Work Machine
The hydraulic excavator stabilizes work by using sensors and a control device to maintain tool position and execute damping control, addressing shaking issues and ensuring stable operation.
Patent Information
- Application Number
- JP2021016619
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-02-04
- Publication Date
- 2024-10-23
- Estimated Expiration
- 2041-02-04
AI Technical Summary
Hydraulic excavators experience instability and shaking due to ground irregularities, making stable work difficult, and existing technologies fail to adequately address this issue.
A hydraulic excavator equipped with a position sensor, attitude sensor, and inclination sensor, along with a control device that calculates and maintains the working tool's position and speed relative to a target surface, and executes damping control to attenuate shaking through a virtual spring and damper model.
The system enables stable work performance even when the excavator shakes, suppressing bucket movement and maintaining accuracy without requiring advanced operator skills.
Smart Images

Figure 0007572258000006 
Figure 0007572258000007 
Figure 0007572258000008
Abstract
Description
[Technical field]
[0001] The present invention relates to a work machine. [Background technology]
[0002] There is known a working machine such as a hydraulic excavator that includes a vehicle body consisting of a lower traveling body and an upper rotating body, and a multi-joint front working mechanism that is provided on the upper rotating body so as to be able to be raised or lowered and has a boom, an arm, and a bucket. Patent Document 1 discloses a working machine that includes a function for assisting an operator in operating the front working mechanism so that excavation is performed along a target excavation surface. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2003-105795 A Summary of the Invention [Problem to be solved by the invention]
[0004] If the ground at the work site is uneven or has steps, the work machine shakes during work, making it difficult to perform stable work. Patent Document 1 discloses a technique for shifting the front working implement upward in advance when the body of the hydraulic excavator is lifted to one side. However, the technique described in Patent Document 1 is intended to prevent the bucket from shifting downward below the target excavation surface and getting stuck there when the body returns to its original state by suddenly dropping from the lifted state, and is not a technique that can solve the above problem, and may even increase the shaking depending on the situation.
[0005] An object of the present invention is to provide a work machine that is capable of performing stable work even if the work machine shakes due to unevenness, steps, etc. on the ground at the work site. [Means for solving the problem]
[0006] A work machine according to one aspect of the present invention includes a body, a multi-joint type work device attached to the body and having a boom, an arm, and a work implement, a position sensor that detects the position of the body, an attitude sensor that detects the attitude of the work implement, an inclination sensor that detects the inclination state of the body, and a control device that sets a target plane and controls the work implement so that the work implement moves along the target plane. Calculating a position and a velocity of the work tool relative to the target surface based on the detection results of the position sensor, the detection results of the attitude sensor, and the detection results of the tilt sensor; When the work device is being controlled so that the work implement moves along the target surface, a determination is made as to whether or not the vehicle is shaking based on the detection result of the inclination sensor, and if it is determined that the vehicle is shaking, damping control of the work device is executed so as to attenuate the shaking of the work implement. In the damping control, the control device calculates a work tool target speed for damping the speed of the work tool based on a mechanical model in which the work tool is supported by a virtual spring and a virtual damper, and controls an actuator that drives the boom so that the speed of the work tool approaches the work tool target speed. Effect of the Invention
[0007] According to the present invention, it is possible to provide a work machine that is capable of performing stable work even if the work machine is shaken. [Brief description of the drawings]
[0008] [Figure 1] FIG. 1 is a perspective view of a hydraulic excavator according to an embodiment of the present invention. [Diagram 2] FIG. 1 is a schematic diagram of a hydraulic drive system mounted on a hydraulic excavator. [Diagram 3] FIG. 4 is a diagram showing the configuration of a hydraulic control unit. [Figure 4] FIG. 2 is a functional block diagram of the controller. [Diagram 5] FIG. 2 is a diagram showing the coordinate system (excavator reference coordinate system) in a hydraulic excavator. [Figure 6] 13 is a diagram showing an example of a trajectory of the tip of the bucket when the tip of the bucket is controlled according to a corrected target velocity vector Vca. FIG. [Figure 7] FIG. 13 is a diagram showing an example of horizontal excavation operation by machine control. [Figure 8]5 is a flowchart showing the contents of a process for setting an attenuation control flag executed by a controller. [Figure 9] FIG. 13 is a diagram showing a dynamic model combining a virtual spring, a virtual damper, and a virtual mass point. [Figure 10] 10A and 10B are diagrams illustrating a target surface distance set by a controller according to a modified example of the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] Hereinafter, a hydraulic excavator will be described as an example of a working machine according to an embodiment of the present invention with reference to the drawings. In each drawing, the same reference numerals are used to designate the same members, and duplicated descriptions will be omitted as appropriate.
[0010] FIG. 1 is a perspective view of a hydraulic excavator according to the present embodiment.
[0011] As shown in Fig. 1, a hydraulic excavator (working machine) 1 comprises a vehicle body (machine body) 1A and a multi-joint type front working mechanism (hereinafter simply referred to as working mechanism) 1B attached to the vehicle body 1A. The vehicle body 1A comprises a lower traveling body 11 and an upper rotating body 12 rotatably attached on the lower traveling body 11. The lower traveling body 11 is driven to travel by a right traveling motor (not shown) and a left traveling motor 3b. The upper rotating body 12 is driven to rotate by a swing hydraulic motor 4.
[0012] The working device 1B has a plurality of driven members (8, 9, 10) that are rotatably connected, and a plurality of hydraulic cylinders (5, 6, 7) that drive the driven members. In this embodiment, a boom 8, an arm 9, and a bucket 10 as three driven members are connected in series. The boom 8 has a base end portion rotatably connected to the front of the upper rotating body 12 by a boom pin 91 (see FIG. 5). The arm 9 has a base end portion rotatably connected to the tip of the boom 8 by an arm pin 92 (see FIG. 5). The bucket 10, which is a working tool, is rotatably connected to the tip of the arm 9 by a bucket pin 93 (see FIG. 5). The boom pin 91, the arm pin 92, and the bucket pin 93 are arranged parallel to one another, and the driven members (8, 9, 10) are capable of relative rotation in the same plane.
[0013] The boom 8 rotates vertically by the extension and retraction of the boom cylinder 5. The arm 9 rotates by the extension and retraction of the arm cylinder 6. The bucket 10 rotates by the extension and retraction of the bucket cylinder 7. One end of the boom cylinder 5 is connected to the boom 8, and the other end is connected to the frame of the upper rotating body 12. One end of the arm cylinder 6 is connected to the arm 9, and the other end is connected to the boom 8. One end of the bucket cylinder 7 is connected to the bucket 10 via a bucket link (link member), and the other end is connected to the arm 9.
[0014] An operator's cab 1C for an operator is provided on the front left side of the upper rotating body 12. In the operator's cab 1C, a right travel lever 13a and a left travel lever 13b for issuing operation commands to the lower traveling body 11, and a right operation lever 14a and a left operation lever 14b for issuing operation commands to the boom 8, the arm 9, the bucket 10, and the upper rotating body 12 are arranged.
[0015] A boom angle sensor 21 that detects the rotation angle of the boom 8 is attached to a boom pin 91 that connects the boom 8 to the upper rotating body 12. An arm angle sensor 22 that detects the rotation angle of the arm 9 is attached to an arm pin 92 that connects the arm 9 to the boom 8. A bucket angle sensor 23 that detects the rotation angle of the bucket 10 is attached to a bucket pin 93 that connects the bucket 10 to the arm 9. A vehicle body inclination angle sensor 24 that detects the fore-and-aft inclination angle of the upper rotating body 12 (vehicle body 1A) with respect to a reference plane (e.g., a horizontal plane) is attached to the upper rotating body 12. Angle signals output from the angle sensors 21-23 and the vehicle body inclination angle sensor 24 are input to a controller 20 (see FIG. 2) described later.
[0016] Fig. 2 is a schematic configuration diagram of the hydraulic drive system 100 mounted on the hydraulic excavator 1 shown in Fig. 1. For ease of explanation, Fig. 2 shows only parts related to the drive of the boom cylinder 5, the arm cylinder 6, the bucket cylinder 7, and the swing hydraulic motor 4, and omits parts related to the drive of other hydraulic actuators.
[0017] As shown in FIG. 2, the hydraulic drive system 100 includes hydraulic actuators (4-7), a prime mover 49, a hydraulic pump 2 and a pilot pump 48 driven by the prime mover 49, flow control valves 16a-16d that control the direction and flow rate of hydraulic oil (working fluid) supplied from the hydraulic pump 2 to the hydraulic actuators 4-7, hydraulic pilot type operating devices 15A-15D for operating the flow control valves 16a-16d, a hydraulic control unit 60, a shuttle block 46, and a controller 20 as a control device that controls each part of the hydraulic excavator 1.
[0018] The prime mover 49 is the power source of the hydraulic excavator 1 and is, for example, constituted by an internal combustion engine such as a diesel engine. The hydraulic pump 2 is equipped with a tilting swash plate mechanism (not shown) having a pair of input and output ports, and a regulator 47 that adjusts the inclination angle of the swash plate to adjust the discharge capacity (displacement volume). The regulator 47 is operated by pilot pressure supplied from a shuttle block 46, which will be described later.
