A single-stage reusable rocket power measurement and control system and its test method

Through industrial computers and network switches with CPCI architecture in the rocket power measurement and control system, the control process is simplified and the measurement and control work after the rocket lands is realized, the problems of complexity and cumbersome testing of traditional systems are solved, and the reliability of the system is improved. Data processing capability.

CN114089723BActive Publication Date: 2024-11-01KUAIZHOU AEROSPACE TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202111361371.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-11-17
Publication Date
2024-11-01
Estimated Expiration
2041-11-17

AI Technical Summary

Technical Problem

The traditional liquid rocket power measurement and control system is complex and not suitable for single-stage reusable rockets. It cannot achieve the measurement and control work after the rocket lands. The test process is cumbersome and cannot be independently closed-loop testing.

Method used

An industrial computer with CPCI architecture is used as a front-end measurement and control computer, simplifying the control process, realizing information interaction between the front-end and back-end through a network switch, using a relay combination board and current acquisition board for power system control and monitoring, and setting arrows on the front-end of measurement and control Data simulation computers perform closed-loop testing.

Benefits of technology

It realizes simplified control of a single-stage reusable rocket power measurement and control system, can conduct measurement and control work after the rocket lands, and conduct independent closed-loop testing when it cannot be connected to the external system, improving the reliability and data processing capabilities of the system. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114089723B_ABST
    Figure CN114089723B_ABST
Patent Text Reader

Abstract

The invention relates to a single-stage reusable rocket power measurement and control system, comprising a measurement and control front end and a measurement and control back end, wherein a back end measurement and control device is placed at the measurement and control back end, and the back end measurement and control device comprises a main command and control computer, a slave command and control computer, a monitoring computer, a back end switch, a measurement, launch and control system back end and a measurement system back end; a front end measurement and control device is placed at the measurement and control front end, and the front end measurement and control device comprises a front end measurement and control computer, a relay combination board, a power supply system, a front end switch, a measurement, launch and control system front end and a measurement system front end; the front end measurement and control computer is an industrial computer adopting a CPCI architecture; the power measurement and control system provided by the invention is suitable for a single-stage reusable rocket, and multi-stage workstations are removed, and only a single-stage workstation is needed; the control of the filling process is also controlled by the back end command and control computer, and subordinate filling workstations are no longer provided, thereby greatly simplifying the control process and realizing the measurement and control work after the rocket lands.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of aerospace measurement and control technology, and in particular to a single-stage reusable rocket power measurement and control system and a testing method. Background Art

[0002] The power measurement and control system is an important component of the rocket propulsion system and is used to complete the measurement and control work at all stages of the rocket propulsion system. Due to the multi-stage structure of traditional liquid rockets, their power measurement and control systems are relatively complex, including multi-stage power measurement and control command and workstations, with numerous equipment and cumbersome operation processes. They need to be uniformly dispatched through the master control network, and the system architecture is relatively complex. In addition, the power measurement and control system of traditional launch vehicles only needs to complete the measurement and control work of the rocket launch phase, and does not consider the rocket recovery phase. For single-stage reusable rockets, their structure is relatively simple and does not require a complex multi-stage power measurement and control system. At the same time, after the rocket lands, the power measurement and control system still needs to perform measurement and control work. Therefore, the power measurement and control system of existing multi-stage launch vehicles is no longer suitable for the working requirements of the power measurement and control system of single-stage reusable rockets.

[0003] When testing traditional liquid rocket propulsion measurement and control systems, they are equipped with front-end equivalents that can simulate the state quantities and analog signals of ground equipment, but cannot simulate the command and data interaction between the propulsion measurement and control system and external systems. They need to be connected to external systems through a master control network, and the testing process is complicated and cumbersome. The propulsion measurement and control system cannot be connected to external systems during factory acceptance, so a test system and method are needed to complete independent closed-loop testing of the propulsion measurement and control system.

[0004] Compact PCI (CPCI) technology is a modified PCI technology. The modified CPCI industrial computer is suitable for industrial field applications. With hot-swappable and redundant design capabilities, high-availability systems can be built to meet the requirements of telecommunications, digital communications, military equipment and other high-reliability fields. The openness, high reliability and hot-swappable characteristics of CPCI make this technology widely used in communications, networks, and computer telephone integration. At the same time, it is also suitable for real-time system control, industrial automation, real-time data acquisition, military systems and other fields that require high-speed computing, as well as modular applications such as intelligent transportation, aerospace, medical equipment, and water conservancy that require extremely high reliability and can be used for a long time.

