Supply / demand adjustment controller, supply / demand adjustment control method, integration supply / demand adjustment method, and program
The supply and demand adjustment control device optimizes load distribution and bidding by considering generator efficiency and market demands, enhancing power plant efficiency and decision-making.
Patent Information
- Application Number
- JP2023062798
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-07
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2043-04-07
AI Technical Summary
Power plants with multiple generators face inefficiencies in load distribution and bidding strategies for supply and demand adjustment markets, leading to decreased operating efficiency when generators operate at partial loads.
A supply and demand adjustment control device that acquires power requirements from both the central power dispatch center and the market, distributes loads among generators based on operating efficiency, and determines bidding decisions based on the ability to meet these demands while optimizing generator usage.
Enhances operational efficiency by distributing loads closer to rated values, optimizing generator usage, and making informed bidding decisions, thereby improving the overall efficiency and effectiveness of power plant operations.
Smart Images

Figure 2024149111000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a supply and demand adjustment control device, a supply and demand adjustment control method, an integrated supply and demand adjustment method, and a program. [Background technology]
[0002] Power plants with multiple generators are required to operate the multiple generators efficiently according to the load required by the central load dispatching center or the supply and demand adjustment market. For example, Patent Document 1 discloses an operation schedule calculation device that ranks the power generation efficiency for each load band that represents the output range of the generators, and plans to operate the generators with high power generation efficiency with priority according to the magnitude of the required load.
[0003] Generally, generators are designed to maximize efficiency at rated output, and even when operated at various load ranges, a load range close to the rated output is more economical to operate (called operating efficiency). For this reason, it is preferable to operate generators at a load as close to the rated output as possible. In this regard, the technology of Patent Document 1 provides a control that adjusts output by reducing the load of both units and operating them at partial load if the required load decreases while two power generation facilities are operating at rated load, for example. In this case, the operating efficiency of both units decreases. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2011-169234 A [Patent Document 2] JP 2014-85853 A Summary of the Invention [Problem to be solved by the invention]
[0005] When a power plant submits a bid in response to a request from the supply and demand balancing market, it is preferable to operate the generators by performing load allocation that takes into account the operating efficiency of the power plant as a whole. It is also desirable to determine whether or not to accept the bid after performing such load allocation.
[0006] The present disclosure provides a supply and demand adjustment control device, a supply and demand adjustment control method, a comprehensive supply and demand adjustment method, and a program that can solve the above problems. [Means for solving the problem]
[0007] The supply and demand adjustment control device disclosed herein includes an acquisition unit that acquires a first power requested from a power plant having multiple generators and a second power requested from a supply and demand adjustment market, a load allocation unit that allocates a total load, which is the sum of the first power and the second power, to the multiple generators in order of highest operating efficiency so that the load allocated to the generators is as close as possible to the rated load, and a bid determination unit that determines whether to bid on a request from the supply and demand adjustment market based on whether the full load is available.
[0008] The supply and demand adjustment method disclosed herein includes the steps of obtaining a first power requested from a power plant having a plurality of generators and a second power requested from a supply and demand adjustment market, allocating a total load, which is the sum of the first power and the second power, to the plurality of generators in order of highest operating efficiency so that the load allocated to the generators is as close as possible to a rated load, and determining whether to bid on the request from the supply and demand adjustment market based on whether the full load can be provided.
[0009] The integrated supply and demand adjustment method disclosed herein includes the steps of obtaining a first power requested from a plurality of power plants and a second power requested from a supply and demand adjustment market, allocating a total load, which is the sum of the first power and the second power, to generators equipped at the plurality of power plants in order of highest operating efficiency, such that the load allocated to the generators is as close as possible to a rated load, and determining whether to bid on a request from the supply and demand adjustment market based on whether the full load can be provided.
[0010] The program disclosed herein causes a computer to execute the steps of: obtaining a first power requested from a power plant having multiple generators and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to the multiple generators in order of highest operating efficiency so that the load allocated to the generators is as close as possible to the rated load; and determining whether to bid on the request from the supply and demand adjustment market based on whether the full load is available.
[0011] The program disclosed herein causes a computer to execute the steps of: acquiring a first power requested from a plurality of power plants and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to generators equipped at the plurality of power plants in order of highest operating efficiency, such that the load allocated to the generators is as close as possible to the rated load; and determining whether to bid on the request from the supply and demand adjustment market based on whether the full load is available. Effect of the Invention
[0012] According to the supply and demand adjustment control device, supply and demand adjustment control method, and program disclosed herein, in response to a request for electricity supply from the supply and demand adjustment market, load allocation to generators can be calculated taking into account operating efficiency, and a determination can be made as to whether or not to accept a bid. [Brief description of the drawings]
[0013] [Figure 1] 1 is a diagram illustrating an example of a power supply system according to an embodiment. [Figure 2A] FIG. 2 is a first diagram showing an example of an operating efficiency database according to the embodiment. [Figure 2B] FIG. 2 is a second diagram showing an example of an operating efficiency database according to the embodiment. [Diagram 3] FIG. 4 is a diagram showing an example of an operation schedule according to the embodiment. [Figure 4] 10 is a diagram showing an example of a data table in which past operating environments and power supply requests according to an embodiment are recorded; FIG. [Figure 5A] FIG. 4 is a diagram illustrating an example of a relationship between the output of the generator and the atmospheric temperature according to the embodiment. [Figure 5B] FIG. 4 is a diagram showing an example of a relationship between the output of the generator and the atmospheric temperature according to the embodiment. [Figure 6] FIG. 2 is a diagram illustrating an example of an on-site power database according to the embodiment. [Figure 7] FIG. 2 is a diagram illustrating an example of a bidding record database according to the embodiment. [Figure 8A] 13 is a flowchart showing an example of a bidding necessity determination process according to the embodiment. [Figure 8B] FIG. 13 is a diagram showing an outline of a method for calculating an overload output according to an embodiment. [Figure 