A construction method for rapid sealing and pressure-sealing of the shield starting section using a short sleeve
By using short sleeves and sealing structures in the construction of the shield starting section, rapid pressure sealing is achieved, solving the problem of soil layer settlement accuracy and water influx, and improving construction quality and safety.
Patent Information
- Application Number
- CN202210301682.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-25
- Publication Date
- 2024-11-29
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In the construction of the shield starting section, the existing rapid sealing method is difficult to meet the requirements of soil layer settlement accuracy, and water influx is prone to occur in water-rich areas, affecting construction quality and safety.
The fast sealing method is adopted to perform a short sleeve. By setting up a reaction frame, a first annular sealing structure and a second annular sealing structure in the tunnel, an elastic steel brush plate and annular pen rubber plate are used to form a sealing cavity, and sealing grease is poured into it to achieve Fast sealing to reduce soil layer disturbance.
The stability of the internal soil and water pressure of the tunnel is achieved, the soil layer disturbance is reduced, the construction quality and safety are improved, and the soil layer settlement accuracy requirements are met.
Smart Images

Figure CN114622922B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of tunnel construction, and in particular to a construction method for rapidly sealing a starting section of a shield machine using a short sleeve. Background Art
[0002] The shield machine is a tunnel boring machine that uses the shield method and plays an important role in tunnel construction. When the shield machine is constructed on the starting section of the existing line, the normal operation of the existing line must be ensured. During the tunnel excavation process, the construction requirements for the settlement accuracy of the soil layer are high, and the settlement accuracy of the soil layer is usually required to be no more than ±0.6mm. Therefore, in order to minimize the disturbance of the soil layer, it is necessary to quickly seal the pressure when the shield machine starts.
[0003] The current rapid sealing method for shield tunneling is: after the shield machine has excavated a certain depth, it will first lay a segment inside the tunnel. After the segment is laid, the shield machine will continue to excavate and separate from the segment. After that, the tunnel door will be closed, and then shield tail grease will be poured between the segment and the tunnel wall for sealing. During this process, in order to ensure stable pressure inside the tunnel, the shield machine usually needs to excavate about 10m, and it needs to wait until the tunnel door is closed before sealing. The sealing time is long, and the settlement accuracy of the soil layer is difficult to meet the construction requirements. In addition, in water-rich areas, water gushing is not only easy to occur. Summary of the invention
[0004] In order to quickly seal the starting section of a shield machine and reduce soil disturbance during subsequent excavation, the present application provides a construction method for quickly sealing the starting section of a shield machine using a short sleeve.
[0005] The present application provides a construction method for quickly sealing and pressing a shield starting section using a short sleeve, which adopts the following technical solution:
[0006] A construction method for quickly sealing and pressing a shield starting section using a short sleeve comprises the following steps:
[0007] S1. Make a reaction frame, and then arrange a short sleeve between the reaction frame and the tunnel face;
[0008] S2. A first annular sealing structure is arranged on the inner wall of the short sleeve, and a second annular sealing structure is arranged on the end of the short sleeve away from the tunnel face, and the distance between the first annular sealing structure and the second annular sealing structure is controlled to be 0.5-0.6 m;
[0009] S3, drive the shield machine to the front of the tunnel through the short sleeve, and then lay the pipe segments to form the initial pipe section;
[0010] S4, connecting the initial pipe section and the reaction frame together;
[0011] S5. Pour shield tail grease between the outer wall of the initial pipe segment and the shell of the shield machine, and then the shield machine starts to excavate and gradually separates from the pipe segment. When the shield tail of the shield machine moves to separate from the first annular sealing structure, pour sealing grease into the sealing cavity surrounded by the first annular sealing structure, the second annular sealing structure and the initial pipe segment until the sealing grease fills the sealing cavity.
