A rail-mounted concrete distributor
By designing a track-mounted concrete placing boom, which employs a placing box girder, a traveling mechanism, and multi-compartment collaborative operation, the problem of low automation in existing equipment has been solved, achieving efficient and precise placing of precast concrete products and improving production quality.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- TANGSHAN XINGDOU ROAD&BRIDGE MACHINERY CO LTD
- Filing Date
- 2025-04-27
- Publication Date
- 2026-07-03
AI Technical Summary
Existing precast concrete production equipment has low functional integration and insufficient automation, making it difficult to meet diverse and high-precision production needs, and also suffers from high material loss and energy consumption.
A track-mounted concrete placing boom was designed, comprising a placing box girder, transverse and longitudinal traveling mechanisms, a main placing bin, a metering bin, and a precision placing bin. The bin doors and mixing mechanism are controlled by hydraulic telescopic rods to achieve automated control and precise placing. Production efficiency is improved by alternating the operation of multiple precision placing bins.
It achieves accurate metering and uniform distribution of precast concrete products, improves production efficiency, reduces material loss and energy consumption, and enhances production quality and automation.
Smart Images

Figure CN224446338U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to a track-type concrete placing machine, belonging to the field of precast concrete processing technology. Background Technology
[0002] Precast concrete products are precast concrete components manufactured and processed in a prefabrication yard. They are then transported directly to the construction site for installation. During the manufacturing process, a hollow mold is first made from slabs. Reinforcing steel bars are then placed in the hollow portion of the mold, and finally, concrete is poured into the hollow area. After drying, the slabs are removed, leaving the precast concrete product.
[0003] Existing production equipment has significant shortcomings in functional integration. Most production lines still use separate equipment to independently complete the material receiving, unloading, and placement processes. Each step requires manual transfer or the addition of intermediate buffer devices, which not only increases material loss and energy consumption but also easily causes time delays, leading to concrete slump loss and affecting construction quality. In addition, the equipment has a low degree of automation and cannot adjust process parameters in real time according to parameters such as the specifications of precast concrete products and concrete mix proportions, making it difficult to meet diverse and high-precision production needs. Utility Model Content
[0004] The purpose of this invention is to provide a track-mounted concrete placing boom to solve the aforementioned technical problems.
[0005] To achieve the above objectives, the technical solution adopted by this utility model is as follows:
[0006] A track-mounted concrete placing boom includes a placing box girder, a transverse traveling mechanism mounted on the placing box girder, and a placing mechanism mounted on the transverse traveling mechanism. The placing mechanism includes a main placing bin, a metering bin, and a precision placing bin, arranged sequentially from top to bottom. The discharge port at the bottom of the main placing bin corresponds to the metering bin, and the discharge port at the bottom of the metering bin corresponds to the precision placing bin. The opening and closing of the discharge ports of the main placing bin, the metering bin, and the precision placing bin are controlled by bin doors controlled by telescopic rods.
[0007] A further improvement to the technical solution of this utility model is that the telescopic rod is a hydraulic telescopic rod; the fabric placing machine also includes a hydraulic control system and an electrical control system.
[0008] A further improvement to the technical solution of this utility model is that a stirring mechanism is provided inside the main fabric bin; the stirring mechanism includes a stirring shaft driven by a motor and several stirring blades arranged on the stirring shaft.
[0009] A further improvement to the technical solution of this utility model is that the metering chamber is a detachable installation structure, and metering chambers of different sizes can be disassembled and replaced.
[0010] A further improvement to the technical solution of this utility model is that: longitudinal walking mechanisms are provided at both ends of the cloth box girder; it also includes a longitudinal walking track; the longitudinal walking mechanism drives the whole machine to move on the longitudinal walking track.
[0011] A further improvement to the technical solution of this utility model is that a concrete mixing plant is set at one end of the longitudinal walking track.
[0012] A further improvement to the technical solution of this utility model is that the track-mounted concrete placing boom is controlled by remote control or automatically controlled by a control system.
[0013] A further improvement to this utility model is that the precision material distribution bin and the metering bin are set separately, with multiple precision material distribution bins. A material distribution track is set below the material distribution box beam to allow the precision material distribution bins to move. The precision material distribution bins are mounted on the material distribution track via a material distribution trolley.
