Report preparation system, report preparation method, and program

The report creation system addresses the challenge of creating tailored reports for facilities with air-conditioning systems by using facility and environmental data to determine appropriate indicators, resulting in customized reports that meet user requirements.

JP2025012474APending Publication Date: 2025-01-24DAIKIN INDUSTRIES LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023115331
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-07-13
Publication Date
2025-01-24

AI Technical Summary

Technical Problem

Conventional systems struggle to create reports for facilities with air-conditioning systems that include various indicators required by users, as these vary based on the facility's application, purpose, or business, making it difficult to provide tailored reports.

Method used

A report creation system that includes an air-conditioning system and a control unit, which uses facility information, indoor environmental data, and user inputs to determine and generate reports containing appropriate indicators based on the facility's type, purpose, size, location, and user base.

Benefits of technology

Enables the creation of customized reports for facilities with air-conditioning systems, including relevant health and environmental indicators, tailored to the facility's specific needs, enhancing user satisfaction and operational efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2025012474000001_ABST
    Figure 2025012474000001_ABST
Patent Text Reader

Abstract

To facilitate the preparation of a report on a facility including various indexes required by a user according to facilities where an air conditioning system is installed.SOLUTION: A report preparation system includes a communication unit which acquires indoor environment information from an air-conditioning system, and a control unit. The control unit prepares a report including various indexes on a facility where the air-conditioning system is installed on the basis of information on the facility and the indoor environment information, and determines the various indexes included in the report on the basis of the information on the facility.SELECTED DRAWING: Figure 6
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a report creation system, a report creation method, and a program. [Background technology]

[0002] An index calculation system is known that calculates data related to the thermal insulation of a building and displays a report of indexes for evaluating the health risk in the building based on the calculated data and a comparison temperature that serves as an indicator of the health risk (see, for example, Patent Document 1). [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-21333 A Summary of the Invention [Problem to be solved by the invention]

[0004] There is a demand for creating reports including various indicators, such as air quality or health risks, related to facilities in which air conditioning systems are installed, and providing the reports to users.

[0005] However, since the various indicators required by a user vary depending on, for example, the facility's use, purpose, or industry, conventional technology makes it difficult to create a report on a facility that includes the various indicators required by a user depending on the facility.

[0006] The present disclosure makes it easy to create a report about a facility including various indicators required by a user depending on the facility in which an air conditioning system is installed. [Means for solving the problem]

[0007] A report creation system according to a first aspect of the present disclosure includes a communication unit that acquires indoor environment information from an air conditioning system, and a control unit, wherein the control unit creates a report including various indicators related to a facility in which the air conditioning system is installed based on information about the facility and the indoor environment information, and determines the various indicators to be included in the report based on the information about the facility.

[0008] According to the report creation system according to the first aspect of the present disclosure, it becomes easy to create a report about a facility including various indices required by a user according to the facility in which the air conditioning system is installed.

[0009] A second aspect of the present disclosure is the report creation system according to the first aspect, wherein the information about the facility includes information about a use of the facility, a type of business of the facility, or a purpose of the facility. This allows the report creation system to provide a report about the facility including various more appropriate indicators according to the use of the facility, the type of business of the facility, the purpose of the facility, or the like.

[0010] A third aspect of the present disclosure is the report creation system according to the first or second aspect, wherein the information about the facility includes information about the size of the facility or the location conditions of the facility. This enables the report creation system to provide a report about the facility including various more appropriate indicators according to the size of the facility or the location conditions of the facility.

[0011] A fourth aspect of the present disclosure is a report creation system according to any one of the first to third aspects, wherein the information about the facility includes information about the number of users of the facility, the number of users of the facility, or the user demographics of the facility. This allows the report creation system 1 to provide a report about the facility including various more appropriate indicators depending on the number of users of the facility, the number of users of the facility, the user demographics of the facility, etc.

[0012] A fifth aspect of the present disclosure is the report creation system according to any one of the first to fourth aspects, wherein the facility includes an elderly care facility, a business facility, an educational facility, a medical facility, or a commercial facility.

[0013] A sixth aspect of the present disclosure is the report creation system according to any one of the first to fifth aspects, wherein the various indices include an index related to health.

[0014] A seventh aspect of the present disclosure is a report creation system described in the sixth aspect, wherein the health-related indicators include an indicator for a respiratory disease, an indicator for a viral infection, an indicator for hypothermia, or an indicator for heat stroke.

[0015] An eighth aspect of the present disclosure is the report creation system according to any one of the first to seventh aspects, wherein the various indices include an index related to an air environment of the facility, or an index related to an electricity bill.

[0016] A ninth aspect of the present disclosure is a report creation system described in any of the first to eighth aspects, wherein the control unit further determines the various indicators to be included in the report based on time information indicating a season or season.

[0017] A tenth aspect of the present disclosure is a report creation system described in any of the first to ninth aspects, wherein the report includes representative values ​​of indicators for other facilities that share information about the facility with the facility, and the indicators for the facility.

[0018] An eleventh aspect of the present disclosure is a report creation system described in any of the first to tenth aspects, wherein the control unit has a plurality of conditions, and when the conditions are met, adds an indicator corresponding to the conditions to the report.

[0019] A report creation method according to a twelfth aspect of the present disclosure is a report creation system including a communication unit that acquires indoor environment information from an air conditioning system and a control unit, in which the control unit creates a report including various indicators related to the facility in which the air conditioning system is installed based on information about the facility and the indoor environment information, and determines the various indicators to be included in the report based on the information about the facility.

[0020] A program according to a thirteenth aspect of the present disclosure is a report creation system including a communication unit that acquires indoor environment information from an air conditioning system and a control unit, and causes the control unit to execute a process of creating a report including various indicators related to a facility in which the air conditioning system is installed based on information about the facility and the indoor environment information, and a process of determining the various indicators to be included in the report based on the information about the facility. [Brief description of the drawings]

[0021] [Figure 1] FIG. 1 is a diagram showing an example of the configuration of a report creation system according to an embodiment of the present invention; [Diagram 2] FIG. 1 shows an example of a report according to the embodiment. [Diagram 3] FIG. 2 shows an example of a report according to the embodiment. [Figure 4] FIG. 2 illustrates an example of the configuration of the report creation system according to the present embodiment. [Diagram 5] FIG. 2 is a diagram illustrating an example of a hardware configuration of a computer according to the present embodiment. [Figure 6] 10 is a flowchart illustrating an example of a report creation process according to the embodiment. [Figure 7] FIG. 1 is a diagram showing an example of information managed by the report creation system according to the present embodiment. [Figure 8] 1 is a flowchart (1) illustrating an example of an index determination process according to the first embodiment. [Figure 9] 11 is a flowchart (2) illustrating an example of the index determination process according to the first embodiment. [Figure 10] 11 is a flowchart (3) illustrating an example of the index determination process according to the first embodiment. [Figure 11] 11 is a flowchart (4) illustrating an example of the index determination process according to the first embodiment. [Figure 12] 11 is a flowchart (5) illustrating an example of the index determination process according to the first embodiment. [Figure 13] 11 is a flowchart (6) illustrating an example of the index determination process according to the first embodiment. [Figure 14] 13 is a flowchart illustrating an example of an index determination process according to the second embodiment. [Figure 15] FIG. 2 shows an example of information managed by the report creation system according to the embodiment. [Figure 16] FIG. 3 shows an example of a report according to the embodiment. [Figure 17] FIG. 11 is a diagram showing an example of displaying another index according to the present embodiment. [Figure 18] FIG. 13 is a diagram showing a display example of another index according to the embodiment; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0022] Hereinafter, an embodiment of the present disclosure (the present embodiment) will be described with reference to the accompanying drawings. In this specification and the drawings, components having substantially the same functional configurations are denoted by the same reference numerals, and redundant description will be omitted.