[0019] The pilot pump 48 is connected to pilot pressure control valves 52-59 and a hydraulic control unit 60, which will be described later, via a lock valve 51. The lock valve 51 opens and closes in response to the operation of a gate lock lever (not shown) provided near the entrance of the cab 1C. When the gate lock lever is operated to a position (pushed-down position) that restricts the entrance of the cab 1C, the lock valve 51 opens in response to a command from the controller 20. This allows the discharge pressure of the pilot pump 48 (hereinafter, pilot primary pressure) to be supplied to the pilot pressure control valves 52-59 and the hydraulic control unit 60, enabling the operation of the flow control valves 16a-16d by the operating devices 15A-15D. On the other hand, when the gate lock lever is operated to a position (pushed-up position) that opens the entrance of the cab 1C, the lock valve 51 closes in response to a command from the controller 20. As a result, the supply of pilot primary pressure from the pilot pump 48 to the pilot pressure control valves 52-59 and the hydraulic control unit 60 stops, and operation of the flow rate control valves 16a-16d by the operating devices 15A-15D becomes impossible.
[0020] The operation device 15A is an operation device that operates the boom 8 (boom cylinder 5), and has a boom operation lever 15a, a boom-raising pilot pressure control valve 52, and a boom-lowering pilot pressure control valve 53. Here, the boom operation lever 15a corresponds to the right operation lever 14a (see FIG. 1) when operated in the forward / rearward direction, for example.
[0021] The boom-raising pilot pressure control valve 52 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, boom-raising pilot pressure) corresponding to the lever stroke (hereinafter, operation amount) of the boom operation lever 15a in the boom-raising direction. The boom-raising pilot pressure output from the boom-raising pilot pressure control valve 52 is guided to one pilot pressure receiving portion (left side in the figure) of the boom flow control valve 16a via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 529, and drives the boom flow control valve 16a to the right in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the bottom side of the boom cylinder 5, and the hydraulic oil on the rod side is discharged to the tank 50, and the boom cylinder 5 extends.
[0022] The boom-lowering pilot pressure control valve 53 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, boom-lowering pilot pressure) according to the amount of operation of the boom operation lever 15a in the boom-lowering direction. The boom-lowering pilot pressure output from the boom-lowering pilot pressure control valve 53 is guided to the other pilot pressure receiving portion (right side in the figure) of the boom flow control valve 16a via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 539, and drives the boom flow control valve 16a to the left in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the rod side of the boom cylinder 5, and the hydraulic oil on the bottom side is discharged to the tank 50, and the boom cylinder 5 is contracted.
[0023] The operating device 15B is an operating device that operates the arm 9 (arm cylinder 6), and has an arm operating lever 15b, an arm crowding pilot pressure control valve 54, and an arm dumping pilot pressure control valve 55. Here, the arm operating lever 15b corresponds to the left operating lever 14b (see FIG. 1) when operated in the left / right direction, for example.
[0024] The arm crowding pilot pressure control valve 54 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, referred to as arm crowding pilot pressure) according to the operation amount of the arm operating lever 15b in the arm crowding direction. The arm crowding pilot pressure output from the arm crowding pilot pressure control valve 54 is guided to one pilot pressure receiving portion (left side in the figure) of the arm flow control valve 16b via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 549, and drives the arm flow control valve 16b in the right direction in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the bottom side of the arm cylinder 6, and the hydraulic oil on the rod side is discharged to the tank 50, and the arm cylinder 6 extends.
[0025] The arm dumping pilot pressure control valve 55 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, referred to as arm dumping pilot pressure) according to the amount of operation of the arm operating lever 15b in the arm dump direction. The arm dumping pilot pressure output from the arm dumping pilot pressure control valve 55 is guided to the other pilot pressure receiving portion (right side in the figure) of the arm flow control valve 16b via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 559, and drives the arm flow control valve 16b in the left direction in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the rod side of the arm cylinder 6, and the hydraulic oil on the bottom side is discharged to the tank 50, and the arm cylinder 6 contracts.
[0026] The operating device 15C is an operating device that operates the bucket 10 (bucket cylinder 7) and has a bucket operating lever 15c, a bucket crowding pilot pressure control valve 56, and a bucket dumping pilot pressure control valve 57. Here, the bucket operating lever 15c corresponds to the right operating lever 14a (see FIG. 1) when operated in the left-right direction, for example.
[0027] The bucket crowding pilot pressure control valve 56 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, bucket crowding pilot pressure) according to the operation amount of the bucket operation lever 15c in the bucket crowding direction. The bucket crowding pilot pressure output from the bucket crowding pilot pressure control valve 56 is guided to one pilot pressure receiving portion (left side in the figure) of the bucket flow control valve 16c via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 569, and drives the bucket flow control valve 16c in the right direction in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the bottom side of the bucket cylinder 7, and the hydraulic oil on the rod side is discharged to the tank 50, and the bucket cylinder 7 extends.
[0028] The pilot pressure control valve 57 for bucket dump reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, pilot pressure for bucket dump) corresponding to the amount of operation of the bucket operation lever 15c in the bucket dump direction. The pilot pressure for bucket dump output from the pilot pressure control valve 57 for bucket dump is guided to the other pilot pressure receiving portion (right side in the figure) of the bucket flow control valve 16c via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 579, and drives the bucket flow control valve 16c in the leftward direction in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 is supplied to the rod side of the bucket cylinder 7, and the hydraulic oil on the bottom side is discharged to the tank 50, and the bucket cylinder 7 contracts.
[0029] The operation device 15D has a turning operation lever 15d, a right turning pilot pressure control valve 58, and a left turning pilot pressure control valve 59. Here, the turning operation lever 15d corresponds to the left operating lever 14b (see FIG. 1) when operated in the forward / rearward direction, for example.
[0030] The right-turn pilot pressure control valve 58 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, right-turn pilot pressure) according to the operation amount of the swing operation lever 15d in the right swing direction. The right-turn pilot pressure output from the right-turn pilot pressure control valve 58 is led to one pilot pressure receiving portion (right side in the figure) of the swing flow control valve 16d via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 589, and drives the swing flow control valve 16d to the left in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 flows into one inlet / outlet port (right side in the figure) of the swing hydraulic motor 4, and the hydraulic oil flowing out from the other inlet / outlet port (left side in the figure) is discharged to the tank 50, and the swing hydraulic motor 4 rotates in one direction (the direction to swing the upper swing body 12 to the right).
[0031] The left-turn pilot pressure control valve 59 reduces the pilot primary pressure supplied via the lock valve 51, and generates a pilot pressure (hereinafter, left-turn pilot pressure) according to the operation amount of the left-turn direction of the swing operation lever 15d. The left-turn pilot pressure output from the left-turn pilot pressure control valve 59 is led to the other (left side in the figure) pilot pressure receiving portion of the swing flow control valve 16d via the hydraulic control unit 60, the shuttle block 46, and the pilot piping 599, and drives the swing flow control valve 16d in the right direction in the figure. As a result, the hydraulic oil discharged from the hydraulic pump 2 flows into the other (left side in the figure) inlet / outlet port of the swing hydraulic motor 4, and the hydraulic oil flowing out from the one (right side in the figure) inlet / outlet port is discharged to the tank 50, and the swing hydraulic motor 4 rotates in the other direction (the direction to swing the upper swing body 12 left).
[0032] The hydraulic control unit 60 is a device for executing machine control (MC), and corrects the pilot pressure input from the pilot pressure control valves 52-57 in response to a command from the controller 20, and outputs the corrected pilot pressure to the shuttle block 46. This makes it possible to cause the working implement 1B to perform a desired operation regardless of the lever operation by the operator.
[0033] Shuttle block 46 outputs the pilot pressure input from hydraulic control unit 60 to pilot pipes 529, 539, 549, 559, 569, and 579. In addition, shuttle block 46 selects the maximum pilot pressure from the input pilot pressures and outputs it to regulator 47 of hydraulic pump 2. This makes it possible to control the discharge flow rate of hydraulic pump 2 in accordance with the amount of operation of operation levers 15a to 15d.
[0034] FIG. 3 is a configuration diagram of the hydraulic control unit 60 shown in FIG.
[0035] As shown in FIG. 3, the hydraulic control unit 60 includes an electromagnetic cutoff valve 61, shuttle valves 522, 534, 564, and 574, and electromagnetic proportional valves 525, 532, 537, 542, 552, 562, 567, 572, and 577.
[0036] The inlet port of the solenoid cutoff valve 61 is connected to the outlet port of the lock valve 51 (see FIG. 2). The outlet port of the solenoid cutoff valve 61 is connected to the inlet ports of the solenoid proportional valves 525, 537, 567, and 577. The solenoid cutoff valve 61 has an opening of zero when de-energized, and has an opening of maximum when current is supplied from the controller 20. When machine control is enabled, the opening of the solenoid cutoff valve 61 is set to maximum, and the supply of pilot primary pressure to the solenoid proportional valves 525, 537, 567, and 577 is started. On the other hand, when machine control is disabled, the opening of the solenoid cutoff valve 61 is set to zero, and the supply of pilot primary pressure to the solenoid proportional valves 525, 537, 567, and 577 is stopped.
[0037] Switching between enabling and disabling machine control is performed based on an operation signal from an MC switch 26 (see FIG. 2) provided in the operator's cab 1C. The MC switch 26 is, for example, an alternate action switch provided on the right operation lever 14a or the left operation lever 14b. When an operation signal for enabling machine control is input from the MC switch 26, the controller 20 supplies a control current to the solenoid of the electromagnetic cutoff valve 61, and maximizes the opening of the electromagnetic cutoff valve 61. When an operation signal for disabling machine control is input from the MC switch 26, the controller 20 stops supplying the control current to the solenoid of the electromagnetic cutoff valve 61, and sets the opening of the electromagnetic cutoff valve 61 to zero.