[0014] A further improvement to the technical solution of this utility model is that: the lower end of the precision material distribution bin is provided with several material discharge ports set at intervals; the opening and closing size of each material discharge port is controlled by a bin door controlled by a telescopic rod.
[0015] A method for operating a track-mounted concrete placing boom, using the aforementioned track-mounted concrete placing boom, characterized in that: a plurality of arranged formwork platforms for serving as templates for precast concrete products are provided on the inner side of the longitudinal travel track.
[0016] The construction steps are as follows:
[0017] 1) The placing boom moves to the bottom of the concrete mixing plant, and the main placing hopper moves to the corresponding position below the discharge port of the concrete mixing plant;
[0018] 2) The concrete batching plant's mixer discharges material, and the mixing in the main material distribution hopper is started;
[0019] 3) After the mixer finishes discharging the material, the material distribution machine moves to the mold table position and is positioned.
[0020] 4) After positioning is completed, select the appropriate placement parameters according to the different sizes of precast concrete products, and start the placement process;
[0021] 5) The main fabric bin discharge port opens to release material into the metering bin;
[0022] 6) After the metering hopper is full, the discharge port of the main concrete placing hopper is closed; the discharge port of the metering hopper is opened to discharge material into the precision placing hopper until all the concrete material is placed into the precision placing hopper.
[0023] 7) The precision material feeding bin door opens, the whole machine moves, and material feeding begins;
[0024] 8) At the same time as the material is laid, the feeding hopper door of the metering hopper closes and the feeding hopper door of the main material laying hopper opens, and the second feeding of material into the metering hopper begins.
[0025] A further improvement to the above technical solution is as follows: After the first precast concrete product is placed, the placing machine moves to the corresponding position according to the position of the second precast concrete product to be processed selected by the placing machine; at the same time, after the main placing bin is unloaded, the unloading bin door of the main placing bin is closed; the unloading bin door of the metering bin is opened to release material into the precision placing bin; this cycle is repeated until the placement of the entire precast concrete product on the mold platform is completed.
[0026] A further improvement to the above technical solution is as follows: after all the concrete material in the main placing hopper has been discharged, it is sent to the concrete mixing plant for receiving.
[0027] Due to the adoption of the above technical solution, the technical effects achieved by this utility model are as follows:
[0028] This utility model discloses a track-mounted concrete placing machine, which includes a main placing bin, a metering bin, and a precision placing bin. The main placing bin has a large capacity and is used to hold the concrete material. The metering bin measures the amount of concrete, ensuring accurate placement. The precision placing bin is used to directly feed concrete into the mold, achieving uniform and precise placement. Through the coordinated operation of the three bins, accurate metering and uniform placement are achieved, improving the production efficiency of precast concrete products.
[0029] In this utility model of a track-mounted concrete placing boom, the metering bin is detachable and replaceable. It can calculate the required volume of concrete based on different sizes of precast concrete products and adjust the size of the metering bin accordingly. The metering bin is a detachable installation structure, which improves the application range of this track-mounted concrete placing boom.
[0030] The track-type concrete placing machine of this utility model has several discharge ports set at intervals at the lower end of the precision placing bin. The opening and closing size of each discharge port is controlled by a bin door controlled by a telescopic rod. The setting of multiple discharge ports can improve the placing effect and improve the production quality of precast concrete products.