[0023] <Report creation system configuration> 1 is a diagram (1) showing an example of the configuration of a report creation system according to this embodiment. The report creation system 1 is a system that creates a report including various indices required by a user 21 according to a facility 2 in which an air conditioning system 3 is installed, and provides the created report to the user 21.

[0024] 1, the report creation system 1 includes a management server 100, a communication device 10, a user terminal 20, and an administrator terminal 30. The management server 100, the communication device 10, the user terminal 20, and the administrator terminal 30 are communicatively connected via a communication network N such as the Internet and a LAN (Local Area Network).

[0025] The communication device 10 is an information processing device having a computer configuration. The communication device 10 acquires measurement results from, for example, air conditioners 11a, 11b, ... such as indoor units, and sensors 12a, 12b, ... such as temperature sensors, humidity sensors, airflow sensors, or odor sensors, which are included in an air conditioning system 3 installed in a facility 2. The communication device 10 also transmits indoor environment information including the acquired measurement results to the management server 100 via a communication network N.

[0026] In the following description, when referring to any one of the multiple air conditioners 11a, 11b, ..., the term "air conditioner 11" is used. When referring to any one of the multiple sensors 12a, 12b, ..., the term "sensor 12" is used.

[0027] The user terminal 20 is an information processing device having a computer configuration such as a PC (Personal Computer), a tablet terminal, or a smartphone, which is used by a user 21 of the report creation system 1. The user 21 is, for example, an administrator who manages the air conditioning system 3 installed in the facility 2, or a user who uses the air conditioning system 3, and can use the user terminal 20 to display a report provided by the management server 100.

[0028] The administrator terminal 30 is an information processing device having a computer configuration such as a PC, a tablet terminal, or a smartphone, which is used by an administrator 31. The administrator 31 is, for example, an administrator who manages the report creation system 1 or the management server 100. Using the administrator terminal 30, the administrator 31 can manage (register, change, delete, etc.) various information managed by the management server 100 (for example, facility information 111, user information 112, selection information 113, index information 114, setting information, etc.).

[0029] The management server 100 is an information processing device having a computer configuration, or a system including a plurality of computers. In the example of Fig. 1, the management server 100 includes a communication unit 101, a control unit 102, a storage unit 103, and the like.

[0030] The communication unit 101 connects the management server 100 to the communication network N and communicates with the communication device 10, the user terminal 20, the administrator terminal 30, and the like. The communication unit 101 also acquires indoor environment information from an air conditioning system 3 installed in the facility 2. For example, the communication unit 101 receives indoor environment information transmitted by the communication device 10 of the air conditioning system 2. The communication unit 101 also acquires measurement results of, for example, the indoor temperature, humidity, carbon dioxide concentration (hereinafter referred to as CO2 concentration), airflow, odor, and the like, included in the received indoor environment information.

[0031] The control unit 102 is a processor such as a CPU (Central Processing Unit) included in the management server 100. The control unit 102 executes a program stored in a storage medium such as the storage unit 103 to create a report including various indices required by the user 21 according to the facility 2 in which the air conditioning system 3 is installed, and provides the created report to the user 21.

[0032] The storage unit 103 is realized by a storage device or the like included in the management server 100, and stores various information including, for example, facility information 111, user information 112, selection information 113, and index information 114. Note that the storage unit 103 may be realized by another server capable of communicating with the management server 100 via the communication network N, cloud storage, or the like.

[0033] The facility information 111 stores various information related to the facility 2 in which the air conditioning system 3 is installed (e.g., the facility name, the type of facility 2, information on users of the facility 2, the size of the facility 2, business hours, location conditions, and a user ID corresponding to the facility 2). The facility information 111 may be managed by the control unit 102, or may be acquired by the control unit 102 from an external system that manages the facility information 111. The user information 112 stores various information related to users who use the report creation system 1 (e.g., user IDs, user names, passwords, and email addresses). The selection information 113 and the index information 114 will be described later.

[0034] In the above-described system configuration, the control unit 102 creates a report including various indices related to the facility 2 based on facility information 111 including information related to the facility 2 in which the air conditioning system 3 is installed and indoor environment information acquired by the communication unit 101. At this time, the control unit 102 determines (or changes) various indices to be included in the report based on the information related to the facility 2.

[0035] As an example, when the facility 2 is an elderly care facility (for example, a nursing home for the elderly, a special nursing home for the elderly, or a care house), the control unit 102 creates a report 200 as shown in Fig. 2, for example, and provides it to the user 21. In this case, the control unit 102 acquires measurement results of temperature, humidity, airflow, and the like from the indoor environment information of the facility 2, and creates the report 200 including an index showing the impact on the health of the residents of the facility 2 based on the acquired measurement results. In the example of Fig. 2, the report 200 displays, for example, indexes such as virus 201, respiratory disease 202, hypothermia 203, elevated blood pressure 204, and nighttime temperature 205.

[0036] If the nighttime temperature exceeds 18 degrees, it may pose a health risk to the elderly. Therefore, it is considered appropriate for the room temperature at night in elderly care facilities to be around 18 degrees. The control unit 102 performs, for example, A, B, C judgment and calculation of achievement level based on the magnitude of difference between the measured nighttime room temperature and the appropriate temperature of 18 degrees, and creates an index of nighttime temperature 205.

[0037] However, this is just an example, and in this embodiment, the specific determination method and calculation method of the various indices may be any method. Also, the various indices may be indices other than the A, B, and C ratings and the achievement level.

[0038] As another example, when the facility 2 is a business facility (for example, an office or a workshop of a company), the control unit 102 creates a report 300 as shown in Fig. 3, for example, and provides it to the user 21. In this case, the control unit 102 acquires measurement results of temperature, humidity, airflow, etc. from the indoor environment information of the facility 2, and creates the report 300 including an index showing the impact on the working environment of employees based on the acquired measurement results. In the example of Fig. 3, the report 300 displays, for example, indexes such as virus 301, ventilation status 302, and room temperature 303.

[0039] In this way, the report creation system 1 of this embodiment creates reports 200, 300 regarding the facility 2 including various indicators required by the user, depending on the facility 2 in which the air conditioning system 3 is installed, and provides them to the user 21.

