One-time hole-forming PVC micro-pipe jacking apparatus and pipe jacking process therefor

Through the primary hole PVC micro-pipe hoisting device, the hydraulic unit and the force transmission screw share the pinch force, the applicability of traditional micro-pipe hoisting technology to plastic pipes is solved, and the efficient laying and stability of PVC pipes is achieved, which expands the Technical application scope.

WO2024234478A1PCT designated stage expired Publication Date: 2024-11-21HUBEI KINMA PLASTIC IND

Patent Information

Application Number
PCT/CN2023/109847
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-18
Filing Date
2023-07-28
Publication Date
2024-11-21

AI Technical Summary

Technical Problem

Traditional micro-pipe tipping technology is cumbersome to operate and is only suitable for concrete, steel or cast iron pipes, but not for plastic pipes. Moreover, plastic pipes are prone to damage during the pipe tipping process, limiting the scope of application of the technology.

Method used

A single-hole PVC micro-pipe hoisting device was designed to share the pinch force to the bore machine through the hydraulic unit and the force transmission screw, reducing the oncoming resistance of the PVC pipe, and using a high-pressure pump and a sedimentation tank to treat mud to realize the PVC pipe. Lay out holes at one time.

Benefits of technology

It realizes efficient laying of plastic pipes, omits multiple hole expansion steps, improves the maturity of technology and application range, and ensures the stability and safety of PVC pipes during the ejection process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023109847_21112024_PF_FP_ABST
    Figure CN2023109847_21112024_PF_FP_ABST
Patent Text Reader

Abstract

Disclosed is a one-time hole-forming PVC micro-pipe jacking apparatus and a pipe jacking process therefor. The apparatus comprises a soil layer, a receiving steel well and a starting steel well are vertically provided downward on two sides of the soil layer, and a top portion of the soil layer is separately provided with a sedimentation tank, a high-pressure pump machine, and a hydraulic unit. An operating platform, a pipe push-pull machine, and a rear seat for supporting the pipe push-pull machine are separately disposed in the starting steel well, and the hydraulic unit is connected to the pipe push-pull machine by means of a hydraulic pipe. The present invention relates to the technical field of municipal pipeline trenchless construction. The one-time hole-forming PVC micro-pipe jacking apparatus and pipe jacking process therefor are more mature technologies by virtue of applying micro-pipe jacking technology to the laying of plastic pipelines, and compared with conventional plastic pipeline laying methods such as guided drilling and directional drilling, the step of reaming multiple times is omitted, and the advantage of one-time hole forming is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

One-time hole forming PVC micro pipe jacking device and pipe jacking process Technical Field

[0001] The invention relates to the technical field of trenchless construction of municipal pipelines, in particular to a one-time hole-forming PVC micro-pipe jacking device and a pipe jacking process thereof. Background Art

[0002] Micro pipe jacking is a trenchless technology suitable for laying small-diameter underground municipal pipelines. Compared with the open-cut method commonly used in traditional municipal pipeline projects, it has the advantages of low noise and vibration, no disturbance to ground traffic, and less danger to nearby pipelines and buildings.

[0003] Traditional pipe jacking is typically only used for laying concrete, steel, or cast iron pipes. Micro-pipe jacking requires a jacking device to sequentially push a guide drill pipe, a mud pipe, and a mud transmission screw into the receiving well. The jacking machine then pushes the mud pipe into the soil. The rotation of the cutterhead drives the mud transmission screw, ultimately pushing multiple prefabricated pipe sections into the soil. This process is a secondary and tedious one.

[0004] It can be seen that the traditional pipe jacking technology has at least the following shortcomings. First, the opening of the pipe trench is a secondary method, which is cumbersome to operate. Second, it is only used for the laying of concrete, steel or cast iron pipes, and this technology cannot be applied to the laying of plastic pipes. The reason is that the material strength of the plastic pipe itself is relatively weak, and it is difficult to withstand the jacking pressure during the jacking process and is easily damaged, thus reducing the application scope of the pipe jacking technology.

[0005] Summary of the Invention

[0006] (1) Technical problems solved

[0007] In view of the deficiencies in the prior art, the present invention provides a one-time hole-forming PVC micro-pipe jacking device and a pipe jacking process thereof, which solves the problems of the prior micro-pipe jacking device being cumbersome to operate and having a small application range.