[0005] CPCI uses a 2mm high-density pinhole bus connector. Compared with PCI cards using gold finger connectors, it has the characteristics of reliable connection and complete airtightness. The card has high shock resistance and corrosion resistance. In addition, CPCI cards use the EuroCard structure that has been tested in field use for more than 20 years. The EuroCard uses a vertical installation and front extraction structure, which improves the heat dissipation, shock resistance and easy maintenance of the card.

[0006] Compared with PLC and traditional industrial computers, industrial computers using CPCI architecture are compact, efficient, easy to transfer and move, and all interfaces are connected by aviation plugs, which can be easily wired on site. At the same time, various signal lines and control lines in the system are in the form of PCB routing, which can greatly simplify the layout and wiring difficulty of the system and improve the reliability of the entire system. At the same time, industrial computers using CPCI architecture have more powerful data processing capabilities and network communication functions than PLCs, and can execute more complex control algorithms. Summary of the invention

[0007] The present invention adopts an industrial computer with CPCI architecture as the front-end measurement and control computer, and provides a single-stage reusable liquid rocket propulsion measurement and control system, which can realize the control of all controlled objects of the rocket propulsion measurement and control system in different working stages and the measurement and monitoring of the power system status and parameters. Only a single-stage workstation needs to be established, and the control of the filling process is also controlled by the back-end command and control computer. There is no need to set up subordinate filling workstations, which simplifies the control process.

[0008] The specific scheme of the present invention is:

[0009] A single-stage reusable rocket power measurement and control system includes a measurement and control front end and a measurement and control back end, wherein the measurement and control front end is arranged near the rocket launch area, and the measurement and control back end is arranged in a safe area far away from the rocket launch area, and the measurement and control equipment of the measurement and control front end and the measurement and control back end exchange information through a network switch;

[0010] The measurement and control back-end is provided with back-end measurement and control equipment, and the back-end measurement and control equipment includes a main command and control computer, a slave command and control computer, a monitoring computer, a back-end switch, a measurement, launch and control system back-end, and a measurement system back-end; the back-end main and slave command and control computers and the monitoring computer are respectively connected to the back-end switch via a network cable (Ethernet); the measurement, launch and control system back-end and the measurement system back-end are connected to the back-end switch via a network cable (Ethernet); the power measurement and control system back-end command and control computer communicates with the measurement, launch and control system, the telemetry system and other external systems via Ethernet;

[0011] The front-end measurement and control front end is provided with a front-end measurement and control device, which includes a front-end measurement and control computer, a relay assembly board, a power supply system, a front-end switch, a measurement and control system front end, and a measurement system front end; the front-end measurement and control computer is an industrial computer using a CPCI architecture;

[0012] The front-end measurement and control computer and the power supply system are connected to the front-end switch through network cables respectively, and the relay combination board is connected to the power supply system and the measurement and control computer through cables;

[0013] The front end of the test, launch and control system and the front end test and control computer are connected by cables

[0014] The front end of the test, launch and control system and the front end switch are connected via a network cable;

[0015] The front end of the measurement system and the front end switch are connected via a network cable;

[0016] The front-end switch and the back-end switch are connected via optical fiber.

[0017] The front-end measurement and control computer runs the power system front-end measurement and control software, which is used to execute the control instructions issued by the back-end command and control computer, collect the switching quantity and analog quantity (4mA~20mA current signal) of the ground equipment, receive the contact command signal of the measurement and control system, and feedback the command execution results, processed measurement parameters and command signals to the back-end measurement and control equipment of the power measurement and control system.

[0018] The relay combination is used for power distribution and drive of solenoid valves. Each circuit adopts a double relay contact series-parallel design and reverse peak elimination protection circuit, and has a 24V power supply signal recovery function.

[0019] The front-end switch is used for information exchange between the front-end equipment and the back-end equipment of the power measurement and control system.