[0040] 1 is an example of the system configuration of the report creation system 1. For example, as shown in FIG 4, the communication unit 101, the control unit 102, and the storage unit 103 may be included in a communication device 10 instead of the management server 100.

[0041] Fig. 4 is a diagram (2) showing a configuration example of the report creation system according to this embodiment. In the example of Fig. 4, the management server 100 is an information processing device that manages a user information DB (Database) 411 that manages facility information 111 of a plurality of facilities 2, a facility information DB 412 that manages user information 112 of a plurality of users 21, and the like, or a system including a plurality of information processing devices.

[0042] In the example of FIG. 4, instead of the management server 100, the communication device 10 includes a communication unit 101, a control unit 102, a storage unit 103, and the like.

[0043] In this case, the communication unit 101 connects the communication device 10 to the communication network N and communicates with the management server 100, the user terminal 20, the administrator terminal 30, etc. The communication unit 101 is also communicatively connected to the air conditioners 11 and sensors 12, etc. included in the air conditioning system 3 installed in the facility 2, and acquires measurement results (indoor environment information) from the air conditioners 11 and the sensors 12.

[0044] In this case, the control unit 102 is a processor such as a CPU included in the communication device 10. The control unit 102 executes a program stored in a storage medium such as the storage unit 103 to create a report including various indices required by the user 21 according to the facility 2 in which the air conditioning system 3 is installed, and provides the created report to the user 21.

[0045] In this case, the memory unit 103 is realized by a storage device or the like included in the communication device 10, and stores various information including, for example, facility information 111, user information 112, selection information 113, and index information 114. For example, the control unit 102 may acquire facility information 111 of the facility 2 and user information 112 of the user 21 from the management server 100, and store them in the memory unit 103.

[0046] In the example of FIG. 4, the communication device 10 creates reports 200, 300 regarding the facility 2 including various indices required by the user according to the facility 2 in which the air conditioning system 3 is installed, and provides the reports to the user 21.

[0047] In this way, the communication unit 101, the control unit 102, and the storage unit 103 may be included in any of the devices included in the report creation system 1. In addition, the communication unit 101, the control unit 102, and the storage unit 103 may be distributed or provided in multiple devices.

[0048] <Hardware configuration> The communication device 10, the user terminal 20, the administrator terminal 30, and the management server 100 each have, for example, the hardware configuration of a computer 500 as shown in Fig. 5. The management server 100 may be configured by a plurality of computers 500.

[0049] 5 is a diagram showing an example of the hardware configuration of a computer according to this embodiment. The computer 500 includes, for example, a control unit 102, a memory 501, a storage device 502, a communication I / F (Interface) 503, an output device 504, an input device 505, a drive device 506, and the like.

[0050] The control unit 102 is a processor such as a CPU that realizes various functions by executing a predetermined program stored in a storage medium such as the storage device 502 or the memory 501. Note that the control unit 102 may include a processor such as a GPU (Graphics Processing Unit) or a DSP (Digital Signal Processor) in addition to the CPU.

[0051] The memory 501 includes, for example, a RAM (Random Access Memory) which is a volatile memory used as a work area or the like for the control unit 102, and a ROM (Read Only Memory) which is a non-volatile memory that stores programs for starting up the control unit 102. The storage device 502 is a non-volatile large-capacity storage device that stores an OS (Operating System), programs such as applications, and various data.

[0052] The communication I / F 503 includes various communication interfaces for communicating with other devices, such as a network interface card (NIC) that connects the computer 500 to a communication network, or a wireless communication interface that performs wireless wide area network (WAN) communication or wireless LAN communication.

[0053] The output device 504 is an output device that outputs to the outside, such as a display, a speaker, or an LED (Light Emitting Diode). The input device 505 is an input device that receives input from the outside, such as a touch panel, a keyboard, or a pointing device. Note that the output device 504 and the input device 505 may be a display input device such as a touch panel display.

[0054] The drive unit 506 is a device for connecting a storage medium (recording medium) 507 to the computer 500. The storage medium 507 here includes media that record information optically, electrically, or magnetically, such as a CD-ROM, a flexible disk, or a magneto-optical disk. The storage medium 507 may also include semiconductor memories that record information electrically, such as a ROM or a flash memory. The bus 508 is commonly connected to the above components, and transmits, for example, address signals, data signals, and various control signals.

[0055] <Processing flow> Next, the process flow of the report creation method according to this embodiment will be described.

[0056] (Report creation process) 6 is a flowchart showing an example of a report creation process according to the present embodiment. This process shows an example of a report creation process executed by the report creation system 1.

[0057] In step S601, the communication unit 101 acquires indoor environment information from the air conditioning system 3. As another example, the communication unit 101 may store the indoor environment information acquired from the air conditioning system 3 in the storage unit 103, and in step S601, the control unit 102 may acquire the indoor environment information from the storage unit 103. This indoor environment information includes, for example, measurement results of temperature, humidity, airflow, odor, and the like in the facility 2.

[0058] In step S602, the control unit 102 determines the indices to be displayed in a report to be provided to the user 21, based on the information on the facility 2 included in the facility information 111. Note that the index determination process for determining the indices to be displayed in the report will be described later with a number of examples.

[0059] FIG. 7(A) shows an image of an example of facility information 111. In the example of FIG. 7(A), the facility information 111 includes information such as "facility ID", "facility name", "user ID", "type", "number of users", "capacity", "nighttime use", "size", and "location conditions" as items. "Facility ID" is identification information that identifies facility 2. Note that the facility ID may be other names such as a property ID, a customer ID, a tenant ID, or a management ID. "Facility name" is information that indicates the name of facility 2.

[0060] The "user ID" is identification information for identifying the user 21 corresponding to the facility 2. The user ID may be another name such as a customer ID, a tenant ID, or an administrator ID. The "type" is information indicating the type of the facility 2 (for example, the use of the facility 2, the type of business of the facility 2, or the purpose of the facility 2, etc.). In the example of FIG. 7, the "type" includes educational facilities (elementary and junior high schools, high schools, universities, etc.), medical facilities (hospitals or clinics, etc.), and commercial facilities (large-scale retail facilities, supermarkets, convenience stores, etc.) in addition to the elderly care facilities and business facilities described above.

[0061] "Number of users" is information indicating the number of users using facility 2 (e.g., the number of residents in an elderly care facility, etc.). "Capacity" is the number of users that can be accommodated in facility 2. Note that "number of users" and "capacity" are examples of information on users using facility 2. User information may include other information, such as the number of users using facility 2, and the demographics of users (e.g., gender, age group, etc.).

[0062] "Nighttime use" is information indicating whether facility 2 is a facility used at night (e.g., an elderly care facility or a hotel, etc.). "Size" is information indicating the size of facility 2. "Location conditions" is information indicating the location conditions of facility 2 (e.g., near the sea or in a cold region, etc.). "Type," "Number of users," "Capacity," "Nighttime use," "Size," and "Location conditions" are examples of information regarding facility 2.