[0012] By adopting the above technical solution, when the shield machine is constructing the starting section, the shield machine moves in the short sleeve. When the shield machine starts to excavate and separates from the first annular sealing structure, the first annular sealing structure, the second annular sealing structure and the initial pipe segment form a closed sealing cavity. By pouring sealing grease into the sealing cavity, rapid sealing and pressure sealing can be completed at the initial stage of excavation of the starting section, so that the soil pressure inside the tunnel remains stable, thereby reducing soil disturbance, which is beneficial to improving construction quality and construction safety.
[0013] Preferably, the inner ring diameter of the first annular sealing structure is smaller than the outer diameter of the initial pipe segment, and the first annular sealing structure includes a plurality of elastic steel brush plates, which are stacked and spliced in a ring shape. When installing the elastic steel brush plates, it is necessary to ensure that when the elastic steel brush plates abut against the shield shell of the shield machine, there is still a stacking area between two adjacent elastic steel brush plates.
[0014] By adopting the above technical solution, since the outer diameter of the shield shell of the shield machine is larger than the outer diameter of the initial pipe segment, during the movement of the shield machine in the short sleeve, the shield machine will squeeze the elastic steel brush plate to cause the elastic steel brush plate to undergo elastic deformation, so that the end of the elastic steel brush plate away from the side wall of the short sleeve is pressed against the shell of the shield machine, so that there will be no pressure release, which is conducive to maintaining the stability of the water pressure and soil pressure inside the tunnel. When the shield machine is separated from the elastic steel brush plate, the elastic steel brush plate abuts against the outer wall of the initial pipe segment during the rebound process, thereby playing a sealing role again, which is conducive to maintaining the stability of the water pressure and soil pressure inside the tunnel, thereby reducing the disturbance of the soil layer during the tunnel excavation process.
[0015] Preferably, the elastic steel brush plate is bent at an obtuse angle, and the angle of the elastic steel brush plate is arranged toward the second annular sealing structure.
[0016] By adopting the above technical solution, the shield machine can move more smoothly.
[0017] Preferably, in S2, when installing the elastic steel brush plate, two annular positioning plates whose outer diameters match the inner diameter of the short sleeve are placed in the short sleeve, and the spacing between the two annular positioning plates is adjusted to be equal to the width of one side where the elastic steel brush plate is connected to the short sleeve, and then the elastic steel brush plate is installed between the two annular positioning plates. After the installation is completed, the annular positioning plates are removed.
[0018] By adopting the above technical solution, when installing the elastic steel brush plate, if the elastic steel brush plate is misaligned in the axial direction of the short sleeve, it will cause the contact time between different elastic steel brush plates and the shield machine to be inconsistent, resulting in gaps between the elastic steel brush plates, and then pressure relief, which cannot meet the requirements of the soil layer settlement accuracy in this application. Therefore, before installing the elastic steel brush plate, an annular positioning plate is first installed in the short sleeve. The annular positioning plate has a positioning effect on the elastic steel brush plate, so that the installed elastic steel brush plate will not be misaligned in the axial direction of the short sleeve, which is beneficial to improve the sealing of the first annular sealing structure.
[0019] Preferably, in S2, after the elastic steel brush plate is installed, a test tube having an outer diameter consistent with the outer diameter of the shield shell of the shield machine is placed in the short sleeve, the position of the short sleeve is adjusted so that its axis is collinear with the axis of the short sleeve, and then the test tube is pushed so that the test tube passes over the elastic steel brush plate, and whether there is a gap between adjacent elastic steel brush plates; if a gap is generated, it means that the lengths of the two adjacent elastic steel brush plates are unequal, and the longer elastic steel brush plate is cut until its length is consistent with the length of the shorter elastic screen steel brush plate, and then the test is repeated until no gap is generated.
