A high hoisting device for water gate formwork

By using a high-rise formwork hoisting device for sluice gates, and by adjusting the cables with a winch and electric cylinder, the problem of limited hoisting height of sluice gate pier formwork in low-lying river valleys was solved, enabling large-span hoisting and efficient construction.

CN224547925UActive Publication Date: 2026-07-24浙江省第一水电建设集团股份有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
浙江省第一水电建设集团股份有限公司
Filing Date
2025-09-02
Publication Date
2026-07-24

Smart Images

  • Figure CN224547925U_ABST
    Figure CN224547925U_ABST
Patent Text Reader

Abstract

The utility model discloses a high and big template hoisting device of water gate relates to hydraulic engineering technical field, including two groups of bearing frame, the top fixedly connected with total fixed frame of bearing frame, the front fixedly connected with PLC controller of bearing frame top, the top of total fixed frame is provided with the adjusting assembly who can further adjust height. This high and big template hoisting construction device of water gate is provided with central frame, first winch, second winch, balance cable, walking cable, when using, third winch is pulled up central frame through the lifting ring, central frame is along total fixed frame inside up and down sliding, during adjustment electric cylinder retraction, after adjusting to the appropriate position, electric cylinder extends, and the clamping block is clamped into the clamping groove of limiting slide rail, and its position is limited, realizes the function of being convenient for large -span hoisting, solves the problem that the device does not have the function of being convenient for large -span hoisting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of water conservancy engineering technology, specifically to a hoisting device for tall formwork of a sluice gate. Background Technology

[0002] When constructing sluice gate piers for large-scale water conservancy projects, formwork casting is usually used. Due to the large volume of the piers themselves, the formwork itself is also large in size and needs to be hoisted to the base by hoisting equipment for construction.

[0003] At current water conservancy project sluice gate formwork construction sites, truck cranes are mostly used for hoisting. However, the construction of sluice gate piers is mostly in low-lying river valleys, making it difficult for truck cranes to enter and exit. Furthermore, when hoisting the formwork of multiple piers, the hoisting height is limited by the specifications of the cylinder itself. There is room for improvement in both height adjustment and overall hoisting efficiency, and it does not have the function of facilitating large-span hoisting.

[0004] Now, a new type of high-formwork hoisting construction device for sluice gates is proposed to solve the above problems. Utility Model Content

[0005] The purpose of this utility model is to provide a high-span formwork hoisting device for sluice gates, so as to solve the problem mentioned in the background art that it does not have the function of facilitating large-span hoisting.

[0006] To achieve the above objectives, this utility model provides the following technical solution:

[0007] It includes two sets of load-bearing frames. Limiting components are fixedly connected to the front and rear ends of one side of the top of the load-bearing frame. A main fixing frame is fixedly connected to the top. A central frame is set inside. Two sets of balance cables and one set of travel cables are arranged laterally between the two sets of central frames. A lifting trolley is set outside the balance cables and travel cables.

[0008] The top of the main frame is also equipped with an adjustment assembly for further height adjustment, including two sets of third winches, which are respectively installed at the front and rear ends of the top of the main frame;

[0009] Lifting rings are welded to the front and rear ends of the top of the central frame. I-shaped frames are fixedly connected to the front and rear ends of the central frame. Pre-cut slots are provided on both sides of the top of the I-shaped frames. Electric cylinders are fixedly connected inside the pre-cut slots. A locking block is fixedly connected to the output end of the electric cylinder. Limiting slide rails are vertically welded to both sides of the front and rear ends inside the main fixing frame. Multiple sets of locking slots are opened inside the limiting slide rails.

[0010] As a further technical solution of this utility model, the steel cable of the third winch is connected to the lifting ring, and the shape and size of the outside of the I-shaped frame are matched with the shape and size of the inside of the main fixed frame, so that the I-shaped frame can slide up and down along the inside of the main fixed frame.

[0011] As a further technical solution of this utility model, the card block passes through the I-shaped frame and extends to the outside, and the shape and size of the card block match the shape and size of the card slot.

[0012] As a further technical solution of this utility model, the card slots are arranged at equal intervals.

[0013] As a further technical solution of this utility model, two sets of first winches are installed on one side inside the central frame, and a second winch is installed at the bottom inside the central frame.

[0014] As a further technical solution of this utility model, the balance cable is coiled around the outside of the first winch, and the travel cable is coiled around the outside of the second winch.

[0015] As a further technical solution of this utility model, the limiting component includes a limiting cylinder, in which a positioning pile is vertically inserted. A hammer head is welded to the top of the positioning pile, and a lifting hole is provided inside the hammer head. The outer diameter of the positioning pile matches the inner diameter of the limiting cylinder, and the positioning pile can slide up and down along the inside of the limiting cylinder.

[0016] As a further technical solution of this utility model, a PLC controller is fixedly connected to the front end of the top of the support frame.

