Test support system and control method thereof

The test support system addresses the issue of undetected defects by updating test contents to include all necessary tests, ensuring comprehensive execution and improved test efficiency.

JP7651081B1Active Publication Date: 2025-03-25MITSUBISHI ELECTRIC BUILDING SOLUTIONS CORP +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2024564574
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2023-06-28
Publication Date
2025-03-25
Estimated Expiration
2043-06-28

AI Technical Summary

Technical Problem

Existing automated test execution systems may inadvertently exclude necessary tests when removing duplicates, leading to undetected defects in unit tests that are only detected in system tests, thereby reducing test efficiency and potentially causing issues in customer-facing products.

Method used

A test support system that includes a processor and memory to update test contents by adding tests to a second confirmation test based on differences between the contents of a first and second confirmation test, ensuring that all necessary tests are executed without duplicating effort.

Benefits of technology

Prevents defects from being undetected in confirmation tests by ensuring that all necessary tests are executed, improving test efficiency and reducing the risk of issues in customer products.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007651081000001
    Figure 0007651081000001
  • Figure 0007651081000002
    Figure 0007651081000002
  • Figure 0007651081000003
    Figure 0007651081000003
Patent Text Reader

Abstract

The processor (411) executes an update process to update the contents of a plurality of tests. The monitoring system executes internal processing according to a given input value, and outputs an output value as a result. The confirmation tests include a first confirmation test and a second confirmation test that is performed after the first confirmation test. In the update process, the processor (411) adds a test to the second confirmation test based on the difference between the contents of the first confirmation test and the contents of the second confirmation test.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a test support system that supports a verification test for verifying the validity of input / output values ​​input and output in a monitoring system including equipment and a server device that monitors the equipment via a controller. [Background technology]

[0002] Japanese Patent Laid-Open Publication No. 2009-217664 (Patent Document 1) discloses an automatic test execution system that analyzes the source code of the test target and tests the target program by inputting various values ​​to the program. This automatic test execution system analyzes the conditional expressions defined in the method, extracts boundary values, and generates all test data and return values ​​of the test data as a test execution result table.

[0003] Then, by embedding a trace function that tracks the process flow in the source code to be tested, trace information is derived and linked to the test execution result table mentioned above to eliminate duplicate test cases that should be executed. By eliminating duplicate test cases, it is possible to exclude from the test targets test cases that do not contribute to the coverage rate, which is an index showing the percentage of a program that has been tested. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] JP 2009-217664 A Summary of the Invention [Problem to be solved by the invention]

[0005] However, in the automatic test execution system described in Patent Document 1, by deleting duplicated tests (test cases), tests that are necessary but do not contribute to improving the coverage rate may be excluded. For example, there is a case where tests that check input / output values ​​that can change continuously are performed consecutively. In such a case, by performing these two tests, it is possible to check the change in the output value. However, if the latter test is deleted, the above check cannot be performed.

[0006] In a monitoring system that includes equipment and a server device that monitors the equipment via a controller such as a PLC (Programmable Logic Controller), for example, a testing format is envisaged in which a unit test that checks the input / output data of the PLC is carried out as a confirmation test, and then a system test (combination test) that tests the entire monitoring system is carried out as the next step of confirmation testing.

[0007] In this case, by deleting duplicate tests in unit testing in order to reduce the number of tests, defects that should have been detected in unit testing may not be detected in the unit testing, but may be detected in the next process, system testing. In such a case, after fixing the software defects, the tester must go back to the unit testing and retest, which reduces the efficiency of the testing.

[0008] In addition, if the test items for system testing are not sufficiently selected and the tests that should be performed are not performed, defects may occur in the product that is in operation at the customer's site after the product is delivered to the customer. This can happen because different testers are responsible for unit testing and system testing, and the necessary information is not shared between them. For example, even if the test items for unit testing are sufficiently selected, the contents of these test items may not be fully reflected in the system testing, and test items that should be performed in the system testing may be missing.

[0009] The present disclosure has been made to solve the above-mentioned problems, and its purpose is to provide a test support system and a control method thereof that can prevent defects that should be detected in confirmation testing from occurring at a customer's site. [Means for solving the problem]

[0010] The test support system according to the present disclosure is a system that supports a confirmation test that confirms the validity of input / output values ​​input and output in a monitoring system that includes equipment and a server device that monitors the equipment via a controller. The test support system includes a memory and a processor. The memory stores the contents of multiple tests to be performed in the confirmation test. The processor executes an update process that updates the contents of the multiple tests. The monitoring system executes internal processing according to a given input value, and outputs an output value as a result. The confirmation test includes a first confirmation test and a second confirmation test that is performed after the first confirmation test. In the update process, the processor adds a test to the second confirmation test based on a difference between the contents of the first confirmation test and the contents of the second confirmation test.

