Device for remotely marking drilling position in roadway
By using handheld rods and marking bearing plate devices in the tunnel, and using marking cylinders and adsorbent materials to apply pigment on the top of the tunnel, the complex and dangerous problems of drilling position measurement are solved, and long-distance and accurate drilling position marking is achieved. Improve construction efficiency and safety.
Patent Information
- Application Number
- CN202420163030.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-23
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2034-01-23
AI Technical Summary
In mining or tunnel construction, measuring and marking of drilling hole locations requires workers to get up and down the escalator, which is complex, time-consuming and labor-intensive, and is dangerous.
A device including a handheld rod, a marking bearing plate, a marking cylinder, an adsorption material and a shielding sheet is designed. Through the fixed connection between the handheld rod and the marking bearing plate, the marking cylinder and end point marking frame are used to apply pigment on the top of the tunnel to form a ring. The shape of the ring and marking point can be used to determine the drilling position at a distance on the tunnel ground.
It reduces drilling construction time, reduces work difficulty and danger, improves operation accuracy and efficiency, and avoids drilling position offset.
Smart Images

Figure CN222258270U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of tunnel drilling construction, and in particular relates to a device for remotely marking drilling positions in a tunnel. Background Art
[0002] Auxiliary drilling for mining or tunneling projects, drilling for ventilation, drainage, water exploration, gas exploration, freezing, transportation, as well as pipeline installation for construction and communication, blasting, sampling, grouting, etc. during mining or tunneling construction.
[0003] The five major disasters in coal mines are coal dust, gas explosion, fire, water seepage and roof collapse. In order to deal with these disasters, various drilling methods are needed, such as drilling for water release, drilling special tunnels for water release, drilling for pressure reduction, and interception-type gas discharge drilling. However, when drilling is required for underground disaster management, the positions of the holes are measured and marked manually by going up and down escalators. The operation is complicated, time-consuming, labor-intensive, and dangerous. Utility Model Content
[0004] The utility model aims to provide a device for remotely marking drilling positions in a tunnel, so as to solve the problem that the drilling positions need to be operated on a ladder, which is complicated, time-consuming and labor-intensive.
[0005] The utility model adopts the following technical solution: a device for remotely marking drilling positions in a tunnel, comprising:
[0006] A hand-held pole, arranged vertically, with its lower end being held by a worker while standing on the ground of the tunnel;
[0007] The marking bearing plate is arranged horizontally, the lower side of which is fixedly connected to the upper end of the hand-held rod, and a marking groove is vertically penetrated along the direction of the marking bearing plate;
[0008] The two marking tubes are cylindrical structures with an open top, located on the upper side of the marking bearing plate, and the bottoms of the two marking tubes are fixedly connected with a vertically arranged first fixing rod, the first fixing rod passes through the marking groove and extends downward, and is threadedly connected with the fixing bolt, thereby fixing the marking tube on the marking bearing plate; the spacing between the two marking tubes is the predetermined spacing between the two drill holes;
[0009] The first adsorption material is filled in the marking tube and is used to absorb the pigment. When the marking tube is pressed against the top of the tunnel, the adsorbed pigment is painted on the top of the tunnel, thereby obtaining the position of the drill hole from a distance.
[0010] Furthermore, the marking tube also includes:
[0011] The center column is vertically arranged and located in the marking tube, with its lower end fixedly connected to the center of the bottom of the marking tube and its upper end extending upward;
[0012] The shielding sheet is horizontally arranged and located on the upper side of the central column, and its lower side is fixedly connected to the upper end of the central column. The cavity in the marking tube and below the shielding sheet is filled with the first adsorption material. The shielding sheet is used to leave a blank space at the top of the tunnel when the first adsorption material is applied to the top of the tunnel, so that a ring-shaped circle with a blank center is obtained when the paint is applied to the top of the tunnel, so that the drill rod can be aligned with the blank space of the ring-shaped circle to start drilling when drilling.
[0013] Furthermore, it also includes:
[0014] The two endpoint marking frames are both frame structures with an open top, located on the upper side of the marking carrier plate, and the bottom of which is fixedly connected with a second vertically arranged fixing rod, the second fixing rod extends downward through the marking slot, and is threadedly connected with the fixing bolt, thereby fixing the endpoint marking frame on the marking carrier plate;
[0015] The second adsorption material is filled in each endpoint marking frame and is used to paint the adsorbed pigment on the top of the alley when the endpoint marking frame is against the top of the alley, so that the marking carrier plate can be rotated 180 degrees after this marking. When marking the drill hole again, the spacing between adjacent drill holes between the two marks is calculated based on the painted point.
