An assembly adjustment device
By using a mechanical tensioning and adjustment mechanism for the assembly and adjustment equipment, the safety hazards and low efficiency of the traditional manual splicing method have been solved, realizing the mechanized operation of auxiliary piles and engineering piles, and improving construction safety and efficiency.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- HUANENG TAICANG PORT LLC
- Filing Date
- 2025-09-05
- Publication Date
- 2026-07-28
AI Technical Summary
In building construction, port and bridge foundation construction, the traditional method of splicing auxiliary piles and engineering piles relies on manual labor and large lifting machinery, which poses safety hazards and low construction efficiency.
The system employs an assembly and adjustment device, including components such as a first support, a second support, a connecting rod, a jack, and a tie rod. The position and posture of the auxiliary pile and the engineering pile are adjusted through a mechanical tensioning and adjustment mechanism, avoiding high-risk manual operations.
The mechanized assembly of auxiliary piles and engineering piles has been achieved, which has improved construction safety and efficiency and avoided mechanical damage and crushing risks.
Smart Images

Figure CN224565212U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of auxiliary pile installation technology, specifically to an assembly and adjustment device. Background Technology
[0002] In the foundation construction of building projects, ports, docks, bridges, etc., it is often necessary to install auxiliary piles and splice them with the main engineering piles. The purpose of this splicing is usually to stabilize the main engineering piles so that subsequent concrete pouring, equipment installation or foundation pit support can be carried out.
[0003] Currently, in this type of temporary splicing construction, the traditional method mainly relies on manual operation in conjunction with large lifting machinery. Construction workers need to be in the operating area between the auxiliary pile and the engineering pile, and direct the crane to move the auxiliary pile through observation and measurement. The auxiliary pile is initially aligned manually, and then simple tools such as crowbars and jacks are used for rough fine-tuning. Finally, the inner cylinder of the auxiliary pile is inserted into or aligned with the engineering pile. Construction workers still need to work below when the heavy component auxiliary pile and engineering pile are moving, which poses a risk of mechanical injury and crushing. The component may accidentally slide or tilt during the adjustment process, which poses a safety hazard. Utility Model Content
[0004] In view of the shortcomings of the prior art, this utility model provides an assembly and adjustment device that solves the problems mentioned in the background.
[0005] This utility model provides the following technical solution: an assembly and adjustment device, comprising: at least one set of assembly and adjustment components, wherein the assembly and adjustment components are configured to be installed between engineering piles and auxiliary piles;
[0006] The assembly and adjustment component includes a first support and a second support. The first support is installed on the engineering pile, and the second support is installed on the auxiliary pile. A connecting rod is installed on the first support, and a jack is installed on the second support. A tie rod is installed on the jack, and the connecting rod and the tie rod are connected by an extension device.
[0007] Preferably, the tie rod is made of precision-rolled threaded steel bar, and one end of the tie rod passes through the second support and the jack in sequence and is connected to the anchor plate and the fixing nut, while the other end of the tie rod is threaded to the inner wall of the extension device.
[0008] Preferably, the second support is welded to the surface of the auxiliary pile.
[0009] Preferably, the connecting rod is a threaded rod, the first support has an installation hole for the connecting rod to pass through, and the surface of the connecting rod is threaded with two positioning nuts, which are respectively connected to both sides of the first support. One end of the connecting rod is threadedly connected to the inner wall of the extension device.
[0010] Preferably, the surface of the engineering pile is provided with a fixing hole, and the first support is welded to the inner wall of the fixing hole.
[0011] Preferably, a stop block is symmetrically connected to one side of the first support, and the surface of the stop block is connected to the surface of the engineering pile.
[0012] Compared with the prior art, the present invention has the following beneficial effects:
[0013] This assembly and adjustment equipment, through a mechanical tensioning and adjustment mechanism consisting of a through-hole jack, a tie rod, anchor plates, and fixing nuts, controls the movement of the jack. The jack drives the tie rod, which in turn drives the connecting rod through an extension device, thereby adjusting the relative position and posture between the auxiliary pile and the engineering pile. This achieves mechanized operation of the assembly process, avoiding manual work by construction personnel in a high-risk environment between the two piles, and effectively solving the safety problems of mechanical injury and crushing risks that exist in traditional manual splicing methods. Attached Figure Description
[0014] Figure 1 This is a side view of the structure of this utility model;
[0015] Figure 2 This utility model Figure 1 Schematic diagram of the side section structure at position AA;
[0016] Figure 3 This is a schematic diagram of the connection structure between the first support and the engineering pile of this utility model;
[0017] Figure 4 This is a schematic diagram of the fixing hole structure of this utility model;
[0018] Figure 5 This is a schematic diagram of the stop block structure of this utility model;
[0019] Figure 6 This is a top view of the first support structure of this utility model.
