Job management apparatus and job management method
The job management device optimizes job scheduling in multi-tenant systems by considering execution conditions and priority flags, ensuring resource efficiency and adherence to user-defined end times.
Patent Information
- Application Number
- JP2023066182
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-14
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2043-04-14
AI Technical Summary
In multi-tenant systems, resource shortages occur due to simultaneous job execution by multiple tenants, leading to strained resources and challenges in determining optimal job execution times without increasing costs or violating user-defined end times.
A job management device and method that schedules jobs based on execution conditions, including start and end times, priority flags, and analysis information to optimize resource usage and meet end times while considering the execution conditions of other tenants.
The solution ensures that shared resources are not overwhelmed and job end times are met, allowing for efficient resource utilization and user-defined priority execution.
Smart Images

Figure 2024152151000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a job management device and a job management method. [Background technology]
[0002] In a multi-tenant system, multiple customers (users) share and use the same hardware or software resources. A multi-tenant server (multi-tenant system) provides resources to each tenant of multiple users. In job operations on a multi-tenant server, multiple customers may compete for the same resources, resulting in resource congestion. For example, when multiple banks use the same multi-tenant server, it is conceivable that jobs of each bank, such as tabulation work, may start simultaneously at the time when the bank's counter business ends. In this case, in the conventional technology, the problem of resource congestion was solved by scaling out the resources (see Patent Document 1). Patent Document 2 is a technology related to the present invention. The technology of Patent Document 2 calculates the total power consumption of jobs, which is the sum of the power consumption of each job when a job and similar jobs are executed at a fixed time interval shorter than the execution time of the job, based on a job information database, and creates a job schedule based on the total power consumption to improve the utilization efficiency of resources. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2016-103113 A [Patent Document 2] JP 2016-71841 A Summary of the Invention [Problem to be solved by the invention]
[0004] If the problem of resource tightness is addressed by scaling out, as in the technology of Patent Document 1, the costs (fixed costs / variable costs) will be large. If multi-tenant systems are operated with limited resources without scaling out resources in consideration of costs, users of each tenant will not know the execution conditions of jobs requested by users of other tenants, and therefore will not know the optimal time to execute the jobs. For this reason, in multi-tenant systems, the use of resources for processing jobs of each tenant will be concentrated at specific times, which can lead to resource tightness.
[0005] Furthermore, when scheduling jobs, changes to the start time of a job requested by each user are permitted to a certain extent, but it is important to strictly adhere to the end time requested by each user, as this could cause disruption to the work of each user.
[0006] The technology of Patent Document 2 targets job scheduling, but is not a technology that can resolve issues specific to multi-tenancy (for example, the issue that users of each tenant do not know the execution conditions of jobs of other tenants). Therefore, even if the technology of Patent Document 2 is applied to multi-tenancy, each tenant's job will be scheduled without considering the execution conditions of jobs of other tenants, which may result in resource shortages.
[0007] Therefore, one object of the present invention is to provide a job management device and a job management method that can schedule jobs so as not to overload the limited resources shared by each user in a multi-tenant system and to ensure that job completion times are met. [Means for solving the problem]
[0008] In order to solve the above problems, the job management device of the present invention is a job management device that includes an information processing device that schedules jobs to be executed by each tenant of a multi-tenant server, and the information processing device is configured to acquire job execution conditions including execution time conditions regarding the execution start time and execution end time of the job of each tenant and a priority flag indicating whether or not to prioritize job execution, and job execution analysis information that analyzes job execution results, and to schedule jobs based on the job execution conditions and the job execution analysis information.
[0009] The job management method of the present invention is a job management method using an information processing device that schedules jobs to be executed by each tenant of a multi-tenant server, in which the information processing device acquires job execution conditions including execution time conditions regarding the execution start time and execution end time of the job of each tenant and a priority flag indicating whether or not to prioritize job execution, as well as job execution analysis information that analyzes the job execution results, and schedules jobs based on the job execution conditions and the job execution analysis information. Effect of the Invention
[0010] According to the present invention, jobs can be scheduled so that the limited resources shared by each user in a multi-tenant system are not strained and the job end time is not exceeded. [Brief description of the drawings]
[0011] [Figure 1] FIG. 1 is a system configuration diagram of a system including a job management device according to an embodiment of the present invention. [Diagram 2] Figure 2 shows an example of the hardware configuration of a multi-tenant server. [Diagram 3] FIG. 3 is a functional block diagram showing an example of the configuration of a multi-tenant server. [Figure 4] FIG. 4 is a diagram for explaining analysis information during job execution and an example of acquiring the analysis information. [Diagram 5]FIG. 5 is a diagram for explaining an example of the job execution analysis information. [Figure 6] FIG. 6 is a diagram for explaining an example of the power consumption analysis information. [Figure 7] FIG. 7 is a diagram for explaining an example of job unit price information. [Figure 8A] FIG. 8A is a diagram illustrating an example of job power consumption prediction information. [Figure 8B] FIG. 8B is a flowchart showing the process flow of "power consumption prediction." [Figure 9] FIG. 9 is a diagram for explaining an example of the determination condition information. [Figure 10] FIG. 10 is a diagram for explaining an example of the determination condition information. [Figure 11] FIG. 11 is a diagram for explaining an example of scheduling determination information on a job registration date. [Figure 12] FIG. 12 is a diagram for explaining an example of the job creation screen. [Figure 13] FIG. 13 is a flowchart showing the process flow of automatic job scheduling. [Figure 14] FIG. 14 is a flowchart showing the process flow of "processing for determining new job execution time." [Figure 15] FIG. 15 is a flowchart showing the process flow of "processing for determining the start time of a job in which condition 1 and condition 2 are the same." [Figure 16] FIG. 16 is a flowchart showing the process flow of "processing for determining the start time of a job where condition 1 and condition 2 are different." [Figure 17] FIG. 17 is a flowchart for explaining the "processing for determining the start time of a job with a low priority." [Figure 18] FIG. 18 is a flowchart for explaining "processing for confirming that job execution can be completed by the end time of execution of condition 2." [Figure 19] FIG. 19 is a diagram for explaining an example of a report screen of a job execution result. [Figure 20]FIG. 20 is a diagram for explaining an example of a report screen that is displayed after the selection option ((1) Charge reduction) is selected and executed on the report screen of FIG. [Figure 21] FIG. 21 is a diagram for explaining an example of a report screen that is displayed after the selection option ((2) Power consumption reduction) is selected and executed on the report screen of FIG. [Figure 22] FIG. 22 is a diagram for explaining an example of a report screen that is displayed after the selection option ((3) Power type eco mode) is selected and executed on the report screen of FIG. [Diagram 23] FIG. 23 is a flowchart for explaining the selected option execution process. [Figure 24] FIG. 24 is a flowchart for explaining the process of determining the execution time of a job in "(1) Charge reduction." [Diagram 25] FIG. 25 is a flowchart for explaining the process of determining the execution time of a job in "(2) Power consumption reduction." [Figure 26] FIG. 26 is a flowchart for explaining the process of determining the execution time of a job in "(3) power type eco mode." DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0012] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In all the drawings of the embodiment, the same or corresponding parts may be given the same reference numerals. In the following description, various information may be described using expressions such as "record", but the various information may be expressed using other data structures. When describing identification information, expressions such as "ID", "name", and "number" are used, but these are mutually interchangeable. In the following description, processing may be described using a program or a functional block as the subject, but the subject of processing may be a CPU or a device (server) instead of a program or a functional block.
[0013] <<Embodiment>> 1 is a system configuration diagram of a system including a job management device (job management server 300) according to an embodiment of the present invention. The system includes a multi-tenant server 100, user terminals 200a to 200c, and a job management server 300. The multi-tenant server 100, the user terminals 200a to 200c, and the job management server 300 are connected to each other via a network NW1 so as to be able to transmit and receive information. Note that the user terminals 200a to 200c may be referred to as "user terminals 200" when there is no need to particularly distinguish between them. The user terminal 200 is, for example, a terminal equipped with a display (display device), such as a PC (Personal Computer), and is, for example, a terminal used in each tenant bank.
[0014] The multi-tenant server 100 includes tenant 1TN1 to tenant 3TN3. Hereinafter, tenant 1TN1 to tenant 3TN3 will be referred to as "tenant TN" when there is no need to particularly distinguish between them. Each tenant TN is a computer resource space that is logically isolated from each other and that the multi-tenant server 100 provides to each customer (user). In this example, the tenant TN in the multi-tenant server 100 is composed of one or more virtual servers built on a physical server.
[0015] Fig. 2 shows an example of the hardware configuration of the multi-tenant server 100. As shown in Fig. 2, the multi-tenant server 100 includes a CPU 111, a ROM 112, a RAM 113, a non-volatile storage device (HDD) 114 that can read and write data, a network interface 115, and an input / output interface 116. These are connected to each other via a bus 117 so as to be able to communicate with each other. The multi-tenant server 100 may be composed of a plurality of physical servers. The multi-tenant server 100 includes a storage battery 160 (not shown in Fig. 2) that stores power. Note that the storage battery 160 may be installed outside the multi-tenant server 100.
[0016] The CPU 111 loads various programs (not shown) stored in the ROM 112 and / or the HDD 114 into the RAM 113 and executes the programs loaded into the RAM 113 to realize various functions. As described above, various programs executed by the CPU 111 are loaded into the RAM 113, and data used when the CPU 111 executes the various programs is temporarily stored. The ROM 112 and / or the HDD 114 are non-volatile storage media, and various programs are stored therein. The network interface 115 is an interface for connecting the multi-tenant server 100 to the network NW1. The input / output interface 116 is an interface for connecting to an operating device such as a keyboard and a mouse, and a display (display device). Note that the virtual server has a configuration in which the above configuration of the physical server is virtualized.