[0017] As a further technical solution of this utility model, a traction frame is fixedly connected to the side of the supporting frame.

[0018] As a further technical solution of this utility model, the front and rear ends of the inside of the crane trolley are respectively provided with balance pulleys, the bottom end is provided with drive pulleys, and the top two sides are respectively installed with fourth winches, and the steel cables of the two sets of fourth winches are synchronously suspended with lifting devices.

[0019] Compared with the prior art, the beneficial effects of this utility model are: the sluice gate high formwork hoisting construction device not only realizes the function of facilitating large-span hoisting, but also realizes the function of facilitating cable tension adjustment and facilitating rapid reinforcement;

[0020] The system comprises a central frame, a first winch, a second winch, a balance cable, a traveling cable, a third winch, lifting rings, an I-beam frame, pre-grooved slots, electric cylinders, locking blocks, limit rails, and slots. During operation, the supporting frame is towed by a semi-trailer, with two sets of supporting frames positioned on either side of the river channel. The balance cable and traveling cable are taut, and the sluice gate template is suspended on the lifting device. The fourth winch rewinds and lifts it up. Driven by a motor, the drive pulley allows the crane trolley to travel along the balance cable and traveling cable above the river channel. During the lifting process... In addition to adjusting the tension, the height of the balance cable and the travel cable can also be further adjusted. The third winch pulls the central frame upward through the lifting ring, and the central frame slides up and down along the inside of the main fixed frame. During the adjustment, the electric cylinder retracts. After adjusting to the appropriate position, the electric cylinder extends, and the locking block is locked into the slot of the limit slide rail to limit its position. With the fourth winch, the up and down adjustment can be more precise and flexible, avoiding the cable bending down in the middle position and causing the position to be too low. It is convenient for construction on large-span river channels and realizes the function of facilitating large-span hoisting.

[0021] By setting up a first winch, a second winch, a balance cable, and a traveling cable, the balance cable and traveling cable serve as the main supporting steel cables during use. Their tension is controlled by the first winch and the second winch. The first winch and the second winch can control their tension by winding and releasing, thus making it easy to adjust their height and realizing the function of easily adjusting the cable tension.

[0022] By setting up a limiting cylinder, positioning piles, hammers, and lifting holes, when in use, as the two sets of load-bearing frames are in place, the positioning piles are inserted along the limiting cylinders, and the hammers are driven into the ground by the pile driving equipment, so that the load-bearing frames on both sides are stable. The lifting holes facilitate hoisting and subsequent pile removal, thus realizing the function of easy and rapid reinforcement. Attached Figure Description

[0023] Figure 1 This is a front view structural diagram of the present utility model;

[0024] Figure 2 This is a top-view enlarged structural schematic diagram of the load-bearing frame of this utility model;

[0025] Figure 3 This is a top-view enlarged structural diagram of the central frame of this utility model;

[0026] Figure 4 This is a partial enlarged front view of the limiting slide rail of this utility model;

[0027] Figure 5 This is a side view enlarged structural schematic diagram of the lifting trolley of this utility model.

[0028] Attached diagram labels: 1. Carrier frame; 2. Main fixed frame; 3. PLC controller; 4. Central frame; 5. First winch; 6. Second winch; 7. Balance cable; 8. Travel cable; 9. Third winch; 10. Lifting ring; 11. I-beam frame; 12. Pre-grooved slot; 13. Electric cylinder; 14. Locking block; 15. Limiting slide rail; 16. Locking slot; 17. Limiting cylinder; 18. Positioning stake; 19. Hammer head; 20. Lifting hole; 21. Traction frame; 22. Lifting trolley; 23. Balance pulley; 24. Drive pulley; 25. Fourth winch; 26. Lifting tool. Detailed Implementation

[0029] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0030] Example: Please refer to Figure 1-5 A high formwork hoisting device for a sluice gate includes two sets of support frames 1. A main fixing frame 2 is fixedly connected to the top of the support frame 1. A PLC controller 3 is fixedly connected to the front end of the top of the support frame 1. A central frame 4 is set inside the main fixing frame 2. Two sets of balance cables 7 and one set of travel cables 8 are arranged horizontally between the two sets of central frames 4. A traction frame 21 is fixedly connected to the side of the support frame 1. An adjustment component that can further adjust the height is set at the top of the main fixing frame 2.