[0020] By adopting the above technical solution, due to the partial overlapping arrangement of the elastic steel brush plates, due to human construction errors, the side of the installed elastic steel brush plates away from the short sleeve may be of different lengths. If the side of the elastic steel brush plates away from the short sleeve is of different lengths, then after the subsequent shield machine squeezes the elastic steel brush plates, the angles of the elastic steel brush plates of different lengths will change inconsistently, resulting in gaps between the elastic steel brush plates. Since the elastic steel brush plates are partially stacked, a chain reaction will occur, thereby releasing pressure, and further making it difficult to control the settlement accuracy of the soil layer within the required range. Therefore, by using a test tube to detect the sealing performance of the first annular sealing structure, when the side of the elastic steel brush plates away from the short sleeve is of different lengths, the above problem can be solved by cutting off the excess part of the longer elastic steel brush plates, thereby ensuring that the elastic steel brush plates are always pressed against each other during elastic deformation, thereby ensuring the sealing performance of the first annular sealing structure.
[0021] Preferably, in S2, after completing the sealing test of the elastic steel brush plate, sealant is filled in the joint between the elastic steel brush plate and the short sleeve.
[0022] By adopting the above technical solution, the sealant fills the joint between the elastic steel brush plate and the short sleeve, further improving the sealing performance of the first annular sealing structure.
[0023] Preferably, the second annular sealing structure comprises an annular cord rubber plate and a circular ring plate fixed in sequence on the end of the short sleeve away from the tunnel face, the inner ring diameters of the annular cord rubber plate and the circular ring plate are both smaller than the inner diameter of the initial pipe segment; the circular ring plate is formed by a plurality of connecting plates spliced in a ring shape, the connecting plate comprises a fixed plate fixedly connected to the short sleeve, the lower end of the fixed plate is hinged with a movable plate, and the hinge point of the fixed plate and the movable plate is located outside the moving track of the shield machine.
[0024] By adopting the above technical solution, the annular rubber sheet has good elastic deformation ability. Therefore, when the shield machine passes through the second annular sealing structure, the annular rubber sheet will rebound immediately until it is pressed against the outer wall of the initial pipe section, thereby forming a seal. The movable plate provides stable support for the annular rubber sheet, so that in the subsequent process of pouring sealing grease into the sealing cavity, the annular rubber sheet will not expand irregularly and cause pressure release.
[0025] Preferably, the first annular sealing structure is provided with two layers.
[0026] By adopting the above technical solution, since the elastic steel brush plate will inevitably release pressure during the process of separation and rebound of the shield machine, two first annular sealing structures are provided. When the shield machine is separated from the first set of elastic steel brush plates, the second set of elastic steel brush plates still press against the outer wall of the shield shell of the shield machine, and cooperate with the second annular sealing structure to form two seals. When the shield machine is separated from the second set of elastic steel brush plates, the first set of elastic steel brush plates press against the outer wall of the initial pipe section, and cooperate with the second annular sealing structure to still form two seals, thereby further reducing the possibility of pressure release. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a vertical view of the first annular sealing structure and the second annular sealing structure in the present application installed in the short sleeve;
[0028] Figure 2 It is an elevation view of the shield machine passing through the short sleeve in this application;
[0029] Figure 3 It is a vertical view of the shield machine in this application after it starts to dig and separates from the second first annular sealing structure.
[0030] Description of reference numerals:
[0031] 1. Tunnel face; 2. Short sleeve; 3. End wall; 4. Shield machine; 5. Initial pipe section; 6. Elastic steel brush plate; 7. Annular curtain rubber plate; 8. Connecting plate; 81. Fixed plate; 82. Movable plate. DETAILED DESCRIPTION
[0032] The following is combined with Figure 1-3This application is described in further detail.
[0033] The present application embodiment discloses a construction method for quickly sealing the starting section of a shield machine using a short sleeve. The method comprises the following steps:
[0034] S1. Reference Figure 1 , a reaction frame is constructed in front of the tunnel face 1, and then a short sleeve 2 is arranged between the reaction frame and the tunnel face 1, and the length of the short sleeve 2 is 2 to 3 meters. When arranging the short sleeve 2, it is necessary to ensure that one end of the short sleeve 2 is pressed against the tunnel face 1, and use a laser calibrator to calibrate the placement of the short sleeve 2 until the axis of the short sleeve 2 is in line with the axis of the tunnel, and then an end wall 3 is constructed in the tunnel starting shaft to stabilize the short sleeve 2.