[0011] A control method according to the present disclosure is a control method for a test support system that supports a confirmation test that confirms the validity of input / output values ​​input and output in a monitoring system including equipment and a server device that monitors the equipment via a controller. The control method includes a step of storing the contents of a plurality of tests to be performed in the confirmation test, and a step of updating the contents of the plurality of tests. The monitoring system executes internal processing according to a given input value, and outputs an output value as a result. The confirmation test includes a first confirmation test and a second confirmation test that is performed after the first confirmation test. The updating step further includes a step of adding a test to the second confirmation test based on a difference between the contents of the first confirmation test and the contents of the second confirmation test. Effect of the Invention

[0012] According to the present disclosure, tests are added to the confirmation test of the next process based on the differences between the contents of the confirmation test of the previous process and the contents of the confirmation test of the next process, thereby preventing defects that should be detected in the confirmation test from occurring at the customer's site. [Brief description of the drawings]

[0013] [Figure 1] 1 is a diagram illustrating an example of an overall configuration of a monitoring system and a test support system according to a first embodiment. [Diagram 2] FIG. 2 is a diagram illustrating an example of a hardware configuration of a monitoring system and a test support system. [Diagram 3] FIG. 2 is a functional block diagram of the test support system. [Figure 4] FIG. 4 is a diagram illustrating control of the rotation speed of a pump. [Diagram 5] FIG. 13 is a diagram illustrating an example of a test specification for a unit test. [Figure 6] FIG. 1 is a diagram illustrating an example of a test specification for a system test. [Figure 7] 1 is a flowchart of a process executed by the test support system. [Figure 8] FIG. 11 is a diagram illustrating control of the rotation speed of a pump in the second embodiment. [Figure 9] FIG. 13 is a diagram illustrating an example of a test specification for a unit test. [Figure 10] FIG. 1 is a diagram illustrating an example of a test specification for a system test. [Figure 11] 1 is a flowchart of a process executed by the test support system. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0014] Hereinafter, an embodiment will be described with reference to the drawings. In the following description, the same components are denoted by the same reference numerals. Their names and functions are also the same. Therefore, detailed description thereof will not be repeated.

[0015] Embodiment 1 FIG. 1 is a diagram showing an example of the overall configuration of a monitoring system 1 and a test support system 400 according to the first embodiment.

[0016] The monitoring system 1 (also referred to as an “air conditioning instrumentation system”) includes a server device 100, a PLC (Programmable Logic Controller) 200 as a controller, and equipment (PLC) 300.

[0017] The monitoring system 1 is a system that manages various facilities installed in a building. The server device 100 monitors and controls the facility 300 via the PLC 200. A signal output from the facility 300 is acquired by the server device 100 via the PLC 200 and can be displayed (monitored) on a display unit 421 (FIG. 2). In addition, a person 5 (administrator of the monitoring system 1) who performs the confirmation test can transmit a control signal from the server device 100 to the facility 300 via the PLC 200 by operating the input unit 420 (FIG. 2).

[0018] The equipment (PLC) 300 includes air conditioning equipment installed in the building. The equipment (PLC) 300 may also include other equipment such as lighting equipment installed in the building. The PLC 200 relays and transmits input / output signals between the equipment (PLC) 300 and the server device 100, and controls the equipment (PLC) 300.

[0019] The test support system 400 is a system that supports a verification test that verifies the validity of input / output values ​​(input / output signals) input and output in the monitoring system 1.

[0020] The confirmation test includes a "unit test" as a first confirmation test, and a "system test" as a second confirmation test that is performed after the first confirmation test. The unit test is a test that checks input / output data input to and output from some devices included in the monitoring system 1. In the first embodiment, this "some devices" is the PLC 200, but may also be equipment (PLC) 300.

[0021] The system test is a test (combination test) that comprehensively tests the behavior of the entire monitoring system 1. First, a unit test is performed as a confirmation test, and then a system test is performed as a confirmation test for the next process.

[0022] In the first embodiment, a case is described in which a PLC300, which is a device installed to simulate equipment and inputs and outputs signals in place of the equipment, is connected to the monitoring system 1, but confirmation tests may also be performed by connecting actual equipment to the monitoring system 1.

[0023] The verification test can be automatically executed using a test support system 400. The test support system 400 includes a support tool 401, a browser 402, a console 403, an operation flow 414, a test specification 415, an input / output test program 416, and an input / output test code 417.

[0024] The server device 100 can be accessed via a browser 402. The browser 402 is displayed on the screen of a display unit 421 (FIG. 2), and values ​​acquired by the server device 100 (for example, various values ​​acquired from an air conditioning facility) are displayed on the browser 402. In addition, the facility (PLC) 300 can be controlled via the browser 402 by operating the input unit 420 (FIG. 2). For example, the set temperature of the air conditioning facility can be set on the browser 402.

[0025] The support tool 401 is a tool that automatically executes the operation of the browser 402 and automatically executes the confirmation test. The support tool 401 controls the browser 402 and the console 403 according to a procedure described in a preset operation flow 414 to execute the confirmation test.

[0026] A procedure for automatically operating the browser 402 is created using the support tool 401. The created procedure is stored in the operational flow 414.

[0027] The input / output test program 416 generates an input / output test code 417. The support tool 401 starts the input / output test program 416 from the console 403. The contents of the test to be executed in the confirmation test are described in a test specification 415. The input / output test program 416 reads the test specification 415 and generates the input / output test code 417 based on the test specification 415.