[0031] Please see Figure 1-5 A high-formwork hoisting device for a sluice gate also includes an adjustment assembly. The adjustment assembly includes two sets of third winches 9, which are respectively installed at the front and rear ends of the top of the main fixed frame 2. Lifting rings 10 are welded to the front and rear ends of the top of the central frame 4. I-beams 11 are fixedly connected to the front and rear ends of the central frame 4. Pre-grooved slots 12 are provided on both sides of the top of the I-beams 11. Electric cylinders 13 are fixedly connected inside the pre-grooved slots 12. A locking block 1 is fixedly connected to the output end of the electric cylinders 13. 4. Limiting slide rails 15 are vertically welded to both sides of the front and rear ends inside the main fixed frame 2. Multiple sets of slots 16 are opened inside the limiting slide rails 15. A lifting trolley 22 is set outside the balance cable 7 and the traveling cable 8. Balance pulleys 23 are set at both the front and rear ends inside the lifting trolley 22. A drive pulley 24 is set at the bottom inside the lifting trolley 22. A fourth winch 25 is installed on both sides of the top of the lifting trolley 22. The steel cables of the two sets of fourth winches 25 are synchronously suspended by lifting devices 26.

[0032] The steel cable of the third winch 9 is connected to the lifting ring 10. The external shape and size of the I-shaped frame 11 are adapted to the internal shape and size of the main fixed frame 2. The I-shaped frame 11 can slide up and down along the inside of the main fixed frame 2. The locking block 14 passes through the I-shaped frame 11 and extends to the outside. The shape and size of the locking block 14 are adapted to the shape and size of the locking slot 16. The locking slot 16 is arranged at equal intervals. The PLC controller 3, the third winch 9, and the electric cylinder 13 are electrically connected, which facilitates hoisting in a large-span river channel.

[0033] Specifically, such as Figure 1 , Figure 2 , Figure 3 , Figure 4 and Figure 5 As shown, the sluice gate template is suspended on the lifting device 26. The fourth winch 25 winds up and lifts it. Driven by the motor, the driving pulley 24 drives the trolley 22 to travel along the balance cable 7 and the traveling cable 8 above the river. During the hoisting process, in addition to adjusting the tension, the height of the balance cable 7 and the traveling cable 8 can also be further adjusted. The third winch 9 pulls the central frame 4 upward through the lifting ring 10. The central frame 4 slides up and down along the inside of the main fixed frame 2. During the adjustment, the electric cylinder 13 retracts. After adjusting to the appropriate position, the electric cylinder 13 extends, and the locking block 14 is locked into the slot 16 of the limiting slide rail 15 to limit its position. With the fourth winch 25, the up and down adjustment can be more precise and flexible, avoiding the cable bending down in the middle position and causing the position to be too low. It is convenient for construction on a large-span river.

[0034] Two sets of first winches 5 are installed on one side inside the central frame 4, and a second winch 6 is installed at the bottom inside the central frame 4. The balance cable 7 is coiled around the outside of the first winch 5, and the travel cable 8 is coiled around the outside of the second winch 6. The PLC controller 3, the first winch 5, and the second winch 6 are electrically connected to facilitate the adjustment of the cable tension.

[0035] Specifically, such as Figure 1 and Figure 3 As shown, the balance cable 7 and the travel cable 8 serve as the main supporting steel cables. Their tension is controlled by the first winch 5 and the second winch 6. The first winch 5 and the second winch 6 can control their tension by winding and releasing, thus facilitating the adjustment of their height.

[0036] Limiting cylinders 17 are fixedly connected to the front and rear ends of one side of the top of the load-bearing frame 1. A positioning pile 18 is vertically inserted into the inside of the limiting cylinder 17. A hammer head 19 is welded to the top of the positioning pile 18. A lifting hole 20 is provided inside the hammer head 19. The outer diameter of the positioning pile 18 is matched with the inner diameter of the limiting cylinder 17. The positioning pile 18 can slide up and down along the inside of the limiting cylinder 17 for easy and quick fixation.

[0037] Specifically, such as Figure 1 and Figure 2As shown, with the two sets of supporting frames 1 in place, the positioning piles 18 are inserted along the limiting cylinder 17, and the hammer head 19 is hammered by the pile driving equipment. The positioning piles 18 are driven into the ground, making the positions of the supporting frames 1 on both sides stable, and the lifting holes 20 facilitate lifting and subsequent pile removal.

[0038] Working Principle: In use, the first step is towing the support frame 1 by a semi-trailer. Two sets of support frames 1 are positioned on either side of the river channel. As the two sets of support frames 1 are in place, positioning piles 18 are inserted along the limiting cylinder 17. The pile driving equipment then hammers the hammer head 19, driving the positioning piles 18 into the ground, stabilizing the positions of the support frames 1 on both sides. The lifting hole 20 facilitates lifting and subsequent pile removal. The balance cable 7 and travel cable 8 are taut and pulled. The sluice gate template is suspended on the lifting device 26, and the fourth winch 25 rewinds and lifts it. Driven by the motor, the drive pulley 24 pulls the lifting trolley 22 along the balance cable... 7. The traveling cable 8 travels above the river channel. During hoisting, in addition to adjusting the tension, the height of the balance cable 7 and the traveling cable 8 can be further adjusted. The third winch 9 pulls the central frame 4 upward through the lifting ring 10. The central frame 4 then slides up and down along the inside of the main fixed frame 2. During adjustment, the electric cylinder 13 retracts. After adjusting to the appropriate position, the electric cylinder 13 extends, and the locking block 14 engages with the slot 16 of the limiting slide rail 15 to limit its position. With the cooperation of the fourth winch 25, the up and down adjustment can be more precise and flexible, avoiding the cable bending downward in the middle position and causing the position to be too low. This facilitates construction on large-span river channels. The balance cable 7 and the traveling cable 8, as the main supporting steel cables, have their tension controlled by the first winch 5 and the second winch 6. The first winch 5 and the second winch 6 can control their tension by winding and releasing, thus facilitating the adjustment of their height.

