Air conditioning system
The air conditioning system addresses discomfort during defrosting by managing temperature and humidity through a combined heat storage operation in an indoor unit and floor heating system, ensuring comfort by preventing excessive temperature and humidity changes.
Patent Information
- Application Number
- JP2021188395
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-11-19
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2041-11-19
AI Technical Summary
Conventional air conditioning systems experience discomfort due to excessive room temperature rise during defrosting, leading to dryness and reduced humidity, which impairs heating comfort.
An air conditioning system with an indoor unit and floor heating operation, utilizing a water-refrigerant heat exchanger and a heat storage operation to manage temperature and humidity by circulating hot water and refrigerant through multiple circuits, adjusting temperatures and times to maintain comfort during defrosting.
The system effectively maintains comfort by distributing heat storage over multiple targets, preventing excessive temperature rise and humidity drop, thus enhancing user comfort during defrosting operations.
Smart Images

Figure 0007579771000001 
Figure 0007579771000002 
Figure 0007579771000003
Abstract
Description
[Technical field]
[0001] The present invention relates to an air conditioning system that performs linked operation of a hot air heating operation of an indoor unit and a floor heating operation of a heat exchange terminal. [Background technology]
[0002] This type of air conditioner performs a defrosting operation to remove frost from the air heat exchanger, and some air conditioners perform a pre-defrosting operation before the defrosting operation to raise the room temperature in advance, thereby preventing a loss of the feeling of warmth. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2016-017725 A Summary of the Invention [Problem to be solved by the invention]
[0004] In this conventional system, the room temperature is controlled to be raised in advance by performing a pre-defrost operation. However, when the room temperature alone is raised to prevent the loss of feeling of warmth during defrosting, the room temperature may rise too much, causing a feeling of heat. In addition, if the room temperature rises too much, the relative humidity decreases, causing the room to become dry, resulting in a loss of comfort. [Means for solving the problem]
[0005] In order to solve the above problem, in claim 1 of the present invention, there is provided an indoor unit having an indoor heat exchanger that exchanges heat between indoor air in a space to be air-conditioned and a refrigerant, an outdoor unit having a refrigerant passage and a water passage, and a water-refrigerant heat exchanger that exchanges heat between the refrigerant in the refrigerant passage and the water in the water passage, an air heat exchanger that exchanges heat between the refrigerant and outside air, and a compressor, the outdoor unit having an outdoor air temperature detection means that detects an outdoor air temperature, and an air heat exchanger temperature detection means that detects a temperature of the air heat exchanger, the water passage of the water-refrigerant heat exchanger and the heat exchange terminal are connected in a ring shape by hot and cold water piping to form a hot and cold water circulation circuit, and the indoor heat exchanger, the refrigerant passage of the water-refrigerant heat exchanger, the air heat exchanger, and the compressor In an air conditioning system capable of performing linked operations of a warm air heating operation for heating the indoor air by the indoor unit and a floor heating operation for heating the floor by the heat exchange terminal, in which units are connected with a refrigerant piping to form a refrigerant circulation circuit, the system judges whether or not the air heat exchanger has frosted depending on the difference between the outside air temperature and the temperature of the air heat exchanger, and if frost has formed on the air heat exchanger, performs a defrosting operation to remove the frost that has formed on the air heat exchanger, and before the defrosting operation, performs a combined heat storage operation in which two types of heat storage operations are performed together: a first heat storage operation in which the indoor air is used as a heat storage target by the indoor unit and the temperature of this heat storage target is raised by a predetermined temperature, and a second heat storage operation in which the hot water circulating through the heat exchange terminal is used as a heat storage target and the temperature of this heat storage target is raised by a predetermined temperature.
[0006] In addition, in claim 2, the heat storage operation is such that a second predetermined temperature, which is the temperature at which the temperature of the heat storage target of the first heat storage operation is increased when the combined heat storage operation is performed, is set to a smaller value than a first predetermined temperature, which is the temperature at which the temperature of the heat storage target of the first heat storage operation is increased when an independent heat storage operation is performed in which only the first heat storage operation is performed, and / or a fourth predetermined temperature, which is the temperature at which the temperature of the heat storage target of the second heat storage operation is increased when the combined heat storage operation is performed, is set to a smaller value than a third predetermined temperature, which is the temperature at which the temperature of the heat storage target of the second heat storage operation is increased when an independent heat storage operation is performed in which only the second heat storage operation is performed.
[0007] In addition, in claim 3, the heat storage time, which is the time from when the heat storage operation in which at least one of the first heat storage operation and the second heat storage operation is started to when the heat storage operation is ended and the defrosting operation is started, is set to be shorter than the first heat storage time, which is the heat storage time when a single heat storage operation in which only one of the first heat storage operation and the second heat storage operation is performed, and the second heat storage time, which is the heat storage time when the combined heat storage operation is performed.
[0008] In addition, in claim 4, there are a first predetermined temperature which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the first heat storage operation is performed, a second predetermined temperature which is a temperature at which the temperature of the heat storage target of the first heat storage operation is increased when performing the combined heat storage operation, a third predetermined temperature which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the second heat storage operation is performed, and a fourth predetermined temperature which is a temperature at which the temperature of the heat storage target of the second heat storage operation is increased when performing the combined heat storage operation, and at least one of the first predetermined temperature, the second predetermined temperature, the third predetermined temperature, and the fourth predetermined temperature is determined according to a heat storage temperature coefficient calculated by subtracting the temperature of the heat storage target at the start of the heat storage operation from the target temperature of the heat storage target during heating operation, and the larger the heat storage temperature coefficient, the higher the value is determined.
[0009] In addition, in claim 5, the start of the heat storage operation is determined according to a temperature difference calculated by subtracting the outside air temperature from the temperature of the air heat exchanger, and the second temperature difference, which is the temperature difference at which the combined heat storage operation is started, is set to a larger value than a first temperature difference, which is the temperature difference at which a single heat storage operation is started in which only one of the first heat storage operation and the second heat storage operation is performed. Effect of the Invention
[0010] According to claim 1 of this invention, before the defrosting operation, a combined heat storage operation is performed in which two types of heat storage operation are performed together: a first heat storage operation in which the indoor air is used as a heat storage target by the indoor unit and the temperature of this heat storage target is raised to a predetermined temperature; and a second heat storage operation in which the hot water circulating through the heat exchange terminal is used as a heat storage target and the temperature of this heat storage target is raised to a predetermined temperature. This allows heat to be distributed and stored in multiple heat storage targets, making it possible to maintain comfort without compromising the feeling of warmth.
[0011] Furthermore, according to claim 2, by setting the second predetermined temperature to a value smaller than the first predetermined temperature and / or setting the fourth predetermined temperature to a value smaller than the third predetermined temperature, when heat is distributed and stored in a plurality of heat storage targets, comfort can be maintained without excessively raising the temperature of the heat storage targets.
[0012] In addition, according to claim 3, by setting the second heat storage time to be shorter than the first heat storage time, when heat is distributed and stored in multiple heat storage targets, the temperature of the heat storage targets is not raised too much, and comfort can be maintained.
[0013] According to claim 4, at least one of the first, second, third and fourth predetermined temperatures is determined according to a heat storage temperature coefficient calculated by subtracting the temperature of the heat storage object at the start of the heat storage operation from the target temperature of the heat storage object during heating operation. The larger this heat storage temperature coefficient is, the higher the value is determined to be, thereby making it possible to maintain comfort without raising the temperature of the heat storage object too much.
[0014] Furthermore, according to claim 5, the start of heat storage operation is determined according to the temperature difference calculated by subtracting the outside air temperature from the temperature of the air heat exchanger, and the second temperature difference, which is the temperature difference at which the combined heat storage operation is started, is set to a larger value than the first temperature difference, which is the temperature difference at which a single heat storage operation is started in which only one of the first heat storage operation and the second heat storage operation is performed. This makes it possible to start the heat storage operation at an appropriate timing, so that the temperature of the heat storage object is not raised too much and, further, the temperature of the heat storage object is not raised insufficiently, thereby maintaining comfort. [Brief description of the drawings]
[0015] [Figure 1] An overall circuit configuration diagram of an air conditioning system according to an embodiment of the present invention. [Diagram 2] Floor heating remote control appearance [Diagram 3] Diagram explaining operation during floor heating operation [Figure 4] Diagram explaining operation during warm air heating operation [Diagram 5] Diagram explaining operation during linked operation [Figure 6] Flowchart explaining the operation of heat storage during warm air heating operation [Figure 7] Flowchart explaining the operation of heat storage during floor heating operation [Figure 8] A flowchart for explaining the operation of the heat storage operation during the linked operation of one embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0016] Hereinafter, one embodiment of the present invention will be described with reference to FIGS.
[0017] The overall circuit configuration of an air conditioning system 1 of this embodiment is shown in Fig. 1. As shown in Fig. 1, the air conditioning system 1 has an outdoor unit 4, which is a heat source of the air conditioning system 1, an indoor unit 17, and a heat exchange terminal 27. In this embodiment, the heat exchange terminal 27 is laid on the floor of the same room in which the indoor unit 17 is installed, and the indoor unit 17 and the heat exchange terminal 27 are installed side by side inside the same room (air-conditioned space).
[0018] <Heating circulation circuit> The outdoor unit 4 has a refrigerant-side flow path 7b as a refrigerant passage for circulating the refrigerant and a water-side flow path 7a as a water passage, and is equipped with a water-refrigerant heat exchanger 7 that functions as a condenser that exchanges heat between high-temperature, high-pressure refrigerant and hot and cold water to a heat exchange terminal 27, and a variable-speed circulation pump 34. That is, the water-side flow path 7a of the water-refrigerant heat exchanger 7 and the heat exchange terminal 27 are connected in a ring shape by a forward pipe 28 (corresponding to a forward pipeline) and a return pipe 29 (corresponding to a return pipeline) that serve as hot and cold water piping, and a heating circulation circuit 33 is formed as a hot and cold water circulation circuit.
[0019] A single forward header 30 is provided midway along the forward pipe 28 extending from the water-refrigerant heat exchanger 7 toward the heat exchange terminal 27. The portion of the forward pipe 28 upstream of the forward header 30 is configured as a single common forward pipe 28a, to which hot water (which may be a circulating fluid other than water that contains antifreeze or the like; the same applies below) heated in the water-refrigerant heat exchanger 7 is supplied. The portion of the forward pipe 28 downstream of the forward header 30 branches into a plurality of individual forward pipes 28b (four in the illustrated example). A thermal valve 31, which is an on-off valve, is attached to each of the branched individual forward pipes 28b.
[0020] Similar to the outgoing pipe 28, a return header 32 is provided midway along the return pipe 29 extending from the heat exchange terminal 27 toward the water-refrigerant heat exchanger 7, and the portion of the return pipe 29 upstream of the return header 32 branches into a plurality of individual return pipes 29b (four in this example). The portion of the return pipe 29 downstream of the return header 32 is configured as a common return pipe 29a, and the hot water introduced via the individual return pipes 29b is returned to the water-refrigerant heat exchanger 7.
[0021] In this embodiment, for the sake of simplicity, an example is shown in which one heat exchange terminal 27 is connected, but a heat exchange terminal 27 may also be connected to each of the four individual supply pipes 28b branched as described above (i.e., four units may be connected).
[0022] The circulation pump 34 is provided midway through the common return pipe 29a, and circulates the hot and cold water in the heat exchange terminals 27 while circulating the hot and cold water from the return pipe 29 to the forward pipe 28 via the water-side flow path 7a. A cistern 35 is provided on the common return pipe 29a upstream of the circulation pump 34 to store hot water and adjust the pressure of the heating circulation circuit 33. Each of the individual return pipes 29b of the return pipe 29 is provided with an inlet water temperature sensor 123 (corresponding to a return temperature detection means) that detects the inlet water temperature T1 as the return temperature of the hot and cold water flowing into the water-side flow path 7a of the water-refrigerant heat exchanger 7.
[0023] <Refrigerant circulation circuit> On the other hand, a refrigerant circulation circuit 130 capable of heating hot and cold water in a heat exchange terminal 27 by heat exchange (described in detail later) in a water-refrigerant heat exchanger 7 is provided from the outdoor unit 4 to the indoor unit 17. The refrigerant circulation circuit 130 includes a main heat pump circuit section 130A, a floor heating side heat pump circuit section 130B, and an air conditioning side heat pump circuit section 130C.
[0024] <Main heat pump circuit section> The main heat pump circuit section 130A includes a refrigerant piping 11 that serves as a refrigerant flow path, a compressor 5 that compresses the refrigerant, a four-way valve 6, and an air heat exchanger 10 that selectively functions as a condenser or an evaporator by heat exchange between the refrigerant and outside air. They are connected by the refrigerant piping 11. The air heat exchanger 10 is, for example, a fin-tube type heat exchanger, and an outdoor fan 9 is provided to pass outside air through the air heat exchanger 10.
[0025] In detail, the refrigerant piping 11 includes a piping section 11a which is the discharge side of the compressor 5, and a piping section 11b which is connected to the piping section 11a via a four-way valve 6 during floor heating operation (see Figure 3 described later, etc.).
