Passageway barrier
By replacing the steel pipe tie rods with floor-mounted ones in the temporary guardrails and fixing them with connecting components, the problem of passage obstructed by steel pipes protruding from the ground was solved, improving the safety and efficiency of passage at the construction site.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- THE THIRD CONSTR ENG CO LTD OF CHINA CONSTR SECOND ENG BUREAU
- Filing Date
- 2025-06-10
- Publication Date
- 2026-06-09
AI Technical Summary
In the temporary protective passage at the construction site, steel pipe tie-ins protruded from the ground, causing pedestrians to slip and fall and obstructing the passage of small machinery. Formwork had to be laid to allow passage.
Using floor mats instead of steel pipes as tie rods, and using connecting components to fix the uprights to the floor mats, avoids steel pipes protruding from the ground and simplifies the construction of guardrails.
The height of the guardrail protruding from the ground has been reduced, improving traffic safety and efficiency, preventing falls and obstruction, and simplifying the construction process.
Smart Images

Figure CN224338733U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building construction technology, and in particular to a temporary barrier railing for barrier-free passageways. Background Technology
[0002] In the temporary protective structures used at construction sites, steel pipes are used to tie the bottom of the guardrails on both sides to the ground to increase their stability. The spacing between the steel pipes is generally about 4 to 6 meters. The steel pipes protrude about 8 centimeters above the ground, posing a slip and fall hazard to pedestrians, especially obstructing the movement of carts or small machinery, requiring the installation of additional formwork before passage is possible. Finding a solution that allows passage through temporary protective passages without the need for formwork remains an ongoing problem. Utility Model Content
[0003] To address the issue of ensuring smooth passage through temporary protective walkways without the need for formwork, this invention provides a barrier-free temporary protective railing. In constructing the temporary protective railing, a floor-mounted base plate replaces the steel pipes as tie rods. Connecting components are used to connect the uprights of the temporary railing to the base plate, which acts as the tie rods. This solves the problem of obstructing the ground surface and hindering passage caused by the steel pipe tie rods used to stabilize the temporary railing.
[0004] A temporary barrier for barrier-free passageways includes two barriers on both sides of the passageway. Each barrier includes uprights and horizontal bars. Multiple uprights are evenly spaced along the passageway direction, and multiple horizontal bars are evenly spaced along the vertical direction of the uprights. The uprights and horizontal bars are connected by fasteners. The barrier also includes a floor panel and connecting components. Two uprights symmetrically positioned on both sides of the passageway are respectively connected to two connecting components at the ends away from the passageway. The floor panel covers the passageway, and both ends of the floor panel are bolted to the ground near the ends of the two connecting components.
[0005] Furthermore, the connecting component includes a base plate and a core rod. The end of the base plate away from the channel is fixedly connected to the core rod, and the upright is sleeved outside the core rod. The end of the base plate near the channel and the end that is attached to the floor are pressed and fixed to the ground by bolts.
[0006] Furthermore, the upright is a φ48*2.8 steel pipe, and the core rod is a φ40*2.8 steel pipe.
[0007] Furthermore, the bottom plate is welded and fixedly connected to the core rod at the end away from the channel.
[0008] Furthermore, the bottom plate is provided with a threaded hole near the channel end, and a nut is welded on the threaded hole. The bolt passes through the threaded hole and the nut to press the bottom plate near the channel end and the end that is attached to the floor onto the ground.
[0009] Furthermore, both the base plate and the floor plate are grounding flat irons, the nuts are M10 nuts, and the bolts are 30~40mm long M10 bolts.
[0010] The beneficial effects of this utility model are as follows:
[0011] (1) In this utility model, the steel pipe tie rods of the stable guardrail are replaced with floor-mounted ones, which significantly reduces the height of the tie rods protruding from the road, thereby avoiding road obstruction. This solves the problem that road obstructions make it easy for pedestrians to slip and fall, and small vehicles must lay templates to pass. It improves the safety and efficiency of passage and reduces safety hazards.
[0012] (2) This utility model replaces the connecting fasteners of the guardrail uprights and tie rods with connecting components, which further reduces the height of the guardrail against the floor and simplifies the guardrail construction operation, improves the efficiency of the passage guardrail construction, and helps to solve the problem of passage obstruction caused by passage obstacles. Attached Figure Description
[0013] Figure 1 This is a cross-sectional view of a temporary barrier structure for barrier-free passageways according to this utility model;
[0014] Figure 2 This is a top view of the structure of a temporary barrier railing for barrier-free passageways according to this utility model;
[0015] Figure 3 yes Figure 2 Cross-sectional view along the AA direction;
[0016] Figure 4 yes Figure 2 Cross-sectional view along the BB direction.
[0017] Explanation of symbols in the attached diagram:
[0018] 1. Upright pole, 2. Horizontal bar, 3. Flooring, 4. Connecting components, 41. Base plate, 42. Core pole, 5. Channel, 6. Bolts
[0019] 7. Nuts. Detailed Implementation
[0020] To enable those skilled in the art to better understand the technical solution of this utility model, the present utility model will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0021] The accompanying drawings are for illustrative purposes only and are schematic diagrams, not actual images. They should not be construed as limiting the scope of this patent. To better illustrate the embodiments of this utility model, some components in the drawings may be omitted, enlarged, or reduced, and do not represent the actual dimensions of the product. It is understandable to those skilled in the art that some well-known structures and their descriptions may be omitted in the drawings.