[0035] S2, reference Figure 1 A first annular sealing structure is arranged on the inner wall of the short sleeve 2, and a second annular sealing structure is arranged at the end of the short sleeve 2 away from the tunnel face 1. Two first annular sealing structures need to be arranged, and the spacing between the two first annular sealing structures is controlled to be 0.2-0.3m, and the spacing between the first annular sealing structure away from the tunnel face 1 and the second annular sealing structure is controlled to be 0.5-0.6m.
[0036] S3. Reference Figure 2 and Figure 3 , the shield machine 4 is opened to the front of the tunnel face 1 through the short sleeve 2, and then the pipe segments are laid to form the initial pipe section 5.
[0037] Reference Figure 1 to Figure 3 Specifically, the first annular sealing structure includes a plurality of elastic steel brush plates 6, and the plurality of elastic steel brush plates 6 are partially stacked and spliced in annular shapes. The structure of the elastic steel brush plate 6 is similar to the tail brush of the shield machine 4. The elastic steel brush plate 6 is composed of an elastic steel plate clamping a wire brush, so that the elastic steel brush plate 6 has good elastic deformation ability. The elastic steel brush plate 6 is bent at an obtuse angle, and the angle of the elastic steel brush plate 6 faces away from the tunnel face 1. One side of the elastic steel brush plate 6 is fixed to the inner wall of the sleeve by bolts, and the other side of the elastic steel brush plate 6 naturally droops. And the inner diameter of the ring surrounded by the elastic steel brush plate 6 is smaller than the outer diameter of the initial pipe section 5, so that the shield machine 4 can apply force to the elastic steel brush plate 6 during the movement in the short sleeve 2, so that the elastic steel brush plate 6 undergoes elastic deformation and presses against the shield shell of the shield machine 4.
[0038] In S2, before installing the elastic steel brush plate 6 in the short sleeve 2, two annular positioning plates whose outer diameters match the inner diameter of the short sleeve 2 are first placed in the short sleeve 2, and the width of the annular positioning plates is consistent with the thickness of the elastic steel brush plate 6. The position of the annular positioning plates in the short sleeve 2 is adjusted so that the distance between the annular positioning plates and the end of the short sleeve 2 away from the tunnel face 1 is 0.5 to 0.6 m. Then adjust the spacing between the two annular positioning plates to be equal to the width of the side where the elastic steel brush plate 6 is connected to the short sleeve 2, and then fix the annular positioning plates.
[0039] Then place the elastic steel brush plate 6 between the two annular positioning plates, and fix the positioning plates in the sleeve with bolts. It should be noted that the elastic steel brush plates 6 need to be arranged in a stacked manner according to the construction drawings to ensure that after the elastic steel brush plates 6 are elastically deformed under the action of the shield machine 4, there are still stacked areas between adjacent elastic steel brush plates 6, so that the first annular sealing structure always has good sealing properties.
[0040] After the installation of the two sets of elastic steel brush plates 6 is completed, the annular positioning plate is removed, and then the sealing of the first annular sealing structure is tested. A test tube with an outer diameter consistent with the outer diameter of the shield shell of the shield machine 4 is placed in the short sleeve 2, and the axis of the test tube is adjusted to be consistent with the axis of the short sleeve 2, and then the test tube is pushed until the test tube passes through the second first annular sealing structure, and whether a gap is generated between the two adjacent elastic steel brush plates 6. If a gap is generated, it means that the lengths of the two elastic steel brush plates 6 at this location are not equal. Thereafter, the excess part of the longer elastic steel brush plate 6 is cut off to make its length consistent with the length of the shorter elastic steel brush plate 6. However, the test is repeated until no gap is generated between the adjacent elastic steel brush plates 6 when the test tube passes through the first annular sealing structure, so as to ensure that the first annular sealing structure has excellent sealing performance.