[0020] Furthermore, the front-end measurement and control computer includes a main control board, a switch quantity input board, a switch quantity output board, a current acquisition board, and a current output board;

[0021] The main control board receives control instructions from the back-end command and control computer through Ethernet, and is responsible for sending status parameters, collected ground measurement parameters and received measurement, launch and control system instructions to the back-end command and control computer;

[0022] The main control board and the switch input board, the switch output board, the current acquisition board and the current output board communicate with each other using a custom CAN bus.

[0023] The present invention also provides a measurement and control method for the above-mentioned single-stage reusable rocket power measurement and control system, comprising the following steps:

[0024] S1. Before work, the back-end command and control computer sends a system self-check instruction to the front-end measurement and control computer to self-check the status of each board in the front-end computer; in the back-end command and control computer, the master and slave command and control computers are mutually redundant backups, running the power measurement and control system command and control software, responsible for sending control instructions to the front-end measurement and control equipment and exchanging information with the external system;

[0025] S2. After the self-test is completed, the back-end command and control computer sends the solenoid valve control instruction to the front-end measurement and control computer through the network. The front-end measurement and control computer calls the switch output board to control the relay combination board to drive the ground solenoid valve to work and complete the control of the ground solenoid valve;

[0026] The relay assembly board and the ground withdrawal device are connected by cables, and the relay assembly board controls the withdrawal of the ground withdrawal device;

[0027] At the same time, the front-end measurement and control computer inputs the power supply signal of the board card recovery relay combination through the switch quantity, and feeds it back to the back-end measurement and control equipment;

[0028] S3, the back-end command and control computer sends a control valve opening adjustment instruction to the front-end measurement and control computer through the network, and the front-end measurement and control computer calls the current output board to output the control valve servo mechanism control signal, controls the servo mechanism action of the ground control valve, and completes the control of the control valve opening adjustment;

[0029] S4. The current acquisition board of the front-end measurement and control computer collects the current signals of the ground sensor, transmitter and regulating valve positioner, processes the data through the front-end measurement and control software, obtains the ground measurement parameters and the opening of the regulating valve, and sends the processed data to the back-end measurement and control equipment of the power measurement and control system through the network;

[0030] S5. The measurement and control equipment at the back end of the power measurement and control system exchanges data with the back end of the measurement, launch and control system and the back end of the measurement system through the back end switch to obtain telemetry parameters and valve status on the arrow; the back end command and control computer sends the control instruction of the on-arrow solenoid valve to the back end of the measurement, launch and control system through the network, and the back end of the measurement, launch and control system forwards the control instruction to the front end of the measurement, launch and control system to complete the control of the on-arrow solenoid valve;

[0031] S6. The front-end measurement and control computer collects the switch quantity status of the ground equipment through the switch quantity input board, sends the switch quantity status to the back-end measurement and control equipment of the power measurement and control system through the network, and receives the contact output signal of the front-end equipment of the measurement and control system.

[0032] Furthermore, in step S1, the specific self-test contents are: front-end computer online status, RAM status, program CRC, timer, I / O initial status, and A / D measurement status.

[0033] Furthermore, in step S3, the servo mechanism of the ground regulating valve is powered by a power supply system; in step S4, the ground sensor and transmitter are powered by a power supply system.

[0034] Furthermore, the front end of the measurement system obtains signals from sensors and transmitters on the arrow through telemetry and processes the signals; the front end measurement system collects measurement parameters on the arrow and sends them to the back end of the measurement system, which then forwards the arrow data to the back end measurement and control equipment.

[0035] Furthermore, in step S5, the front-end measurement and control computer can also receive the working phase switching instruction sent by the front-end of the measurement and control system through the switch input board, and send it to the back-end measurement and control equipment of the power measurement and control system through the network, thereby switching the control working mode of the power measurement and control system.

[0036] The default initial working stage of the back-end command and control computer is the launch preparation stage. The front-end equipment of the measurement, launch and control system sends a contact signal to switch the working state. When the leakage start signal is received from the front-end equipment of the measurement, launch and control system, the power measurement and control system enters the leakage working stage, and the back-end command and control computer switches to the leakage control mode; when the landing signal is received from the front-end equipment of the measurement, launch and control system, the power measurement and control system enters the post-landing processing working stage, and the back-end command and control computer switches to the post-landing processing control mode.