[0026] The refrigerant piping 11 also includes a piping section 11c which is the suction side of the compressor 5. The refrigerant piping 11 further includes a piping section 11d which connects the compressor 5 side of the air heat exchanger 10 (in other words, the outlet side during floor heating operation, see FIG. 3, etc. below) to the piping section 11c via the four-way valve 6 during floor heating operation (see FIG. 3, etc. below). The refrigerant piping 11 also includes a piping section 11e which is connected to the opposite side of the air heat exchanger 10 to the compressor 5 (in other words, the inlet side during floor heating operation, see FIG. 3, etc. below).
[0027] The four-way valve 6 is a valve with four ports, and switches which of the two ports for the remaining pipe sections 11a and 11c is connected to each of the two ports for the pipe sections 11b and 11d (constituting the main refrigerant path) of the refrigerant pipe 11. The two ports for the pipe sections 11a and 11c are connected to each other by a secondary refrigerant path consisting of the pipe sections 11a and 11c arranged in a loop, and the compressor 5 is provided on this secondary refrigerant path. For example, when the four-way valve 6 is switched to the state shown in FIG. 3, which will be described later, it connects the pipe section 11a, which is the discharge side of the compressor 5, to the pipe section 11b, which is the inlet side of the water-refrigerant heat exchanger 7. On the other hand, when performing the cold air cooling operation, which will be described later, it connects the pipe section 11a to the pipe section 11d, which is the air heat exchanger 10 side. An outdoor air temperature sensor 12, which serves as an outdoor air temperature detection means, is provided in the air heat exchanger 10 and detects the outdoor air temperature. A refrigerant temperature sensor 13 serving as air heat exchanger temperature detection means is provided in a piping section 11d from the air heat exchanger 10 to the compressor 5, and detects the temperature of the refrigerant on the outlet side of the air heat exchanger 10.
[0028] <Floor heating side heat pump circuit section> The floor heating side heat pump circuit section 130B includes a refrigerant pipe 125 which serves as a refrigerant passage, and a passage 7b on the refrigerant side of the water-refrigerant heat exchanger 7 is connected to the refrigerant pipe 125.
[0029] Specifically, the refrigerant pipe 125 is branched off from and connected to the pipe section 11b. The refrigerant pipe 125 includes a pipe section 125b connected to an inlet side of the water-refrigerant heat exchanger 7 (specifically, the flow path 7b on the refrigerant side) on the side opposite the pipe section 11b, and a pipe section 125c connected to an outlet side of the water-refrigerant heat exchanger 7 (specifically, the flow path 7b on the refrigerant side). The pipe section 125c includes an expansion valve 8 with a full closing function, and is connected to the pipe section 11e downstream of the expansion valve 8.
[0030] <Air conditioning heat pump circuit section> The air conditioning side heat pump circuit section 130C includes a refrigerant pipe 126 which serves as a refrigerant passage, and an indoor heat exchanger 14 which selectively functions as a condenser or an evaporator by heat exchange between the refrigerant and indoor air is connected to the refrigerant pipe 126. The indoor heat exchanger 14 is provided with an indoor fan 18 for passing indoor air through the indoor heat exchanger 14. The indoor air sent by the operation of the indoor fan 18 is heat exchanged in the indoor heat exchanger 14, and the air heated or cooled by the heat exchange is supplied to the room.
[0031] In the air-conditioning-side heat pump circuit section 130C, in detail, the refrigerant pipe 126 is connected by branching off from the pipe section 11b, similar to the pipe section 125b. The refrigerant pipe 126 includes a pipe section 126a whose side opposite the pipe section 11b is connected to the inlet side (see FIG. 4, etc., described later) of the indoor heat exchanger 14 during hot air heating operation, and one side of the refrigerant pipe 126 communicates with the pipe section 11e, similar to the pipe section 125c. The refrigerant pipe 126 includes a pipe section 126b whose side opposite the pipe section 11e is connected to the outlet side (see FIG. 4, etc., described later) of the indoor heat exchanger 14 during hot air heating operation, etc. The pipe section 126a includes a two-way valve 16 capable of opening and closing the communication between the pipe section 11b and the indoor heat exchanger 14, and the pipe section 126b includes an expansion valve 15 with a full-closing function. The two-way valve 16 allows the flow of the refrigerant circulating through the air-conditioning-side heat pump circuit section 130C by opening the valve, and blocks the flow of the refrigerant by closing the valve.
[0032] The compressor 5, four-way valve 6, air heat exchanger 10, outdoor fan 9, two-way valve 16, expansion valves 8 and 15, water-refrigerant heat exchanger 7, etc. are provided in the outdoor unit 4 (see dashed lines in FIG. 1).
[0033] <Refrigerant, various detection signals, etc.> In the refrigerant circulation circuit 130, any refrigerant such as HFC refrigerant or carbon dioxide refrigerant is used as the refrigerant to form a heat pump cycle. In the refrigerant piping 11 of the main heat pump circuit section 130A, a discharge temperature sensor 120 is provided in the piping section 11a for detecting the refrigerant discharge temperature Tout discharged from the compressor 5. The detection result of this discharge temperature sensor 120 is input to an outdoor unit control section 44 provided in the outdoor unit 4. The outdoor unit control section 44 is mainly composed of a microcomputer equipped with a CPU, ROM, RAM, etc., and controls the operation of the air conditioning system 1 upon receiving signals from various sensors in the outdoor unit 4, the indoor unit control section 20, the floor heating remote control 36, etc., as described later.
[0034] Furthermore, for the refrigerant piping 126 of the air-conditioning-side heat pump circuit section 130C, the indoor heat exchanger 14 is provided with an indoor temperature sensor 19 that detects the indoor temperature Tr of the space to be air-conditioned. The detection result of this indoor temperature sensor 19 is input to an indoor unit control section 20 provided in the indoor unit 17, and is also input to an outdoor unit control section 44 provided in the outdoor unit 4 as appropriate (it may be received via the indoor unit control section 20, or may be received directly from the indoor temperature sensor 19).
[0035] The outdoor unit control unit 44 of the outdoor unit 4 and the indoor unit control unit 20 of the indoor unit 17 are connected to each other so that they can communicate with each other, and control the operation of each device and actuator in the outdoor unit 4 while coordinating with each other based on the detection results of each sensor. In particular, the indoor unit control unit 20 controls the opening and closing operation and opening degree of the four-way valve 6, the two-way valve 16, and the expansion valves 8 and 15, so that the indoor unit control unit 20 switches the path through which the refrigerant flows. As a result, the indoor unit control unit 20 performs a floor heating operation to heat the floor surface of the air-conditioned space by the heat exchange terminal 27. At the same time, the indoor unit control unit 20 performs a hot air heating operation to heat the indoor air of the air-conditioned space by the indoor unit 17. At the same time, the indoor unit control unit 20 performs a linked operation (details will be described later) in which the floor heating operation and the hot air heating operation are linked with each other. At the same time, the indoor unit control unit 20 performs a cold air cooling operation to cool the indoor air of the air-conditioned space by the indoor unit 17. Moreover, the indoor unit control unit 20 can selectively execute these operations.
[0036] <Indoor unit remote control> Here, the indoor unit 17 can be operated by an indoor unit remote control 21 configured as a wireless remote control in this example. That is, a transmission unit (not shown) of the indoor unit remote control 21 and a reception unit (not shown) of the indoor unit control unit 20 perform wireless communication by infrared rays or the like, and information is transmitted by one-way communication from the transmission unit of the indoor unit remote control 21 to the reception unit of the indoor unit control unit 20. A signal transmitted from the transmission unit of the indoor unit remote control 21 is received by the reception unit of the indoor unit control unit 20, and the indoor unit control unit 20 reads the information transmitted from the indoor unit remote control 21 and performs the instructed control. The indoor unit control unit 20 can transmit information by two-way communication by exchanging a control signal S11 with the outdoor unit control unit 44. Furthermore, the outdoor unit control unit 44 can also obtain information corresponding to the control signal S1 transmitted from the indoor unit remote control 21 via the indoor unit control unit 20.
[0037] The indoor unit remote control 21 is provided with a heating switch 22 for causing the indoor unit 17 to execute a hot air heating operation for supplying hot air to the room. Furthermore, the indoor unit remote control 21 is provided with a cooling switch 23 for causing the indoor unit 17 to execute a cold air cooling operation for supplying cold air to the room. Furthermore, the indoor unit remote control 21 is provided with a stop switch 24 for stopping the hot air heating operation or the cold air cooling operation. Furthermore, the indoor unit remote control 21 is provided with an indoor temperature setting switch 25 for setting the indoor temperature during the hot air heating operation or the cold air cooling operation, i.e., for setting the air conditioner set temperature Tcon. Furthermore, the indoor unit remote control 21 is provided with a display unit 26 for displaying the air conditioner set temperature Tcon and various operating states, and a timer switch 45 for instructing the indoor unit 17 to operate according to a timer.
[0038] When the heating switch 22 is operated to perform hot air heating operation, or when the cooling switch 23 is operated to perform cold air cooling operation, the air conditioner set temperature Tcon, the operating state, etc. are displayed on the display unit 26. When the stop switch 24 is operated to stop the hot air heating operation or the cold air cooling operation, the display unit 26 disappears and becomes in a non-display state.
[0039] <Floor heating remote control> The heat exchange terminal 27 can be operated by a floor heating remote control 36, which in this example is attached to the wall surface inside the room as a wired remote control. The floor heating remote control 36 exchanges control signals S2 with the outdoor unit control section 44 and can transmit information by two-way communication. This allows the floor heating remote control 36 to obtain operation information of the indoor unit 17 (whether it is operating or stopped, etc.).
[0040] <Floor heating remote control details> As shown in Fig. 2, the floor heating remote control 36 is provided with a display unit 37, an on / off switch 38 for instructing the heat exchange terminal 27 to start and stop operation, and a timer switch 39 for instructing the heat exchange terminal 27 to operate according to a timer. The floor heating remote control 36 is also provided with an operation changeover switch 40 for instructing the heat exchange terminal 27 to switch between operating modes (normal mode, save mode, etc.), a back switch 41 for returning the screen display to the previous screen, and a menu / decision switch 42. The floor heating remote control 36 is also provided with a cross key 43 for up, down, left, and right directions. Although not shown in the figure, the floor heating remote control 36 is equipped with a CPU, a memory as a storage means, and the like for controlling the operation of the heat exchange terminal 27 and for various displays.
[0041] The display unit 37 can switch between a plurality of setting screens (setting screens 100-101 described below) under the control of the CPU. That is, in the example shown in Fig. 2(a), the display unit 37 displays a setting screen 100 for making settings related to the entire air conditioning system 1. In addition, in the example shown in Fig. 2(b), the display unit 37 displays a setting screen 101 for making settings related to the heat exchange terminal 27, including settings for starting and stopping the operation of the heat exchange terminal 27 provided in the room.
[0042] At this time, a tab TM labeled "MAIN" for selecting the setting screen 100 is provided protruding upward near the right end of the upper portion of each of the setting screens 100-101 displayed on the display unit 37. Also, a tab TA labeled "A" for selecting the setting screen 101 is provided near the left end of the upper portion of each of the setting screens 100-101. By operating either the tab TM or TA via the cross key 43 or the like, the setting screen 100-101 having the operated tab TM or TA can be displayed.
[0043] <Floor heating operation> First, the floor heating operation will be described with reference to Fig. 3. During the floor heating operation shown in Fig. 3, the four-way valve control unit 44A switches the four-way valve 6 to a position that connects the pipe section 11a to the pipe section 11b and connects the pipe section 11c to the pipe section 11d. The two-way valve control unit 44F switches the two-way valve 16 to a closed state. The expansion valve control unit 44C controls the expansion valve 8 to an open state and the expansion valve 15 to a fully closed state.
[0044] As a result, a refrigerant path is formed, from piping section 11a on the discharge side of compressor 5 → piping section 11b → piping section 125b → refrigerant side flow path 7b of water-refrigerant heat exchanger 7 → piping section 125c (expansion valve 8) → piping section 11e → air heat exchanger 10 → piping section 11d → piping section 11c on the suction side of compressor 5. As a result, in water-refrigerant heat exchanger 7 functioning as a condenser, water flowing in water-side flow path 7a is heated by heat from the refrigerant flowing in refrigerant-side flow path 7b, and high-temperature water (heated water) is supplied into heat exchange terminal 27, heating the floor surface of the space to be air-conditioned.
[0045] <Warm air heating operation> Next, the hot air heating operation will be described with reference to Fig. 4. During the hot air heating operation shown in Fig. 4, the four-way valve control unit 44A switches the four-way valve 6 to the same side as in the floor heating operation. The two-way valve control unit 44F switches the two-way valve 16 to an open state. Furthermore, the expansion valve control unit 44C controls the expansion valve 8 to a fully closed state and the expansion valve 15 to an open state.
[0046] As a result, a refrigerant path is formed from the piping section 11a on the discharge side of the compressor 5, → the piping section 11b, → the piping section 126a, → the indoor heat exchanger 14 of the indoor unit 17, → the piping section 126b (expansion valve 15), → the piping section 11e, → the air heat exchanger 10, → the piping section 11d, → the piping section 11c on the suction side of the compressor 5. As a result, the refrigerant exchanges heat with the indoor air in the indoor heat exchanger 14 functioning as a condenser, releasing heat and heating the air in the space to be air-conditioned.
