Construction management system

The construction management system simplifies data input and management by using layered block units and web applications, addressing complexity issues and enabling widespread use without specialized hardware.

JP2024158409APending Publication Date: 2024-11-08KUMAGAI GUMI CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
JP2023073576
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-27
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

Conventional construction management systems face difficulties in managing construction data due to the complexity of linking voxel blocks, requiring special software and high-performance PCs, making it difficult for on-site users to input and output construction data, and limiting dissemination.

Method used

A construction management system that manages construction data in units of layered blocks defined by construction thickness and horizontal contours, using a web application to input and present construction status, allowing easy data input and management via a user terminal without specialized software or high-performance computers.

Benefits of technology

Enables easy input and management of construction data according to progress, simplifies operations, and allows widespread use by users with standard devices, enhancing efficiency and accessibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024158409000001_ABST
    Figure 2024158409000001_ABST
Patent Text Reader

Abstract

To easily input construction data according to the progress of a construction object, and to manage the construction object according to the progress.SOLUTION: A construction management system 1 that manages the construction of building and civil engineering projects, comprises: a management server 2 for managing a construction target with construction data in a unit of a layered block defined by a predetermined construction thickness and a horizontal outline according to a construction progress, and presenting the construction status of the construction target based on the construction data by a web application; and a user terminal 4 for enabling input of the construction data for each block constituting the construction target to the management server 2 in response to a user operation and receiving the presentation of the construction status from the management server 2.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a construction management system for managing construction work in construction and civil engineering projects. [Background technology]

[0002] In construction management systems that manage construction in construction and civil engineering projects, BIM / CIM (Building / Construction Information Modeling) is applied to share construction data at each stage, such as planning, investigation, design, construction, and management, in order to improve the efficiency of production and management systems.

[0003] Patent Document 1 relates to information processing technology for displaying structures to be constructed in a construction project, and discloses a program for causing a computer to function as a display data generation means which extracts from the plan data a plan storage means which stores plan data including the planned period for each work item of the construction project, a design acquisition means which acquires design data from a design storage means which stores design data of structures associated with the work items of the construction project, and a display data generation means which, when a display request specifying a reference time point for display is received, extracts from the plan data the work items that are scheduled to be completed by the reference time point, and generates display data to be used for displaying structures that are scheduled to be constructed by the reference time point based on the design data associated with the extracted work items.

[0004] Moreover, the embankment construction management support system disclosed in Patent Document 2 creates embankment site information from information acquired at the borrow site and the embankment site and sent to a cloud server during embankment construction in which soil is loaded onto a dump truck by a backhoe at a borrow site, transported to the embankment site, unloaded, and compacted by a vibratory roller. This embankment construction management support system divides the embankment site into multiple mesh-like voxel blocks, creates unloaded soil information showing the location and soil quality of the unloaded soil from the information sent to the cloud server, determines the soil quality of each voxel block from the unloaded soil information and compaction information obtained by the vibratory roller to create embankment site information, and displays the multiple voxel blocks of the embankment site information on a monitor in a visible state. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2016-143345 A [Patent Document 2] Patent Publication No. 2022-135525 Summary of the Invention [Problem to be solved by the invention]

[0006] In conventional construction management systems, attribute information and external reference files are registered during and after construction using BIM / CIM, but in civil engineering works that are easily affected by the natural environment, it is difficult to output information including models according to the progress of construction.In addition, since the construction object is divided into voxel blocks of a certain shape such as a specified cube and each data of a large number of voxel blocks is managed, linking each voxel block is complicated, and it is difficult to manage the construction object according to its progress.

[0007] Conventional construction management systems require specialized software to manage construction data of construction targets and create and output models, and also require operations such as inputting attribute information of the construction targets and linking it to location information of the construction targets, etc. This makes it difficult for on-site users to input construction data of construction targets and create and output models of construction targets, and the work is outsourced.