[0017] Fig. 3 is a functional block diagram showing a configuration example of the multi-tenant server 100. As shown in Fig. 3, the multi-tenant server 100 includes a virtual server 120a included in tenant 1TN1, a virtual server 120b included in tenant 2TN2, and a virtual server 120c included in tenant 3TN3. Furthermore, the multi-tenant server 100 includes a power consumption analysis server 130 configured as a virtual server, and a power management server 140 configured as a virtual server.
[0018] Each virtual server 120 of each tenant TN includes a power consumption information unit 121a (121b, 121c), a job execution registration unit 122a (122b, 122c), and an execution control unit 123a (123b, 123c). When there is no need to distinguish between the power consumption information units 121a to 121c, the power consumption information units 121a to 121c are referred to as the "power consumption information unit 121." When there is no need to distinguish between the job execution registration units 122a to 122c, the job execution registration units 122a to 122c are referred to as the "job execution registration unit 122." When there is no need to distinguish between the execution control units 123a to 123c, the execution control units 123a to 123c are referred to as the "execution control unit 123."
[0019] The power consumption information unit 121 acquires and holds (stores) information on the power consumption consumed by each tenant TN (analysis information 400 during job execution in FIG. 4). Details of the analysis information 400 during job execution will be described later.
[0020] In the job execution registration unit 122, jobs to be scheduled for execution in the tenant TN input from the user terminal 200 are registered.
[0021] The execution control unit 123 controls the execution timing of a job so that the job is executed according to the schedule.
[0022] The power consumption information unit 121 is constituted by a virtualized HDD 114. The job execution registration unit 122 is constituted by a program stored in the virtualized ROM 112 and / or HDD 114 executed by the virtualized CPU 111, and the virtualized HDD 114. The execution control unit 123 is constituted by a program stored in the virtualized ROM 112 and / or HDD 114 executed by the virtualized CPU 111.
[0023] The power consumption analysis server 130 includes a power consumption information acquisition unit 131, an analysis unit 132, a billing unit 133, and a data storage unit 134.
[0024] The power consumption information acquisition unit 131 acquires information regarding power consumption from each tenant TN.
[0025] The analysis unit 132 analyzes the information acquired by the power consumption information acquisition unit 131 .
[0026] The accounting unit 133 calculates the charge for job execution by multiplying the job cost (yen) by the power consumption (kw).
[0027] The data storage unit 134 stores (memorizes, holds) the information acquired by the power consumption information acquisition unit 131, the information calculated by the analysis unit 132 and the billing unit 133 (job execution analysis information 500 in FIG. 5, power consumption analysis information 600 in FIG. 6, and job power consumption prediction information 800 in FIG. 8A), and other information necessary for analysis (job unit price information 700 in FIG. 7). Details of the job execution analysis information 500, power consumption analysis information 600, job unit price information 700, and job power consumption prediction information 800 will be described later.
[0028] The power consumption information acquiring unit 131 is configured by a program stored in the virtualized ROM 112 and / or the HDD 114 and executed by the virtualized CPU 111 .
[0029] The analysis unit 132 is constituted by a virtualized ROM 112 executed by the virtualized CPU 111 and / or a program stored in the HDD 114. The accounting unit 133 is constituted by a virtualized ROM 112 executed by the virtualized CPU 111 and / or a program stored in the HDD 114. The data storage unit 134 is constituted by the HDD 114.
[0030] The power management server 140 includes an electric power type determination unit 141 and an electric power acquisition unit 142. The electric power type determination unit 141 determines the type of electric power for each amount of electric power charged to the storage battery 160. The electric power type determination unit 141 holds (memorizes, stores) electric power management information for each electric power type (not shown), and manages the amount of electric power for each electric power type using the electric power management information. The electric power management information includes information that associates the amount of electric power charged to the storage battery 160 with the type of electric power.
[0031] The power acquisition unit 142 determines which power source, a power company supplied power source 171, a power company supplied power source 172, a renewable energy source 173, or a private power generation source 174, is to be used to charge the storage battery 160, and controls the storage battery 160 by sending a command to the controller so that the storage battery 160 charges with power from the determined power source. The power stored in the storage battery 160 is used as power to operate the multi-tenant server 100.
[0032] The power type determination unit 141 is configured by a program stored in the virtualized ROM 112 and / or HDD 114 executed by the virtualized CPU 111, and the HDD 114. The power acquisition unit 142 is configured by a program stored in the virtualized ROM 112 and / or HDD 114 executed by the virtualized CPU 111.
[0033] The job management server 300 includes a scheduling unit 301 and a data storage unit 302. The scheduling unit 301 schedules jobs to determine the execution timing of jobs registered in the job execution registration unit 122 of each tenant TN. The data storage unit 302 stores (memorizes, holds) condition information 900 at the time of job creation, judgment condition information 1000, and scheduling judgment information 1100, which are acquired by the scheduling unit 301 and registered in the job execution registration unit 122.
[0034] Details of the condition information 900 at the time of job creation, the judgment condition information 1000, and the scheduling judgment information 1100 will be described later. The job management server 300 is configured with a server having the same hardware configuration as that shown in Fig. 2 above. The server may be configured with multiple servers, or may be a virtual server on the cloud. The server may also be called an "information processing device".
[0035] The scheduling unit 301 is implemented by a program stored in the ROM 112 and / or the HDD 114 and executed by the CPU 111. The data storage unit 302 is implemented by the HDD 114.
[0036] The storage battery 160 is a battery module including a secondary battery capable of being charged and discharged, and a controller that controls charging and discharging of the secondary battery, selects a power source to be charged, measures power, and the like. The storage battery 160 functions as a power source that supplies power to the multi-tenant server 100. As described above, the power type determination unit 141 of the power management server 140 holds (memorizes, stores) power management information that associates the amount of power charged in the storage battery 160 with the type of power. The power type determination unit 141 virtually manages the power stored in the storage battery 160 by virtually classifying the amount of power for each type of power using the power management information.
[0037] For example, when the storage battery 160 is charged, the power type determination unit 141 increases the amount of power for each virtual power type according to the type of power source supplying power to the storage battery 160. For example, when the power source type when charging the storage battery 160 is renewable energy, the power type determination unit 141 increases the amount of power associated with the power type: renewable energy in the power management information by the amount of charged power.
[0038] When a job for which a specified power type is executed is performed, the power type discrimination unit 141 acquires the power consumption per job when the job is executed. The power type discrimination unit 141 regards the power consumption per job consumed by the execution of the job as the power consumption of the power type associated with the job, and updates the power management information by reducing the power consumption of the corresponding power type among the power consumption of the storage battery 160 by the amount of power consumption consumed by the execution of the job.
[0039] In the multi-tenant server 100, the computational resources of the multi-tenant server 100 required for each tenant TN to execute a job are allocated to each tenant TN, and the job is executed. The more jobs that are executed simultaneously in the same time period, the greater the amount of computational resources used in that time period, and the greater the power consumption of the multi-tenant server 100. Note that in this example, it is assumed that when each tenant TN of the multi-tenant server 100 executes a large number of jobs and the resource usage rate of the multi-tenant server 100 is 80%, the power consumption of the multi-tenant server 100 is 80 kW.
[0040] FIG. 4 is a diagram for explaining analysis information 400 at the time of job execution stored in the power consumption information unit 121 of each virtual server 120 of each tenant TN and an example of acquiring the same. The analysis information 400 at the time of job execution includes, as columns for storing information (values), #401, job name 402, execution start time 403, execution completion time 404, subsequent job 405, power type 406, power consumption (kw) 407, and billing amount (yen) 408. In the analysis information 400 at the time of job execution, information corresponding to each column when the tenants TN1 to TN3 (tenant TN1 in this example) executed a job is associated with each other and stored as information (records) on a row-by-row basis. Specifically, a number associated with the information (record) is stored in #401. The name of the job is stored in job name 402. The execution start time 403 stores the time when the associated job actually started execution. The execution completion time 404 stores the time (time) when the associated job actually completed execution. The succeeding job 405 stores the succeeding job of the associated job. The power type 406 stores the power type when the associated job was executed. The power consumption (kW) 407 stores the power consumption (kW) when the associated job was executed. The billed amount (yen) 408 stores the billed amount (yen) when the associated job was executed.
[0041] For example, when tenant TN1 executes Jobs 11, 12, and 13, the power consumption information unit 121a acquires information corresponding to each column of the analysis information 400 at the time of job execution, creates the analysis information 400 at the time of job execution, and transmits the created analysis information 400 at the time of job execution to the power consumption analysis server 130. The power consumption information acquisition unit 131 of the power consumption analysis server 130 stores and accumulates the analysis information 400 at the time of job execution received from the virtual server 120a of tenant TN1 in the data storage unit 134.
[0042] 5 is a diagram for explaining an example of job execution analysis information 500 stored in the data storage unit 134 of the power consumption analysis server 130. The job execution analysis information 500 is created (updated) based on the job execution analysis information 400 accumulated in the data storage unit 134. The job execution analysis information 500 is newly created or the information is updated based on the job execution analysis information 400 of FIG. 4 accumulated in the data storage unit 134.