[0047] <Setting whether to execute linked operation using the remote control> As described above, in this embodiment, it is possible to perform linked operation in which the warm air heating operation by the indoor unit 17 and the floor heating operation by the heat exchange terminal 27 are both operated in conjunction with each other, and it is possible to set whether or not to perform the linked operation using the floor heating remote control 36.
[0048] <Linked operation> The linked operation performed as described above (more specifically, the state of "start-up operation 2" described later) will be described with reference to Fig. 5. Even during this linked operation, the four-way valve control unit 44A switches the four-way valve 6 to the same side as in the floor heating operation. The two-way valve control unit 44F switches the two-way valve 16 to an open state. Furthermore, the expansion valve control unit 44C controls the expansion valves 8 and 15 to an open state (more specifically, discharge control described later is being performed).
[0049] As a result, the refrigerant path passes through piping section 11a on the discharge side of the compressor 5, and then piping section 11b, before splitting into two. One of the paths passes through piping section 125b, the refrigerant-side flow path 7b of the water-refrigerant heat exchanger 7, and then piping section 125c (expansion valve 8) to reach piping section 11e. The other path passes through piping section 126a, the indoor heat exchanger 14, and then piping section 126b (expansion valve 15), before joining piping section 11e. The subsequent path is piping section 11e, the air heat exchanger 10, piping section 11d, and then piping section 11c on the suction side of the compressor 5.
[0050] As a result, floor heating operation of the heat exchange terminal 27 by heating the water in the water-side flow path 7a of the water-refrigerant heat exchanger 7 and hot air heating operation of the indoor unit 17 by releasing heat from the indoor heat exchanger 14 are carried out in parallel.
[0051] <Defrosting operation during warm air heating operation> Next, the defrosting operation during the warm air heating operation will be described. The defrosting operation during the warm air heating operation is a mode in which the refrigerant is circulated in the opposite direction to that during the warm air heating operation (so-called reverse cycle defrosting). The refrigerant discharged from the compressor 5 passes through the expansion valve 8 via the air heat exchanger 10 and is supplied to the water-refrigerant heat exchanger 7 to melt the frost formed on the air heat exchanger 10.
[0052] The defrosting operation is started when the defrost control unit 44G judges whether the defrosting start condition described above is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether a predetermined defrosting end condition is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether the defrosting start condition is satisfied. The defrosting end condition is, for example, that the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 reaches a preset defrosting end temperature (for example, 5°C).
[0053] When the defrosting operation is started, the defrost control unit 44G outputs a signal to the compressor control unit 44B indicating that the defrosting operation is in progress, and the compressor control unit 44B receives the signal and controls the compressor 5 at a preset defrosting rotation speed (constant rotation speed). Note that, although the compressor control unit 44B controls the rotation speed of the compressor 5 based on an instruction from the defrost control unit 44G here, the same control can be implemented even if the defrost control unit 44G directly controls the rotation speed of the compressor 5 during the defrosting operation.
[0054] Also, when the defrosting operation is started, the defrost control unit 44G outputs a signal to the expansion valve control unit 44C indicating that the defrosting operation is in progress. The expansion valve control unit 44C receives the signal and expands the expansion valve 8 to a predetermined opening degree (for example, fully open) that is greater than the opening degree during the warm air heating operation, so that the refrigerant passing through the expansion valve 8 is not depressurized by the expansion valve 8. Here, the expansion valve control unit 44C controls the opening degree of the expansion valve 8 based on an instruction from the defrost control unit 44G, but the same control can be performed even if the defrost control unit 44G directly controls the opening degree of the expansion valve 8 during the defrosting operation. The defrosting operation during the warm air heating operation has been described by taking as an example a form in which the refrigerant is circulated in the opposite direction to that during the warm air heating operation (so-called reverse cycle defrosting). However, the defrosting operation during the warm air heating operation may be a form in which the refrigerant is circulated in the same direction as that during the warm air heating operation (so-called forward cycle defrosting). At this time, the refrigerant discharged from the compressor 5 passes through the water-refrigerant heat exchanger 7, the expansion valve 8, and is supplied to the air heat exchanger 10, where it melts the frost that has formed in the air heat exchanger 10 and is returned to the compressor 5.
[0055] <Heat storage operation during warm air heating operation> Next, the heat storage operation during the warm air heating operation will be described. The heat storage operation during the warm air heating operation is performed before the defrosting operation during the warm air heating operation, and is a first heat storage operation in which the room temperature is stored as heat to prevent the room temperature from dropping during the defrosting operation and the feeling of warmth from being impaired.
[0056] Next, the heat storage operation during linked operation will be described, based on a situation in which hot air heating operation is performed with the indoor unit 17. The heat storage operation is a first heat storage operation that uses the indoor unit 17 for forced heating to raise the room temperature above the set temperature set by the user when a predetermined heat storage operation start condition is met during hot air heating operation. The heat storage operation start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. In other words, it is a condition that suggests that a defrosting operation will soon be started based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10 (a condition that is met before the defrosting start condition is met).
[0057] During the hot air heating operation, the heat storage control unit 44H judges whether the heat storage operation start condition is satisfied, and when it judges that the heat storage operation start condition is satisfied, it starts the heat storage operation. At the same time as the start of this heat storage operation, the counting unit 44H1 also starts counting. When the heat storage operation is started, the heat storage control unit 44H outputs a signal indicating that the heat storage operation is in progress. The target room temperature determination unit 44J receives the signal and sets the heat storage target room temperature Ta1 as a first predetermined temperature higher than the air conditioner set temperature Tcon during the hot air heating operation that was set up until then as a new target room temperature. In addition, the heat storage target room temperature Ta1, which is the temperature to raise the temperature of the indoor air, is determined according to the heat storage temperature coefficient. This heat storage temperature coefficient is calculated by subtracting the indoor air temperature at the start of the heat storage operation from the target room temperature during the hot air heating operation. The larger this heat storage temperature coefficient is, the higher the heat storage target room temperature Ta1 is determined to be.
[0058] At this time, the compressor control unit 44B controls the rotation speed of the compressor 5 so that the temperature of the indoor air detected by the indoor temperature sensor 19 becomes the heat storage target room temperature Ta1 set by the target room temperature determination unit 44J. In actual operation, immediately after the start of the heat storage operation, the target room temperature is changed to the heat storage target room temperature Ta1, which is a temperature higher than the target room temperature (air conditioner set temperature Tcon) during the warm air heating operation that had been set up until then. As a result, the temperature difference between the indoor air temperature detected by the indoor temperature sensor 19 and the target room temperature (heat storage target room temperature Ta1) becomes larger than during the warm air heating operation immediately before the heat storage operation, so the compressor control unit 44B increases the rotation speed of the compressor 5. Then, when the indoor air temperature detected by the indoor temperature sensor 19 reaches the target room temperature (heat storage target room temperature Ta1), the compressor control unit 44B reduces the rotation speed of the compressor 5 in order to maintain the indoor air temperature detected by the indoor temperature sensor 19 at the target room temperature.
[0059] Also, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal indicating that the heat storage operation is in progress to the target discharge temperature setting unit 44I. When the target discharge temperature setting unit 44I receives the signal, it controls to maintain the target discharge temperature that was set during the hot air heating operation immediately before the heat storage operation was started. That is, during the heat storage operation, the setting method of changing the target discharge temperature according to the target room temperature (air conditioner set temperature Tcon) as in the hot air heating operation is not adopted. Also, during the heat storage operation, even if the target room temperature is changed to a predetermined heat storage target room temperature Ta1 that is higher than that during the hot air heating operation, the target discharge temperature that was set during the hot air heating operation immediately before the heat storage operation was started is maintained as it is. As a result, during the heat storage operation, the target discharge temperature is maintained until the heat storage operation is completed.
[0060] At this time, the target discharge temperature is maintained as it was when it was set during the hot air heating operation immediately before the start of the heat storage operation. Therefore, the expansion valve control unit 44C does not significantly change the opening of the expansion valves 8 and 15, and maintains the opening during the hot air heating operation immediately before the start of the heat storage operation immediately after the start of the heat storage operation. During the heat storage operation, although the temperature of the refrigerant discharged from the compressor 5 may be somewhat high or low, the target discharge temperature is not made higher than that during the hot air heating operation immediately before the start of the heat storage operation. Therefore, the expansion valve control unit 44C does not significantly narrow (close) the opening of the expansion valves 8 and 15, and the temperature of the refrigerant circulated to the air heat exchanger 10 does not drop significantly.
[0061] Furthermore, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal indicating that the heat storage operation is in progress to the indoor unit control unit 20. Upon receiving this signal, the indoor unit control unit 20 controls the rotation speed of the indoor fan 18 to be increased to a heat storage operation rotation speed that is higher than that during the warm air heating operation.
[0062] Here, it is assumed that the temperature of the refrigerant flowing into the indoor heat exchanger 14 is constant, and a constant amount of heat is imparted from the refrigerant to the indoor air in the indoor heat exchanger 14. In this case, when the rotation speed of the indoor fan 18 is increased, the circulating flow rate of the indoor air per unit time increases, and the heat exchange efficiency increases, so the amount of heat to be imparted from the indoor heat exchanger 14 to the indoor air increases. Therefore, by increasing the rotation speed of the indoor fan 18 during the heat storage operation, the indoor air temperature can be increased. Furthermore, since the target room temperature during the heat storage operation is set to the heat storage target room temperature Ta1, which is higher than the target room temperature during the warm air heating operation, the rotation speed of the compressor 5 is controlled to increase. As a result, the circulating flow rate of the refrigerant passing through the indoor heat exchanger 14 increases, and the amount of heat that the refrigerant attempts to give to the indoor air in the indoor heat exchanger 14 increases, making it easier to increase the temperature of the indoor air.
[0063] During warm air heating operation and heat storage operation, if the outside air temperature is low, frost gradually forms on the air heat exchanger 10. If a predetermined defrost start condition is met during the heat storage operation, the defrost control unit 44G starts executing a defrost operation to melt the frost on the air heat exchanger 10 after the heat storage operation is terminated.
[0064] The control procedure executed by the outdoor unit control unit 44 to realize the control during the above-mentioned heat storage operation will be described with reference to the flowchart of Fig. 6. Here, a scene in which the indoor unit 17 performs hot air heating operation will be described.
[0065] During the warm air heating operation, the heat storage control unit 44H judges whether or not the heat storage operation start condition is satisfied. Here, the satisfaction of the heat storage operation start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. This heat storage operation start condition is, for example, a condition that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C) and the first temperature difference is outdoor air temperature - refrigerant temperature on the outlet side of the air heat exchanger 10 > 4°C. When the heat storage control unit 44H judges that the heat storage operation start condition is satisfied (step ST1: YES), it starts the heat storage operation (step ST2), and the counting unit 44H1 starts counting the time of the heat storage operation (step ST3).
[0066] Thereafter, the target room temperature determining unit 44J sets the heat storage target room temperature Ta1 as the target room temperature (step ST4), and proceeds to step ST5.
[0067] In step ST5, the target discharge temperature setting unit 44I continues to set, as the target discharge temperature, the same temperature as the target discharge temperature that was set during the warm air heating operation immediately before the start of the heat storage operation.
[0068] In step ST6, the indoor unit control section 20 increases the rotation speed of the indoor fan 18 to the heat storage operation rotation speed, which is a rotation speed higher than that during the warm air heating operation, and then proceeds to step ST7.
[0069] In step ST7, the heat storage control unit 44H judges whether or not the temperature of the indoor air detected by the indoor temperature sensor 19 has reached the target room temperature (heat storage target room temperature Ta1) set in step ST4. If the temperature of the indoor air detected by the indoor temperature sensor 19 has not reached the heat storage target room temperature Ta1, the judgment is not satisfied (step ST7: NO), and the process proceeds to step ST8. In step ST8, the defrost control unit 44G judges whether or not a predetermined defrost start condition is satisfied. Here, the satisfaction of the defrost start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. For example, the defrost start condition is a condition that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C), and the outdoor air temperature - the refrigerant temperature on the outlet side of the air heat exchanger 10 > 8°C. Alternatively, the condition is a condition that a first heat storage time (for example, 40 minutes) has elapsed since the start of the heat storage operation, that is, the time counted by the counting unit 44H1 exceeds a certain time. The defrosting start condition is that either one of these conditions is satisfied.
[0070] In step ST8, if the predetermined defrost start condition is not established, the determination is not satisfied (step ST8: NO), and the process proceeds to step ST7.
[0071] As described above, there are cases where the indoor air temperature detected by the indoor temperature sensor 19 has not reached the target room temperature (thermal storage target room temperature Ta1) (step ST7: NO), and the defrosting start condition is not satisfied (step ST8: NO). In this case, the process loops from step ST7: NO to step ST8: NO to step ST7.
[0072] In step ST7, the indoor air temperature detected by the indoor temperature sensor 19 has not reached the target room temperature (heat storage target room temperature Ta1) (step ST8: NO), but the defrosting start condition may be satisfied (step ST8: YES). In this case, the heat storage control unit 44H ends the heat storage operation (step ST9). Then, the defrost control unit 44G starts the defrosting operation.