[0063] Returning now to Fig. 6, the description of the flowchart will be continued. In step S603, the control unit 102 creates a report including the indices determined in step S602 based on the indoor environment information of the facility 2 acquired in step S601 and the information about the facility 2 described above. For example, the control unit 102 creates a report including various indices required by the user 21 according to the facility 2, such as the report 200 for the elderly care facility described in Fig. 2 or the report 300 for the business facility described in Fig. 3.

[0064] In step S604, the control unit 102 provides the report created in step S603 to the user 21 corresponding to the facility 2. The method of providing the report may be, for example, that the control unit 102 transmits the report to the user terminal 20 used by the user 21, or that the user 21 uses the user terminal 20 to access a web server provided by the control unit 102 and display the report.

[0065] FIG. 7(B) shows an image of an example of user information 112. In the example of FIG. 7(B), the user information 112 includes information such as "user ID", "user name", "password", and "email address" as items. "User ID" is identification information for identifying the user 21, and corresponds to "user ID" in the facility information 111. This "user ID" enables the control unit 102 to specify the user 21 corresponding to the facility 2. "User name" is information indicating the name of the user. The user name may be various names such as, for example, a contract name, a tenant name, or an individual name.

[0066] "Password" is a password (an example of authentication information) corresponding to the user ID. For example, the control unit 102 may provide a web page for displaying the created report to the user 21 who logs in to a web server provided by the control unit 102 using the "user ID" and the "password."

[0067] The "email address" is the email address of the user 21. For example, the control unit 102 may transmit the created report or a notification indicating that the report has been updated to the user terminal 20 used by the user 21.

[0068] Through the processing of Figure 6, the report creation system 1 can create a report regarding the facility 2 including various indicators required by the user 21 according to the facility 2 in which the air conditioning system 3 is installed, and provide the created report to the user 21.

[0069] <Index determination process> Next, the index determination process executed by the control unit 102 in step S602 in FIG. 6 will be described.

[0070] [Example 1] 8 to 13 are flowcharts illustrating an example of the index determination process according to the embodiment 1. This process illustrates an example of the index determination process executed by the control unit 102 in step S602 in FIG.

[0071] In step S801, the control unit 102 determines whether the facility 2 is a facility for the elderly. For example, the control unit 102 can determine whether the facility 2 is a facility for the elderly based on the "type" of the facility information 111 as shown in FIG. 7(A). If the facility 2 is a facility for the elderly, the control unit 102 executes the processes of steps S811 to S821 (hereinafter referred to as an index determination process for the elderly facility). On the other hand, if the facility 2 is not a facility for the elderly, the control unit 102 shifts the process to step S802.

[0072] When the process proceeds to step S802, the control unit 102 determines whether or not the facility 2 is a business facility. For example, the control unit 102 can determine whether or not the facility 2 is a business facility based on the "type" of the facility information 111 as shown in Fig. 7(A). If the facility 2 is a business facility, the control unit 102 executes the process shown in Fig. 9 (hereinafter referred to as a business facility index determination process). On the other hand, if the facility 2 is not a business facility, the control unit 102 causes the process to proceed to step S803.

[0073] When the process proceeds to step S803, the control unit 102 determines whether or not the facility 2 is an educational facility. For example, the control unit 102 can determine whether or not the facility 2 is an educational facility based on the "type" of the facility information 111 as shown in FIG. 7(A). If the facility 2 is an educational facility, the control unit 102 executes the process of FIG. 10 (hereinafter referred to as an educational facility index determination process). On the other hand, if the facility 2 is not an educational facility, the control unit 102 causes the process to proceed to step S804.

[0074] When the process proceeds to step S804, the control unit 102 determines whether or not the facility 2 is a medical facility. For example, the control unit 102 can determine whether or not the facility 2 is a medical facility based on the "type" of the facility information 111 as shown in FIG. 7(A). If the facility 2 is a medical facility, the control unit 102 executes the process of FIG. 11 (hereinafter referred to as a medical facility index determination process). On the other hand, if the facility 2 is not a medical facility, the control unit 102 causes the process to proceed to step S805.

[0075] When the process proceeds to step S805, the control unit 102 determines whether or not the facility 2 is a commercial facility. For example, the control unit 102 can determine whether or not the facility 2 is a commercial facility based on the "type" of the facility information 111 as shown in FIG. 7(A). If the facility 2 is a commercial facility, the control unit 102 executes the process of FIG. 12 (hereinafter referred to as the process for determining indexes of commercial facilities). On the other hand, if the facility 2 is not a commercial facility, the control unit 102 executes the process of FIG. 13 (hereinafter referred to as the process for determining indexes of other facilities).

[0076] (Indicator determination process for elderly care facilities) Next, the process of determining an index for an elderly care facility in steps S811 to S821 in FIG. 8 will be described.

[0077] When the process proceeds to step S811, the control unit 102 determines whether or not there are many users of the facility 2. As an example, the control unit 102 calculates the population density (= number of users / occupancy capacity) of the facility 2, and determines that there are many users when the calculated population density is equal to or greater than a predetermined first threshold value. Note that the population density may be the ratio of the number of users to the size of a room, or the number of users per room, etc. When there are many users of the facility 2, the control unit 102 proceeds to step S812. On the other hand, when there are not many users of the facility 2, the control unit 102 proceeds to step S813.

[0078] In step S812, the control unit 102 selects, for example, the index with index number (3) from the index information 114 as shown in FIG. 7(C).

[0079] FIG. 7(C) shows an image of an example of index information 114. In the example of FIG. 7(C), index information 114 includes information such as "index number" and "index" as items. "Index number" is an identification number that identifies an index. "Index number" may be an index ID. "Index" is a candidate for an index to be displayed in a report created by report creation system 1.

[0080] When the process proceeds to step S813, the control unit 102 selects the indexes with index numbers (5), (7), and (8) from the above-mentioned index information 114. Here, index number (5) corresponds to, for example, the index of respiratory disease 202 included in the report 200 of Fig. 2. Index number (7) corresponds to, for example, the index of blood pressure rise 204 included in the report 200 of Fig. 2. Index number (8) corresponds to, for example, the index of nighttime temperature 205 included in the report 200 of Fig. 2.

[0081] In step S814, the control unit 102 determines whether the current season is summer or not. For example, the control unit 102 determines that it is summer if the current date is between April and October. Preferably, the control unit 102 may determine that it is summer if the facility 2 is in a warm region and the current date is between March and November. If it is summer, the control unit 102 shifts the process to step S815. On the other hand, if it is not summer, the control unit 102 shifts the process to step S816.

[0082] In step S815, the control unit 102 selects the index with index number (9) from the index information 114 described above.

[0083] When the process proceeds to step S816, the control unit 102 determines whether the current season is winter or not. For example, if the current date is between November and March, the control unit 102 determines that it is winter. Preferably, if the facility 2 is in a cold region and the current date is between October and April, the control unit 102 may determine that it is winter. If it is winter, the control unit 102 shifts the process to step S817. On the other hand, if it is not summer, the control unit 102 shifts the process to step S818.