[0031] This utility model of a track-type concrete placing machine can significantly improve the production efficiency of precast concrete products, save labor costs, and achieve good overall results through mechanized operation and automated control. Attached Figure Description
[0032] Figure 1 This is a three-dimensional schematic diagram of the track-type concrete placing boom of this utility model;
[0033] Figure 2 This is a schematic diagram of the placing mechanism of the track-type concrete placing machine of this utility model;
[0034] Figure 3 This is a side view of the placing mechanism of the track-type concrete placing machine of this utility model;
[0035] Figure 4 This is a schematic diagram of the precision fabric bin of the fabric feeding mechanism of this utility model;
[0036] Figure 5 This is a schematic diagram of the installation of the track-mounted concrete placing boom of this utility model;
[0037] Figure 6 This is a schematic diagram of the operation of the track-mounted concrete placing boom of this utility model;
[0038] Figure 7 This is a schematic diagram of the operation of the track-mounted concrete placing boom. Figure 2 ;
[0039] Among them, 1. Concrete placing box girder, 2. Main concrete placing bin, 3. Metering bin, 4. Precision concrete placing bin, 5. Telescopic rod, 6. Mixing blade, 7. Longitudinal traveling mechanism, 8. Longitudinal traveling track, 9. Concrete mixing plant, 10. Telescopic rod, 11. Mold table, 12. Lateral traveling mechanism, 13. Concrete placing track, 14. Concrete placing trolley. Detailed Implementation
[0040] To make the technical means, creative features, objectives and effects of this utility model easier to understand, the present utility model will be further described below in conjunction with specific embodiments.
[0041] In the description of this utility model, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model.
[0042] This utility model relates to a track-mounted concrete placing boom, an automated machine for producing precast concrete products, enabling automated placement and construction of precast concrete products, such as precast concrete slabs. This placing boom can also be applied to the placement of other precast products.
[0043] like Figure 1As shown, the track-mounted concrete placing boom mainly includes a placing box girder 1 and a placing mechanism. The placing box girder 1 is a long box girder structure, and a transverse traveling mechanism 12 is set on the placing box girder 1, on which the placing mechanism is mounted. The transverse traveling mechanism 12 drives the placing mechanism to travel laterally on the placing box girder 1. The main body of the transverse traveling mechanism 12 is a traveling trolley with wheels, which are driven by a motor.
[0044] like Figure 2 , Figure 3 As shown, the concrete placement mechanism includes a main placement bin 2, a metering bin 3, and a precision placement bin 4. The main placement bin 2 is used to hold concrete material and has a large capacity. The metering bin 3 is used to measure the amount of concrete. The required volume of concrete is determined according to the specifications of the precast concrete product. The size of the metering bin 3 is adjusted accordingly to change its volume, thus measuring the required amount of material. The precision placement bin 4 is used to directly place the concrete into the mold platform 11. The main placement bin 2, metering bin 3, and precision placement bin 4 are arranged sequentially from top to bottom. The concrete in the main placement bin 2 is poured into the metering bin 3, the concrete in the metering bin 3 is poured into the precision placement bin 4, and the concrete in the precision placement bin 4 is placed into the mold platform of the precast concrete product.
[0045] In specific implementation, the discharge port at the bottom of the main concrete placement bin 2 needs to be accurately aligned with the metering bin 3; the discharge port at the bottom of the metering bin 3 needs to be accurately aligned with the precision concrete placement bin 4; to ensure that the concrete material can accurately fall into the corresponding functional bin.
[0046] like Figure 2 As shown, the main material distribution bin 2, the metering bin 3, and the precision material distribution bin 4 are all equipped with discharge ports at their lower parts for material discharge, and each has a bin door controlled by a telescopic rod 10. The opening and closing size of the discharge port is controlled by controlling the position of the bin door through the telescopic rod 10. In specific implementations, the telescopic rod 10 is usually a hydraulic telescopic rod, which enables precise control.
[0047] To achieve better concrete placement, several discharge ports are installed at the lower end of the precision concrete placement bin 4, with these ports spaced at intervals. Each discharge port's opening and closing is controlled by a bin door controlled by a telescopic rod 10. The multiple discharge ports improve the concrete placement effect and enhance the production quality of precast concrete products. Specifically... Figure 4 As shown.