[0020] In the diagram: 1. Engineering pile; 2. Auxiliary pile; 3. First support; 4. Second support; 5. Connecting rod; 6. Jack; 7. Tie rod; 8. Extension device; 9. Anchor plate; 10. Fixing nut; 11. Mounting hole; 12. Positioning nut; 13. Fixing hole; 14. Stop block. Detailed Implementation
[0021] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0022] Please see Figure 1-6 An assembly and adjustment device includes: at least one set of assembly and adjustment components, the assembly and adjustment components being configured to be installed between an engineering pile 1 and an auxiliary pile 2;
[0023] The assembly and adjustment assembly includes a first support 3 and a second support 4. The first support 3 is installed on the engineering pile 1, and the second support 4 is installed on the auxiliary pile 2. A connecting rod 5 is installed on the first support 3, and a jack 6 is installed on the second support 4. A tie rod 7 is installed on the jack 6. The connecting rod 5 and the tie rod 7 are connected by an extension device 8.
[0024] The tie rod 7 is made of precision-rolled threaded steel bars. One end of the tie rod 7 passes through the second support 4 and the jack 6 in sequence and is connected to the anchor plate 9 and the fixing nut 10. The other end of the tie rod 7 is threaded to the inner wall of the extension device 8. The extension device 8 connects the connecting rod 5 and the tie rod 7 to form a complete and continuous force transmission chain. It also converts the span between the first support 3 and the second support 4 into an adjustable structure, which enhances the adaptability of the equipment to different spacing conditions, ensures the effective transmission of force and the overall stability of the structure, and allows the distance between the engineering pile 1 and the auxiliary pile 2 with different spacings to be adjusted, ensuring the reliability of temporary splicing. The second support 4 is welded to the surface of the auxiliary pile 2.
[0025] The connecting rod 5 is a threaded rod. The first support 3 has a mounting hole 11 for the connecting rod 5 to pass through. Two positioning nuts 12 are threadedly connected to the surface of the connecting rod 5, and the two positioning nuts 12 are respectively connected to both sides of the first support 3. One end of the connecting rod 5 is threadedly connected to the inner wall of the extension device 8. A fixing hole 13 is provided on the surface of the engineering pile 1. The first support 3 is welded to the inner wall of the fixing hole 13. A stop block 14 is symmetrically connected to one side of the first support 3, and the surface of the stop block 14 is connected to the surface of the engineering pile 1.
[0026] When assembling the engineering pile 1 and auxiliary pile 2, the first support 3 is pre-installed on the engineering pile 1, and the second support 4 is pre-installed on the auxiliary pile 2. A connecting rod 5 is installed on the first support 3, passing through the mounting hole 11 on the first support 3. Two positioning nuts 12 are installed on the connecting rod 5 to fix its position. The extension device 8 connects the connecting rod 5 and the tie rod 7, forming a complete and continuous force transmission chain. This converts the span between the first support 3 and the second support 4 into an adjustable structure, enhancing the equipment's adaptability to different spacing conditions, ensuring effective force transmission and overall structural stability, and allowing for adjustments to the distance between engineering piles 1 and auxiliary piles 2 at different spacings. Adjustable, ensuring the reliability of temporary splicing, and using the jack 6 installed on the second support 4 to move the tie rod 7. The jack 6 is a through jack, providing a powerful, controllable and linear jacking or pulling force, thereby adjusting the relative position and attitude between the auxiliary pile 2 and the engineering pile 1. This realizes the mechanized operation of the entire process of centering, guiding and splicing of the auxiliary pile 2 and the engineering pile 1, solving the problems of low construction efficiency, poor splicing accuracy and need for repeated adjustments caused by the traditional method of relying on cranes for rough adjustment and manual prying. At the same time, it avoids the high-risk manual operation of construction personnel between the two piles, effectively solving the safety problems of mechanical injury and crush risk in the traditional manual splicing method.
[0027] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. An assembly and adjustment device, characterized in that, include: At least one set of assembly and adjustment components, the assembly and adjustment components being configured to be installed between the engineering pile (1) and the auxiliary pile (2); The assembly and adjustment assembly includes a first support (3) and a second support (4). The first support (3) is installed on the engineering pile (1), and the second support (4) is installed on the auxiliary pile (2). A connecting rod (5) is installed on the first support (3), and a jack (6) is installed on the second support (4). A tie rod (7) is installed on the jack (6), and the connecting rod (5) and the tie rod (7) are connected by an extension device (8).
2. The assembly and adjustment device according to claim 1, characterized in that, The tie rod (7) is made of finely rolled threaded steel bar, and one end of the tie rod (7) passes through the second support (4) and the jack (6) in sequence and is connected to the anchor plate (9) and the fixing nut (10). The other end of the tie rod (7) is threaded to the inner wall of the extension device (8).
3. The assembly and adjustment device according to claim 2, characterized in that, The second support (4) is welded to the surface of the auxiliary pile (2).
4. The assembly and adjustment device according to claim 1, characterized in that, The connecting rod (5) is a threaded rod. The first support (3) has an installation hole (11) through which the connecting rod (5) passes. The surface of the connecting rod (5) is threaded with two positioning nuts (12), and the two positioning nuts (12) are respectively connected to the two sides of the first support (3). One end of the connecting rod (5) is threadedly connected to the inner wall of the extension device (8).
5. The assembly and adjustment device according to claim 1, characterized in that, The surface of the engineering pile (1) is provided with a fixing hole (13), and the first support (3) is welded to the inner wall of the fixing hole (13).
6. The assembly and adjustment device according to claim 1, characterized in that, A stop block (14) is symmetrically connected to one side of the first support (3), and the surface of the stop block (14) is connected to the surface of the engineering pile (1).