[0073] In addition, in step ST7, if the indoor air temperature detected by the indoor temperature sensor 19 reaches the target room temperature (thermal storage target room temperature Ta1), the determination is satisfied (step ST7: YES), and the thermal storage control unit 44H ends the thermal storage operation (step ST10). After that, the thermal storage control unit 44H proceeds to step ST11.
[0074] In step ST11, the defrost control unit 44G determines whether or not a predetermined defrost start condition is satisfied. Until the defrost start condition is satisfied, the determination in step ST11 is not satisfied (step ST11: NO) and the system remains in a loop waiting state. When the defrost start condition is satisfied, the determination is satisfied (step ST11: YES), and the defrost control unit 44G starts the defrost operation.
[0075] <Defrosting operation during floor heating operation> Next, the defrosting operation during floor heating operation will be described. The defrosting operation during floor heating operation is a mode in which the refrigerant is circulated in the same direction as during floor heating operation (so-called positive cycle defrosting), and the refrigerant discharged from the compressor 5 passes through the water-refrigerant heat exchanger 7, the expansion valve 8, and is supplied to the air heat exchanger 10 to melt the frost formed on the air heat exchanger 10.
[0076] The defrosting operation is started when the defrost control unit 44G judges whether the defrosting start condition described above is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether a predetermined defrosting end condition is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether the defrosting start condition is satisfied. The defrosting end condition is, for example, that the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 reaches a preset defrosting end temperature (for example, 5°C).
[0077] When the defrosting operation is started, the defrost control unit 44G outputs a signal to the compressor control unit 44B indicating that the defrosting operation is in progress, and the compressor control unit 44B receives the signal and controls the compressor 5 at a preset defrosting rotation speed (constant rotation speed). Note that, although the compressor control unit 44B controls the rotation speed of the compressor 5 based on an instruction from the defrost control unit 44G here, the same control can be implemented even if the defrost control unit 44G directly controls the rotation speed of the compressor 5 during the defrosting operation.
[0078] Furthermore, when the defrosting operation is started, the defrost control unit 44G outputs a signal to the expansion valve control unit 44C to the effect that the defrosting operation is in progress. The expansion valve control unit 44C receives the signal and expands the expansion valve 8 to a predetermined opening degree (for example, fully open) that is greater than the opening degree during floor heating operation, so that the refrigerant passing through the expansion valve 8 is not depressurized by the expansion valve 8. Note that, here, the expansion valve control unit 44C controls the opening degree of the expansion valve 8 based on an instruction from the defrost control unit 44G, but similar control can be performed even if the defrost control unit 44G directly controls the opening degree of the expansion valve 8 during the defrosting operation.
[0079] Furthermore, when the defrosting operation is started, the defrost control unit 44G outputs a signal to the pump control unit 44D indicating that the defrosting operation is in progress, and the pump control unit 44D receives the signal and controls the drive of the circulation pump 34 based on the refrigerant temperature detected by the refrigerant temperature sensor 13. Note that here, the pump control unit 44D controls the drive of the circulation pump 34 based on an instruction from the defrost control unit 44G. Alternatively, the same control can be performed even if the defrost control unit 44G directly controls the drive of the circulation pump 34 during the defrosting operation. For the sake of simplicity, hereinafter, it is assumed that the defrost control unit 44G directly controls the drive of the circulation pump 34 during the defrosting operation.
[0080] Here, the drive control (rotation speed control) of the circulation pump 34 during the defrosting operation will be described. During the defrosting operation, the defrost control unit 44G fully opens the expansion valve 8 to allow high-temperature refrigerant to flow through the air heat exchanger 10 to defrost the air heat exchanger 10, while controlling the drive of the circulation pump 34 based on the temperature detected by the refrigerant temperature sensor 13. Details will be described below.
[0081] First, at the start of the defrosting operation, the defrost control unit 44G stops the operation of the circulation pump 34, which had been operating up until then, and stops the circulation of the hot water. If the circulation pump 34 is in operation at the start of the defrosting operation, a part of the heat amount held by the refrigerant is absorbed by the hot water side due to the heat exchange between the refrigerant and the hot water in the water-refrigerant heat exchanger 7. As a result, the heat amount for defrosting the air heat exchanger 10 is taken away, and the defrosting of the air heat exchanger 10 does not progress, so the operation of the circulation pump 34 is stopped at the start of the defrosting operation. In particular, since the amount of frost formed on the air heat exchanger 10 is large at the start of the defrosting operation, it is preferable to stop the operation of the circulation pump 34 at the start of the defrosting operation so that the heat amount held by the refrigerant is used only for defrosting. The above-mentioned stopping of the circulation of the hot water means that the flow of the hot water is substantially stopped.
[0082] During the defrosting operation, the defrost control unit 44G judges whether the temperature detected by the refrigerant temperature sensor 13 reaches a predetermined condition, which is a predetermined circulation pump drive start condition that is always satisfied before the defrost end condition is satisfied. When the predetermined condition is satisfied, the defrost control unit 44G drives the circulation pump 34 at a rotation speed lower than that during the floor heating operation to circulate the hot water.
[0083] The circulation pump drive start condition is, for example, whether or not the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 has reached a preset circulation pump drive start temperature (higher than 0°C and lower than the defrost end temperature of 5°C, for example, 1°C) or higher. When the defrost control unit 44G determines that the circulation pump drive start condition is met, it starts driving the circulation pump 34 at a predetermined rotation speed (for example, 1000 rpm) lower than that during floor heating operation. The defrost control unit 44G controls the circulation pump 34 to increase the rotation speed as the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is met with an increase.
[0084] When the frost on the air heat exchanger 10 starts to melt during the defrosting operation, the amount of heat held by the refrigerant becomes excessive with respect to the amount of heat required for defrosting, and the refrigerant temperature detected by the refrigerant temperature sensor 13 rises. If nothing is done, the surplus heat other than the amount of heat required for defrosting is simply radiated from the air heat exchanger 10, resulting in heat radiation loss. In order to use the amount of heat radiation loss as the amount of heat for heating, when the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 rises and reaches a preset temperature or higher, the circulation pump 34 starts to operate at a lower rotation speed than during floor heating operation. Furthermore, the defrost control unit 44G absorbs part of the heat held by the refrigerant into the hot water side in the water-refrigerant heat exchanger 7, and uses part of the heat that was previously used only for defrosting for heating. Also, the fact that the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 rises and approaches the direction in which the defrost end condition is satisfied means that the amount of surplus heat other than the amount of heat required for defrosting has increased. In such a case, as the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 approaches the state in which the defrost termination condition is met, the rotation speed of the circulation pump 34 is increased to control the amount of heat used for heating.
[0085] At the start of defrosting operation, since there is a large amount of frost on the air heat exchanger 10, the operation of the circulation pump 34 is stopped so that the heat contained in the refrigerant is used only for defrosting. However, if the refrigerant temperature detected by the refrigerant temperature sensor 13 during defrosting operation rises to a predetermined temperature, the operation of the circulation pump 34 is started to circulate hot water to the heat exchange terminals 27 while continuing defrosting, thereby enabling heating.
[0086] In addition, table data showing the correspondence relationship between the refrigerant temperature r at the outlet side of the air heat exchanger 10 and the driving rotation speed of the circulation pump 34 is stored in advance in the defrost control unit 44G, and the rotation speed of the circulation pump 34 is determined based on this table data. Here, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is less than 1°C, the rotation speed of the circulation pump 34 is determined to be 0 rpm, that is, the circulation pump 34 is stopped. When the refrigerant temperature detected by the refrigerant temperature sensor 13 is 1°C or more and less than 2°C, the rotation speed of the circulation pump 34 is determined to be 1000 rpm. Furthermore, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is 2°C or more and less than 3°C, the rotation speed of the circulation pump 34 is determined to be 1200 rpm. Moreover, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is 3°C or more and less than 5°C, the rotation speed of the circulation pump 34 is determined to be 1500 rpm.
[0087] As described above, the air conditioning system 1 stops the circulation of hot water at the start of the defrosting operation (positive cycle defrosting). During the positive cycle defrosting, the system continues defrosting the air heat exchanger 10, and when it is determined that a predetermined condition is reached based on the refrigerant temperature detected by the refrigerant temperature sensor 13, circulates hot water. In this way, while performing defrosting during the defrosting operation, the circulation pump 34 is appropriately driven to circulate hot water according to the refrigerant temperature on the outlet side of the air heat exchanger 10, and heating can also be performed by the heat exchange terminals 27.
[0088] In addition, the defrost control unit 44G stops the circulation pump 34 at the start of defrosting, and during the defrosting operation, determines that the refrigerant temperature detected by the refrigerant temperature sensor 13 has reached the circulation pump drive start condition that is satisfied before the defrost end condition is satisfied. In this case, the defrost control unit 44G drives the circulation pump 34 at a rotation speed lower than that during floor heating operation. As a result, at the start of the defrosting operation, since the amount of frost on the air heat exchanger 10 is large, the drive of the circulation pump 34 is stopped and defrosting is performed intensively so that the heat held by the refrigerant is used only for defrosting. Then, when the refrigerant temperature detected by the refrigerant temperature sensor 13 rises and reaches the circulation pump drive start condition, the circulation pump 34 is started to be driven at a rotation speed lower than that during floor heating operation so as not to take away too much heat required for defrosting. As a result, while continuing defrosting, hot water can be circulated to the heat exchange terminal 27 to perform heating, and the non-heating time during the defrosting operation can be shortened.
[0089] Furthermore, after determining that the circulation pump drive start condition has been reached, the defrost control unit 44G increases the rotation speed of the circulation pump 34 as the refrigerant temperature detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied (defrost end temperature). As a result, the refrigerant temperature detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied after reaching the circulation pump drive condition. That is, the temperature of the refrigerant on the outlet side of the air heat exchanger 10 is rising. Also, this means that the amount of surplus heat other than the amount of heat required for defrosting the air heat exchanger 10 has increased. In this case, as the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied, the rotation speed of the circulation pump 34 can be increased to increase the amount of heat used for heating. Furthermore, a decrease in the feeling of warmth during defrosting operation can be suppressed.
[0090] In addition, the defrosting operation during floor heating operation has been described using an example in which the refrigerant is circulated in the same direction as during floor heating operation (so-called forward cycle defrosting), but the defrosting operation during floor heating operation may be a mode in which the refrigerant is circulated in the same direction as during cold air cooling operation (so-called reverse cycle defrosting). At that time, the refrigerant discharged from the compressor 5 is supplied to the air heat exchanger 10, melts the frost formed in the air heat exchanger 10, passes through the expansion valve 8, and is returned to the compressor 5 via the water-refrigerant heat exchanger 7.
[0091] <Heat storage operation during floor heating operation> Next, the heat storage operation during floor heating operation will be described. Here, the explanation will be based on a scene where floor heating operation is performed by the heat exchange terminal 27. The heat storage operation during floor heating operation is performed before the defrost operation during floor heating operation, and is a second heat storage operation that stores heat in the hot water refrigerant to prevent the room temperature from dropping during the defrost operation and impairing the feeling of warmth. The second heat storage operation is to increase the temperature of the circulating liquid supplied to the heat exchange terminal 27 when a predetermined heat storage operation start condition is established during floor heating operation. The heat storage operation start condition is a condition that is set based on the outside air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. In other words, it is a condition that is estimated from the outside air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10 that the defrost operation will soon be started (a condition that is established before the defrost start condition is established).
[0092] During floor heating operation, the heat storage control unit 44H judges whether the heat storage operation start condition is satisfied, and when it judges that the heat storage operation start condition is satisfied, the heat storage operation is started. At the same time as the start of this heat storage operation, the counting unit 44H1 also starts counting. When the heat storage operation is started, a signal indicating that the heat storage operation is in progress is output from the heat storage control unit 44H. The target return temperature determination unit 44E receives the signal and sets the heat storage target water temperature Tb1 as a third predetermined temperature higher than the target return temperature (target hot water temperature) during floor heating operation that had been set up until then as a new target return temperature (target hot water temperature). In addition, the heat storage target water temperature Tb1, which is the temperature to increase the hot water temperature, is determined according to the heat storage temperature coefficient. This heat storage temperature coefficient is calculated by subtracting the hot water temperature at the start of the heat storage operation from the target return temperature during floor heating operation. The larger this heat storage temperature coefficient is, the higher the heat storage target water temperature Tb1 is determined to be.
[0093] At this time, the compressor control unit 44B controls the rotation speed of the compressor 5 so that the hot water temperature detected by the inlet water temperature sensor 123 becomes the heat storage target water temperature Tb1 set by the target return temperature determination unit 44E. In actual operation, immediately after the start of the heat storage operation, the target return temperature (target hot water temperature) is changed to the heat storage target water temperature Tb1, which is a temperature higher than the target return temperature during the floor heating operation that had been set up until then. As a result, the temperature difference between the hot water temperature detected by the inlet water temperature sensor 123 and the target return temperature (heat storage target water temperature Tb1) becomes larger than during the floor heating operation immediately before the heat storage operation, so the compressor control unit 44B increases the rotation speed of the compressor 5. Then, when the hot water temperature detected by the inlet water temperature sensor 123 reaches the target return temperature (heat storage target water temperature Tb1), the rotation speed of the compressor 5 is reduced in order to maintain the hot water temperature detected by the inlet water temperature sensor 123 at the target return temperature.