[0028] The result of the verification test is determined by executing an input / output test code 417. The support tool 401 starts and executes the input / output test code 417 from a console 403. The console 403 is a console screen that can be started in the test support system 400. By executing commands on the console 403, various software that can be executed on the test support system 400 can be executed.

[0029] The test support system 400 is connected to the PLC 200 and the equipment (PLC) 300 via signal lines so that the input / output signals of the PLC 200 and the equipment (PLC) 300 can be acquired. When the input / output test code 417 is executed, the input / output signals of the PLC 200 and the equipment (PLC) 300 are acquired, and the test results (validation of the input / output data) are judged based on the test contents of the test specifications 415. Specifically, the values ​​described in the test specifications 415 are compared with the values ​​actually acquired to judge whether the values ​​are valid. The results are recorded in the test specifications 415.

[0030] With the above configuration, the test support system 400 automatically executes the confirmation test. Note that the above example is merely an example, and any other means may be used to realize the automatic execution of the confirmation test, the implementer 5 may directly operate the browser 402 to execute the confirmation test, the implementer 5 may visually confirm the results of the confirmation test, or the system may be configured to automatically execute part of the confirmation test.

[0031] The support tool 401 is one of the so-called no-code tools that do not require programming. The test support system 400 may be constructed using any commonly distributed no-code tool, or, without using such a tool, the process of controlling the operation of the browser 402 may be implemented by a program to automatically execute the confirmation test.

[0032] Furthermore, in the first embodiment, the input / output test program 416 is configured to be able to execute an update process for updating (deleting or adding) the test contents of the test specification 415. The update process includes a process for updating the test contents of a unit test and a process for updating the test contents of a system test. The input / output test program 416 can delete or add the test contents of the test specification 415 and update the test contents of the test specification 415 based on the test contents of the test specification 415 and a program executed by a device (e.g., the PLC 200) to be tested in the monitoring system 1 (this will be described in detail later with reference to FIG. 3 and subsequent figures).

[0033] As described above, the update process is implemented as a process executed by the input / output test program 416 running on the server device 100, but the update process may be implemented in any form as long as it is implemented as a process executable on the test support system 400. For example, the update process may be provided as a plug-in for application software running on the server device 100, or as an add-on operable on a browser, or the update process may be implemented to be executed on a server device installed in a remote location other than the server device 100.

[0034] 2 is a diagram showing an example of a hardware configuration of the monitoring system 1 and the test support system 400. As described above, the monitoring system 1 includes the server device 100, the PLC 200, and the PLC 300. The server device 100 and the PLC 300 are connected by a communication line (signal line) via the PLC 200, and are configured to be able to communicate with each other.

[0035] The test support system 400 is also connected to the PLC 300 and the PLC 200 by communication lines (signal lines) and is configured to be able to acquire signals input to and output from the PLC 300 and the PLC 200. The test support system 400 is configured to be able to communicate with the server device 100 via a browser 402.

[0036] The server device 100, which is configured with at least one or more units, includes a processor 111, a memory 112, and a communication unit 113. The processor 111 is, for example, a CPU (Central Processing Unit). The memory 112 is, for example, configured to include a ROM (Read Only Memory), a RAM (Random Access Memory), and a storage device. The storage device is a non-volatile storage device such as an HDD or SSD.

[0037] The processor 111 performs overall control of the entire server device 100. The processor 111 executes programs stored in the memory 112. The ROM stores programs in which the processing procedures of the server device 100 are written. The RAM serves as a working area when the CPU executes a program, and temporarily stores programs and data for executing the programs. The communication unit 113 is an interface for communicating with the PLC 200 and the test support system 400.

[0038] The PLC 200, which is made up of at least one or more units, includes a processor 211, a memory 212, a communication unit 213, and an input / output terminal 214. The processor 211 is, for example, a CPU. The memory 212 is, for example, made up of a ROM, a RAM, and a storage device. The processor 211 controls the entire PLC 200. The processor 211 executes programs stored in the memory 212. The communication unit 213 is an interface for communicating with the server device 100, the PLC 300, and the test support system 400. The communication unit 213 transmits and receives input / output signals to and from the PLC 300 via the input / output terminal 214.

[0039] The PLC 300, which is made up of at least one or more units, includes a processor 311, a memory 312, a communication unit 313, and an input / output terminal 314. The processor 311 is, for example, a CPU. The memory 312 is, for example, made up of a ROM, a RAM, and a storage device. The processor 311 controls the entire PLC 300. The processor 311 executes a program stored in the memory 312. The communication unit 313 is an interface for communicating with the PLC 200 and the test support system 400. The communication unit 313 transmits and receives input / output signals to and from the PLC 200 via the input / output terminal 314. The input / output terminal 214 of the PLC 200 and the input / output terminal 314 of the PLC 300 are connected by a plurality of signal lines. Electrical signals (input / output signals) are input and output between the PLC 200 and the PLC 300 via a plurality of signal lines connected between the input / output terminal 214 and the input / output terminal 314.