[0084] When the process proceeds to step S817, the control unit 102 selects the indicators of index numbers (4) and (6) from the above-mentioned index information 114. Here, index number (4) corresponds to, for example, the indicator of virus 201 included in the report 200 of Fig. 2. Index number (6) corresponds to, for example, the indicator of hypothermia 203 included in the report 200 of Fig. 2. The processes of steps S814 to S817 are an example of a process in which the control unit 102 further determines (or changes) various indicators included in the report based on time information indicating the season or the season.

[0085] When the process proceeds to step S818, the control unit 102 determines whether or not the facility 2 is available for nighttime use (whether or not the facility 2 is a facility that is used at night). For example, the control unit 102 can determine whether or not the facility 2 is available for nighttime use based on the "nighttime use" information in the facility information 111 as shown in FIG. 7(A). If the facility 2 is available for nighttime use, the control unit 102 transitions the process to step S819. On the other hand, if the facility 2 is not available for nighttime use, the control unit 102 transitions the process to step S820.

[0086] In step S819, the control unit 102 selects the index with index number (8) from the above-mentioned index information 114. Here, index number (8) corresponds to, for example, the index of nighttime temperature 205 included in the report 200 in FIG.

[0087] When the process proceeds to step S820, the control unit 102 determines whether or not the ocean is close to the facility 2. For example, the control unit 102 can determine whether or not the ocean is close to the facility 2 based on the "location conditions" information in the facility information 111 as shown in Fig. 7(A). If the ocean is close, the control unit 102 proceeds to the process in step S821. On the other hand, if the ocean is not close, the control unit 102 ends the process in Fig. 8.

[0088] In step S821, the control unit 102 selects the index with index number (2) from the index information 114 described above.

[0089] Through the above process, the control unit 102 can determine various indices for the elderly care facility and create a report 200 for the elderly care facility, for example, as shown in Fig. 2. However, the process shown in Fig. 8 is only an example. The control unit 102 may determine various indices for the elderly care facility through other processes.

[0090] (Business facility index determination process) Next, a description will be given of the business facility index determination process in steps S901 to S910 in Fig. 9. Note that here, detailed description of the same process content as that described in Fig. 8 will be omitted.

[0091] In step S901, the control unit 102 selects an index having an index number (1) from the index information 114 as shown in Fig. 7(C), for example. Here, the index number (1) corresponds to the index of room temperature 303 included in the report 300 in Fig. 3, for example.

[0092] In step S902, the control unit 102 determines whether or not the ratio of female users of the facility 2 is high. For example, if the facility 2 is an office, the manager 31 or the like registers the male / female ratio and the like of the facility 2 in advance in the facility information 111. This allows the control unit 102 to determine whether or not the ratio of female users of the facility 2 is high based on the facility information 111. If the ratio of female users is high, the control unit 102 shifts the process to step S904. On the other hand, if the ratio of female users is not high, the control unit 102 shifts the process to step S903.

[0093] In step S903, the control unit 102 determines whether or not the ocean is close to the facility 2. If the ocean is close, the control unit 102 shifts the process to step S904. On the other hand, if the ocean is not close, the control unit 102 shifts the process to step S905.

[0094] In step S904, the control unit 102 selects the index with index number (2) from the index information 114 described above.

[0095] When the process proceeds to step S905, the control unit 102 judges whether or not there are many users of the facility 2. For example, the control unit 102 may judge that there are many users when the ratio of the "number of users" to the "capacity" in the facility information 111 as shown in FIG. 8(A) is equal to or greater than a predetermined second threshold. If there are many users, the control unit 102 shifts the process to step S906. On the other hand, if there are not many users, the control unit 102 shifts the process to step S907.

[0096] In step S906, the control unit 102 selects the index with index number (3) from the above-mentioned index information 114. Here, index number (3) corresponds to, for example, the index of ventilation status 302 included in the report 300 in FIG.

[0097] When the process proceeds to step S907, the control unit 102 judges whether or not it is currently in the pollen dispersion season. For example, if the current date is between March and April, or between October and November, the control unit 102 judges that it is in the pollen dispersion season. If it is in the pollen dispersion season, the control unit 102 shifts the process to step S908. On the other hand, if it is not in the pollen dispersion season, the control unit 102 shifts the process to step S909.

[0098] When the process proceeds to step S908, the control unit 102 selects the index with index number (18) from the above-mentioned index information 114. Note that the processes of steps S907 and S908 are another example of a process in which the control unit 102 further determines (or changes) various indexes included in the report based on time information indicating the season or season.

[0099] In step S909, the control unit 102 determines whether the current season is summer. If it is summer, the control unit 102 moves the process to step S910. On the other hand, if it is not summer, the control unit 102 ends the process of FIG.

[0100] In step S910, the control unit 102 selects the index with index number (9) from the index information 114 described above.

[0101] By the process of Fig. 9, the control unit 102 can determine various indices for the business facility and create a report 300 for the business facility, for example, as shown in Fig. 3. However, the process shown in Fig. 9 is only an example. The control unit 102 may determine various indices for the business facility by other processes.

[0102] (Indicator determination process for educational facilities) Next, a description will be given of the process of determining the index of an educational facility in steps S1001 to S1012 in Fig. 10. Note that detailed description of the process contents similar to those described in Figs.

[0103] In step S1001, the control unit 102 determines whether or not there are many users of the facility 2. For example, the control unit 102 may determine that there are many users when the ratio of the "number of users" to the "capacity" in the facility information 111 as shown in FIG. 8(A) is equal to or greater than a third predetermined threshold value. If there are many users, the control unit 102 shifts the process to step S1002. On the other hand, if there are not many users, the control unit 102 shifts the process to step S1003.

[0104] In step S1002, the control unit 102 selects, for example, the index with index number (3) from the index information 114 as shown in FIG. 7(C).

[0105] When the process proceeds to step S1003, the control unit 102 determines whether or not the user of the facility 2 is in the upper grades of elementary school or above. For example, if the facility 2 is a school, the administrator 31 or the like registers the grades and the like of the users of the facility 2 in the facility information 111 in advance. This allows the control unit 102 to determine whether or not the user of the facility 2 is in the upper grades of elementary school or above, based on the facility information 111. If the user is in the upper grades of elementary school or above, the control unit 102 transitions the process to step S1004. On the other hand, if the user is not in the upper grades of elementary school or above, the control unit 102 transitions the process to step S1005.

[0106] In step S1004, the control unit 102 selects the indices having index numbers (1), (2), (4), and (10) from the index information 114 described above, for example.

[0107] When the process proceeds to step S1005, the control unit 102 determines whether or not the user of the facility 2 is in the middle grades of elementary school or below. For example, if the facility 2 is a school, the administrator 31 or the like registers the grades and the like of the users of the facility 2 in the facility information 111 in advance. This allows the control unit 102 to determine whether or not the user of the facility 2 is in the middle grades of elementary school or below, based on the facility information 111. If the user is in the middle grades of elementary school or below, the control unit 102 proceeds to step S1006. On the other hand, if the user is not in the middle grades of elementary school or below, the control unit 102 proceeds to step S1007.