[0094] Also, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal to the target discharge temperature setting unit 44I indicating that the heat storage operation is in progress. When the target discharge temperature setting unit 44I receives the signal, it controls to maintain the target discharge temperature that was set during floor heating operation immediately before the heat storage operation was started. That is, during the heat storage operation, the setting method of changing the target discharge temperature according to the target return temperature (target hot water temperature) as in the floor heating operation is not adopted. Also, even if the target return temperature is changed to a predetermined heat storage target water temperature Tb1 that is higher than during the floor heating operation, the target discharge temperature that was set during floor heating operation immediately before the heat storage operation was started is maintained as it is, and the target discharge temperature is maintained until the heat storage operation is completed.
[0095] At this time, the target discharge temperature is maintained as it was when it was set during floor heating operation immediately before the start of heat storage operation. Therefore, the expansion valve control unit 44C does not significantly change the opening of the expansion valve 8, and immediately after the start of heat storage operation, it maintains the opening during floor heating operation immediately before the start of heat storage operation. During heat storage operation, although the temperature of the refrigerant discharged from the compressor 5 may be somewhat high or low, the target discharge temperature is not made higher than that during floor heating operation immediately before the start of heat storage operation. Therefore, the opening of the expansion valve 8 is not significantly narrowed (closed), and the temperature of the refrigerant circulated to the air heat exchanger 10 does not drop significantly.
[0096] In addition, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal to the pump control unit 44D indicating that heat storage operation is in progress, and when the pump control unit 44D receives this signal, the pump control unit 44D controls the rotation speed of the circulation pump 34 to be lower than during floor heating operation.
[0097] Here, it is assumed that the temperature of the hot water flowing into the water-refrigerant heat exchanger 7 is constant, and a constant amount of heat is given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7. When the rotation speed of the circulation pump 34 is reduced, the circulation flow rate of the hot water per unit time is reduced and the temperature efficiency is increased, so the temperature of the hot water flowing out from the water-refrigerant heat exchanger 7 is higher. Therefore, when the rotation speed of the circulation pump 34 is reduced during the heat storage operation, the temperature of the hot water supplied to the heat exchange terminal 27 can be increased. Furthermore, since the target hot water temperature during the heat storage operation is set to the heat storage target water temperature Tb1 that is higher than the target hot water temperature during the floor heating operation, the rotation speed of the compressor 5 is controlled in a direction to increase. As a result, the circulation flow rate of the refrigerant passing through the water-refrigerant heat exchanger 7 increases, and the amount of heat to be given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7 increases, so that it becomes easier to increase the temperature of the hot water flowing out from the water-refrigerant heat exchanger 7. In addition, since the rotation speed of the circulation pump 34 is lower than that during floor heating operation, the amount of heat given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7 is reduced, and the temperature of the refrigerant flowing out from the water-refrigerant heat exchanger 7 is increased. This increases the temperature of the refrigerant circulated to the air heat exchanger 10, and the progress of frost adhesion to the air heat exchanger 10 can be suppressed. Furthermore, the rotation speed of the circulation pump 34 is reduced during heat storage operation to increase the temperature of the hot water supplied to the heat exchange terminal 27, but by reducing the rotation speed of the circulation pump 34, the circulating flow rate of the hot water is reduced, and it becomes difficult for heat to be dissipated by the heat exchange terminal 27. As a result, although the temperature of the hot water itself becomes higher, the room temperature of the room corresponding to the heat exchange terminal 27 does not rise too much, and the user does not feel uncomfortable.
[0098] The control of the reduction in the rotation speed of the circulation pump 34 during the heat storage operation will be described in more detail. During the heat storage operation, the pump control unit 44D controls the rotation speed of the circulation pump 34 to be gradually reduced by a predetermined value at every predetermined time until the hot water temperature detected by the inlet water temperature sensor 123 reaches the heat storage target water temperature Tb1. The lower limit rotation speed of the circulation pump 34 that can be reduced during the heat storage operation is set in advance. The rotation speed of the circulation pump 34 may reach the preset lower limit rotation speed while the rotation speed of the circulation pump 34 is gradually reduced and the hot water temperature detected by the inlet water temperature sensor 123 reaches the heat storage target water temperature Tb1. In this case, after the lower limit rotation speed is reached, the circulation pump 34 is controlled at the lower limit rotation speed.
[0099] During floor heating operation and heat storage operation, when the outdoor air temperature is low, frost gradually forms on the air heat exchanger 10. When a predetermined defrost start condition is met during the heat storage operation, the defrost control unit 44G starts executing a defrost operation to melt the frost on the air heat exchanger 10 after the heat storage operation is terminated. The details of the defrost operation will be described later.
[0100] In order to realize the control during the above-mentioned heat storage operation, the control procedure executed by the outdoor unit control unit 44 will be described with reference to the flowchart of Fig. 7. Here, a scene in which floor heating operation is performed by the heat exchange terminal 27 will be described.
[0101] During floor heating operation, the heat storage control unit 44H judges whether or not the heat storage operation start condition is satisfied. Here, the satisfaction of the heat storage operation start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. For example, the heat storage operation start condition is a condition that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C) and the first temperature difference is outdoor air temperature - refrigerant temperature on the outlet side of the air heat exchanger 10 > 4°C. When the heat storage control unit 44H judges that the heat storage operation start condition is satisfied (step ST12: YES), it starts the heat storage operation (step ST13), and the counting of the time of the heat storage operation by the counting unit 44H1 starts (step ST14).
[0102] Thereafter, the target return temperature determination unit 44E sets the heat storage target water temperature Tb1 as the target hot water temperature (target return temperature) (step ST15), and proceeds to step ST16.
[0103] In step ST16, the target discharge temperature setting unit 44I continues to set the target discharge temperature to the same temperature as the target discharge temperature set during floor heating operation immediately before the start of heat storage operation. In step ST17, the pump control unit 44D reduces the rotation speed of the circulation pump 34 by a predetermined value (e.g., 100 rpm) from the rotation speed during floor heating operation (e.g., 3500 rpm).
[0104] Thereafter, in step ST18, the heat storage control unit 44H determines whether a predetermined time (here, one minute) has elapsed. If one minute has not elapsed, the determination is not satisfied and the system waits in a loop (step ST18: NO), but if one minute has elapsed, the determination is satisfied (step ST18: YES), and the system proceeds to step ST19.
[0105] In step ST19, the heat storage control unit 44H judges whether or not the hot water temperature detected by the inlet water temperature sensor 123 has reached the target hot water temperature (heat storage target water temperature Tb1) set in step ST15. If the hot water temperature detected by the inlet water temperature sensor 123 has not reached the heat storage target water temperature Tb1, the judgment is not satisfied (step ST19: NO), and the process proceeds to step ST20. In step ST20, the defrost control unit 44G judges whether or not a predetermined defrost start condition is satisfied. Here, the satisfaction of the defrost start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. For example, the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C), and the outdoor air temperature minus the refrigerant temperature on the outlet side of the air heat exchanger 10 is greater than 8°C. Alternatively, the condition is that a first heat storage time (for example, 40 minutes) has elapsed since the start of the heat storage operation, that is, the time counted by the counting unit 44H1 exceeds a certain time. The defrost start condition is satisfied when either one of these conditions is satisfied.
[0106] In step ST20, if a predetermined defrost start condition is not satisfied, the determination is not satisfied (step ST20: NO), and the process proceeds to step ST21, where the pump control unit 44D determines whether or not the current rotation speed of the circulation pump 34 is the lower limit rotation speed. If the current rotation speed of the circulation pump 34 is not the lower limit rotation speed, the determination is not satisfied (step ST21: NO), and the process proceeds to step ST17, where the rotation speed of the circulation pump 34 is reduced by 100 rpm.
[0107] As described above, there are cases where the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (thermal storage target water temperature Tb1) (step ST19: NO). In addition, there are cases where the defrost start condition is not satisfied (step ST20: NO) and the current rotation speed of the circulation pump 34 is not the lower limit rotation speed (step ST21: NO). At this time, the rotation speed of the circulation pump 34 is reduced by 100 rpm every minute by looping step ST19: NO → step ST20: NO → step ST21: NO → step ST17 → step ST18 → step ST19. And there are cases where the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (thermal storage target water temperature Tb1) (step ST19: NO) and the defrost start condition is not satisfied (step ST20: NO). Furthermore, if the current rotation speed of the circulation pump 34 reaches the lower limit rotation speed (step ST21: YES), the process proceeds to step ST19, and thereafter, the rotation speed of the circulation pump 34 is maintained at the lower limit rotation speed until the heat storage operation ends.
[0108] In step ST19, if the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (heat storage target water temperature Tb1) (step ST19: NO), the process proceeds to step ST20. In step ST20, if the defrost start condition is met (step ST20: YES), the heat storage control unit 44H ends the heat storage operation (step ST22). Then, the defrost control unit 44G starts the defrost operation.
[0109] Furthermore, in step ST19, if the hot water temperature detected by the inlet water temperature sensor 123 reaches the target hot water temperature (heat storage target water temperature Tb1), the determination is satisfied (step ST19: YES). Thereafter, the heat storage control unit 44H ends the heat storage operation (step ST23) and proceeds to step ST24. In step ST24, the defrost control unit 44G determines whether or not a predetermined defrost start condition is satisfied. Until the defrost start condition is satisfied, the determination in step ST24 is not satisfied (step ST24: NO) and the process waits in a loop, and when the defrost start condition is satisfied, the determination is satisfied (step ST24: YES), and the defrost control unit 44G starts the defrost operation.
[0110] <Defrosting operation during linked operation> Next, the defrosting operation during the linked operation will be described. The defrosting operation during the linked operation is a mode in which the refrigerant is circulated in the same direction as during the linked operation (so-called positive cycle defrosting), and the four-way valve control unit 44A switches the four-way valve 6 to a position in which the pipe section 11a communicates with the pipe section 11b and the pipe section 11c communicates with the pipe section 11d. The two-way valve control unit 44F switches the two-way valve 16 to a closed state. Furthermore, the expansion valve control unit 44C controls the expansion valve 8 to be in an open state and the expansion valve 15 to be in a fully closed state. The refrigerant discharged from the compressor 5 passes through the expansion valve 8 via the water-refrigerant heat exchanger 7 and is supplied to the air heat exchanger 10 to melt the frost generated on the air heat exchanger 10.
[0111] The defrosting operation is started when the defrost control unit 44G judges whether the defrosting start condition described above is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether a predetermined defrosting end condition is satisfied. The defrosting operation is completed when the defrost control unit 44G judges whether the defrosting start condition is satisfied. The defrosting end condition is, for example, that the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 reaches a preset defrosting end temperature (for example, 5°C).
[0112] When the defrosting operation is started, the defrost control unit 44G outputs a signal to the compressor control unit 44B indicating that the defrosting operation is in progress, and the compressor control unit 44B receives the signal and controls the compressor 5 at a preset defrosting rotation speed (constant rotation speed). Note that, although the compressor control unit 44B controls the rotation speed of the compressor 5 based on an instruction from the defrost control unit 44G here, the same control can be implemented even if the defrost control unit 44G directly controls the rotation speed of the compressor 5 during the defrosting operation.
[0113] Furthermore, when the defrosting operation is started, the defrost control unit 44G outputs a signal to the expansion valve control unit 44C to the effect that the defrosting operation is in progress. The expansion valve control unit 44C receives the signal and expands the expansion valve 8 to a predetermined opening degree (for example, fully open) that is greater than the opening degree during the linked operation, so that the refrigerant passing through the expansion valve 8 is not depressurized by the expansion valve 8. Note that, here, the expansion valve control unit 44C controls the opening degree of the expansion valve 8 based on an instruction from the defrost control unit 44G, but similar control can be performed even if the defrost control unit 44G directly controls the opening degree of the expansion valve 8 during the defrosting operation.
[0114] Furthermore, when the defrosting operation is started, the defrost control unit 44G outputs a signal to the pump control unit 44D indicating that the defrosting operation is in progress, and the pump control unit 44D receives the signal and controls the drive of the circulation pump 34 based on the refrigerant temperature detected by the refrigerant temperature sensor 13. Note that here, the pump control unit 44D controls the drive of the circulation pump 34 based on an instruction from the defrost control unit 44G. Alternatively, the same control can be performed even if the defrost control unit 44G directly controls the drive of the circulation pump 34 during the defrosting operation. For the sake of simplicity, hereinafter, it is assumed that the defrost control unit 44G directly controls the drive of the circulation pump 34 during the defrosting operation.
[0115] Here, the drive control (rotation speed control) of the circulation pump 34 during the defrosting operation will be described. During the defrosting operation, the defrost control unit 44G fully opens the expansion valve 8 to allow high-temperature refrigerant to flow through the air heat exchanger 10 to defrost the air heat exchanger 10, while controlling the drive of the circulation pump 34 based on the temperature detected by the refrigerant temperature sensor 13. Details will be described below.