[0008] (2) Technical solution

[0009] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a one-time hole-forming PVC micro-pipe jacking device and its jacking process, comprising a soil layer, with a receiving steel well and a starting steel well vertically arranged downward on both sides of the soil layer, and a sedimentation tank, a high-pressure pump and a hydraulic unit respectively arranged on the top of the soil layer.

[0010] An operating table, a pipe push-pull machine and a rear seat for supporting the pipe push-pull machine are respectively provided in the starting steel shaft. The hydraulic unit is connected to the pipe push-pull machine through a hydraulic pipeline.

[0011] The rotating end of the push-pull pipe machine is rotatably connected to a power transmission screw, the outer cover of the power transmission screw is provided with a top cylinder, the outer cover of the top cylinder is provided with a PVC pipe, and one end of the PVC pipe abuts against the end face of the push-pull pipe machine.

[0012] A PVC micro-tube jacking mechanism is installed at one end of the force transmission screw away from the push-pull pipe machine. The PVC micro-tube jacking mechanism is fixed to the PVC pipe through a cylindrical connecting joint.

[0013] As a further preferred embodiment, the PVC micro-tube jacking mechanism includes a PVC micro-tube jacking body and a micro-tube jacking head. The micro-tube jacking head is coaxially fixed with the force transmission screw, and a cutter disc is provided at the axis of the micro-tube jacking head.

[0014] As a further preference, at least two groups of high-pressure pumps are provided, one of which is connected to the sedimentation tank. This group of high-pressure pumps can pump out the mud inside the top cylinder, and the other group of high-pressure pumps is used to inject water into the power transmission screw.

[0015] As a further preferred embodiment, the interior of the force transmission screw is a hollow structure, and the rotating end of the push-pull pipe machine is provided with a water injection hole that is connected to the interior of the force transmission screw.

[0016] As a further preference, a laser theodolite is provided on the top of the push-pull tube machine.

[0017] A pipe jacking process of a one-time hole-forming PVC micro pipe jacking device is characterized in that the specific process flow is as follows:

[0018] Construction of micro steel caisson:

[0019] First, excavate the starting and receiving steel shafts, and prefabricate circular starting and receiving openings at multiple locations. The actual opening position is determined according to the jacking pipe elevation, and is sealed with double-layer flanges and rubber rings, as well as an outer cover. After sinking to the preset height, remove the outer cover of the steel shaft at the required height. Keep the outer cover sealed in the steel shaft opening area that is not needed in this project. The excavation depth of the bottom of the receiving steel shaft should be flush with the lowest point of the pipeline height. Space for equipment assembly should be reserved in the starting steel shaft soil, and the bottom soil of the shaft should be leveled.

[0020] Equipment assembly:

[0021] After arranging the sedimentation tank and high-pressure pump, the push-pull pipe machine is placed on the receiving steel well, and the level and height are adjusted to the preset position. The operating table is placed on the push-pull pipe machine, and the push-pull pipe machine is placed in front of the rear seat. The top cylinder is connected to the push-pull pipe machine, and the laser theodolite is placed. The communication line, hydraulic oil circuit unit, and water inlet circuit are connected, and the drill bit is installed. The PVC pipe, top cylinder, and force transmission screw are connected to the rear of the tunnel boring machine. Among them, the top cylinder is connected to the rear of the tunnel boring machine, and the force transmission screw is located between the upper and lower top cylinders. The PVC pipe to be laid is located outside the top cylinder.

[0022] Pipe jacking starts:

[0023] A push-pull pipe machine is used to push the tunnel boring machine and the PVC pipe connected to it, the jacking cylinder, and the force transmission screw into the starting hole and into the soil. The other end of the force transmission screw is connected to the rotating device in the push-pull pipe machine. During the subsequent jacking process, the jacking force is divided into two parts: the head-on resistance of the tunnel boring machine and the side friction resistance of the pipe. The force transmission screw can transfer part of the jacking force to the tunnel boring machine to balance the head-on resistance. The push-pull pipe machine applies part of the jacking force to the pipe cross section.

[0024] Pipe section advancement:

[0025] The water inlet circuit in the force transmission screw is opened, and the force transmission screw rotation oil circuit is opened. After the water is stably discharged from the force transmission screw, the propulsion oil circuit is opened and the whole pipe is pushed forward. As the jacking pipe is pushed forward, the subsequent PVC pipes, jacking cylinders, and force transmission screws are also lengthened to ensure the continuous jacking of the jacking pipe. The cross section of the pipe section fits the push-pull pipe machine and can withstand the jacking force.