[0108] In step S1006, the control unit 102 selects the indices having index numbers (12), (13), (14), and (15) from the index information 114 described above, for example.

[0109] In step S1007, the control unit 102 determines whether or not the ocean is close to the facility 2. If the ocean is close, the control unit 102 shifts the process to step S1008. On the other hand, if the ocean is not close, the control unit 102 shifts the process to step S1009.

[0110] In step S1008, the control unit 102 selects, for example, the index having the index number (2) from the index information 114 described above.

[0111] In step S1009, the control unit 102 determines whether the current season is summer. If it is summer, the control unit 102 causes the process to proceed to step S1010. On the other hand, if it is not summer, the control unit 102 causes the process to proceed to step S1011.

[0112] In step S1010, the control unit 102 selects, for example, the index with index number (9) from the index information 114 described above.

[0113] In step S1011, the control unit 102 determines whether or not it is currently in the pollen dispersion season. If it is currently in the pollen dispersion season, the control unit 102 causes the process to proceed to step S1012. On the other hand, if it is not currently in the pollen dispersion season, the control unit 102 ends the process of FIG.

[0114] In step S1012, the control unit 102 selects, for example, the index having the index number (18) from the index information 114 described above.

[0115] The control unit 102 can determine various indices for an educational facility by the process of Fig. 10. However, the control unit 102 may determine various indices for an educational facility by other processes.

[0116] (Medical facility index determination process) Next, a description will be given of the process of determining an index of a medical facility in steps S1101 to S1109 in Fig. 11. Note that detailed description of the process contents similar to those described in Figs. 8 to 10 will be omitted here.

[0117] In step S1101, the control unit 102 selects the index with index number (19) from the index information 114 as shown in FIG. 7(C), for example.

[0118] In step S1102, the control unit 102 determines whether or not there are many users of the facility 2. For example, the control unit 102 may determine that there are many users when the ratio of the "number of users" to the "capacity" in the facility information 111 as shown in FIG. 8(A) is equal to or greater than a fourth predetermined threshold value. If there are many users, the control unit 102 shifts the process to step S1103. On the other hand, if there are not many users, the control unit 102 shifts the process to step S1104.

[0119] In step S1103, the control unit 102 selects the index with index number (3) from the index information 114 described above.

[0120] In step S1104, the control unit 102 determines whether or not the ocean is close to the facility 2. If the ocean is close, the control unit 102 transitions the process to step S1105. On the other hand, if the ocean is not close, the control unit 102 transitions the process to step S1106.

[0121] In step S1105, the control unit 102 selects, for example, the index having the index number (2) from the index information 114 described above.

[0122] In step S1106, the control unit 102 determines whether the current season is summer. If it is summer, the control unit 102 causes the process to proceed to step S1107. On the other hand, if it is not summer, the control unit 102 causes the process to proceed to step S1108.

[0123] In step S1107, the control unit 102 selects, for example, the index having the index number (9) from the index information 114 described above.

[0124] In step S1108, the control unit 102 determines whether or not it is currently in the pollen dispersion season. If it is currently in the pollen dispersion season, the control unit 102 causes the process to proceed to step S1109. On the other hand, if it is not currently in the pollen dispersion season, the control unit 102 ends the process of FIG.

[0125] In step S1109, the control unit 102 selects, for example, the index having the index number (18) from the index information 114 described above.

[0126] The control unit 102 can determine various indices for a medical facility by the process of Fig. 10. However, the control unit 102 may determine various indices for a medical facility by other processes.

[0127] (Indicator determination process for commercial facilities) Next, the index determination process for a commercial facility in steps S1201 to S1207 in Fig. 12 will be described. Note that the following description will be given assuming that the commercial facility is a facility that handles fresh food. Also, detailed description of the process that is the same as the process described in Figs. 8 to 11 will be omitted.

[0128] In step S1201, the control unit 102 selects the index with index number (16) from the index information 114 as shown in FIG. 7(C), for example.

[0129] In step S1202, the control unit 102 determines whether or not there are many users of the facility 2. For example, the control unit 102 may obtain information such as the degree of congestion of a commercial facility provided by an external cloud service or the like to determine whether or not there are many users of the facility 2. If there are many users, the control unit 102 shifts the process to step S1203. On the other hand, if there are not many users, the control unit 102 shifts the process to step S1204.

[0130] In step S1203, the control unit 102 selects the index with index number (3) from the index information 114 described above.

[0131] In step S1204, the control unit 102 determines whether or not the ocean is close to the facility 2. If the ocean is close, the control unit 102 transitions the process to step S1205. On the other hand, if the ocean is not close, the control unit 102 transitions the process to step S1206.

[0132] In step S1205, the control unit 102 selects, for example, the index having the index number (2) from the index information 114 described above.

[0133] In step S1206, the control unit 102 determines whether or not it is currently in the pollen dispersion season. If it is currently in the pollen dispersion season, the control unit 102 causes the process to proceed to step S1207. On the other hand, if it is not currently in the pollen dispersion season, the control unit 102 ends the process of FIG.

[0134] In step S1207, the control unit 102 selects, for example, the index having the index number (18) from the index information 114 described above.

[0135] The control unit 102 can determine various indices for a commercial facility through the process of Fig. 12. However, the control unit 102 may determine various indices for a commercial facility through other processes.

[0136] (Indicator determination process for other facilities) Next, a description will be given of the process of determining the indexes of other facilities in steps S1301 to S1308 in Fig. 13. Note that detailed description of the process contents that are the same as those described in Figs. 8 to 12 will be omitted here.

[0137] In step S1301, the control unit 102 determines whether or not there are many users of the facility 2. If there are many users, the control unit 102 shifts the process to step S1302. On the other hand, if there are not many users, the control unit 102 shifts the process to step S1303.

[0138] In step S1302, the control unit 102 selects, for example, the index with index number (3) from the index information 114 as shown in FIG. 7(C).

[0139] In step S1303, the control unit 102 determines whether or not the ocean is close to the facility 2. If the ocean is close, the control unit 102 causes the process to proceed to step S1304. On the other hand, if the ocean is not close, the control unit 102 causes the process to proceed to step S1305.

[0140] In step S1304, the control unit 102 selects, for example, the index having the index number (2) from the index information 114 described above.

[0141] In step S1305, the control unit 102 determines whether the current season is summer. If it is summer, the control unit 102 causes the process to proceed to step S1306. On the other hand, if it is not summer, the control unit 102 causes the process to proceed to step S1307.

[0142] In step S1306, the control unit 102 selects, for example, the index with index number (9) from the index information 114 described above.