[0016] Furthermore, scales are arranged on the mark bearing plate along its direction, and the distance between any end mark frame and its adjacent mark cylinder is equal to half of the distance between the two mark cylinders.
[0017] The beneficial effects of the utility model are:
[0018] The utility model reduces the drilling construction time, avoids workers going up and down ladders to determine the drilling position, reduces the difficulty and intensity of work, and also reduces the danger;
[0019] The utility model can be operated remotely and determine the drilling position of the top of the tunnel, that is, the worker can stand on the ground of the tunnel to determine the drilling position of the top very accurately;
[0020] The utility model can easily determine the distance between the two top drilling holes by indicating the scale on the marking carrier plate and then moving the distance between the two marking cylinders, and can accurately draw the positions of the drilling holes without close measurement;
[0021] The utility model provides two end point marking frames, and after the first marking is completed, the marking carrier plate can be rotated 180 degrees, and the marking point marked by the end point marking frame can be aligned for the second marking, so that the distance between the adjacent drilling positions in the two markings can be ensured to be equal to the distance between the two marking cylinders that have been set, and the drilling positions can be marked for multiple times continuously, thereby improving the work efficiency;
[0022] The utility model can form an annular circle with a blank center by setting a shielding piece, so that the contact position of the drill rod during drilling can be clearer and more accurate, and avoid the contact position of the drill rod being offset from the actual position due to the circle area being too large, thereby causing inaccurate drilling position. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a structural schematic diagram of the utility model;
[0024] Figure 2 It is a top view of the utility model.
[0025] Among them: 10, hand-held rod; 11, marking bearing plate; 12, marking tube; 13, center column; 14, shielding sheet; 15, first fixed rod; 16, end point marking frame; 17, second fixed rod. DETAILED DESCRIPTION
[0026] The utility model is described in detail below with reference to the accompanying drawings and specific implementation modes.
[0027] In the description of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "multiple" means two or more. The "direction" in the present utility model is based on the position of the present utility model in the Figure 1 Description of the trend in the state.
[0028] The utility model discloses a device for remotely marking drilling positions in a tunnel, such as Figure 1 and 2 As shown, it comprises a hand-held rod 10, a marking carrier plate 11, two marking tubes 12 and a first adsorbent material.
[0029] The hand-held rod 10 is arranged vertically, and the lower end of the hand-held rod 10 is used for workers to hold and stand on the ground of the tunnel; the marking bearing plate 11 is arranged horizontally, and the lower side of the marking bearing plate 11 is fixedly connected to the upper end of the hand-held rod 10, and a marking groove is opened vertically along the direction of the marking bearing plate 11.
[0030] The two marking tubes 12 are cylindrical structures with open tops. The two marking tubes 12 are located on the upper side of the marking carrier plate 11, and a vertically arranged first fixing rod 15 is fixedly connected to the bottom thereof. The first fixing rod 15 extends downward through the marking groove and is threadedly connected to the fixing bolt, thereby fixing the marking tube 12 on the marking carrier plate 11; the spacing between the two marking tubes 12 is the predetermined spacing between the two drill holes.
[0031] The first adsorbent material is filled in the marking tube 12. The first adsorbent material is used to absorb the pigment. When the marking tube 12 is pressed against the top of the tunnel, the absorbed pigment is painted on the top of the tunnel, thereby obtaining the location of the drill hole from a distance.
[0032] The marking tube 12 further includes a central column 13 and a shielding sheet 14 .
[0033] The center column 13 is vertically arranged, and the center column 13 is located in the marking tube 12. The lower end of the center column 13 is fixedly connected to the center of the bottom of the marking tube 12, and the upper end of the center column 13 extends upward; the shielding piece 14 is horizontally arranged, and the shielding piece 14 is located on the upper side of the center column 13, and the lower side of the shielding piece 14 is fixedly connected to the upper end of the center column 13. The cavity in the marking tube 12 and below the shielding piece 14 is filled with the first adsorption material. The shielding piece 14 is used to leave a blank space at the top of the lane when the first adsorption material is applied to the top of the lane, so that a ring-shaped circle with a blank center is obtained when the paint is applied to the top of the lane, so that the drill rod can align with the blank space of the ring-shaped circle when drilling and start drilling.
[0034] The utility model further comprises: two end point marking frames 16 and a second adsorption material.
[0035] The two endpoint marking frames 16 are both frame structures with an open top. The two endpoint marking frames 16 are located on the upper side of the marking carrier plate 11, and a vertically arranged second fixing rod 17 is fixedly connected to the bottom thereof. The second fixing rod 17 extends downward through the marking groove and is threadedly connected to the fixing bolt, thereby fixing the endpoint marking frame 16 on the marking carrier plate 11.