[0038] The shuttle valve 522 has two inlet ports and one outlet port, and outputs the higher pressure of the pressures input from the two inlet ports from the outlet port. One inlet port of the shuttle valve 522 is connected to the boom-raising pilot pressure control valve 52 via pilot piping 521. The other inlet port of the shuttle valve 522 is connected to the outlet port of the solenoid proportional valve 525 via pilot piping 524. The outlet port of the shuttle valve 522 is connected to the shuttle block 46 via pilot piping 523.
[0039] The inlet port of the electromagnetic proportional valve 525 is connected to the outlet port of the electromagnetic cutoff valve 61. The outlet port of the electromagnetic proportional valve 525 is connected to the other inlet port of the shuttle valve 522 via the pilot pipe 524. The electromagnetic proportional valve 525 has an opening of zero when de-energized, and increases its opening in response to the current supplied from the controller 20. The electromagnetic proportional valve 525 reduces the pilot primary pressure supplied via the electromagnetic cutoff valve 61 in response to the opening, and outputs it to the pilot pipe 524. This makes it possible to supply the boom-raising pilot pressure to the pilot pipe 523 even when the boom-raising pilot pressure is not supplied from the boom-raising pilot pressure control valve 52 to the pilot pipe 521. Note that when machine control for the boom-raising operation is not executed, the electromagnetic proportional valve 525 is in a de-energized state, and the opening of the electromagnetic proportional valve 525 is zero. At this time, the boom-raising pilot pressure supplied from the boom-raising pilot pressure control valve 52 is led to one pilot pressure receiving portion of the boom flow control valve 16a, enabling the boom to be raised in response to the lever operation by the operator.
[0040] The shuttle valve 534 has two inlet ports and one outlet port, and outputs the higher pressure of the pressures input from the two inlet ports from the outlet port. One inlet port of the shuttle valve 534 is connected to the outlet port of the electromagnetic proportional valve 532 via a pilot pipe 533. The other inlet port of the shuttle valve 534 is connected to the outlet port of the electromagnetic proportional valve 537 via a pilot pipe 536. The outlet port of the shuttle valve 534 is connected to the shuttle block 46 via a pilot pipe 535.
[0041] An inlet port of the solenoid proportional valve 532 is connected to the boom-lowering pilot pressure control valve 53 via a pilot pipe 531. An outlet port of the solenoid proportional valve 532 is connected to one inlet port of a shuttle valve 534 via a pilot pipe 533. The solenoid proportional valve 532 opens to the maximum when de-energized, and reduces the opening from the maximum to zero in response to the current supplied from the controller 20. The solenoid proportional valve 532 reduces the boom-lowering pilot pressure input via the pilot pipe 531 in response to the opening, and outputs it to the pilot pipe 533. This makes it possible to reduce the boom-lowering pilot pressure or set it to zero by operating the lever by the operator.
[0042] The inlet port of the electromagnetic proportional valve 537 is connected to the outlet port of the electromagnetic cutoff valve 61, and the outlet port of the electromagnetic proportional valve 537 is connected to the other inlet port of the shuttle valve 534 via a pilot pipe 536. The electromagnetic proportional valve 537 has an opening of zero when de-energized, and increases its opening according to the current supplied from the controller 20. The electromagnetic proportional valve 537 reduces the pilot primary pressure supplied via the electromagnetic cutoff valve 61 according to its opening, and outputs it to the pilot pipe 536. This makes it possible to supply the boom-lowering pilot pressure to the pilot pipe 535 even when the boom-lowering pilot pressure control valve 53 does not supply the boom-lowering pilot pressure to the pilot pipe 531. Note that when machine control for the boom-lowering operation is not executed, the electromagnetic proportional valves 532 and 537 are in a de-energized state, the opening of the electromagnetic proportional valve 532 is fully open, and the opening of the electromagnetic proportional valve 537 is zero. At this time, the boom lowering pilot pressure supplied from the boom lowering pilot pressure control valve 53 is led to the other pilot pressure receiving portion of the boom flow control valve 16a, making it possible to lower the boom in response to the lever operation by the operator.
[0043] An inlet port of the solenoid proportional valve 542 is connected to the arm crowding pilot pressure control valve 54 via a pilot pipe 541. An outlet port of the solenoid proportional valve 542 is connected to the shuttle block 46 via a pilot pipe 543. The solenoid proportional valve 542 has a maximum opening when de-energized, and decreases the opening from the maximum to zero according to the current supplied from the controller 20. The solenoid proportional valve 542 reduces the pilot pressure for the arm crowding input via the pilot pipe 541 according to the opening, and outputs it to the pilot pipe 543. This makes it possible to reduce or set the pilot pressure for the arm crowding by the lever operation of the operator. When machine control for the arm crowding operation is not executed, the solenoid proportional valve 542 is in a non-energized state, and the opening of the solenoid proportional valve 542 is fully open. At this time, the pilot pressure for the arm crowding supplied from the arm crowding pilot pressure control valve 54 is led to one pilot pressure receiving portion of the arm flow control valve 16b, so that the arm crowding operation according to the lever operation of the operator is possible.
[0044] An inlet port of the electromagnetic proportional valve 552 is connected to the arm dump pilot pressure control valve 55 via a pilot pipe 551. An outlet port of the electromagnetic proportional valve 552 is connected to the shuttle block 46 via a pilot pipe 553. The electromagnetic proportional valve 552 has a maximum opening when de-energized, and decreases the opening from the maximum to zero according to the current supplied from the controller 20. The electromagnetic proportional valve 552 reduces the arm dump pilot pressure input via the pilot pipe 551 according to the opening, and outputs it to the pilot pipe 553. This makes it possible to reduce the arm dump pilot pressure or set it to zero by the lever operation of the operator. Note that when machine control for the arm dump operation is not executed, the electromagnetic proportional valve 552 is in a de-energized state, and the opening of the electromagnetic proportional valve 552 is fully open. At this time, the arm dump pilot pressure supplied from the arm dump pilot pressure control valve 55 is led to the other pilot pressure receiving portion of the arm flow control valve 16b, so that the arm dump operation according to the lever operation of the operator is possible.
[0045] The shuttle valve 564 has two inlet ports and one outlet port, and outputs the higher pressure of the pressures input from the two inlet ports from the outlet port. One inlet port of the shuttle valve 564 is connected to the outlet port of the solenoid proportional valve 562 via a pilot pipe 563. The other inlet port of the shuttle valve 564 is connected to the outlet port of the solenoid proportional valve 567 via a pilot pipe 566. The outlet port of the shuttle valve 564 is connected to the shuttle block 46 via a pilot pipe 565.
[0046] An inlet port of the solenoid proportional valve 562 is connected to the bucket crowding pilot pressure control valve 56 via a pilot pipe 561. An outlet port of the solenoid proportional valve 562 is connected to one inlet port of a shuttle valve 564 via a pilot pipe 563. The solenoid proportional valve 562 opens to the maximum when de-energized, and decreases the opening from the maximum to zero in response to the current supplied from the controller 20. The solenoid proportional valve 562 reduces the bucket crowding pilot pressure input via the pilot pipe 561 in response to the opening, and outputs it to the pilot pipe 563. This makes it possible to reduce the bucket crowding pilot pressure or set it to zero by the operator's lever operation.
[0047] The inlet port of the electromagnetic proportional valve 567 is connected to the outlet port of the electromagnetic cutoff valve 61, and the outlet port of the electromagnetic proportional valve 567 is connected to the other inlet port of the shuttle valve 564 via a pilot pipe 566. The electromagnetic proportional valve 567 has an opening of zero when de-energized, and increases its opening according to the current supplied from the controller 20. The electromagnetic proportional valve 567 reduces the pilot primary pressure supplied via the electromagnetic cutoff valve 61 according to its opening, and outputs it to the pilot pipe 566. This makes it possible to supply the pilot pressure for bucket crowding to the pilot pipe 565 even when the pilot pressure for bucket crowding is not supplied from the pilot pressure control valve 56 for bucket crowding to the pilot pipe 561. Note that when machine control for the bucket crowding operation is not executed, the electromagnetic proportional valves 562 and 567 are in a de-energized state, the opening of the electromagnetic proportional valve 562 is fully open, and the opening of the electromagnetic proportional valve 567 is zero. At this time, the pilot pressure for bucket crowding supplied from the pilot pressure control valve 56 for bucket crowding is led to one pilot pressure receiving portion of the bucket flow rate control valve 16c, enabling the bucket crowding operation in response to the lever operation by the operator.
[0048] The shuttle valve 574 has two inlet ports and one outlet port, and outputs the higher pressure of the pressures input from the two inlet ports from the outlet port. One inlet port of the shuttle valve 574 is connected to the outlet port of the electromagnetic proportional valve 572 via a pilot pipe 573. The other inlet port of the shuttle valve 574 is connected to the outlet port of the electromagnetic proportional valve 577 via a pilot pipe 576. The outlet port of the shuttle valve 574 is connected to the shuttle block 46 via a pilot pipe 575.
[0049] An inlet port of the electromagnetic proportional valve 572 is connected to the pilot pressure control valve 57 for bucket dumping via a pilot pipe 571. An outlet port of the electromagnetic proportional valve 572 is connected to one inlet port of a shuttle valve 574 via a pilot pipe 573. The electromagnetic proportional valve 572 has a maximum opening when de-energized, and reduces the opening from the maximum to zero in accordance with the current supplied from the controller 20. The electromagnetic proportional valve 572 reduces the pilot pressure for bucket dumping input via the pilot pipe 571 in accordance with the opening, and supplies the reduced pressure to the pilot pipe 573. This makes it possible to reduce the pilot pressure for bucket dumping or set it to zero by the operator operating the lever.