[0037] The back-end command and control computer and monitoring computer can receive the on-rocket telemetry parameters and ground equipment monitoring video forwarded by the back-end of the measurement system and the on-rocket electromagnetic valve status forwarded by the measurement, launch and control system through the network. At the same time, the back-end command and control computer can indirectly control the on-rocket electromagnetic valve through the back-end of the measurement, launch and control system.

[0038] The front-end measurement and control computer collects signals from ground sensors and transmitters through current acquisition cards and processes the signals to obtain ground measurement parameters and regulating valve opening, and finally sends the data to the command control and monitoring computers through the network.

[0039] The present invention also provides the above-mentioned single-stage reusable liquid rocket propulsion measurement and control test system, which is used to perform closed-loop testing on the power measurement and control system in the absence of the controlled and measured object of the power measurement and control system and the external system equipment. Based on the above-mentioned single-stage reusable rocket propulsion measurement and control system, an arrow data simulation computer is set at the measurement and control front end, and the arrow data simulation computer runs the arrow data simulation software to simulate the arrow valve state of the measurement and launch control system and all the arrow telemetry parameters of the measurement system, and send the simulated state and parameters to the back-end command control and monitoring computer of the power measurement and control system; the arrow data simulation computer is connected to the back-end switch via a network cable; specifically includes the following functions:

[0040] On-rocket telemetry parameter simulation and output function: The on-rocket data simulation software can simulate the selected telemetry parameters and send the simulated data to the power measurement and control back-end command and control computer and monitoring computer through the network;

[0041] Valve status simulation and output function of the test platform: The arrow data simulation software receives the arrow valve control instructions issued by the power system command software, simulates the status of the corresponding valve after the instruction is executed, and sends the status signal to the power system command software and monitoring software through the network.

[0042] A front-end equivalent computer (i.e., front-end equivalent device) is arranged at the front-end of measurement and control. The front-end equivalent computer calls the current output board to simulate the analog signals of ground sensors, transmitters, and control valve positioners, and calls the switch output board to simulate the switch digital signals of ground equipment and the contact signals sent by the front-end measurement and control equipment of the measurement, launch and control system to the front-end measurement and control computer of the power measurement and control system. At the same time, the front-end equivalent computer can collect the control valve servo mechanism drive signal sent by the front-end measurement and control computer through the current acquisition board, so as to test the ground control valve opening control function of the power measurement and control system; collect the solenoid valve power supply signal of the relay combination and the contact signals sent by the front-end measurement and control computer to the front-end measurement and control equipment of the measurement, launch and control system through the switch input board; the front-end equivalent computer is connected to the measurement and control computer through a cable.

[0043] Furthermore, a custom CAN bus is used to communicate between the main control board (processor and peripheral circuit) of the front-end equivalent computer and the switch input board, switch output board, current acquisition board and current output board.

[0044] Furthermore, the simulation process of the arrow data simulation software includes a telemetry parameter simulation process and an arrow valve status simulation process;

[0045] The telemetry parameter simulation process is as follows: check the telemetry parameters on the arrow that need to be simulated, define the parameter size and sending frequency, and then send the simulation parameters to the back-end command and monitoring computer;

[0046] The process of simulating the valve status on the arrow is: accepting the control instructions from the back-end command and control computer, simulating the status of the valve after action according to the control instructions, and then feeding back the simulated valve status to the back-end command and control and monitoring computer.

[0047] Compared with the prior art, the power measurement and control system provided by the present invention is suitable for single-stage reusable rockets, eliminating multi-stage workstations and only requiring a single-stage workstation. The control of the refueling process is also controlled by the back-end command and control computer, and no subordinate refueling workstations are required, which greatly simplifies the control process. It can realize the measurement and control work after the rocket lands.

[0048] Industrial computers using CPCI architecture can greatly simplify the layout and wiring difficulty of the system and improve the reliability of the entire system. At the same time, industrial computers using CPCI architecture have more powerful data processing capabilities and network communication functions than PLCs, and can execute more complex control algorithms.