[0040] The test support system 400 includes a processor 411, a memory 412, a communication unit 413, an input unit 420, and a display unit 421. The processor 411 is, for example, a CPU. The memory 412 is, for example, configured to include a ROM, a RAM, and a storage device. The processor 411 comprehensively controls the entire test support system 400. The processor 411 executes a program stored in the memory 412. The communication unit 413 is an interface for communicating with the server device 100, the PLC 200, and the PLC 300.

[0041] The display unit 421 is a display that displays various information images. The input unit 420 accepts input from the implementer 5. The input unit 420 is, for example, a keyboard, a mouse, or a touch panel.

[0042] 1, the support tool 401, the browser 402, the console 403, the input / output test program 416, and the input / output test code 417 are stored in a memory 412 and executed by a processor 411. An operation flow 414 and a test specification 415 are stored in the memory 412. The test support system 400 may be a personal computer or the like equipped with a display unit 421 and an input unit 420.

[0043] 3 is a functional block diagram of a test support system 400. The test support system 400 includes a test specification 415, a test data generation unit 432, test data 433, a test data execution unit 434, a test data tracing unit 435, a tracing result 436, a test result output unit 437, a test result 438, a test attribute 440, and a test data complementation unit 441.

[0044] The above function is executed by the input / output test program 416, and updates the test contents of the test specification 415 based on the test contents of the test specification 415 and the program executed by the device (such as PLC 200) to be tested in the monitoring system 1.

[0045] The test specification 415, the test data 433, the tracing result 436, the test result 438, and the test attributes 440 are stored in the memory 412 of the test support system 400. The test data generating unit 432, the test data executing unit 434, the test data tracing unit 435, the test result output unit 437, and the test data complementing unit 441 are executed by the processor 411 of the test support system 400.

[0046] The test data generation unit 432 reads the test specifications 415 for the unit test and generates test data 433. The test data 433 is data obtained by extracting input / output data to be input to and output from the monitoring system 1 based on the test specifications 415.

[0047] The test data execution unit 434 inputs the test data 433 to the monitoring system 1 and runs a program executed in the monitoring system 1. The monitoring system 1 executes internal processing (processing executed by a program) according to a given input value, and outputs an output value as a result.

[0048] The test data tracing unit 435 acquires the source code of the program executed in the monitoring system 1. When the test data 433 is input to the monitoring system 1 and the program is operated, the test data tracing unit 435 identifies the process executed by the program executed in the monitoring system 1 and stores it as a tracing result 436.

[0049] For example, assume that the target for inputting and outputting data is the PLC 200. In this case, assume that when input data X is given to the PLC 200, output data Y is output. The test data tracing unit 435 analyzes the source code from the set of input data X and output data Y to identify which internal process has been executed in the program running on the PLC 200.

[0050] For example, in a program running on the PLC 200, when input data X is given, processing of function A is executed with input data X given as an argument, and output data Y is output as a return value of function A, the test data tracing unit 435 identifies "function A" as the internal processing to be executed. In cases where processing A1 in function A is executed when input data is X1, and processing A2 in function A is executed when input data is X2, "processing A1 of function A" and "processing A2 of function A" may be identified as the internal processing, respectively.

[0051] Such processing for analyzing the source code by the test data executing unit 434 and the test data tracing unit 435 may be realized using a known technique such as that shown in Japanese Patent Application Laid-Open No. 2009-217664.

[0052] The process of identifying which internal process has been executed in a program running on PLC 200 is not limited to the above-mentioned process of identifying by analyzing the source code, but may be identified from test specifications 415. For example, if test items, program functions when these are executed, input data (arguments) to be input to the functions, and output data (return values) to be output from the functions are described in test specifications 415, the internal process to be executed may be identified based on these descriptions.

[0053] The test data complementing unit 441 determines test attributes based on the test data 433 and the tracing result 436, and stores them as test attributes 440. The test data complementing unit 441 executes an update process to update (delete or add) the contents of multiple tests. In the update process, the test data complementing unit 441 targets test data of unit tests with overlapping internal processes as targets for deletion. Based on the test data 433 and the test attributes, the test data complementing unit 441 determines whether or not to exclude tests targeted for deletion from the targets for deletion. In the update process, the test data complementing unit 441 finally deletes the test data of the unit test targeted for deletion. Furthermore, in the update process, the test data complementing unit 441 adds test items missing from the system test to the test specification for the system test based on the difference between the contents of the unit test and the contents of the system test.

[0054] The test result output unit 437 saves the test results of the test data of the unit test updated in the update process as test results 438 , and also reflects the test results of the unit test in the test specification 415 .

[0055] The update process executed by the test data complementing unit 441 will now be described in detail. 4 is a diagram showing the control of the pump rotation speed. For example, assume that an air conditioning system is installed in a building, and the PLC 300 is installed as a device that simulates the air conditioning system. The air conditioning system is a device that lowers or raises the temperature of the outside air taken in from outside by heat exchange with hot or cold water, and supplies the air to the room.

[0056] Here, the temperature of the outside air taken in from outside is measured as the "outdoor temperature." The indoor temperature set in the monitoring system 1 is acquired as the "indoor temperature." The temperature of the outside air that is heat exchanged and supplied to the room is measured as the "outlet temperature." PLC 200 controls the pump rotation speed by issuing a command to PLC 300 based on the outdoor air temperature, the indoor temperature, and the outlet temperature.