[0043] Job execution analysis information 500 includes columns for storing information (values), such as #501, job name 502, execution start time (condition 1) 503, execution end time (condition 2) 504, power type (condition 3) 505, priority flag 506, previous execution start time 507, previous execution completion time 508, average execution time (min) 509, subsequent job 510, tenant 511, average power consumption (kw) 512, and billed amount (yen) 513.
[0044] In the job execution analysis information 500, information corresponding to each column regarding information analyzed and created (updated) based on the analysis information 400 at the time of job execution stored (accumulated) in the data storage unit 134 is associated with each other and stored as information (records) in rows. Specifically, a number associated with the information (record) is stored in #501. Job name 502 stores job identification information (name). Execution start time (condition 1) 503 stores the execution start time (condition 1) set as the execution condition of the associated job. Execution end time (condition 2) 504 stores the execution end time (condition 2) set as the execution condition of the associated job. Power type (condition 3) 505 stores the power type (condition 3) set as the execution condition of the associated job. Priority flag 506 stores information (ON or OFF) indicating the setting state of the priority flag 506 set as the execution condition of the associated job. When the priority flag 506 is set to "ON", this indicates that the job execution priority of the associated job is higher than the job execution priority when the priority flag 506 is set to "OFF". When the priority flag 506 of an execution condition of a certain job is set to "ON", this is referred to as "a certain job has been given priority". When the priority flag 506 of an execution condition of a certain job is set to "OFF", this is referred to as "a certain job has not been given priority".
[0045] Previous execution start time 507 stores the previous execution start time (execution start time) of the associated job. Previous execution completion time 508 stores the previous execution completion time of the associated job. Average execution time (min) 509 stores the average execution time (min) of the associated job. Subsequent job 510 stores the name of the subsequent job of the associated job. Tenant 511 stores identification information (number) of the tenant of the associated job. Average power consumption (kw) 512 stores the average power consumption (kw) of the associated job. Charge amount (yen) 513 stores the charge amount (yen) of the associated job.
[0046] FIG. 6 is a diagram for explaining an example of power consumption analysis information 600 stored in the data storage unit 134 of the power consumption analysis server 130. The power consumption analysis information 600 includes, as columns for storing information (values), a time 601, a total power consumption (kw) 602, a power consumption (kw) of tenant 1 603, a power consumption (kw) of tenant 2 604, a power consumption (kw) of tenant 3 605, and a job registration determination priority 606. In the power consumption analysis information 600, information corresponding to each column related to the power consumption of each tenant in the past (for example, when the previous job was executed (for example, the day before the registration date)) is associated with each other and stored as information (records) in rows. Specifically, the time 601 stores a time period that is an analysis unit of power consumption. The total power consumption (kw) 602 stores the total power consumption of tenant 1TN1 to tenant 3TN3 in the associated time period. The power consumption (kw) of tenant 1 603 stores the power consumption of tenant 1TN1 in the associated time period. The power consumption of tenant 2TN2 during the associated time period is stored in tenant 2 power consumption (kw) 604. The power consumption of tenant 3TN3 during the associated time period is stored in tenant 3 power consumption (kw) 605. The priority of the time period to which a job is assigned is stored in job registration determination priority 606.
[0047] FIG. 7 is a diagram for explaining an example of job unit price information 700 stored in the data storage unit 134 of the power consumption analysis server 130. The job unit price information 700 includes columns for storing information (values), such as #701, power type 702, and unit price (yen) 703 per job. In the job unit price information 700, information corresponding to each column relating to the unit price per job of each power type is associated with each other and stored as information (records) on a row-by-row basis. Specifically, a number associated with the information (record) is stored in #701. The type of power (power source) stored in the storage battery 160 is stored in the power type 702. The unit price (yen) per job of the associated power type is stored in the unit price (yen). The unit price (yen) per job of the power type is calculated based on the power rate of the power type and the cost of power generation, and the higher the power rate and cost, the higher the unit price (yen) per job.
[0048] 8A illustrates an example of job power consumption prediction information 800 stored in the data storage unit 134 of the power consumption analysis server 130. The job power consumption prediction information 800 includes, as columns for storing information (values), a time 801, a power consumption prediction (kw) 802 of the multi-tenant server 100, a total number of jobs on the job registration date 803, a power consumption prediction (kw) 804 in tenant 1 on the job registration date, a power consumption prediction (kw) 805 in tenant 2 on the job registration date, a power consumption prediction (kw) 806 in tenant 3 on the job registration date, a number of jobs 807 in tenant 1 on the job registration date, a number of jobs 808 in tenant 2 on the job registration date, and a number of jobs 809 in tenant 3 on the job registration date.
[0049] In the job power consumption prediction information 800, information corresponding to each column regarding the power consumption prediction of the multi-tenant server 100 is associated with each other and stored as information (records) in rows. Specifically, the time 801 stores the time period of the time range to be predicted. In the power consumption prediction (kw) 802 of the multi-tenant, the predicted power consumption in the multi-tenant server 100 for the associated time period is stored. In the total number of jobs on the job registration date 803, the total number of jobs on the job registration date for the associated time period is stored. In the power consumption prediction (kw) 804 of the job registration date of the tenant 1, the predicted power consumption on the job registration date of the tenant 1TN1 for the associated time period is stored. In the power consumption prediction (kw) 805 of the job registration date of the tenant 2, the predicted power consumption on the job registration date of the tenant 2TN2 for the associated time period is stored. In the power consumption prediction (kw) 806 of the job registration date of the tenant 3, the predicted power consumption on the job registration date of the tenant 3TN3 for the associated time period is stored. The number of jobs on the job registration date in tenant 1TN1 is stored in the number of jobs on the job registration date in tenant 1 807. The number of jobs on the job registration date in tenant 2TN2 is stored in the number of jobs on the job registration date in tenant 2 808. The number of jobs on the job registration date in tenant 3TN3 is stored in the number of jobs on the job registration date in tenant 3.
[0050] The job power consumption prediction information 800 is created and updated by the analysis unit 132. FIG. 8B is a flowchart showing the flow of the "power consumption prediction" process executed by the analysis unit 132 of the power consumption analysis server .
[0051] The analysis unit 132 creates and updates job power consumption prediction information 800 in response to a request from the job management server 300. The analysis unit 132 starts "power consumption prediction" from step 820 in Fig. 8B, and after sequentially executing the processes of steps 821 to 825 described below, proceeds to step 830 and temporarily ends this processing flow.
[0052] Step 821: The analysis unit 132 acquires job registration information (the number of jobs for each tenant TN, etc.) on the job registration date.
[0053] Step 822: The analysis unit 132 calculates the number of jobs on the job registration date in 10-minute intervals.
[0054] Step 823: The analysis unit 132 refers to the job execution analysis information 500 and acquires the average power consumption.
[0055] Step 824: The analysis unit 132 calculates a predicted power consumption for the job registration date in 10-minute increments based on the average power consumption.
[0056] Step 825 : The analysis unit 132 updates the power consumption prediction of the job power consumption prediction information 800 .
[0057] 9 is a diagram for explaining an example of condition information 900 at the time of job creation stored in the data storage unit 302 of the job management server 300. Note that the condition information 900 at the time of job creation is acquired from the job execution registration unit 122 of the virtual server 120 of each tenant TN and stored in the data storage unit 302.
[0058] Condition information 900 when creating a job includes columns for storing information (values), such as #901, job name 902, execution start time (condition 1) 903, execution end time (condition 2) 904, power type (condition 3) 905, priority flag 906, subsequent job 907, and tenant 908.
[0059] In the job creation condition information 900, information corresponding to each column regarding the job execution condition set by the user when creating the job is associated with each other and stored as information (records) on a row-by-row basis. Specifically, a number associated with the information (record) is stored in #901. In the job name 902, the name of the job is stored. In the execution start time (condition 1) 903, the execution start time as the condition 1 of the associated job is stored. In the execution end time (condition 2) 904, the execution end time (execution end time) as the condition 2 of the associated job is stored. In the power type (condition 3) 905, the power type as the condition 3 of the associated job is stored. In the priority flag 906, "ON" or "OFF" indicating the state of the priority flag given to the associated job is stored. In the subsequent job 907, the name of the subsequent job of the associated job is stored. In the tenant 908, the identification information (number) of the tenant TN in which the job is executed is stored.
[0060] 10 is a diagram for explaining an example of judgment condition information 1000 stored in the data storage unit 302 of the job management server 300. The judgment condition information 1000 includes, as columns for storing information (values), #1001, judgment type 1002, and error threshold (kW) 1003 between the previous total power consumption and the predicted power consumption on the registration date.
[0061] In the judgment condition information 1000, information corresponding to each column regarding the judgment condition for allocating a job with low power consumption is associated with each other and stored as information (records) on a row-by-row basis. Specifically, a number associated with the information (record) is stored in #1001. Information indicating the judgment type (◯, △, or ×) is stored in judgment type 1002. The error threshold (kw) 1003 between the previous total power consumption and the predicted power consumption on the registration date stores the judgment condition when the associated judgment type is determined.
[0062] 11 is a diagram for explaining an example of scheduling determination information 1100 for a job registration date stored in the data storage unit 302 of the job management server 300. The scheduling determination information 1100 for a job registration date includes columns for storing information (values), such as time 1101, previous total power consumption (kW) 1102, power consumption prediction for the registration date 1103, job registration determination priority 1104, determination 1105, and scheduling decision 1106.