[0049] The single-stage reusable liquid rocket propulsion measurement and control test system provided by the present invention can perform independent closed-loop testing on the measurement and control system when it cannot be connected to an external system, and the testing process is simple and reliable. BRIEF DESCRIPTION OF THE DRAWINGS

[0050] Figure 1 This is a schematic diagram of the power measurement and control system of the present invention;

[0051] Figure 2 This is a schematic diagram of the power measurement and control system test system of the present invention;

[0052] Figure 3 This is a schematic diagram of the front-end measurement and control computer components of the power measurement and control system;

[0053] Figure 4 It is a schematic diagram of the equivalent computer components of the front end of the power measurement and control system;

[0054] Figure 5 This is a schematic diagram of the simulation process of telemetry parameters of the onboard data simulation software of the power measurement and control system;

[0055] Figure 6 This is a schematic diagram of the valve status simulation of the arrow data simulation software of the power measurement and control system. DETAILED DESCRIPTION

[0056] The present invention is described in detail below in conjunction with specific implementation modes.

[0057] In order to make the functions of the structure of the present invention clearer, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and specific implementation methods.

[0058] See also Figure 1 As shown, the power measurement and control system includes a back-end master and slave command and control computers (i.e., a master command and control computer and a slave command and control computer), a monitoring computer, a back-end switch, a front-end switch, a front-end measurement and control computer, a relay combination, a measurement, launch and control system, a measurement system and a power supply system. Among them, the master and slave command and control computers, the monitoring computer, the back-end of the measurement, launch and control system, the back-end of the measurement system and the back-end switch are located at the back-end of the measurement and control, and the back-end master and slave command and control computers and the monitoring computer are respectively connected to the back-end switch through a network cable; the front-end switch, the front-end measurement and control computer, the relay combination, the front-end of the measurement, launch and control system, the front-end of the measurement system and the power supply system are located at the front-end of the measurement and control, and the front-end measurement and control computer and the power supply system are respectively connected to the front-end switch through a network cable, and the relay combination board is connected to the power supply system and the measurement and control computer through a cable. The front-end switch and the back-end switch are connected through optical fibers.

[0059] See also Figure 2 As shown, the power measurement and control system test system includes all the measurement and control equipment of the above-mentioned power measurement and control system, as well as the arrow data simulation computer and the front-end equivalent computer. The arrow data simulation software is connected to the back-end switch through a network cable to replace the back-end measurement and control equipment of the measurement system and the power measurement and control system to exchange data with the back-end equipment. The front-end equivalent computer is connected to the relay combination and the front-end measurement and control computer through a cable to replace the ground controlled and measured objects to exchange data with the front-end measurement and control computer.

[0060] See also Figure 3 As shown, the front-end measurement and control computer components of the power measurement and control system mainly include a network interface, a main control board (processor and peripheral circuits), current input and output boards, and switch quantity input and output boards.

[0061] See also Figure 4 As shown, the front-end equivalent computer components of the power measurement and control system mainly include the main control board (processor and peripheral circuits), current input and output boards, and switch input and output boards.

[0062] See also Figure 5 The Arrow Data Simulation Software sends the simulated parameters to the back-end command computer and monitoring computer of the power measurement and control system through the back-end network at a certain sending frequency according to the telemetry parameters selected and input by the user, thereby simulating the data interaction between the measurement system and the back-end of the power measurement and control system.

[0063] See also Figure 6 The arrow data simulation software simulates the state of the valve after it is actuated according to the arrow valve control instructions received from the back-end command and control computer, and feeds back the state of the valve after it is actuated to the back-end command and control computer and monitoring computer of the power measurement and control system, thereby simulating the control process of the power measurement and control system controlling the arrow valve through the measurement and control system.

[0064] Working process of power measurement and control system:

[0065] The rocket propulsion measurement and control system includes a measurement and control front end and a measurement and control back end. The measurement and control front end is set near the rocket launch area, and the measurement and control back end is set in a safe area far away from the rocket launch area (more than 2km). The measurement and control equipment of the measurement and control front end and the measurement and control back end exchange information through a network switch;

[0066] Before starting work, place the power measurement and control system back-end measurement and control equipment at the measurement and control back-end, the power measurement and control system front-end equipment at the measurement and control front-end, and Figure 1 Connect as shown to realize the control communication of the front-end and back-end devices of the power measurement and control system.

[0067] The front-end and back-end devices of the power measurement and control system are powered by the measurement and control front end and the measurement and control back end respectively. After the system is powered on, the back-end accusation computer sends a system self-check instruction to the front-end measurement and control computer to perform a self-check on the status of each board in the front-end computer. The specific inspection contents are: the online status of the front-end computer, RAM status, program CRC, timer, I / O initial status, and A / D measurement status.

