Glass Tempering Furnace
By designing a fiberglass furnace including multiple furnace bodies and a transport mechanism, and using a control system to coordinate the processing of flow, the existing fiberglass furnace has been solved, and the utilization rate of equipment resources has been improved.
Patent Information
- Application Number
- CN201910853534.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-07-05
- Filing Date
- 2019-09-10
- Publication Date
- 2025-04-04
- Estimated Expiration
- 2039-09-10
AI Technical Summary
The existing fiberglass tempering furnaces occupy a large space and the furnace body is idle for too long, resulting in a low utilization rate of equipment resources.
A fiberglass tempering furnace including a first furnace body, a pickup mechanism, a second furnace body, a third furnace body and a transport mechanism are designed. Through the coordinated control of the control system, efficient flow of preheating, tempering and slow cooling treatment of the glass cover plate is achieved, reducing idle time.
It effectively reduces the space occupation and idle time of the equipment, improves the utilization rate of equipment resources, and meets the normal production requirements of the tempering process of glass cover plates.
Smart Images

Figure CN110451789B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a glass cover plate processing technology, in particular to a glass tempering furnace. Background Art
[0002] In the field of glass cover manufacturing industry, chemical tempering furnace is a common production equipment, which mainly includes preheating treatment, tempering treatment and slow cooling treatment processes.
[0003] When using the existing tempering furnace for production, the preheating furnace, tempering furnace, tempering furnace and slow cooling furnace are usually used to complete the tempering process of the glass cover. However, the preheating furnace and the slow cooling furnace are often idle for too long, and the space occupied is large, and the utilization rate of equipment resources is low. Summary of the invention
[0004] The invention provides a glass tempering furnace to solve the problems that the existing glass tempering furnace occupies a large space and the furnace body has a long idle time.
[0005] The technical solution proposed by the present invention for the above-mentioned technical problem is as follows:
[0006] The present invention provides a glass tempering furnace, characterized in that it comprises:
[0007] A first furnace body for preheating and slowly cooling the glass cover plate;
[0008] A picking mechanism for picking up and placing the tempered cage loaded with the glass cover plate, wherein the picking mechanism is arranged on the first furnace body;
[0009] A second furnace body and a third furnace body for respectively performing tempering treatment on the glass cover plate;
[0010] A transport mechanism for transporting the first furnace body to the second furnace body and the third furnace body respectively; and
[0011] A control system, the control system being used to control:
[0012] After the temperature in the first furnace body reaches a first preset temperature, the first group of tempering cages are placed into the first furnace body for preheating by using the picking mechanism;
[0013] After the temperature inside the first furnace body reaches a second preset temperature and the temperature inside the second furnace body reaches a third preset temperature, the first furnace body is transported to the second furnace body position by the transport mechanism, and the tempering cage in the first furnace body is placed into the second furnace body by the picking mechanism so as to perform tempering treatment on the glass cover plates in the first group of tempering cages by the second furnace body;
[0014] After the temperature in the first furnace body drops to the first preset temperature, the second group of tempered cages loaded with the glass cover plates are placed into the first furnace body by the picking mechanism for preheating;
[0015] After the temperature in the first furnace body reaches the second preset temperature and the temperature in the third furnace body reaches the third preset temperature, the first furnace body is transported to the position of the third furnace body by the transport mechanism, and the second group of tempering cages in the first furnace body is placed in the third furnace body by the picking mechanism;
[0016] After the second furnace body performs a tempering treatment on the glass cover plates in the first group of tempering cages, the first furnace body is transported to the second furnace body position by the transport mechanism, and the first group of tempering cages in the second furnace body is placed into the first furnace body by the picking mechanism to perform a slow cooling treatment on the glass cover plates in the first group of tempering cages;
[0017] The first furnace body performs a slow cooling treatment on the glass cover plates in the first group of tempered cages, and after the first group of tempered cages are placed at a preset position by the picking mechanism, the first furnace body is transported to the third furnace body position by the transport mechanism, and the tempered cages in the third furnace body are placed into the first furnace body by the picking mechanism to perform a slow cooling treatment on the glass cover plates in the second group of tempered cages.