[0116] First, at the start of the defrosting operation, the defrost control unit 44G stops the operation of the circulation pump 34, which had been operating up until then, and stops the circulation of the hot water. If the circulation pump 34 is in operation at the start of the defrosting operation, a part of the heat amount held by the refrigerant is absorbed into the hot water side due to the heat exchange between the refrigerant and the hot water in the water-refrigerant heat exchanger 7. As a result, the heat amount for defrosting the air heat exchanger 10 is lost, and the defrosting of the air heat exchanger 10 does not progress, so the operation of the circulation pump 34 is stopped at the start of the defrosting operation. In particular, since the amount of frost formed on the air heat exchanger 10 is large at the start of the defrosting operation, it is preferable to stop the operation of the circulation pump 34 at the start of the defrosting operation so that the heat amount held by the refrigerant is used only for defrosting. Note that the above-mentioned stopping of the circulation of the hot water means that the flow of the hot water is substantially stopped.
[0117] During the defrosting operation, the defrost control unit 44G may determine that the temperature detected by the refrigerant temperature sensor 13 has reached a predetermined circulating pump drive start condition that is always satisfied before the defrosting end condition is satisfied. In this case, the defrost control unit 44G drives the circulating pump 34 at a lower rotation speed than during the linked operation to circulate the hot water.
[0118] The circulation pump drive start condition is, for example, whether or not the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 has reached a preset circulation pump drive start temperature (higher than 0°C and lower than the defrost end temperature of 5°C, for example, 1°C) or higher. When the defrost control unit 44G determines that the circulation pump drive start condition is met, it starts driving the circulation pump 34 at a predetermined rotation speed (for example, 1000 rpm) lower than that during linked operation. As the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 increases and approaches the direction in which the defrost end condition is met, the defrost control unit 44G controls the circulation pump 34 to increase its rotation speed.
[0119] When the frost on the air heat exchanger 10 starts to melt during the defrosting operation, the amount of heat held by the refrigerant becomes excessive with respect to the amount of heat required for defrosting, and the refrigerant temperature detected by the refrigerant temperature sensor 13 rises. If nothing is done, the surplus heat other than the amount of heat required for defrosting is simply radiated from the air heat exchanger 10, resulting in heat radiation loss. In order to use the amount of heat radiation loss as heat for heating, the circulation pump 34 is started to operate when the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 rises and reaches a preset temperature or higher. At this time, the circulation pump 34 is started to operate at a lower rotation speed than during the linked operation, and part of the heat held by the refrigerant is absorbed into the hot water side in the water-refrigerant heat exchanger 7, and part of the heat that was previously used only for defrosting is used for heating. In addition, the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 rises and approaches the direction in which the defrost end condition is satisfied, which means that the amount of surplus heat other than the amount of heat required for defrosting has increased. In such a case, as the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 approaches the state in which the defrost termination condition is met, the rotation speed of the circulation pump 34 is increased to control the amount of heat used for heating.
[0120] At the start of defrosting operation, since there is a large amount of frost on the air heat exchanger 10, the operation of the circulation pump 34 is stopped so that the heat contained in the refrigerant is used only for defrosting. However, if the refrigerant temperature detected by the refrigerant temperature sensor 13 during defrosting operation rises to a predetermined temperature, the operation of the circulation pump 34 is started to circulate hot water to the heat exchange terminals 27 while continuing defrosting, thereby enabling heating.
[0121] In addition, table data showing the correspondence relationship between the refrigerant temperature r at the outlet side of the air heat exchanger 10 and the driving rotation speed of the circulation pump 34 is stored in advance in the defrost control unit 44G, and the rotation speed of the circulation pump 34 is determined based on this table data. Here, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is less than 1°C, the rotation speed of the circulation pump 34 is determined to be 0 rpm, that is, the circulation pump 34 is stopped. Furthermore, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is 1°C or more and less than 2°C, the rotation speed of the circulation pump 34 is determined to be 1000 rpm. Furthermore, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is 2°C or more and less than 3°C, the rotation speed of the circulation pump 34 is determined to be 1200 rpm. Furthermore, when the refrigerant temperature detected by the refrigerant temperature sensor 13 is 3°C or more and less than 5°C, the rotation speed of the circulation pump 34 is determined to be 1500 rpm.
[0122] As described above, the air conditioning system 1 stops the circulation of hot water at the start of a defrosting operation (positive cycle defrosting). During positive cycle defrosting, while continuing defrosting of the air heat exchanger 10, if it is determined that a predetermined condition has been reached based on the refrigerant temperature detected by the refrigerant temperature sensor 13, the circulation of hot water is started. In this way, while performing defrosting during the defrosting operation, the circulation pump 34 is appropriately driven to circulate hot water according to the refrigerant temperature on the outlet side of the air heat exchanger 10, and heating can also be performed by the heat exchange terminals 27.
[0123] In addition, the defrost control unit 44G stops the circulation pump 34 at the start of defrosting, and drives the circulation pump 34 when it is determined that the refrigerant temperature detected by the refrigerant temperature sensor 13 during defrosting operation has reached the circulation pump drive start condition that is satisfied before the defrost end condition is satisfied. At this time, the circulation pump 34 is driven at a lower rotation speed than during linked operation. As a result, at the start of the defrosting operation, since the amount of frost on the air heat exchanger 10 is large, the drive of the circulation pump 34 is stopped and defrosting is performed intensively so that the heat held by the refrigerant is used only for defrosting. Then, when the refrigerant temperature detected by the refrigerant temperature sensor 13 rises and reaches the circulation pump drive start condition, the circulation pump 34 is started to be driven at a lower rotation speed than during linked operation. As a result, it is possible to circulate hot water to the heat exchange terminal 27 to perform heating while continuing defrosting without taking away too much heat required for defrosting, and it is possible to shorten the non-heating time during the defrosting operation.
[0124] Furthermore, after determining that the circulation pump drive start condition has been reached, the defrost control unit 44G increases the rotation speed of the circulation pump 34 as the refrigerant temperature detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied (defrost end temperature). In this way, the fact that the refrigerant temperature detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied after reaching the circulation pump drive condition means that the temperature of the refrigerant on the outlet side of the air heat exchanger 10 has risen. Also, the amount of excess heat other than the amount of heat required for defrosting the air heat exchanger 10 has increased. In this case, the rotation speed of the circulation pump 34 is increased as the temperature of the refrigerant on the outlet side of the air heat exchanger 10 detected by the refrigerant temperature sensor 13 approaches the direction in which the defrost end condition is satisfied. This makes it possible to increase the amount of heat used for heating, and to suppress a decrease in the feeling of heating during defrosting operation.
[0125] The defrosting operation during linked operation has been described with an example in which the refrigerant is circulated in the same direction as during linked operation (so-called forward cycle defrosting). However, the defrosting operation during linked operation may be in a form in which the refrigerant is circulated in the same direction as during cold air cooling operation (so-called reverse cycle defrosting). In this case, the refrigerant discharged from the compressor 5 is supplied to the air heat exchanger 10, melts the frost formed in the air heat exchanger 10, passes through the expansion valve 8, and is returned to the compressor 5 via the water-refrigerant heat exchanger 7.
[0126] <Heat storage operation during linked operation> Next, the heat storage operation during the linked operation in this embodiment will be described. The heat storage operation during the linked operation is performed before the defrosting operation during the linked operation, and prevents the room temperature from dropping during the defrosting operation, which impairs the feeling of warmth. This heat storage operation is a combination of two types of heat storage operations: a first heat storage operation in which the room temperature is stored as the heat storage target, as in the heat storage operation during the warm air heating operation described above, and a second heat storage operation in which the hot water refrigerant is stored as the heat storage target, as in the heat storage operation during the floor heating operation described above.
[0127] Next, the heat storage operation during the linked operation will be described. Here, the description will be based on a situation where heating operation is performed by both the indoor unit 17 and the heat exchange terminal 27. When a predetermined heat storage operation start condition is satisfied during the linked operation, the heat storage operation during the linked operation performs a first heat storage operation to raise the room temperature above the set temperature set by the user by forced heating using the indoor unit 17. Furthermore, the heat storage operation during the linked operation performs a second heat storage operation to raise the temperature of the circulating fluid supplied to the heat exchange terminal 27. The heat storage operation during the linked operation performs both the first heat storage operation and the second heat storage operation. As a result, the heat storage operation during the linked operation can store heat distributed to multiple heat storage targets, so that comfort can be maintained without compromising the feeling of heating. Furthermore, the heat storage operation during the linked operation raises the room temperature and / or the temperature of the circulating fluid to a lower temperature than when only the first heat storage operation or the second heat storage operation is performed. The heat storage operation start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. That is, it is a condition that indicates that the defrosting operation will soon be started based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10 (a condition that is established before the defrosting start condition is established). Compared to the case where only the first heat storage operation or the second heat storage operation is performed, the condition that indicates that the defrosting operation will soon be started is, for example, a condition where the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10 have a larger difference. As a result, in the heat storage operation during the linked operation, the heat storage operation start condition is established at a timing closer to the timing at which the defrosting start condition is established.
[0128] During the linked operation, the heat storage control unit 44H judges whether the heat storage operation start condition is satisfied, and when it judges that the heat storage operation start condition is satisfied, it starts the heat storage operation. At the same time as the start of this heat storage operation, the counting unit 44H1 also starts counting. When the heat storage operation is started, a signal indicating that the heat storage operation is in progress is output from the heat storage control unit 44H. The target room temperature determination unit 44J receives the signal and sets the heat storage target room temperature Ta2 as a second predetermined temperature that is higher than the air conditioner set temperature Tcon during the linked operation that was set up until then and lower than the heat storage target room temperature Ta1 as a new target room temperature. At the same time, the target return temperature determination unit 44E receives the signal and sets the heat storage target water temperature Tb2 as a fourth predetermined temperature that is higher than the target return temperature during the linked operation that was set up until then and lower than the heat storage target water temperature Tb1 as a new target return temperature. As a result, when storing heat distributed to multiple heat storage targets, the temperature of the heat storage targets is not raised too much and the relative humidity does not drop significantly, so the room does not become dry and comfort can be maintained.
[0129] At this time, the compressor control unit 44B controls the rotation speed of the compressor 5 so that the temperature of the indoor air detected by the indoor temperature sensor 19 becomes the heat storage target room temperature Ta2 set by the target room temperature determination unit 44J. At the same time, the compressor control unit 44B controls the rotation speed of the compressor 5 so that the temperature of the hot water detected by the inlet water temperature sensor 123 becomes the heat storage target water temperature Tb2 set by the target return temperature determination unit 44E. In actual operation, immediately after the start of the heat storage operation, the target room temperature is changed to the heat storage target room temperature Ta2, which is a temperature higher than the target room temperature (air conditioner set temperature Tcon) during the linked operation that had been set up until then. In addition, the heat storage target room temperature Ta2, which is the temperature by which the temperature of the indoor air is increased, is determined according to the heat storage temperature coefficient. This heat storage temperature coefficient is calculated by subtracting the temperature of the indoor air at the start of the heat storage operation from the target room temperature during the warm air heating operation. The larger this heat storage temperature coefficient is, the higher the heat storage target room temperature Ta2 is determined to be. At the same time, the target return temperature (target hot water temperature) is changed to the heat storage target water temperature Tb2, which is a temperature higher than the target return temperature during the linked operation that had been set up until then. Also, the heat storage target water temperature Tb2, which is the temperature to which the hot water temperature is increased, is determined according to the heat storage temperature coefficient. This heat storage temperature coefficient is calculated by subtracting the water temperature at the start of the heat storage operation from the target return temperature during floor heating operation. The larger this heat storage temperature coefficient is, the higher the heat storage target water temperature Tb2 is determined to be. This makes it possible to maintain comfort without excessively increasing the temperature of the heat storage target. As a result, the temperature difference between the indoor air temperature detected by the indoor temperature sensor 19 and the heat storage target room temperature Ta2, and the temperature difference between the hot water temperature detected by the inlet water temperature sensor 123 and the heat storage target water temperature Tb2 are larger than those during the linked operation immediately before the heat storage operation. This causes the compressor control unit 44B to increase the number of revolutions of the compressor 5. Then, when the indoor air temperature detected by the indoor temperature sensor 19 reaches the target room temperature (heat storage target room temperature Ta2), the indoor air temperature detected by the indoor temperature sensor 19 is maintained at the target room temperature. At the same time, when the hot water temperature detected by the inlet water temperature sensor 123 reaches the target return temperature (thermal storage target water temperature Tb2), the hot water temperature detected by the inlet water temperature sensor 123 is maintained at the target return temperature. To achieve this, the compressor control unit 44B reduces the rotation speed of the compressor 5.
[0130] Also, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal indicating that the heat storage operation is in progress to the target discharge temperature setting unit 44I. When the target discharge temperature setting unit 44I receives the signal, it controls to maintain the target discharge temperature that was set during the linked operation immediately before the heat storage operation was started. That is, during the heat storage operation, the setting method of changing the target discharge temperature according to the target room temperature (air conditioner set temperature Tcon) or the target return temperature (target hot water temperature) as in the linked operation is not adopted. As a result, even if the target room temperature is changed to a predetermined heat storage target room temperature Ta2 that is higher than during the linked operation, or the target return temperature is changed to a predetermined heat storage target water temperature Tb2 that is higher than during the linked operation, the target discharge temperature that was set during the linked operation immediately before the heat storage operation was started is maintained as it is. That is, the target discharge temperature is maintained until the heat storage operation is completed.