9A] FIG. 11 is a first diagram showing an example of a support screen according to the embodiment. [Figure 9B] FIG. 2 is a second diagram showing an example of a support screen according to the embodiment. [Figure 10A] FIG. 3 is a third diagram showing an example of a support screen according to the embodiment. [Figure 10B] FIG. 4 is a fourth diagram showing an example of a support screen according to the embodiment. [Figure 11A] FIG. 5 is a fifth diagram showing an example of a support screen according to the embodiment. [Figure 11B] FIG. 6 is a sixth diagram showing an example of a support screen according to the embodiment. [Figure 12] FIG. 7 is a seventh diagram showing an example of a support screen according to the embodiment. [Figure 13] FIG. 8 is an eighth diagram showing an example of a support screen according to the embodiment. [Figure 14A] FIG. 9 is a ninth diagram showing an example of a support screen according to the embodiment. [Figure 14B] FIG. 10 is a tenth diagram showing an example of a support screen according to an embodiment. [Figure 14C] FIG. 11 is an eleventh diagram showing an example of a support screen according to the embodiment. [Figure 15A] FIG. 12 is a twelfth diagram showing an example of a support screen according to the embodiment. [Figure 15B] FIG. 13 is a thirteenth figure showing an example of a support screen according to the embodiment. [Figure 15C] FIG. 14 is a fourteenth figure showing an example of a support screen according to the embodiment. [Figure 16] FIG. 11 is a diagram illustrating another example of a power supply system according to the embodiment. [Figure 17] 2 is a diagram illustrating an example of a hardware configuration of a supply and demand adjustment control device according to an embodiment. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] <Embodiment> Hereinafter, the power supply system of the present disclosure will be described with reference to FIGS. (composition) FIG. 1 is a block diagram showing an example of a power supply system according to an embodiment. The power supply system 100 includes a power system 1, a central load dispatching center 2, a supply and demand adjustment market 3, and a power plant 4. The power plant 4 includes a supply and demand adjustment control device 10, an AVQR facility 20, load control devices 30-1 to 30-n, and generators 40-1 to 40-n. The central load dispatching center 2 issues a command to the power plant 4 regarding the power that the power plant 4 should supply to the power system 1. In response to this command, the power plant 4 operates the generators 40-1 to 40-n to generate power so as to supply the specified power. In the supply and demand adjustment market 3, a request for power (adjustment capacity) according to fluctuations in power supply and demand is presented. In response to this, if the power plant 4 is able to meet the request in the supply and demand adjustment market 3 and judges that there is a possibility of winning the bid, it bids in the supply and demand adjustment market 3, and does not bid otherwise. For example, there are five types of products in the supply and demand adjustment market 3, and it judges whether or not to bid for tertiary adjustment capacity (1) and (2). The supply and demand adjustment control device 10 of the power plant 4 determines whether or not to accept the bid and allocates loads to the generators 40-1 to 40-n when supplying adjustment power. If the bid is successful, the power plant 4 operates the generators 40-1 to 40-n so as to supply the total amount of power required by the central load dispatching center 2 and the supply and demand adjustment market 3. The load control device 30-1 operates the generator 40-1 with the load allocated by the supply and demand adjustment control device 10. Similarly, each of the load control devices 30-2 to 30-n operates the generators 40-2 to 40-n with the load allocated to the generators 40-2 to 40-n by the supply and demand adjustment control device 10. The generators 40-1 to 40-n have a configuration in which the generators are connected to the rotors of, for example, a gas turbine or a steam turbine. Hereinafter, the generator 40-1 may be referred to as the No. 1 generator, the generator 40-2 as the No. 2 generator, the generator 40-3 as the No. 3 generator, . . . , and the generator 40-n as the No. n generator.
[0015] The AVQR (Automatic Voltage & Q Regulator) equipment 20 is equipped with a bus voltage adjustment function that monitors the voltage fluctuation of the power system 1 and controls the voltage to be constant, an inter-series balance function that distributes the reactive power share of the generators 40-1 to 40-n according to the generated reactive power (Q) relative to the active power (P), and a VQ control series discrimination function that determines V control and Q control according to the operating state of each generator 40-1 to 40-n. For example, when a small-scale distributed power source such as a solar power generation system is introduced into the power distribution system, voltage control of the power distribution system close to the consumer is essential. Assuming that the voltage of the power distribution system becomes unstable due to a sudden change in weather or a trouble at a substation, the power plant 4 is provided with the AVQR equipment 20, and controls the excitation device provided in the AVQR equipment 20 so that the voltage of the power system 1 is maintained at a set value for the power requested to be supplied. In addition, when the AVQR equipment 20 is requested to supply reactive power required to transmit the requested power, the AVQR equipment 20 has a function of calculating the leading side reactive power allocation and lagging side reactive power allocation of the generators 1 to n and controlling the generators 40-1 to 40-n via the load control devices 30-1 to 30-n to supply the required reactive power.
[0016] The supply and demand adjustment control device 10 is configured with one or more computers. The supply and demand adjustment control device 10 includes an input / output unit 11, a load distribution calculation unit 12, an operation schedule calculation unit 13, a support information output unit 14, and a storage unit 15.
[0017] The input / output unit 11 acquires command information for supplied power from the central load dispatching center 2 and command information for adjustment capacity (EDC signal, LFC signal) from the supply and demand balancing market 3. When submitting a bid to the supply and demand balancing market 3, the input / output unit 11 transmits information indicating a bid to the supply and demand balancing market 3.
[0018] The load allocation calculation unit 12 calculates the load to be allocated to the generators 40-1 to 40-n based on the power requested by the central load dispatching center 2 and the supply and demand adjustment market 3. The load allocation calculation unit 12 calculates the load allocation so that the generators 40-1, etc. are operated at rated load as much as possible to improve the operating efficiency. In addition, the load allocation calculation unit 12 judges whether or not to accept a bid for the adjustment capacity presented by the supply and demand adjustment market 3.
[0019] The operation schedule calculation unit 13 calculates the operation schedule of the generators 40-1 to 40-n based on the load distribution calculated by the load distribution calculation unit 12. There is no particular limitation on the method of calculating the operation schedule of the generators 40-1 to 40-n, and a known method can be applied (for example, Patent Document 2).
[0020] The support information output unit 14 presents to the operator the result of the load distribution calculation unit 12's determination as to whether or not bidding is possible, and if it is determined that bidding is possible, support information for the operator to make a final decision on whether or not to bid.
[0021] The storage unit 15 stores various information such as setting information and processing data. The storage unit 15 also stores an operation efficiency DB (DB is an abbreviation for database) 151, an on-site power DB 152, a bidding record DB 153, etc. Below, the functions of the load distribution calculation unit 12 will be described along with examples of data contents registered in the databases and data tables manually stored in the storage unit 15.