[0063] In the scheduling determination information 1100 for the job registration date, information corresponding to each column related to the power consumption prediction for the job registration date is associated with each other and stored as information (records) in rows. Specifically, the time 1101 stores the time period of the time range to be determined. The total previous power consumption (kw) 1102 stores the total power consumption of each tenant TN in the associated time period last time (for example, the day before the registration date). The power consumption prediction for the registration date stores the predicted power consumption of the job in the associated time period on the registration date. The job registration determination priority 1104 stores the priority of the associated time period (priority when determining the time period to which the job is assigned). The determination 1105 stores information indicating the determination result of the error between the total previous power consumption for the associated time period and the predicted power consumption on the registration date (determination result according to the determination condition information 1000). The scheduling determination 1106 stores information (◯) indicating that the associated time period has been determined.
[0064] <Overview of operation> A user of each tenant TN operates a job creation screen 1200 of FIG. 12, which is a GUI screen displayed on the display of the user terminal 200, to register a job to be executed by each tenant TN in the job execution registration unit 122. The job creation screen 1200 is displayed, for example, on the display of the user terminal 200. FIG. 12 is a diagram for explaining an example of the job creation screen 1200. The job creation screen 1200 includes an input box 1201 for a job name, an input box 1202 for an execution registration date, an input box 1203 for an execution start time (condition 1), an input box 1204 for an execution end time (condition 2), an input box 1205 for a power type (condition 3), an input box 1206 for a priority flag, and a setting button 1207.
[0065] After the user inputs information into each of the input boxes 1201 to 1206 of the job creation screen 1200, the user operates a setting button 1207, whereby the job to be scheduled is registered in the job execution registration unit 122 with the input execution conditions.
[0066] The job management server 300 acquires condition information 900 at the time of job creation from the job execution registration unit 122 and stores it in the data storage unit 302. The job management server 300 refers to the condition information 900 at the time of job creation and performs scheduling for a plurality of jobs of each tenant TN that are the target of scheduling. At this time, the job management server 300 optimally sets the start time of the job in the scheduling based on the job execution analysis information 500, the power consumption analysis information 600, the job unit price information 700, the job power consumption prediction information 800, the condition information 900 (execution start time, execution end time, priority flag, and power type), the judgment condition information 1000, and the scheduling judgment information 1100 on the job registration date. Details of this scheduling method will be described later. The job execution analysis information 500 and the power consumption analysis information 600 are information obtained by analyzing the actual results regarding the charge amount when the job is executed and the power consumption consumed by each tenant TN, and may be referred to as "job execution analysis information" for convenience.
[0067] Before determining the final schedule, the job management server 300 checks whether each job will be completed by the execution end time (condition 2) in the schedule based on the set job start time. If the job management server 300 can confirm that each job will be completed by the execution end time in the set schedule, it determines the set schedule (confirms it as the final schedule).
[0068] <Specific operation> FIG. 13 is a flowchart showing the process flow of automatic job scheduling executed by the scheduling unit 301 of the job management server 300.
[0069] The scheduling unit 301 starts the process from step 1300 in FIG. 13, and executes the processes from step 1305 to step 1365 described below in accordance with the flowchart, and then proceeds to step 1395 to temporarily end this processing flow.
[0070] Step 1305: The scheduling unit 301 acquires the condition information 900 at the time of job creation shown in FIG. 9, thereby acquiring multiple jobs to be scheduled, the job execution time conditions (condition 1 and condition 2) of each job, the power type (condition 3), and whether or not a priority flag has been assigned (ON or OFF).
[0071] Step 1310: The scheduling unit 301 judges whether or not there is a job to which a priority flag has been assigned among the multiple jobs to be scheduled (hereinafter referred to as "jobs to be scheduled"). If there is a job to which a priority flag has been assigned, the scheduling unit 301 judges "YES" and proceeds to step 1315. If there is no job to which a priority flag has been assigned, the scheduling unit 301 judges "NO" and proceeds directly to step 1320.
[0072] Step 1315: The scheduling unit 301 sets the job start time in the scheduling for jobs to which a priority flag has been assigned as the execution start time of condition 1 for the jobs to be scheduled. As a result, for jobs to which a priority flag has been assigned, the execution start time of condition 1 is preferentially set as the job start time. Therefore, for example, if a priority flag is assigned by a user's setting operation to a job for which priority is desired for execution (e.g., a job of high importance), the job is scheduled with priority. Therefore, the job management server 300 can schedule jobs to match the user's request to prioritize the execution of jobs of high importance.
[0073] Step 1320: The scheduling unit 301 acquires the job analysis information 500 from the power consumption analysis server 130, and refers to the job analysis information 500 to determine whether or not there is a new job for which the job start time has not been set among the jobs to which a priority flag has not been assigned among the jobs to be scheduled. Note that a "new job" refers to a job for which an "identical job" or a "similar job" is not stored in the job execution analysis information 500. An "identical job" refers to a job with an exactly identical name, and a "similar job" refers to a job with a different name but with the same or similar execution conditions, such as where at least most of the execution conditions overlap.
[0074] If there is a new job whose start time has not been set, the scheduling unit 301 determines "YES" and proceeds to step 1325. If there is no new job whose start time has not been set, the scheduling unit 301 determines "NO" and proceeds to step 1330.
[0075] Step 1325: The scheduling unit 301 extracts new jobs whose start times have not been set among the jobs to be scheduled, sets the start times of the extracted new jobs by the "processing for determining the start time of a new job", and returns to step 1320. The details of the "processing for determining the start time of a new job" will be described later.
[0076] Step 1330: The scheduling unit 301 determines whether or not there is a job with the same conditions 1 and 2 among the jobs to be scheduled, other than the new job, that has no priority flag assigned thereto.
[0077] If there is a job with all the same conditions for condition 1 and condition 2, the scheduling unit 301 determines "YES" in step 1330 and proceeds to step 1335. If there is no job with all the same conditions for condition 1 and condition 2 among the jobs to be scheduled, the scheduling unit 301 determines "NO" in step 1330 and proceeds to step 1345.
[0078] Step 1335: The scheduling unit 301 sets the job execution time for jobs among the jobs to be scheduled that have the same conditions 1 and 2 by "processing for determining the start time of jobs having the same conditions 1 and 2." Details of the "processing for determining the start time of jobs having the same conditions 1 and 2" will be described later.
[0079] Step 1340: The scheduling unit 301 determines whether or not there is a job for which the job start time has not been set among the jobs to be scheduled. If there is a job for which the job start time has not been set, there remains a job for which the job start time has not been set and for which condition 1 and condition 2 are different among the jobs to be scheduled. Therefore, in this case, the scheduling unit 301 determines "YES" and proceeds to step 1345. If there is no job for which the job start time has not been set, the scheduling unit 301 determines "NO" and proceeds to step 1350.
[0080] Step 1345: The scheduling unit 301 sets the start time of a job for which condition 1 and condition 2 are different among the jobs to be scheduled by the "processing for determining the start time of a job for which condition 1 and condition 2 are different", and then proceeds to step 1350. The details of the "processing for determining the start time of a job for which condition 1 and condition 2 are different" will be described later.
[0081] Step 1350: The scheduling unit 301 refers to the power consumption analysis information 600 and determines whether there is a time slot in which the resource usage exceeds 80% (a time slot in which the power consumption exceeds 80 kW in the total power consumption (kW) of each time slot). If there is no time slot in which the resource usage exceeds 80%, the scheduling unit 301 determines "NO" and proceeds to step 1365. If there is a time slot in which the resource usage exceeds 80%, the scheduling unit 301 determines "YES" and proceeds to step 1355.
[0082] Step 1355: The scheduling unit 301 sets, among the jobs to be scheduled, jobs to which no priority flag has been assigned as "jobs of low priority."
[0083] Step 1360: The scheduling unit 301 executes a "process for determining a start time of a low priority job" for the "low priority job" set in step 1355. The "process for determining a start time of a low priority job" will be described in detail later. As a result, the start time of a job in a time period when resources are expected to be tight is set to a time that is changed from the execution start time of the job's execution conditions, thereby alleviating resource tightness.
[0084] Step 1365: The scheduling unit 301 executes "processing to confirm that job execution can be completed by the end time of execution of condition 2" for each job to be scheduled. Details of "processing to confirm that job execution can be completed by the end time of execution of condition 2" will be described later.
[0085] FIG. 14 is a flowchart showing the process flow of “processing for determining the start time of a new job” executed by the scheduling unit 301 of the job management server 300.
[0086] When the scheduling unit 301 proceeds to step 1325 in FIG. 13, it starts the "processing of determining the start time of a new job" from step 1400 in FIG. 14, and executes the processing of steps 1405 to 1435 described below in accordance with the flowchart, and then proceeds to step 1495, where it temporarily terminates this processing flow.
[0087] Step 1405: The scheduling unit 301 selects one new job whose start time has not been set from among the jobs to be scheduled.
[0088] Step 1410: The scheduling unit 301 sets the start time in the scheduling of the selected new job to the time of condition 1.
[0089] Step 1415: The scheduling unit 301 refers to the power consumption analysis information 600 in Fig. 6 and determines whether the resource usage rate exceeds 80% during the time period of condition 1 (the time period to which condition 1 applies) in the previous total power consumption. If the resource usage rate exceeds 80% during the time period of condition 1, the scheduling unit 301 determines "YES" and proceeds to step 1420. If the resource usage rate does not exceed 80% during the time period of condition 1, the scheduling unit 301 determines "NO" and proceeds to step 1435. In this case, the start time of the new job is set to the time of step 1410.
