two, the hinged end one and the hinged end two are staggered and plugged, and a pin is passed through the through holes.
[0008] Preferably, the support trolley includes: a support base plate for installing support rods, a walking wheel is provided at the bottom of the support base plate, the support rods include main support rods, secondary support rods and cross-linking rods, the bottom end of the main support rods is fixed to the support base plate, a fixing frame is installed at the top end of the main support rods, the fixing frame is clamped on the steel frame column, the two ends of the cross-linking rod are respectively connected to the main support rod and the anchor column, and the two ends of the secondary support rod are respectively connected to the main support rod and the support base plate.
[0009] Preferably, a side connecting rod is installed on the side of the bracket base plate, and a stabilizing frame is provided at one end of the side connecting rod, and the stabilizing frame is clamped at the bottom of the anchor column.
[0010] Preferably, the temporary cantilever support includes: a bottom frame, a middle frame and a top frame clamped on the concrete column, vertical fixing rods are inserted between the bottom frame, the middle frame and the top frame, a support frame is clamped on the concrete column between the top frame and the middle frame, the support frame extends horizontally, and a diagonal support is connected between the support frame and the bottom frame; the support frame includes longitudinal ribs, outer transverse ribs, inner transverse ribs and diagonal ribs, a plurality of support rods are arranged on the top surface of the support frame, and the support rods are supported under the cantilever steel frame.
[0011] Preferably, the steel frame further comprises a secondary beam, the secondary beam and the concrete column are arranged at corresponding positions, one end of the cantilever steel frame is fixed on the secondary beam, and the cantilever steel frame is also provided with a secondary beam corresponding to the concrete column.
[0012] The beneficial effects of the utility model are:
[0013] 1) The steel frame column and the anchor column are hingedly connected, and the connection between the two is changed from a traditional fixed connection to a semi-flexible connection through the hinged connection, reducing the risk of brittle failure at the connection.
[0014] 2) The hinged ends are respectively arranged on the steel frame column and the anchor column, so as to facilitate the hinged connection between the steel frame column and the anchor column, and the method of use is convenient.
[0015] 3) Use the support trolley to temporarily stabilize the steel frame column to prevent the steel frame column from lateral displacement and deviation, thereby ensuring the connection reliability of the steel frame column. The support trolley is movable for flexible positioning.
[0016] 4) The cantilever steel frame is constructed using temporary cantilever supports, which are used as temporary bearing platforms for the cantilever steel frame to ensure the temporary stability of the cantilever steel frame and the safety of the installation process. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic diagram of the steel roof truss structure of an articulated special-shaped steel frame railway station building;
[0018] Figure 2 for Figure 1 Schematic diagram of node A in the middle;
[0019] Figure 3 for Figure 1 Schematic diagram of node B in the middle;
[0020] Figure 4 This is a schematic diagram of the embedded end structure of the steel roof truss of the articulated special-shaped steel frame railway station building;
[0021] Figure 5 for Figure 4 Schematic diagram of the C node;
[0022] Figure 6 This is a schematic diagram of the construction status of the steel roof truss of the articulated special-shaped steel frame railway station building;
[0023] Figure 7 for Figure 6 Schematic diagram of the D node;
[0024] Figure 8 for Figure 6 Schematic diagram of the E node.
[0025] Explanation of reference numerals: 1. steel frame; 2. steel frame column; 3. cantilever steel frame; 4. concrete column; 5. secondary beam; 6. fulcrum; 7. hinged end; 8. anchor column; 9. connecting plate; 10. embedded plate; 11. hinged end 1; 12. hinged end 2; 13. pin shaft; 14. embedded end; 15. steel pipe; 16. embedded plate; 17. longitudinal steel plate; 18. transverse steel plate; 19. support trolley; 2 0. Walking wheel; 21. Bracket bottom plate; 22. Stabilizing frame; 23. Horizontal connecting rod; 24. Fixed frame; 25. Main support rod; 26. Secondary support rod; 27. Side connecting rod; 28. Temporary cantilever support; 29. Bottom frame; 30. Middle frame; 31. Top frame; 32. Diagonal support; 33. Longitudinal rib; 34. Support frame; 35. Outer transverse rib; 36. Inner transverse rib; 37. Diagonal rib; 38. Support rod; 39. Vertical fixing rod. DETAILED DESCRIPTION
[0026] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.