[0050] An inlet port of the electromagnetic proportional valve 577 is connected to an outlet port of the electromagnetic cutoff valve 61. An outlet port of the electromagnetic proportional valve 577 is connected to the other inlet port of the shuttle valve 574 via a pilot pipe 576. The electromagnetic proportional valve 577 sets the opening to zero when de-energized, and increases the opening according to the current supplied from the controller 20. The electromagnetic proportional valve 577 reduces the pilot primary pressure supplied via the electromagnetic cutoff valve 61 according to the opening and supplies it to the pilot pipe 576. This makes it possible to supply the pilot pressure for bucket dump to the pilot pipe 575 even when the pilot pressure for bucket dump is not supplied from the pilot pressure control valve 57 for bucket dump to the pilot pipe 571. Note that when machine control for the bucket dump operation is not executed, the electromagnetic proportional valves 572 and 577 are in a de-energized state, the opening of the electromagnetic proportional valve 572 is fully opened, and the opening of the electromagnetic proportional valve 577 is zero. At this time, the pilot pressure for bucket dumping supplied from the pilot pressure control valve 57 for bucket dumping is led to the other pilot pressure receiving portion of the bucket flow control valve 16c, enabling a bucket dump operation in response to the lever operation by the operator.
[0051] The pilot pipe 521 is provided with a pressure sensor 526 that detects the boom-raising pilot pressure supplied from the boom-raising pilot pressure control valve 52. The pilot pipe 531 is provided with a pressure sensor 538 that detects the boom-lowering pilot pressure supplied from the boom-lowering pilot pressure control valve 53. The pilot pipe 541 is provided with a pressure sensor 544 that detects the arm crowding pilot pressure supplied from the arm crowding pilot pressure control valve 54. The pilot pipe 551 is provided with a pressure sensor 554 that detects the arm dumping pilot pressure supplied from the arm dumping pilot pressure control valve 55. The pilot pipe 561 is provided with a pressure sensor 568 that detects the bucket crowding pilot pressure supplied from the bucket crowding pilot pressure control valve 56. The pilot pipe 571 is provided with a pressure sensor 578 that detects the bucket dumping pilot pressure supplied from the bucket dumping pilot pressure control valve 57. The pilot pressures detected by the pressure sensors 526, 538, 544, 554, 568, and 578 are input to the controller 20 as operation signals that indicate the operation direction and operation amount of the operation devices 15A to 15C.
[0052] 2, the controller 20 is composed of a microcomputer including a CPU (Central Processing Unit) 20a as an operating circuit, a ROM (Read Only Memory) 20b as a storage device, a RAM (Random Access Memory) 20c as a storage device, an input interface 20d, an output interface 20e, and other peripheral circuits. The controller 20 may be composed of one microcomputer or multiple microcomputers.
[0053] The ROM 20b is a non-volatile memory such as an EEPROM, and stores programs capable of executing various calculations. In other words, the ROM 20b is a storage medium capable of reading programs that realize the functions of this embodiment. The RAM 20c is a volatile memory, and is a work memory that directly inputs and outputs data to and from the CPU 20a. The RAM 20c temporarily stores necessary data while the CPU 20a is executing the program. The controller 20 may further include a storage device such as a flash memory or a hard disk drive.
[0054] The CPU 20 is a processing device that loads a program stored in the ROM 20b into the RAM 20c and executes calculations, and performs predetermined calculations on signals received from the input interface 20d, the ROM 20b, and the RAM 20c in accordance with the program. Signals from the MC switch 26, the attitude detection device 34, the target plane setting device 35, the operation detection device 36, the GNSS antenna 27, etc. are input to the input interface 20d.
[0055] The attitude detection device 34 has a boom angle sensor 21 (see FIG. 1), an arm angle sensor 22 (see FIG. 1), and a bucket angle sensor 23 (see FIG. 1) as attitude sensors that detect the attitude of the working device 1B, and a vehicle body inclination angle sensor 24 (see FIG. 1) as an inclination sensor that detects the inclination state of the vehicle body 1A. The operation detection device 36 has pressure sensors 526, 538, 544, 554, 568, 578 (see FIG. 3).
[0056] The input interface 20d converts the input signal so that it can be calculated by the CPU 20a. The output interface 20e generates an output signal according to the calculation result by the CPU 20a, and outputs the signal to the proportional solenoid valves 525, 532, 537, 542, 552, 562, 567, 572, 577 and the solenoid cutoff valve 61, etc.
[0057] The controller 20 executes machine control when a predetermined condition is satisfied when any of the operating devices 15A, 15B, 15C is operated (for example, when an arm operation is performed). In the machine control, the controller 20 outputs a control signal for driving the corresponding flow control valves 16a, 16b, 16c to the hydraulic control unit 60. For example, the controller 20 extends the boom cylinder 5 and forcibly performs a boom-up operation by outputting a control signal for operating the flow control valve 16a to the electromagnetic proportional valve 525 (see FIG. 3). The machine control includes, for example, an area limiting control (ground leveling control) that is executed when the arm operation is performed by the operating device 15B, and a stop control that is executed when the boom lowering operation is performed by the operating device 15A without performing the arm operation.
[0058] As shown in FIG. 7, the controller 20 controls at least one of the hydraulic actuators (5, 6, 7) so that the tip (e.g., the toe) of the bucket 10 is positioned on or above a predetermined target surface St. In the area limiting control, the operation of the working implement 1B is controlled so that the tip of the bucket 10 moves along the target surface St by the arm operation. Specifically, when the arm is being operated, the controller 20 issues a command to raise or lower the boom so that the velocity vector of the toe of the bucket 10 in the direction perpendicular to the target surface St becomes zero. The area limiting control is performed when the distance between the toe of the bucket 10 and the target surface St becomes smaller than a predetermined distance Ya1 (see FIG. 6) with the machine control enabled by the MC switch 26.
[0059] In this embodiment, the control point of the working device 1B used in the machine control is set to the tip of the bucket 10 of the hydraulic excavator 1, but the control point can be changed to a point other than the tip of the bucket 10 as long as it is a point at the tip of the working device 1B. For example, the bottom surface of the bucket 10 or the outermost part of the bucket link may be set as the control point. A configuration may be adopted in which a point on the outer surface of the bucket 10 that is closest to the target surface St is appropriately set as the control point. In the machine control, there are "automatic control" in which the operation of the working device 1B is controlled by the controller 20 when the operating devices 15A, 15B, and 15C are not operated, and "semi-automatic control" in which the operation of the working device 1B is controlled by the controller 20 only when the operating devices 15A, 15B, and 15C are operated. Note that the semi-automatic control is also called "intervention control" because the control by the controller 20 intervenes in the operation by the operator.
[0060] FIG. 4 is a functional block diagram of the controller 20 shown in FIG.
[0061] 4, the controller 20 executes a program stored in the ROM 20b to function as an attitude calculation unit 30, a target surface setting unit 31, a target motion calculation unit 32, a solenoid valve control unit 33, a damping control flag setting unit 71, and a damping target speed calculation unit 72. The solenoid proportional valve 500 shown in FIG. 4 is representative of the solenoid proportional valves 525, 532, 537, 542, 552, 562, 567, 572, and 577 (see FIG. 3).
[0062] The posture calculation unit 30 calculates the posture of the working device 1B based on the posture information from the posture detection device 34. The posture calculation unit 30 calculates the position of the tip of the bucket 10 (hereinafter also referred to as the tip position) Pb in a local coordinate system (shovel reference coordinates) based on the posture information from the posture detection device 34 and geometric information of the working device 1B stored in the ROM 20b (for example, lengths L1, L2, L3 of the driven members shown in FIG. 5).
[0063] The posture of the working device 1B can be defined based on the shovel reference coordinate system of Fig. 5. Fig. 5 is a diagram showing a coordinate system (shovel reference coordinate system) in the hydraulic excavator 1. The shovel reference coordinate system of Fig. 5 is a coordinate system set with respect to the upper rotating body 12, with the central axis of the boom pin 91 as the origin, an axis parallel to the central axis of the upper rotating body 12 as the Y axis, and an axis perpendicular to the Y axis and the boom pin 91 as the X axis. The inclination angle of the boom 8 with respect to the X axis is defined as the boom angle α, the inclination angle of the arm 9 with respect to the boom 8 as the arm angle β, and the inclination angle of the bucket 10 with respect to the arm 9 as the bucket angle γ. The inclination angle of the vehicle body 1A (upper rotating body 12) with respect to the horizontal plane (reference plane), i.e., the angle between the horizontal plane (reference plane) and the X axis, is defined as the vehicle body inclination angle θ. The boom angle α is detected by a boom angle sensor 21 , the arm angle β by an arm angle sensor 22 , the bucket angle γ by a bucket angle sensor 23 , and the vehicle body inclination angle θ by a vehicle body inclination angle sensor 24 .
[0064] If the length from the center position of the boom pin 91 to the center position of the arm pin 92 is L1, the length from the center position of the arm pin 92 to the center position of the bucket pin 93 is L2, and the length from the center position of the bucket pin 93 to the tip (end) of the bucket 10 is L3, the tip position Pb of the bucket 10 in the shovel reference coordinate system is bk is the X-axis position, and Y is the bk is the Y-direction position, and can be expressed by the following equations (1) and (2).