[0022] An example of the operation efficiency DB 151 is shown in FIG. 2A. As shown in the figure, the operation efficiency DB 151 has items such as "rank (operation efficiency)", "operability", "constraint condition", and "rating" for each generator. The name and identification information of the generator are registered in "generator ID", and the magnitude of the rated load is registered in "rating". The "rank (operation efficiency)" is set with the order of operation efficiency and operation efficiency of the generators 40-1 to 40-n. The value in parentheses is the operation efficiency. The operation efficiency may be a value obtained by calculating the output load of the gas turbine with respect to the amount of fuel input to the gas turbine. For example, even if the generators are the same type, the operation efficiency differs depending on the repair status of the moving blades, stationary blades, and diaphragms. The load distribution calculation unit 12 calculates the load distribution to the generators 40-1 to 40-n so that the generator with the highest operation efficiency is preferentially selected and operated. In "operability", whether the generators 40-1 to 40-n can be operated or not is set. For example, the generator 40-1 (No. 1) is undergoing repair and cannot be operated. In this case, the ranking of the operating efficiency set in the operating efficiency DB 151 is Unit 3, Unit 1, and Unit 2, but since Unit 1 cannot be operated, the actual ranking is Unit 3, Unit 2, .... The contents of the operating efficiency DB 151 are updated, for example, once a day, depending on the status of the generators 40-1 to 40-n. However, for example, if a problem occurs with generator 40-1 in the morning of a certain day, the setting contents for generator 40-1 in the operating efficiency DB 151 may be updated in the afternoon of that day (for example, the "operability" of Unit 1 is updated to "not operable").
[0023] Here, it is assumed that the rated load of the first to third units is 200 (MW), and the contents of the operation efficiency DB 151 are as shown in FIG. 2A. Also, it is assumed that a supply command of 100 (MW) is transmitted from the central load dispatching center 2. In this case, the load dispatch calculation unit 12 decides to allocate 100 (MW) to the most efficient third unit (the partial load factor of the third unit is 50%), and not to allocate load to the other generators 40-2 to 40-n. Next, it is assumed that an adjustment capacity of 150 (MW) is requested from the supply and demand adjustment market 3, and it is decided to bid for this request. In this case, the load dispatch calculation unit 12 decides to operate the most efficient third unit at the most efficient rated load, and to allocate the remainder to the second unit with the second highest operation efficiency. As a result, 200 (MW) is allocated to the third unit, and 50 (MW) is allocated to the second unit (the third unit is at the rated load, and the second unit is at the partial load factor of 25%).
[0024] Some power plants may be operated in a manner that performs equal-amount control (operation in which loads are allocated equally to multiple generators). For example, if a supply command of 300 (MW) is sent from the central load dispatching center 2, 150 (MW) is allocated to units 2 and 3 for operation. In this situation, assume that an adjustment capacity of 50 (MW) is requested from the supply and demand adjustment market 3. In this case, if it is assumed that the power requested from the supply and demand adjustment market 3 does not have to be allocated equally even in a power plant that operates in an equal amount, the load distribution calculation unit 12 may allocate 50 (MW) from the supply and demand adjustment market 3 to unit 3 and operate it at rated load, and allocate 150 (MW) to unit 2, instead of allocating 25 (MW) each to units 2 and 3. Even when the power requested from the supply and demand adjustment market 3 is allocated equally, the load distribution calculation unit 12 distributes the load so that each generator operates at a load as close to the rated load as possible.
[0025] Another example of the operation efficiency DB 151 is shown in FIG. 2B. In the "constraint condition" of the operation efficiency DB 151, the constraint condition for each of the generators 40-1 to 40-n is registered. For example, in the example of FIG. 2B, the "constraint condition" of the No. 1 unit is set to not be able to operate in the load band of 130 (MW) due to some circumstances, such as the load prohibition band designed for gas turbine combustion burner switching. In such a case, the load distribution calculation unit 12 determines the load allocation so as to satisfy the constraint condition. For example, it is assumed that the requested load until 9:00 a.m. is 130 (MW) from the central load dispatching center 2, and that the total of 200 (MW) is supplied at 9:00 a.m., consisting of 100 (MW) from the central load dispatching center 2 and 100 (MW) from the supply and demand adjustment market 3. In this case, the load distribution calculation unit 12 calculates load distribution such that 130 (MW) is allocated to Unit 2 before 9:00, taking into consideration the constraints of Unit 1, and the 200 (MW) required at 9:00 is allocated to Unit 1, which has better operating efficiency, instead of Unit 2, which has been operating until then. The operation schedule calculation unit 13 calculates an operation schedule such as that shown in FIG. 3 based on the load distribution calculated by the load distribution calculation unit 12.
[0026] The load allocation calculation unit 12 may calculate the load allocation (whether to continue operation at the minimum load or to stop) of the second unit, which reduces the load instead of the first unit, after 9:00 by predicting the power demand for the time period after 9:00. For example, if the situation described in FIG. 2B and FIG. 3 is 9:00 a.m. on a summer day predicted to be sunny, there is a possibility that an additional power request will be presented from the supply and demand adjustment market 3 due to demand for air conditioning in the time period after 9:00. In such a case, the load allocation calculation unit 12 may allocate the minimum load to the second unit. Also, even if it is a sunny summer day, if it is currently 9:00 p.m. and it is determined that there is no prospect of an increase in power demand in the future, the load allocation calculation unit 12 may determine to stop the second unit (not to allocate the load). For example, the load distribution calculation unit 12 may determine whether to continue or stop operation of Unit 2 (whether to allocate a minimum load or not to allocate a load) based on a data table or the like in which information correlating the following time period, forecasted weather values, forecasted temperature values, and past time periods, weather, temperatures, and actual power requests from the supply and demand adjustment market 3 is registered. An example of the data table is shown in FIG. 4. The data table shown in FIG. 4 is stored in the storage unit 15. Also, a bidding record DB 153 described later may be used for this purpose.
[0027] The load distribution calculation unit 12 may also take into consideration atmospheric temperature characteristics when allocating loads to the generators 40-1 to 40-n. In general, in power generation using a gas turbine, the output decreases when the atmospheric temperature rises. As a result, during the day when the atmospheric temperature rises, there is a possibility that the desired output cannot be obtained even if the generators 40-1 and the like are operated at rated load. This is shown in FIG. 5A. A graph 51 in FIG. 5A shows the transition of the atmospheric temperature on a certain day, and a graph 52 shows the transition of the output when the generators 40-n are operated at rated load. For example, the storage unit 15 stores a data table shown in FIG. 5B, which specifies the relationship between the atmospheric temperature and the output of the generators 40-1 to 40-n, and the load distribution calculation unit 12 predicts the output of the generators 40-1 and the like to which the load is allocated, based on this data table and a predicted value of the temperature during the operating time period (for example, the actual temperature value during the same time period on the previous day may be used, or a forecast value provided by the Japan Meteorological Agency or the like may be used). 5A, for example, if it is predicted that the output will decrease between 10:00 and 15:00, the load distribution calculation unit 12 may allocate a load to the backup generator 40-n to cover the predicted shortfall in output. Alternatively, if the backup generator 40-n cannot be prepared, the load distribution calculation unit 12 may decide not to submit a bid, fearing a penalty in the event that the requested supply of power cannot be supplied.