[0008] In addition, in conventional construction management systems, dedicated software and a high-performance PC (personal computer) are required to refer to the model of the construction object, and each user must own this software and PC in order to share construction data of the construction object, making it difficult to popularize construction management systems.

[0009] In order to solve the above-mentioned problems, the present invention aims to provide a construction management system that enables easy input of construction data according to the progress of a construction object, and can manage the construction object according to its progress. [Means for solving the problem]

[0010] The construction management system of the present invention is a construction management system that manages the construction of construction and civil engineering projects, and is characterized in that it manages construction objects using construction data in units of layered blocks defined by a predetermined construction thickness and a horizontal contour corresponding to the construction progress, and is equipped with a management server that presents the construction status of the construction objects based on the construction data using a web application, and a user terminal that enables the construction data to be input into the management server for each block that constitutes the construction object in accordance with user operation, and receives the presentation of the construction status from the management server. Effect of the Invention

[0011] According to the present invention, construction data according to the progress of a construction object can be easily input, and the construction object can be managed according to its progress. [Brief description of the drawings]

[0012] [Figure 1] 1 is a block diagram showing a construction management system according to an embodiment of the present invention. [Diagram 2] 1 is a front view showing an example of a management screen displaying a construction model in a construction management system according to an embodiment of the present invention. FIG. [Diagram 3] 1 is a front view showing an example of a management screen displaying a construction model in which a selected block is highlighted in a construction management system according to an embodiment of the present invention. FIG. [Figure 4] 1 is a front view showing an example of a management screen displaying a construction model in which selected blocks are displayed separately in a stacked state in a construction management system according to an embodiment of the present invention. FIG. [Diagram 5] 1 is a front view showing an example of a management screen displaying a construction model in which selected blocks are displayed separately in a distributed state in a construction management system according to an embodiment of the present invention. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0013] Hereinafter, an embodiment of the present invention will be described with reference to the accompanying drawings. First, a construction management system 1 of the present embodiment will be described with reference to Fig. 1. Fig. 1 is a block diagram showing the construction management system 1.

[0014] The construction management system 1 manages the construction of construction and civil engineering projects, and includes a management server 2 that manages construction targets on-site, an online storage 3 that stores various files such as construction data files, and a user terminal 4 that accepts input of construction data and presentation of construction status. In the construction management system 1, the management server 2, the online storage 3, and the user terminal 4 are connected to each other so as to be able to communicate with each other via a network 5 such as the Internet.

[0015] The management server 2 is equipped with a control unit 10 consisting of a computer such as a CPU, and the control unit 10 is connected to a memory unit 11 such as a ROM, RAM, hard disk drive, flash memory, etc., and a communication unit 12 that communicates with external devices.

[0016] The storage unit 11 stores programs and data for controlling each part and various functions of the management server 2, and the control unit 10 executes arithmetic processing based on the programs and data stored in the storage unit 11, thereby controlling each part and various functions of the management server 2. The communication unit 12 is connected to the online storage 3 and the user terminal 4 via the network 5 so as to be able to communicate with them.

[0017] For example, the control unit 10 of this embodiment executes a program stored in the storage unit 11 to provide a web application executed by a browser of the user terminal 4, and operates as a data input unit 20, a construction status display unit 21, and a form output unit 22. In other words, the control unit 10 executes the data input unit 20, the construction status display unit 21, and the form output unit 22 in the web application.

[0018] Using a web application, the management server 2 manages the construction target at the site with construction data divided into layered block units, and also presents the construction status of the construction target based on the construction data. For example, using the web application, the management server 2 displays a predetermined management screen 100 on the browser of the user terminal 4, as shown in Figures 2, 3, 4, and 5.

[0019] The data input unit 20 acquires, from the online storage 3, a construction data file of construction data uploaded to the online storage 3 for a specific construction target, and stores and manages the construction data described in the construction data file in the storage unit 11 in association with the construction target. The construction data stored in the storage unit 11 is shared among users logged in to the management server 2.