[0048] This technical solution can set up multiple precision fabric bins 4, which can improve fabric production efficiency, such as... Figure 1As shown, specifically, the precision placement bin 4 and the metering bin 3 are set separately, and multiple precision placement bins 4 can be set. Concrete material is added to different precision placement bins 4 by the metering bin 3. A placement track 13 is set below the placement box girder 1 to allow the precision placement bins 4 to move on it; a placement trolley 14 is also set to drive the movement of the precision placement bins 4, and the precision placement bins 4 are mounted on the placement track 13 via the placement trolley 14. Multiple combinations of precision placement bins 4 and placement trolleys 14 are set on the placement track 13. During operation, multiple precision placement bins 4 work alternately or simultaneously, thereby improving placement efficiency. In this embodiment, a placement trolley is set for the precision placement bin 4, and the precision placement bin 4 is mounted on the placement trolley 14. The placement trolley 14 drives the precision placement bins 4 to move on the placement track 13. When the metering bin 3 releases material into the precision placement bin 4, it is necessary to ensure that the metering bin 3 is aligned with the precision placement bin 4. The efficiency of precast concrete placement is improved by setting up multiple precision placement bins 4. Since the metering bin 3 has already pre-measured the required amount of concrete as needed, the metering bin can quickly tilt and unload into the precision placement bin 4.
[0049] The fabric placing machine also includes a hydraulic control system and an electrical control system.
[0050] The main placing hopper 2 of this track-mounted concrete placing boom is used to hold a large amount of concrete. To prevent the concrete from failing to solidify, a mixing mechanism is installed inside the main placing hopper 2. During operation, the mixing mechanism agitates the concrete to prevent solidification. Specifically, the mixing mechanism includes a motor-driven mixing shaft and several mixing blades 6 mounted on the shaft. The motor is equipped with a frequency converter to control its speed, ensuring an appropriate speed for mixing the concrete.
[0051] In this track-mounted concrete placing boom, the metering chamber 3 is the mechanism for measuring concrete material. Depending on the size of the precast concrete product, the required volume of concrete varies. The size of the metering chamber 3 is adjusted accordingly to change its volume, ensuring that the required volume of material is measured precisely. Therefore, the metering chamber 3 is a detachable installation structure, allowing for the removal and replacement of different sized metering chambers as needed.
[0052] like Figure 5 , Figure 7As shown, this track-mounted concrete placing boom typically places concrete onto multiple arranged formwork platforms 11 during the production of precast concrete products. Several formwork platforms 11 are arranged, and the track-mounted concrete placing boom adjusts its position via a track system to place concrete into the formwork platforms 11. This track-mounted concrete placing boom needs to be able to travel longitudinally; correspondingly, longitudinal travel mechanisms 7 are installed at both ends of the placing beam 1. These longitudinal travel mechanisms mainly consist of traveling seats equipped with traveling wheels, which are driven by a motor.
[0053] The longitudinal movement of the track-type concrete placing boom also requires the installation of a longitudinal travel track 8. During operation, the longitudinal travel mechanism 7 drives the entire machine to move on the longitudinal travel track 8.
[0054] A concrete mixing plant 9 is installed at one end of the longitudinal travel track 8, and the concrete mixing plant 9 supplies the concrete material. Specifically, as follows... Figure 6 , Figure 7 As shown.
[0055] This track-mounted concrete placing boom can be controlled remotely or automatically via a control system.
[0056] This technical solution also discloses the working method of the track-type concrete placing machine, which uses the aforementioned track-type concrete placing machine. First, two longitudinal traveling tracks 8 are set up at a certain distance. In the area between the two longitudinal traveling tracks 8, several arranged formworks 11 are placed. The formworks 11 here act as templates, and concrete needs to be injected into the formworks 11.
[0057] The construction steps are as follows:
[0058] 1. Move the placing boom to a position below the concrete mixing plant, and move the main placing hopper 2 to the corresponding position below the discharge port of the concrete mixing plant 9.
[0059] 2. The mixer of concrete batching plant 9 discharges the material, and the mixing in the main material distribution hopper 2 is started to prevent the concrete material from solidifying.
[0060] 3. After the mixer finishes discharging the material, move the material distribution machine to position 11 on the mold table for positioning.
[0061] 4. After positioning is completed, select the appropriate placement parameters according to the different sizes of precast concrete products, and start placing.
[0062] 5. First, open the discharge port of the main fabric bin 2 and discharge the material into the metering bin 3. The capacity of the metering bin 3 is fixed.