[0028] An example of the on-site power DB 152 is shown in FIG. 6. As shown in the figure, the on-site power DB 152 has items such as "equipment ID", "power consumption", "time period", and "operation condition". In the "equipment ID", the name and identification information of the equipment that consumes power in the power plant 4 are registered, in the "power consumption", the power consumed by the equipment is registered, in the "time period", the time period during which the equipment operates is registered, and in the "operation condition", the condition under which the equipment operates is registered. For example, the air conditioner A is set to consume X1 (kW) and operate from 9:00 to 20:00 when the temperature is 28° C. or higher. The equipment B is set to consume X2 (kW) and operate from 16:00 to 22:00 from November to March. The load allocation calculation unit 12 refers to the on-site power DB 152, selects equipment that operates in the time period to which the load is assigned, tabulates the power consumption of the selected equipment, and subtracts the tabulated power consumption from the total load generated by the generator 40-1, etc., to which the load is assigned. The value after the subtraction becomes the actual power that can be supplied to the power system 1.
[0029] An example of the bidding record DB 153 is shown in FIG. 7. As shown in the figure, the bidding record DB 153 has items such as "company ID", "power plant ID", "load band", "date", "time slot", and "bidding result". The "company ID" and "power plant ID" register the names and identification information of other power plants connected to the power system 1, the "load band" registers the past load bands in which the power plant bid in response to requests from the supply and demand adjustment market 3, the "date" and "time slot" register the date and time slot in which the power plant bid, respectively, and the "bidding result" registers whether or not the bid was successful ("◯" if the bid was successful, and "×" if the bid was not successful). When a request for supply of adjustment capacity is presented from the supply and demand adjustment market 3, the load dispatch calculation unit 12 refers to the bidding records of its own and other power plants recorded in the bidding record DB 153 to determine whether or not to bid. For example, if the power plant A has won a bid for the load band of X1 (MW) a predetermined number of times or more in the past, the load dispatch calculation unit 12 determines that the power plant A is strong in this load band, and if the supply and demand adjustment market 3 requests X1 (MW), the load dispatch calculation unit 12 determines that the power plant A is unlikely to win against the power plant A and does not bid. Also, if the season or time period in which the power plant A wins a bid for the load band of X1 (MW) is limited (for example, mornings or evenings in summer), the load dispatch calculation unit 12 may determine that the power plant A may not have the spare capacity to supply X1 (MW) under these conditions and may determine that the power plant A is able to bid if the season or time period is other than the season or time period in which the power plant A has won a bid, and may determine that the power plant A is able to bid. Also, the load dispatch calculation unit 12 may determine that the power plant A is able to bid if the conditions are similar to those when the power plant itself was able to win a bid in the past. If the load dispatch calculation unit 12 determines that the power requested to be supplied can be supplied by operating the generators 40-1 to 40-n and that there is a possibility of winning the bid based on the bidding history DB 153, the load dispatch calculation unit 12 determines that the power plant A will bid for the adjustment capacity presented by the supply and demand adjustment market 3. Furthermore, when the bidding results in the supply and demand adjustment market 3 are known, the input / output unit 11 may add a record of the bidding history to the bidding history DB 153. This allows information on the bidding history to be accumulated in the bidding history DB 153, and the load dispatch calculation unit 12 can accurately predict the likelihood of a successful bid.
[0030] (operation) Next, the operation of the supply and demand adjustment control device 10 will be described with reference to FIG. FIG. 8 is a flowchart showing an example of the bidding necessity determination process according to the embodiment. It is assumed that the load allocation to the generators 40-1 to 40-n in response to a power supply request transmitted, for example, once a day from the central load dispatching center 2 has been completed. The load allocation calculation unit 12 allocates the load to the generators with good operating efficiency so that they can be operated at a load as close to the rated load as possible.
[0031] First, the input / output unit 11 acquires an adjustment power generation request from the supply and demand balancing market 3 (step S1). Next, the load dispatch calculation unit 12 judges whether the sum of the power requested from the central load dispatch center 2 and the adjustment power requested from the supply and demand balancing market 3 is within the output range of the power plant 4 (step S2). If it is within the output range (step S2; Yes), the process proceeds to step S4.
[0032] If it is not within the output range (step S2; No), the load distribution calculation unit 12 judges whether it can be handled by overload operation (step S3). Depending on the power plant, for example, operation exceeding the authorized output by 5% may be permitted, and in operating conditions such as winter atmospheric temperature being low, overload operation may be expected to improve output. FIG. 5B shows an example of the relationship between the atmospheric temperature and the output (maximum output) when overload operation is performed, and the relationship between the atmospheric temperature and the output (rated output) during normal operation that is not overload operation. Graph 52-A in FIG. 5B shows the output during normal operation, and graph 52-B shows the output during overload operation. As shown in the figure, below a certain atmospheric temperature, it is possible to obtain an output that exceeds the rated output by overload operation. The load distribution calculation unit 12 judges whether it is within the range of output that can be handled by overload operation. For example, the load distribution calculation unit 12 calculates how much overload is possible beyond the rated load while having a margin within the maximum output based on the power factor curves of the generators 40-1 to 40-n as shown in FIG. 8B. The load distribution calculation unit 12 also determines whether the calculated overload can be output, taking into consideration the atmospheric temperature characteristic of the output during overload operation (graph 52-B) shown in FIG. 5B. The details of the method for calculating the maximum load that can be output, which exceeds the rated load with a predetermined margin, based on the power factor curve, are publicly known and will not be described here. The load distribution calculation unit 12 determines that the overload operation is not possible if the overload operation is not permitted, if the required power cannot be supplied even if the overload operation is performed, or if it is determined that the calculated overload (for example, 5%) cannot be output due to operating conditions such as the atmospheric temperature. The load distribution calculation unit 12 determines that the overload operation is possible if the overload operation is permitted and the required power can be supplied by the overload operation. If the load distribution calculation unit 12 determines that the overload operation is not possible (step S3; No), the load distribution calculation unit 12 decides not to bid for the current request for supply of adjustment power. In this case, the support information output unit 14 outputs information notifying that the bid is not possible (step S13). For example, the support information output unit 14 outputs a screen such as that shown in FIG. 9A to a display device monitored by an operator.This screen displays a message such as "MW supply request was received, but no bid was made because it would exceed the output range." If it is determined that the request can be handled by overload operation (step S3; Yes), the process proceeds to step S4.
