Production method of prefabricated type shear wall component

A production method and assembly technology, applied in the direction of molds, etc., can solve the problems of side molds that cannot be reused and high production costs, and achieve the effects of reducing work difficulty, improving efficiency, and saving production costs

CN106738230AInactive Publication Date: 2017-05-31XI'AN UNIVERSITY OF ARCHITECTURE AND TECHNOLOGY
6 Cites 1 Cited by

Patent Information

Authority / Receiving Office
CN · China
Current Assignee / Owner
Publication Date
2017-05-31
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention provides a production method of a prefabricated type shear wall component. According to the production method of the prefabricated type shear wall component, threaded-hole rods, four lower side formwork units, four upper side formwork units, hidden column steel reinforcement fixing plates and hidden beam steel reinforcement fixing plates are sequentially manufactured; then, the hidden column steel reinforcement fixing plates, the hidden beam steel reinforcement fixing plates and stirrup baffles are sequentially installed on the lower side formwork units, the four lower side formwork units are prefabricated, and then a lower side formwork is formed; steel reinforcement sleeves, lifting rings, hidden column steel reinforcements and hidden beam steel reinforcements are installed, then the hidden column steel reinforcements, the hidden beam steel reinforcements, u-stirrups or stirrups and a steel reinforcement mesh are bound, and an upper side formwork is combined with the lower side formwork in a covered manner; after detection, the concrete pouring procedure and the concrete vibrating tamping procedure are conducted; and after use, the prefabricated type shear wall component is cut and recycled to be reused. By the adoption of the production method of the prefabricated type shear wall component, a convenient and economical production method of the prefabricated shear wall component of the prefabricated type shear wall structure is provided, the consumption on the aspect of steel materials in the production process of the prefabricated component is reduced, the production cost is greatly reduced, and the production efficiency of the prefabricated component is improved at the same time.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention belongs to the field of construction engineering, and relates to a prefabricated shear wall component, in particular to a production method of the prefabricated shear wall component. Background technique

[0002] The prefabricated building is a building that is assembled by dismantling the structural components of the building in advance and transporting them to the site through reliable connections after they are prefabricated in the factory. This kind of building is characterized by fast construction speed, less restricted by climatic conditions, labor saving, and improved building quality. The prefabricated shear wall structure is currently the most widely used prefabricated building in my country.

[0003] With the advancement of urbanization, about 4 billion m of new buildings are built every year in the world. 2 of residential buildings, and my country's annual new building area ranks first in the world. There is a large demand fo...

Examples

Embodiment

[0067] Such as Figure 1 to Figure 14 As shown, the present embodiment provides a production method of a prefabricated shear wall member, the method comprising the following steps:

[0068] Step 1, determine the length of the side form according to the side length of the target prefabricated prefabricated shear wall member, determine the length of the steel bar according to the length of the side form; position, the position of the exposed part of the concealed beam reinforcement 12, the position of the exposed part of the open stirrup or the stirrup 13, the position of the reinforcement sleeve 14 and the position of the lifting ring 15, and the threaded hole corresponding to the position of the reinforcement is set on the steel bar 7. Obtain the threaded hole rod 1-7;

[0069] Step 2, place the threaded hole rod 1-7 in the fixed connection groove 1-6 of a pair of half-side mold units 1-5, and the two ends of the threaded hole rod 1-7 are respectively supported on the blind e...