[0036] The second adsorption material is filled in each endpoint marking frame 16. The second adsorption material is used to paint the adsorbed pigment on the top of the alley when the endpoint marking frame 16 is against the top of the alley, so that the marking carrier plate 11 can be rotated 180 degrees after this marking. When marking the drill hole again, the spacing between adjacent drill holes between the two marks is calculated based on the painted point.
[0037] Graduations are arranged on the marking carrier plate 11 along its direction, and the distance between any end marking frame 16 and its adjacent marking cylinder 12 is equal to half of the distance between the two marking cylinders 12 .
[0038] The utility model can easily determine the distance between the two top bore holes by indicating the scale on the marking carrier plate 11 and then moving the distance between the two marking cylinders 12, and can accurately draw the positions of the bore holes without close-range measurement.
[0039] The utility model sets two end point marking frames 16, and after the first marking is completed, the marking carrier plate 11 can be rotated 180 degrees, and the marking point marked by the end point marking frame 16 can be aligned for the second marking, so that the distance between the adjacent drilling positions in the two markings can be ensured to be equal to the distance between the two marking tubes 12 that have been set, so that the drilling positions can be marked multiple times in succession, thereby improving work efficiency.
[0040] The utility model can form an annular circle with a blank center by setting a shielding piece 14, so that the contact position of the drill rod during drilling can be clearer and more accurate, and avoid the contact position of the drill rod being offset from the actual position due to the circle area being too large, thereby causing inaccurate drilling position.
[0041] Example 1
[0042] When marking drill holes during underground disaster management at a certain mine, there is a large workload. The drill hole positions need to be measured and marked by workers going up and down ladders or drilling rigs. The operation is complicated, time-consuming, labor-intensive, and dangerous.
[0043] By using the utility model for 2 months, the drilling construction time was reduced, the danger of personnel going up and down the escalator was solved, and the work efficiency of marking the drilling was accelerated.
[0044] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A device for remotely marking drilling positions in a tunnel, characterized in that: include: A hand-held rod (10) is arranged vertically, and its lower end is used for workers to hold it while standing on the ground of the tunnel; A marking bearing plate (11) is arranged horizontally, the lower side of which is fixedly connected to the upper end of the hand-held rod (10), and a marking groove is vertically penetrated along the direction of the marking bearing plate; The two marking tubes (12) are cylindrical structures with an open top, and are located on the upper side of the marking carrier plate (11), and the bottoms of the two marking tubes are fixedly connected to a vertically arranged first fixing rod (15), the first fixing rod (15) extending downward through the marking groove and being threadedly connected to a fixing bolt, thereby fixing the marking tube (12) on the marking carrier plate (11); the spacing between the two marking tubes (12) is the predetermined spacing between the two drill holes; The first adsorption material is filled in the marking tube (12) and is used to absorb the pigment. When the marking tube (12) is pressed against the top of the tunnel, the adsorbed pigment is painted on the top of the tunnel, thereby obtaining the location of the drill hole from a distance.
2. A device for remotely marking drilling positions in a tunnel according to claim 1, characterized in that: The marking cylinder (12) further comprises: A central column (13) is vertically arranged and located in the marking tube (12), with its lower end fixedly connected to the center of the bottom of the marking tube (12) and its upper end extending upward; The shielding sheet (14) is horizontally arranged and located on the upper side of the central column (13), and its lower side is fixedly connected to the upper end of the central column (13). The cavity in the marking tube (12) and below the shielding sheet (14) is filled with the first adsorption material. The shielding sheet (14) is used to leave a blank space at the top of the laneway when the first adsorption material is applied to the top of the laneway, so that a ring-shaped ring with a blank center is obtained when the paint is applied to the top of the laneway, so that the drill rod can align with the blank space of the ring-shaped ring when drilling a hole and start drilling.
3. A device for remotely marking drilling positions in a tunnel according to claim 1, characterized in that: Also includes: The two end point marking frames (16) are both frame structures with an open top, located on the upper side of the marking carrier plate (11), and the bottom of the frame structures is fixedly connected to a second vertically arranged fixing rod (17), the second fixing rod (17) extending downward through the marking slot and being threadedly connected to a fixing bolt, thereby fixing the end point marking frame (16) on the marking carrier plate (11); The second adsorption material is filled in each of the endpoint marking frames (16) and is used to paint the adsorbed pigment on the top of the lane when the endpoint marking frame (16) is pressed against the top of the lane.
4. A device for remotely marking drilling positions in a tunnel according to claim 3, characterized in that: The marking carrier plate (11) is provided with scales along its direction, and the distance between any of the end point marking frames (16) and its adjacent marking cylinder (12) is equal to half the distance between the two marking cylinders (12).