[0131] At this time, the target discharge temperature is maintained as it was when it was set during the linked operation immediately before the start of the heat storage operation. Therefore, the expansion valve control unit 44C does not significantly change the opening of the expansion valve 8 and the expansion valve 15. Also, immediately after the start of the heat storage operation, the opening is maintained at the time of the linked operation immediately before the start of the heat storage operation. During the heat storage operation, although the temperature of the refrigerant discharged from the compressor 5 may be somewhat high or low, the target discharge temperature is not made higher than that during the linked operation immediately before the start of the heat storage operation. Therefore, the opening of the expansion valve 8 and the expansion valve 15 is not significantly narrowed (closed), and the temperature of the refrigerant circulated to the air heat exchanger 10 does not drop significantly.
[0132] Furthermore, when the heat storage operation is started, the heat storage control unit 44H also outputs a signal to the indoor unit control unit 20 indicating that the heat storage operation is in progress. When the indoor unit control unit 20 receives this signal, the indoor unit control unit 20 controls the rotation speed of the indoor fan 18 to be increased to a heat storage operation rotation speed that is higher than that during linked operation. Furthermore, a signal to the effect that the heat storage operation is in progress is also output from the heat storage control unit 44H to the pump control unit 44D, and when the pump control unit 44D receives this signal, the pump control unit 44D controls the rotation speed of the circulation pump 34 to be lower than that during linked operation.
[0133] Here, it is assumed that the temperature of the refrigerant flowing into the indoor heat exchanger 14 is constant, and a constant amount of heat is given from the refrigerant to the indoor air in the indoor heat exchanger 14. When the rotation speed of the indoor fan 18 is increased, the circulation flow rate of the indoor air per unit time increases, and the heat exchange efficiency increases, so the amount of heat to be given from the indoor heat exchanger 14 to the indoor air increases. Therefore, when the rotation speed of the indoor fan 18 is increased during the heat storage operation, the temperature of the indoor air can be increased. Furthermore, since the target room temperature during the heat storage operation is set to a predetermined heat storage target room temperature Ta2 that is higher than the target room temperature during the linked operation and lower than the heat storage target room temperature Ta1, the rotation speed of the compressor 5 is controlled in a direction to increase. As a result, the circulation flow rate of the refrigerant passing through the indoor heat exchanger 14 increases, and the amount of heat to be given from the refrigerant to the indoor air in the indoor heat exchanger 14 increases, so that the temperature of the indoor air is easily increased. In addition, the rotation speed of the indoor fan 18 is increased during the heat storage operation to increase the temperature of the hot air supplied to the indoor air, but heat storage in hot water is also performed in combination. Therefore, compared to when heat is stored by only increasing the temperature of the indoor air, the temperature by which the indoor air temperature is increased is kept low, so that the room temperature of the room corresponding to the indoor unit 17 does not rise too much, and the user does not feel uncomfortable.
[0134] Here, it is assumed that the temperature of the hot water flowing into the water-refrigerant heat exchanger 7 is constant, and a constant amount of heat is given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7. When the rotation speed of the circulation pump 34 is reduced, the circulation flow rate of the hot water per unit time is reduced and the temperature efficiency is increased, so the temperature of the hot water flowing out from the water-refrigerant heat exchanger 7 is higher. Therefore, when the rotation speed of the circulation pump 34 is reduced during the heat storage operation, the temperature of the hot water supplied to the heat exchange terminal 27 can be increased. Furthermore, since the target hot water temperature during the heat storage operation is set to the heat storage target water temperature Tb2 that is higher than the target hot water temperature during the linked operation, the rotation speed of the compressor 5 is controlled in a direction to increase. As a result, the circulation flow rate of the refrigerant passing through the water-refrigerant heat exchanger 7 increases, and the amount of heat to be given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7 increases, so that it becomes easier to increase the temperature of the hot water flowing out from the water-refrigerant heat exchanger 7. In addition, since the rotation speed of the circulation pump 34 is lower than that during the linked operation, the amount of heat given from the refrigerant to the hot water in the water-refrigerant heat exchanger 7 is reduced, and the temperature of the refrigerant flowing out from the water-refrigerant heat exchanger 7 is increased. This increases the temperature of the refrigerant circulated to the air heat exchanger 10, and the progress of frost adhesion to the air heat exchanger 10 can be suppressed. Furthermore, the rotation speed of the circulation pump 34 is reduced during the heat storage operation to increase the temperature of the hot water supplied to the heat exchange terminal 27, but the rotation speed of the circulation pump 34 is reduced. This reduces the circulation flow rate of the hot water, making it difficult for heat to be dissipated by the heat exchange terminal 27, and although the temperature of the hot water itself increases, heat storage in the indoor air is also performed in combination. Therefore, compared to the case where only the temperature of the hot water is increased to store heat, the temperature of the hot water is increased to a low level, so the room temperature of the room corresponding to the heat exchange terminal 27 does not rise too much, and the user does not feel uncomfortable.
[0135] The control of the rotation speed reduction of the circulation pump 34 during the heat storage operation will be described in more detail. During the heat storage operation, the pump control unit 44D controls the rotation speed of the circulation pump 34 to be gradually reduced by a predetermined value at every predetermined time until the hot water temperature detected by the inlet water temperature sensor 123 reaches the heat storage target water temperature Tb2. The lower limit rotation speed of the circulation pump 34 that can be reduced during the heat storage operation is set in advance. In addition, the rotation speed of the circulation pump 34 is gradually reduced, and there are cases where the rotation speed of the circulation pump 34 reaches the preset lower limit rotation speed while the hot water temperature detected by the inlet water temperature sensor 123 reaches the heat storage target water temperature Tb2. In such a case, after reaching the lower limit rotation speed, the circulation pump 34 is controlled at the lower limit rotation speed.
[0136] During the linked operation and the heat storage operation, if the outside air temperature is low, frost gradually forms on the air heat exchanger 10. If a predetermined defrost start condition is met during the heat storage operation, the defrost control unit 44G starts executing a defrost operation to melt the frost on the air heat exchanger 10 after the heat storage operation is terminated.
[0137] In order to realize the control during the heat storage operation, the control procedure executed by the outdoor unit control unit 44 will be described with reference to the flowchart in Fig. 8. Here, a situation where linked operation is performed using both the indoor unit 17 and the heat exchange terminal 27 will be described.
[0138] During the linked operation, the heat storage control unit 44H judges whether or not the heat storage operation start condition is satisfied (step ST25). Here, the satisfaction of the heat storage operation start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. The heat storage operation start condition is, for example, a condition that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C) and the outdoor air temperature-the refrigerant temperature on the outlet side of the air heat exchanger 10>6°C as a second temperature difference larger than the first temperature difference. In addition, by setting the second temperature difference larger than the first temperature difference, the heat storage control unit 44H does not raise the temperature of the heat storage target too much and does not raise the temperature of the heat storage target insufficiently, so that comfort can be maintained. When the heat storage control unit 44H judges that the heat storage operation start condition is satisfied, it starts the heat storage operation (step ST26), and the counting unit 44H1 starts counting the time of the heat storage operation (step ST27).
[0139] Thereafter, the target room temperature determination unit 44J sets the heat storage target room temperature Ta2 as the target room temperature (step ST28), and proceeds to step ST29. Note that the heat storage target room temperature Ta2 in step ST28 is a temperature lower than the heat storage target room temperature Ta1 in ST4.
[0140] Thereafter, the target return temperature determination unit 44E sets the heat storage target water temperature Tb2 as the target hot water temperature (target return temperature) (step ST29), and proceeds to step ST30. Note that the heat storage target water temperature Tb2 set in step ST29 is a temperature lower than the heat storage target water temperature Tb1 set in step ST15.
[0141] In step ST30, the target discharge temperature setting unit 44I continues to set the target discharge temperature to the same temperature as the target discharge temperature that was set during the linked operation immediately before the start of the heat storage operation.
[0142] In step ST31, the indoor unit control section 20 increases the rotation speed of the indoor fan 18 to the heat storage operation rotation speed, which is a rotation speed higher than that during linked operation.
[0143] In step ST32, the pump control unit 44D reduces the rotation speed of the circulation pump 34 from the rotation speed during linked operation (eg, 3500 rpm) by a predetermined value (eg, 100 rpm).
[0144] Thereafter, in step ST33, the heat storage control unit 44H determines whether a predetermined time (here, one minute) has elapsed. If one minute has not elapsed, the condition is not satisfied and the process enters a loop standby state (step ST33: NO), whereas if one minute has elapsed, the condition is satisfied (step ST33: YES) and the process proceeds to step ST34.
[0145] In step ST34, the heat storage control unit 44H judges whether or not the hot water temperature detected by the inlet water temperature sensor 123 has reached the target hot water temperature (heat storage target water temperature Tb2) set in step ST29. If the hot water temperature detected by the inlet water temperature sensor 123 has not reached the heat storage target water temperature Tb2, the judgment is not satisfied (step ST34: NO), and the process proceeds to step ST35. In step ST35, the defrost control unit 44G judges whether or not a predetermined defrost start condition is satisfied. Here, the satisfaction of the defrost start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. For example, the condition is that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C), and the outdoor air temperature-the refrigerant temperature on the outlet side of the air heat exchanger 10>10°C, making it more difficult to start defrosting than when performing a single heat storage operation. Or, a second heat storage time (e.g., 30 minutes) that is shorter than the first heat storage time has elapsed since the start of the heat storage operation, that is, the time counted by the counting unit 44H1 exceeds a certain time. Either one of these conditions must be met. Furthermore, by setting the second heat storage time to be shorter than the first heat storage time, heat can be stored in a short time when heat is distributed and stored in a plurality of heat storage targets, and comfort can be maintained without excessively increasing the temperature of the heat storage targets.
[0146] In step ST35, if a predetermined defrost start condition is not satisfied, the determination is not satisfied (step ST35: NO), and the process proceeds to step ST36, where the pump control unit 44D determines whether or not the current rotation speed of the circulation pump 34 is the lower limit rotation speed. If the current rotation speed of the circulation pump 34 is not the lower limit rotation speed, the determination is not satisfied (step ST36: NO), and the process proceeds to step ST32, where the rotation speed of the circulation pump 34 is reduced by 100 rpm.
[0147] As described above, there are cases where the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (thermal storage target water temperature Tb2) (step ST34: NO). In addition, there are cases where the defrost start condition is not satisfied (step ST35: NO) and the current rotation speed of the circulation pump 34 is not the lower limit rotation speed (step ST36: NO). In this case, the process loops from step ST34: NO to step ST35: NO to step ST36: NO to step ST32 to step ST33 to step ST34, and the rotation speed of the circulation pump 34 decreases by 100 rpm every minute. Then, there are cases where the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (thermal storage target water temperature Tb2) (step ST34: NO). In addition, there are cases where the defrost start condition is not satisfied (step ST35: NO) but the current rotation speed of the circulation pump 34 has reached the lower limit rotation speed (step ST36: YES). In this case, the process proceeds to step ST34, and thereafter, the rotation speed of the circulation pump 34 is maintained at the lower limit rotation speed until the heat storage operation is completed.
[0148] In step ST34, if the hot water temperature detected by the inlet water temperature sensor 123 has not reached the target hot water temperature (heat storage target water temperature Tb2) (step ST34: NO), the process proceeds to step ST35. In step ST35, if the defrost start condition is met (step ST35: YES), the heat storage control unit 44H ends the heat storage operation (step ST37). Then, the defrost control unit 44G starts the defrost operation.
[0149] Furthermore, in step ST34, if the hot water temperature detected by the inlet water temperature sensor 123 reaches the target hot water temperature (thermal storage target water temperature Tb2), the determination is satisfied (step ST34: YES), and the process proceeds to step ST38.
[0150] In step ST38, the heat storage control unit 44H judges whether or not the temperature of the indoor air detected by the indoor temperature sensor 19 has reached the target room temperature (heat storage target room temperature Ta2) set in step ST28. If the temperature of the indoor air detected by the indoor temperature sensor 19 has not reached the heat storage target room temperature Ta2, the judgment is not satisfied (step ST38: NO), and the process proceeds to step ST39. In step ST39, the defrost control unit 44G judges whether or not a predetermined defrost start condition is satisfied. Here, the satisfaction of the defrost start condition is a condition that is set based on the outdoor air temperature and the refrigerant temperature on the outlet side of the air heat exchanger 10. For example, the condition is that the outdoor air temperature is equal to or lower than a predetermined temperature (for example, 2°C), and the outdoor air temperature-the refrigerant temperature on the outlet side of the air heat exchanger 10>10°C, making it more difficult to start defrosting than when performing a single heat storage operation. Or, one of the following conditions is met: a second heat storage time (e.g., 30 minutes) that is shorter than the first heat storage time has elapsed since the start of heat storage operation, i.e., the time counted by counting unit 44H1 exceeds a certain time.
[0151] In step ST39, if the predetermined defrost start condition is not established, the determination is not satisfied (step ST39: NO), and the process proceeds to step ST38.
[0152] As described above, there are cases where the indoor air temperature detected by the indoor temperature sensor 19 has not reached the target room temperature (heat storage target room temperature Ta2) (step ST38: NO), and the defrost start condition is not satisfied (step ST39: NO). In this case, the process loops from step ST38: NO to step ST39: NO to step ST38.