[0020] The data input unit 20 accepts an operation to upload a construction data file to the online storage 3 on the management screen 100. The online storage 3 holds construction data files for each data type of construction object, such as embankment, structure, buried equipment, design, etc. The online storage 3 has a folder for each construction object, and stores the construction data file of the construction data of each construction object in the folder corresponding to the construction object.

[0021] The construction data indicates information on the construction target in units of layered blocks defined by a specified construction thickness in the vertical direction and a horizontal outline according to the construction progress, and each block is identified by block identification information (ID). Each construction data is composed of position information and attribute information of each block of the construction target. The construction data file is a file created with spreadsheet software, and is composed of a position information sheet with each position information described in each row, and an attribute information sheet with each attribute information described in each row.

[0022] In the online storage 3, a folder for each block is provided under the folder for each construction target, and the construction data file for each block is stored in the folder corresponding to the block. Note that the management server 2 may automatically create a folder corresponding to a block when a construction data file for the block is uploaded, for example, or may create a folder corresponding to the block in response to a user operation.

[0023] The position information includes, for example, a block ID, a base surface elevation (LF) which is the vertical height of the base surface (bottom surface) of the block, a construction thickness in the vertical direction of the block, and coordinate values ​​of the vertices of the horizontal contour of the block. Note that other information may be set in the position information as necessary.

[0024] The cross-sectional shape of each block along the horizontal direction is assumed to be the same shape at each vertical position within the range of the construction thickness of each block. Here, if the cross-sectional shape of the block does not have a recess (a recess having two or more vertices between two vertices), the cross-sectional shape is represented by a single polygon, and the block has one piece of position information having the coordinate values ​​of each vertex of the single polygon. On the other hand, if the cross-sectional shape of the block has a recess (a recess having two or more vertices between two vertices) or if the inside of the cross-sectional shape of the block is hollowed out, the cross-sectional shape is represented by two or more polygons, and the block has two or more pieces of position information having the coordinate values ​​of each vertex of the two or more polygons.

[0025] The attribute information includes, for example, a block ID, the date the block was constructed, weather conditions (weather, temperature, probability of precipitation in each time period, maximum temperature, minimum temperature, etc.), construction start time and construction end time, material names of materials constituting the block, quality test results, design quantity, construction quantity. Note that other information may be set as the attribute information as necessary.

[0026] Furthermore, the data input unit 20 acquires a design data file of design data uploaded to the online storage 3 for a predetermined construction target from the online storage 3, and stores and manages the design data described in the design data file in the storage unit 11 in association with the construction target. The data input unit 20 accepts an operation to upload the design data file to the online storage 3 on the management screen 100.

[0027] The design data file is composed of a CAD data file having CAD data showing a design model of a three-dimensional shape of a construction target designed by a design support software such as CAD. The design data may have not only the dimensions of the design target but also coordinate values. In the online storage 3, the design data file corresponding to the construction target is stored in the folder of the construction target.

[0028] Furthermore, the data input unit 20 acquires from the online storage 3 a terrain data file of terrain data uploaded to the online storage 3 for the terrain to be constructed of a specified construction target, and stores and manages the terrain data described in the terrain data file in the memory unit 11 in association with the construction target. The data input unit 20 accepts an operation to upload the terrain data file to the online storage 3 on the management screen 100.

[0029] The terrain data file is composed of a plurality of terrain data each indicating the position of a plurality of triangles in order to provide a terrain model by a mesh model composed of a plurality of triangles. Each triangle constituting the terrain model is arranged in a three-dimensional space, and each terrain data has three-dimensional position coordinates of each vertex of the corresponding triangle. In the online storage 3, the terrain data file corresponding to the construction target is stored in the folder of the construction target.