[0027] As an example, Figures 1 to 8 As shown, this articulated special-shaped steel bent frame railway station steel roof truss includes a steel bent frame 1, a cantilever steel frame 3, a concrete column 4 and an anchor column 8. One end of the steel bent frame 1 is provided with a plurality of steel frame columns 2, the bottom end of the steel frame column 2 is hinged to the top end of the anchor column 8, and the other end of the steel bent frame 1 is constructed with a cantilever steel frame 3, and the concrete column 4 is supported under the steel bent frame 1 and the cantilever steel frame 3;
[0028] like Figure 4 and Figure 5 As shown, an embedded end 14 is embedded on the anchor column 8, and the embedded end 14 includes an embedded plate at the top of the anchor column 8, and the lower part of the embedded plate is connected to a steel pipe 15, a longitudinal steel plate 17 and a transverse steel plate 18, and the longitudinal steel plate 17 and the transverse steel plate 18 are arranged vertically, and the longitudinal steel plate 17 and the transverse steel plate 18 are inserted between the steel pipe 15.
[0029] like Figure 3As shown, the steel frame column 2 and the anchor column 8 are connected by the hinged end 7, the bottom of the steel frame column 2 is connected to a connecting plate 9, the bottom of the connecting plate 9 is connected to a hinged end 11, the hinged end 11 and the hinged end 2 12 are both provided with matching through holes, the hinged end 11 and the hinged end 2 12 are staggered and inserted, and a pin shaft 13 is passed through the through holes.
[0030] A support trolley 19 is fixed next to the anchor column 8 for temporarily supporting the steel frame column 2 ; a temporary cantilever support is installed on the concrete column 4 below the cantilever steel frame 3 for temporarily supporting the cantilever steel frame 3 .
[0031] like Figure 1 and Figure 2 As shown, the steel bent frame 1 also includes a secondary beam 5, and the secondary beam 5 and the concrete column 4 are arranged at corresponding positions. One end of the cantilever steel frame 3 is fixed on the secondary beam 5, and the cantilever steel frame 3 is also provided with a secondary beam 5 corresponding to the concrete column 4. A fulcrum 6 is provided at the top of the concrete column 4 to support the bottom of the concrete column 4.
[0032] Embodiment 2
[0033] As another embodiment, this embodiment 2 is proposed on the basis of the embodiment 1, such as the articulated special-shaped steel frame railway station steel roof truss Figure 6 and Figure 7 As shown, the support trolley 19 includes: a support base plate 21 for installing support rods, a walking wheel 20 is provided at the bottom of the support base plate 21, the support rods include a main support rod 25, a secondary support rod 26 and a transverse connecting rod 23, the bottom end of the main support rod 25 is fixed on the support base plate 21, the top end of the main support rod 25 is installed with a fixing frame 24, the fixing frame 24 is clamped on the steel frame column 2, the two ends of the transverse connecting rod 23 are respectively connected to the main support rod 25 and the anchor column 8, and the two ends of the secondary support rod 26 are respectively connected to the main support rod 25 and the support base plate 21.
[0034] A side connecting rod 27 is installed on the side of the bracket bottom plate 21 , and a stabilizing frame 22 is provided at one end of the side connecting rod 27 . The stabilizing frame 22 is clamped at the bottom of the anchor column 8 .