[0090] Step 1420: The scheduling unit 301 acquires, from the power consumption analysis server 300, predicted information on power consumption for job execution (job power consumption predicted information 800).
[0091] Step 1425: The scheduling unit 301 assigns the job to the time slot with the lowest power consumption among the time slots within the ranges of condition 1 and condition 2 of the selected new job in the job power consumption prediction information 800. Note that if there are multiple time slots with the same lowest power consumption, the scheduling unit 301 assigns the job to the time slot closest to the time of condition 1.
[0092] Step 1430: The scheduling unit 301 sets the start point of the time slot allocated in step 1425 as the job start time, instead of the time set in step 1410. This makes it possible to set the start time of a new job to avoid a time slot in which resources are expected to be tight.
[0093] Step 1435: The scheduling unit 301 judges whether or not the job start times have been set for all new jobs among the jobs to be scheduled. If the job start times have not been set for all new jobs, the scheduling unit 301 judges "NO" and returns to step 1405. If the job start times have been set for all new jobs, the scheduling unit 301 judges "YES" and proceeds to step 1495.
[0094] 15 is a flowchart showing the process flow of "processing for determining the start time of a job with the same conditions 1 and 2" executed by the scheduling unit 301 of the job management server 300. In this process flow, for jobs to be scheduled that have the same execution start condition and execution end condition, the process sets the job start time and determines the priority order indicating the order in which the job execution is to be prioritized.
[0095] In this process, job start times are set for multiple jobs other than new jobs that are scheduled and have the same conditions 1 and 2, and priorities are assigned to each of the multiple jobs with the same conditions.
[0096] When the scheduling unit 301 proceeds to step 1335 in FIG. 13, it starts the "process of determining the start time of a job in which conditions 1 and 2 are the same" from step 1500 in FIG. 15, and executes the processes of steps 1505 to 1550 described below in accordance with the flowchart, and then proceeds to step 1595 and temporarily ends this processing flow.
[0097] Step 1505: The scheduling unit 301 selects a set of jobs having the same condition 1 and condition 2 from among the jobs to be scheduled.
[0098] Step 1510: The scheduling unit 301 acquires the job unit price information 700 of Fig. 7 from the power consumption analysis server 130, acquires the unit price of one job for each power type from the job unit price information 700, and prioritizes the jobs with the same selected conditions 1 and 2 so that the power type with the highest unit price is given priority. According to the job unit price information 700 of Fig. 7, the unit price of one job is highest in the following order: renewable energy > private power generation > power company supplied power > power supply power (surplus power), so the priorities are assigned in this order. In other words, the priority is assigned so that the power type with the greatest contribution to ecology has a higher priority.
[0099] Step 1515: The scheduling unit 301 determines whether or not there are multiple jobs with the same power type and priority set among the multiple jobs with the same selected conditions 1 and 2. If there are no jobs with the same power type and priority set, the result is determined as "NO" and the process proceeds to step 1545. If there are multiple jobs with the same selected conditions 1 and 2 and the same power type and priority set, the process is determined as "YES" and the process proceeds to step 1520.
[0100] Step 1520: The scheduling unit 301 acquires the billing amount from the job execution analysis information 500 for each of the multiple jobs for which the same power type is set.
[0101] Step 1525: The scheduling unit 301 prioritizes a plurality of jobs for which the same power type is set in the order of the highest charge amount.
[0102] Step 1530: The scheduling unit 301 determines whether there are jobs with the same prioritized power type set and a job charge difference of less than 10%. If there are no jobs with a job charge difference of less than 10%, the scheduling unit 301 determines "NO" and proceeds to step 1545. If there are jobs with a job charge difference of less than 10%, the scheduling unit 301 determines "YES" and proceeds to step 1535.
[0103] Step 1535: The scheduling unit 301 acquires information on average power consumption from the job execution analysis information 500 for each of the multiple jobs whose job charge difference is less than 10%.
[0104] Step 1540: The scheduling unit 301 prioritizes jobs whose job charge amounts differ by less than 10% so that jobs with lower average power consumption are prioritized.
[0105] Step 1545: For each of a plurality of jobs for which condition 1 and condition 2 are the same, the scheduling unit 301 sets the job start time under condition 1 and determines the final priority. This priority is used in the step processing of FIG. 17, which will be described later.
[0106] Step 1550: The scheduling unit 301 judges whether or not there is a group of jobs that have the same conditions 1 and 2 and whose job start times are not set among the jobs to be scheduled. If there is a group of jobs that have the same conditions 1 and 2 and whose job start times are not set among the jobs to be scheduled, the scheduling unit 301 judges "YES" and returns to step 1505. If there is no group of jobs that have the same conditions 1 and 2 and whose job start times are not set among the jobs to be scheduled, the scheduling unit 301 judges "NO" and proceeds to step 1595.
[0107] 16 is a flowchart showing the process flow of "processing to determine the start time of a job with different conditions, condition 1 and condition 2," executed by the scheduling unit 301 of the job management server 300. Note that, if the result of the determination in step 1340 is "NO" and the process proceeds to step 1345, the remaining jobs among the jobs to be scheduled whose start times have not been set are scheduled in this "processing to determine the start time of a job with different conditions, condition 1 and condition 2."
[0108] When the scheduling unit 301 proceeds to step 1345 in FIG. 13, it starts the "process of determining the start time of a job where condition 1 and condition 2 are different" from step 1600 in FIG. 16, and executes the processes of steps 1605 to 1645 described below in accordance with the flowchart, and then proceeds to step 1695 and temporarily ends this processing flow.
[0109] Step 1605: The scheduling unit 301 selects one job whose start time has not been set from among the jobs to be scheduled.
[0110] Step 1610: The scheduling unit 301 acquires the scheduling determination information 1100 for the job registration date. The scheduling unit 301 refers to the power consumption analysis information 600 and updates the value of the previous total power consumption (kw) 1102 in the scheduling determination information 1100 for the job registration date.
[0111] Step 1615: The scheduling unit 301 assigns the job registration determination priority of 1 to 5 for the selected job, based on "time of condition 1 > time of low power consumption", to the time period within the time range of the execution conditions of the selected job (time range between condition 1 and condition 2). The smaller the number among 1 to 5, the higher the priority. That is, as shown in FIG. 11, the job registration determination priority is assigned (stored) to the row corresponding to the time period of the job registration priority 1104 of the scheduling determination information 1100 on the job registration date. When assigning 1 to 5 to the time periods according to "time of condition 1 > time of low power consumption", first, 1 is assigned to the time period corresponding to the time of condition 1. Next, 2 to 5 are assigned in the order of the time period with the lowest power consumption of the total power consumption (kw) 602. In this case, if there are multiple time periods with the same power consumption, the higher priority is assigned to the time period closer to the time period of condition 1.
[0112] Step 1620: The scheduling unit 301 acquires predicted information on power consumption for job execution (predicted information on power consumption for job execution (job power consumption predicted information 800)) from the power consumption analysis server 130. The scheduling unit 301 updates the value of the power consumption prediction 1103 on the registration date of the scheduling determination information 1100 on the job registration date based on the acquired predicted information on power consumption for job execution.
[0113] Step 1625: The scheduling unit 301 refers to the scheduling judgment information 1100 on the job registration date, and calculates the error threshold between the previous power consumption information and the power consumption prediction information on the registration date (= “power consumption prediction (kw) on the registration date” - “total power consumption (kw) of the previous date”).
[0114] Step 1630: The scheduling unit 301 judges whether the judgment condition of the error threshold for the time period corresponding to the current job registration judgment priority (judgment type of the judgment condition information 1000) is "o" and the power consumption is 80 kW or less. The job registration judgment priority in the first judgment is "1". If the judgment condition of the error threshold for the time period corresponding to the job registration judgment priority is not "o", or the power consumption is not 80 kW or less, or both, the scheduling unit 301 judges "NO" and proceeds to step 1635. If the judgment condition of the error threshold for the time period corresponding to the current job registration judgment priority is "o" and the power consumption is 80 kW or less, the scheduling unit 301 judges "YES" and proceeds to step 1640.
[0115] Step 1635: The scheduling unit 301 increments the current job registration determination priority by “1” and returns to step 1630.
[0116] Step 1640: The scheduling unit 301 sets the start point of the time period for which the judgment condition is "◯" as the job start time of the selected job.
[0117] Step 1645: The scheduling unit 301 judges whether or not there is a job whose start time has not been set among the jobs to be scheduled. If there is a job whose start time has not been set, the scheduling unit 301 judges "YES" and returns to step 1605. If there is no job whose start time has not been set, the scheduling unit 301 judges "NO" and proceeds to step 1695.
[0118] FIG. 17 is a flowchart for explaining the "processing for determining the start time of a job with a low priority" executed by the scheduling unit 301.
[0119] For convenience of explanation, jobs that have the same conditions 1 and 2 among the jobs to be scheduled will be referred to as "overlapping jobs" below.
[0120] In this "process to determine the start time of a low priority job", in order to prevent resource congestion, for overlapping jobs that do not have a priority flag (low priority) during a time period in which the total power consumption (kW) 602 in the power consumption analysis information 600 exceeds 80 kW, the start time of the job is set based on the priority (the priority assigned (set) to the job in the process of Figure 17).
[0121] When the scheduling unit 301 proceeds to step 1345 in FIG. 13, it starts the "processing for determining the start time of a low priority job" from step 1700 in FIG. 17, and executes the processing of steps 1705 to 1765 described below in accordance with the flowchart, and then proceeds to step 1795 to temporarily end this processing flow.