[0065]
number
[0066]
number
[0067] The hydraulic excavator 1 is equipped with a pair of GNSS (Global Navigation Satellite System) antennas 27 (27A, 27B) on the upper rotating body 12. The GNSS antenna 27 functions as a position sensor that detects the position of the vehicle body 1A. The controller 20 calculates the position and orientation of the upper rotating body 12 in the global coordinate system based on information from the GNSS antenna 27. The controller 20 calculates the toe position Pb of the bucket 10 in the global coordinate system based on the vehicle body inclination angle θ detected by the vehicle body inclination angle sensor 24, the position and orientation of the upper rotating body 12 in the global coordinate system, and the toe position Pb of the bucket 10 in the local coordinate system.
[0068] Furthermore, in addition to the toe position Pb, the posture calculation unit 30 also calculates the positions in the global coordinate system of the boom pin 91, arm pin 92, and bucket pin 93 which indicate the posture of the working device 1B, and outputs this information to the respective units (31, 32, 71, 72) as posture information of the hydraulic excavator 1. In addition to the calculation results, the posture calculation unit 30 outputs the angles (α, β, γ, θ) detected by the posture detection device 34 as posture information to the respective units (31, 32, 71, 72).
[0069] The target plane setting unit 31 sets the target plane St based on information (three-dimensional data) from the target plane setting device 35 and the attitude information from the attitude calculation unit 30. Here, the target plane setting device 35 is connected to an external terminal (not shown) that stores three-dimensional data of the target plane defined on the global coordinate system (absolute coordinate system). The input of the target plane via the target plane setting device 35 may be performed manually by an operator. Based on the attitude information (attitude of the working device 1B in the global coordinate system) from the attitude calculation unit 30, the target plane setting unit 31 sets the cross-sectional shape obtained by cutting the three-dimensional target plane with a plane on which the working device 1B moves (operation plane (XY plane) of the working device) as the target plane St (two-dimensional target plane).
[0070] Based on information from the posture calculation unit 30, the target plane setting unit 31 and the operation detection device 36, the target motion calculation unit 32 calculates a target motion of the working device 1B so that the bucket 10 moves without entering the target plane St.
[0071] Specifically, the target motion calculation unit 32 calculates the target speed of each hydraulic cylinder (5, 6, 7) based on the target surface St set by the target surface setting unit 31, the calculation result (attitude information) of the attitude calculation unit 30, and the detection result (operation information) of the operation detection device 36. The target motion calculation unit 32 calculates the target speed of each hydraulic cylinder (5, 6, 7) in the area limit control so that the lower side of the target surface St is not excavated by the working device 1B. Hereinafter, a detailed description will be given with reference to FIG. 6. FIG. 6 is a diagram showing an example of a trajectory of the tip of the bucket 10 when the tip of the bucket 10 is controlled according to the corrected target speed vector Vca. In the description here, the Xt axis and the Yt axis are set as shown in FIG. 6. The Xt axis is an axis parallel to the target surface St, and the Yt axis is an axis perpendicular to the target surface St.
[0072] The target motion calculation unit 32 calculates a target speed (primary target speed) of each hydraulic cylinder (5, 6, 7) based on the operation amount of the operation devices 15A, 15B, 15C. Next, the target motion calculation unit 32 calculates a target speed vector Vca0 of the tip (tip) of the bucket 10 based on the target speed (primary target speed) of each hydraulic cylinder (5, 6, 7), the tip position Pb of the bucket 10 calculated by the posture calculation unit 30, posture information (α, β, γ) of the working device 1B, and the dimensions (L1, L2, L3, etc.) of each part of the working device 1B stored in the ROM 20b. In addition, the target motion calculation unit 32 calculates a distance in the Yt axis direction (also referred to as a target surface distance) between the tip position Pb of the bucket 10 calculated by the posture calculation unit 30 and the target surface St set by the target surface setting unit 31.
[0073] The target motion calculation unit 32 performs control (direction conversion control) to convert the velocity vector of the tip of the bucket 10 to Vca by correcting the primary target velocity of the necessary hydraulic cylinders among the hydraulic cylinders (5, 6, 7) so that the component Vcay (velocity component in the Yt axis direction) perpendicular to the target surface St in the target velocity vector Vca0 of the tip of the bucket 10 approaches 0 (zero) as the target surface distance approaches 0 (zero) and calculating the secondary target velocity. When the target surface distance is 0 (zero), the target velocity vector Vca has only the component Vcax (velocity component in the Xt axis direction) parallel to the target surface St. This keeps the tip of the bucket 10 (control point) positioned at or above the target surface St.
[0074] For example, when the arm crowd is operated alone and the target plane distance becomes equal to or less than a predetermined distance Ya1 (i.e., when the tip of the bucket 10 enters a set area formed by the target plane St and a plane that is Ya1 away from the target plane St in the Yt axis direction), the target movement calculation unit 32 extends the arm cylinder 6 and also extends the boom cylinder 5, thereby executing direction change control to convert the velocity vector Vca0 to Vca.
[0075] The direction change control may be performed by a combination of boom raising or boom lowering and arm crowding, or may be performed by a combination of boom raising or boom lowering and arm dumping. In either case, when the tip of the bucket 10 is located above the target surface St and the target speed vector Vca includes a downward component (Vcay<0) approaching the target surface St, the target motion calculation unit 32 calculates a target speed of the boom cylinder 5 in the boom raising direction that cancels out the downward component. Conversely, when the target speed vector Vca includes an upward component (Vcay>0) moving away from the target surface St, the target motion calculation unit 32 calculates a target speed of the boom cylinder 5 in the boom lowering direction that cancels out the upward component. Also, when the tip of the bucket 10 is located below the target surface St and the target speed vector Vca includes an upward component (Vcay>0) approaching the target surface St, the target motion calculation unit 32 calculates a target speed of the boom cylinder 5 in the boom lowering direction that cancels out the upward component. Conversely, when the target velocity vector Vca includes an upward component (Vcay<0) moving away from the target surface St, the target motion calculation unit 32 calculates a target velocity of the boom cylinder 5 in the boom raising direction that cancels out the downward component.
[0076] The solenoid valve control unit 33 outputs commands to the solenoid cutoff valve 61 and the solenoid proportional valve 500 based on the calculation results (target speeds of the hydraulic cylinders) of the target motion calculation unit 32.
[0077] An example of the operation of the hydraulic excavator 1 when machine control is executed will be described with reference to Fig. 7. Fig. 7 is a diagram showing an example of a horizontal excavation operation by machine control.
[0078] When the operator performs an independent boom lowering operation using the operating device 15A to place the bucket 10 at a predetermined position (excavation start point) at the start of excavation work, stop control is executed by the controller 20. When the bucket 10 approaches the target level St, the controller 20 controls the solenoid proportional valve 532 (see FIG. 3) to decelerate the speed of the boom 8 so that the bucket 10 does not enter below the target level St. When the bucket 10 has reached the target level St, the controller 20 controls the solenoid proportional valve 532 (see FIG. 3) so that the speed of the boom 8 becomes zero.
[0079] When the operator operates the operating device 15B to perform horizontal excavation by pulling the arm 9 in the direction of the arrow A (crowd operation), the controller 20 executes area restriction control. The controller 20 controls the solenoid proportional valve 525 (see FIG. 3) to automatically perform the lifting operation of the boom 8 so that the tip of the bucket 10 does not enter below the target surface St. At this time, in order to improve the excavation accuracy, the solenoid proportional valve 542 (see FIG. 3) may be controlled to reduce the speed of the arm 9 as necessary. Note that the controller 20 may control the solenoid proportional valve 577 (see FIG. 3) so that the bucket 10 automatically rotates in the direction of the arrow C so that the angle B of the bucket 10 with respect to the target surface St becomes a constant value and the leveling work becomes easy.
[0080] When performing horizontal excavation by pulling the arm 9 in the direction of arrow A, if the bucket 10 penetrates below the target level St, the controller 20 controls the electromagnetic proportional valve 525 (see Figure 3) to automatically perform a raising operation of the boom 8 so that the bucket 10 returns to above the target level St.
[0081] In this manner, the controller 20 controls the working device 1B so that the tip (end) of the bucket 10 moves along the target surface St.
[0082] Incidentally, if the ground contact surface of the vehicle body 1A of the hydraulic excavator 1 is uneven or has steps, the vehicle body 1A may repeatedly sway back and forth during work. For example, if the vehicle body 1A repeatedly sways back and forth during horizontal excavation, the toe (tip) of the bucket 10 may move in a wavy manner. For this reason, the controller 20 according to this embodiment determines whether the vehicle body 1A is swaying or not while controlling the working device 1B so that the bucket 10 moves along the target surface St, and if it is determined that the vehicle body 1A is swaying, executes damping control of the working device 1B so as to damp the swinging of the bucket 10.
[0083] The contents of the damping control will be described in detail below with reference to Figures 4, 8 and 9. A damping control flag setting unit 71 shown in Figure 4 sets a damping control flag based on the vehicle body inclination angle θ detected by the vehicle body inclination angle sensor 24, the target plane St set by the target plane setting unit 31, and the tiptoe position Pb of the bucket 10 calculated by the attitude calculation unit 30. The damping control flag is a flag for determining whether or not to execute damping control, and when it is set on, damping control is executed, and when it is set off, damping control is not executed.
[0084] The details of the damping control flag setting process performed by the damping control flag setting unit 71 will be described with reference to the flowchart in Fig. 8 and the model diagram in Fig. 9. As shown in Fig. 9, the direction perpendicular to the target surface St is defined as the z direction. Fig. 8 is a flowchart showing the details of the damping control flag setting process executed by the controller 20. The process of the flowchart shown in Fig. 8 is started when the machine control is enabled by the MC switch 26, and after initial setting (not shown) is performed, it is repeatedly executed at a predetermined control period. In the initial setting, the damping control flag is set to off.