[0033] In step S4, the load dispatch calculation unit 12 judges whether there is a request for reactive power (step S4). It judges whether reactive power is included in the request from the supply and demand adjustment market 3. If there is no request for reactive power (step S4; No), proceed to step S6. If there is a request for reactive power (step S4; Yes), the load dispatch calculation unit 12 judges whether the reactive power request can be met (step S5). The load dispatch calculation unit 12 inquires of the AVQR equipment 20 whether it is possible to supply the requested reactive power. The AVQR equipment 20 judges whether adjustment to supply the requested reactive power is possible, and responds to the load dispatch calculation unit 12 with the judgment result. The AVQR equipment 20 has a function of calculating the share allocation of reactive power to supply the requested reactive power. With this function, the AVQR equipment 20 calculates the allocation of reactive power to the generators 40-1 to 40-n, and as a result, if the reactive power to be allocated to each generator is within a range determined by the power plant 4, it is judged that adjustment is possible, and if not, it is judged that adjustment is not possible. When the load dispatch calculation unit 12 receives a response from the AVQR facility 20 indicating that the adjustment is possible, it determines that the reactive power request can be handled, and when the load dispatch calculation unit 12 receives a response indicating that the adjustment is impossible, it determines that the reactive power request cannot be handled. When it is determined that the reactive power request cannot be handled (step S5; No), the load dispatch calculation unit 12 decides not to bid for the current request for supply of adjustment power. In this case, the support information output unit 14 outputs information notifying that the bid cannot be made (step S13). For example, the support information output unit 14 outputs a screen shown in FIG. 9A to a display device monitored by an operator. This screen displays a message such as "MW supply request was received, but reactive power adjustment was not possible, so a bid was not made." When it is determined that the reactive power request can be handled (step S5; Yes), the process proceeds to step S6.
[0034] Next, the load dispatch calculation unit 12 analyzes the output characteristics (step S6). For example, the load dispatch calculation unit 12 predicts the output of each of the generators 40-1 to 40-n during the time period when the supply and demand adjustment market 3 requires adjustment power, based on the atmospheric temperature. The load dispatch calculation unit 12 also refers to the operation efficiency DB 151 to acquire information such as whether each of the generators 40-1 to 40-n can be operated, the load range in which operation is not possible, and the magnitude of the rated load.
[0035] Next, the load dispatch calculation unit 12 analyzes the on-site power (step S7). The load dispatch calculation unit 12 refers to the on-site power DB 152 and tallies the power used by the facilities in the power plant 4 during the time period when the supply and demand adjustment market 3 requests adjustment power.
[0036] Next, the load dispatch calculation unit 12 judges whether the load corresponding to the adjustment power generation request acquired in step S1 can be output from the analysis results of steps S6 and S7 (step S8). The load dispatch calculation unit 12 calculates the total load of the generators 40-1 to 40-n that can output during the time period when the supply and demand adjustment market 3, analyzed in step S6, requests adjustment power, and subtracts the total power used by the equipment in the power plant 4, analyzed in step S7, from the result. If the value of the subtraction result is equal to or greater than the adjustment power required by the supply and demand adjustment market 3, the load dispatch calculation unit 12 judges that output is possible, and if not, judges that output is impossible. Note that, in order to bid on the supply and demand adjustment market 3, if output suppression of the equipment in the power plant 4 can be requested, the power suppression function may be provided. In that case, the value of the power consumption in the on-site power DB 152 is rewritten to the value after suppression.
[0037] When it is determined that the load corresponding to the adjustment power generation request from the supply and demand adjustment market 3 cannot be output (step S8; No), the load dispatch calculation unit 12 decides not to bid for the current adjustment power supply request. In this case, the support information output unit 14 outputs information notifying that the bid is not possible (step S13). For example, the support information output unit 14 outputs a screen as shown in FIG. 9A to a display device monitored by an operator. This screen displays a message such as "MW supply request was received, but output was determined to be impossible, so no bid was made." When it is determined that the reactive power request can be handled (step S8; Yes), the process proceeds to step S9.
[0038] Next, the load dispatch calculation unit 12 analyzes its own and other bidders' bidding records (step S9). For example, the load dispatch calculation unit 12 judges whether or not bidding is possible based on the time period and the magnitude of adjustment capacity (load band) required by the supply and demand adjustment market 3 based on the bidding record DB 153. For example, if the current bidding conditions match or are within a range that can be considered to match the season, time period, and load band of a successful bid in the past, the load dispatch calculation unit 12 judges that bidding is possible. Alternatively, the load dispatch calculation unit 12 may judge that bidding is possible if two of the season, time period, and load band match or are within a range that can be considered to match, or if the load band matches even if the season or time period is different. If it is judged that bidding is possible (step S10; Yes), the process proceeds to step S11.
[0039] When it is determined that bidding is not possible (step S10; No), the load dispatch calculation unit 12 decides not to bid for the current request for supply of adjustment capacity. In this case, the support information output unit 14 outputs information notifying that bidding is not possible (step S13). For example, the support information output unit 14 outputs a screen exemplified in FIG. 9A to a display device monitored by an operator. This screen displays a message such as "MW supply request was received, but a bid was not made because it was determined that the possibility of winning the bid was low." Note that the display and non-display of the screen exemplified in FIG. 9A may be switched by settings. For example, if the operator feels that the screen is disturbing during operation monitoring, the screen is set not to be displayed. Also, this screen is displayed when the judgment is No in steps S3, S5, S8, and S10, but the display and non-display may be switched depending on the situation. For example, the screen of FIG. 9A may be displayed only when the judgment is No in step S10, and may be set not to be displayed when the judgment is No in steps S3, S5, and S8.
[0040] In addition, although the judgment in step S10 is performed by the load distribution calculation unit 12, the load distribution calculation unit 12 may refer to the bidding record DB 153 to analyze the possibility of winning the bid and present the result to the operator, and the operator may decide whether to bid or not. For example, the support information output unit 14 may display a screen on the basis of the result of the analysis by the load distribution calculation unit 12, which allows the operator to select "Yes" or "No" along with a message such as "Another power plant A has won bids for this load range in the past 10 times, and this power plant has zero winning bids. Would you like to bid this time?". In this case, if the operator selects "Yes", the process proceeds to step S11.
[0041] Next, the load distribution calculation unit 12 performs load distribution calculation (step S11). The load distribution calculation unit 12 refers to the operation efficiency DB 151 to acquire information such as the rated load, operation possibility, and operation efficiency of each generator 40-1, etc., and calculates load distribution so that as many generators as possible 40-1, etc. are operated at a load close to the rated load at which they are maximized, for the requested load, which is the sum of the power requested from the central load dispatch center 2 and the adjustment power requested from the supply and demand adjustment market 3. Specifically, the load distribution is adjusted by giving priority to the generator with a high partial load rate so that it operates at its rated load, and then allocating partial load operation corresponding to the remaining load output. In addition, the load distribution calculation unit 12 performs load distribution so that the generators 40-1, etc. with high operating efficiency are given priority so that they operate at their rated load. For example, it is assumed that currently, all of the generators 1 to 3 with a rated load of 200 (MW) are operating at a partial load of 100 (MW), and the generator 1 has the highest operating efficiency, followed by the generator 2. In this situation, when 200 (MW) newly requested from the supply and demand adjustment market 3 is to be added and allocated, the load allocation calculation unit 12 sums up the original load 300 (MW) and the newly requested load 200 (MW), and allocates 200 (MW) of the total of 500 (MW) to the first unit with the highest operating efficiency so that it becomes the rated load, allocates 200 (MW) to the second unit with the next highest operating efficiency so that it becomes the rated load, and allocates the remaining 100 (MW) to the third unit. In this way, by allocating the total load in descending order of the operating efficiency of the multiple generators so that the load allocation to the generator is as close as possible to the rated load, it is possible to maximize the operating efficiency of each generator, and as a result, it is possible to maximize the operating efficiency of the entire power plant 4. The load allocation calculation unit 12 records the load allocation in the memory unit 15 when the bid is successful.