[0018] Preferably, the control system is also used to control:
[0019] After the first set of tempered cages are placed at a preset position by using a picking mechanism, and before the picking mechanism places the second tempered cages in the third furnace body into the first furnace body to perform a slow cooling treatment on the glass cover plates in the second set of tempered cages, the picking mechanism is used to place the third set of tempered cages into the first furnace body for preheating treatment;
[0020] After the temperature inside the first furnace body reaches the second preset temperature and the temperature inside the second furnace body reaches the third preset temperature, the first furnace body is transported to the second furnace body position by the transport mechanism, and the third group of tempered cages in the first furnace body is placed into the second furnace body by the picking mechanism so as to use the second furnace body to perform tempering on the glass cover plates in the third group of tempered cages.
[0021] Preferably, the first furnace body comprises a first accommodating cavity for placing the tempered cage and a first opening and closing door structure of the first accommodating cavity;
[0022] The picking mechanism includes a fixing portion disposed on the first furnace body and a picker connected to the fixing portion;
[0023] The transport mechanism comprises a guide rail and a transport carrier arranged on the guide rail, the first furnace body is arranged on the transport carrier; the initial transport position of the transport carrier is located between the second furnace body and the third furnace body;
[0024] The second furnace body includes a second accommodating chamber for placing the tempered cage and a second opening and closing door structure of the second accommodating chamber, and the third furnace body includes a third accommodating chamber for placing the tempered cage and a third opening and closing door structure of the third accommodating chamber.
[0025] Preferably, the initial carrying position is located at a middle position between the second furnace body and the third furnace body.
[0026] Preferably, the first preset temperature is 90 degrees Celsius, the second preset temperature is 370 degrees Celsius, and the third preset temperature is 420 degrees Celsius.
[0027] Preferably, the guide rail includes a first slide rail and a second slide rail arranged in parallel, the carrier includes a first carrier part arranged on the first slide rail and a second carrier part arranged on the second slide rail, and the first carrier part and the second carrier part are fixedly connected to the outer wall of the first furnace body.
[0028] Preferably, a material placement platform is provided below the initial transport position.
[0029] Preferably, an air flow passage connected to the air delivery channel of the air delivery device is opened on the wall of the first accommodating chamber, and the air flow passage is used to input heat-conducting gas at a first preset temperature into the first accommodating chamber during preheating treatment, and to input heat-conducting gas at a second preset temperature into the first accommodating chamber during slow cooling treatment.
[0030] The technical solution provided by the embodiment of the present invention has the following beneficial effects:
[0031] Compared with the traditional method of using two furnace bodies separately, which brings the problem of occupying space and having more idle time in the tempering process, under the condition of still meeting the production requirements, the present embodiment uses the first furnace body to realize the preheating treatment and slow cooling treatment of the glass cover plate loaded in the tempering cage to reduce the space occupied by the equipment, and controls the processing coordination between the first furnace body, the second furnace body, and the third furnace body to reduce the idle time of the furnace body and improve the utilization rate of equipment resources. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0033] Figure 1 A three-dimensional structural schematic diagram of a glass tempering furnace according to an embodiment of the present invention is provided;
[0034] Figure 2 Another three-dimensional structural schematic diagram of a glass tempering furnace under an embodiment of the present invention is provided. DETAILED DESCRIPTION
[0035] In order to make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.
[0036] See also Figure 1 and Figure 2 , Figure 1 A three-dimensional structural schematic diagram of a glass tempering furnace according to an embodiment of the present invention is provided; Figure 2 Another three-dimensional structural schematic diagram of a glass tempering furnace under an embodiment of the present invention is provided. Figure 1 As shown, the glass tempering furnace 1 provided by the present invention may include a frame 11, on which a first furnace body 12, a picking mechanism 13, a second furnace body 14, a third furnace body 15, a transport mechanism 16 and a corresponding control system (not shown) are provided, wherein the first furnace body 12 is used to complete the glass cover plate preheating step and the slow cooling step in the glass tempering process; the picking mechanism 13 is used to pick up and place the tempering cage loaded with the glass cover plate; the second furnace body 14 and the third furnace body 15 are both used to temper the glass cover plate; the transport mechanism 16 is used to carry the first furnace body 12, so as to realize the transport of the tempering cage in the first furnace body 12 to the positions of the second furnace body 14 and the third furnace body 15 respectively.
[0037] It is understandable that, in actual production, a tempered cage can be loaded with thirty to forty tempered racks, and each tempered rack can be loaded with one hundred glass cover plates. Here, the glass cover plate can be specifically a mobile phone glass cover plate.