[0026] Complete propulsion, recover equipment:

[0027] After the tunneling equipment enters the receiving steel shaft, the PVC pipe is laid through one-time drilling. Then the tunneling equipment is recovered, the force transmission screw is retracted and pulled out, and finally the steel micro caisson is added with an outer cover and pulled out as a whole and recovered. (3) Beneficial effects

[0028] The present invention provides a one-time hole-forming PVC micro-pipe jacking device and its jacking process. It has the following beneficial effects:

[0029] This one-time hole-forming PVC micro-pipe jacking device and its jacking process, by applying micro-pipe jacking technology to the laying of plastic pipes, is more mature. Compared with traditional plastic pipe laying methods such as pilot drilling and directional drilling, it omits the multiple hole expansion steps and has the advantage of one-time hole formation. Secondly, since the mechanical properties of plastic pipes are lower than those of concrete, steel, or cast iron pipes, to solve this problem, a force transmission screw is directly connected to the jacking mechanism. The force transmission screw transmits part of the jacking force to balance the head-on resistance in front of the tunnel boring machine and share the force on the PVC pipe. The PVC pipe wall only bears frictional resistance, preventing it from becoming unstable or damaged during the jacking process, thereby realizing the grafting of pipe jacking technology into the laying application of plastic pipes. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] FIG1 is a schematic structural diagram of the present invention;

[0031] FIG2 is an enlarged view of a local structure of the present invention;

[0032] FIG3 is a side view of a receiving steel well of the present invention;

[0033] FIG4 is a side view of a local structure of the present invention.

[0034] In the figure: 1. Soil layer; 2. Sedimentation tank; 3. High-pressure pump; 4. Operating table; 5. Starting steel well; 6. Laser theodolite; 7. Hydraulic unit; 8. Receiving steel well; 9. PVC micro-pipe jacking mechanism; 10. Push-pull pipe machine; 11. Back seat; 12. Cutter head; 13. PVC micro-pipe jacking machine body; 14. Connecting joint; 15. PVC pipe; 16. Jacking cylinder; 17. Power transmission screw; 18. Micro-pipe jacking machine head; 19. Flange and rubber ring; 20. Outer cover; 21. Hole opening. DETAILED DESCRIPTION

[0035] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.

[0036] As shown in Figures 1 and 3, the present invention provides a technical solution: a one-time hole-forming PVC micro-pipe jacking device and its jacking process, including a soil layer 1, with a receiving steel well 8 and a starting steel well 5 vertically arranged downward on both sides of the soil layer 1, and a sedimentation tank 2, a high-pressure pump 3 and a hydraulic unit 7 (providing hydraulic power) are respectively arranged on the top of the soil layer 1.

[0037] As shown in Figure 1, there are at least two groups of high-pressure pumps 3, one of which is connected to the sedimentation tank 2. This group of high-pressure pumps 3 can extract the mud inside the top cylinder 16, and the other group of high-pressure pumps 3 is used to inject water into the power transmission screw 17.

[0038] As shown in FIG1 , an operating platform 4 , a pipe push-pull machine 10 and a rear seat 11 for supporting the pipe push-pull machine 10 are respectively provided in the starting steel shaft 5 , and the hydraulic unit 7 is connected to the pipe push-pull machine 10 through a hydraulic pipeline.

[0039] As shown in Figure 2, the rotating end of the push-pull pipe machine 10 is rotatably connected to a force transmission screw 17. The interior of the force transmission screw 17 is a hollow structure, and the rotating end of the push-pull pipe machine 10 is provided with a water injection hole that is connected to the interior of the force transmission screw 17. The external cover of the force transmission screw 17 is provided with a top cylinder 16, and the outer cover of the top cylinder 16 is provided with a PVC pipe 15. One end of the PVC pipe 15 abuts against the end face of the push-pull pipe machine 10.

[0040] As shown in FIG1 , a laser theodolite 6 is provided on the top of the pipe pushing and pulling machine 10 , and the laser theodolite 6 can be used to timely detect whether the position of the hole is offset.

[0041] As shown in Figure 2, a PVC micro-tube jacking mechanism 9 is installed at the end of the force transmission screw 17 away from the push-pull pipe machine 10. The PVC micro-tube jacking mechanism 9 includes a PVC micro-tube jacking body 13 and a micro-tube jacking head 18. The micro-tube jacking head 18 is coaxially fixed with the force transmission screw 17. A cutter disc 12 is provided at the axis of the micro-tube jacking head 18. The PVC micro-tube jacking mechanism 9 is fixed to the PVC pipe 15 through a cylindrical connecting joint 14.