[0030] The construction status display unit 21 presents the construction status of the construction target to the user by displaying the construction status on the screen of the browser of the user terminal 4 using a web application based on the construction data acquired from the construction data files of each data type by the data input unit 20. The management server 2 displays the management screen 100 on the browser of the user terminal 4 using a web application, and the construction status display unit 21 may accept, on the management screen 100, a selection operation of the construction target for which the construction status is to be presented, from among one or more construction targets for which construction data is stored in the storage unit 11.

[0031] The construction status display unit 21 creates a construction model 101, which is a three-dimensional model that visualizes the construction target based on the construction data of each data type, and displays it on the management screen 100 as a presentation of the construction status using a web application.

[0032] The construction status display unit 21 creates a block model 102, which is a three-dimensional model that visualizes each block, based on the position information of the construction data of each block, and displays the block models 102 in a stacked manner on the management screen 100 to display a construction model 101, which is a three-dimensional model of the construction target. Regardless of whether one block has one piece of position information or two or more pieces of position information, the construction status display unit 21 displays one block model 102 for one block. The construction status display unit 21 may display the construction model 101 by applying a different color to each block model 102 for each data type.

[0033] The construction status display unit 21 can also create a mesh model terrain model 105 consisting of multiple triangles based on the terrain data acquired from the terrain data file by the data input unit 20 through a web application, and display it on the management screen 100 displayed on the browser of the user terminal 4. At this time, the construction status display unit 21 may display the construction model 101 and the terrain model 105 by overlapping them with their coordinate values ​​aligned.

[0034] The construction status display unit 21 can accept rotation operations and zoom-in / zoom-out operations of the construction model 101 in response to click operations or touch operations on the management screen 100, and change the images of the construction model 101 and the topographical model 105 viewed via the management screen 100.

[0035] The construction status display unit 21 can display a construction model 101 consisting of block models 102 of each block whose construction has been completed by a specified construction date according to the construction history of the construction target on the management screen 100. For example, the construction status display unit 21 displays a slider bar on the management screen 100 that allows the construction date of the block to be referenced to be set, and displays the construction model 101 consisting of block models 102 whose construction has been completed by the construction date set according to the operation of the slider bar.

[0036] The construction status display unit 21 accepts the selection operation of each block that constitutes the construction target on the management screen 100, and further has a highlighting function that highlights and displays the block model 102 corresponding to the selected block on the construction model 101, and a separated display function that displays the block model 102 corresponding to the selected block with a vertical gap between them on the construction model 101.

[0037] For example, the construction status display unit 21 accepts a selection of a block in response to a selection operation (for example, a click operation or a touch operation) of a block model 102 for a construction model 101 consisting of one or more block models 102 displayed on the management screen 100.

[0038] Furthermore, the construction status display unit 21 displays a list screen 110 on the management screen 100 that displays a list of one or more blocks that constitute the construction target, and accepts the selection of a block in response to a selection operation on the list screen 110.

[0039] Furthermore, the construction status display unit 21 displays a condition setting screen 120 on the management screen 100 for setting selection conditions for selecting a block from one or more blocks constituting the construction target, and accepts selection of a block that satisfies the selection conditions set on the condition setting screen 120. The construction status display unit 21 makes it possible to set, for example, the data type, the construction date of the block, the block ID, the construction elevation (the elevation based on the base level elevation and the construction thickness), and each attribute information as the selection conditions.

[0040] As a highlighting function, the construction status display unit 21 highlights the block model 102 of the selected block by changing the shading, coloring, or blinking a different color in comparison with the other block models 102 that were not selected in the construction model 101 displayed on the management screen 100, as shown in Fig. 3. Note that the construction status display unit 21 may be capable of switching between displaying and hiding the other block models 102 that were not selected in response to an arbitrary operation on the management screen 100.

[0041] As a separate display function, the construction status display unit 21 displays a construction model 101 consisting of block models 102 of unselected blocks on the management screen 100, as well as a separated model 103 consisting of block models 102 of selected blocks, separated at a predetermined first interval vertically above the construction model 101, as shown in Fig. 4 and Fig. 5. The construction status display unit 21 may set the first interval so that the construction model 101 and the separated model 103 do not overlap, and may also be able to set the first interval in response to an arbitrary operation.