[0038] The control system provided by the present invention is used to control the first furnace body 12, the picking mechanism 13, the second furnace body 14, the third furnace body 15, and the carrying mechanism 16 accordingly. The specific control may include:
[0039] Action 1: After the temperature inside the first furnace body 12 reaches the first preset temperature, the first set of tempering cages is placed into the first furnace body for preheating by using the pickup mechanism 13. Here, the first preset temperature may be 90 degrees Celsius.
[0040] Action 2: After the temperature inside the first furnace body 12 reaches the second preset temperature and the temperature inside the second furnace body 12 reaches the third preset temperature, the first furnace body 12 is transported to the second furnace body 14 by the transport mechanism 16, and the first set of tempering cages in the first furnace body 12 is placed in the second furnace body 14 by the pick-up mechanism 13 so as to perform tempering treatment on the glass cover plates in the first set of tempering cages by the second furnace body 14. Here, the second preset temperature may be 370 degrees Celsius, and the third preset temperature may be 420 degrees Celsius.
[0041] Action 3: After the temperature in the first furnace body 12 drops to the first preset temperature, the second set of tempered cages loaded with glass cover plates are placed into the first furnace body 12 by using the picking mechanism 13 for preheating.
[0042] Action 4: After the temperature inside the first furnace body 12 reaches the second preset temperature and the temperature inside the third furnace body 15 reaches the third preset temperature, the first furnace body 12 is transported to the third furnace body 15 by the transport mechanism 16, and the picking mechanism 13 places the second group of tempering cages in the first furnace body 12 into the third furnace body 15.
[0043] Action 5: After the second furnace body 15 performs tempering treatment on the glass cover plates in the first group of tempering cages, the first furnace body 12 is transported to the second furnace body 14 by the transport mechanism 16, and the first group of tempering cages in the second furnace body 14 is placed into the first furnace body 12 by the picking mechanism 13 to perform slow cooling treatment on the glass cover plates in the first group of tempering cages.
[0044] Action 6: The first furnace body 12 performs a slow cooling treatment on the glass cover plates in the second group of tempered cages, and after the first group of tempered cages are placed at a preset position by the picking mechanism 13, the first furnace body 12 is transported to the position of the third furnace body 15 by the transport mechanism 16, and the second group of tempered cages in the third furnace body 15 is placed into the first furnace body 12 by the picking mechanism 13 to perform a slow cooling treatment on the glass cover plates in the second group of tempered cages.
[0045] The glass tempering furnace and corresponding action execution provided by the present invention, compared with the traditional method of using two furnace bodies separately to cause the problem of occupying space and more idle time in the tempering process, the present invention uses the first furnace body to realize preheating treatment and slow cooling treatment of the glass cover plate loaded in the tempering cage while meeting normal production requirements to reduce the space occupied by the equipment, and controls the processing coordination between the first furnace body, the second furnace body, and the third furnace body to reduce the idle time of the furnace body, thereby improving the utilization rate of equipment resources.
[0046] In this embodiment, the control system is also used to control:
[0047] Action 7: After the first set of tempered cages are placed at the preset position by the picking mechanism 13, and before the picking mechanism 13 places the second set of tempered cages in the third furnace body 15 into the first furnace body to perform a slow cooling treatment on the glass cover plate, the picking mechanism is used to place the third set of tempered cages into the first furnace body for preheating treatment;
[0048] After the temperature inside the first furnace body 12 reaches the second preset temperature and the temperature inside the second furnace body 14 reaches the third preset temperature, the first furnace body 12 is transported to the position of the second furnace body 14 by the transport mechanism 16, and the third group of tempered cages in the first furnace body 12 is placed in the second furnace body 14 by the picking mechanism 13 so that the glass cover plates in the third group of tempered cages are tempered by the second furnace body 14, thereby realizing the reuse of the first furnace body 12 for preheating treatment and slow cooling treatment, and at the same time, using the time gap of the third furnace body 15 for tempering the glass cover plates in the second group of tempered cages, using the first furnace body 12 to preheat the third group of tempered cages, thereby further reducing the idle time of the first furnace body 12.
[0049] It should be understood that, during the tempering process of the third group of tempering cages in the second furnace body 14, the first furnace body can be brought to the third furnace body by the transport mechanism, and the second group of tempering cages in the third furnace body can be picked up by the picking mechanism to perform a slow cooling process on the glass cover plates in the second group of tempering cages in the first furnace body. Similarly, after the slow cooling, the second group of tempering cages is placed at a preset position, and during the tempering process of the third group of tempering cages in the second furnace body 14, the first furnace body 12 can be used to preheat the fourth group of tempering cages, and so on and so forth for the tempering process of the subsequent groups of tempering cages.