[0153] In step ST38, if the indoor air temperature detected by the indoor temperature sensor 19 has not reached the target room temperature (heat storage target room temperature Ta2) (step ST38: NO), the process proceeds to step ST39. In step ST39, if the defrosting start condition is met (step ST39: YES), the heat storage control unit 44H ends the heat storage operation (step ST37). Then, the defrost control unit 44G starts the defrosting operation.
[0154] In step ST38, if the indoor air temperature detected by the indoor temperature sensor 19 reaches the target room temperature (thermal storage target room temperature Ta2), the determination is satisfied (step ST38: YES), and the thermal storage control unit 44H ends the thermal storage operation (step ST40). Then, the process proceeds to step ST41.
[0155] In step ST41, the defrost control unit 44G determines whether or not a predetermined defrost start condition is satisfied. Until the defrost start condition is satisfied, the determination in step ST41 is not satisfied (step ST41: NO) and the system remains in a loop waiting state. When the defrost start condition is satisfied, the determination is satisfied (step ST41: YES), and the defrost control unit 44G starts the defrost operation.
[0156] In the conventional system, when frost forms on the air heat exchanger 10, a heat storage operation is performed to prevent loss of warmth during defrosting. At that time, only one of the two types of heat storage operation, the first heat storage operation in which the room temperature is stored as the heat storage target, and the second heat storage operation in which the hot water refrigerant is stored as the heat storage target, is performed.
[0157] However, when only the first heat storage operation is performed and only the room temperature is raised, the room temperature may rise too much, resulting in a loss of comfort. Also, when only the second heat storage operation is performed and only the hot water temperature is raised, the hot water temperature supplied to the heat exchange terminal 27 may rise too much, resulting in a loss of comfort.
[0158] <Overview of the Method of the Present Embodiment> Therefore, in this embodiment, if frost forms on the air heat exchanger 10 during linked operation, a defrosting operation is performed, and a heat storage operation is performed before the defrosting operation. This heat storage operation is a first heat storage operation in which the indoor air is used as a heat storage target by the indoor unit 17, and the temperature of this heat storage target is raised to a predetermined temperature. At the same time, the heat storage operation is a second heat storage operation in which the hot water circulating through the heat exchange terminals 27 is used as a heat storage target, and the temperature of this heat storage target is raised to a predetermined temperature. The heat storage operation is a combined heat storage operation in which these two types of heat storage operations are performed together.
[0159] Further, the heat storage target room temperature Ta2, which is the temperature at which the temperature of the heat storage target of the first heat storage operation is increased when the combined heat storage operation is performed, is set to a value smaller than the heat storage target room temperature Ta1, which is the temperature at which the temperature of the heat storage target is increased when the independent heat storage operation is performed in which only the first heat storage operation is performed. And / or, the heat storage target water temperature Tb2, which is the temperature at which the temperature of the heat storage target of the second heat storage operation is increased when the combined heat storage operation is performed, is set to a value smaller than the heat storage target water temperature Tb1, which is the temperature at which the temperature of the heat storage target is increased when the independent heat storage operation is performed in which only the second heat storage operation is performed.
[0160] In addition, the heat storage operation is ended after at least one of the first heat storage operation and the second heat storage operation is started. The heat storage time, which is the time until the defrosting operation is started, is set to be shorter than the first heat storage time, which is the heat storage time when performing the single heat storage operation in which only one of the first heat storage operation and the second heat storage operation is performed, than the second heat storage time, which is the heat storage time when performing the combined heat storage operation.
[0161] The heat storage operation has a heat storage target room temperature Ta1, which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the first heat storage operation is performed, and a heat storage target room temperature Ta2, which is a temperature at which the temperature of the heat storage target of the first heat storage operation is increased when performing a combined heat storage operation. In addition, the heat storage operation has a heat storage target water temperature Tb1, which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the second heat storage operation is performed. Furthermore, the heat storage operation has a heat storage target water temperature Tb2, which is a temperature at which the temperature of the heat storage target of the second heat storage operation is increased when performing a combined heat storage operation. At least one of the heat storage target room temperature Ta1, the heat storage target room temperature Ta2, the heat storage target water temperature Tb1, and the heat storage target water temperature Tb2 is determined according to the heat storage temperature coefficient. The heat storage temperature coefficient is calculated by subtracting the temperature of the heat storage object at the start of heat storage operation from the target temperature of the heat storage object during heating operation, and the larger this heat storage temperature coefficient is, the higher the temperature to which the temperature of the heat storage object is raised when heat storage operation is performed is determined to be.
[0162] Moreover, the start of the heat storage operation is determined according to a temperature difference calculated by subtracting the outside air temperature from the temperature of the air heat exchanger 10. The temperature difference is such that the second temperature difference, which is the temperature difference at which the combined heat storage operation is started, is set to be larger than the first temperature difference, which is the temperature difference at which the single heat storage operation, in which only one of the first heat storage operation and the second heat storage operation is started.
[0163] <Effects of the embodiment> As described above, the air conditioning system 1 of this embodiment performs a heat storage operation before a defrosting operation. In this heat storage operation, the indoor air is treated as a heat storage target by the indoor unit 17, and a first heat storage operation is performed in which the temperature of this heat storage target is raised by a predetermined temperature. At the same time, this heat storage operation performs a second heat storage operation in which hot water circulating through the heat exchange terminal 27 is treated as a heat storage target and the temperature of this heat storage target is raised by a predetermined temperature. This heat storage operation performs a combined heat storage operation in which these two types of heat storage operations are performed together. As a result, this heat storage operation can distribute and store heat in multiple heat storage targets, so that comfort can be maintained without compromising the feeling of warmth.
[0164] In addition, in the heat storage operation, the heat storage target room temperature Ta2 is set to a value smaller than the heat storage target room temperature Ta1, and / or the heat storage target water temperature Tb2 is set to a value smaller than the heat storage target water temperature Tb1. In this way, in the combined heat storage operation, when heat is distributed and stored in a plurality of heat storage targets, the temperature of the heat storage targets is not raised too much, and comfort can be maintained.
[0165] In addition, by setting the second heat storage time to be shorter than the first heat storage time, when distributing and storing heat in multiple heat storage targets, heat can be stored in a short period of time, and comfort can be maintained without excessively raising the temperature of the heat storage targets.
[0166] At least one of the heat storage target room temperature Ta1, the heat storage target room temperature Ta2, the heat storage target water temperature Tb1, and the heat storage target water temperature Tb2, which are the temperatures to which the temperature of the heat storage target is increased, is determined according to the heat storage temperature coefficient. The heat storage temperature coefficient is calculated by subtracting the temperature of the heat storage target at the start of the heat storage operation from the target temperature of the heat storage target during heating operation. The larger the heat storage temperature coefficient is, the higher the temperature to which the temperature of the heat storage target is increased is determined, so that comfort can be maintained without excessively increasing the temperature of the heat storage target.
[0167] In addition, the start of the heat storage operation is determined according to the temperature difference calculated by subtracting the outside air temperature from the temperature of the air heat exchanger 10. The second temperature difference, which is the temperature difference at which the combined heat storage operation is started, is set to a value larger than the first temperature difference, which is the temperature difference at which the single heat storage operation is started, in which only one of the first heat storage operation and the second heat storage operation is performed. This makes it possible to maintain comfort since the heat storage operation does not raise the temperature of the heat storage target too much and does not insufficiently raise the temperature of the heat storage target.
[0168] In addition, in this embodiment, the heat exchange terminal 27 is described as a so-called floor heating panel that heats the floor surface, but a hot water panel or a hot / cold water panel capable of heating may also be used.
[0169] Furthermore, in this embodiment, the terminal that heats the air in the space to be air-conditioned has been described as the so-called indoor unit 17 of an air conditioner. However, the terminal that heats the air in the space to be air-conditioned may be a heat exchange terminal 27 equipped with a fan equivalent to the indoor fan of the indoor unit 17. For example, the terminal that heats the air in the space to be air-conditioned may be a fan coil or a hot water room heater that uses hot water as a heat source by passing it through the heat exchange terminal 27, exchanges heat with the indoor air, and releases the heat to heat the air in the space to be air-conditioned. [Explanation of symbols]
[0170] 1. Air conditioning system 4 Outdoor unit 5. Compressor 7 Water refrigerant heat exchanger 7a Water flow path (water passage) 7b Refrigerant side flow path (refrigerant passage) 10. Air Heat Exchanger 12 Outside air temperature sensor (outside air temperature detection means) 13 Refrigerant temperature sensor (air heat exchanger temperature detection means) 14 Indoor heat exchanger 17 Indoor unit 27 Heat exchange terminal 33 Heating circulation circuit (hot water circulation circuit) 130 Refrigerant circulation circuit
Claims
1. an indoor unit including an indoor heat exchanger that exchanges heat between the indoor air in a space to be air-conditioned and a refrigerant; A heat exchange terminal for heating a floor surface of the space to be air-conditioned; an outdoor unit including a water-refrigerant heat exchanger having a refrigerant passage and a water passage, the water passage being configured to exchange heat between the refrigerant in the refrigerant passage and the water in the water passage, an air heat exchanger being configured to exchange heat between the refrigerant and outside air, and a compressor; having The air conditioner includes an outside air temperature detection means for detecting an outside air temperature, and an air heat exchanger temperature detection means for detecting a temperature of the air heat exchanger, In an air conditioning system, the water passage of the water-refrigerant heat exchanger and the heat exchange terminal are connected in a ring shape by hot and cold water piping to form a hot and cold water circulation circuit, and the indoor heat exchanger, the refrigerant passage of the water-refrigerant heat exchanger, the air heat exchanger, and the compressor are connected by refrigerant piping to form a refrigerant circulation circuit, and the system can perform linked operations of a hot air heating operation for heating indoor air by the indoor unit and a floor heating operation for heating the floor surface by the heat exchange terminal, This air conditioning system is characterized by: determining whether or not frost has formed on the air heat exchanger depending on the difference between the outside air temperature and the temperature of the air heat exchanger; and, if frost has formed on the air heat exchanger, performing a defrosting operation to remove the frost that has formed on the air heat exchanger; and, prior to the defrosting operation, performing a combined heat storage operation to perform two types of heat storage operations together: a first heat storage operation in which the indoor air is used as a heat storage target by the indoor unit and the temperature of this heat storage target is raised to a predetermined temperature; and a second heat storage operation in which hot water circulating through the heat exchange terminal is used as a heat storage target and the temperature of this heat storage target is raised to a predetermined temperature.
2. The air conditioning system according to claim 1, characterized in that a second predetermined temperature, which is a temperature at which the temperature of the heat storage target of the first heat storage operation is increased when the combined heat storage operation is performed, is set to a smaller value than a first predetermined temperature, which is a temperature at which the temperature of the heat storage target of the first heat storage operation is increased when an independent heat storage operation is performed in which only the first heat storage operation is performed, and / or a fourth predetermined temperature, which is a temperature at which the temperature of the heat storage target of the second heat storage operation is increased when the combined heat storage operation is performed, is set to a smaller value than a third predetermined temperature, which is a temperature at which the temperature of the heat storage target of the second heat storage operation is increased when an independent heat storage operation is performed in which only the second heat storage operation is performed.
3. 3. The air conditioning system according to claim 1 or 2, wherein a heat storage time, which is a time from when a heat storage operation in which at least one of the first heat storage operation and the second heat storage operation is started to when the heat storage operation is ended and the defrosting operation is started, is set to be shorter than a first heat storage time, which is a heat storage time when a single heat storage operation in which only one of the first heat storage operation and the second heat storage operation is performed, and a second heat storage time, which is a heat storage time when the combined heat storage operation is performed.
4. The air conditioning system according to any one of claims 1 to 3, characterized in that the air conditioning system has a first predetermined temperature which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the first heat storage operation is performed, a second predetermined temperature which is a temperature at which the temperature of the heat storage target of the first heat storage operation is increased when performing the combined heat storage operation, a third predetermined temperature which is a temperature at which the temperature of the heat storage target is increased when performing an independent heat storage operation in which only the second heat storage operation is performed, and a fourth predetermined temperature which is a temperature at which the temperature of the heat storage target of the second heat storage operation is increased when performing the combined heat storage operation, and at least one of the first predetermined temperature, the second predetermined temperature, the third predetermined temperature, and the fourth predetermined temperature is determined according to a heat storage temperature coefficient calculated by subtracting the temperature of the heat storage target at the start of the heat storage operation from the target temperature of the heat storage target during heating operation, and the larger the heat storage temperature coefficient, the higher the value of the heat storage temperature coefficient is determined.
5. The air conditioning system according to any one of claims 1 to 4, characterized in that the start of the heat storage operation is determined based on a temperature difference calculated by subtracting the outside air temperature from the temperature of the air heat exchanger, and a second temperature difference, which is a temperature difference at which the combined heat storage operation is started, is set to a larger value than a first temperature difference, which is a temperature difference at which a single heat storage operation is started in which only one of the first heat storage operation and the second heat storage operation is performed.
Citation Information
Patent Citations
Heat-pump floor heater air conditioner
JP2003172523A
Heat pump type air conditioner
JP2006046692A
Floor heating device
JP2006046700A
Air conditioner
JP2016017725A
Air conditioner
JP2018066502A