[0042] At this time, the construction status display unit 21 may display a separated model 103 configured to stack the block models 102 of the selected blocks, as shown in Figure 4, in other words, may display a construction model 101 separating the separated models 103 in a stacked state.

[0043] Alternatively, the construction status display unit 21 may display the separated models 103 (vertical dispersion display) using a vertically dispersed model in which the block models 102 of the selected block are further arranged at a second interval (preferably an interval smaller than the first interval) in the vertical direction for each block, as shown in Fig. 5, in other words, may display the construction model 101 separating the dispersed separated models 103. The construction status display unit 21 may set the second interval so that the separated models 103 fit within the screen dimensions, and may also make the second interval settable in response to an arbitrary operation.

[0044] The construction status display unit 21 makes it possible to switch, in response to any operation, between displaying the construction model 101 in which all block models 102 are stacked regardless of the selection, displaying the stacked separated models 103 separated from the construction model 101, and displaying the separated models 103 of the vertically distributed model separated from the construction model 101.

[0045] The construction status display unit 21 can also create a design model that designs the three-dimensional shape of the construction target based on the design data acquired from the design data file by the data input unit 20 using a web application, and display it on the management screen 100 displayed on the browser of the user terminal 4. At this time, the construction status display unit 21 may display the construction model 101 and the design model by overlapping them with the coordinate values ​​aligned. The construction status display unit 21 may display the construction model 101 in a way that makes it clearer than the design model by using shading, color, etc., and may also detect and highlight differences between the construction model 101 and the design model.

[0046] Furthermore, the construction status display unit 21 displays an information display screen 130 displaying the position information and attribute information of the selected block as a presentation of the construction status on the management screen 100. The type of information to be displayed on the information display screen 130 may be set in advance, or may be set according to an arbitrary operation.

[0047] The report output unit 22 creates a report file of one or more blocks to be constructed based on the construction data of the one or more blocks as a presentation of the construction status by a web application, and outputs the report file to the online storage 3. The report output unit 22 creates the report file as a file in a format that can be referenced by spreadsheet software. The report output unit 22 accepts an operation to download the report file from the online storage 3 on the management screen 100.

[0048] In the online storage 3, the report file created for the construction target is stored in the folder of the construction target. The report output unit 22 may accept, on the management screen 100, a selection operation of a block for creating a report from one or more blocks for which construction data is stored in the storage unit 11, for the construction target presented on the management screen 100 by the construction status display unit 21. In addition, the report output unit 22 may display, on the management screen 100, a report information screen (not shown) for selecting the type of information to be output by the report from the position information and attribute information included in the construction data, and create the report by writing the information selected on the report information screen.

[0049] The user terminal 4 is composed of a tablet terminal, a smartphone, a personal computer, etc. The user terminal 4 has a control unit 30 composed of a computer such as a CPU, and the control unit 30 is connected to a storage unit 31 such as a ROM, a RAM, a hard disk drive, a flash memory, etc., and a communication unit 32 that communicates with external devices. The control unit 30 is also connected to a display unit 33 composed of a liquid crystal display, etc., and an operation unit 34 composed of a keyboard, a pointing device, etc. The display unit 33 and the operation unit 34 may be composed of a touch panel.

[0050] The storage unit 31 stores programs and data for controlling each unit and various functions of the user terminal 4, and the control unit 30 controls each unit and various functions of the user terminal 4 by executing arithmetic processing based on the programs and data stored in the storage unit 31. The communication unit 32 is connected to the management server 2 and the online storage 3 via the network 5 so as to be able to communicate with them.

[0051] For example, the control unit 30 executes a program stored in the storage unit 31, whereby the user terminal 4 starts a browser and displays it on the display unit 33, and executes a web application provided by the management server 2 via the browser. The user terminal 4 displays, in the browser of the display unit 33, a management screen 100 provided by the web application of the management server 2.