[0085] As shown in FIG. 8, in step S110, the damping control flag setting unit 71 acquires the vehicle body inclination angle θ detected by the vehicle body inclination angle sensor 24, the toe position Pb of the bucket 10 calculated by the posture calculation unit 30, and the target surface St set by the target surface setting unit 31, and proceeds to step S120.
[0086] In step S120, the damping control flag setting unit 71 calculates the distance (target surface distance) Z in the z direction between the toe position Pb of the bucket 10 and the target surface St based on the information (θ, Pb, St) acquired in step S110, and proceeds to step S125. As shown in FIG. 9, the target surface distance Z is a relative distance of the toe (tip) of the bucket 10 with respect to the target surface St. The damping control flag setting unit 71 calculates it by subtracting the z direction coordinate of the target surface St facing the toe position Pb in the z direction from the z direction coordinate of the toe position Pb of the bucket 10. For this reason, the target surface distance Z is a positive value when the toe of the bucket 10 is located above the target surface St, and is a negative value when the toe of the bucket 10 is located below the target surface St.
[0087] 8, in step S125, the damping control flag setting unit 71 calculates the relative velocity (hereinafter also referred to as the tip velocity) Vz in the z direction of the tip (leading end) of the bucket 10 with respect to the target surface St based on the target surface distance Z calculated in step S120, and proceeds to step S130. The damping control flag setting unit 71 calculates the tip velocity Vz (=(Zb-Za) / (tb-ta)), which is the time rate of change of the target surface distance Z, by dividing the difference (Zb-Za) between the previous value Za (for example, the value calculated in step S120 of the previous calculation cycle) of the target surface distance Z, which is repeatedly calculated in a predetermined control period, and the current value Zb, by the time Δt (=tb-ta) from the time ta when the previous value Za is acquired to the time tb when the current value Zb is acquired. The time is measured by a timer function of the controller 20.
[0088] In step S130, the damping control flag setting unit 71 calculates the tilt angular velocity ω, and the process proceeds to step S140. The damping control flag setting unit 71 calculates the tilt angular velocity ω (=(θb-θa) / (tb-ta)), which is the time rate of change of the vehicle body tilt angle θ, by dividing the difference (θb-θa) between the previous value θa of the vehicle body tilt angle θ (for example, the value acquired in step S110 of the previous calculation cycle) θa, which is repeatedly acquired in a predetermined control period, and the current value θb, by the time Δt (=tb-ta) from the time ta when the previous value θa was acquired to the time tb when the current value θb was acquired.
[0089] In step S140, the attenuation control flag setting unit 71 determines whether the magnitude (i.e., absolute value |ω|) of the tilt angular velocity ω calculated in step S130 is equal to or greater than a predetermined value ω0. If it is determined in step S140 that the absolute value |ω| of the tilt angular velocity ω is equal to or greater than the predetermined value ω0, the process proceeds to step S150. If it is determined in step S140 that the absolute value |ω| of the tilt angular velocity ω is less than the predetermined value ω0, the process proceeds to step S160.
[0090] The predetermined value ω0 (>0) is a threshold value for determining whether or not swaying has occurred in the vehicle body 1A, and is stored in advance in the ROM 102. In other words, the process of step S140 can be said to be a determination process for determining whether or not the vehicle body 1A is swaying based on the inclination angular velocity ω calculated from the detection result of the vehicle body inclination angle sensor 24. In step S140, if the absolute value |ω| of the inclination angular velocity ω is equal to or greater than the predetermined value ω0, the damping control flag setting unit 71 determines that the vehicle body 1A is swaying, and proceeds to step S150. In step S140, if the absolute value |ω| of the inclination angular velocity ω is less than the predetermined value ω0, the damping control flag setting unit 71 determines that the vehicle body 1A is not swaying, and proceeds to step S160.
[0091] In step S150, the attenuation control flag setting unit 71 sets the attenuation control flag to ON, and the process shown in the flowchart of FIG. 8 ends.
[0092] In step S160, the attenuation control flag setting unit 71 determines whether the absolute value |Z| of the target surface distance Z calculated in step S120 is less than a predetermined distance Z0. If it is determined in step S160 that the absolute value |Z| of the target surface distance Z is less than the predetermined distance Z0, the process proceeds to step S170. If it is determined in step S160 that the absolute value |Z| of the target surface distance Z is equal to or greater than the predetermined distance Z0, the process shown in the flowchart of FIG. 8 ends.
[0093] The predetermined distance Z0 (>0) is a threshold value for determining whether or not the tip of the bucket 10 has deviated from the set area where area restriction control is performed. The predetermined distance Z0 is set in advance to a value equal to the width Ya1 (see FIG. 6) based on the target surface St in the set area where area restriction control is performed. In other words, the process of step S160 can be said to be a determination process for determining whether or not the tip of the bucket 10 has deviated from the set area where area restriction control is performed based on the relative position (relative distance) of the tip of the bucket 10 with respect to the target surface St.
[0094] In step S160, if the absolute value |Z| of the target surface distance Z is equal to or greater than the predetermined distance Z0, the attenuation control flag setting unit 71 determines that the tip of the bucket 10 has deviated from the set area, and ends the processing shown in the flowchart of Fig. 8. In step S160, if the absolute value |Z| of the target surface distance Z is less than the predetermined distance Z0, the attenuation control flag setting unit 71 determines that the tip of the bucket 10 has not deviated from the set area, and proceeds to step S170.
[0095] In step S170, the attenuation control flag setting unit 71 determines whether the magnitude of the toe velocity Vz calculated in step S125 (i.e., the absolute value |Vz|) is less than a predetermined velocity V0. If it is determined in step S170 that the absolute value |Vz| of the toe velocity Vz is less than the predetermined velocity V0, the process proceeds to step S180. If it is determined in step S170 that the absolute value |Vz| of the toe velocity Vz is equal to or greater than the predetermined velocity V0, the process shown in the flowchart in FIG. 8 ends.
[0096] The predetermined speed V0 (>0) is set as a threshold value for determining whether or not there is a risk that the tip of the bucket 10 will deviate from the set area in which the area limit control is performed. The predetermined speed V0 is determined in advance by an experiment or the like, and is stored in the ROM 102.
[0097] In other words, the process of step S170 can be regarded as a determination process for determining whether or not there is a risk that the toe of the bucket 10 will deviate from the set area in which area restriction control is performed, based on the relative speed of the bucket 10 with respect to the target surface St.
[0098] In step S170, if the absolute value |Vz| of the toe speed Vz is equal to or greater than the predetermined speed V0, the damping control flag setting unit 71 determines that there is a risk that the toe of the bucket 10 will deviate from the set area, and ends the processing shown in the flowchart of Fig. 8. In step S170, if the absolute value |Vz| of the toe speed Vz is less than the predetermined speed V0, the damping control flag setting unit 71 determines that there is no risk that the toe of the bucket 10 will deviate from the set area, and proceeds to step S180.
[0099] In step S180, the attenuation control flag setting unit 71 sets the attenuation control flag to OFF, and ends the process shown in the flowchart of FIG.
[0100] Next, the contents of the calculation process of the bucket target speed performed by the damping target speed calculation unit 72 (see FIG. 4) will be described with reference to Fig. 9. Fig. 9 is a diagram showing a dynamic model combining a virtual spring 81, a virtual damper 82, and a virtual mass point 83. The damping target speed calculation unit 72 calculates a bucket target speed (work tool target speed) for damping the toe speed Vz, which is the speed of the bucket 10 in the z direction (the up-down direction in the figure), using the dynamic model (virtual model) combining the virtual spring 81, the virtual damper 82, and the virtual mass point 83, and calculates a boom target speed based on the bucket target speed. This will be described in detail below.
[0101] As shown in Figure 9, the virtual model according to this embodiment is a mechanical model in which a virtual mass point 83, which is a virtual mass point, is provided at the tip of the bucket 10, and the virtual mass point 83 is supported by a virtual spring 81, which is a virtual spring provided along the z direction, and a virtual damper 82, which is a virtual damper.
[0102] The equation of motion of such a dynamic model is expressed by the following equation (3), where M is the mass of the virtual mass point 83, D is the damping coefficient of the virtual damper 82, and K is the spring constant of the virtual spring 82.
[0103]
number
[0104] By transforming and integrating equation (3), the velocity Z′ of the virtual mass point 83 in the z direction is expressed by the following equation (4).
[0105]
number
[0106] The mass M of the virtual mass point 83, the spring constant K of the virtual spring 81, and the damping coefficient D of the virtual damper 82 are determined in advance by experiments or the like, and are stored in the ROM 102. It is preferable that the mass M, the spring constant K, and the damping coefficient D are set so that the damping ratio ζ is equal to or greater than 1. The damping ratio ζ is expressed by the following equation (5).
[0107]
number
[0108] This makes it possible to prevent the tip of the bucket 10 from overshooting the target surface St when the tip of the bucket 10 approaches the target surface St due to the damping operation of the boom 8 described below. As a result, it is possible to prevent the induction of shaking due to the reaction of the damping operation of the boom 8, and it is possible to converge the tip of the bucket 10 to the target surface St.