[0050] In this embodiment, the first furnace body 12 may specifically include a first accommodating cavity for placing the tempered cage and a first opening and closing door structure of the first accommodating cavity. The picking mechanism 13 may specifically include a fixing portion provided on the first furnace body 12 and a picker connected to the fixing portion, and the picker is used to pick up the tempered cage or place the picked up tempered cage at a designated position. The second furnace body 14 may specifically include a second accommodating cavity for placing the tempered cage and a second opening and closing door structure of the second accommodating cavity, and the third furnace body 15 may include a third accommodating cavity for placing the tempered cage and a third opening and closing door structure of the third accommodating cavity.
[0051] The transport mechanism 16 includes a guide rail 161 and a carrier 162 disposed on the guide rail 161. The first furnace body 12 is disposed on the carrier 162. The initial transport position of the carrier 162 is located between the second furnace body 14 and the third furnace body 15. Here, the initial transport position is located above the material placement table, and the initial transport position and the material placement table can be further located at the middle position between the second furnace body 14 and the third furnace body 15. Therefore, during the initial operation, the picking mechanism 13 uses a picker to pick up the tempered cage placed on the material placement table and places it into the first accommodating cavity of the first furnace body 12.
[0052] The aforementioned preset position may coincide with the material placement table, or may be arranged below the guide rail outside the material placement table.
[0053] Here, the guide rail 161 includes a first slide rail and a second slide rail arranged in parallel, and the carrier 16 includes a first carrier part arranged on the first slide rail and a second carrier part arranged on the second slide rail. The first carrier part and the second carrier part are fixedly connected to the outer wall of the first furnace body 12, so when the first carrier part and the second carrier part move on the corresponding slide rails, they can drive the first furnace body 12 to achieve displacement.
[0054] It can be understood that when implementing specific actions, the control system can also control the opening and closing of the corresponding opening and closing door structure and the tempering time and temperature. The corresponding control basis, such as the opening and closing of the corresponding opening and closing door structure, can be an electrical signal including position information emitted by a position sensor signal, such as an electrical signal emitted by an optical position sensor or a limit switch; the corresponding tempering time can be an electrical signal including time information emitted by a timing circuit, such as an electrical signal emitted by a timing unit; the corresponding temperature can be an electrical signal including temperature information emitted by a temperature sensor, such as an electrical signal emitted by an electronic thermometer.
[0055] In the actual production process, the controller can simultaneously control the first furnace body 12, the second furnace body 14 and the third furnace body 15 to start heating up. When the temperature inside the first furnace body 12 rises to 90°C, the first opening and closing door structure of the first furnace body 12 opens, and the picking mechanism 13 hoists the mobile phone glass cover plates in the first group of tempered cages into the first furnace body 12. The first opening and closing door structure of the first furnace body 12 is closed to start preheating the mobile phone glass cover plates in the first group of tempered cages.
[0056] After 0.5 hours, the temperature in the first furnace body 12 rises to 370°C, and the preheating treatment is completed after 1 hour. At the same time, if the temperature of the molten salt in the second furnace body 14 and the third furnace body 15 is 420°C, the first furnace body 12 is driven to move toward the second furnace body 14 by the carrier mechanism 16, and stops moving when it moves directly above the second furnace body 14. The second opening and closing door structure of the second furnace body 14 is opened to allow the first group of tempered cages in the first furnace body 12 to be placed in the second accommodating cavity of the second furnace body 14. Thereafter, the second opening and closing door structure of the second furnace body 14 is closed, and the second furnace body 14 performs tempering treatment on the mobile phone glass cover in the first group of tempered cages.
[0057] Afterwards, the transport mechanism 16 drives the first furnace body 12 to move back to the middle position (initial transport position) and starts cooling. After 1 hour, the temperature inside the first furnace body 12 drops to 90°C. The first opening and closing door structure of the first furnace body 12 is opened, and the picking mechanism 13 hoists the second set of tempered cages (which also have mobile phone glass cover plates loaded thereon) into the first accommodating cavity of the first furnace body 12. The first opening and closing door structure of the first furnace body 12 is closed to start preheating the mobile phone glass cover plates in the second set of tempered cages.