[0052] When the user terminal 4 receives an upload operation specifying a specific construction data file, design data file, or terrain data file on the management screen 100 of the browser, it uses a web application to send an upload instruction to the management server 2 together with the construction data file, design data file, and terrain data file, and the construction data file, design data file, and terrain data file are uploaded to the online storage 3 via the management server 2. Alternatively, the user terminal 4 may directly access the online storage 3 without going through the management server 2 to upload the construction data file, design data file, and terrain data file.

[0053] In addition, when the user terminal 4 receives a selection operation of a construction object for presenting the construction status on the management screen 100 of the browser, it uses a web application to send a selection instruction for the construction object to the management server 2, and displays a construction model 101 of the construction object provided by the management server 2 via the web application on the management screen 100.

[0054] When the user terminal 4 receives a block selection operation on the management screen 100 displaying the construction model 101, the user terminal 4 uses a web application to transmit a block selection instruction to the management server 2, and displays the construction model 101 updated by a highlighting function or a separated display function on the management screen 100. When the user terminal 4 receives a rotation operation or a zoom-in / zoom-out operation of the construction model 101 on the management screen 100 displaying the construction model 101, the user terminal 4 uses a web application to transmit a rotation instruction or a zoom-in / zoom-out instruction of the construction model 101 to the management server 2, and displays an image of the construction model 101 that has changed in response to the rotation operation or the zoom-in / zoom-out operation on the management screen 100.

[0055] Furthermore, when the user terminal 4 receives an operation to download a form file specifying a specific block on the management screen 100 of the browser, the user terminal 4 uses a web application to send a download instruction for the form file to the management server 2, and downloads the form file acquired by the management server 2 from the online storage 3 from the management server 2. Alternatively, the user terminal 4 may directly access the online storage 3 without going through the management server 2 to download the form file.

[0056] According to this embodiment, as described above, the construction management system 1 for managing the construction of construction and civil engineering projects manages the construction object with construction data in units of layered blocks defined by a predetermined construction thickness and a horizontal contour according to the construction progress, and is equipped with a management server 2 that presents the construction status of the construction object based on the construction data via a web application, and a user terminal 4 that enables input of construction data to the management server 2 for each block that constitutes the construction object in response to user operation, and receives the presentation of the construction status from the management server 2.

[0057] As a result, the construction management system 1 manages construction data in units of blocks according to the construction progress, so that the construction status that appropriately reflects each construction progress can be easily presented to the user. In addition, since construction data can be input for each constructed block, the input operation of construction data is simplified. Furthermore, in the construction management system 1, since the construction status is provided to the user terminal 4 from the management server 2 by a web application, the user terminal 4 does not need to have a function for managing construction data, and as long as there is an Internet environment, the user can easily receive the construction status using a browser regardless of location, and the work on site can be made more efficient. In addition, since the user terminal 4 does not need to be equipped with dedicated software or a high-performance computer, the user can easily use the construction management system 1, and the construction management system 1 can be widely disseminated. In this way, the construction management system 1 makes it possible to easily input construction data according to the progress of the construction target, and also to manage the construction target according to its progress.

[0058] Furthermore, according to the construction management system 1 of this embodiment, the user terminal 4 uploads a construction data file, which is a file created by spreadsheet software and contains construction data consisting of position information and attribute information of one or more blocks, to a predetermined online storage 3. The management server 2 acquires the construction data file uploaded to the online storage 3 and manages the construction data described in the construction data file.

[0059] As a result, the construction management system 1 allows users to input construction data using a means that is easier to operate, making the construction management system 1 easier to use and enabling the construction management system 1 to become more widely used.