[0022] In the accompanying drawings of this utility model, the same or similar reference numerals correspond to the same or similar components. In the description of this utility model, it should be understood that if terms such as "upper," "lower," "left," "right," "inner," and "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, they are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, the terms used to describe positional relationships in the drawings are only for illustrative purposes and should not be construed as limiting this patent. For those skilled in the art, the specific meaning of the above terms can be understood according to the specific circumstances.
[0023] In the description of this patent, unless otherwise explicitly specified and limited, the term "connection" or similar designation indicating a connection between components should be interpreted broadly. For example, it can refer to a fixed connection, a detachable connection, or an integral part; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can refer to the internal communication between two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.
[0024] A temporary barrier for accessible passageways, such as Figures 1 to 4 As shown, two guardrails are installed on both sides of the passage 5. The guardrails include uprights 1 and crossbars 2. Multiple uprights 1 are evenly spaced along the passage direction, and multiple crossbars 2 are evenly spaced along the vertical direction of the multiple uprights. The uprights 1 and crossbars 2 are connected by fasteners. The guardrail is characterized by further including a floor panel 3 and connecting components 4. Two uprights 1 at symmetrical positions on both sides of the passage 5 are respectively sleeved and connected to two connecting components 4 at the ends away from the passage. The floor panel 3 covers the passage 5, and the two ends of the floor panel 3 are respectively pressed and fixed to the ground by bolts 6 at the ends of the two connecting components 4 near the passage.
[0025] This invention replaces steel pipes with floor-mounted panels as tie rods, and replaces fasteners with connecting components to connect the guardrail posts to the floor-mounted panels. The connecting components firmly press the floor-mounted panels onto the passageway floor, preventing obstruction of passage and allowing normal passage without the need for formwork. It solves the problem of blocked passageways caused by steel pipe tie rods used to stabilize temporary guardrails. This improves safety and efficiency of passage, and reduces safety hazards.
[0026] Furthermore, such as Figures 1 to 4 As shown, the connecting assembly 4 includes a base plate 41 and a core rod 42. The end of the base plate 41 away from the channel is fixedly connected to the core rod 42. The upright 1 is sleeved on the outside of the core rod 42. The end of the base plate 41 near the channel is pressed and fixed to the ground by bolts 6. Further, the upright 1 is a φ48*2.8 steel pipe, and the core rod 42 is a φ40*2.8 steel pipe.
[0027] Furthermore, such as Figures 1 to 4 As shown, the base plate 41 is welded and fixedly connected to the steel pipe at the end away from the channel. Furthermore, a threaded hole is provided at the end of the base plate 41 near the channel, and a nut 7 is welded to the threaded hole. A bolt 6 passes through the threaded hole and the nut to press the end of the base plate 41 near the channel and the end of the floor 3 against the ground.
[0028] Furthermore, such as Figures 1 to 4 As shown, the base plate 41 and the floor plate 3 are both grounding flat irons, the nut is an M10 nut, and the bolt is a 30~40mm long M10 bolt.
[0029] It should be stated that the above-described specific embodiments are merely preferred embodiments of this utility model and the technical principles employed. Those skilled in the art should understand that various modifications, equivalent substitutions, and variations can be made to this utility model. However, such variations, as long as they do not depart from the spirit of this utility model, should be within the protection scope of this utility model. Furthermore, some terminology used in this application specification and claims is not limiting, but merely for ease of description.
Claims
1. A temporary barrier railing for unobstructed passageways, comprising two railings on both sides of a passageway (5), each railing including uprights (1) and crossbars (2), wherein multiple uprights (1) are evenly spaced along the passageway direction, and multiple crossbars (2) are evenly spaced along the vertical direction of the uprights, and the uprights (1) and crossbars (2) are connected by fasteners, characterized in that, The guardrail also includes a flooring (3) and connecting components (4). Two uprights (1) on both sides of the passage (5) are symmetrically connected to the two connecting components (4) at the ends away from the passage. The flooring (3) covers the passage (5). The two ends of the flooring (3) are respectively pressed and fixed to the ground by bolts (6) to the two connecting components (4) near the ends of the passage.
2. The temporary barrier railing for unobstructed passageways according to claim 1, characterized in that, The connecting assembly (4) includes a base plate (41) and a core rod (42). The base plate (41) is fixedly connected to the core rod (42) at the end away from the channel. The upright (1) is sleeved on the outside of the core rod (42). The end of the base plate (41) near the channel is pressed and fixed to the ground by bolts (6) at one end of the floor (3).
3. The temporary barrier railing for unobstructed passageways according to claim 2, characterized in that, The base plate (41) is welded and fixedly connected to the core rod at the end away from the channel.
4. The temporary barrier railing for unobstructed passageways according to claim 3, characterized in that, The upright (1) is a φ48*2.8 steel pipe, and the core rod (42) is a φ40*2.8 steel pipe.
5. The temporary barrier railing for unobstructed passageways according to claim 2, characterized in that, The bottom plate (41) has a threaded hole near the channel end, and a nut (7) is welded on the threaded hole. A bolt (6) passes through the threaded hole and the nut to press the bottom plate (41) near the channel end and the end of the floor (3) against the ground.
6. The temporary barrier-free guardrail for passageways according to claim 5, characterized in that, The base plate (41) and the floor plate (3) are both grounding flat irons, the nut is an M10 nut, and the bolt is a 30~40mm long M10 bolt.