[0057] FIG. 4 shows the pump speed [%] (vertical axis) controlled relative to the outlet temperature [°C] (horizontal axis) when the set temperature is "23°C" and the outside air temperature is "10°C." When the pump is rotating at the maximum speed, the pump speed is 100%. When the pump is rotating at K% of the maximum speed, the pump speed is K%. The minimum pump speed is 50% of the maximum speed.

[0058] In this example, when the outlet temperature is "t1", the pump speed is controlled to "50% (minimum speed)". After that, as the pump speed is increased, it is controlled to "65%" at an outlet temperature of "10°C" (Test 1 in FIG. 5), to "75%" at an outlet temperature of "20°C" (Test 2 in FIG. 5), to "85%" at an outlet temperature of "25°C" (Test 3 in FIG. 5), and to "100%" at an outlet temperature of "t2°C".

[0059] 5 is a diagram showing an example of a test specification 91 (corresponding to the test specification 415 in FIG. 3) for a unit test. The test specification 91 describes the test contents (tests 1 to 3, etc.) of the unit test as a confirmation test.

[0060] Test 1 is a test to check whether a pump speed of "65%" is output as an output value from the PLC 200 when an outlet temperature of "10°C", a set temperature of "23°C", and an outside air temperature of "10°C" are given as input values ​​to the PLC 200. As shown in "Test 1" in Fig. 4, the pump speed gradually increases, and it is expected that "65%" will be detected as the pump speed when the outlet temperature reaches "10°C".

[0061] Test 2 is a test to check whether a pump speed of "75%" is output as an output value from the PLC 200 when an outlet temperature of "20°C", a set temperature of "23°C", and an outside air temperature of "10°C" are given as input values ​​to the PLC 200. As shown in "Test 2" in Figure 4, the pump speed gradually increases, and it is expected that "75%" will be detected as the pump speed when the outlet temperature reaches "20°C".

[0062] Test 3 is a test to check whether a pump speed of "85%" is output as an output value from the PLC 200 when an outlet temperature of "25°C", a set temperature of "23°C", and an outside air temperature of "10°C" are given as input values ​​to the PLC 200. As shown in "Test 3" in Figure 4, the pump speed gradually increases, and it is expected that "85%" will be detected as the pump speed when the outlet temperature reaches "25°C".

[0063] The internal processes of tests 1 to 3 are all the same because the "processing of increasing the pump rotation speed" is executed as an internal process of the PLC 200. In such a case, as described with reference to FIG. 3, the test data complementing unit 441 selects tests 2 and 3 as deletion targets.

[0064] On the other hand, the input and output values, that is, the outlet temperature, the set temperature, the outside air temperature, and the pump speed, are continuous values ​​(also called "continuous analog values") that can change continuously. In tests 1 to 3, not only is it possible to confirm which pump speed is output when the outlet temperature, the set temperature, and the outside air temperature are given, but it is also possible to confirm whether the pump speed is increasing in a state in which an increase in the pump speed is expected. In such a case, the test data complementing unit 441 sets the test attribute of tests 1 to 3 to "continuous analog value" and excludes tests 1 to 3 whose test attribute is set to "continuous analog value" from the deletion targets.

[0065] As a result, tests 2 and 3 would have been deleted from the unit test in the conventional method, but in the first embodiment, they are not deleted and all tests 1 to 3 are executed. Note that tests 2 and 3 may be deleted from the unit test and executed in the system test.

[0066] After the unit test is performed, a system test is performed. Fig. 6 is a diagram showing an example of a test specification 93 for a system test. The test specification 93 initially describes tests Y1 to Y3. Tests Y4 and Y5 are added by the process shown in the flowchart of Fig. 7, which will be described later.

[0067] Test Y1 is a test to check the minimum pump speed. The minimum pump speed is 50%. Test Y2 is a test to check the maximum pump speed. The maximum pump speed is 100%. Test Y3 is a test to check a pump speed other than the maximum and minimum. In this case, a pump speed that is 75% is checked.

[0068] The following description will be given with reference to a flowchart. Fig. 7 is a flowchart of the process executed by the test support system 400. This process is an update process executed by the test data complementing unit 441, etc. Hereinafter, "step" may also be simply referred to as "S".

[0069] S101 to S105 are processes related to the unit test specification 91. When this process starts, the processor 411 acquires a plurality of unit tests and the corresponding tracing results from the test data 433 and the tracing result 436 in S101.

[0070] In S102, the processor 411 sets, based on the tracing result, a test among the multiple tests whose internal processing matches as a test to be deleted. In the example shown in FIG. 5, the multiple tests include test 1 as a first test and tests 2 and 3 as second tests. Tests 2 and 3 have internal processing matching with test 1, and are set as tests to be deleted. Here, if test 1 and test 2 are tests performed consecutively, test 2 may be set as a test to be deleted, and if test 2 and test 3 are tests performed consecutively, test 3 may be set as a test to be deleted.

[0071] The processor 411 determines the test attribute based on the type of input value and the type of output value for each of the multiple tests. Specifically, in S103, the processor 411 determines that the test attribute is a continuous value (continuous analog value) when the input value and the output value are continuously variable for each of the multiple tests.