[0109] The damping target speed calculation unit 72 acquires the target surface distance Z calculated in step S120 of Fig. 8 as Z to be multiplied by the spring constant K on the right side of equation (4), and acquires the toe velocity Vz calculated in step S125 of Fig. 8 as Z' to be multiplied by the damping coefficient D on the right side of equation (4). The damping target speed calculation unit 72 calculates the z-directional velocity Z' of the virtual mass point 83 constituting the left side of equation (4) as the bucket target speed Vzt, based on the acquired Z and Z' and the constants (mass M, spring constant K and damping coefficient D) stored in ROM 102. That is, the controller 20 according to this embodiment calculates the bucket target speed Vzt for damping the toe velocity Vz of the bucket 10, based on a dynamic model in which the bucket 10 is supported by the virtual spring 81 and the virtual damper 82.
[0110] Specifically, the damping target speed calculation unit 72 acquires the target surface distance Z(t) calculated in step S120 in the calculation cycle when the damping control flag is switched from off to on as the initial value Z(0). The damping target speed calculation unit 72 acquires the toe speed Vz (=Z(t)') calculated in step S125 in the calculation cycle when the damping control flag is switched from off to on as the initial value Z(0)'. The damping target speed calculation unit 72 calculates the initial value Z''(0) of the acceleration Z(t)'' using equation (3) based on the initial values Z(0) and Z(0)'.
[0111] Damping target speed calculation unit 72 uses equation (3) to repeatedly calculate acceleration Z(t)" at a predetermined control period, and calculates speed Z(t)' by adding the previous value (acceleration Z(t)" calculated in the immediately preceding calculation cycle) to the current value. For example, after calculating an initial value of acceleration Z", the speed Z' in the next calculation cycle is calculated by adding the initial value as the previous value to the acceleration Z" calculated in that calculation cycle.
[0112] The damping target speed calculation unit 72 calculates the speed Z' of the virtual mass point 83 in the z direction until the damping control flag is set to off, and performs initialization processing to set the speed Z' to 0 (zero) when the damping control flag is set to off. The damping target speed calculation unit 72 sets the calculated speed Z' as the bucket target speed Vzt of the bucket 10 in the z direction.
[0113] The damping target speed calculation unit 72 calculates a target speed (target angular velocity) of the boom 8 so that the toe speed Vz of the bucket 10 approaches the bucket target speed Vzt. The target angular velocity of the boom 8 can be calculated using inverse kinematics based on the bucket target speed Vzt, the attitude information of the working implement 1B, and the dimensional data of the working implement 1B.
[0114] The damping target speed calculation unit 72 calculates the target speed of the boom cylinder 5 based on the target angular velocity of the boom 8, the boom angle α detected by the posture detection device 34, and the dimensional data representing the relationship between the boom 8 and the boom cylinder 5 stored in ROM 102.
[0115] When the damping control flag setting unit 71 sets the damping control flag to ON, the target movement calculation unit 32 corrects the secondary target speed of the boom cylinder 5 by adding the target speed of the boom cylinder 5 calculated by the damping target speed calculation unit 72 to the secondary target speed of the boom cylinder 5 described above. The target movement calculation unit 32 outputs the corrected secondary target speed to the solenoid valve control unit 33. The solenoid valve control unit 33 controls the solenoid proportional valve 525 or the solenoid proportional valve 537 so that the boom cylinder 5 operates at the corrected secondary target speed. As a result, the boom cylinder 5 is controlled so that the toe speed Vz of the bucket 10 approaches the bucket target speed Vzt, and a damping operation of the boom 8 is performed to damp the swinging of the bucket 10.
[0116] When the damping control flag is switched from on to off, the target movement calculation unit 32 does not correct the secondary target speed of the boom cylinder 5. When the damping control flag is switched from on to off, if the target surface distance is equal to or less than a predetermined distance Ya1, normal area limiting control is executed.
[0117] According to the above-described embodiment, the following advantageous effects are obtained.
[0118] (1) A hydraulic excavator (working machine) 1 includes a vehicle body (machine body) 1A, an articulated working device 1B attached to the vehicle body 1A and having a boom 8, an arm 9, and a bucket (working implement) 10, a GNSS antenna (position sensor) 27 for detecting the position of the vehicle body 1A, attitude sensors (boom angle sensor 21, arm angle sensor 22, and bucket angle sensor 23) for detecting the attitude of the working device 1B, a vehicle body inclination angle sensor (inclination sensor) 24 for detecting a vehicle body inclination angle θ representing the inclination state of the vehicle body 1A, and a controller (control device) 20 for setting a target plane St and controlling the working device 1B so that the bucket 10 moves along the target plane St. When controlling the working device 1B so that the bucket 10 moves along the target plane St, the controller 20 determines whether the vehicle body 1A is swaying based on the detection result of the vehicle body inclination angle sensor 24, and when it is determined that the vehicle body 1A is swaying, executes damping control of the working device 1B so as to damp the swing of the bucket 10.
[0119] As a result, even if the vehicle body 1A sways due to unevenness, steps, or the like on the ground surface of the vehicle body 1A while the bucket 10 is moving along the target surface St (while machine control is being executed), it is possible to suppress the swaying of the toe (tip) of the bucket 10. In other words, according to this embodiment, it is possible to provide a hydraulic excavator 1 that is capable of stable work even if the hydraulic excavator 1 sways. Furthermore, since the swaying of the toe of the bucket 10 is automatically suppressed when the vehicle body 1A sways, no advanced operating technique is required. Therefore, even an operator with little experience can easily perform work with high precision.
[0120] (2) Controller 20 calculates the toe position Pb and toe velocity Vz of bucket 10 based on target plane St, based on the detection results of GNSS antenna 27, the detection results of the attitude sensors (angle sensors 21-23), and the detection result of vehicle body inclination angle sensor 24. Controller 20 calculates bucket target velocity Vzt for attenuating the toe velocity Vz of bucket 10. Controller 20 controls boom cylinder (actuator) 5 that drives boom 8 so that the toe velocity Vz of bucket 10 approaches bucket target velocity Vzt.
[0121] According to this embodiment, it is possible to damp the swinging of the bucket 10 by driving the boom 8. Therefore, according to this embodiment, compared to the case where the swinging of the bucket 10 is damped by driving the arm 9, it is possible to reduce the change in the angle of the bucket 10 caused by the damping operation of the driven member, thereby enabling more stable work.
[0122] (3) The controller 20 calculates the bucket target speed (work tool target speed) Vzt based on a dynamic model in which the bucket (work tool) 10 is supported by a virtual spring 81 and a virtual damper 82. This makes it possible to appropriately suppress the swinging of the bucket 10. In addition, by adjusting the mass M of the virtual mass point 81, the spring constant K of the virtual spring 81, and the damping coefficient D of the virtual damper 82, the degree of damping can be adjusted.
[0123] (4) The controller 20 calculates the inclination angular velocity ω of the vehicle body 1A based on the detection result of the vehicle body inclination angle sensor 24 (step S130 in FIG. 8), and if the inclination angular velocity ω of the vehicle body 1A is greater than a predetermined value ω0 (Y in step S140), it determines that the vehicle body 1A is shaking and executes damping control (step S150). Even if the inclination angular velocity ω of the vehicle body 1A is less than the predetermined value ω0 (N in step S140) after executing the damping control, the controller 20 continues the damping control if the distance (target surface distance) Z between the bucket 10 and the target surface St is equal to or greater than the predetermined distance Z0 (N in step S160).
[0124] As a result, even if the shaking of the vehicle body 1A has subsided, if the tip of the bucket 10 is away from the target surface St, the tip of the bucket 10 can be brought closer to the target surface St while continuing the damping control. Therefore, for example, if the tip of the bucket 10 is above the target surface St by a predetermined distance Z0 or more, the damping operation of the boom 8 is continued to move the tip of the bucket 10 into the set region, thereby making it possible to smoothly return to normal region limiting control.
[0125] (5) Furthermore, after executing the damping control, the controller 20 continues the damping control if the toe speed Vz of the bucket 10 is equal to or greater than the predetermined speed V0 (N in step S170), even if the inclination angular velocity ω of the vehicle body 1A is smaller than the predetermined value ω0 (N in step S140).
[0126] This makes it possible to suppress the tip of the bucket 10 from moving away from the target surface St by the predetermined distance Z0 or more when the tip speed Vz of the bucket 10 is high, even when the shaking of the vehicle body 1A has subsided. As a result, it is possible to prevent the tip of the bucket 10 from moving far away from the target surface St or from biting into the target surface St by a large amount.
[0127] The following modified examples are also within the scope of the present invention, and it is possible to combine the configurations shown in the modified examples with the configurations described in the above-mentioned embodiments, or to combine the configurations described in the different modified examples below.
[0128] <Variation 1> In the above embodiment, an example has been described in which the vehicle body inclination angle sensor 24 is provided as an inclination sensor that detects the inclination state of the vehicle body 1A, but the present invention is not limited to this. Instead of the vehicle body inclination angle sensor 24, a sensor that detects the inclination angular velocity ω and the inclination angular acceleration ω' as the inclination state of the vehicle body 1A may be provided. For example, an IMU (Inertial Measurement Unit) can be adopted as the inclination sensor. The IMU detects the angular velocity and acceleration of three orthogonal axes of a member to which it is attached, and outputs the detection results to the controller. In this case, the controller calculates the vehicle body inclination angle θ based on the detection results of the IMU.
[0129] <Variation 2> In the above embodiment, an example has been described in which the boom angle sensor 21, the arm angle sensor 22, and the bucket angle sensor 23 are provided as posture sensors that detect the posture of the working implement 1B, but the present invention is not limited to this. An IMU may be provided as a posture sensor as in Modification 1, and the controller may calculate the boom angle α, the arm angle β, and the bucket angle γ based on the detection results of the IMU.