[0122] Step 1705: The scheduling unit 301 extracts overlapping jobs without a priority flag in a time period exceeding 80 kW.
[0123] Step 1710: The scheduling unit 301 selects a set of unselected overlapping jobs from the extracted overlapping jobs.
[0124] Step 1715: The scheduling unit 301 selects the job with the lowest priority among the selected overlapping jobs.
[0125] Step 1720: The scheduling unit 301 refers to the job execution analysis information 500, and changes the job start time of the selected low priority job to the time immediately after the previous execution completion time of the high priority job.
[0126] Step 1725: The scheduling unit 301 refers to the power consumption analysis information 600 and determines (confirms) whether the total power consumption during the time period of the changed job start time exceeds 80 kW (resource usage rate of 80%). If the resource usage rate does not exceed 80%, the scheduling unit 301 determines "NO" and proceeds to step 1760. If the resource usage rate exceeds 80%, the scheduling unit 301 determines "YES" and proceeds to step 1730.
[0127] Step 1730: The scheduling unit 301 acquires the scheduling determination information 1100 for the job registration date. The scheduling unit 301 refers to the power consumption analysis information 600 and updates the value of the previous total power consumption (kw) 1102 in the scheduling determination information 1100 for the job registration date.
[0128] Step 1735: The scheduling unit 301 assigns job registration determination priorities from 1 to 5 in ascending order of power consumption to the time slots in the time range of the execution conditions of the overlapping jobs (the time range between condition 1 and condition 2). The scheduling unit 301 updates the job registration determination priority 1104 in the scheduling determination information 1100 for the job registration date with the assigned value.
[0129] Step 1740: Obtain predicted information on power consumption for job execution (predicted information on power consumption for job execution (job power consumption predicted information 800)) from the power consumption analysis server 130. The scheduling unit 301 updates the value of the power consumption prediction 1103 on the registration date of the scheduling determination information 1100 on the job registration date based on the obtained predicted information on power consumption for job execution.
[0130] Step 1745: The scheduling unit 301 refers to the scheduling decision information 1100 for the job registration date, and calculates the error threshold value between the previous power consumption information for the time period corresponding to the job registration priority and the power consumption prediction information for the registration date (= "power consumption prediction for the registration date (kW)" - "total power consumption for the previous date (kW)").
[0131] Step 1750: The scheduling unit 301 judges whether the judgment condition of the error threshold corresponding to the job registration judgment priority (judgment type of the judgment condition information 1000) is "O" or not. Note that the job registration judgment priority in the first judgment is "1". If the judgment condition of the error threshold corresponding to the job registration judgment priority is not "O", the scheduling unit 301 judges "NO" and proceeds to step 1755. If the judgment condition of the error threshold corresponding to the job registration judgment priority is "O", the scheduling unit 301 judges "YES" and proceeds to step 1760.
[0132] Step 1755: The scheduling unit 301 increments the current job registration determination priority by “1” and returns to step 1750.
[0133] Step 1760: For the selected job with the lowest priority, the scheduling unit 301 sets the start point of the time period for which the judgment condition is "○" in step 1750 as the job start time. Note that if the scheduling unit 301 judges "NO" in step 1725 and proceeds to this step, for the job whose start time was changed in step 1720, it sets the job start time to the changed start time.
[0134] Step 1765: The scheduling unit 301 judges whether or not all pairs of overlapping jobs without a priority flag have been selected. If all pairs of overlapping jobs without a priority flag have not been selected, the result is judged as "NO" and the process returns to step 1705. If all pairs of overlapping jobs without a priority flag have been selected, the result is judged as "YES" and the process proceeds to step 1795.
[0135] 18 is a flowchart for explaining the "processing to confirm that job execution can be completed by the end time of execution of condition 2" executed by the scheduling unit 301. In the "processing to confirm that job execution can be completed by the end time of execution of condition 2", it is confirmed whether each job to be scheduled will be completed by the end time of execution of condition 2, at the job start time set for each of the jobs to be scheduled by the above-mentioned processing. In other words, it is confirmed whether each of the jobs to be scheduled that have been scheduled by the above-mentioned processing will be completed by the end time of execution of condition 2.
[0136] When the scheduling unit 301 proceeds to step 1365 in FIG. 13, it starts "processing to confirm that job execution can be completed by the end time of execution of condition 2" from step 1800 in FIG. 18, and after executing the processing of steps 1805 to 1845 described below in accordance with the flowchart, it proceeds to step 1895 and temporarily ends this processing flow.
[0137] Step 1805: The scheduling unit 301 acquires the job registration time (the job start time set for each job to be scheduled). Step 1810 : The scheduling unit 301 acquires the average execution time of the job from the job execution analysis information 500 .
[0138] Step 1815: The scheduling unit 301 calculates a predicted job execution end time on the job registration date based on the job registration time and the average execution time.
[0139] Step 1820: The scheduling unit 301 judges whether the predicted job execution end time on the job registration date falls within the execution end time of condition 2. If the predicted job execution end time on the job registration date is not within the execution end time of condition 2, the scheduling unit 301 judges "NO" and proceeds to step 1825. If the predicted job execution end time on the job registration date falls within the execution end time of condition 2, the scheduling unit 301 judges "YES" and proceeds to step 1835.
[0140] Step 1825: The scheduling unit 301 cancels job registration for the job that is determined not to fall within the execution end time of the condition 2.
[0141] Step 1830: The scheduling unit 301 notifies the user to change condition 1 and condition 2 for the job determined not to fall within the execution end time of condition 2. Note that the user can cause the scheduling unit 301 to change at least one of condition 1 and condition 2 of the target job to the input changed time by, for example, inputting the changed time into an input screen displayed on the display of the user terminal 200.
[0142] Step 1835: The scheduling unit 301 determines (confirms) the schedule of the job at the set start time of the job.
[0143] FIG. 19 is a diagram for explaining an example of a report screen of a job execution result. The report screen 1900 includes a date display field 1901, a charge amount display field 1902, a power consumption display field 1903, a selection option display input field 1904, a power type usage ratio graph 1905, a charge breakdown table 1906, and an execution button 1907. The date display field 1901 displays a period for which job execution is analyzed. The charge amount display field 1902 displays a job charge amount for the period for which job execution is analyzed. The power consumption display field 1903 displays power consumption for the period for which job execution is analyzed. The selection option display input field 1904 displays an input selection option. The power type usage ratio graph 1905 is a graph showing the usage ratio of the power type used in the execution of a job during the period for which job execution is analyzed. The charge breakdown table 1906 is a table showing the job charge amount, the job charge amount, the power consumption, and the power consumption ratio for each power type. The execute button 1907 is a button formed of an image, and is operated (pressed) to cause the job management server 300 to execute a schedule change.
[0144] When an execute button 1907 is operated, scheduling (rescheduling) is executed according to the option entered and displayed in the selected option display input field 1904. In this example, three options can be entered: (1) billing amount reduction, (2) power consumption reduction, and (3) power type eco mode. (1) When a charge reduction is selected and executed, job scheduling (rescheduling) is performed so that the charge is reduced, and the resulting schedule is proposed. (2) Once power consumption reduction is selected and implemented, job scheduling (rescheduling) is performed to reduce power consumption, and a resulting schedule is proposed. (3) When the power type eco mode is selected and executed, job scheduling (rescheduling) is performed so that the eco contribution is high, and the resulting schedule is proposed.
[0145] Fig. 20 is a diagram for explaining an example of a report screen that is displayed after selecting and executing a selection option ((1) Charge reduction) on the report screen of Fig. 19. A report screen 2000 includes a selection option display field 2001, a changed job display field 2002, a charge reduction forecast display field 2003, a job change content table 2004, and an execute button 2005.
[0146] The selected option display field 2001 displays the selected option that has been executed. The changed job display field 2002 displays the name of the job whose execution conditions will be changed by executing the selected option. The predicted charge reduction display field 2003 displays the predicted charge reduction amount that will be reduced by executing the selected option. The job change details table 2004 displays information after the change regarding the job whose execution conditions have been changed. The execute button 2005 is a button made up of an image, and is operated to confirm (register) the job schedule after it has been changed by the job management server 300 in the job execution registration unit 122.
[0147] Fig. 21 is a diagram illustrating an example of a report screen that is displayed after selecting and executing a selection option ((2) Power consumption reduction) on the report screen of Fig. 19. A report screen 2100 includes a selection option display field 2101, a changed job display field 2102, a power consumption reduction prediction display field 2103, a job change content table 2104, and an execute button 2105.
[0148] The selected option display field 2101 displays the selected option that has been executed. The changed job display field 2102 displays the name of the job whose execution conditions will be changed by executing the selected option. The predicted power consumption reduction display field 2103 displays the predicted amount of power consumption that will be reduced by executing the selected option. The job change content table 2104 displays information after the change regarding the job whose execution conditions will be changed. The execute button 2105 is a button made up of an image, and is operated to confirm (register) the job schedule after it has been changed by the job management server 300 in the job execution registration unit 122.
[0149] Fig. 22 is a diagram illustrating an example of a report screen that is displayed after selecting and executing a selection option ((3) power type eco mode) on the report screen of Fig. 19. A report screen 2200 includes a selection option display field 2201, a changed job display field 2202, a changed power type display field 2203, a job change content table 2204, a changed power type usage ratio graph 2205, a changed power type usage ratio table 2206, and an execute button 2207.