[0072] A continuously variable value is a value with a different nature from a value that is set to one of two values, such as 0 or 1, ON or OFF. Also, in cases where the input value is ON or OFF and the output value is a continuously variable value, the test attribute may be determined to be a continuous value (continuous analog value).

[0073] The processor 411 excludes the second test (test 2, 3) from the deletion target according to the test attribute of the first test (test 1) and the test attribute of the second test (test 2). Specifically, the processor 411 excludes from the deletion target those tests whose test attribute is a continuous analog value among the tests set as deletion targets in S104. As a result, even if the processor 411 determines that the internal processing of the first test (test 1) and the second test (test 2, 3) is the same, when it is determined that both the test attribute of the first test (test 1) and the test attribute of the second test (test 2, 3) are continuous values, the second test (test 2, 3) is excluded from the deletion target.

[0074] In S105, the processor 411 deletes the test set as the deletion target, updates the test specification 91 of the unit test (test specification 415 in FIG. 3), and outputs the test result 438.

[0075] S106 is a process related to the test specification 93 of the system test. In S106, the processor 411 adds a test to the test specification of the system test based on the difference between the contents of the unit test and the contents of the system test. Adding a test to the system test is realized, for example, by the following method.

[0076] Test Y1 of the system test illustrated in FIG. 6 is a test to check the pump speed at "50%", test Y2 is a test to check the pump speed at "100%, and test Y3 is a test to check the pump speed at "75%". In contrast, test 1 of the unit test illustrated in FIG. 5 is a test to check the pump speed at "65%," test 2 is a test to check the pump speed at "75%, and test 3 is a test to check the pump speed at "85%". Among these, the pump speed (75%) of test 2 and test Y3 are the same. On the other hand, the output values ​​of tests 1 and 3 of the unit test do not match the output values ​​of any of the system tests. For this reason, for example, test Y4 to check the output value of test 1 (pump speed "65%) and test Y5 to check the output value of test 3 (pump speed "85%") are added to the system test. In this case, after test Y3 which checks for a pump speed of "75%," a test Y4 which changes the output value of test 1 (pump speed "65%) (i.e., a test which checks for a decrease in the pump speed) may be added, and further a test Y5 which changes the output value of test 3 (pump speed "85%) (i.e., a test which checks for an increase in the pump speed) may be added. A more detailed method of adding tests to the system tests will be described in embodiment 2 using Figs. 8 to 11.

[0077] As described above, the test support system 400 is a system that supports a confirmation test that confirms the validity of input / output values ​​input and output in the monitoring system 1 that includes the equipment (PLC) 300 and the server device 100 that monitors the equipment via the PLC 200 as a controller. The test support system 400 includes a memory 412 and a processor 411. The memory 412 stores the contents of a plurality of tests to be performed in the confirmation test. The processor 411 executes an update process that updates the contents of the plurality of tests. The monitoring system 1 (PLC 200) executes internal processing according to a given input value, and outputs an output value as a result. The confirmation test includes a unit test as a first confirmation test, and a system test as a second confirmation test that is performed after the unit test. In the update process, the processor 411 adds a test to the system test based on the difference between the contents of the unit test and the contents of the system test.

[0078] If the test items for the system test are not sufficiently extracted and the tests that should be performed are not performed, defects will occur in the product that is in operation at the customer's site after the product is delivered to the customer. This can occur because the testers for the unit test and the system test are different and the necessary information is not shared between them. For example, even if the test items for the unit test are sufficiently extracted, the contents of these test items may not be sufficiently reflected in the system test, and test items that should be performed in the system test may be missing. With the above configuration, tests can be added to the system test based on a comparison with the contents of the unit test, so that defects that should be detected in the system test can be prevented from occurring at the customer's site.

[0079] In the update process, the processor 411 deletes the test set as the deletion target from the unit test. When the input value and the output value are values ​​that can be changed continuously in each of the multiple tests, the processor 411 determines that the test attribute is a continuous value (continuous analog value). The multiple tests in the unit test include a first test (test 1) and a second test (tests 2, 3). When the processor 411 determines that the internal processing of the first test (test 1) and the second test (tests 2, 3) is the same, the processor 411 sets the second test (tests 2, 3) as the deletion target. Even when the processor 411 determines that the internal processing of the first test (test 1) and the second test (tests 2, 3) is the same, the processor 411 excludes the second test (test 2, 3) from the deletion target when it is determined that both the test attribute of the first test (test 1) and the test attribute of the second test (test 2, 3) are the continuous value (continuous analog value).

[0080] In unit testing, by deleting duplicated tests (tests 2 and 3 in the above example) in order to reduce the number of tests, defects that should have been detected in the unit testing may not have been detected in the unit testing, but may have been detected in the next process, the system testing. In such cases, after fixing the software defects, it is necessary to perform the unit testing and the system testing again, and this double work reduces the efficiency of the testing. As described above, when the internal processing is consistent and the input and output values ​​are continuously variable, by excluding them from the deletion target in the update process, it is possible to perform a test in the unit testing to check the change state of the output value (continuity of the output value). This makes it possible to prevent defects that should have been detected in the confirmation test of the previous process (unit testing) from being detected in the confirmation test of the next process (system testing). Furthermore, as described above, since test items that are missing in the system testing can be added based on the unit testing, not only can defects that should have been detected in the unit testing be prevented from being detected in the system testing, but also defects that should have been detected in the system testing can be prevented from occurring at the customer's site.