[0042] In the next step S12, the support information output unit 14 outputs bidding confirmation information (step S12), and finally decides whether or not to submit a bid based on the judgment of the operator. If it is determined that bidding is not possible, the support information output unit 14 outputs bidding confirmation information (step S12). First, the support information output unit 14 displays a screen as exemplified in FIG. 9B. If "No" is selected on this screen, bidding is not performed. If "Yes" is selected, the support information output unit 14 displays a screen as exemplified in FIG. 10A. In FIG. 10A, the load distribution calculated in step S11 is displayed. If "Yes" is selected on the screen of FIG. 10A, the support information output unit 14 displays a confirmation screen as exemplified in FIG. 10B. If "No" is selected on this confirmation screen, bidding is not performed. If "Yes" is selected, bidding is performed. The input / output unit 11 transmits information to the supply and demand adjustment market 3 that a bid will be submitted.
[0043] When "Change" is selected on the screen of FIG. 10A, the support information output unit 14 displays a change screen exemplified in FIG. 11A or FIG. 12. The change screen of FIG. 11A will be described. On the change screen of FIG. 11A, the operator can set the load to be assigned to each unit. The operator sets, for example, 200 (MW) to Unit 1, 100 (MW) to Unit 2, and 200 (MW) to Unit 3, and selects "Confirm." When "Confirm" is selected on the screen of FIG. 11A, the support information output unit 14 displays a confirmation screen exemplified in FIG. 11B. When "Back" is selected on the screen of FIG. 11A, the support information output unit 14 displays the confirmation screen of FIG. 10B.
[0044] The confirmation screen illustrated in FIG. 11B displays the load distribution before the change and the load distribution set by the operator, and further displays the average value of the operating efficiencies of Units 1 to 3 as the total efficiency. When "Confirm" is selected on the screen in FIG. 11B, the bid is submitted. When "Back" is selected, the confirmation screen in FIG. 11A is displayed.
[0045] Next, the confirmation screen of FIG. 12 will be described. In the change screen of FIG. 12, the load distribution calculated in step S11 ("standard setting" in FIG. 12) and the load distribution recalculated by the load distribution calculation unit 12 ("recommended setting" in FIG. 12) are displayed. The recommended setting is the load distribution calculated by the load distribution calculation unit 12 again by referring to the latest contents of the operation efficiency DB 151 after the operator selects "change" on the screen of FIG. 10A. The operation efficiency DB 151 is updated once a day, but if, for example, a situation occurs in the morning of that day that makes it impossible to operate the No. 1 unit at its rated load, the content is not immediately reflected in the operation efficiency DB 151. In such a case, when the operator confirms that 200 (MW) is assigned to the No. 1 unit on the screen of FIG. 10A, for example, the operator sets the fact that the No. 1 unit cannot operate at its rated load (200 (MW)) as a "constraint condition" of the operation efficiency DB 151 and updates the operation efficiency DB 151. After that, the operator selects "change" on the screen of FIG. 10A. Then, for example, the load distribution illustrated in "recommended settings" in Fig. 12 is calculated, and the confirmation screen illustrated in Fig. 12 is displayed. When "Accept" is selected on the screen in Fig. 12, the bid is submitted. When "Back" is selected, the confirmation screen in Fig. 10A is displayed.
[0046] When "No" is selected on the screen of FIG. 10A, the support information output unit 14 displays a confirmation screen as exemplified in FIG. 13. The screen of FIG. 13 requests confirmation of returning the supply request (not bidding). When "Yes" is selected on the screen of FIG. 13, the bidding is not executed. When "No" is selected on the screen of FIG. 13, the support information output unit 14 displays a confirmation screen as exemplified in FIG. 10A.
[0047] Also, if the determination in step S4 is Yes, the support information output unit 14 displays a screen exemplified in FIG. 14A. If "No" is selected on the screen of FIG. 14A, the bidding is not executed. If "Yes" is selected on the screen of FIG. 14A, the support information output unit 14 displays a screen exemplified in FIG. 14B. The rated reactive power and the lagging reactive power in FIG. 14B are calculated by the AVQR equipment 20. This calculation itself is publicly known and is performed by the AVQR equipment of a general power plant, so the calculation method will not be described. If "No" is selected on the screen of FIG. 14B, the bidding is not executed. For example, if the change of reactive power is not allowed, the operator selects "No". If "Yes" is selected on the screen of FIG. 14B, the support information output unit 14 displays a screen exemplified in FIG. 14C. The screen of FIG. 14C displays the allocation of reactive power to units 1 to 3. This allocation is calculated by the AVQR equipment 20 by a publicly known calculation method. If "No" is selected on the screen of FIG. 14C, the bidding is not executed. When "Yes" is selected on the screen of FIG. 14C, bidding is executed. Alternatively, when something other than reactive power is requested, a screen exemplified in FIG. 9B is displayed, and the process described with reference to FIG. 9B to FIG. 13 is executed. When "Change" is selected on the screen of FIG. 14C, a screen is displayed on which the operator can set the reactive power to be allocated to each unit, and when "Yes" is selected after setting the allocation of reactive power on this screen, bidding is executed. Generally, it is rare to adjust reactive power in order to bid on a request from the supply and demand adjustment market 3, but there is a possibility that bidding will be considered in cases such as when the capacitor function does not work due to a trouble at a substation. According to this embodiment, the possibility of adjusting reactive power and the allocation of reactive power to each unit are automatically calculated, and the results are presented, so that the operator can determine whether or not to bid on a request for reactive power simply by checking the results.