[0068] After the self-test is completed, the back-end control computer sends the solenoid valve control command to the front-end measurement and control computer through the network. The front-end measurement and control computer calls the switch output board to control the relay combination action, drives the solenoid valve to work, and completes the control of the solenoid valve. At the same time, the front-end measurement and control computer retrieves the 24V power supply signal of the relay combination through the switch input board, and feeds it back to the back-end measurement and control equipment.

[0069] The front-end measurement and control computer uses a 3U8-slot CPCI backplane, which uses a custom CAN bus for communication. The backplane provides data channels and power channels for each functional module. Key equipment uses redundant hot backup (CPU, power module, etc.), runs the front-end measurement and control software of the power system, and is used to execute the control instructions issued by the back-end control computer, collect the switch quantity and analog quantity (4mA~20mA current signal) of the ground equipment, receive the contact command signal of the measurement and control system, and feedback the command execution results, processed measurement parameters and command signals to the back-end measurement and control equipment of the power measurement and control system. The relay combination is used for the power distribution drive of the solenoid valve. Each circuit adopts a double relay contact series-parallel design and a reverse peak elimination protection circuit, and has a 24V power supply signal recovery function. The power supply system mainly includes a 24V DC output power supply, which can be controlled by the measurement and control computer and is used to power the ground solenoid valve and the two devices. The front-end switch is used for information exchange between the front-end equipment and the back-end equipment of the power measurement and control system.

[0070] The back-end control computer sends the control valve opening adjustment instruction to the front-end measurement and control computer through the network. The front-end measurement and control computer calls the current output board to output the control valve servo mechanism control signal, controls the action of the control valve servo mechanism, and completes the control of the control valve opening adjustment.

[0071] The back-end control computer sends the control instructions of the on-arrow solenoid valve to the back-end of the measurement, launch and control system through the network, and the back-end of the measurement, launch and control system forwards the control instructions to the front-end of the measurement, launch and control to complete the control of the on-arrow solenoid valve.

[0072] The 4mA~20mA current signals of the two ground devices and the regulating valve positioner are collected through the current acquisition board of the front-end measurement and control computer, and the data is processed through the front-end measurement and control software to obtain the ground measurement parameters and the regulating valve opening. The processed data is sent to the back-end measurement and control equipment of the power measurement and control system through the network.

[0073] The switch quantity input board of the front-end measurement and control computer collects the switch quantity status of the ground equipment, and sends the switch quantity status to the back-end measurement and control equipment of the power measurement and control system through the network. At the same time, the front-end measurement and control computer can also receive the working stage switching instruction sent by the measurement and control system through the switch quantity input board, and send it to the back-end measurement and control equipment of the power measurement and control system through the network, thereby switching the control working mode of the power measurement and control system.

[0074] The front-end measurement system collects the measurement parameters on the arrow and sends them to the back-end of the measurement system. The back-end of the measurement system then forwards the arrow data to other back-end measurement and control equipment.

[0075] The back-end measurement and control equipment of the power measurement and control system can exchange data with the back-end of the measurement and control system and the back-end of the measurement system through the back-end switch to obtain the telemetry parameters and valve status on the arrow.

[0076] Power measurement and control system test system working process:

[0077] The arrow data simulation computer, front-end equivalent computer and power measurement and control system measurement and control equipment are connected Figure 2 As shown in the connection, the data simulation computer on the arrow is connected to the back-end switch through a network cable, the front-end equivalent computer is connected to the measurement and control computer through a cable, and the power measurement and control system measurement and control equipment is powered on for self-test.

[0078] The on-arrow data simulation computer can be used to simulate the on-arrow valve status of the measurement and launch control system and all the on-arrow telemetry parameters of the measurement system, and send the simulated status and parameters to the back-end command and monitoring computer of the power measurement and control system to test the back-end data interaction between the power measurement and control system and the external system.

[0079] The telemetry parameter simulation process of the arrow data simulation software is as follows: check the arrow telemetry parameters to be simulated, define the parameter size and sending frequency, and then send the simulation parameters to the back-end command and monitoring computer;

[0080] The Arrow Valve Status Simulation Process of the Arrow Data Simulation Software is as follows: accept the control instructions from the back-end command and control computer, simulate the status of the valve after it is actuated according to the control instructions, and then feed back the simulated valve status to the back-end command and control and monitoring computer.