[0081] The update process in the unit test may be executed by the test support system 400 as described above, or may be executed in whole or in part by a human. For example, the implementer 5 may visually check the test specification 91 and decide whether to exclude the test from the deletion target. Furthermore, the test that is the deletion target in the unit test may be executed in the system test, not in the unit test. Furthermore, the test that is the deletion target may be executed in both the unit test and the system test. Furthermore, in the first embodiment, the test is added or deleted from a plurality of tests recorded in the test specification 415 prepared in advance, but the test support system 400 may generate all the test items and record them in the test specification 415.

[0082] Embodiment 2 Next, the test support system 400 in the second embodiment will be described. In the first embodiment, the processor 411 is configured to add a test to the system test based on the difference between the contents of the unit test and the contents of the system test in the update process. Also, the processor 411 is configured to exclude from deletion targets in the update process when the internal processing is consistent and the input / output values ​​are continuously variable values ​​in the unit test.

[0083] In the second embodiment, a test is added to the system test by the method described below. Note that in the second embodiment, only the parts that are different from the first embodiment will be described, and the parts that are common to the first embodiment will not be described.

[0084] Fig. 8 is a diagram showing control of the rotation speed of a pump in the second embodiment. The content of Fig. 8 is the same as that described in Fig. 4. Fig. 9 is a diagram showing an example of a test specification 92 for a unit test. Fig. 10 is a diagram showing an example of a test specification 93 for a system test. The content of Fig. 10 is the same as that described in Fig. 6.

[0085] The content of the unit test shown in Fig. 9 is substantially the same as the content of the unit test shown in Fig. 5. Test 1 in Fig. 5 corresponds to tests X1 to X3 in Fig. 9, test 2 in Fig. 5 corresponds to tests X4 to X6 in Fig. 9, and test 3 in Fig. 5 corresponds to tests X7 to X9 in Fig. 9.

[0086] For example, in test X1, a pump speed of "65%" is output when the outlet temperature is "10°C", in test X2, a pump speed of "65%" is output when the set temperature is "23°C", and in test X3, a pump speed of "65%" is output when the outside air temperature is "10°C". When the outlet temperature is "10°C" and the set temperature is "23°C", as shown in FIG. 8, the outlet temperature and the pump speed continuously increase with time, so that a pump speed of "75%" is measured for an outlet temperature of "20°C" and a pump speed of "85%" is measured for an outlet temperature of "25°C" as in FIG. 5. As a result, tests X4 to X9 can be performed.

[0087] In the test specification 92 for the unit test, the test attribute for tests X1 to X9 is set to be a continuous analog value, and a "circle" is added to indicate that the results of tests X1 to X9 are valid.

[0088] Test specifications 93 for a system test to be performed after the unit test is performed is as shown in Fig. 10. Tests Y1 to Y3 are initially described in test specifications 93. Tests Y4 and Y5 are added by the process shown in the flowchart of Fig. 11, which will be described later.

[0089] Test Y1 is a test to check the minimum pump speed. As shown in FIG. 8, the minimum pump speed is 50%. Test Y2 is a test to check the maximum pump speed. As shown in FIG. 8, the maximum pump speed is 100%. Test Y3 is a test to check a pump speed other than the maximum and minimum. As shown in FIG. 8, a pump speed of 75% is checked here.

[0090] 11 is a flowchart of the process executed by the test support system 400. In this process, a process of adding a test to the system test is executed based on the difference between the contents of the unit test and the contents of the system test. This process may be executed by the input / output test program 416 after the test result output unit 437 finishes processing, for example.

[0091] When this process starts, in S201, the processor 411 acquires the contents of multiple unit tests recorded in the test specification 92 for the unit test and the contents of multiple system tests recorded in the test specification 93 for the system test.

[0092] In S202, the processor 411 extracts tests whose test attribute is a continuous value (continuous analog value) and whose internal processing is the same from among the multiple tests in the unit test. For example, in the example of Fig. 9, tests such as X3, X6, and X9 whose test attribute is a continuous analog value and whose internal processing is the same are extracted.

[0093] In S203, the processor 411 classifies the extracted tests into tests whose output values ​​match the output values ​​of the system tests and tests whose output values ​​do not match the output values ​​of the system tests. Test Y1 of the system tests is a test to check the pump speed at "50%", test Y2 is a test to check the pump speed at "100%," and test Y3 is a test to check the pump speed at "75%". Test X3 of the unit tests is a test to check the pump speed at "65%," test X6 is a test to check the pump speed at "75%," and test X9 is a test to check the pump speed at "85%". Of these, test X6 matches test Y3 in pump speed (75%), but tests X3 and X9 do not match the output values ​​of any of the system tests.