[0150] The selected option display field 2201 displays the selected option that has been executed. The changed job display field 2202 displays the name of the job whose execution conditions are changed by executing the selected option. The changed power type display field 2203 displays the power type to be changed. The job change content table 2204 displays information after the change regarding the job whose execution conditions are changed. The changed power type usage ratio graph 2205 is a graph showing the changed power type usage ratio (prediction of the power type usage ratio for the next month). The changed power type usage ratio table 2206 displays information showing the actual power type usage ratio (actual power consumption ratio for this month) and the predicted power consumption (prediction of the power consumption ratio for the next month). The execute button 2207 is a button formed of an image, and is operated to confirm (register) the schedule of the job after it has been changed by the job management server 300 in the job execution registration unit 122.
[0151] Fig. 23 is a flowchart for explaining a selection option execution process executed by the scheduling unit 301 of the job management server 300. The scheduling unit 301 starts the process from step 1800 in Fig. 23, and executes the processes of steps 2305 to 2340 described below according to the flowchart, and then proceeds to step 2395 to temporarily end this processing flow.
[0152] Step 2305: The scheduling unit 301 acquires report information for creating the report screen 1900 of the tenant TN for which a report is to be created.
[0153] Step 2310: The scheduling unit 301 displays the report screen 1900 on the user terminal 200 of the user corresponding to the tenant TN for which the report is to be created.
[0154] Step 2315: The scheduling unit 301 judges whether or not the execute button 1907 has been operated with the proposed option selected (input). If the execute button 1907 has not been operated with the proposed option selected (input), the scheduling unit 301 judges as "NO" and proceeds to step 2320. If the execute button 1907 has been operated with the proposed option selected (input), the scheduling unit 301 judges as "YES" and proceeds to step 2325.
[0155] Step 2320: The scheduling unit 301 temporarily ends this processing flow.
[0156] Step 2325: The scheduling unit 301 determines which proposed option has been selected (input) at the time the execute button 1907 is operated. If "(1) Reduce billing amount" has been selected (input), the scheduling unit 301 proceeds to step 2330. If "(2) Reduce power consumption" has been selected (input), the scheduling unit 301 proceeds to step 2335. If "(3) Power type eco mode" has been selected (input), the scheduling unit 301 proceeds to step 2340.
[0157] Step 2330: The scheduling unit 301 executes “processing for determining a job start time in '(1) reducing the charge amount'.” Details of the “processing for determining a job start time in '(1) reducing the charge amount'” will be described later.
[0158] Step 2335: The scheduling unit 301 executes “processing for determining a job start time in '(2) power consumption reduction'”. Details of the “processing for determining a job start time in '(2) power consumption reduction'” will be described later.
[0159] Step 2340: The scheduling unit 301 executes “processing for determining a job start time in '(3) power type eco mode'”. Details of the “processing for determining a job start time in '(3) power type eco mode'” will be described later.
[0160] Fig. 24 is a flowchart for explaining the "processing for determining the job start time in '(1) Charge reduction'" executed by the scheduling unit 301 of the job management server 300. When the scheduling unit 301 proceeds to step 2330 in Fig. 23, it starts the "processing for determining the job start time in '(1) Charge reduction'" from step 2400 in Fig. 24, and executes the processes of steps 2405 to 2450 described below according to the flowchart, and then proceeds to step 2495 to temporarily end this processing flow.
[0161] Step 2405: The scheduling unit 301 acquires the job execution analysis information 500 from the power consumption analysis server 130.
[0162] Step 2410: The scheduling unit 301 acquires scheduled jobs from the job execution registration unit 122 corresponding to the tenant TN for which a report is to be created, and extracts jobs to which no priority flag has been assigned from among the scheduled jobs.
[0163] Step 2415: The scheduling unit 301 extracts jobs whose execution conditions include the power type "renewable energy" from among the jobs to which no priority flag has been assigned.
[0164] Step 2420: The scheduling unit 301 changes the type of power in the execution conditions of the job to which the priority flag is not assigned, extracted in step 2415, from “renewable energy” to “power company supplied power” (i.e., a type of power with a lower unit price than the current price of the job).
[0165] Step 2425: The scheduling unit 301 acquires the power consumption analysis information 600 from the power consumption analysis server 130.
[0166] Step 2430: The scheduling unit 301 assigns the job with the changed execution conditions to a time period in which power consumption is lower than the current time period (that is, the execution start time of the job is changed to the start point of a time period in which power consumption is lower than the current time period).
[0167] Step 2435: The scheduling unit 301 calculates a billing amount forecast (billing amount reduction forecast), and displays it on the report screen 2000 of FIG.
[0168] Step 2440: The scheduling unit 301 displays job candidates for changing the job start time (jobs that do not have a priority flag and whose power type is “renewable energy”) on the report screen 2000 (e.g., the changed job display field 2002 and the job change details table 2004).
[0169] Step 2445: The scheduling unit 301 judges whether or not the execute button 2005 has been pressed (operated) on the report screen 2000. If the execute button 2005 has been pressed on the report screen 2000, the scheduling unit 301 judges "YES" and proceeds to step 2450. If the execute button 2005 has not been pressed on the report screen 2000, the scheduling unit 301 judges "NO" and proceeds to step 2495.
[0170] Step 2450: The scheduling unit 301 sets the job start time to the changed job execution start time for the job to which no priority flag has been assigned, and finalizes the schedule.
[0171] Fig. 25 is a flowchart for explaining the process of determining the job start time in "(2) Power consumption reduction" executed by the scheduling unit 301 of the job management server 300. When the scheduling unit 301 proceeds to step 2335 in Fig. 23, it starts "process of determining the job start time in "(2) Power consumption reduction"" from step 2500 in Fig. 25, and executes the processes of steps 2505 to 2540 described below according to the flowchart, and then proceeds to step 2595 to temporarily end this processing flow.
[0172] Step 2505: The scheduling unit 301 acquires the job execution analysis information 500 from the power consumption analysis server 130.
[0173] Step 2510: The scheduling unit 301 acquires scheduled jobs from the job execution registration unit 122 corresponding to the tenant TN for which a report is to be created, and extracts jobs to which no priority flag has been assigned from among the scheduled jobs.
[0174] Step 2515: The scheduling unit 301 acquires the power consumption analysis information 600 from the power consumption analysis server 130.
[0175] Step 2520: The scheduling unit 301 refers to the power consumption analysis information 600 and extracts, from the jobs that do not have a priority flag assigned, jobs that correspond to a time period in which the total power consumption of the multi-tenant server 100 is 50 kW or more (resource utilization rate of 50% or more).
[0176] Step 2525: The scheduling unit 301 allocates the extracted job to a time period in which power consumption is lower than that of the current time period (that is, the execution start time of the job is changed to the start point of a time period in which power consumption is lower than that of the current time period).
[0177] Step 2530: The scheduling unit 301 calculates the changed power consumption prediction, and displays it on the report screen 2100 of FIG.
[0178] Step 2535: The scheduling unit 301 displays the job start time change candidate jobs on the report screen 2100 (for example, the changed job display field 2102 and the job change content table 2104).
[0179] Step 2540: The scheduling unit 301 judges whether or not the execute button 2105 has been pressed (operated) on the report screen 2100. If the execute button 2105 has been pressed on the report screen 2100, the scheduling unit 301 judges "YES" and proceeds to step 2545. If the execute button 2105 has not been pressed on the report screen 2100, the scheduling unit 301 judges "NO" and proceeds to step 2595.
[0180] Step 2545: The scheduling unit 301 sets the job start time to the changed job execution start time for the job to which no priority flag has been assigned, and finalizes the schedule.
[0181] Fig. 26 is a flowchart for explaining the process of determining the start time of a job in "(3) power type eco mode" executed by the scheduling unit 301 of the job management server 300. When the scheduling unit 301 proceeds to step 2340 in Fig. 23, it starts "process of determining the start time of a job in '(3) power type eco mode'" from step 2600 in Fig. 26, and executes the processes of steps 2605 to 2645 described below according to the flowchart, and then proceeds to step 2695 to temporarily end this processing flow.
[0182] Step 2605: The scheduling unit 301 acquires the job execution analysis information 500 from the power consumption analysis server 130.
[0183] Step 2610: The scheduling unit 301 acquires scheduled jobs from the job execution registration unit 122 corresponding to the tenant TN for which a report is to be created, and extracts jobs to which no priority flag has been assigned from among the scheduled jobs.
[0184] Step 2615: The scheduling unit 301 acquires the power consumption analysis information 600 from the power consumption analysis server 130.
[0185] Step 2620: The scheduling unit 301 extracts jobs whose execution conditions include the power type "power company supply" from among the jobs to which no priority flag has been assigned.
[0186] Step 2625: The scheduling unit 301 changes the power type in the execution conditions of the jobs extracted in step 2620 that do not have a priority flag from “power company supplied power” to “renewable energy” (i.e., a power type with a greater eco-contribution than the current one).
[0187] Step 2630: The scheduling unit 301 calculates a predicted power consumption ratio for each power type after the change, and displays it on the report screen 2200 (for example, the power type usage ratio graph 2205 after the change and the power type usage ratio table 2206 after the change).
[0188] Step 2635: The scheduling unit 301 displays job candidates for changing the job start time (jobs that do not have a priority flag and whose power type is “power company supplied power”) on the report screen 2200 (e.g., the changed job display field 2202 and the job change details table 2204).
[0189] Step 2640: The scheduling unit 301 determines whether or not the execute button 2207 has been pressed (operated) on the report screen 2200. If the execute button 2207 has been pressed on the report screen 2200, the scheduling unit 301 determines "YES" and proceeds to step 2645. If the execute button 2207 has not been pressed on the report screen 2200, the scheduling unit 301 determines "NO" and proceeds to step 2595.