[0058] After 0.5 hours, the temperature inside the first furnace body 14 rises to 370°C, and the preheating treatment is completed after 1 hour. The transport mechanism 16 drives the first furnace body 12 to move toward the third furnace body 15, and stops moving when it moves directly above the third furnace body 15. The third opening and closing door structure of the third furnace body 15 is opened to allow the second tempered cage in the first furnace body 12 to be placed in the third accommodating cavity of the third furnace body 15. Thereafter, the third opening and closing door structure of the third furnace body 15 is closed, and the third furnace body 15 tempers the mobile phone glass cover plates in the second group of tempered cages. At this time, the mobile phone glass cover plates in the first group of tempered cages in the second furnace body 14 are tempered for 2.5 hours, as shown in Table 1, tempering parameter table for conventional material products:
[0059]
[0060] It can be seen from the table that the time required for tempering is 4 hours, so after 1.5 hours, the mobile phone glass cover plates in the first group of tempered cages in the second furnace body 14 are tempered. After that, the transport mechanism 16 drives the first furnace body 12 to move toward the second furnace body 14, and stops moving when it moves to the top of the second furnace body 14. The second opening and closing door structure of the second furnace body 14 is opened, and the picking mechanism 13 hoists the tempered cage loaded with the mobile phone glass cover plates in the first group of tempered cages in the second furnace body 14 into the first furnace body 12 to perform a slow cooling treatment on the mobile phone glass cover plates.
[0061] The transport mechanism 16 drives the second furnace body 12 to move, and stops moving when it moves to the initial transport position, and the first opening and closing door structure of the first furnace body 12 is closed, and the slow cooling treatment is completed after 1 hour. After the slow cooling treatment is completed, the first opening and closing door structure of the first furnace body 12 is opened, and the first group of tempered cages with mobile phone glass cover plates after the slow cooling treatment are placed on the material placement table by the picker 13, completing the tempering process of the mobile phone glass cover plates in the first group of tempered cages.
[0062] Afterwards, the picking mechanism 13 hoists the third set of tempered cages loaded with the mobile phone glass cover plate into the first furnace body 12 to perform the same tempering steps as the preheating treatment in the first furnace body 12, the tempering treatment in the second furnace body 14, and the slow cooling treatment in the first furnace body 12, and when the third set of tempered cages is placed in the second furnace body 14 to temper the mobile phone glass cover plate loaded on the second set of tempered cages, the mobile phone glass cover plate in the third furnace body 15 is tempered for 4 hours, and the tempering treatment is completed. Thereafter, the transport mechanism 16 drives the first furnace body 12 to move toward the third furnace body 15, and stops moving when it moves to the top of the third furnace body 15. The third opening and closing door structure of the third furnace body 15 is opened, and the picking mechanism 13 hoists the second set of tempered cages loaded with the mobile phone glass cover plate in the third furnace body 15 into the first furnace body 12 to perform slow cooling treatment on the mobile phone glass cover plate, and the slow cooling treatment is completed after 1 hour. Afterwards, the first opening and closing door structure of the first furnace body 12 is opened, and the second set of tempered cages equipped with mobile phone glass cover plates after slow cooling are placed on the loading platform by the picker 13, completing the tempering process of the mobile phone glass cover plates in the second set of tempered cages. It can be seen that the first furnace body 12 is effectively reused according to the time of each treatment to implement the preheating and slow cooling steps, while still meeting the production requirements, reducing the idle time of the equipment, improving the utilization rate of equipment resources, and reducing the space occupied by the equipment.
[0063] In the glass tempering furnace provided by the present invention, an air flow passage for connecting with the air delivery channel of the gas delivery device is opened on the wall of the first accommodating chamber of the first furnace body, and the air flow passage is used to input heat-conducting gas of a first preset temperature into the first accommodating chamber during preheating treatment, and to input heat-conducting gas of a second preset temperature into the first accommodating chamber during slow cooling treatment.
[0064] Among them, the gas supply device is used to provide heat-conducting gas at a preset temperature. By inputting heat-conducting gas of corresponding temperature, the temperature effect on the glass cover plate can be enhanced, effectively shortening the processing time of preheating and slow cooling of the first furnace body, and improving production efficiency.