[0035] like Figure 8 As shown, the temporary cantilever support includes: a bottom frame 29, a middle frame 30 and a top frame 31 which are clamped on the concrete column 4, a vertical fixing rod 39 is inserted between the bottom frame 29, the middle frame 30 and the top frame 31, a support frame 34 is clamped on the concrete column 4 between the top frame 31 and the middle frame 30, the support frame 34 extends horizontally, and a diagonal support 32 is connected between the support frame 34 and the bottom frame 29; the support frame 34 includes longitudinal ribs 33, outer transverse ribs 35, inner transverse ribs 36 and diagonal ribs 37, and a plurality of support rods 38 are arranged on the top surface of the support frame 34, and the support rods 38 are supported under the cantilever steel frame 3.
Claims
1. An articulated special-shaped steel frame railway station steel roof truss, characterized in that: It includes a steel frame, a cantilever steel frame, a concrete column and an anchor column. One end of the steel frame is provided with several steel frame columns, the bottom end of the steel frame column is hinged with the top end of the anchor column, and the other end of the steel frame is constructed with a cantilever steel frame. The concrete column is supported under the steel frame and the cantilever steel frame. A support trolley is fixed next to the anchor column to temporarily support the steel frame column; a temporary cantilever support is installed on the concrete column under the cantilever steel frame to temporarily support the cantilever steel frame.
2. The articulated special-shaped steel frame railway station steel roof truss according to claim 1 is characterized in that: An embedded end is embedded on the anchor column, and the embedded end includes an embedded plate on the top of the anchor column. The lower part of the embedded plate is connected to a steel pipe, a longitudinal steel plate and a transverse steel plate. The longitudinal steel plate and the transverse steel plate are arranged vertically, and the longitudinal steel plate and the transverse steel plate are inserted between the steel pipes.
3. The articulated special-shaped steel frame railway station steel roof truss according to claim 2 is characterized in that: The steel frame column and the anchor column are connected by the hinged end. The bottom of the steel frame column is connected to a connecting plate. The bottom of the connecting plate is connected to the hinged end 1. The hinged end 1 and the hinged end 2 are both provided with matching through holes. The hinged end 1 and the hinged end 2 are staggered and inserted, and a pin shaft is inserted between the through holes.
4. The articulated special-shaped steel frame railway station steel roof truss according to claim 1 is characterized in that: The support trolley includes: a support base plate for installing support rods, a walking wheel is provided at the bottom of the support base plate, the support rods include main support rods, secondary support rods and cross-linking rods, the bottom end of the main support rods is fixed on the support base plate, a fixing frame is installed on the top end of the main support rods, the fixing frame is clamped on the steel frame column, the two ends of the cross-linking rod are respectively connected to the main support rod and the anchor column, and the two ends of the secondary support rod are respectively connected to the main support rod and the support base plate.
5. The articulated special-shaped steel frame railway station steel roof truss according to claim 4 is characterized in that: A side connecting rod is installed on the side of the bracket bottom plate, and a stabilizing frame is arranged at one end of the side connecting rod, and the stabilizing frame is clamped at the bottom of the anchor column.
6. The articulated special-shaped steel frame railway station steel roof truss according to claim 1 is characterized in that: The temporary cantilever support includes: a bottom frame, a middle frame and a top frame which are clamped on the concrete column, vertical fixing rods are provided between the bottom frame, the middle frame and the top frame, a support frame is clamped on the concrete column between the top frame and the middle frame, the support frame extends horizontally, and a diagonal support is connected between the support frame and the bottom frame; the support frame includes longitudinal ribs, outer transverse ribs, inner transverse ribs and diagonal ribs, a number of support rods are provided on the top surface of the support frame, and the support rods are supported under the cantilever steel frame.
7. The articulated special-shaped steel frame railway station steel roof truss according to claim 1 is characterized in that: The steel frame also includes a secondary beam, and the secondary beam and the concrete column are arranged at corresponding positions. One end of the cantilever steel frame is fixed on the secondary beam, and the cantilever steel frame is also provided with a secondary beam corresponding to the concrete column.