[0190] Step 2645: The scheduling unit 301 finalizes the schedule (changed power type) for the job to which no priority flag is assigned.
[0191] <Effects> As described above, the job management device according to an embodiment of the present invention schedules jobs so that, for jobs whose execution times overlap during time periods when resources may be tight, the execution start time of a lower priority job is changed to a time between the execution start time and execution end time.
[0192] This allows the job management device to schedule jobs so that limited resources shared by users in a multi-tenant environment are not strained and so that job end times are respected. Furthermore, the job management device can schedule jobs to meet user requests for priority execution of jobs with high importance.
[0193] The job management device confirms whether the execution of each job is completed by the execution end time of each job in the job schedule set by the scheduling, and then determines the job schedule, so that the job can be scheduled so as to keep to the job end time requested by each user.
[0194] The job management device reschedules jobs according to the options selected by the user. This allows the job management device to schedule jobs to match a user request for prioritizing reduction in billing amounts, a user request for prioritizing reduction in power consumption, and a user request for prioritizing eco. The job management device can contribute to reducing power consumption because it can accommodate a user request for prioritizing reduction in power consumption. The job management device can also accommodate a user request for prioritizing eco, thereby contributing to reducing CO2 emissions and saving power.
[0195] <<Modifications>> The present invention is not limited to the above embodiment, and various modifications can be adopted within the scope of the present invention. The job management server 300 may be located inside the multi-tenant server 100 or on a cloud.
[0196] In the above embodiment, the job management server 300 may schedule jobs as follows.
[0197] Based on the power consumption analysis information 600, the job management server 300 extracts jobs from among the jobs to be scheduled, excluding new jobs whose execution start time (condition 1) falls within a time period exceeding 80 kW. If the extracted jobs include both jobs with and without a priority flag, the job management server 300 sets the execution start time (condition 1) of the jobs with a priority flag to the job start time in the scheduling. For jobs without a priority flag, the job start time is set by the process of FIG. 16 described above.
[0198] If the extracted jobs include only jobs to which a priority flag has been assigned, the job management server 300 determines the job for which the execution start time (condition 1) is to be prioritized based on at least one of the power type, the billing amount, and the power consumption.
[0199] For jobs that are to be prioritized, the execution start time (condition 1) is set to the job start time in the schedule. For jobs that are not to be prioritized, the job start time is set by the process of FIG.
[0200] If the extracted jobs include only jobs to which no priority flag has been assigned, the job management server 300 determines the job to be prioritized in terms of execution start time (condition 1) based on at least one of the power type, billing amount, and power consumption.
[0201] For jobs that are to be prioritized, the execution start time (condition 1) is set to the job start time in the schedule. For jobs that are not to be prioritized, the job start time is set by the process of FIG.
[0202] In the above variant, when determining which job should have a priority in terms of execution start time (condition 1) based on all of the power type, charge, and power consumption, the job management server 300 may determine the priority of the job by the process shown in Figure 15 described above.
[0203] In the above embodiment, instead of step 1360, the job management server 300 may allow the user to manually set the start time of a job set as a "job of low priority." [Explanation of symbols]
[0204] 100... multi-tenant server, 120a to 120c... virtual servers, 121a to 121c... power consumption information unit, 122a to 122c... job execution registration unit, 123a to 123c... execution control unit, 130... power consumption analysis server, 131... power consumption information acquisition unit, 132... analysis unit, 133... billing unit, 134... data storage unit, 140... power management server, 141... power type discrimination unit, 142... power acquisition unit, 160... storage battery, 200a to 200c... user terminal, 300... job management server, 301... scheduling unit, 302... data storage unit
Claims
1. A job management device including an information processing device that schedules jobs to be executed by each tenant of a multi-tenant server, The information processing device includes: Acquire job execution conditions including execution time conditions regarding the execution start time and execution end time of the job of each tenant and a priority flag indicating whether or not to prioritize the job execution, and job execution analysis information obtained by analyzing the job execution results; scheduling the job based on the job execution conditions and the job execution analysis information; It was configured as follows: Job management device.
2. 2. The job management device according to claim 1, The information processing device includes: scheduling the job such that, when the priority flag of the execution conditions of the job indicates that the job execution is to be prioritized, the execution start time of the job is set as the start time of the job with priority; It was configured as follows: Job management device.
3. 3. The job management device according to claim 2, The job execution conditions include a type of power used to execute the job, The job execution analysis information includes information obtained by analyzing a billing amount when the job is executed and a performance record regarding power consumption consumed by each of the tenants, The information processing device includes: For the jobs with overlapping execution time conditions, the priority flags do not indicate that the job execution is to be prioritized, determining a priority based on at least one of the power type of the job, the charge for the job based on the job execution analysis information, and the power consumption amount of the job based on the job execution analysis information, and scheduling the job such that the execution start time of the job having the high priority is preferentially set as the start time of the job; It was configured as follows: Job management device.
4. 4. The job management device according to claim 3, The information processing device includes: When the priority is determined based on the power type of the jobs with overlapping execution time conditions, the priority is determined so that a job with a power type that contributes more to ecology has a higher priority. It was configured as follows: Job management device.
5. 4. The job management device according to claim 3, The information processing device includes: When the priority is determined based on the charge amount for the jobs having the same execution time condition, the priority is determined such that the job having a higher charge amount has a higher priority. It was configured as follows: Job management device.
6. 4. The job management device according to claim 3, The information processing device includes: When the priority is determined based on the power consumption of the jobs having the overlapping execution time conditions, the priority is determined such that the job having the lower power consumption has a higher priority. It was configured as follows: Job management device.
7. 4. The job management device according to claim 3, The information processing device includes: When the priority is determined based on all of the power type of the job, the charge for the job, and the power consumption of the job, the priority is determined based on the power type, the charge for the job, and the power consumption of the job in a predetermined order; If the priority is not assigned in each determination performed in a predetermined order, the priority is assigned to the job not assigned in the next determination in the order. It was configured as follows: Job management device.
8. 4. The job management device according to claim 3, The information processing device includes: changing an execution start time of the job having a lower priority and setting the changed time as a start time of the job, thereby scheduling the job. It was configured as follows: Job management device.
9. 9. The job management device according to claim 8, The information processing device includes: setting a start time of the job having a low priority to a time period during which the total power consumption of each of the tenants based on the job execution analysis information is relatively low; It was configured as follows: Job management device.
10. 10. The job management device according to claim 9, the information processing device predicts a total power consumption of each of the tenants for each time period, and sets a job start time to a time period in which an error between the predicted total power consumption and a previous total power consumption of each of the tenants based on the job execution analysis information satisfies a predetermined condition; It was configured as follows: Job management device.
11. 3. The job management device according to claim 2, The job execution conditions include a type of power used to execute the job, The job execution analysis information includes information obtained by analyzing a billing amount when the job is executed and a performance record regarding power consumption consumed by each of the tenants, The information processing device includes: extracting, from among the jobs to be scheduled based on the job execution analysis information, a job whose execution start time falls within a time period in which the total power consumption of each of the tenants based on the job execution analysis information is higher than a predetermined power consumption; Regarding the extracted job, determining a priority based on at least one of the priority flag, the power type of the job, the charge for the job based on the job execution analysis information, and the power consumption amount of the job based on the job execution analysis information, and scheduling the job such that the execution start time of the job with the highest priority is preferentially set as the start time of the job; It was configured as follows: Job management device.
12. 2. The job management device according to claim 1, The information processing device includes: In the job scheduling, checking whether the scheduled job will be completed by the execution end time; It was configured as follows: Job management device.
13. 4. The job management device according to claim 3, the information processing device displays a proposal report screen, which analyzes the execution result of the job, on a display device capable of displaying images. It was configured as follows: Job management device.
14. 14. The job management device according to claim 13, The information processing device includes: connected to an information input device into which information can be input by a user; the information processing device reschedules a scheduled job according to any one of charge amount reduction priority scheduling, power consumption reduction priority scheduling, and eco priority scheduling in response to a request based on information input to the information input device; It is configured as follows: when scheduling jobs using charge reduction priority scheduling, the information processing device reschedules jobs such that the charge amount is reduced for jobs whose priority flags do not indicate that the job execution is to be prioritized; When scheduling jobs with power consumption reduction priority scheduling, rescheduling the jobs so that the power consumption is reduced for the jobs whose priority flags do not indicate that the job execution is to be prioritized; When scheduling jobs with eco-priority scheduling, rescheduling jobs for which the priority flag does not indicate that the job execution is to be prioritized by changing the power type of the job execution conditions to a power type that contributes more to ecology. Job management device.
15. A job management method using an information processing device that schedules jobs to be executed by each tenant of a multi-tenant server, comprising: By the information processing device, Acquire job execution conditions including execution time conditions regarding the execution start time and execution end time of the job of each tenant and a priority flag indicating whether or not to prioritize the job execution, and job execution analysis information obtained by analyzing the job execution results; scheduling the job based on the job execution conditions and the job execution analysis information; Job management methods.
Citation Information
Patent Citations
Task scheduling method and device and storage medium
CN111221631A
Queue scheduling method, device and system based on multi-tenant technology
CN113986497A
Computer system and task executing method of computer system
JP2017091330A
Systems and methods for dynamic scheduling of data processing
US20220083376A1
Workflow-based scheduling and batching in multi-tenant distributed systems
US20220276893A1