[0042] A pipe jacking process of a one-time hole-forming PVC micro pipe jacking device, the specific process flow is as follows:

[0043] Construction of micro steel caisson:

[0044] First, excavate the starting steel shaft 5 and the receiving steel shaft 8, and prefabricate circular starting and receiving openings 21 at multiple locations. Figure 4 shows three groups of openings 21. The actual opening position is determined according to the jacking pipe elevation, and is supplemented by a double-layer flange and rubber ring 19, and an outer cover 20 is added for sealing. After sinking to the preset height, the outer cover 20 of the steel shaft at the required height is removed. The outer cover 20 is retained in the area of ​​the steel shaft opening 21 that is not needed in this project. The excavation depth of the bottom soil of the receiving steel shaft 8 should be flush with the lowest point of the pipeline height. Space for equipment assembly should be reserved in the soil of the starting steel shaft 5, and the soil at the bottom of the shaft should be leveled.

[0045] Equipment assembly:

[0046] After the sedimentation tank 2 and high-pressure pump 3 are laid out, the push-pull pipe machine 10 is placed on the receiving steel well 8, and the level and height are adjusted to the preset position. The operating platform 4 is placed on the push-pull pipe machine 10, and the push-pull pipe machine 10 is placed in front of the rear seat 11. The top cylinder 16 is connected to the push-pull pipe machine 10, and the laser theodolite 6 is placed. The communication line, hydraulic oil circuit unit 7, and water inlet circuit are connected, and the drill bit is installed. The PVC pipe 15, the top cylinder 16, and the force transmission screw 17 are connected to the rear of the tunneling machine. Among them, the top cylinder 16 is connected to the rear of the tunneling machine, and the force transmission screw 17 is located between the upper and lower top cylinders 16. The PVC pipe 15 to be laid is located outside the top cylinder 16;

[0047] Pipe jacking starts:

[0048] The tunnel boring machine and the PVC pipe 15, jacking cylinder 16, and force transmission screw 17 connected thereto are pushed into the starting hole 21 and into the soil using the push-pull pipe machine 10. The other end of the force transmission screw 17 is connected to the rotating device in the push-pull pipe machine 10. During the subsequent jacking process, the jacking force is divided into two parts: the head-on resistance of the tunnel boring machine and the side friction resistance of the pipe. The force transmission screw 17 can transmit part of the jacking force to the tunnel boring machine to balance the head-on resistance. The push-pull pipe machine 10 applies part of the jacking force to the pipe cross section.

[0049] Pipe section advancement:

[0050] The water inlet circuit in the force transmission screw 17 is opened, and the rotating oil circuit of the force transmission screw 17 is opened. After the water is stably discharged from the outside of the force transmission screw 17, the propulsion oil circuit is opened, and the whole pipe is pushed forward. As the jacking pipe is pushed forward, the subsequent PVC pipe 15, the jacking cylinder 16, and the force transmission screw 17 are also lengthened to ensure the continuous jacking of the jacking pipe. The cross section of the pipe section fits with the push-pull pipe machine 10 to withstand the jacking force.

[0051] Complete propulsion, recover equipment:

[0052] After the excavation equipment enters the receiving steel well 8, the laying of the PVC pipe 15 is completed through one-time drilling. Then the excavation equipment is recovered, the force transmission screw 17 is retracted and pulled out, and finally the steel micro caisson is added with the outer cover 20 and the entire caisson is pulled out and recovered.

[0053] At the same time, the contents not described in detail in this specification belong to the existing technology known to professional and technical personnel in this field.

[0054] When in use, first place the PVC pipe 15 at the bottom of the starting steel well 5 and directly in front of the push-pull pipe machine 10, then place the top cylinder 16 on the inside of the PVC pipe 15, and then install the force transmission screw 17 on the rotating end of the push-pull pipe machine 10, and finally extend the force transmission screw 17 into the top cylinder 16. At this time, the tail end of the PVC pipe 15 is in contact with the cross-section of the push-pull pipe machine 10.

[0055] Start the hydraulic unit 7 to drive the push-pull pipe machine 10 to push. At the same time, the rotating end of the push-pull pipe machine 10 drives the force transmission screw 17 to rotate, so that the force transmission screw 17 can be pushed forward in a screw-in manner, and the force transmission screw 17 drives the cutter head 12 to perform the hole opening operation.