[0130] <Variation 3> In the above embodiment, an example has been described in which the predetermined distance Z0 is the same value as the width Ya1 of the set area, but the present invention is not limited to this. For example, the predetermined distance Z0 may be a value less than the width Ya1 of the set area. In this case, the predetermined distance Z0 is set as a threshold value for determining whether or not there is a risk that the tip of the bucket 10 will deviate from the set area in which area limit control is performed. The predetermined distance Z0 is determined in advance by an experiment or the like, and is stored in the ROM 102.
[0131] In other words, in this modified example, the processing of step S160 in FIG. 8 can be considered as a determination process in which it is determined whether or not there is a risk that the tip of the bucket 10 will deviate from the set area in which area restriction control is performed, based on the position of the tip of the bucket 10 relative to the target surface St.
[0132] In step S160, if the absolute value |Z| of the target surface distance Z is equal to or greater than the predetermined distance Z0, the damping control flag setting unit 71 determines that there is a risk that the tip of the bucket 10 will deviate from the set area, and ends the processing shown in the flowchart of Fig. 8. In step S160, if the absolute value |Z| of the target surface distance Z is less than the predetermined distance Z0, the damping control flag setting unit 71 determines that there is no risk that the tip of the bucket 10 will deviate from the set area, and proceeds to step S170.
[0133] <Variation 4> In the above embodiment, an example has been described in which the height (width) Ya1 of the set area above the target surface St and the depth (width) Ya1 of the set area below the target surface St have the same value, but the present invention is not limited to this. The height of the set area above the target surface St and the depth of the set area below the target surface St may have different values. In this case, as the threshold value Z0 for determining whether the tip of the bucket 10 has deviated from the set area in which the area limiting control is performed, it is preferable to set the upper threshold value Z0a and the lower threshold value Z0b individually so that their absolute values are different. The upper threshold value Z0a (>0) is a threshold value used when the tip position Pb of the bucket 10 is located above the target surface St, and the lower threshold value Z0b is a threshold value used when the tip position Pb of the bucket 10 is located below the target surface St.
[0134] In this case, in step S160 of Fig. 8, the controller 20 judges whether the target surface distance Z is greater than the lower threshold Z0b and less than the upper threshold Z0a. If it is judged in step S160 that the target surface distance Z is greater than the lower threshold Z0b and less than the upper threshold Z0a, the process proceeds to step S170. If it is judged in step S160 that the target surface distance Z is equal to or less than the lower threshold Z0b, or if it is judged that the target surface distance Z is equal to or greater than the upper threshold Z0a, the process shown in the flowchart of Fig. 8 is terminated.
[0135] <Variation 5> In the above embodiment, an example has been described in which the controller 20 determines whether or not the absolute value |Vz| of the toe velocity Vz is less than the predetermined velocity V0 in step S170 in Fig. 8, but the present invention is not limited to this. The first velocity threshold V0a (>0) used when the vector direction of the toe velocity Vz is upward and the second velocity threshold V0b (<0) used when the vector direction of the toe velocity Vz is downward may be different values.
[0136] In this case, in step S170, the controller 20 determines whether the toe speed Vz is greater than the second speed threshold V0b and less than the first speed threshold V0a. If it is determined in step S170 that the toe speed Vz is greater than the second speed threshold V0b and less than the first speed threshold V0a, the process proceeds to step S180. If it is determined in step S170 that the toe speed Vz is equal to or less than the second speed threshold V0b, or if it is determined that the toe speed Vz is equal to or greater than the first speed threshold V0a, the process shown in the flowchart of FIG. 8 ends.
[0137] <Variation 6> 8 described in the above embodiment may be omitted. In this case, when it is determined in step S140 that the absolute value |ω| of the tilt angular velocity ω is less than the predetermined value ω0, the process proceeds to step S180, where the damping control flag is set to OFF and the damping control ends.
[0138] <Variation 7> In the above embodiment, an example has been described in which the mass M of the virtual mass point 81, the spring constant K of the virtual spring 81, and the damping coefficient D of the virtual damper 82 are stored in advance in the ROM 102, but the present invention is not limited to this. The mass M, the spring constant K, and the damping coefficient D may be changed to any value by an operator operating an input device (such as a touch panel) connected to the controller 20.
[0139] <Variation 8> In the above embodiment, an example has been described in which the direction perpendicular to the target surface St is defined as the z direction, and the z direction distance between the toe position Pb of the bucket 10 and the target surface St is defined as the target surface distance Z, but the present invention is not limited to this. For example, as shown in Fig. 10, when the target surface St is inclined with respect to a reference surface (horizontal plane), the vertical direction (direction of gravity) may be defined as the z direction, and the z direction distance between the toe position Pb of the bucket 10 and the target surface St may be defined as the target surface distance Z to calculate the bucket target velocity Vzt.
[0140] <Variation 9> In the above embodiment, an example has been described in which controller 20 operates boom 8 to attenuate the swinging of bucket 10 when it is determined that vehicle body 1A is swinging, but the present invention is not limited to this. Controller 20 may operate arm 9 to attenuate the swinging of bucket 10 when it is determined that vehicle body 1A is swinging.
[0141] <Modification 10> In the above embodiment, the working machine is a crawler type hydraulic excavator 1, but the present invention is not limited to this. The present invention can be applied to various working machines that drive multiple driven members with actuators, such as wheeled hydraulic excavators and backhoes.
[0142] <Modification 11> In the above embodiment, the operating devices 15A to 15D are hydraulic pilot type operating devices, but the present invention is not limited to this. An electric operating device may be provided, and the flow control valves 16a to 16d may be driven by a controller controlling the electromagnetic proportional valves based on an electric signal from the operating device.
[0143] <Modification 12> In the above embodiment, an example has been described in which the actuators that drive the boom 8, the arm 9, and the bucket 10 are hydraulic cylinders, but the present invention is not limited to this. The actuators that drive the boom 8, the arm 9, and the bucket 10 may be electric cylinders.
[0144] <Modification 13> Some or all of the functions of the control device (controller 20) described in the above embodiment may be realized by hardware (for example, by designing logic for executing each function in an integrated circuit).
[0145] Although the embodiments of the present invention have been described above, the above-mentioned embodiments merely show some of the application examples of the present invention, and it is not intended that the technical scope of the present invention be limited to the specific configurations of the above-mentioned embodiments. [Explanation of symbols]
[0146] 1...hydraulic excavator (working machine), 1A...vehicle body (machine body), 1B...working device, 5...boom cylinder (actuator), 8...boom, 9...arm, 10...bucket (working tool), 15A, 15B, 15C...operating device, 20...controller (control device), 24...vehicle body inclination angle sensor (inclination sensor), 27...GNSS antenna (position sensor), 81...virtual mass point, 82...virtual damper, 83...virtual mass point, D...damping coefficient, K...spring constant, M...mass, Pb...toe position, St...target surface, V0...predetermined speed, Vz...toe speed (relative speed), Vzt...bucket target speed (working tool target speed), Z...target surface distance (distance), Z0...predetermined distance, θ...vehicle body inclination angle (inclination state), ω...inclination angular velocity (inclination state), ω'...inclination angular acceleration (inclination state), ω0...predetermined value
Claims
1. A work machine including a body, a multi-joint type working device attached to the body and having a boom, an arm, and a working tool, a position sensor that detects the position of the body, an attitude sensor that detects the attitude of the working device, an inclination sensor that detects the inclination state of the body, and a control device that sets a target plane and controls the working device so that the working tool moves along the target plane, The control device includes: Calculating a position and a velocity of the work tool relative to the target surface based on the detection results of the position sensor, the detection results of the attitude sensor, and the detection results of the tilt sensor; determining whether the vehicle body is shaking based on a detection result of the tilt sensor while the working device is being controlled so that the working tool moves along the target surface; When it is determined that the vehicle body is shaking, a damping control of the working device is executed so as to damp the shaking of the working device; The control device, in the damping control, Calculating a work tool target velocity for damping the velocity of the work tool based on a dynamic model in which the work tool is supported by a virtual spring and a virtual damper; controlling an actuator that drives the boom so that the speed of the work implement approaches the work implement target speed; A working machine characterized by:
2. 2. The work machine according to claim 1, The control device includes: Calculating an inclination angular velocity of the aircraft based on the detection result of the inclination sensor; When the tilt angular velocity of the airframe is greater than a predetermined value, it is determined that the airframe is shaking and the damping control is executed; Even if the tilt angular velocity of the machine body is smaller than the predetermined value after the damping control is executed, the damping control is continued when the distance between the work tool and the target surface is equal to or greater than a predetermined distance. A working machine characterized by:
3. 2. The work machine according to claim 1, The control device includes: Calculating an inclination angular velocity of the aircraft based on the detection result of the inclination sensor; When the tilt angular velocity of the airframe is greater than a predetermined value, it is determined that the airframe is shaking and the damping control is executed; After executing the damping control, even if the tilt angular velocity of the machine body is smaller than the predetermined value, the damping control is continued when the speed of the work tool is equal to or greater than a predetermined speed. A working machine characterized by:
Citation Information
Patent Citations
Work attachment stop control device for construction machinery
JP1999117346A
Drilling control device of hydraulic shovel
JP2003105795A
Excavation control system for hydraulic shovel
JP2015007370A
Shovel, and vibration damping method for shovel
JP2016166505A
Construction machine
JP2019090185A