[0143] In step S1307, the control unit 102 determines whether or not it is currently in the pollen dispersion season. If it is currently in the pollen dispersion season, the control unit 102 causes the process to proceed to step S1308. On the other hand, if it is not currently in the pollen dispersion season, the control unit 102 ends the process of FIG.

[0144] In step S1308, the control unit 102 selects, for example, the index having the index number (18) from the index information 114 described above.

[0145] The control unit 102 can determine various indices for other facilities by the process of Fig. 13. However, the control unit 102 may determine various indices for other facilities by other processes.

[0146] 8 to 13, the report creation system 1 can create a report about the facility 2 including various indices required by the user according to the facility 2 based on information about the facility 2 in which the air conditioning system 3 is installed.

[0147] [Example 2] The report creation system 1 may further determine (or change) various indices to be displayed in the report based on other information such as setting information by the user 21 in addition to the information related to the facility 2.

[0148] Fig. 14 is a flowchart showing an example of an index determination process according to the second embodiment. This process shows another example of the index determination process executed by the control unit 102 in step S602 in Fig. 6. Note that detailed description of the same process as in the first embodiment will be omitted here.

[0149] In step S1401, the control unit 102 determines whether the facility 2 is a facility for the elderly. If the facility 2 is a facility for the elderly, the control unit 102 transitions to step S1402. On the other hand, if the facility 2 is not a facility for the elderly, the control unit 102 transitions the process to step S1403.

[0150] In step S1402, the control unit 102 executes the elderly care facility index determination process described in steps S811 to S821 of FIG. 8, for example.

[0151] In step S1403, the control unit 102 determines whether or not the facility 2 is a business facility. If the facility 2 is a business facility, the control unit 102 shifts the process to step S1404. On the other hand, if the facility 2 is not a business facility, the control unit 102 shifts the process to step S1405.

[0152] In step S1404, the control unit 102 executes the business facility index determination process described with reference to FIG.

[0153] In step S1405, the control unit 102 determines whether or not the facility 2 is an educational facility. If the facility 2 is an educational facility, the control unit 102 shifts the process to step S1406. On the other hand, if the facility 2 is not an educational facility, the control unit 102 shifts the process to step S1407.

[0154] In step S1406, the control unit 102 executes the educational facility index determination process described with reference to FIG.

[0155] In step S1407, the control unit 102 determines whether or not the facility 2 is a medical facility. If the facility 2 is a medical facility, the control unit 102 shifts the process to step S1408. On the other hand, if the facility 2 is not a medical facility, the control unit 102 shifts the process to step S1409.

[0156] In step S1408, the control unit 102 executes, for example, the medical facility index determination process described with reference to FIG.

[0157] In step S1409, the control unit 102 determines whether or not the facility 2 is a commercial facility. If the facility 2 is a commercial facility, the control unit 102 causes the process to proceed to step S1420. On the other hand, if the facility 2 is not a commercial facility, the control unit 102 causes the process to proceed to step S1411.

[0158] In step S1410, the control unit 102 executes, for example, the process of determining an index of a commercial facility, as described in Fig. 12. On the other hand, in step S1411, the control unit 102 executes the process of determining an index of another facility, as described in Fig. 13.

[0159] After the processes of steps S1401 to S1411, in step S1421, the control unit 102 determines whether or not the visualization setting of the electricity bill is enabled. For example, the user 21 can use the user terminal 20 to log in to the management server 100 and set whether or not an index for visualizing the electricity bill is to be displayed in a report. In this case, the control unit 102 can determine whether or not the visualization setting of the electricity bill is enabled, based on the setting information set by the user 21. If the visualization setting of the electricity bill is enabled, the control unit 102 shifts the process to step S1422. On the other hand, if the visualization setting of the electricity bill is not enabled, the control unit 102 ends the process of FIG. 14.

[0160] In step S1422, the control unit 102 selects, for example, the index having the index number (11) from the index information 114 as shown in FIG. 7(C).

[0161] In this way, the report creation system 1 may determine (or change) various indices to be displayed in the report based not only on the information about the facility 2 but also on other information.

[0162] (Selection information) Preferably, the report creation system 1 stores selection information 113 for selecting an index for each type of facility 2 in the storage unit 103 or the like.

[0163] FIG. 15(A) shows an example of selection information 113a for elderly care facilities. In the example of FIG. 15(A), selection information 113a for elderly care facilities includes information such as "conditions," "selection index," and "remarks" as items. For example, when information on facility 2 satisfies the "conditions," control unit 102 uses selection information 113a for elderly care facilities to select a "selection index" corresponding to the "conditions." For example, when facility 2 satisfies the condition "many users," control unit 102 selects the index with index number (3). In addition, supplementary information and the like that is used by control unit 102 to determine whether the "conditions" are satisfied is stored in "remarks."

[0164] Preferably, the control unit 102 executes an index determination process for an elderly care facility as shown in steps S811 to S821 of FIG. 8, using elderly care facility selection information 113a as shown in FIG. 15(A).

[0165] Fig. 15(B) shows an example of business facility selection information 113b. The control unit 102 executes a business facility index determination process as shown in Fig. 9 using the business facility selection information 113b as shown in Fig. 15(B), for example.

[0166] This allows the administrator 31 to easily customize the index determination process by, for example, logging in to the management server 100 using the administrator terminal 30 and changing the selection information 113.

[0167] (Report display example) Fig. 16 is a diagram (3) showing an example of a report according to this embodiment. This diagram shows another example of the report 200 for an elderly care facility described in Fig. 2. In the example of Fig. 16, the report 200 for an elderly care facility displays various indicators such as virus 1610, respiratory disease 1620, hypothermia 1630, elevated blood pressure 1640, and nighttime temperature 1650, similar to Fig. 2. In addition, in the example of Fig. 16, the various indicators display the degree of achievement for each room (or area) in the facility 2.

[0168] For example, for the virus 1610 indicator, the achievement levels for the rooms, dining room, lobby, and hallways in the facility 2 are displayed in bar graphs 1611. In this manner, the report creation system 1 may create a report 1600 showing various indicators for each room (or area) in the facility 2, and provide it to the user 21.

[0169] (Example of indicator display) 17 and 18 are diagrams showing display examples of other indices according to this embodiment. In FIG. 17, the index of heat stroke risk 1710 corresponds to the index number (9) of the index information 114. The index of concentration level 1720 corresponds to the index number (10) of the index information 114. The index of electricity bill 1730 corresponds to the index number (11) of the index information 114. The index of allergic rhinitis 1749 corresponds to the index number (12) of the index information 114. The index of otitis media 1750 corresponds to the index number (13) of the index information 114. The index of atopic dermatitis 1760 corresponds to the index number (12) of the index information 114.

[0170] 18, the index of asthma 1819 corresponds to the index number (15) of the index information 114. The index of ventilation status 1820 shows another example of an index corresponding to the index number (3) of the index information 114.