[0056] During the drilling process, the force transmission screw 17 transmits part of the jacking force to balance the headwind in front of the tunnel boring machine and share the force on the PVC pipe 15. The wall of the PVC pipe 15 only bears the frictional resistance, preventing it from becoming unstable during the jacking process and also playing a certain protective role.

[0057] At the same time, through two groups of high-pressure pumps 3, one group of high-pressure pumps 3 (not shown in the figure) injects high-pressure water into the power transmission screw 17 to mix the excavated soil to form mud for easy discharge, and the other group of high-pressure pumps 3 penetrates into the gap between the power transmission screw 17 and the top cylinder 16, and the mud is pumped through the gap into the sedimentation tank 2 for temporary storage.

[0058] As the jacking pipe advances, the subsequent PVC pipe 15 should be quickly connected, and the jacking cylinder 16 and the force transmission screw 17 are also lengthened to ensure the continuous jacking of the jacking pipe.

[0059] In summary, the one-time hole-forming PVC micro-pipe jacking device and its jacking process apply micro-pipe jacking technology to the laying of plastic pipes. The technology is more mature, and compared with traditional plastic pipe laying methods such as guided drilling and directional drilling, it omits the steps of multiple hole expansions and has the advantage of one-time hole formation. Secondly, since the mechanical properties of plastic pipes are lower than those of concrete, steel or cast iron pipes, in order to solve this problem, we directly connect the force transmission screw to the jacking mechanism, and transmit part of the jacking force through the force transmission screw to balance the head-on resistance in front of the tunnel boring machine and share the force on the PVC pipe. The PVC pipe wall only bears frictional resistance to prevent it from becoming unstable or damaged during the jacking process, thereby realizing the grafting of jacking technology into the laying application of plastic pipes.

[0060] It should be noted that the electrical components appearing in this article are all connected to an external main controller and 380V AC power, and the main controller is a conventional known device that can control a computer, etc. Its control principle, internal structure, and control switch mode are all conventional means of the prior art, which are directly quoted here without further elaboration. In this article, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device that includes a series of elements includes not only those elements, but also other elements that are not explicitly listed, or also includes elements that are inherent to such process, method, article or device.

[0061] While embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions, and variations may be made to these embodiments without departing from the principles and spirit of the invention, and that the scope of the invention is defined by the appended claims and their equivalents.

Claims

1. A one-time hole-forming PVC micro-pipe jacking device, characterized in that: It comprises a soil layer (1), with a receiving steel well (8) and a starting steel well (5) respectively arranged vertically downward on both sides of the soil layer (1), and a sedimentation tank (2), a high-pressure pump (3) and a hydraulic unit (7) respectively arranged on the top of the soil layer (1); An operating table (4), a pipe push-pull machine (10) and a rear seat (11) for supporting the pipe push-pull machine (10) are respectively arranged in the starting steel well (5), and the hydraulic unit (7) is connected to the pipe push-pull machine (10) through a hydraulic pipeline; The rotating end of the push-pull pipe machine (10) is rotatably connected to a force transmission screw (17), the outer cover of the force transmission screw (17) is provided with a top cylinder (16), the outer cover of the top cylinder (16) is provided with a PVC pipe (15), and one end of the PVC pipe (15) abuts against the end surface of the push-pull pipe machine (10); A PVC micro-tube jacking mechanism (9) is installed at one end of the force transmission screw (17) away from the pipe push-pull machine (10), and the PVC micro-tube jacking mechanism (9) is fixed to the PVC pipe (15) through a cylindrical connecting joint (14).

2. A one-time hole forming PVC micro-pipe jacking device according to claim 1, characterized in that: The PVC micro-tube jacking mechanism (9) comprises a PVC micro-tube jacking body (13) and a micro-tube jacking head (18); the micro-tube jacking head (18) is coaxially fixed with a force transmission screw (17); and a cutter disc (12) is arranged at the axis of the micro-tube jacking head (18).

3. The one-time hole-forming PVC micro-pipe jacking device according to claim 1 is characterized in that: At least two groups of high-pressure pumps (3) are provided, one of which is connected to the sedimentation tank (2). This group of high-pressure pumps (3) can pump out the mud inside the top cylinder (16), and the other group of high-pressure pumps (3) is used to inject water into the inside of the power transmission screw (17).