[0065] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A glass tempering furnace, characterized in that: include: A first furnace body for preheating and slowly cooling the glass cover plate; A picking mechanism for picking up and placing the tempered cage loaded with the glass cover plate, wherein the picking mechanism is arranged on the first furnace body; A second furnace body and a third furnace body for respectively performing tempering treatment on the glass cover plate; A transport mechanism for transporting the first furnace body to the positions of the second furnace body and the third furnace body respectively; and A control system, the control system being used to control: After the temperature in the first furnace body reaches a first preset temperature, the first group of tempering cages are placed into the first furnace body for preheating by using the picking mechanism; After the temperature inside the first furnace body reaches a second preset temperature and the temperature inside the second furnace body reaches a third preset temperature, the first furnace body is transported to the second furnace body position by the transport mechanism, and the first group of tempered cages in the first furnace body is placed into the second furnace body by the picking mechanism so as to use the second furnace body to perform tempering treatment on the glass cover plates in the first group of tempered cages; After the temperature in the first furnace body drops to the first preset temperature, the second group of tempered cages loaded with the glass cover plates are placed into the first furnace body by the picking mechanism for preheating; After the temperature inside the first furnace body reaches the second preset temperature and the temperature inside the third furnace body reaches the third preset temperature, the first furnace body is transported to the position of the third furnace body by the transport mechanism, and the second group of tempering cages in the first furnace body is placed in the third furnace body by the picking mechanism; After the second furnace body performs a tempering treatment on the glass cover plates in the first group of tempering cages, the first furnace body is transported to the second furnace body position by the transport mechanism, and the first group of tempering cages in the second furnace body is placed into the first furnace body by the picking mechanism to perform a slow cooling treatment on the glass cover plates in the first group of tempering cages; The glass cover plates in the first group of tempered cages are subjected to a slow cooling treatment in the first furnace body, and after the first group of tempered cages are placed at a preset position by using a picking mechanism, the first furnace body is transported to the third furnace body position by using the transport mechanism, and the tempered cages in the third furnace body are placed into the first furnace body by using the picking mechanism to perform a slow cooling treatment on the glass cover plates in the second group of tempered cages; The transport mechanism includes a guide rail and a transport carrier arranged on the guide rail, the first furnace body is arranged on the transport carrier; the initial transport position of the transport carrier is located between the second furnace body and the third furnace body; the guide rail includes a first slide rail and a second slide rail arranged in parallel, the transport carrier includes a first transport part arranged on the first slide rail and a second transport part arranged on the second slide rail, and the first transport part and the second transport part are fixedly connected to the outer wall of the first furnace body.
2. The glass tempering furnace according to claim 1, characterized in that: The control system is also used to control: After the first set of tempered cages are placed at a preset position by using a picking mechanism, and before the picking mechanism places the second tempered cages in the third furnace body into the first furnace body to perform a slow cooling treatment on the glass cover plates in the second set of tempered cages, the picking mechanism is used to place the third set of tempered cages into the first furnace body for preheating treatment; After the temperature inside the first furnace body reaches the second preset temperature and the temperature inside the second furnace body reaches the third preset temperature, the first furnace body is transported to the second furnace body position by the transport mechanism, and the third group of tempered cages in the first furnace body is placed into the second furnace body by the picking mechanism so as to use the second furnace body to perform tempering on the glass cover plates in the third group of tempered cages.
3. The glass tempering furnace according to claim 1, characterized in that: The first furnace body comprises a first accommodating cavity for placing the tempered cage and a first opening and closing door structure of the first accommodating cavity; The picking mechanism includes a fixing portion disposed on the first furnace body and a picker connected to the fixing portion; The second furnace body includes a second accommodating chamber for placing the tempered cage and a second opening and closing door structure of the second accommodating chamber, and the third furnace body includes a third accommodating chamber for placing the tempered cage and a third opening and closing door structure of the third accommodating chamber.
4. The glass tempering furnace according to claim 3, characterized in that: The initial carrying position is located at a middle position between the second furnace body and the third furnace body, and the initial carrying position corresponds to the preset position.
5. The glass tempering furnace according to claim 4, characterized in that: The first preset temperature is 90 degrees Celsius, the second preset temperature is 370 degrees Celsius, and the third preset temperature is 420 degrees Celsius.
6. The glass tempering furnace according to claim 3, characterized in that: A material placement platform is provided below the initial transport position.
7. The glass tempering furnace according to any one of claims 3 to 6, characterized in that: An air flow passage is provided on the wall of the first accommodating chamber for communicating with the air delivery channel of the air delivery device. The air flow passage is used to input heat-conducting gas at a first preset temperature into the first accommodating chamber during preheating treatment, and to input heat-conducting gas at a second preset temperature into the first accommodating chamber during slow cooling treatment.
Citation Information
Patent Citations
Vertical hoist type glass tempering equipment and operating flow thereof
TW201130767A