[0039] It will be apparent to those skilled in the art that this invention is not limited to the details of the exemplary embodiments described above, and that it can be implemented in other specific forms without departing from the spirit or essential characteristics of this invention. Therefore, the embodiments should be considered illustrative and non-limiting in all respects, and the scope of this invention is defined by the appended claims rather than the foregoing description. Thus, it is intended that all variations falling within the meaning and scope of equivalents of the claims be included within this invention. No reference numerals in the claims should be construed as limiting the scope of the claims.

Claims

1. A high-formwork hoisting device for a sluice gate, comprising two sets of supporting frames (1), characterized in that: Limiting components are fixedly connected to the front and rear ends of the top side of the load-bearing frame (1), and a limiting component is fixedly connected to the top end. Main fixing frame (2), The main fixed frame (2) is provided with a central frame (4) inside. Two sets of balance cables (7) and one set of traveling cables (8) are arranged horizontally between the two sets of central frames (4). A lifting trolley (22) is provided outside the balance cables (7) and the traveling cables (8). The top of the main fixing frame (2) is provided with a height adjustment feature. Adjustment components, The adjustment assembly includes two sets of third winches (9), which are respectively installed at the front and rear ends of the top of the main fixed frame (2); lifting rings (10) are welded to the front and rear ends of the top of the central frame (4); I-shaped frames (11) are fixedly connected to the front and rear ends of the central frame (4), and pre-grooved slots (12) are respectively provided on both sides of the top of the I-shaped frame (11), and electric cylinders (13) are fixedly connected inside the pre-grooved slots (12), and a locking block (14) is fixedly connected to the output end of the electric cylinders (13); limit slide rails (15) are vertically welded to both sides of the front and rear ends inside the main fixed frame (2), and multiple sets of locking slots (16) are opened inside the limit slide rails (15).

2. The sluice gate high formwork hoisting device according to claim 1, characterized in that: The steel cable of the third winch (9) is connected to the lifting ring (10). The external shape and size of the I-shaped frame (11) match the internal shape and size of the main fixed frame (2). The I-shaped frame (11) can slide up and down along the inside of the main fixed frame (2).

3. The sluice gate high formwork hoisting device according to claim 1, characterized in that: The card block (14) passes through the I-shaped frame (11) and extends to the outside. The shape and size of the card block (14) match the shape and size of the card slot (16).

4. The sluice gate high formwork hoisting device according to claim 3, characterized in that: The slots (16) are arranged at equal intervals.

5. The sluice gate high formwork hoisting device according to claim 1, characterized in that: Two sets of first winches (5) are installed on one side inside the central frame (4), and a second winch (6) is installed at the bottom inside the central frame (4).

6. The sluice gate high formwork hoisting device according to claim 5, characterized in that: The balancing cable (7) is coiled around the outside of the first winch (5), and the traveling cable (8) is coiled around the outside of the second winch (6).

7. The sluice gate high formwork hoisting device according to claim 1, characterized in that: The limiting component includes The limiting cylinder (17) has a positioning pile (18) inserted vertically inside. A hammer head (19) is welded to the top of the positioning pile (18). A lifting hole (20) is provided inside the hammer head (19). The outer diameter of the positioning pile (18) is matched with the inner diameter of the limiting cylinder (17). The positioning pile (18) can slide up and down along the inside of the limiting cylinder (17).

8. The sluice gate high formwork hoisting device according to claim 1, characterized in that: A PLC controller (3) is fixedly connected to the front end of the top of the carrier frame (1).

9. A high-formwork hoisting device for a sluice gate according to claim 1, characterized in that: The side of the load-bearing frame (1) is fixedly connected to a traction frame (21).

10. A high-formwork hoisting device for a sluice gate according to claim 1, characterized in that: The front and rear ends of the trolley (22) are respectively equipped with balance pulleys (23), the bottom end is equipped with drive pulleys (24), and the top two sides are respectively equipped with fourth winches (25). The steel cables of the two sets of fourth winches (25) are synchronously suspended with lifting devices (26).