[0060] According to the construction management system 1 of this embodiment, the management server 2 provides a web application that displays the construction model 101, a three-dimensional model that visualizes the construction target based on the construction data, as a presentation of the construction status. The user terminal 4 displays the three-dimensional construction model 101 on a browser screen using the web application. At this time, the web application has a highlighting function that accepts the selection of blocks that constitute the construction target and highlights and displays the selected blocks on the construction model 101, and a separated display function that displays the selected blocks on the construction model 101 with a vertical gap between them.

[0061] As a result, in the construction management system 1, users can refer to the construction status using an easier-to-operate means, making it easier to use the construction management system 1 and enabling the construction management system 1 to be more widely used. In addition, since constructed blocks can be selected and displayed, the construction status according to progress can be easily confirmed.

[0062] Furthermore, according to the construction management system 1 of this embodiment, the management server 2 provides, as a presentation of the construction status, a web application that creates a report file for one or more blocks to be constructed based on the construction data for the one or more blocks and outputs the report file to a predetermined online storage 3. The user terminal 4 accepts a download of the report file via the web application and downloads the report file from the online storage 3.

[0063] As a result, in the construction management system 1, users can obtain reports using an easier-to-operate means, making it easier to use the construction management system 1 and enabling the construction management system 1 to be more widely used. In addition, because reports can be created by selecting constructed blocks, the construction status can be easily checked according to progress.

[0064] In another embodiment, in the construction management system 1, the management server 2 (construction status display unit 21) may create a graph that plots attribute information and completion rate, etc. of each block being constructed in a time series based on the construction data of each data type, and display the graph on the management screen 100 as a presentation of the construction status using a web application.

[0065] In the construction management system 1, the management server 2 (data input unit 20) associates the construction data of the construction data file uploaded to the online storage 3 with the construction target and stores it in the memory unit 11, but in another embodiment, a construction data file consisting of the construction data of each block selected from the construction data stored in the memory unit 11 may be restored and output to the online storage 3. Then, the user terminal 4 may accept an operation to download the restored construction data file from the online storage 3 on the management screen 100.

[0066] The description of the embodiment shows one aspect of the construction management system according to the present invention, and the technical scope of the present invention is not limited to the above embodiment. The present invention may be modified, substituted, or altered in various ways without departing from the spirit of the technical idea, and the claims include all embodiments that may be included within the scope of the technical idea. [Explanation of symbols]

[0067] 1 Construction management system 2 Management Server 3. Online Storage 4 User terminal 5. Network 10 Control section 11 Storage section 20 Data Entry Section 21 Construction status display section 22 Report output section 30 Control section 33 Display section 34 Control section 100 Management screen 101 Construction Model 102 Block Model 103 Separate Model

Claims

1. A construction management system for managing construction and civil engineering projects, A management server that manages a construction target by using construction data in units of layered blocks defined by a predetermined construction thickness and a horizontal outline according to the construction progress, and presents the construction status of the construction target by a web application based on the construction data; a user terminal that enables input of the construction data for each of the blocks constituting the construction target to the management server in response to a user's operation and receives a presentation of the construction status from the management server; A construction management system comprising:

2. The user terminal uploads a construction data file, which is a file created by spreadsheet software and in which the construction data consisting of position information and attribute information of one or more of the blocks is described, to a predetermined online storage; The management server acquires the construction data file uploaded to the online storage and manages the construction data described in the construction data file. The construction management system according to claim 1 .

3. the management server provides the web application that displays a three-dimensional model that visualizes the construction target based on the construction data as the presentation of the construction status; The user terminal displays the three-dimensional model on a browser screen using the web application; The web application has a highlighting function for accepting a selection of the blocks constituting the construction target and highlighting and displaying the selected blocks in the three-dimensional model, and a separation display function for displaying the selected blocks in the three-dimensional model with a vertical gap therebetween. The construction management system according to claim 1 .

4. the management server provides the web application that creates a report file of the one or more blocks of the construction target based on the construction data of the one or more blocks as the presentation of the construction status, and outputs the report file to a predetermined online storage; The user terminal accepts the download of the form file through the web application and downloads the form file from the online storage. The construction management system according to claim 1 .