[0081] Use the front-end equivalent computer to call the current output board to simulate the 4mA~20mA analog signals of the two ground devices and the control valve positioner, call the switch output board to simulate the switch digital signals of the ground equipment and the contact signals sent to the front-end measurement and control computer of the power measurement and control system by the front-end measurement and control equipment of the measurement, launch and control system. At the same time, the front-end equivalent computer can collect the 4mA~20mA control valve opening analog control signal sent by the front-end measurement and control computer through the current acquisition board, so as to test the ground control valve opening control function of the power measurement and control system; collect the solenoid valve 24V power supply signal of the relay combination through the switch input board to send the contact model of the front-end measurement and control equipment of the measurement, launch and control system to the front-end measurement and control computer.

[0082] The onboard data simulation computer and the front-end equivalent computer are used for testing and are not connected to the network during actual launch. And for security reasons, in order to prevent data conflicts between the simulated data of the onboard data simulation computer and the data sent by the test, launch and control system and the measurement system, when the onboard data simulation computer and the test, launch and control system are connected to the network at the same time, all data related to the test, launch and control system in the onboard simulation software are prohibited from being simulated; when the onboard data simulation computer and the measurement system are connected to the network at the same time, all data related to the measurement system in the onboard simulation software are prohibited from being simulated.

Claims

1. A single-stage reusable rocket power measurement and control system, Features It includes a measurement and control front end and a measurement and control back end. The measurement and control front end is set near the rocket launch area, and the measurement and control back end is set in a safe area far away from the rocket launch area. The measurement and control equipment of the measurement and control front end and the measurement and control back end exchange information through a network switch; The back-end measurement and control equipment is placed on the measurement and control back-end, and the back-end measurement and control equipment includes a master command and control computer, a slave command and control computer, a monitoring computer, a back-end switch, a measurement, launch and control system back-end, and a measurement system back-end; the back-end master and slave command and control computers and the monitoring computer are respectively connected to the back-end switch through network cables; the measurement, launch and control system back-end and the measurement system back-end are connected to the back-end switch through network cables; The front-end measurement and control front end is provided with a front-end measurement and control device, which includes a front-end measurement and control computer, a relay assembly board, a power supply system, a front-end switch, a measurement and control system front end, and a measurement system front end; the front-end measurement and control computer is an industrial computer using a CPCI architecture; The front-end measurement and control computer and the power supply system are connected to the front-end switch through network cables respectively, and the relay combination board is connected to the power supply system and the measurement and control computer through cables; The front end of the test, launch and control system and the front end test and control computer are connected by cables The front end of the test, launch and control system and the front end switch are connected via a network cable; The front end of the measurement system and the front end switch are connected via a network cable; The front-end switch and the back-end switch are connected via optical fiber; An arrow data simulation computer is set at the measurement and control back end, and the arrow data simulation computer runs arrow data simulation software to simulate the arrow valve state of the measurement, launch and control system and all arrow telemetry parameters of the measurement system, and sends the simulation state and parameters to the back end charge and monitoring computer of the power measurement and control system; the arrow data simulation computer is connected to the back end switch via a network cable; A front-end equivalent computer is arranged at the measurement and control front end, and the front-end equivalent computer calls the current output board to simulate the analog signals of the ground sensor, transmitter and regulating valve positioner, and calls the switch output board to simulate the switch digital signal of the ground equipment and the contact signal sent by the front-end measurement and control equipment of the measurement, launch and control system to the front-end measurement and control computer of the power measurement and control system. At the same time, the front-end equivalent computer can collect the regulating valve opening analog control signal sent by the front-end measurement and control computer through the current acquisition board, so as to test the ground regulating valve opening control function of the power measurement and control system; collect the solenoid valve power supply signal of the relay combination and the contact signal sent by the front-end measurement and control computer to the front-end measurement and control equipment of the measurement, launch and control system through the switch input board; the front-end equivalent computer is connected to the measurement and control computer through a cable.