[0041] After completing the sealing test of the first annular sealing structure, fill the joint between the elastic steel brush plate 6 and the short sleeve 2 with sealant to further improve the sealing performance.
[0042] Reference Figure 1 to Figure 3 The second annular sealing structure includes an annular rubber sheet 7 and an annular plate which are sequentially arranged at the end of the short sleeve 2 away from the tunnel face 1. The annular rubber sheet 7 and the annular plate are fixed to the end of the short sleeve 2 by bolts and nuts. When in a natural state, the inner ring diameters of the annular rubber sheet 7 and the annular plate are both smaller than the outer diameter of the initial pipe segment 5, and the inner ring diameter of the annular rubber sheet 7 is smaller than the inner ring diameter of the annular plate.
[0043] Reference Figure 1 to Figure 3The annular plate is formed by a number of connecting plates 8 connected in a ring shape. The connecting plate 8 includes a fixed plate 81 fixedly connected to the short sleeve 2. The fixed plate 81 is hinged with a movable plate 82 on the side facing the tunnel axis. The hinge axis between the fixed plate 81 and the movable plate 82 is located outside the moving track of the shield machine 4 and inside the short sleeve 2, so that the shield machine 4 can pass smoothly. The presence of the annular curtain rubber plate 7 can block the gap between the movable plate 82 and the initial pipe section 5 and the gap between adjacent movable plates 82 to enhance the sealing of the second annular sealing structure. The movable plate 82 provides stable support for the annular curtain rubber plate 7, so that during the process of injecting sealing grease, the annular curtain rubber plate 7 will not be excessively deformed to cause grease leakage and pressure relief.
[0044] S4, connecting the initial pipe section 5 and the reaction frame together. Specifically, pouring concrete between the initial pipe section 5 and the reaction frame.
[0045] S5. Shield tail grease is poured between the outer wall of the segment and the shell of the shield machine 4, and then the shield machine 4 starts to excavate and gradually separates from the segment. When the shield tail of the shield machine 4 moves to separate from the second first annular sealing structure, sealing grease is poured into the sealing cavity surrounded by the first first annular sealing structure, the second annular sealing structure, and the initial pipe section 5 until the sealing grease fills the sealing cavity. The sealing grease uses shield tail grease.
[0046] Specifically, the sealing grease is pumped into the sealing cavity along the circumference of the initial pipe segment 5 by using an oil injection pump, so that the sealing grease is filled evenly, which is beneficial to improving the sealing performance.
[0047] The implementation principle of a construction method for rapid sealing and pressing using a short sleeve at the starting section of a shield machine in the embodiment of the present application is as follows:
[0048] When the shield machine is excavating the starting section, a short sleeve 2 is set on the face 1, which is equivalent to constructing a section of tunnel, and then a first annular sealing structure and a second annular sealing structure are set inside the tunnel, and the first annular sealing structure and the second annular sealing structure are always pressed against the shield shell of the shield machine 4 during the movement of the shield machine 4. When the shield machine 4 is separated from the first annular sealing structure and the second annular sealing structure, the first annular sealing structure and the second annular sealing structure are pressed against the outer wall of the initial pipe segment 5 again, so that the shield machine 4 can inject sealing grease into the sealing cavity at the initial stage of excavation, realize rapid sealing and pressure sealing, greatly reduce the disturbance of the soil layer in the subsequent excavation process, and help improve construction quality and construction safety.