4. The one-time hole-forming PVC micro-pipe jacking device according to claim 1, characterized in that: The interior of the force transmission screw (17) is a hollow structure, and the rotating end of the push-pull pipe machine (10) is provided with a water injection hole which is in communication with the interior of the force transmission screw (17).

5. The one-time hole-forming PVC micro-pipe jacking device according to claim 1, characterized in that: A laser theodolite (6) is arranged on the top of the pipe push-pull machine (10).

6. A pipe jacking process according to any one of claims 1 to 5, characterized in that: The specific process is as follows: (1) Construction of micro steel caisson: First, the starting steel well (5) and the receiving steel well (8) are excavated, and circular starting and receiving openings are prefabricated at multiple locations. The actual opening position is determined according to the elevation of the top pipe, and is supplemented with a double-layer flange and a rubber ring (19), and an outer cover (20) is added for sealing. After sinking to a preset height, the outer cover (20) of the steel well of the required height is removed, and the outer cover (20) is retained in the steel well opening (21) area that is not used in the project. The excavation depth of the bottom soil of the receiving steel well (8) should be flush with the lowest point of the pipeline height. The soil of the starting steel well (5) needs to reserve equipment assembly space and level the soil at the bottom of the well; (2) Equipment assembly: After the sedimentation tank (2) and the high-pressure pump (3) are arranged, the push-pull pipe machine (10) is placed on the receiving steel well (8), the level and height are adjusted to the preset position, the operating table (4) is placed on the push-pull pipe machine (10), the push-pull pipe machine (10) is placed in front of the rear seat (11), the top cylinder (16) is connected to the push-pull pipe machine (10), and the laser theodolite (6) is placed, the communication line, the hydraulic oil circuit unit (7), and the water inlet circuit are connected, the drill bit is installed, and the rear of the tunnel boring machine is connected to the PVC pipe (15), the top cylinder (16), and the force transmission screw (17), wherein the top cylinder (16) is connected to the rear of the tunnel boring machine, the force transmission screw (17) is located between the upper and lower top cylinders (16), and the PVC pipe (15) to be laid is located outside the top cylinder (16); (3) Pipe jacking starts: The tunnel boring machine and the PVC pipe (15), the jacking cylinder (16), and the force transmission screw (17) connected thereto are pushed into the starting hole (21) and into the soil by using a push-pull pipe machine (10). The other end of the force transmission screw (17) is connected to a rotating device in the push-pull pipe machine (10). In the subsequent pushing process, the pushing force is divided into two parts: the head-on resistance of the tunnel boring machine and the side friction resistance of the pipe. The force transmission screw (17) can transmit part of the pushing force to the tunnel boring machine to balance the head-on resistance. The push-pull pipe machine (10) applies part of the pushing force to the cross section of the pipe. (4) Pipe segment advancement: The water inlet circuit in the force transmission screw (17) is opened, the rotation oil circuit of the force transmission screw (17) is opened, and after the water is stably discharged from the outside of the force transmission screw (17), the propulsion oil circuit is opened, and the whole is pushed forward. The subsequent PVC pipe (15), the jacking cylinder (16), and the force transmission screw (17) should be quickly connected and lengthened accordingly to ensure the continuous jacking of the jacking pipe, and the cross section of the pipe section fits with the push-pull pipe machine (10) to withstand the jacking force; (5) Complete the advancement and recover the equipment: After the excavation equipment enters the receiving steel well (8), the PVC pipe (15) is laid through a one-time hole forming, and then the excavation equipment is recovered, the force transmission screw (17) is retracted and pulled out, and finally the steel micro caisson is added with an outer cover (20) and pulled out as a whole and recovered.

Citation Information

Patent Citations

  • Small pipe diameter drainage pipeline pipe jacking machine tool and pipe jacking construction method

    CN106988751A

  • Pipe-jacking construction machine of small pipe diameter plastic drainage pipe and pipe-jacking construction method of plastic drainage pipe

    CN108386608A

  • Construction method of continuous operation of small-bore pipelines

    CN108916469A

  • Underground pipeline micro pipe jacking secondary construction method construction process

    CN111750173A

  • One-time pore-forming PVC (polyvinyl chloride) miniature pipe jacking device and pipe jacking process thereof

    CN116480841A

Cited By

  • Indoor test simulation system and method for rectangular pipe jacking curve construction

    CN119321910A

  • Pipeline positioning assembly and sewage pipe network pipe jacking construction device and construction method

    CN120739939A

  • Non-excavation pipeline supporting device for municipal drainage pipeline

    CN121593490A