[0048] Also, if the determination in step S3 is Yes, the support information output unit 14 displays a screen exemplified in FIG. 15A. If "No" is selected on the screen of FIG. 15A, the bidding is not executed. If "Yes" is selected on the screen of FIG. 15A, the support information output unit 14 displays a screen exemplified in FIG. 15B. If "No" is selected on the screen of FIG. 15B, the bidding is not executed. For example, even if the calculation in step S3 calculates that an overload output is possible, if an increase in atmospheric temperature is predicted and the associated output reduction is taken into account, the operator selects "No" when it is expected that the requested load cannot be generated. If "Yes" is selected on the screen of FIG. 15B, the support information output unit 14 displays a screen exemplified in FIG. 15C. The target output and lagging reactive power on the screen of FIG. 15C are calculated by the AVQR facility 20 using a known calculation method. If "No" is selected on the screen of FIG. 15C, the bidding is not executed. When "Yes" is selected on the screen of Fig. 15C, the support information output unit 14 displays the screen exemplified in Fig. 14C. The subsequent processing is as described with reference to Fig. 14C. According to this embodiment, the possibility of overload operation and the allocation to each unit are automatically calculated, and the results are presented, so that the operator can decide whether to perform overload operation and submit a bid simply by checking the results.
[0049] (effect) As described above, according to this embodiment, when there is a request for supply of adjustment power from the supply and demand adjustment market 3, load allocation for each of the generators 40-1 to 40-n that optimizes the operating efficiency of the entire power plant 4 is calculated, and whether or not to accept a bid can be determined based on the load allocation result. Furthermore, when determining whether or not to accept a bid, the available power is calculated taking into consideration whether or not each generator can be operated, operating constraint conditions, atmospheric temperature characteristics, whether or not overload operation and reactive power can be adjusted, and the power consumed in the power plant 4, and whether or not to accept a bid can be determined from the calculation result. In addition, whether or not to accept a bid can be determined after anticipating the possibility of winning the bid based on past bidding records.
[0050] In FIG. 1, load allocation and bid acceptance for the supply request from the supply and demand adjustment market 3 are performed within one power plant, but as shown in FIG. 16, a higher-level control device 50 having the same functions as the supply and demand adjustment control devices 10a to 10c may be provided above the multiple power plants 4a to 4c, and the multiple power plants 4a to 4c may cooperate to optimize the load allocation of the generators owned by each power plant in response to a supply request for one adjustment capacity from the supply and demand adjustment market 3, and may determine whether or not to accept a bid, and may control the multiple power plants 4a to 4c to cooperate to supply the requested adjustment capacity. For example, the higher-level control device 50 allocates the total load, which is the sum of the power supply request from the central load dispatching center 2 and the adjustment capacity generation request from the supply and demand adjustment market 3, to the multiple generators equipped at the power plants 4a to 4c in descending order of operating efficiency so that the load allocated to the generators is as close as possible to the rated load.
[0051] FIG. 17 is a diagram illustrating an example of a hardware configuration of the supply and demand adjustment control device. The computer 900 includes a CPU 901 , a main memory device 902 , an auxiliary memory device 903 , an input / output interface 904 , and a communication interface 905 . The above-mentioned supply and demand adjustment control devices 10, 10a to 10c and the upper control device 50 are implemented in a computer 900. The above-mentioned functions are stored in the auxiliary storage device 903 in the form of a program. The CPU 901 reads the program from the auxiliary storage device 903, loads it in the main storage device 902, and executes the above-mentioned processing in accordance with the program. The CPU 901 also secures a storage area in the main storage device 902 in accordance with the program. The CPU 901 also secures a storage area in the auxiliary storage device 903 for storing data being processed in accordance with the program. The CPU 901 also loads information inputted from the input / output interface 904 and the communication interface 905 in the main storage device 902, executes the above-mentioned processing in accordance with the program, and outputs the information.
[0052] In addition, a program for realizing all or part of the functions of the supply and demand adjustment control devices 10, 10a to 10c, and the upper control device 50 may be recorded in a computer-readable recording medium, and the program recorded in the recording medium may be read into a computer system and executed to perform processing by each functional unit. The term "computer system" as used herein includes hardware such as an OS and peripheral devices. In addition, if a WWW system is used, the term "computer system" also includes a homepage providing environment (or display environment). In addition, the term "computer-readable recording medium" refers to a portable medium such as a CD, DVD, or USB, and a storage device such as a hard disk built into a computer system. In addition, if the program is distributed to the computer 900 through a communication line, the computer 900 that receives the program may expand the program in the main storage device 902 and execute the above processing. In addition, the above program may be for realizing part of the above-mentioned functions, and may further be capable of realizing the above-mentioned functions in combination with a program already recorded in the computer system.
[0053] As described above, several embodiments according to the present disclosure have been described, but all of these embodiments are presented as examples and are not intended to limit the scope of the invention. These embodiments can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope of the invention and its equivalents as described in the claims, as well as in the scope and gist of the invention.
[0054] <Additional Notes> The supply and demand adjustment control device, the supply and demand adjustment control method, and the program described in the embodiments can be understood, for example, as follows.
[0055] (1) A supply and demand adjustment control device according to a first aspect includes an acquisition unit that acquires a first power requested from a power plant having a plurality of generators and a second power requested from a supply and demand adjustment market, a load allocation unit that allocates a total load, which is the sum of the first power and the second power, to the plurality of generators in order of highest operating efficiency so that the allocation to the generators is as close as possible to a rated load, and a bid determination unit that determines whether to bid in response to a request from the supply and demand adjustment market based on whether the full load can be provided. This makes it possible to calculate load allocation to generators taking into account operating efficiency in response to requests for electricity supply from the supply and demand adjustment market, and to determine whether or not to accept a bid.
[0056] (2) A second aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (1), wherein the bid determination unit determines whether to bid for the request based on whether the reactive power included in the request can be supplied. This also makes it possible to respond to requests for reactive power.
[0057] (3) A third aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (1) to (2), wherein the bid determination unit determines whether the full load can be supplied by operating the generator at an overload when the full load exceeds an upper limit of the load that the power plant can output. This allows a decision to be made as to whether or not to respond to a request from the balancing market 3 by performing overload operation.
[0058] (4) A fourth aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (1) to (3), wherein the bid determination unit determines whether the full load is possible based on the atmospheric temperature characteristics of the generator. This makes it possible to avoid a situation in which a desired load cannot be supplied due to an increase in the atmospheric temperature.
[0059] (5) A fifth aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (1) to (4), wherein the bid determination unit subtracts the power required in the power plant from the total power output by the multiple generators to determine whether the full load can be supplied. This allows the decision on whether or not to accept a bid to be made taking into account the electricity used within the power plant.
[0060] (6) A sixth aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (1) to (5), wherein the bid determination unit determines whether or not to bid for the request based on bidding history for past requests from the supply and demand adjustment market. This makes it possible to avoid bidding when there is no prospect of winning the bid.