[0094] In S204, the processor 411 adds to the system tests a test for changing the output value from the matched output value to the mismatched output value, and a test for further changing the output value to another mismatched output value. In the above example, after the test Y3 for checking that the pump speed is "75%" whose output matches the test X6, a test Y4 for changing the output value to the output value of the test X3 (pump speed "65%) (i.e., a test for checking a decrease in the pump speed) is added, and further a test Y5 for changing the output value to the output value of the test X9 (pump speed "85%) (i.e., a test for checking an increase in the pump speed) is added.

[0095] As described above, if it is determined that the internal processing of the first test (Test X6) and the second test (Test X3) in the unit test is consistent, and if it is determined that the test attributes of the first test (Test X6) and the test attributes of the second test (Test X3) are both continuous analog values, and if the system test does not include a test to check the output value of the second test (Test X3) (pump rotation speed "65%)), an additional test Y4 to check the output value of the second test (Test X3) is added to the system test in the update process.

[0096] In particular, if the system test includes a test to confirm the output value of the first test (test X6) (pump speed "75%), an additional test Y4 may be added to confirm that the output value of the first test (test X6) (pump speed "75%) changes to the output value of the second test (test X3) (pump speed "65%) (the pump speed decreases).

[0097] In this way, the results of the unit test and the system test can be compared, and the test contents of the system test can be supplemented from the test contents that have been performed in the unit test but not in the system test. This makes it possible to prevent defects that should be detected in the system test from occurring at the customer's site.

[0098] The embodiments disclosed herein are also intended to be combined as appropriate within the scope of technical inconsistency. The embodiments disclosed herein should be considered to be illustrative and not restrictive in all respects. The technical scope of the present disclosure is defined by the claims, not the description of the above embodiments, and is intended to include all modifications within the scope and meaning equivalent to the claims. [Explanation of symbols]

[0099] 1 monitoring system, 5 implementer, 91-93 test specification, 100 server device, 111, 211, 311, 411 processor, 112, 212, 312, 412 memory, 113, 213, 313, 413 communication unit, 214, 314 input / output terminal, 420 input unit, 421 display unit, 200 PLC, 300 equipment (PLC), 400 test support system, 401 support tool, 402 browser, 403 console, 414 operation flow, 415 test specification, 416 input / output test program, 417 input / output test test code, 432 test data generation unit, 433 test data, 434 test data execution unit, 435 test data tracing unit, 436 tracing result, 437 test result output unit, 438 test result, 440 Test Attributes, 441 Test Data Complementary Section.

Claims

1. A test support system that supports a verification test that verifies the validity of input / output values ​​input and output in a monitoring system including a facility and a server device that monitors the facility via a controller, A memory that stores the contents of a plurality of tests to be performed in the confirmation test; A processor for executing an update process for updating the contents of the plurality of tests, the monitoring system executes internal processing in response to a given input value and outputs an output value as a result of the processing; The verification test includes a first verification test and a second verification test performed after the first verification test, The processor, In the update process, a test is added to the second confirmation test based on a difference between the content of the first confirmation test and the content of the second confirmation test; In the update process, a test set as a deletion target is deleted from the first confirmation test; determining that the test attribute is continuous if, for each of the plurality of tests, the input and output values ​​are continuously variable values; The plurality of tests in the first confirmation test include a first test and a second test, The processor, When it is determined that the internal processing of the first test and the internal processing of the second test are identical, the second test is set as the deletion target; A test support system that excludes the second test from the deletion targets even if it is determined that the internal processing of the first test and the second test is the same, when it is determined that the test attribute of the first test and the test attribute of the second test are both continuous values.

2. 2. The test support system of claim 1, wherein when it is determined that the internal processing of the first test and the second test is consistent, and when it is determined that the test attribute of the first test and the test attribute of the second test are both continuous values, and when the second confirmation test does not include a test to confirm the output value of the second test, in the update process, the processor adds an additional test to the second confirmation test to confirm the output value of the second test.

3. 3. The test support system of claim 2, wherein when the second confirmation test includes a test to confirm an output value of the first test, the additional test is a test to confirm a change from an output value of the first test to an output value of the second test.

4. A control method for a test support system that supports a verification test for verifying validity of input / output values ​​input and output in a monitoring system including a facility and a server device that monitors the facility via a controller, comprising: storing the contents of a plurality of tests to be performed in the confirmation test; updating content of the plurality of tests; the monitoring system executes internal processing in response to a given input value and outputs an output value as a result of the processing; The verification test includes a first verification test and a second verification test performed after the first verification test, The updating step includes: adding a test to the second confirmation test based on a difference between a content of the first confirmation test and a content of the second confirmation test; deleting a test set as a deletion target from the first verification test; determining that the test attribute is continuous if the input and output values ​​for each of the plurality of tests are continuously variable; The plurality of tests in the first confirmation test include a first test and a second test, The updating step includes: setting the second test as the deletion target when it is determined that the internal processing of the first test and the internal processing of the second test match; The control method further comprises a step of excluding the second test from the deletion targets when it is determined that the test attribute of the first test and the test attribute of the second test are both continuous values, even if it is determined that the internal processing of the first test and the second test are consistent.

Citation Information

Patent Citations

  • Method for generating test specification