[0049] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A construction method for rapid sealing and pressure relief using a short sleeve at the starting section of a shield machine. Features: The following steps are involved: S1, construct a reaction frame, and then arrange a short sleeve (2) between the reaction frame and the tunnel face (1); S2, a first annular sealing structure is arranged on the inner wall of the short sleeve (2), and a second annular sealing structure is arranged on the end of the short sleeve (2) away from the tunnel face (1), and the distance between the first annular sealing structure and the second annular sealing structure is controlled to be 0.5 to 0.6 m; S3, driving the shield machine (4) through the short sleeve (2) to the front of the tunnel face (1), and then laying pipe segments to form an initial pipe section (5); S4, connecting the initial pipe section (5) and the reaction frame together; S5, pouring shield tail grease between the outer wall of the initial pipe segment (5) and the shell of the shield machine (4), and then the shield machine (4) starts to excavate and gradually separates from the pipe segment, and when the shield tail of the shield machine (4) moves to separate from the first annular sealing structure, pouring sealing grease into the sealing cavity surrounded by the first annular sealing structure, the second annular sealing structure and the initial pipe segment (5), until the sealing grease fills the sealing cavity; The inner ring diameter of the first annular sealing structure is smaller than the outer diameter of the initial pipe section (5), and the first annular sealing structure comprises a plurality of elastic steel brush plates (6), and the plurality of elastic steel brush plates (6) are stacked and spliced in an annular shape. When installing the elastic steel brush plates (6), it is necessary to ensure that when the elastic steel brush plates (6) abut against the shield shell of the shield machine (4), there is still a stacking area between two adjacent elastic steel brush plates (6); The elastic steel brush plate (6) is bent at an obtuse angle, and the angle of the elastic steel brush plate (6) is arranged toward the second annular sealing structure; In S2, when installing the elastic steel brush plate (6), two annular positioning plates whose outer diameters match the inner diameters of the short sleeve (2) are placed inside the short sleeve (2), and the spacing between the two annular positioning plates is adjusted to be equal to the width of the side where the elastic steel brush plate (6) and the short sleeve (2) are connected, and then the elastic steel brush plate (6) is installed between the two annular positioning plates. After the installation is completed, the annular positioning plates are removed; In S2, after the elastic steel brush plate (6) is installed, a test tube having an outer diameter consistent with the outer diameter of the shield shell of the shield machine (4) is placed in the short sleeve (2), and the position of the short sleeve (2) is adjusted so that its axis is colinear with the axis of the short sleeve (2), and then the test tube is pushed so that the test tube passes through the elastic steel brush plate (6), and it is observed whether there is a gap between adjacent elastic steel brush plates (6); if a gap is generated, it means that the lengths of the two adjacent elastic steel brush plates (6) are unequal, and the longer elastic steel brush plate (6) is cut until its length is consistent with the length of the shorter elastic steel brush plate (6), and then repeated testing is performed until no gap is generated.
2. A construction method for rapidly sealing a shield starting section using a short sleeve according to claim 1, Features: In S2, after the sealing test of the elastic steel brush plate (6) is completed, the joint between the elastic steel brush plate (6) and the short sleeve (2) is filled with sealant.
3. According to claim 1, a construction method for rapid sealing and pressing of a shield starting section using a short sleeve, Features: The second annular sealing structure comprises an annular rubber sheet (7) and an annular plate which are fixed in sequence to one end of the short sleeve (2) away from the tunnel face (1); the inner diameters of the annular rubber sheet (7) and the annular plate are both smaller than the inner diameter of the initial pipe section (5); the annular plate is formed by splicing a plurality of connecting plates (8) in an annular shape; the connecting plate (8) comprises a fixed plate (81) fixedly connected to the short sleeve (2); a movable plate (82) is hinged at the lower end of the fixed plate (81); and a hinge point between the fixed plate (81) and the movable plate (82) is located outside the moving track of the shield machine (4).
4. A construction method for rapid sealing and pressing of a shield starting section using a short sleeve according to claim 1, Features: The first annular sealing structure is provided with two layers.
Citation Information
Patent Citations
High water pressure soft soil stratum HFE combined type shield starting method
CN107676097A
Shield can be strengthened and portal sealing device who starts and receive is constructed
CN206707743U