2. A single-stage reusable rocket power measurement and control system according to claim 1, It is characterized in that The front-end measurement and control computer includes a main control board, a switch quantity input board, a switch quantity output board, a current acquisition board and a current output board; The main control board receives the control instructions issued by the back-end control computer through Ethernet and sends the status parameters, the collected ground measurement parameters and the received measurement, launch and control system instructions to the back-end control computer; The main control board and the switch input board, the switch output board, the current acquisition board and the current output board communicate with each other using a custom CAN bus.

3. A single-stage reusable rocket power measurement and control system according to claim 1, It is characterized in that The simulation process of the arrow data simulation software includes a telemetry parameter simulation process and an arrow valve status simulation process; The telemetry parameter simulation process is as follows: check the telemetry parameters on the arrow that need to be simulated, define the parameter size and sending frequency, and then send the simulation parameters to the back-end command and monitoring computer; The process of simulating the valve status on the arrow is: accepting the control instructions from the back-end command and control computer, simulating the status of the valve after action according to the control instructions, and then feeding back the simulated valve status to the back-end command and control and monitoring computer.

4. The measurement and control method of a single-stage reusable rocket power measurement and control system according to claim 2, It is characterized in that The steps include: S1. Before work, send a system self-check instruction to the front-end measurement and control computer to self-check the status of each board in the front-end computer; in the back-end accusation computer, the master and slave accusation computers are mutually redundant backups, run the power measurement and control system command and control software, and are responsible for sending control instructions to the front-end measurement and control equipment and exchanging information with the external system; S2. After the self-test is completed, the back-end control computer sends the solenoid valve control instruction to the front-end measurement and control computer through the network. The front-end measurement and control computer calls the switch output board to control the relay combination board to drive the ground solenoid valve to work and complete the control of the ground solenoid valve; The relay assembly board and the ground withdrawal device are connected by cables, and the relay assembly board controls the withdrawal of the ground withdrawal device; At the same time, the front-end measurement and control computer inputs the power supply signal of the board card recovery relay combination through the switch quantity, and feeds it back to the back-end measurement and control equipment; S3, the back-end control computer sends a control valve opening adjustment instruction to the front-end measurement and control computer through the network, and the front-end measurement and control computer calls the current output board to output the control valve servo mechanism control signal, controls the servo mechanism action of the ground control valve, and completes the control of the control valve opening adjustment; S4. The current acquisition board of the front-end measurement and control computer collects the current signals of the ground sensor, transmitter and regulating valve positioner, processes the data through the front-end measurement and control software, obtains the ground measurement parameters and the opening of the regulating valve, and sends the processed data to the back-end measurement and control equipment of the power measurement and control system through the network; S5. The measurement and control equipment at the back end of the power measurement and control system exchanges data with the back end of the measurement, launch and control system and the back end of the measurement system through the back end switch to obtain the telemetry parameters and valve status on the arrow; the back end control computer sends the control instruction of the on-arrow solenoid valve to the back end of the measurement, launch and control system through the network, and the back end of the measurement, launch and control system forwards the control instruction to the front end of the measurement, launch and control system to complete the control of the on-arrow solenoid valve; S6. Collect the switch quantity status of the ground equipment through the switch quantity input board of the front-end measurement and control computer, and send the switch quantity status to the back-end measurement and control equipment of the power measurement and control system through the network.

5. The measurement and control method of a single-stage reusable rocket power measurement and control system according to claim 4, It is characterized in that In step S1, the specific self-test contents are: front-end computer online status, RAM status, program CRC, timer, I / O initial status, A / D measurement status.

6. The measurement and control method of a single-stage reusable rocket power measurement and control system according to claim 4, It is characterized in that In step S3, the servo mechanism of the ground regulating valve is powered by a power supply system; In step S4, the ground sensor and the transmitter are powered by a power supply system.

7. The measurement and control method of a single-stage reusable rocket power measurement and control system according to claim 4, It is characterized in that The front end of the measurement system obtains signals from sensors and transmitters on the arrow through telemetry and processes the signals.

8. The measurement and control method of a single-stage reusable rocket power measurement and control system according to claim 4, It is characterized in that In step S5, the front-end measurement and control computer can also receive the working phase switching instruction sent by the front-end of the measurement and control system through the switch input board, and send it to the back-end measurement and control equipment of the power measurement and control system through the network, thereby switching the control working mode of the power measurement and control system.