[0063] 6. After the metering chamber 3 is full, the discharge port of the main concrete placing chamber 2 is closed; the discharge port of the metering chamber 3 is opened to discharge material into the precision placing chamber 4 until all the concrete material is placed into the precision placing chamber 4.
[0064] 7. The feeding chamber door of the precision feeding chamber 4 opens, the whole machine moves, and begins to feed material into the mold table.
[0065] 8. At the same time as the fabric is being fed, the feeding chamber door of metering chamber 3 is closed, and the feeding chamber door of main fabric chamber 2 is opened, and the second feeding of fabric into metering chamber 3 begins.
[0066] After the first precast concrete product is placed, the placing machine moves to the corresponding position according to the position of the second precast concrete product to be processed selected by the placing machine; at the same time, after the main placing hopper 2 finishes discharging, the discharge hopper door of the main placing hopper 2 is closed; the discharge hopper door of the metering hopper 3 is opened to discharge material into the precision placing hopper 4; this cycle is repeated until the placement of the entire precast concrete product on the formwork is completed; after all the concrete material in the main placing hopper has been discharged, it is sent to the concrete mixing plant for receiving.
[0067] This utility model of a track-type concrete placing machine, by setting up a main placing bin, a metering bin, and a precision placing bin, can achieve accurate metering and uniform material placement through the cooperation of the three bins, thereby improving the production efficiency of precast concrete products.
[0068] The foregoing has shown and described the basic principles, main features, and advantages of this utility model. Those skilled in the art should understand that this utility model is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of this utility model. Various changes and modifications can be made to this utility model without departing from its spirit and scope, and all such changes and modifications fall within the scope of the claims. The scope of protection of this utility model is defined by the appended claims and their equivalents.
Claims
1. A rail-mounted concrete placing machine characterized by: It includes a fabric box beam (1), a transverse traveling mechanism (12) set on the fabric box beam (1), and a fabric placement mechanism set on the transverse traveling mechanism (12); the fabric placement mechanism includes a main fabric placement bin (2), a metering bin (3), and a precision fabric placement bin (4) set from top to bottom; the discharge port at the bottom of the main fabric placement bin (2) is set to correspond to the metering bin (3); the discharge port at the bottom of the metering bin (3) is set to correspond to the precision fabric placement bin (4); the discharge ports of the main fabric placement bin (2), the metering bin (3), and the precision fabric placement bin (4) are controlled by a bin door controlled by a telescopic rod.
2. A rail-mounted concrete placing machine according to claim 1, characterized in that: The telescopic rod (10) is a hydraulic telescopic rod; the fabric placing machine also includes a hydraulic control system and an electrical control system.
3. A rail-mounted concrete placing machine according to claim 1, wherein: A stirring mechanism is provided inside the main fabric bin (2); the stirring mechanism includes a stirring shaft driven by a motor and several stirring blades (6) arranged on the stirring shaft.
4. A rail-mounted concrete placing machine according to claim 1, wherein: The metering chamber (3) is a detachable installation structure, and metering chambers (3) of different sizes can be disassembled and replaced.
5. A track-mounted concrete placing machine according to any one of claims 1-4, characterized in that: The two ends of the cloth box girder (1) are provided with longitudinal walking mechanisms (7); it also includes a longitudinal walking track (8); the longitudinal walking mechanism (7) drives the whole machine to move on the longitudinal walking track (8).
6. A rail-mounted concrete placing machine according to claim 5, wherein: A concrete mixing plant (9) is set at one end of the longitudinal walking track (8); the track-type concrete placing machine is controlled by remote control or automatically controlled by the control system.
7. A rail-mounted concrete placing machine according to claim 1, wherein: The precision material distribution bin (4) and the metering bin (3) are set separately. Multiple precision material distribution bins (4) are set. A material distribution track (13) is set below the material distribution box beam (1) to allow the precision material distribution bin (4) to move. The precision material distribution bin (4) is installed on the material distribution track (13) by a material distribution trolley (14).
8. A rail-mounted concrete placing machine according to claim 1, wherein: The lower end of the precision material feeding bin (4) is provided with several feeding ports spaced at intervals; the opening and closing size of each feeding port is controlled by a bin door controlled by a telescopic rod (10).