A double-row pile and front support grouting steel pipe combined foundation pit supporting structure
By using a combination of double-row piles and front-supported grouting steel pipes for foundation pit support, the problems of insufficient stability and construction disturbance of traditional support structures under complex geological conditions are solved, achieving a construction effect of high stability and low disturbance.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- CHINA CONSTR FOURTH BUREAU WUHU CONSTR INVESTMENT CO LTD
- Filing Date
- 2025-04-22
- Publication Date
- 2026-07-07
AI Technical Summary
Traditional single-row anti-slide piles and anchor cable structures are not effective in controlling the horizontal displacement of the pile top and adapting to complex geological conditions. They are also costly to construct and affect underground pipelines of nearby buildings. Traditional double-row pile structures cannot achieve micro-disturbance effects under complex geological conditions.
A combined foundation pit support structure using double-row piles and front-supported grouting steel pipes is adopted. The combination of front-row piles, rear-row piles, pile top connecting beams, capping plates, and front-supported grouting steel pipes forms a statically indeterminate structure, enhancing overall stability and reducing the impact of construction on adjacent buildings.
It improves the overall stability and overturning resistance of double-row piles, reduces the disturbance to adjacent buildings during construction, is suitable for complex geological conditions, and reduces construction costs.