[0171] 18, the indicator of ventilation status 1820 displays a transition 1821 of the CO2 concentration in facility 2 and an average value 1822 of the CO2 concentration (or a target value of the CO2 concentration) in other facilities of the same type as facility 2 in a comparable manner. In this way, the various indicators may display representative values ​​of indicators (or target values ​​of indicators) for other facilities that have information about the facility in common with facility 2, and indicators for facility 2.

[0172] The index of food management 1830 corresponds to index number (16) of index information 114. In the example of Fig. 18, the index of food management 1830 indicates the perishability of food in a commercial facility that handles fresh food with gauges 1831 and 1832.

[0173] As described above, according to each embodiment of the present disclosure, it becomes easy to create a report on the facility 2 in which the air conditioning system 3 is installed, the report including various indices required by the user.

[0174] <Summary> The report creation system 1 of the present disclosure is a report creation system including a communication unit 101 that acquires indoor environment information from an air conditioning system 3, and a control unit 102, and the control unit 102 creates a report (e.g., report 200, report 300, report 1600, etc.) including various indicators related to the facility 2 based on information related to the facility 2 in which the air conditioning system 3 is installed and the indoor environment information, and determines (or changes) the various indicators included in report 200, etc. based on the information related to the facility 2.

[0175] According to the present disclosure, the report creation system 1 can easily create the report 200 or the like regarding the facility 2 including various indices required by the user according to the facility 2 in which the air conditioning system 3 is installed.

[0176] Preferably, in the report creation system 1 according to the present disclosure, the information on the facility 2 includes information on the use of the facility 2, the industry of the facility 2, or the purpose of the facility 2. This allows the report creation system 1 to provide a report 200 or the like on the facility 2 that includes various more appropriate indicators depending on the use of the facility 2, the industry of the facility 2, the purpose of the facility 2, or the like.

[0177] Preferably, in the report creation system 1 according to the present disclosure, the information on the facility 2 includes information on the size of the facility 2 or the location conditions of the facility 2. This allows the report creation system 1 to provide the report 200 or the like on the facility 2 that includes various more appropriate indicators depending on the size of the facility 2, the location conditions of the facility 2, or the like.

[0178] In the report creation system 1 according to the present disclosure, the information related to the facility 2 includes information related to the number of users of the facility 2, the number of users of the facility 2, or the user demographics of the facility 2. This allows the report creation system 1 to provide a report 200 or the like related to the facility 2 that includes various more appropriate indicators depending on the number of users of the facility 2, the number of users of the facility 2, the user demographics of the facility 2, or the like.

[0179] In the report creation system 1 according to the present disclosure, the facility 2 includes an elderly care facility, a business facility, an educational facility, a medical facility, or a commercial facility.

[0180] In the report creation system 1 according to the present disclosure, the various indices include health-related indices.

[0181] In the report creation system according to the present disclosure, the health-related indicators include an indicator related to a respiratory disease, an indicator related to a viral infection, an indicator related to hypothermia, or an indicator related to heat stroke.

[0182] In the report creation system according to the present disclosure, the various indices include an index related to the air environment of the facility 2, or an index related to the electricity bill.

[0183] In the report creation system 1 according to the present disclosure, the control unit 102 further determines various indices to be included in the report 200, etc., based on time information indicating the season or season.

[0184] In the report creation system 1 according to the present disclosure, the report 200 etc. includes representative values ​​of indices for other facilities that share information about the facility 2 with the facility 2, and the indices for the facility 2.

[0185] In the report creation system 1 according to the present disclosure, the control unit 102 has a plurality of conditions, and when the conditions are satisfied, adds an index corresponding to the conditions to the report 200 or the like.

[0186] The report creation method of the present disclosure is a report creation system 1 including a communication unit 101 that acquires indoor environment information from an air conditioning system 3, and a control unit 102, in which the control unit 102 creates a report 200 etc. including various indicators related to the facility 2 based on information related to the facility 2 in which the air conditioning system 3 is installed and the indoor environment information, and determines various indicators to be included in the report 200 etc. based on information related to the two facilities.

[0187] The program of the present disclosure is provided in a report creation system 1 including a communication unit 101 that acquires indoor environment information from an air conditioning system 3, and a control unit 102, and causes the control unit 102 to execute a creation process of creating a report 200, etc. including various indicators related to the facility 2 based on information related to the facility 2 in which the air conditioning system 3 is installed and the indoor environment information, and a process of determining various indicators to be included in the report 200, etc. based on the information related to the facility 2.

[0188] Although the embodiments have been described above, it will be understood that various changes in form and details are possible without departing from the spirit and scope of the claims. [Explanation of symbols]

[0189] 1. Report creation system 2 Facilities 3. Air Conditioning System 10. Communications Equipment 20 User terminal 21 users 30 Administrator terminal 100 Management Server 101 Communications Department 102 Control section 103 Storage section 111 Facility Information 112 User Information 113, 113a, 113b Selection information 114 Indicator information 200, 300, 1600 Reports

Claims

1. A report creation system including a communication unit that acquires indoor environment information from an air conditioning system and a control unit, The control unit is creating a report including various indicators related to the facility based on information related to the facility in which the air conditioning system is installed and the indoor environment information; determining the various indicators to be included in the report based on information about the facility; Reporting system.

2. The report creation system according to claim 1 , wherein the information relating to the facility includes information relating to a use of the facility, a type of business of the facility, or a purpose of the facility.

3. The report creation system according to claim 1 , wherein the information relating to the facility includes information relating to a size of the facility or a location condition of the facility.

4. The report creation system according to claim 1 , wherein the information about the facility includes information about the number of users of the facility, the number of users of the facility, or a user demographic of the facility.

5. The report creation system of claim 1 , wherein the facility includes an elderly care facility, an office facility, an educational facility, a medical facility, or a commercial facility.

6. The report creation system according to claim 1 , wherein the various indices include an index related to health.

7. The report creation system according to claim 6 , wherein the health-related indicators include an indicator for a respiratory disease, an indicator for a viral infection, an indicator for hypothermia, or an indicator for heat stroke.

8. The report creation system according to claim 1 , wherein the various indices include an index related to an air environment of the facility or an index related to an electricity bill.

9. The report creation system according to claim 1 , wherein the control unit further determines the various indices to be included in the report based on time information indicating a season or a season.

10. The report creation system according to claim 1 , wherein the report includes representative values ​​of indices for other facilities that share information about the facility with the facility, and the indices for the facility.

11. The report creation system according to claim 1 , wherein the control unit has a plurality of conditions, and when a condition is satisfied, adds an index corresponding to the condition to the report.

12. A report creation system including a communication unit that acquires indoor environment information from an air conditioning system and a control unit, The control unit: creating a report including various indicators related to the facility based on information related to the facility in which the air conditioning system is installed and the indoor environment information; determining the various indicators to be included in the report based on information about the facility; How to create a report.

13. A report creation system including a communication unit that acquires indoor environment information from an air conditioning system and a control unit, The control unit, A process of creating a report including various indicators related to the facility based on information about the facility in which the air conditioning system is installed and the indoor environment information; determining the various indicators to be included in the report based on information about the facility; A program to execute.