[0061] (7) A seventh aspect of the supply and demand adjustment control device is the supply and demand adjustment control device of (6), wherein the bid determination unit, based on the bidding history for past requests from the supply and demand adjustment market, determines not to bid for the request if another power plant has a history of winning bids for the load band included in the request, and determines to bid for the request if there is no history of winning bids for the load band included in the request. It is possible to avoid unpromising bids for load bands where other plants excel.
[0062] (8) A supply and demand adjustment control device according to an eighth aspect is a supply and demand adjustment control device according to any one of (1) to (7), further including a support information output unit that outputs information requesting final confirmation of whether or not to accept the bid when the bid judgment unit judges that a bid will be accepted for the request. This allows the operator to make the final decision on bidding.
[0063] (9) A ninth aspect of the supply and demand adjustment control device is a supply and demand adjustment control device of (8), wherein the support information output unit outputs a user interface (Figure 11A) that allows the load allocated by the load allocation unit to be changed. This allows the operator to set the final load distribution.
[0064] (10) A supply and demand adjustment method according to a tenth aspect includes the steps of: obtaining a first power requested from a power plant having a plurality of generators and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to the plurality of generators in order of highest operating efficiency so that the allocation to the generators is as close as possible to a rated load; and determining whether to bid for the request from the supply and demand adjustment market based on whether the full load can be provided.
[0065] (11) A method for integrated supply and demand adjustment according to an eleventh aspect includes the steps of: obtaining a first power requested from a plurality of power plants and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to generators equipped at the plurality of power plants in order of highest operating efficiency so that the load allocated to the generators is as close as possible to a rated load; and determining whether to bid in response to a request from the supply and demand adjustment market based on whether the full load can be provided.
[0066] (12) A program according to a twelfth aspect causes a computer to execute the steps of: acquiring a first power requested from a power plant having a plurality of generators and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to the plurality of generators in order of highest operating efficiency so that the allocation to the generators is as close as possible to a rated load; and determining whether to bid on the request from the supply and demand adjustment market based on whether the full load is available.
[0067] (13) A program according to a thirteenth aspect causes a computer to execute the steps of: acquiring a first power requested from a plurality of power plants and a second power requested from a supply and demand adjustment market; allocating a total load, which is the sum of the first power and the second power, to generators equipped at the plurality of power plants in order of highest operating efficiency, such that the load allocated to the generators is as close as possible to the rated load; and determining whether to bid in response to a request from the supply and demand adjustment market, based on whether the full load is available. [Explanation of symbols]
[0068] 100 Power supply system 1...Electric power system 2. Central power supply control center 3. Supply and demand adjustment market 4, 4a, 4b, 4c... Power plants 10, 10a, 10b, 10c...Supply and demand adjustment control device 11...Input / output section 12 Load distribution calculation section 13... Operation schedule calculation section 14 Support information output section 15...Storage section 151 Operational efficiency DB 152 ···In-house power DB 153 Bidding record DB 20...AVQR equipment 30-1 to 30-n Load control device 40-1~40-n...Generators 50....Host control device 900...Computer 901···CPU 902...Main memory 903...Auxiliary storage device 904 Input / Output Interface 905 Communication Interface
Claims
1. an acquisition unit that acquires a first power required for a power plant having a plurality of generators and a second power required from a supply and demand balancing market; a load distribution unit that distributes a total load, which is the sum of the first power and the second power, to the generators having the highest operating efficiency among the plurality of generators in order so that the load distributed to the generators is as close as possible to a rated load; a bidding determination unit that determines whether or not to bid on a request from the supply and demand adjustment market based on whether the full load can be supplied; A supply and demand adjustment control device comprising:
2. The bid determination unit, determining whether to bid on the request based on whether the reactive power included in the request can be provided; The supply and demand adjustment control device according to claim 1 .
3. The bid determination unit, determining whether the full load can be delivered by operating the generator at an overload when the full load exceeds an upper limit of the load that the power plant can deliver; The supply and demand adjustment control device according to claim 1 or 2.
4. The bid determination unit, determining whether the full load can be delivered based on the atmospheric temperature characteristics of the plurality of generators; The supply and demand adjustment control device according to claim 1 or 2.
5. The bid determination unit, Determining whether the full load can be supplied by subtracting the power required in the power plant from the total power output by the plurality of generators; The supply and demand adjustment control device according to claim 1 or 2.
6. The bid determination unit, determining whether to bid on the request based on past bidding records for requests from the supply and demand adjustment market; The supply and demand adjustment control device according to claim 1 or 2.
7. The bid determination unit, Based on past bidding records for requests from the supply and demand adjustment market, if there is a record of other power plants having won bids for the load band included in the request, it is determined not to bid for the request, and if there is no record of other power plants having won bids, it is determined to bid for the request. The supply and demand adjustment control device according to claim 6.
8. a support information output unit that outputs information requesting a final confirmation of whether or not to accept the bid when the bid decision unit decides to accept the bid; The supply and demand adjustment control device according to claim 1 or 2, further comprising:
9. The support information output unit outputs a user interface capable of changing the load allocated by the load allocation unit. The supply and demand adjustment control device according to claim 8.
10. obtaining a first power demand for a power plant having a plurality of generators and a second power demand from a balancing market; a step of allocating a total load, which is the sum of the first power and the second power, to the plurality of generators in descending order of operating efficiency such that the load allocated to the generator is as close as possible to a rated load; determining whether to bid on a request from the balancing market based on whether the full load is available; A supply and demand adjustment method having the above structure.
11. obtaining a first power demand from a plurality of power plants and a second power demand from a balancing market; A step of allocating a total load, which is the sum of the first power and the second power, to generators equipped in the plurality of power plants in descending order of operating efficiency, such that the load allocated to the generators is as close as possible to a rated load; determining whether to bid on a request from the balancing market based on whether the full load is available; A comprehensive supply and demand adjustment method.
12. On the computer, obtaining a first power demand for a power plant having a plurality of generators and a second power demand from a balancing market; a step of allocating a total load, which is the sum of the first power and the second power, to the plurality of generators in descending order of operating efficiency such that the load allocated to the generator is as close as possible to a rated load; determining whether to bid on a request from the balancing market based on whether the full load is available; A program that executes the following.
13. On the computer, obtaining a first power demand from a plurality of power plants and a second power demand from a balancing market; A step of allocating a total load, which is the sum of the first power and the second power, to generators equipped in the plurality of power plants in descending order of operating efficiency, such that the load allocated to the generators is as close as possible to a rated load; determining whether to bid on a request from the balancing market based on whether the full load is available; A program that executes the following.
Citation Information
Patent Citations
Power supply trading system
JP2004274822A
System stabilization system
JP2017046507A
Power demand adjustment system, power demand adjustment method, power demand adjustment program, and recording medium of them
JP2022165295A
Power supply-demand adjustment device and method
WO2022181003A1
Operation schedule calculation device
JP2011169234A